Professional Documents
Culture Documents
net/publication/264834873
CITATIONS READS
7 990
2 authors, including:
SEE PROFILE
All content following this page was uploaded by Mohammad Miftaur Rahman Khan Khadem on 22 October 2014.
1 Introduction
Productivity means almost everything in any business (Krugman, 1997) and a long-term
practice of productivity concepts constitutes less cost, less time, and higher quality of
product/service that ultimately results in greater economic growth in business
organisation (Odhigu et al., 2012). In addition, productivity indices are reckoned as
indicators of business performance for stakeholders (Yu and Lee, 2002). As
consequences, because of its largest size and its assistance to all other industries to some
extent, construction productivity contributes significantly to the gross national product
(GNP) both in industrialised and semi-industrialised countries (Chia, 2012; Navon,
2005). Moreover, construction productivity is considered as a vital issue in national and
international competitiveness, increasing living status, and also in achievement of societal
goal in countries (Ghoddousi and Hosseini, 2012; Chia et al., 2012).
428 M.A. Islam and M.M.R.K. Khadem
But the ever-changing multidisciplinary (Jaffar et al., 2011) and instinct desegregated
behaviours (Hohns, 1979) of construction industries make productivity principles
complex. As a result, the construction industry has been facing higher level of
productivity concerns for a long time that necessitate continuous investigation of the
productivity variables or factors. Moreover, lack of systematic investigation impedes the
pursuit of benefits from established productivity concepts in this industry, while other
industries, for example manufacturing industries (Mojahed and Aghazadeh, 2008), and
service industries such as bank (Sufian, 2010) hold the major parts of gain. Thus,
investigating the productivity factors in the purpose of finding the current and future
problems in construction industry is ever essential, especially in unfocused countries
(Shehata and El-Gohary, 2011; Goodrum et al., 2009).
As the common Asian saying, stated by Long et al. (2004), “a problem well defined is
a problem half solved”, and it is always better to be proactive in problem analysis in
which potential problems for the future can be well anticipated. In particular, construction
productivity can be characterised by several levels (e.g., industry, firm, project, and
activity level) and their collaborations from different upstream and downstream industries
(Huang et al., 2009; Dzeng and Wu, 2012). Productivity in construction industry is
studied in literature by three most common indices such as single factor-labour
productivity index, multi factor production index, and capital productivity index
(Li and Liu, 2012; Chia et al., 2012; Allan et al., 2010; Ruddock and Ruddock, 2011;
O’Brien and Associates, Inc., 2008); or by productivity measurement methods such as
Hicks-Moorsteen index (Arora and Arora, 2012), Malmquist productivity index (Sufian,
2012; Li and Song, 2012; Li and Liu, 2010), data envelopment analysis (Ray and Ray,
2012; Xue et al.,2008); or by improvement tools such as Six Sigma (Desai, 2012), cluster
concepts (Phusavat et al., 2012). Despite of various areas of improvement, it is
impossible to bring productivity development in construction industries except the well
identified productivity factors, both present and future, affect it (Jaaskelainen, 2010;
Mojahed and Aghazadeh, 2008). Some of these factors have positive effect and some
have negative effect on overall productivity. The factors have negative effect on
productivity, are considered as problem categories for construction industry.
In general, every kind of development needs some physical infrastructure, which is an
ultimate work for construction industry that in turn significantly influence on
socio-economic development of countries (Bielsa and Duarte, 2011). Similar scenario
prevails in the Sultanate of Oman (hereafter referred as Oman) with dramatic
socio-economic progress presently where construction industry contributed 3% to the
GDP in 2004 and it is expected to raise 10% by 2020 (Oman Chamber of Commerce and
Industry, 2005). Most of the construction farms are belong to small and medium
industries and they have been growing by 34.7% in 2007 as a result of large scale public
and private investment in various infrastructure developments, such as industries, tourism
and commercial property projects, etc. (PwC, 2012). Moreover, under the long term
economic plan called ‘vision 2020’, currently Oman Government is spending 23% more
money in 2012 in compare to 2011 fiscal year in construction industry during the eighth
five-year development plan (2011–2015) (The Consulate General of the Sultanate of
Oman-Australia, 2012). But then, no systematic investigation has been done so far on
productivity area in the construction industry in Oman, although several risk factors are
identified in the construction industry in Oman (Ballal et al., 2007). Hence, it is urgently
needed that factors of productivity are to be well explored that make practitioners and
Productivity determinants in Oman construction industry 429
researchers’ know-how on the present and future problems and prospects of construction
industry in Oman.
This research focuses on identifying:
1 the major productivity determinants and their co-relationship
2 the problem categories those are responsible for construction delay in Oman
construction industry.
2 Literature review
and contractors’ financial difficulties were also stressed in this study. In the USA, design
change, inaccurate evaluation of projects time, complexity of works, risk and uncertainty
associated with projects, non-performance of subcontractors and nominated suppliers,
lack of proper training and experiencing of PM, were found as top delay factors in
construction industry (Olawale and Sun, 2010). In UAE, preparation and approval of
drawings, inadequate early planning of the project and slowness of the owner’s
decision-making process were the causes of construction delay (Faridi and El-Sayegh,
2006). Preparation and approval of drawings, unsuitable leadership style of
construction/project manager and preparation and approval of drawings delayed
construction works in Lebanon (Mezher and Tawil, 1998). In Jordan, the parties such as
client, contractor and labour and equipment were the most responsible for construction
delay (Odeh and Battaineh, 2002); however, design changes by the owner, poor labour
productivity and inadequate planning of contractor were identified as causes of
construction delay in Indonesia (Kaming et al., 1997). A similar study by Long et al.
(2004) found that consultant, contractor, coordinator were the most occurred problem
categories in Vietnamese construction projects. In Malaysia, contractor, labour, and
equipment and materials were prime problem categories for construction delay
(Sambasivan and Soon, 2007).
Thus, productivity concepts in construction industry can be carried out in different
aspects and each aspect has its own significance on productivity. Moreover, factors have
co-relationship in each aspect and it is important to understand their co-relationship
(Doloi et al., 2011).
3 Methodology
4 Result calculation
Table 2 suggests that productivity in small and medium construction industries in Oman
has been affected mostly by ‘lack of professionalism’ of all parties involves in these
industries and less affected by ‘tool/equipment breakdown’, that indicates construction
industries in Oman are still labour oriented. The co-relationship among the factors is not
known from RIIs and means of the data.
Table 3 Communalities of the each factor
4.2 Result 02: Reduction of these factors into the critical variables by principle
components analysis
Prior to principle components analysis, strength of each factor is examined by
communality to decide the accuracy of factor analysis (Ng and Tang, 2010). The
communities of all factors are shown in Table 3. It reveals that each factor has
communality greater than 0.5, which suggests their accuracy valid for factor analysis.
Principle components analysis with varimax orthogonal rotation is used to reduce 25
factors into highly predictive variables of productivity. Table 4 shows a total of ten
variables are developed, named as management, people, collaboration, commitment,
health and safety, logistics, operational activity, authority, quality, and financial matters
with Eigen values greater than 1.00.
Table 4 Ten variables are found by principle components analysis
4.3 Result 03: Reliability test of respondent’s answer and factor analysis
KMO MSA and Bartlett’s test of sphericity are measured to test the adequacy of the
collected data from respondents used in factor analysis. The result of Bartlett’s test of
sphericity are approx. Chi-square = 847.883, df = 300 and significance level, p = 0.000
and KMO MSA value is 0.694, which is suggested to be acceptable for factor analysis
(Hair et al., 1998). A statistic Cronbach’s alpha (Cα) for investigating the internal
consistency of questionnaire is examined for each variable (shown in Table 5).
Table 5 Cronbach’s alpha for each variable
5.1 Management
The first variable is named as ‘management’ that illustrates 15.74% of total variances of
the linear component and eigenvalue is 3.937. Management at every level of construction
industries plays prime role in construction productivity. According to Deming (1982),
management can resolve almost 85% of business problem. In this study, management
variable includes four productivity factors such as, shortage of material, poor
communication, instruction time, and scheduled working overtime. Shortage of material
is ranked fourth in overall ranking of productivity factors. Shortage of material is
common in any construction industry (Makulsawatudom et al., 2004). In Oman, shortage
of materials is occurred not only for scarcity of material, rather it is due to improper
material planning by contractor, inaccurate specification by designers or consultants,
wrong calculation of lead time, poor communication among contractors, site managers,
foremen and vendors. Usage of low quality of material is common in case of change
order and reworks. It is observed that some materials come from abroad; in this case
material shortage or material quality mostly depends on fluctuation of prices. Scheduled
working overtime is ranked seventh in overall ranking. Surprisingly, working at overtime
is obligatory by management not only for site workers but also for employees at
consultancy and contractor firms. Most of the time, it is forced and unpaid overtime. Site
workers do not have the potentiality to ignore the overtime. Scheduled overtime is
happened both at afternoon (before lunch) and evening, which ultimately results to their
poor productivity. Instruction time for worker, is ranked 14th, is another evidence of
mismanagement in a construction industries. Workers do not know the work schedule
even in the morning of the working day. Foremen or contractors are used to act as a
policeman (to impose the order) in site, which is an effective way of control for unskilled
and temporary foreign worker according to foremen and contractors thought. Poor
communication is ranked 12th. It results to poor coordination among the parties (clearing
authority, owners, contractors, and consultants) (Chan and Yeong, 1995). It creates
delays in getting permission from authority, changing order and design, and reworks,
which are responsible for delaying the whole project work (Doloi et al., 2011; Hanna
et al., 1999).
5.2 People
The second variable is people, has two factors, such as lack of responsibility and staff
team morality, illustrating 9.76% of total variances of the linear component and
eigenvalue is 2.441. People are directly responsible and most important factor in
construction industries (Ng et al., 2004). Enshassi et al. (2009) report that people is one
438 M.A. Islam and M.M.R.K. Khadem
of the top three variables in Gaza trip’s construction performance. The factor lack of
responsibility is ranked 21st and staff team morality is ranked 19th in productivity factor.
Construction industries are full of unskilled and temporary workforce in this region.
Moreover, no financial awards, high rate of accidents, no health insurance especially for
workers, and no recreation facility in jobsite, results in lack of responsibility and less
morality among people in construction industries.
5.3 Collaboration
The third variable is collaboration, illustrating 7.93% of total variances of the linear
component and eigenvalue is 1.985. It has four factors such as: change orders, rework,
inspection delay, and interferences from other trade. Collaboration among diversified
parties provides strong teamwork in construction industry (Sveiby and Simons, 2002).
Lack of understanding, and coordination among the parties results in less knowledge
exchange, fear in relationship, and non-impressed behaviour towards others. A strong
team with trusty collaboration among the parties can mitigate the adverse impact of these
factors on productivity. Change orders, reworks and inspection delays are ranked as 15th,
7th, 13th respectively and interferences from other trade is ranked 20th in overall ranking
of productivity factors.
5.4 Commitment
All party’s commitment is required for successful completion of any construction work
(Iyer and Jha, 2005). Commitment is the fourth variable in this study, illustrating 6.42%
of total variances of the linear component and eigenvalue is 1.604. It has two factors: lack
of professionalism and changing of foremen. Lack of professionalism has highest impact
on productivity as it is the first ranked factor in overall ranking of productivity, according
to respondents in this study. It is found that the lack of long-term vision and reluctant
attitude at industry and company level of construction industries imparts lack of
professionalism at all levels of industries. Moreover, most of the contractors are
expatriates, consultants are fresh and expatriate mostly, foremen and workers are
unskilled and 100% expatriates in Oman construction industries. So, cultural
dissimilarity, lack of trust makes them unprofessional in workplace. Changing of
foremen, is ranked 11th in overall ranking, is very frequent in Oman due to lack of
commitment from owners and contractors. Foremen are changed by owner or by
contractor in purpose of paying less money. Sometime contractor is replaced by less paid
foremen by owner.
The fifth variable is health and safety, illustrating 6.06% of total variances of the linear
component and eigenvalue is 1.517. It has two factors such as, safety (accident), and
work load. Lack of safety in organisation produces more accident, injuries and fatalities,
which increase absence of employees, diminish productivity and result in large financial
loss (Kazaz and Ulubeyli, 2007). On the other hand, causes of unsafe workplace are not
only due to limited PPEs but also the unwillingness of employees to comply with safety
Productivity determinants in Oman construction industry 439
rules and regulations. Improper work planning, (for instance, habit to wait maximum to
start the work) and tendency to take more work order raise more safety concern in
workplace. Safety (accident) is ranked 6th and workload is ranked 22nd in overall
ranking.
5.6 Logistics
The sixth variable is logistics, illustrating 5.00% of total variances of the linear
component and eigenvalue is 1.251. It has two factors such as, tool/equipment breakdown
and low technology. Proper and full geared construction work cannot be acquired without
suitable tool/equipment support (Long et al., 2004). Improper maintenance and inaccurate
equipment capacity calculation by contractor or foremen are the main causes of weak
logistics support (Makulsawatudom et al., 2004). Technology is essential in everywhere,
like in management, procurement, designing, generation and sharing the information, in
any construction project. The usage of technology in work is essential for successful
survival in today’s competitive construction business (Long et al., 2004). Here, it is found
that limited access to modern technology, lack of timely and irrelevant information are
the causes of large production cycles and slower decision making in construction
industries. Tool/equipment breakdown is ranked 25th and low technology is ranked 18th
in overall ranking of productivity.
The seventh variable is operational activity, illustrating 4.79% of total variances of the
linear component and eigenvalue is 1.199. It has two factors such as, shift/work timing
and poor site condition. Extreme hot weather is natural in this region due to very high
temperature and humidity. Even though, employees and workers are become habituate to,
shift/work timing in this weather incur lower work productivity, thus proper estimation of
workers and employees’ work productivity are essential. For example, hot weather is
advisably considered before estimating labour productivity in Indian construction (Doloi
et al., 2011). Limited and costly public transportation makes site condition poor in this
region. Moreover, incompetent foremen and contractor in work measurement and work
design make workplace miserable in some cases. Shift/work timing is ranked 16th and
poor site condition is ranked 17th in overall ranking of productivity.
5.8 Authority
The eighth variable is authority, illustrating 4.54% of total variances of the linear
component and eigenvalue is 1.135. It has two factors such as, obtaining permission from
local authority and bureaucracy. Obtaining permission from local authority is ranked 24th
in overall ranking. Slow response manner, lack of communication are the common
barriers of obtaining permission from local authority. Lack of intimacy among the parties
involved in industry causes late permission from local authority. The 9th overall ranked
factor is bureaucracy, which is apparent in both obtaining authority permission and
owners dealing that brings productivity troublesome in this region. Bureaucracy is found
to make management work slow in Vietnam (Long et al., 2004).
440 M.A. Islam and M.M.R.K. Khadem
5.9 Quality
The ninth variable is quality, illustrating 4.09% of total variances of the linear component
and eigenvalue is 1.024. It has three factors such as, incompetent supervisors, incomplete
drawing and lack of skilled manpower. Incompetent supervisors is ranked 3rd, are due to
wrong selection of supervisors, unskilled or non-professional workforce. Improper
planning, schedule problems, lacks of coordination among the parties are often visible
due to incompetent supervisors. Incomplete drawing, ranked 5th, is apparent due to
inexperience designers, quick requirements by owners, lack of budget, and lack of
coordination. Lack of skilled manpower, ranked 23rd, is a major concern in Omani
construction industries. Consultants (local or expatriate) are often new in their job
without enough previous training. It is surprising that not a single consultant is found in
this study having any training experience, even before or after joining the job. Workers
suddenly come from different job into construction and become construction workers,
who ultimately become foremen/supervisors without any further training.
Qatar (2012) Skill of labour Shortage of materials Labour supervision Shortage of experienced Communication between Productivity factor
labour site management and
labour force
Kuwait (2012) Change orders Financial constraints Owner’s lack of Materials Weather Delay/cost factor
experience
Comparison of explored factors of construction industries among countries
Oman (2007) Financial Management team Variation orders and Accuracy of project Material Risk factors on time and
capability/failure additional works programme prices/availability/ cost overruns
supply/quality
Oman (2012) in Lack of professionalism Fairness in financial Incompetent supervisors Shortage of materials Incomplete drawing Productivity factors
present study transactions
441
442 M.A. Islam and M.M.R.K. Khadem
Table 7 shows top five factors of productivity in Thailand were lack of material,
incomplete drawing, incompetent supervisors, lack of tools and equipment, and
absenteeism (Makulsawatudom et al., 2004), whereas another study called key
knowledge factors of Thai construction practice by Teerajetgul et al. (2009) had indicated
the top six critical factors were visionary leadership, incentive or rewards, collaboration,
trust, information technology, and individual competency or skills.
In Iran, it was found that material/tool shortage, construction technology and method,
planning, supervisor system, and rework were the top factors of construction productivity
(Ghoddousi and Hosseini, 2012). In Chile construction industry, top five factors affecting
productivity were materials, tools, rework, equipment, and truck availability (Rivas et al.,
2011). In Italy, major five productivity factor were experience and skill of construction
crew, size of the construction crew, site management, design deficiencies or mistakes and
delivery delay – equipment deficiencies (Pellegrino et al., 2012). In Qatar construction
industry, top five productivity factors were skill of labour, shortage of materials, labour
supervision, shortage of experienced labour, and communication between site
management and labour force (Jarkas et al., 2012). In Indonesia, lack of materials,
rework, absenteeism, interferences and lack of tools were reported as the top productivity
factors of construction industries (Kaming et al., 1997). However, inaccurate time
estimation, slow site clearance, excessive change orders, slow government permits and
severe overtime were the major factors of construction productivity in Vietnam (Long
et al., 2004), whereas construction equipment, materials, tools and consumable goods,
engineering drawing management, and direction and coordination were the top ranked
productivity factors in case of construction industry in the USA (Dai et al., 2009). In
some countries, construction industries were investigated through the construction delay
factors, for example, Saudi Arabia (Al-Kharashi and Skitmore, 2009); Kuwait (Koushki
et al., 2005); Lebanon (Mezher and Tawil, 1998); India (Doloi et al., 2011); and UAE
(Faridi and El-Sayegh, 2006).
In addition, Omani construction projects have been studied once before with a sample
size of 43 professional respondents that identified a total of 32 significant risk factors. Of
them, financial capability/failure, management team, variation orders and additional
works, accuracy of project programme, material prices/availability/supply/quality were
ranked as the top five risk factors (Ballal et al., 2007). The present study involves in
identification of productivity factors and problem categories responsible for construction
delay in Oman reflects the earlier result found by Ballal et al. (2007). Contractor’s
financial difficulty was identified as top significant risk factor on time and cost overruns
in Omani construction industries, whereas in present study it is identified as 10th
significant factor of productivity. It seems that Omani construction industries overcome
this problem presently, but practically, it is found that along with some other new issues
(mentioned in Section 5.10) contractor’s financial difficulties results in some other new
factors such as, unfairness in financial transactions, and unprofessional manner in Omani
construction industries. As a result, present study shows that lack of professionalism is
the top significant factor of productivity, which is followed by fairness in financial
transactions, incompetent supervisors, shortage of material, and incomplete drawing as
productivity factors in case of Omani small and medium construction industries.
Materials shortage/availability was also found as fourth significant factor in previous
study. It seems that the material shortage still has greater influences on Omani
construction works. Although lack of materials is one of the main concerns in
construction industries in today’s very fast urbanisation in around the world (Ghoddousi
Productivity determinants in Oman construction industry 443
and Hosseini, 2012; Rivas et al., 2011; Zakeri et al., 1997; Kaming et al., 1997;
Makulsawatudom et al., 2004).
7 Conclusions
factors can be used as decision making variables for the managers that will facilitate
productivity of the business; in addition, these factors can be used as a pivot for any other
productivity study in the businesses and industries.
Acknowledgements
The authors would like to thank The Research Centre (TRC) of Sultanate of Oman for
financial support for this research study under the project no: RC/ENG/MIED/10/01. The
authors also would like to thank the anonymous reviewers of the paper for their
constructive comments and suggestions.
References
Abdel-Razek, R.H., Elshakour, M.H.A. and Abdel-Hamid, M. (2007) ‘Labor productivity:
benchmarking and variability in Egyptian projects’, International Journal of Project
Management, Vol. 25, No. 2, pp.189–197.
Adebowale, B.O.A. and Oyelaran-Oyeyinka, B. (2012) ‘Determinants of productivity and
inter-firm collaboration in Nigerian clusters’, International Journal of Technology and
Globalisation, Vol. 6, No. 3, pp.188–205.
Al-Ghamdi, S.M., Kazmi, A. and Banaemah, M.S. (2011) ‘Corporate management of productivity
in private sector firms across Saudi Arabia’, Journal for Global Business Advancement,
Vol. 4, No. 2, pp.118–142.
Alinaitwe, H.M., Mwakali, J.A. and Hansson, B. (2007) ‘Factors affecting the productivity of
building craftsmen-studies of Uganda’, Journal of Civil Engineering and Management,
Vol. 13, No. 3, pp.169–176.
Productivity determinants in Oman construction industry 445
Al-Kharashi, A. and Skitmore, M. (2009) ‘Causes of delays in Saudi Arabian public sector
construction projects’, Construction Management and Economics, Vol. 27, No. 1, pp.3–23.
Allan, C., Dungan, A. and Peetz, D. (2010) ‘Anomalies’, damned ‘Anomalies’ and statistics:
construction industry productivity in Australia’, Journal of Industrial Relations, Vol. 52,
No. 1, pp.61–79.
Arora, H. and Arora, P. (2012) ‘Bank productivity measurement using Hicks-Moorsteen indices:
evidence from Indian public sector banks’, International Journal of Business Performance
Management, Vol. 13, Nos. 3/4, pp.386–407.
Ballal, T., Elhag, T. and Ambusaidy, S. (2007) ‘Project risk management in Oman: a survey of risk
practices in the construction industry’, CIB World Building Congress, pp.549–557.
Bielsa, J. and Duarte, R. (2011) ‘Size and linkages of the Spanish construction industry: key sector
or deformation of the economy?’, Cambridge Journal of Economics, Vol. 35, No. 2,
pp.317–334.
Chan, A.P.C. and Yeong, C.M. (1995) ‘A comparison of strategies for reducing variations’,
Construct Manage Economy, Vol. 13, No. 6, pp.467–473.
Chia, F.C. (2012) ‘Construction and economic development: the case of Malaysia’, International
Journal of Construction Management, Vol. 12, No. 1, pp.23–35.
Chia, F.C., Skitmore, M., Runeson, G. and Bridge, A. (2012) ‘An analysis of construction
productivity in Malaysia’, Construction Management and Economics, Vol. 30, No. 12,
pp.1–15.
Costello, A.B. and Osborne, J.W. (2005) ‘Best practices in exploratory factor analysis: four
recommendations for getting the most from your analysis’, Practical Assessment, Research &
Evaluation, Vol. 10, No. 7, pp.1–9.
Dai, J., Goodrum, P.M., Maloney, W.F. and Srinivasan, C. (2009) ‘Latent structures of the factors
affecting construction labor productivity’, Journal of Construction Engineering and
Management, Vol. 135, No. 5, pp.397–406.
Deming, W.E. (1982) Quality, Productivity and Competitive Position, Center for Advance
Engineering Study, Massachusetts Institute of Technology, Cambridge, Mass., USA.
Desai, D.A. (2012) ‘Quality and productivity improvement through Six Sigma in foundry industry’,
International Journal of Productivity and Quality Management, Vol. 9, No. 2, pp.258–280.
Dey, P.K., Ho, W., Charoenngam, C. and Deewong, W. (2008) ‘Relationship characteristics within
the supply chain of small and medium-sized construction enterprises in Thailand’,
International Journal of Manufacturing Technology and Management,Vol. 15, No. 1,
pp.102–118.
Doloi, H. (2009) ‘Analysis of pre-qualification criteria in contractor selection and their impacts on
project success’, Construction Management and Economics, Vol. 27, No. 12, pp.1245–1263.
Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S. (2011) ‘Analyzing factors affecting delays in
Indian construction projects’, International Journal of Project Management, Vol. 30, No. 4,
pp.479–489.
Dzeng, R. and Wu, J. (2012) ‘The cost efficiency of construction industry in Taiwan’, The Open
Construction and Building Technology Journal, Vol. 6, No. 2012, pp.8–16.
El-Maghraby, E., Frick, J. and Irgens, C. (2011) ‘Factors affecting pouring ready mix concrete
production rate using tower cranes in Egypt’, International Journal of Data Analysis
Techniques and Strategies, Vol. 3, No. 4, pp.353–374.
Enshassi, A., Mohamed, S. and Abushaban, S. (2009) ‘Factors affecting the performance of
construction projects in the Gaza strip’, Journal of Civil Engineering and Management,
Vol. 1, No. 3, pp.269–280.
Faridi, A. and El-Sayegh, S. (2006) ‘Significant factors causing delay in the UAE construction
industry’, Construction Management and Economics, Vol. 24, No. 11, pp.1167–1176.
Field, A. (2005) Discovering Statistics Using SPSS, Sage Publications, London.
446 M.A. Islam and M.M.R.K. Khadem
Ghoddousi, P. and Hosseini, M.R. (2012) ‘A survey of the factors affecting the productivity of
construction projects in Iran’, Technological and Economic Development of Economy,
Vol. 18, No. 1, pp.99–116.
Goodrum, P.M., Zhai, D. and Yasin, M.F. (2009) ‘Relationship between changes in material
technology and construction productivity’, Journal of Construction Engineering and
Management, Vol. 135, No. 4, pp.278–287.
Gouett, M.C., Haas, C.T., Goodrum, P.M. and Caldas, C.H. (2011) ‘Activity analysis for
direct-work rate improvement in construction’, American Society of Civil Engineers, Vol. 137,
No. 12, pp.1117–1124.
Grimes, C.F. (2007) Employee Motivation, the Organizational Environment and Productivity,
Accel-Team.Com, Accel-Team, Cumbria.
Hair, J.E. et al. (1998) Multivariate Data Analysis, 5th ed., Prentice Hall, Upper Saddle River,
New Jersey.
Hanna, A.S., Russel, J.S., Nordheim, E.V. and Bruggink, M.J. (1999) ‘Impact of change orders on
labor efficiency for electrical construction’, Journal of Construct Engineering Management,
ASCE, Vol. 125, No. 4, pp.224–232.
Hanson, D.N. (2006) Causes of Client Dissatisfaction in the South African Building Industry and
Ways of Improvement: The Contractors’ Perspectives, MSc thesis in Building, University of
the Witwatersrand, Johannesburg, South Africa.
Haskel, J., Goodridge, P., Pesole, A., Awano, G., Franklin, M. and Kastrinaki, Z. (2011) Driving
Economic Growth: Innovation, Knowledge Spending and Productivity Growth in the UK,
NESTA, London.
Hohns, H.M. (1979) Preventing and Solving Construction Contract Disputes, Van Nostrand
Reinhold, New York.
Huang, A.L., Chapman, R.E. and Butry, D.T. (2009) Metrics and Tools for Measuring
Construction Productivity: Technical and Empirical Considerations, NIST Spec. Publ. 1101,
National Institute of Standards and Technology, Gaithersburg, Maryland.
Iyer, K.C. and Jha, K.N. (2005) ‘Factors affecting cost performance: evidence from Indian
construction projects’, International Journal of Project Management, Vol. 23, No. 4,
pp.283–295.
Jaaskelainen, A. (2010) ‘Identifying factors affecting public service productivity’, International
Journal of Services Technology and Management, Vol. 14, No. 4, pp.360–375.
Jaffar, N., Abdul-Tharim, A.H. and Mohd-Kamar, I.F. (2011) ‘A literature review of ergonomics
risk factors in construction industry’, Procedia Engineering, 2nd International Building
Control Conference, Vol. 20, pp.89–97.
James, P.M., Rust, A.A.B. and Kingma, L. (2012) ‘The well-being of workers in the South African
construction industry: a model for employment assistance’, African Journal of Business
Management, Vol. 6, No. 4, pp.1553–1558.
Jarkas, A.M. and Bitar, C.G. (2012) ‘Factors affecting construction labor productivity in Kuwait’,
American Society of Civil Engineers, Vol. 138, No. 7, pp.811–820.
Jarkas, A.M. and Radosavljevic, M. (2012) ‘Motivational factors impacting the productivity of
construction master craftsmen in Kuwait’, Journal of Management in Engineering, 17
October.
Jarkas, A.M., Kadri, C.Y. and. Younes, J.H. (2012) ‘A survey of factors influencing the
productivity of construction operatives in the state of Qatar’, The International Journal of
Construction Management, Vol. 12, No. 3, pp.1–23.
Kaiser, H.F. (1974) ‘An index of factorial simplicity’, Psychometrika, Vol. 39, No. 1, pp.31–36.
Kaming, P.F., Olomolaiye, P.O., Holt, G.D. and Harris, F.C. (1997) ‘Factor influencing
construction time and cost overruns on high-rise projects in Indonesia’, Construction
Management and Economics, Vol. 15, No. 1, pp.83–94.
Kazaz, A. and Ulubeyli, S. (2007) ‘Drivers of productivity among construction workers: a study in
a developing country’, Building and Environment, Vol. 42, No. 5, pp.2132–2140.
Productivity determinants in Oman construction industry 447
Koushki, P.A., Al-Rashid, K. and Kartam, N. (2005) ‘Delays and cost increases in the construction
of private residential projects in Kuwait’, Construction Management and Economics, Vol. 23,
No. 3, pp.285–294.
Krugman, P. (1997) The Age of Diminished Expectations, US Economic Policy in the 1990s,
3rd ed., New York Times book review, USA.
Lam, P.T.I. and Wong, F.W.H. (2011) ‘A comparative study of buildability perspectives between
clients, consultants and contractors’, Construction Innovation: Information, Process,
Management, Vol. 11, No. 3 pp.305–320.
Lema, N.M. (1995) Construction of Labour Productivity Modeling, University of Dar El-salaam,
Tanzania.
Li, Q. and Song, Y. (2012) ‘Productivity growth in Chinese construction industry considering solid
wastes generation’, Advanced Materials Research, Vol. 472–475, No. 2012, pp.3316–3319.
Li, Y. and Liu, C. (2012) ‘Labor productivity measurement with variable returns to scale in
Australia’s construction industry’, Architectural Science Review, Vol. 55, No. 2, pp.110–118.
Long, N.D., Ogunlana, S., Quang, T. and Lam, K.C. (2004) ‘Large construction projects in
developing countries: a case study from Vietnam’, International Journal of Project
Management, Vol. 22, No. 7, pp.553–561.
Makulsawatudom, A., Emsley, M. and Sinthawanarong, K. (2004) ‘Critical factors influencing
construction productivity in Thailand’, The Journal of KMITNB, Vol. 14, No. 3, pp.1–6.
Mezher, T.M. and Tawil, W. (1998) ‘Causes of delays in the construction industry in Lebanon’,
Engineering, Construction and Architectural Management, Vol. 5, No. 3, pp.252–260.
Mojahed, S. and Aghazadeh, F. (2008) ‘Major factors influencing productivity of water and
wastewater treatment plant construction: evidence from the deep south USA’, International
Journal of Project Management, Vol. 26, No. 2, pp.195–202.
Moselhi, O. and Khan, Z. (2012) ‘Significance ranking of parameters impacting construction labour
productivity’, Construction Innovation: Information, Process, Management, Vol. 12, No. 3,
pp.272–296.
Navon, R. (2005) ‘Automated project performance control of construction projects’, Automation in
Construction, Vol. 14, No. 4, pp.467–476.
Ng, S.T. and Tang, Z. (2010) ‘Labour-intensive construction sub-contractors: their critical success
factors’, International Journal of Project Management, Vol. 28, No. 7, pp.732–740.
Ng, S.T., Skitmore, R.M., Lam, K.C. and Poon, A.W.C. (2004) ‘Demotivating factors influencing
the productivity of civil engineering projects’, International Journal of Project Management,
Vol. 22, No. 2, pp.139–146.
O’Brien, K.E. and Associates, Inc. (2008) Improvement of Onsite Productivity, K.E. O’Brien and
Associates, Inc., Toronto, Ontario.
Odeh, A.M. and Battaineh, H.T. (2002) ‘Causes of construction delay: traditional contracts’,
International Journal of Project Management, Vol. 20, No. 1, pp.67–73.
Odhigu, F.O., Yahya, A., Rani, N.S.A. and Shaikh, J.M. (2012) ‘Investigation into the impacts of
procurement systems on the performance of construction projects in East Malaysia’,
International Journal of Productivity and Quality Management, Vol. 9, No. 1, pp.103–135.
Ofori, G. (2006) ‘Revaluing construction in developing countries: a research agenda’, Journal of
Construction in Developing Countries, Vol. 11, No. 1, pp.1–16.
Olawale, Y.A. and Sun, M. (2010) ‘Cost and time control of construction projects: inhibiting
factors and mitigating measures in practice’, Construction Management and Economics,
Vol. 28, No. 5, pp.509–526.
Oman Chamber of Commerce and Industry (2005) Annual Development Report [online]
http://www.chamberoman.com/pdf/ChamberAnnualReport2005.pdf (accessed 16 October
2011).
448 M.A. Islam and M.M.R.K. Khadem
Pellegrino, R., Costantino, N., Pietroforte, R. and Sancilio, S. (2012) ‘Construction of multi-storey
concrete structures in Italy: patterns of productivity and learning curves’, Construction
Management and Economics, Vol. 30, No. 2, pp.103–115.
Phusavat, K., Nilmaneenava, S., Kanchana, R., Wernz, C. and Helo, P. (2012) ‘Identifying
productivity indicators from business strategies’ surveys’, International Journal of
Productivity and Quality Management, Vol. 9, No. 2, pp.158–176.
PwC (2012) Middle East Region, Oman [online] http://www.pwc.com/m1/en/countries/oman.jhtml
(accessed 16 October 2011).
Ray, S. and Ray, I.A. (2012) ‘Malmquist indices of productivity change in India’s chemical
industry: a subsector-level analysis’, International Journal of Economic Policy in Emerging
Economies, Vol. 5, No. 1, pp.16–36.
Rivas, R.A., Borcherding, J.D., Gonzalez, V. and Alarcon, L.F. (2011) ‘Analysis of factors
influencing productivity using craftsmen questionnaires: case study in a Chilean construction
company’, Journal of Construction Engineering and Management, Vol. 137, No. 4,
pp.312–320.
Ruddock, L. and Ruddock, S. (2011) ‘Evaluation of trends in the UK construction industry
using growth and productivity accounts’, Construction Management and Economics, Vol. 29,
No. 12, pp.1229–1239.
Sambasivan, M. and Soon, Y.W. (2007) ‘Causes and effects of delays in Malaysian construction
industry’, International Journal of Project Management, Vol. 25, No. 2007, pp.517–526.
Setijono, D. (2010) ‘A conceptual framework for managing the performance of construction supply
chain’, International Journal of Productivity and Quality Management, Vol. 5, No. 1,
pp.1–20.
Shehata, M.E. and El-Gohary, K.M. (2011) ‘Towards improving construction labor productivity
and projects’ performance’, Alexandria Engineering Journal, Vol. 50, No. 4, pp.321–330.
Sufian, F. (2010) ‘Sources of banks’ productivity growth in a developing economy: efficiency
change or technological progress?’, International Journal of Management and Enterprise
Development, Vol. 9, No. 2, pp.179–200.
Sufian, F. (2012) ‘Determinants of banks’ total factor productivity: the post-Asian financial crisis
experience of the Philippines’, International Journal of Business Excellence, Vol. 5, Nos. 1/2,
pp.77–100.
Sveiby, K. and Simons, R. (2002) ‘Collaborative climate and effectiveness of knowledge work – an
empirical study’, Journal of Knowledge Management, Vol. 6, No. 5, pp.420–433.
Teerajetgul, W., Chareonngam, C. and Wethyavivorn, P. (2009) ‘Key knowledge factors in Thai
construction practice’, International Journal of Project Management, Vol. 27, No. 8,
pp.833–839.
The Consulate General of the Sultanate of Oman-Australia (2012) Govt. Spending in Construction
Industry to Jump 23% at $10b [online] http://oman.org.au/general-news/387 (accessed 1
February).
Toor, S. and Ogunlana, S.O. (2008) ‘Problems causing delays in major construction projects in
Thailand’, Construction Management and Economics, Vol. 26, No. 4, pp.395–408.
Xue, X., Shen, Q., Wang, Y. and Lu, J. (2008) ‘Measuring the productivity of the construction
industry in China by using DEA-based Malmquist productivity indices’, Journal of
Construction Engineering and Management, Vol. 134, No. 1, pp.64–71.
Yu, J. and Lee, H. (2002) ‘Productivity management system for construction projects’, Journal of
the Architectural Institute of Korea, Vol. 18 No. 7, pp.103–113.
Zakeri, M., Olomolaiye, P., Holt, G.D. and Harris, F.C. (1997) ‘Factors Affecting the motivation of
Iranian construction operatives’, Building and Environment, Vol. 32, No. 2, pp.161–166.
Zhang, X. (2005) ‘Concessionaire’s financial capability in developing build-operate-transfer type
infrastructure projects’, Journal of Construction Engineering and Management, Vol. 131,
No. 10, pp.1054–1064.