Professional Documents
Culture Documents
Abstract
Introduction
Steel girders have become the preferred design choice for complicated
curved bridges because of advantages they offer with regards to fabrication,
erection, and serviceability. However, behavior of these structures is still
not well understood and a need for further research exists. This led to initia-
tion of the Curved Steel Bridge Research Project (CSBRP) by the Federal
Highway Ad ministrati on (FHWA). Its goal is to conduct fundam ental
research into the behavior of curved steel members with the aim of develop-
ing rational design procedures for curved steel bridge structures though
examination of a large-scale experimental system (Zureick et. al., 1997).
This paper briefly summarizes a series of experimental studies com-
pleted during construction of the experimental structure. The tests provided
a unique opportunity to study erection behavior in a laboratory environment.
Six different geometries were tested and each system’s behavior was studied
under its own self weight with various levels of shoring support.
Previous Research
1L
7
G1 1R
G3
The structure was constructed from inner to outer girder (G1 to G3).
G1 and G2 were set onto their bearings and the two end cross frames (1L
and 1R) were placed between them. After this system was properly shored,
the first series of erection study tests took place. Additional tests occurred
as cross frames were placed between G1 and G2 and after the entire three
girder system was assembled. Instrumentation consisted of: load cells at the
abutment and shoring locations; vibrating wire strain gages on the girder
flanges and webs; resistance strain gages on the lower lateral bracing, the
tangential support, and each cross frame member; and LVDT’s, potentiome-
ters and tiltmeters at mid-span and over the abutments. In addition to these
instruments a laser measurement system and total station were used to
obtain global deformation data. A schematic of the test configurations is
shown in Figure 2 followed by a brief description of each test procedure.
ES1-1 to ES1-3 ES1-6
ES1-5
ES3-1
ES1-1 to ES1-3
These three tests investigated single girder behavior during construc-
tion with cross frames 1L and 1R between G1 and G2. G1 and G2 were
shored beneath cross frames 3L, 5L, 7, 5R, and 3R and G1 shoring was peri-
odically removed until it was fully deflected. Another series of testing steps
were then used to return G1 to its initial, shored position.
ES1-4, ES2-1
ES1-4 investigated single girder behavior while ES2-1 examined twin-
girder behavior cross frames 1L, 7, and 1R between G1 and G2. Both girders
were shored at similar locations to tests ES1-1 to ES1-3. ES1-4 proceeded in
the the same manner as the first three tests while ES2-1 followed the lower-
ing portion for G1 with a series of G2 lowering steps. Once all intermediate
shores beneath the G1 and G2 girders had been removed, the structural sys-
tem was returned to its initial, shored position.
ES1-5
ES1-5 examined single girder construction behavior when cross frames
1L, 2L, 2R, and 1R and the lower lateral bracing between G1 and G2 were
in-place. Shoring locations and the testing procedure matched those for the
previous studies.
ES1-6
ES1-6 was the final test that examined single girder behavior and
involved a twin-girder system with six cross frames and the lower lateral
bracing. Testing procedures were unchanged from earlier single girder tests.
ES2-2
The final twin girder investigation involved a framing plan which
included the lower lateral bracing and eight cross frames between G1 and
G2. As had occurred with ES2-1, G1 shoring was sequentially removed fol-
lowed by shoring for G2.
ES3-1
ES3-1 was the last erection study test that examined the behavior of a
three girder system. G3 was lifted onto the abutments and the remaining
cross frames and lower lateral bracing placed. Testing procedures involved:
removal of shoring from beneath all girders, incremental raising and lower-
ing of each girder at mid-span using a single shore, and returning the system
to its initial position.
Summary
Acknowledgments
References
Galambos, T. V., Hajjar, J. F., Leon, R. T., Huang, W., Pulver, B. E., and
Rudie, B. J. (1996), “Stresses in Steel Curved Girder Bridges,” Minnesota
Dept. of Trans. Report No. MN/RC-96/28, Aug.
Mozer, J., Cook, J., and Culver, C. (1973), “Horizontally Curved Highway
Bridges – Stability of Curved Plate Girders,” Carnegie Mellon Univ. Report
No. P3, Research Project HPR-2(111), Jan.
Zureick A., Leon, R. T., Burrell, J., and Linzell, D. (1997), “Proceedings -
Innovations in Structural Design: Strength, Stability, Reliability. A Sympo-
sium Honoring Theodore V. Galambos”, SSRC, Minneapolis, MN, June,
pp.179-190.
Key Words: construction, erection, testing, experimental, curved, steel,
girder, bridge, full-scale, superstructure