Professional Documents
Culture Documents
WOLKITE UNIVERSITY
PREPARED BY
1 DAWIT GIRMA (B.sc)
2 GEMACHU SHUNIYE (B.sc)
3 MELKA LEMA (B.sc)
4 BEDASSA DESSALEGN (M.sc)
February, 2017
Wolkite, Ethiopia
Contents
CHAPTER ONE ................................................................................................................. 4
1.1 INTRODUCTION TO HYDRAULIC STRUCTURES ........................................... 4
1.2 CLASSIFICATION OF DAM TYPES .................................................................... 4
1.3 DAM SITE ASSESSMENT AND INVESTIGATION ............................................ 6
CHAPTER TWO .............................................................................................................. 10
2. GRAVITY DAMS ........................................................................................................ 10
2.1 FORCES ACTING & LOAD COMBINATION ON DAMS ................................ 10
2.2 GRAVITY DAM DESIGN AND ANALYSIS ...................................................... 15
CHAPTER THREE .......................................................................................................... 26
3. BUTTRESS DAMS ...................................................................................................... 26
3.1 COMPONENT PARTS OF BUTTRESS DAMS .................................................. 26
3.2. TYPES OF BUTTRESS DAMS........................................................................ 28
3.3. DESIGN PROCEDURE OF FLAT-SLAB TYPE BUTTRESS DAMS ............... 30
CHAPTER FOUR ............................................................................................................. 31
4. ARCH DAMS ............................................................................................................... 31
4.1 ARCH GEOMETRY AND PROFILE. .................................................................. 31
4.2 DESIGN & ANALYSIS OF ARCH DAMS .......................................................... 33
4.3 CONCRETE DAMS DESIGN FEATURES & CONSTRUCTION ...................... 36
CHAPTER FIVE .............................................................................................................. 39
5. EMBANKMENT DAM................................................................................................ 39
5.1. EARTH – FILL DAM ........................................................................................... 39
5.2. ROCK FILL DAM ................................................................................................. 41
5.3. CAUSES OF FAILURE OF EARTH DAMS ....................................................... 41
5.4. CRITERIA FOR SAFE DESIGN OF EARTH DAM ........................................... 42
5.5. SELECTION OF AN EARTH DAM .................................................................... 42
5.6. SEEPAGE ANALYSIS ......................................................................................... 44
5.7. LAPLACE EQUATION FOR TWO DIMENSIONAL FLOWS .......................... 45
5.8. COMPUTATION OF RATE OF SEEPAGE FROM FLOW NET ....................... 47
5.9. SEEPAGE DISCHARGE FOR ANISOTROPIC SOIL ........................................ 48
5.10. PHREATIC LINE IN EARTH DAM .................................................................. 50
5.11. CHARACTERISTICS OF PHREATIC LINE (SEEPAGE LINE) ..................... 56
5.12. GRAPHICAL DETERMINATION OF FLOW NET ......................................... 57
5.13. STABILITY ANALYSIS .................................................................................... 58
CHAPTER SIX ................................................................................................................. 62
6. OUT LET WORKS....................................................................................................... 62
6.1 INTRODUCTION TO DAM OUT LETS .............................................................. 62
6.2 DETERMINATION OF REQUIRED DAM OUTLET CAPACITIES ................. 62
6.3 SELECTION CRITERIA ....................................................................................... 63
6.4 OUTLET WORKS POSITION IN RELATION TO RESERVOIR STORAGE
LEVELS ........................................................................................................................ 63
6.5 LOCATION OF OUT LET CONTROLS .............................................................. 63
6.6 HYDRAULIC DESIGN OF OUTLET WORKS ................................................... 64
6.7 HYDRAULIC DESIGN CONSIDERATIONS...................................................... 66
6.8 STRUCTURAL DESIGN CONSIDERATION ..................................................... 68
CHAPTER SEVEN .......................................................................................................... 73
7. SPILLWAY .................................................................................................................. 73
7.1TYPES OF SPILLWAY .......................................................................................... 74
7.2 CHUTE SPILLWAY OR TROUGH SPILLWAY................................................. 79
7.3 SIDE CHANNEL SPILLWAY .............................................................................. 82
7.4 SADDLE SIPHON SPILLWAY ............................................................................ 83
7.5 SHAFT SPILL WAY .............................................................................................. 87
CHAPTER EIGHT ........................................................................................................... 89
8. ENERGY DISSIPATERS ............................................................................................ 89
8.1 STILLING BASINS TYPE .................................................................................... 90
8.2 BUCKET TYPE ENERGY DISSIPATERS .......................................................... 93
CHAPTER NINE .............................................................................................................. 97
9. WEIR ............................................................................................................................ 97
9.1 DESIGN OF DIVERSION WEIRS ........................................................................ 97
9.3 UPLIFT PRESSURE UNDER WEIR FOUNDATION ....................................... 112
9.4- STRUCTURAL ANALYSIS OF DIVERSION WEIRS .................................... 125
CHAPTER ONE
1.1 INTRODUCTION TO HYDRAULIC STRUCTURES
Brief list of Hydraulic Structures (including those out of the scope of this module are:
- Dams
- Intakes
- Outlets
- Spillways
- Energy Dissipators: Stilling basins, Plunge pools, Flip Buckets, Ski Jumps,
Aprons,
- Navigation structures- Locks, Ship-lifts and inclined plane, inland ports
- Pumping stations
- Canals, (Navigation and Water Conveyance), (Spawning canals)
- Other conveyance structures like pipelines
- Drop structures, Culverts and siphons
- Steel structures like gates, valves, air vessels, air vents, silt outlets
- Diversion work structures (Diversion dams and Weirs, river intakes, settling
basins,
- Fish ladders and passes
- Check dams
- Hydropower stations
- Earth retaining structures
- other river training structures
- Bridges, aqueducts
- Tunnels
- Irrigation structures
- Levees and canal dikes
- Revetments
- Breakwaters
1.2 CLASSIFICATION OF DAM TYPES
The classification of Dams schematically shown in figure below:
Dams
The various types of dams have been defined by ICOLD (International Commission Of
Large Dams) is given below.
Embankment Dam: Any dam constructed of naturally excavated materials placed without
addition of binding material other than those inherent in the natural material.
Embankment dams are usually referred to be types such as Earth fill, Rock fill,
and Hydraulic fill. The term embankment dam is used to indicate a zoned fill dam
involving selected areas of rock, gravel, earth and impervious zones, or
homogeneous earth fill dam. This is not necessarily zoned.
Earth fill dam: An embankment dam constructed primarily of compacted earth in either
homogeneous or zoned areas containing more than 50% of earth.
Hydraulic Fill dam: An embankment dam constructed of earth, sand, gravel or rock
generally from dredged material conveyed to the site of placement by suspension
in flowing water.
Rock fill dam: An embankment type of dam dependent for its stability primarily on rock.
As rock fill dams must contain an impervious zone, usually of selected earth with
filter zones comprising as substantial volume of the dam, the term rock fill dam
usually represents dams that contain more than 50% compacted or damped
pervious rock fill. The impervious zone may be of cement concrete, bituminous
concrete or other impermeable material.
Gravity dam: A type of dam constructed of mass concrete or stone masonry, or both,
which relies on its weight for stability. The dam is usually roughly triangular in
cross section with its base width so related to its height as to insure stability
against overturning, sliding or crushing.
Arch dam: A dam with upstream curvature which transmits the major portion of the load
or pressure to the abutments rather than to the bottom foundation. In general, an
arch dam has a base thickness less than 60% of its height. Dams of greater
thickness are considered as arch-gravity dams or gravity dams.
Arch-gravity dams: Are dams where the load or pressure is transmitted to both the
abutments and the bottom foundation.
Geology
i) Foundation requirements:
ii) Seismicity (earthquake risk):
Topography:
Availability of Technical skills
Cost effectiveness
Availability of materials
Environment and public opinion
Time and money
Hydrology
1.3 DAM SITE ASSESSMENT AND INVESTIGATION
Parties directly involved in engineering of dam activities are:
- Owner - public or private organization
o Provision of financial resources
o Establishment of general objectives
- Consulting Engineer
o Planning and design
o Construction supervision
- Contractor for civil works
o Construction of required infrastructure
o Construction of civil works
o Assembly of equipments
A) Prior to construction
- Preliminary studies
o Collection and evaluation of existing data
o Field trips- reconnaissance of dam site and reservoir area, downstream
area
o Preliminary dam design including selection of type, main dimensions,
approximate site, costs, etc
- Feasibility studies
o Detailed investigation of site conditions
o Final selection of site
o Final selection of dam type, main dimensions, lay out
- Basic design
o Completion of detailed site investigations
o Detailed design, cost estimates construction schedules,
o Development of:
Basic report
Tender documents for the construction of civil works (drawings,
specifications, general and special contract conditions)
B) During Construction
- Detailed (construction execution design)
o Stepwise detail of dam design a head of construction
o Site investigations oriented towards construction
- Construction activities
o Preliminary installation of contractor at site
o Construction of required infrastructure (road, camp, plant, water and
energy supply, etc)
o River diversion
o Construction of dam and associated structures
- Construction and assembly supervision
- Commissioning and operation manuals
o Preparation of manuals for testing, monitoring and operation of
equipment. Maintenance
C) After construction
- Monitoring, surveillance, operation
o Reading of instruments, evaluation of results
o Planning of operation
o Execution of operation activities
A) Topographic survey
- aims to determine and present:
o Configuration of the dam site
o Configuration of the reservoir area
o Accessibility to the site
o Accessibility to construction material sources and deposits
- Reasons
o Importance in dam type selection
o Importance in the selection of appurtenant structures
- Methods
o Arial surveying (used both for preparation of maps and for different
analysis of the data such as geological, geo-morphological, topographical,
etc)
o Ground surveying (scale maps, ground profiles –sections …)
B) Geological and geotechnical investigations
CHAPTER TWO
2. GRAVITY DAMS
a) Primary Loads
Hydrostatic distribution of pressure with horizontal resultant force P1 (Note also a vertical
component exists in the case of an u/s batter, and equivalent tail water may operate in the
d/s face)
Z12 Z1
Pwh w KN / m acting at
2 3
Where crest gates & other ancillary structures of considerable weight exist they must also
be considered in determining Pm & their appropriate position of line of action.
Equilibrium seepage patterns will establish within & under a dam eg. with resultant
forces identified as P3 & P4.
Pu = Ah (Uw ,avg)
Z Z2
. Ah . w 1 if no drain functioning.
2
is area reduction factor
Ah nominal plane area at a section considered.
If no drains functioning
T 2 Z 2 1 Z 1
Pu acts at Y1 m
3 Z 2 Z1
In modern dams internal uplift is controlled by the provision of vertical relief drains close
behind the u/s face. Mean effective head @ the line of drains, Zd can be expressed as
Zd = Z2+Kd (Z1-Z2) m
The standard provision of deep grout curtain below the u/s face intended to limit seepage
also serves to inhibit pressure within the foundation. However, less certain than efficient
draw system & its effect is commonly disregarded in uplift reduction.
b. Secondary loads
Accumulated silt etc, generates a horizontal thrust, Ps. T the magnitude additional to
Pwh is a function of sediment depth, Z3, submerged unit weight s‟ & active lateral
pressure coefficient. Ka:
s1.Z32
Ps K a & acting @ Z3/3 above plane
2
s‟ = s-w where s is sediment saturated unit weight.
1 Sin s
Ka Where s is angle of shearing resistance
1 Ain s
Transient load (Pwave,) generated by wave action against the dam. It is not normally
significant & depends on the fetch & wind velocity.
Hs F
Hs range from 0.75 Hs for concrete dams to 1.3Hs for earth dams.
iii) Wind load: when the dam is full, wind acts only on the d/s side thus
contribute to stability. When empty the wind can act on the u/s face but in
significant compared to hydrostatic load. For buttress dams load on the
exposed surface has to be considered.
iv) Ice load: Not a problem in Ethiopia. It can be significant where ice sheets
form to appreciable thickness & persist for lengthy periods.
Pice =145 KN/m2 for ice > 0.6m thick, otherwise neglected
Seismic load: Horizontal & vertical inertia loads, are generated with respect to the dam
& the retained water by seismic disturbance. Horizontal & vertical accelerations are not
equal, the former being of grater in density. For design purposes both should be
considered operative in the sense last favorable to stability of the dam, under reservoir
full conditions the most adverse seismic loading will then occur when the ground shock is
associated with.
Horizontal Pemh = h Pm
Vertical Pemv = v Pm operating through centroid of the dam
Relative to any elevation @ depth Z1 below the water surface, the pressure pewh
Resonance: results when period vibrations of the structure & earth quake period are
equal. For a concrete gravity dam of triangular X- section base thickness T
600T Eeff
Fn HZ or HZ ( Eeff 14GN / m2 )
hh 0.012h
As an example, the natural frequency of vibration of monolithic gravity profiles with
nominal height of 20m & 50m are 15-25 & 6-9 HZ respectively ( if major seismic
shock frequency of 1-10 HZ). Thus it is only of concern for large dams & vulnerable
portion of the dam.
Load combinations
Different design authorities have differing load combinations. A concrete dam should
be designed with regard to the most rigorous groupings or combination of loads
which have a reasonable probability of simultaneous occurrence.
Three nominated load combinations are sufficient for almost all circumstances. In
ascending order of severity we can have normal, unusual & extreme load combination
(NLC, ULC, ELE respectively) (see table)
With probability of simultaneous occurrence of load combination decreases, factor of
safety should also decrease.
H V o &
M o
Assessed in relation to all probable conditions of loading, including reservoir empty
conditions the profile must have sufficient safety factor w.r.t:
Over turning
Sliding
Stres X
X s
Module for Holistic, Hydraulic structures 15
Wolkite university, College of Engineering and Technology, HWRE February 2017
a) Overturning stability
Factor of safety against over farming, Fo, in terms of moment about the d/s toe of the dam
M
Fo ve
M inclusive of moment generated by uplift )
M
ve
ve
b) sliding stability
Factor of safety against sliding, Fs, estimated using one of the three definitions:
FSS
H
V
If the foundation plane inclined @ small angle o
H tan
Fss
V
H
1 tan .
V
Fss should not permit to exceed 0.75, but under ELC up to 0.9 is acceptable.
: is the ratio of total resistance to shear & sliding which can be mobilized an a plane to
the total horizontal load.
s
Fsf
H
CAh
s V tan( ) KN / m.
cos (1 tan tan )kN / m
forhoriontalplane ( 0)
s cAh V tan .
CS h V tan
Fsf
H.
In some cases it may be appropriate to include d/s passive wedge resistance, pp, as a
further component of the resistance to sliding which can be mobilized.
s pe CAas
Fsf Where pp Ww tan(
H cos (1 tan tan )
In the presence of horizon with low shear resistance it may be advisable to make S=0.
Load combination
Location of sliding plane Normal Unusual Extreme
Dam concrete, base interface 3.0 2.0 >1.0
Foundation rock 4.0 2.7 1.3
This follows conventional soil mechanics logic in defining FLE, as the ratio of shear
strength to mean applied stress across a plane i.e
f
FLE =
c n tan
FLE n . is stress acting normal to plane of sliding
æ
Referring the above figure, for single plane sliding mode:
FLE
CAh V cos H sin tan
H cos V sin . Note for = 0 FLE =FSF.
FLE =2.0 normal operation & FLE =1.3 under transmit condition embracing
seismic activity)
C. Stress analysis in gravity method (Refer Figures 3.7)
Gravity method is useful to analyses stress in straight dams which are not geometrically
complex. It is founded on 2-D elastic dam on uniformly rigid foundation & linear
variation of stress from u/s to d/s .
Analysis is based on modified beam theory which is by combining axial & bending load.
z
V M * 1
y
Ah I
Where, v- resultant vertical load above the plane considered exclusive of uplift.
M* - summation of moments expressed w.r.t the centroid of the plane.
y‟ - distance from the centroid to point of considerations
I - second moment of area of the plane w.r.t centroid
For 2-D plane section of unit width Parallel to the dam axis, & with thickness T normal to
the axis:
V vey1
z 12 3 and at y‟=T/2
T T
v 6e
z 1
T T
M *
e Where v - excludes uplift
V
For e> T/6, at u/s face –ve stress is developed, i.e. tensile stress. In design, tensile stress
has to be prohibited, but difficult to totally eliminate low tensile stress in gravity dam.
Total vertical stresses at either face are obtained by the addition of external hydrostatic
pressure.
Numerically equal & complementary horizontal (zy) & vertical (yz) shear stresses are
generated @ any point as a result of variation of vertical normal stress over a horizontal
plane.
u Pw zu tan u
&
d zd t tan d
The variation b/n u/s & d/s stress is parabolic, & depend on rate of change of variation of
normal stress
yu Pw zu Pw tan 2u
yd zd tan 2 d
4. Principal stresses
,& 3 may be determined from knowledge of z& y & construction of Mohr‟s circle
diagram to represent stress conditions at a point, or by application of the equation given
below.
z y
Major Principal Stress 1 max
2
z y
Minor principal stress 3 max
2
z y
Where max 2
2
The following table gives permissible compression stresses factor of safety for gravity
dam body & rock foundations. (USBR 1976)
1. A horizontal crack is assumed to exist & extend from the u/s face toward the d/s face
to a point where the vertical stress of adjusted diagram is equal to the uplift pressure @
M
e1
V A3.T
T
T1 3 e1
2
2V A3.T
B5 A3
T1
Kd= 0.4 if drains are effective
= 1.0 if no drains.
t‟ = tensile bond strength of concrete.
Ft‟= Factor of Safety [Ft‟ =3 for NLC,
=2 for ULC,&
= 1.0 for ELC
U/s face flare: the u/s face of a gravity profile is frequently modified by the introduction
of a significant flare.
Design of small dams associated with provision of‟ standard‟ triangular profile of u/s
vertical face & d/s slope of 0.75 horizontal to 1.0 vertical.
In the case of large dams a unique profile should be determined to match the specific
conditions applicable. Two approaches are possible; the multi stage & single stage.
Single stage: is based on definition on a suitable & uniform d/s slope. The apex of the
triangular profile is set @ or just above DFL & initial base thickness T is determined for
each loading combination in terms of F0. The critical value of T is then checked for
sliding stability & modified if necessary before checking heel & toe stress @ base level.
The multistage approach defines a profile where the slopes are altered at suitable
intervals.
Design commences from crest level, & descends downwards through profile stages
corresponding to pre determined elevations. Each stage is proportioned to as to maintain
stress level within acceptable limits. E.g. no tension under any condition of loading.
The resulting profile allows marginal economics on concrete, but more expensive to
construct than the single –stage. Multi-stage profiles are now seldom employed, even on
large dams.
When interaction b/n adjacent monolith result in loads transfer & complex structural
response, and further differential settlement exist, then alternative analytical approaches
called trial loads twist analysis & finite element analysis exist.
y2
FSF H CAh
Sliding Pps V
tan
The pre-stressing tendons are typically located @ 3 to 7m centers to centers along the
crest. The pre-stress load required for each, PT (kN) is the appropriate multiple of Pps .
Pre-stressing also useful for heightening of the dam.
CHAPTER THREE
3. BUTTRESS DAMS
3.1 COMPONENT PARTS OF BUTTRESS DAMS
A buttress dams consists of the following component
1) Sloping membrane: - The sloping membrane or u/s deck supports the water and
transmits the water load to a series of buttresses at right angle to the dam axis.
2) Buttresses: - are constructed at right angles to the axis of the dam at certain intervals.
They support the slopping membranes & transfer the load to the foundation. They are
thin walls of triangular profile with sloping u/s face.
3) Footings: - Footings are required for the buttresses to transfer the loads to the
foundation. If the foundation is relatively strong, spread, footings are provided but for
relatively weak foundation max footing is required.
4) Lateral Braces (strut):- are provided b/n adjacent buttresses at right angles to them to
reduce unsupported length & thus provide lateral stiffness and resistance to buckling of
buttresses.
5) Haunches or Corbels: - The wide upstream end of buttresses which help in transiting
the load from the u/s deck to the buttresses.
6) Cutoff: - is provided at the upstream end of the dam to reduce the seepage & up lift.
Disadvantages
i) Needs reinforcement and expensive shuttering
ii) Additional skilled labor is required to create form work
iii) Threat of deformation of concrete from impounded water is more likely than
from a thick gravity section
iv) More susceptible to damage by sabotage.
CHAPTER FOUR
4. ARCH DAMS
The single –curvature arch dam & the double curvature arch or capola were introduced
with concrete dams previously and the rock & valley conditions which various arch dam
were outlined in the first chapter.
F1
F2 H
Arch dam transfers its loads to the valley sides than to the floor. Overturning & sliding
stability have little relevance here. If the integrity & competence of the abutment is
assured, failure can occur only as a result of overstress. Arch dam design is therefore
centered largely up on stress analysis and the definition of an arch geometry which avoids
local tension stress concentration and /or excessive compressive stress. The area of
cupola dam offer great economics in volume of concrete.
Associated with saving may also be realized in foundation excavation & preparation, but
the sophisticated form of arch dam leads to very much increased unit costs. In case of
complex geology of abutment saving can also be negated by requirement of ensuring
abutment integrity under all conditions.
The horizontal component of arch thrust must be transferred in to the abutment at a safe
angle β as shown in the figure below. In general abutment entry angle of 450 to 700 is
acceptable.
a
Foundat ion rock cont ours
t
en
ng
ί
ta
F
Fig. Angle between arch thrust and rock contour
i) Constant radius profile: is the simplest geometry, U/s face of the dam is of
constant radii with a uniform radial d/s slope. It is apparent that central angle, 2θ,
reaches a max. @ Crest level.
In symmetrical valley minimum concrete volume when 2θ =1330, but entry angle
preclude this & 2θ ≤ 110. The profile is suited to relatively symmetrical U-shaped valley.
ii) Constant angle profile: Central angle of different arch have the same magnitude
from top to bottom & uses up to 70% of concrete as compared to constant radius
arch dam. But it is more complex as demonstrated in the figure. It is best suited to
narrow & steep-sided V-shaped valleys.
iii) Cupola profile. Has a particularly complex geometry & profile, with constantly
varying horizontal & vertical radii to either face.
- The theory envisages that the weight of concrete & that of water on the dam is
carried directly to the foundation not to the abutment
- The horizontal water load is borne entirely by arch action.
- The discrete horizontal arch elements are assumed to form part of a complete ring
subjected to uniform radial pressure, Pw, from the water load & hence it is
assumed to have uniform radial deformation.
Ri t
dh
Ru
F
F
B/2 B/2
V= A.R2θ = T*1*R2θ
hR h
T w KR ; K w
2
B
V KR K
2 2
sin / 2
dV
0 , gives = 1330341. (Most economical angle of arch with minimum volume)
d
Ru
Ri
T
Ru
R
Ri
T
Pu
pi
Ru2 Ru2 Rd 2 / R 2
p w
Ru2 Rd2
ring stress is max @ d / s face
T Ru Rd is uniform at any elevation .
2 w Z 1 Ru
2
Tr For analysis
( Ru Rd )
Note in theory, T should diminish towards crown & increase towards abutments. In
practice, T usually is constant at any elevation on a simple arch profile, and correction for
maximum stress at abutment made by factor, Kr, determined as a function of θ & Ru /T
from curves.
For thin rings theory, therefore,
K r w Z1 Ru
h at abutment .
Tr
h
*
w Ho
?
p=
Mo
Ru
R
Rd
?
Ma abu
tm ent
Ha
Thrust @ crown
PR T2
H o PR 2 sin is in radians.
D R
1 T 2 sin 2
where D
2 2 sin
2
if shear is neglected .
12 R 2
T2 sin 2 T2 sin 2
D 1 2 sin 3
2
( ) if shear is included .
2
2 2
12 R 12 R 2
sin
M 0 PR H o R1
Moment @ crown:
sin
Moment @ abutments: M a R PR H o cos
After calculating thrusts & moments, stresses at intrados & extrados are calculated from
H 6M
2 .
T T
Relief drain efficiency is a function of drain geometry i.e. spacing , distance
form u/s face
Internal design features
Inspection gallery
Collects inflow from seepage & inspection gallery.
Also gives access to appurtenance structures
Should not be less than 2x1.2m
Adequate ventilation & lighting is required
o Transverse contraction joints ( inter- month invites)
Vertical contraction joints are formed @ regular intervals of 12-15m.
They permit minor differential moment
They are made necessary by shrinkage & thermal characteristics conc.
Pulvino
Pulvino or pad, which is heavy perimentral concrete, is constructed between the shell
of a cupola dam & the supporting rock to assist in distributing load in to the
abutments and foundation.
Concrete zoning
Different concrete mix can be need in facing & hearting of concrete dam.
14A
13A
3rd year 12A
11A
10A
9A 12-15m
8B
8A
2nd year 7B
7A
6B
6A 5C
5B
5A 4C
4B
4A 3C
3B
1st year 3A A,B,C= variable concrete quality
2A 2B 2C
1A 1B 1C
Fig:Concrete zoning
Cement:
Aggregates:
Water:
Pozzolana:
Admixtures:
CHAPTER FIVE
5. EMBANKMENT DAM
In the case of Hydraulic fill dam the materials are excavated, transported and placed by
Hydraulic fill method. In this method the flumes are laid at a suitable falling gradient
along the outer edge of the embankment. The material mixed with water at borrow pits, is
pumped into these flumes. The slush is discharged through the outlets in the flume, at
suitable interval along their length. The slush thus flows towards the center of the bank.
The course material of the slush settles at the outer edge while finer material settles at the
center. No compaction is done. At present the method is not in general use.
Rolled fill earth dams can further use subdivided into the following types
(i) Homogeneous embankment type
(ii) Zoned embankment type
(iii) Diaphragm embankment type
Embankment Dam
Accordint to design
According to method of
Constructuion
b) Modified homogeneous
Figure 5.3
(3) Diaphragm embankment type: In this the bulk of the embankment is
constructed of pervious material and a thin diaphragm of impermeable material is
provided to check the seepage. The diaphragm may be of impervious soils,
cement concrete, bituminous concrete or other material and may be placed either
at the centre of the section as a central vertical core or at the u/s face as a blanket.
The designation „rock fill embankment‟ is appropriate where over 50% of the fill material may
be classified as rock pieces. It is an embankment which uses large size rock pieces to provide
stability and impervious membrane to provide water tightness.
Modern practice is to specify a graded rock fill heavily compacted in relatively thin layers by
heavy plants. The constructions method is essentially similar to that of Earth fill Dams. Materials
used for membrane are earth, Concrete steel, asphalt and wood. The impervious membrane can
be placed ether on the upstream face of the dam or as a core inside the embankment. Such a
construction therefore becomes similar to diaphragm type. Rock fill embankments employing a
thin u/s membrane are referred to as decked rock fill dams.
5.3. CAUSES OF FAILURE OF EARTH DAMS
On the basis of investigation reports on most of the past into three main classes:
1. Hydraulic failures : 40%
2. Seepage failures : 30%
3. Structural failures: 30%
Figure 5.5
The preliminary design of an earth dam is done on the basis of past experience and on the basis
of the performance of the dams built in the past. We shall discuss here the preliminary selection
of the following terms:
1) Top width
Module for Holistic, Hydraulic structures 42
Wolkite university, College of Engineering and Technology, HWRE February 2017
2) Free board
3) Casing or outer shells
4) Central impervious core
5) Cut-off trench
6) Downstream drainage system.
1) Top width. The crest width of an earth dam depends on the following considerations:
Nature of the embankment materials and minimum allowable percolation
distance through the embankment at the normal reservoir level.
Height of the structure
Importance of the structure
Width of highway on the top of the dam
Practicability of construction
Protection against earthquake forces.
Following are some of the empirical expressions for the top width b of the earth dam, in terms of
the height H of the dam:
H
b 3 For very low dam (H<10m)
5
b=0.55H1/2 + 0.2H For medium dam (10m<H<30m)
1/3
b=1.65(H+1.5) For large dam (H>10m)
2) Free board. Free board is the vertical distance between the horizontal crest of the
embankment and the reservoir level. Normal free board is the difference in the level
between the crest or top of the embankment and normal reservoir level. Minimum free
board is the difference in the elevation between the crest of the dam and the maximum
reservoir water surface that would result and spillway function as planned. Sufficient free
board must be provided so that there is no possibility whatsoever of the embankment
being overtopped.
3) Casing or outer shells. The function of casing or outer shells is to impart stability and
protect the core. The relatively pervious materials, which are not subjected to cracking on
direct exposure to atmosphere, are suitable for casing. Table 5.2 (a) gives
recommendations for suitability of soils used for earth dams as per IS: 1826-1978.
To determine the quantity of water passing through the body of the dam and
foundation.
To obtain the distribution of pore water pressure.
The seeping water flows under a hydraulic gradient which is due only to gravity
head loss, or Darcy‟s law for flow through porous medium is valid.
There is no change in the degree of saturation in the zone of soil through which
the water seeps and the quantity flowing in to any element of volume is equal to
quantity which flows out in the same length of time.
(Steady flow)
The hydraulic boundary conditions at entry and exit are known.
∆y
Vx Vx+(∂Vx/∂x)∆x
∆x
Consider an element of soil is size x, y and of unit thickness perpendicular to the plane of the
Vy
paper. Let Vx and Vy be the entry velocity components in x and y direction. Then
v
v x x x and
x
v
v y y y
y
will be the corresponding velocity components at the exit of the element. According to
assumption 3 stated above, the quantity of water entering the element is equal to the quantity of
water leaving it. Hence, we get
v v y
vx y.1 v y x.1 vx x x y.1 v y x.1
x y
From which
v x v y
0 … (i)
x y
Module for Holistic, Hydraulic structures 45
Wolkite university, College of Engineering and Technology, HWRE February 2017
According to assumption 2:
h
vx K xix K x * … (ii)
x
h
And VY kY IY Ky … (iii)
y
Where h = hydraulic head under which water flows.
Kx and Ky are coefficient of permeability in x and y direction.
Substituting (ii) and (iii) in (i), we get
2 K x h ( K y .h)
2
0 … (5.1)
x 2 y 2
For an isotropic soil,
Ky = Kx = K
Hence we get from eq. (5.1)
2h 2h
0
x 2 y 2
Substituting velocity potential = = K*h , we get
2 2
0 … (5.2)
x 2 y 2
This is the Laplace equation of flow in two dimensions. The velocity potential may be defined
as a scalar function of space and time such that its derivative with respect to any direction gives
the fluid velocity in that direction.
This is evident, since we have
=Kh
h
K K .i x v x
x x
h
Similarly , K K .i y v y
y y
The solution gives two sets of curves, known as equipotential lines and stream lines (or flow
lines), mutually orthogonal to each other, as shown in Fig. below. The equipotential lines
represent contours of equal head (potential). The direction of seepage is always perpendicular the
equipotential lines. The paths along which the individual particles of water seep through the soil
are called stream lines or flow lines.
Module for Holistic, Hydraulic structures 46
Wolkite university, College of Engineering and Technology, HWRE February 2017
A network of equipotential lines and flow lines is known as a flow net. Fig.5.6 shows a portion
of such a flow net. The portion between any two successive flow lines is known as flow channel.
The portion enclosed between two successive equipotential lines and successive flow lines is
known as field such as that shown hatched in Fig. 5.6.
h
Then h
Nd
h b
q K … (ii)
Nd l
Hence the total discharge through the complete flow net is given by
h b Nf b
q q k . .N f kh .
Nd l Nd l
Where Nf = total number of flow channels in the net. The field is square and hence b=l
Nf
Thus, q kh
Nd
This is the required expression for the discharge passing through a flow net, and is valid only for
isotropic soils in which
k x k y k.
This is not a Laplace equation. Hence flow net cannot be drawn directly. Rewriting, it we get
k x 2h 2h
0
k y x 2 y 2
ky
Let us put xn x
kx
Where xn is the new co-ordinate variable in the x - direction.
Then the above equation becomes,
2h 2h
0 … (5.3)
xn2 y 2
Figure 5.7:
To plot the flow for such a case, the cross-section through anisotropic soils is plotted to a
natural scale in the y-direction, but to a transformed scale in the x-direction, all
ky
dimensions parallel to x- axis being reduced by multiplying by the factor . The flow
kx
net obtained for this transformed section will now be constructed in the normal manner as
if the soil were isotropic. The actual flow net is then obtained by re- transforming the
cross- section including the flow net, back to the natural scale by multiplying the x-
k
coordinates by factor x . The actual flow net thus will not have orthogonal set of
ky
curves. As shown in figure 10.17, field of transformed section will be a square one, while
the field of actual section (retransformed) will be a rectangular one having its length in x
Kx
direction equal to times the width in y direction.
Ky
Phreatic line / seepage line / Saturation line is the line at the upper surface of the seepage
flow at which the pressure is atmospheric.
Figure below shows a homogeneous earth dam with horizontal drainage blanket FK at its
toe. The phreatic line in this case coincides with the base parabola ADC except at the
entrance. The basic property of the parabola which is utilized for drawing the base
parabola is that the distance of any point p from the focus is equal to the distance of the
same point from the directrix. Thus
Distance PF = Distance PR where, PR is the horizontal distance of P from the
Directrix EG
Figure 5.9
Graphical method
Steps:
Starting point of base parabola is @ A AB = 0.3L
F is the focal point
Draw a curve passing through F center @ A
Draw a vertical line EG which is tangent to the curve
EG is the directrix of the base parabola
Plot the various points P on the parabola in such a way that PF = PR
Analytical method
PF = PR
x 2 y 2 x yo
From point A (known), x = b and y = h
yo b 2 h 2 b
d ( y 0 2 xy o )
2
qk ( y o 2 xy o )
2
dx
yo
q k( )( y o 2 xy o )
2
y o 2 xy o …………. (5.7)
2
q kyo
a
Table for the value of with slope angle
a a
a
a a
300 0.36
600 0.32
900 0.26
1200 0.18
1350 0.14
1500 0.10
1800 0.0
Figure 5.11
a. Analytical Solution of Schaffernak and Van Iterson for < 300 (Fig.5.9)
In order to find the value of a analytically, Schaffernak and Van Iterson assumed that the
energy gradient
dy
i tan . This means that the gradient is equal to the slope of the line of seepage,
dx
which is approximately true so long as the slope is gentle (i.e. <300).
b h
a sin tan dx
a cos
a sin
ydy
and
h 2 a 2 sin 2 a
a sin tan (b a cos )
2
Figure 5.12
dy
Thus q kiA k A (5.10)
ds
dy
At J, s= a and y = a sin sin
then,
ds
Where s = distance measured along the curve.
Substituting in (5.10), we get
S h
a sin 2 ds ydy
a a sin
h 2 a 2 sin 2
a sin .( S a)
2
2
2
h
or a 2 2aS 0
sin 2
h2
From which aS S 2
…. (5.12)
Sin 2
a b 2 h 2 b 2 h 2 cot 2 … [5.13]
Figure 5.13
0
Figure 5.14
Based on the above discussions, the characteristics of the phreatic line may be
summarized below:
1. At the entry point, the phreatic line must be normal to the upstream face
since the upstream face is a 100% equipotential line. For other entry
condition (Fig.5.15), the phreatic line starts ta11ngentially with the water
surface.
2. The pressure along the phreatic line is atmospheric. Hence the only change
in the head along it is due to drop in the elevation of various points on it.
Due to this, the successive equipotential lines will meet it at equal vertical
intervals.
3. The focus of the base parabola lies at the break out point of the bottom
flow line, where the flow emerges out from relatively impervious medium
to a highly pervious medium.
4. When horizontal filter or drainage toe is provided, the phreatic line would
tend to emerge vertically.
5. In the absence of any filter, the seepage line will cut the downstream slope
at some point above the base. The location of this point, and the phreatic
line itself, is not dependent on the permeability or any other property, so
long as the dam is homogeneous. The geometry of the dam alone decides
these.
6. The presence of pervious foundation below the dam does not influence the
position of phreatic line.
7. In the case of a zoned dam with central impervious core, the effect of
outer shells can be neglected altogether. The focus of the base parabola
will be located at the downstream. Toe of the core (Fig. 5.14)
After having located phreatic line in an earth dam the flow net can be plotted by trial and
error by observing the following properties of flow net (Fig 5.16), and by following the
practical suggestions given by A Casagrande.
Stability analyses under the following four heads are generally needed:
1. Stability analysis of downstream slope during steady seepage.
2. Stability of upstream slope during sudden Draw down.
3. Stability of upstream & downstream slope during and immediately after
construction.
4. Stability of foundation against shear.
It is one of the most generally accepted methods of checking slope stability. In this
method the potential surface is assumed to be cylindrical, and the factor of safety against
sliding is defined as the ratio of average shear strength, as determined by Coulomb‟s
equation
S = C + tan to the average shearing stress determined by static‟s on the potential
sliding surface. In order to test the stability of the slope, a trial slip circle is drawn, and
the soil material above assumed slip surface is divided in to a convenient number of
vertical strips or slices. The trail sliding mass (i.e. the soil mass contained with in the
assumed failure surface) - is divided in to a number (usually 5 to8) of slices which are
usually, but not necessarily, of equal width. The width is so chosen that the chord and arc
subtended at the bottom of the slice are slice passes through material of one type of soil.
The forces between the slices are neglected and each slice is assumed to act
independently as a column of soil of unit thickness and width b. The weight W of each
slice is assumed to act at its centre. If this weight of each slice is resolved in normal (N)
and tangential (T) components, then the normal component will pass through the center
of rotation (O), and hence does not cause any driving moment on the slice. However, the
tangential component T cause a driving moment
= T (T*r), Where r is the radius of the slip circle. The tangential components of the few
slices at the base may cause resisting moment; in that case T is considered negative.
If c is the unit cohesion and L is the curved length of each slice, then resisting force
from Column‟s equation is = c L + N tan
For the entire slip surface AB, we have
Driving moment Md = rT
Module for holistic exam, hydraulic structures 58
Wolkite university, College of Engineering and Technology, HWRE February 2017
Fellenius gave the method of locating the locus on which probable centers of critical slip
circle may lie. He gives direction angles to be plotted at heel measured from the outer
slope and to be plotted from horizontal line above the top surface of the dam. These two
lines plotted with given direction angle intersect at point P. Point P is one of the centers.
To obtain the locus we obtain point Q by taking a line H m below the base of the dam and
4.5 H m away from toe. When the line PQ is obtained, trial centers are selected around P
on the line PQ and factor of safety corresponding to each centre calculated from Equation
given above as ordinates on the corresponding centers, and a smooth curve is obtained.
The centre corresponding to the lowest factor of safety is then the critical centre.
Critical condition for d/s slope occurs when the reservoir is full and percolation is at its
maximum rate. The directions of seepage forces tend to decrease stability. In other words,
the saturated line reduces the effective stress responsible for mobilizing shearing
resistance.
cL tan ( N U )
F .S . ….. (5.15)
T
When U is the total pore pressure on the slope surface
The pore-water pressure at any point is represented by the piezometric head (hw) at that
point. Thus the variations of pore water pressure along a likely slip surface is obtained by
measuring at each of its intersections with an equipotential line, the vertical height from
that intersection to the level at which the equipotential line cuts the phreatic line. The
pore pressure represented by vertical height so obtained are plotted to scale in a direction
normal to the sliding surface at the respective point of intersection. The distribution of
pore water pressure on the critical slope surface during steady seepage is shown hatched
in fig.5.19.The area of U- diagram can be measured with help of a planimeter.
In the absence of a flow net, the F.S of the d/s slope can approximately be from the
equation
cL tan N '
F .S . … (5.16)
T
The following unit weights may be used for the calculation of N ' and T when pore
pressure are otherwise not included in the stability analysis, however the Phreatic line
needs to be drawn.
CHAPTER SIX
6. OUT LET WORKS
Most of the water, which is stored in a reservoir for irrigation water supply or power
penetration purposes, is stored below the spillway crest level. The spillway is provided at
normal pool level, such that the floods are discharged safety above the spillway. But, in
order to draw water from the reservoir as and when needed, for irrigation, water supply,
power generation etc it is absolutely necessary that outlet works are provided either
through the body of the dam or adjacent to it through some hillside at one end of the dam,
or adjacent to it through some hillside at one end of the dam, this water may be
discharged to the dome stream channel below the dam or may be transported at distances
where required (to some power house, etc) through pipes or canals. The opening a pipe or
tunnel provided for this withdrawal of water is known as a dam out let.
An outlet works may also act as a flood control regulator, to release waters temporarily
stored in flood control storage space or to evacuate storage in anticipation of flood
inflows. Further, the outlets may serve to empty the reservoir to permit inspection, to
make needed repairs, or to maintain the upstream face of the dam or other structures
normally inundated.
Outlet works controls are designed to release water as specific rates, as indicated by
downstream needs, flood control regulation, storage canted regulation, storage
considerations, or legal requirements. Delivery of irrigation water is usually determined
from project or form needs and is related to the consumptive use and to any special water
requirements of the irrigation system. Delivery for domestic are can be similarly
established. Release of flows to satisfy prior rights must generally be included with other
needed releases. Minimum d/s flows for pollution abatement, fish preservation, and other
companion needs may often be accommodated through other required releases.
Flood control releases generally can be combined with the irrigation outlet release if the
out let empties in to the river instead of into a canal. The capacity of the flood control
outlet is determined by the required time of evacuation of a given storage space
considering the inflow into the reservoir during this emptying period.
The type of dam (concrete or embankment) greatly affects the design and the cost of an
outlet. The lengths of waterways and the requirements for energy dissipation have
important effects on costs.
For an out let works with an upstream control discharging in to a free- flowing conduit,
part full flow will occur throughout the length of the structure. Ordinarily, the operating
head and the conduit slope will result in flow at super critical stage.
With controls placed at the u/s end of a conduit, fish screens, stop log, slots, trash racks,
emergency gates, and regulating gates or valves can all be combined in a single intake
structure. In this case, the entire conduit may be readily un watered for inspection or
repair. The intake will consist of a towel rising from the base of an outlet conduit to an
operating deck placed above maximum reservoir water level, with the towel located n the
reservoir area near the upstream toe of the dam.
Where a control gate is placed at an intermediate point along a conduit and discharges
freely in to the d/s section, the internal pressure u/s from the control will be
approximately equal to full reservoir head. The structural design and safety aspects of the
u/s portion will then be concerned with the effects of both the external loadings and the
internal hydrostatic pressure acting on the conduit shell.
The control gates or valves for a conduit through a concrete dam can be positioned at any
point, either u/s to afford full flow or at the d/s end to provide pressure pipe flow. Where
the sluices are provided in the overflow section of the dam (spillway), u/s gates
controlling the entrance or valves operated from an interior gallery in the dam are
ordinary employed. Where the outlets are place in the non-overflow section, either u/s
gates or d/s valves are utilized.
6.6 HYDRAULIC DESIGN OF OUTLET WORKS
The hydraulics of out let works usually involve either one or both of two conditions of
flow-open channel (or free) flow and full conduit (or pressure) flow. Analysis of open
channel flow in outlet works, either in open water way or in a part full conduit, is based
on the principle of steady non uniform flow confirming to the low of conservation of
energy. Full pipe flow in closed conduits is based on pressure flow, which involves a
study of hydraulic losses to determine the total heads needed to produce the required
discharges.
Hydraulic jump basin, baffle or impact block dissipaters or other stilling devices
normally are employed to dissipate the energy of flow at the downstream end of the
outlet works. Many of these devices are designed on the basis of the low of conservation
of momentum.
A) Open channel flow in outlet works
Flow in an open channel outlet works will be similar to that in open channel spillways.
Where un submerged radial or slide gates are used, discharge through the control with the
gates completely opened will be computed by:
Q= CLH3/2
When open channel outlet flow is controlled by partly opened surface gates, sluice flow
will result. Discharges for such flow are given by the equation:
2 g CL H1 2 H 2 2
2 3 3
Q
3
where c is the discharge coefficient, L is the crest length & H is differential head causing
flow.
In instances where there is high tail water due to canal water surfaces or to d/s influences
in the streambed, the control openings may be partly or entirely submerged. For such
conditions the discharge through the control will be in accordance with submerged orifice
or tube flow as computed by the equation:
Q CA 2 gH
Where A = area of the opening
H= d.ce d/n the u/s & d/s openings
C= coefficient of discharge
B) Pressure flow in outlet conduits
If a control gate is placed at some point downstream from the conduit entrance, that
portion above the control gate will flow under pressure an un gated conduit may also
flow full depending on the inlet geometry for a flow in a closed pipe system, Bernoulli‟s
equation can be written as follows:
V2
H T h2
2g
Where HT is the total head needed to overcome the various head losses to produce
discharge and, h2= the cumulative losses of the system.
V2
is velocity head at exit.
2g
The above equation can be expanded to list each loss, as follows,
V2
HT=ht+he+hb+hf+hex+hc+hg+ 1
2g
Where ht= trash pack loss
he=entrance loss
hb= bend loss
hc =constraction loss
hex =expansion loss
hg =gate or valve loss
hf= friction loss, and
V12
= velocity head exit loss at the out let.
2g
For a free discharging out let, HT is measured from the reservoir water surface to the
center of the outlet gate (opening). If the out flowing jet is supported on a d/s floor the
head is measured to the top of the emerging jet at the point of greatest contraction; if the
outlet portal is submerged the head is measured to the tail water level. When various
losses are related to the individual component, hi is written as
V12
H I Ki
2g
Where Ki is the summation of loss coefficients with continuity combined. Therefore the
above equation can be written as
v12 2 gH T
HT K L Then Q a1
2g kL
Intakes
Outlet intake structures have numerous configurations and features needed to satisfy
project equipments and optimize site conditions. Intakes are positioned with respect to
various reservoir levels. Such as the lowest level required for reservoir evacuation, the
bottom of active storage, the minimum level for power generation. The bottom of flood
control storage, the temperature and dissolved oxygen level, the sediment deposition
level, or some other specified operating level. Intakes are also positioned laterally as
required by the delivery point downstream from the dam, or to make best use of
topography and geology.
The shape of intake flow surfaces varies from sharp-edged entrances where slide gates
are mounted on the face of a concrete structure to carefully designed streamlined shapes
where head losses must be minimized, as for power outlets.
Conveyance Structures
Conveyance structures include conduits, tunnels, chutes, pipes, and other water ways.
These structures must be compatible with the upstream and down stream structures.
Conduits and tunnels may be designed for free flow or pressure flow. Many outlets
include a combination of two or more of the types of conveyance structures mentioned. A
common type of outlets is composed of a pressure conduit or tunnel from an intake
structure an emergency gate chamber near the axis of the dam, from which the flow is
carried in a free- standing steel pipe with in a concrete access and maintenance conduit to
a control structure. Downstream from the control structure, a concrete chute may be used
to convey the flow to a stilling basin or flip bucket. Another common type has the
emergency and the control gates located in the gate chamber and a free-flow conduit or
tunnel downstream.
The hydraulic designs of gate chambers include the waterways connecting the upstream
and downstream conveyance structures. Gate chambers are normally located near the axis
of a dam and under or within the dam section or in on both of the abutments. When the
conveyance system pressurized throughout, the gate chamber houses an emergency or
guard gate. A properly sized air vent is required at the gate to prevent collapse of the
downstream portion when a downstream portion of the conveyance system vides for free
flow, the gate chamber houses both gate and regulating (control) gates.
The waterways are normally transitioned from the stream conduit or tunnel configuration
in the gate frames downstream to the configuration of the downstream tunnel or conduit.
The downstream transition may increase where the flow changes from pressure flow to
free flow.
Control Structures
Control structures for outlets may be located in the intake in a terminal structure, or at an
intermediate point conveyance system. The location selected depends on economies,
function, type of dam, and safety considerations.
It is good practice to provide guard or emergency gates upstream from control gates and
valves to satisfy maintenance and inspection requirements. For control use when the
control gate or valve is not available for use, and for replacement of certain types of
control gates or valves.
Conveyance Structures
Conduits for concrete dams are typically located along the centerline of a spillway
monolith. Alignments close to monolith joints are avoided. Air vent intakes for the
conduits can be e located in crest piers. The air vents should never be interconnected.
Dividing outlet release requirements among two or more conduits is preferable to
concentrating the releases in one conduit, so that inspection and maintenance can be
performed in one conduit.
Gate chambers and shafts located under and within embankment dams and in abutments
are suitable alternatives to intake towers in many cases. These chambers and shafts
should be located at or upstream from the dam axis at the location of the grout curtain, if
one is provided Gate shafts constructed in an embankment dam should be located at a
sufficient distance from an abutment to ensure that lateral tilting will not result from
settlement of the embankment toward the center of the mass.
General
The structural design of outlet works should be developed concurrently with the
hydraulic design. By using a combined process. Starting with the conceptualization stage,
extremely difficult structural design problems, and possibly redesign. Can be avoided
with considerable savings of time and effort. The design engineer should be constantly a
ware of the need for economical, safe and reliable designs.
Design loads, temperature loads static live loads, dynamic live loads, temperature
loadings, and unexpected and unusual loads caused by improper operation of gates and
valves.
Static live loads include water pressures on interior and exterior surfaces. Embankment
and backfill loads. Ice loads on intake structures and other structures exposed to ice
loadings. Frost heave, temperature loadings, expansive soil loadings and construction
loadings.
Dynamic loads include seismic loadings, impact loads from flowing water, hydraulic
transient loadings, vibration loads from equipment and from fluctuating water pressures,
wind loadings, and in some cases, loadings from reservoir wave action.
The structural design of inlet and outlet channels is similar to that for approach and exit
channels for spillways. Channel protection for the inlet channels for outlet works in
usually less important than protection for the approach channels for spillways because of
the lower operating velocities of the inlet channels, except during the initial filling period
or when the inlet channels are used for diversion flows during construction.
Outlet channels for outlet works should be more conservatively designed than exit
channels for spillways, because of the greater frequency and longer duration of operation
of the outlet channels.
Intakes
Intakes for outlet works frequently are subjected to differential water loads caused by
partial blockage of trashracks. Intakes located near the water surface are more subject to
trash accumulations than are deeply submerged intakes. However, waterlogged material
tends to accumulate over time and should be considered a potential cause of area
reduction of the trashracks. Many designers use arbitrary amounts of differential head,
depending on the amount of submergence. A minimum of 5 ft (1.5 meters) and a
maximum of 40ft (12.2 meters) differential head are some times used. Another approach
is to compute the actual amount of head loss across the trashracks. Based on an assumed
percentage of net trashracks area.
The choice between an intake tower equipped with control gates and a central control
shaft or chamber should depend on an evaluation of the several factors involved.
The downstream control-structure location for free-flow outlet releases is selected when
an evaluation of he various applicable factors favors this location. Usually economic
factors control the selection. But indirectly the alignment of the waterway with respect to
the river and use of the most suitable type of energy dissipater are important
considerations.
Submerged Intakes
Intakes for embankment dam out-let works frequently are submerged shafts and
ho9rizontal intake types. These are simple and economical structures. They usually have
trash racks or trash beams and stream lined entrances to a conduit or a tunnel. Where
used primarily for flood control, they would not be deeply submerged, except during
periods of flood control operations: so unwatering the conduit or tunnel for routine
examination and maintenance would be relatively simple. However, if the intake must be
located below a deep conservation pool, the problems associated with unwatering are
more difficult. In either case, bulkheads are required.
Wide variety of gates and valves is used in outlet woks. Their use depends on their
purposes, operating characteristics, servicing requirements, life expectancy, and cost.
Large gates and valves for high-head installation may require special designs. Gates
intended for temporary use for the purpose of unwatering the outlet conduit or tunnel are
usually of the bulkhead type, which frequently are designed for removal and on-land
storage. These gates are constructed of reinforced concrete or steel, and require gate slots
equipped with embedded metal sealing and bearing surfaces and slot covers for deeply
submerged installations.
Gates
Cates may be classified according to the following:
1. Position in the dam crest gates and high head (submerged gates & valves
2. Function service, maintenance and emergency gates,
3. Pressure transmission-to piers & abutments, to gate sill etc
4. Mode of operation: Regulating and non-regulating gates or valves
5. Type of motion: - Translatory, rotary, rolling, floating gates, moving along or
across the flow
6. Moving mechanisms: gates powered electrically, mechanically, hydraulically,
outemotically by water pressure or by hand.
The main operating mechanisms of gates are failure-free performance water lightness,
rapidity of operation, minimum hoist capacity and convenience installation and
maintenance.
Crest gates
If a temporary barrier can be installed over the permanent raised crest of a spillway,
additional water can be stored between the spillway crest and the top of the barrier during
the fog-end of the rainy season. The small flows in excess of the barrier top level, may be
permitted to pass over the barrier. If , however, large floods occur, the barrier may be
removed and full spillway capacity made available for the outflow. The basic structural
design of crest gates is the method used for transferring the pressure acting on them.
A) Pressure transmission to piers and abutments used by plain vertical lift gates and
step- lays, radial gates and roller gates; the gates may be designed for flow over
or under the them for a combined flow condition.
B) Pressure transmission to the gate sill is used, for example by sector (drum gates)
(with upstream or downstream hinge, roof (bear-trap) gates etc.
Plain gates
Plain (vertical lift) gates, designed as a lattice, box girder, a grid of horizontal and vertical
becomes and stiffness, or a single slab steel plate, may consist of single or double section
(or even more parts can be involved in the closure of very high openings) in the case of
flow over the top the gate it may be provided with an additional flap gate. The gates can
have slide or wheeled support.
The pill face downstream of the gate slots may be protected against the effect of flow
separation and possible cavitations either by recessing it against the upstream pier face or
by a bevel of a slap up to 20:1
Radial gates
Radial gates (Tainter) gates are constructed as portals with cross bars and arms (straight,
radial, or inclined) but could also be cantilevered over the arms. Their supports hinges are
usually down stream but ( for low heads) could also be upstream, resulting in shorter
piers.
The usual range of heads and spans for radial gates is 2<H(m)<14 and 3< B(m) 55, with
(BH)max 550m2. Radial gates may be designed for more than 20MN per bearing.
The advantages of radial over plain gates are smaller hoist, increased speed of raising,
higher stiffness, lower piers, absence of gate slots, easier automation and better winter
performance; on other hand, radial gates require longer and thicker piers, and there may
be difficulties with the bulk-head installation.
The gate is usually hoisted by cables fixed to each end to prevent it from twisting and
jamming. As the cables are connected to the bottom of the gate its top can be raised
above the level of the hoist itself.
Sector Gates
Sector (dram) gates may be hinged upstream (figure below) or downstream; in the later
case the hinge is usually below the spillway crest by about 0.1H to 0.2H. Sector gates an
dam crests are usually of the upstream hinge type, with the hinge about 0.25H above the
d/s pate sill and a radius of curvature of r=H. The heads can be as high as 10m and the
spans 65m.
Sector gates are difficult to install, and require careful maintenance and heating in winter
conditions; their main advantages are care of automation and absence of lifting gear, fart
movement, accuracy of regulation, are of passing of ice and debris, and low piers.
High head gates and valves
High head (submerged) gates and valves transit the load to the surrounding structure
either directly through their support e.g. Plain (Vertical lift). Radial, or ring follower
gates, or through the shell encasing the valve. The most common values of the latter type
are non-regulating disc values (turning about a horizontal or vertical axis), cylindrical or
ball valves etc.
Radical gates are normally hinged d/s, but sometimes used in reversed position with alms
inside or, more frequently, out side the conduit at the end of which the regulating gate is
installed.
A special feature of some high- head fainter gates is the use of eccentric trunnions which
permit a gap to be formed between the seals and the seal seats before opening the gate so
that only moments causes by the gate weight and hinge friction have to be overcome.
CHAPTER SEVEN
7. SPILLWAY
It is a structure constructed to pass surplus flood water on the D/S of reservoir and Dam.
Essential requirements of a spillway
The required capacity of spillway i.e., maximum outflow rate through spillway must
be determined by flood routing knowing:
(i) Inflow rate v/s time
(ii) Reservoir capacity curve (reservoir surface elevation v/s reservoir storage)
(iii) Discharge curve (out flow v/s reservoir water surface elevation).
Note that large dam with inhabited area on the D/S side needs large protection. Whereas,
Small dams with uninhabited area on its D/S side needs limited protection.
Indians experience for fixing the spillway capacity is shown in the table below.
Class of Dam Gross storage (Mm3) Hydraulic head (m) Inflow flood for safety of dam
Small 0.5 to 10.0 7.5 to 12.0 100 years of flood
Intermediate 10.0 to 60.0 12.0 to 30.0 Standard Project flood (SPF)
Large > 60.0 > 30.0 Probable maximum flood (PMF)
However, floods of large or smaller magnitude may be used if the hazard involved in the
eventuality of a failure of a particular dam is high or low. A reservoir with larger storage
capacity will normally require a smaller out flow rate through the spillway. If the out
flows through the spillway are supplemented by release through the outlets then the
required capacity of spillway may be reduced. For gated spillway more water is stored.
By proper operation of gate higher heads may be developed so that greater out flow
through the spillway is possible to pass the flood.
7.1TYPES OF SPILLWAY
Classification based on the time when the spillways come into operation
(a) Main or service spillway
(b) Auxiliary spillway
(c) Emergency spillway
Auxiliary spillway
It is provided as a supplement to the main spillway and its crest is so located that it comes
into operation only after the floods for which the main spillway is designed is exceeded.
Thus it is provided in conjunction with the main spillway. Conditions favorable for the
provision of auxiliary spillway are the existence of a saddle or depression along the rim
of the reservoir which leads into a natural water way. On the crest of auxiliary spillway
instead of a control gate a fuse plug (earth dam or dyke) may be provided, which allows
the water surface in the reservoir to rise above the crest of spillway and is so designed
That when overtopped it automatically washes out thus releasing excess flood water.
Emergency spillway
It is also provided in addition to main spillway but it comes into operation only during
emergency which may arise at any time which may not have been considered in the
normal design of main spillway. Some of the situations which may lead to emergency
are:
(i) an enforced shut down of the outlet works
(ii) A malfunctioning of spillway gates.
(iii)The necessity of bye passing the regular spillway because of damage or failure of
some part of the structure
(iv) Further an emergency may also arise if a recurring flood occurs before a previous
flood is evacuated by the main spillway and outlet works.
With respect to control structures discharge channel etc, the spillway is classified
into following types.
(i) Free over-fall or straight drop spillway
(ii) Over flow or Ogee spillway
(iii) Chute or open channel or trough spillway
(iv) Side channel spillway
(v) Shaft or morning glory spillway
(vi) Conduit or tunnel spillway
(vii) Siphon spillway
The ogee profile should provide maximum possible hydraulic efficiency, structural
stability and economy and also avoid the formation of objectionable sub-atmospheric
pressure at the crest. The ogee profile may be categorized into three groups:
(i) Overflow dams with vertical U/S face
The following equation as given by U.S. corps of engineers may be used for finding
coordinates (X , Y) for the D/S profile
Where X & Y are coordinates as shown in the figure and Hd is the design head.
For U/S profile following coordinates with origin at crest are recommended
xn = K (Hd)n-1 y
Where: n., K are variable parameters which depends on the inclination of U/S face of the
dam. Hd is the design head. These are called standard “WES standard spillway shapes”
Values of constant K,n , R1,R2, a and b
Shape of K N R1/Hd R2/Hd a/Hd B/Hd
U/S face
Vertical 2.000 1.850 0.5 0.20 0.175 0.282
3V: 1H 1.936 1.836 0.68 0.21 0.139 0.237
3V: 2 H 1.939 1.810 0.48 0.22 0.115 0.240
3V: 3H 1.873 1.776 0.45 0.00 0.119 0.000
The curved profile of the crest section is continued till it meets tangentially the straight
sloping portion of the overflow dam section (spillway).The slope of the d/s face of the
overflow dam usually varies in the range of 0.7(H):1(V) to 0.8:1 and is basically decided
on the basis of stability requirements. The location of the point of tangent depends upon
the slope of the d/s face, where the value of dy/dx for the curved profile and the straight
segment must be equal at the end of the sloping surface of the spillway. At the end of the
sloping surface a curved circular surface called BUCKET is provided to create a smooth
transition of flow from spillway surface to river.
The BUCKET is also useful for dissipation of energy and prevention of scour.
The discharge over ogee spillway is computed from the basic equation of weir given
below:
Q = Cd L H1.5
Where, Q = Discharge in cumec
Cd = coefficient of discharge
L = effective length of overflow crest in meters
H = Head of over flow in meters including velocity of approach head.
H = Hd + Ha
The discharge coefficient is influenced by a number of factors:
(i) Height of spillway above stream bed or depth of approach
(ii) relation of the actual crest shape to the ideal nappe shape
(iii) upstream face slope
(iv) downstream apron interference, and
(v) downstream submergence
(vi) Ratio of actual total head to the design head
(vii) effect of head due to velocity of approach
Model tests indicate that the coefficient of discharge becomes fairly constant when height
of spillway > 3.0 Hd, where Hd is the design head including the head due to velocity of
approach.
Various text books give a plot of Cd versus Hd which is reproduced here in the form of a
table
P/Hd Cd P/Hd Cd P/Hd Cd
0.0 1.7 0.1 1.875 0.2 1.97
0.3 2.025 0.4 2.06 0.5 2.09
0.6 2.12 0.7 2.135 0.8 2.15
0.9 2.16 1.0 2.17 1.5 2.185
2.0 2.195 2.5 2.2 3.0 2.205
4.0 2.210
In the table P is the height of spillway.
When u/s face is inclined the above Cd values gets multiplied by a factor from 0.995 (for
P/ Hd = 1.5) to 1.04 (for P/ Hd = 0.2)
hence provided easily on Earth & Rock-Fill dam. It is also called at times Waste Weir. If
it is constructed in continuation of the dam at one end, it may be called a Flank weir. If it
is constructed in a natural saddle in the bank of the river separated from the main dam by
a high ridge it is called a Saddle Weir.
A chute spillway essentially consists of a steeply sloping open channel placed along a
dam abutment or through a flank or saddle. It leads the water from the reservoir to the
downstream channel below.the base of the channel is usually made of reinforced concrete
slabs 25 to 50 cm thick. Light reinforcement of about 0.25% of concrete area is provided
in the top of the slab.in both directions. The chute is some times of constant width but is
usually narrowed for economy and then widened near the end to reduce the discharging
velocity. Expansion joints are usually provided in the chutes at intervals of about 9to 12m
in either direction. The expansion joint s should be made water tight so as to avoid any
under seepage and its troublesome effects. Under drains are also provided, so as to drain
the water which may seep through the trough bottom and side walls. These drains may be
in the form of a perforated steel pipes., clay tiles or rock filled trenches.
Slope of chute can conform to available topography leading to minimum excavation, but
the slope should be steep enough to maintain supercritical flow to avoid unstable flow
conditions.
When a vertical curve is provided at a point where chute slope changes it must be gradual
& designed to avoid any separation of flow.
XN = a (He)N-1Y
In a side channel spillway, the crest of the control weir is placed along the side of the
discharge channel. the crest is approximately parallel to the side channel at the entrance.
Thus the flow after passing over the crest is carried in a discharge channel running
parallel to the crest. Water flows over the crest into the narrow trough of the discharge
channel opposite the weir, it turns approximately at right angle and then continues in the
discharge channel.
The side channel spillway is usually constructed in a narrow canyon where sufficient
space is not available for an overflow spillway, and where there is neither a suitable
saddle, nor there is a availability of a wide flanks to accommodate a chute spillway. In
such cases, if a crest of length required for the flow to occur perpendicular to the crest is
provided, heavy cutting would be required making the cost of constructing a chute
spillway or an overflow spillway prohibitive.
The crest of a side channel spillway is usually an ogee- shaped section made of concrete.
sometimes it consists of a flat concrete pavement laid on an earthen embankment or the
natural ground surface.
The siphoning action once initiated will continue as long as water level in the reservoir is
above the full reservoir level. The operating head for the spillway is then equal to the
difference between water levels on the U/S and the D/S of the spillway. When the water
level in the reservoir drops to such a level that the inlet of the de-primer hood gets
exposed then the air enters the siphon duct and breaks the siphoning action thus stopping
the flow. This action is called de-priming of the siphon spillway.
Another form of saddle siphon spillway provided in the body of Dam is called „Tilted
Outlet type‟. It has a vertical lower limb and hence the draught of falling water is enough
to cause priming and no other device is needed for its priming. However the outlet is
tilted upwards in order to develop water seal at the bend and thus facilitate early priming.
For De-priming air inlet pipe is provided.
Priming devices
The priming devices are used to expedite the priming of siphon spillway with relatively
small depths. Thus these devices are used to reduce the priming depths for spillway. The
priming devices create effective water seals which cause early priming of siphon
spillways. As such priming devices are also termed as water seals.
Name of some of these devices are:
(i)Baby siphon or Auxiliary siphon : (ii) Joggle or Tudel or Step
(iii) Hinged or Steel plate (iv) Clear over fall (v) Priming weir or over fall weir.
(vi) Provision of a cup type basin (vii) Provision of a tilted outlet
De-priming: De-priming is the reverse process of priming. It is the action of siphon from
the time air starts entering the siphon through the vents until the siphoning action
completely stopped. De-priming is carried out by providing de-primers. A deprimer is an
air vent and is provided to break the siphoning action when the reservoir surface is drawn
below it. If an air vent is not provided, siphoning action once initiated would continue till
the reservoir level is brought down to the level at the inlet which is provided much below
the normal reservoir level.
Discharge through Saddle Syphon
The discharge equation can be expressed in terms of radii of crest and crown
Let R1 = Radius of crest
R2 = Radius of crown
Consider any point P on the vertical section at the throat, and let its radius be r.
The L- section of the throat is shown.
Let V1, V2, and V be the velocities of flow at the crest, crown and point P respectively.
The flow through the throat is governed by free vortex flow for which we have:
V*r = constant
Hence, V1*R1 = V2 *R2 = V*r
Let h0 be the net operative head at the crest. This head is calculated after making due
allowances of all losses occurring in the siphon, h0 = H - Losses through the siphon.
Hence, V1 = (2gh0)0.5
V = V1. (R1/r) = (R1/r)*( (2gh0)0.5)
Consider a thin rectangular strip of thickness dr at P and let dq be the discharge through
this strip of unit length.
dq = V.dr.1 = (R1/r)*( (2gh0)0.5). dr
Hence, discharge q through the throat per unit length is given as
Applying Bernoulli's equation between throat and the outlet one can easily infer that the
pressure at the throat is always going to be negative. Besides the pressure distribution is
non uniform due to the curvature of stream lines and the pressure is lower at the crest
than at the crown. Keeping these in mind, the total drop of siphon structure should be
limited to about 6 m so that negative pressures do not reach the cavitations pressure.
When the water level in the reservoir rises, it seals the air entry and sheet of water
enters the funnel from all sides. The spiral flow of water through the volute causes
suction which sucks all the remaining air and priming is thus achieved very quickly.
The siphon then runs full. When the reservoir level falls, air enters through the de-
primer dome, thus breaking the siphoning action.
Depending upon the type of crest, the shaft spillway can either be standard crested or
flat crested. In a standard crested spillway, the water begins its free fall immediately
upon leaving the crest where as in flat crested spillway water approaches upon the crest
on a flat slope before beginning its free fall. The standard crested spillway would have a
smaller diameter crest since its coefficient of discharge is greater than a flat crest.
Therefore if the shaft spillway is to be constructed in the form of a tower, it would be
economical to have a standard crested spillway. However a flat crested shaft spillway has
a smaller funnel diameter and is therefore more advantageous when the spillway is to be
excavated in rock.
CHAPTER EIGHT
8. ENERGY DISSIPATERS
In hydraulic engineering numerous devices like stilling basins, baffled aprons, and vortex
shaft etc., are known under the collective term ENERGY DISSIPATERS. Their purpose
is to dissipate hydraulic energy (convert to heat). This are also called downstream
protection works and occupies a vital place in design of spillways, weirs and barrages.
Hydraulic Jump type Stilling Basin
(i) Horizontal apron type
(ii) Sloping apron type
Jet Diffusion & free jet stilling basin
(i) Jet diffusion basin
(ii) Interacting jet diffusion basin
(iii) Free jet stilling basin
(iv) Hump stilling basin
(v) Impact stilling basin
Bucket type energy dissipaters
(i) Solid roller bucket type
(ii) Slotted roller bucket type
(iii) Sky jump Bucket type (trajectory or shooting or flip)
Energy dissipation process can be achieved in five separate stages some of which
may be combined or may be absent
(i) On the spillway surface
(ii) In a free falling jet
(iii) At impact into a Downstream pool
(iv) In the stilling basin
(v) At he out flow into a river
(1) stilling basins for Froude's number between 1.7 and 2.5.
For this case only a horizontal apron needs to be provided. As the flow in this case does
not have much turbulence usually no accessories are required to be provided. However,
the apron should be sufficiently long to contain the entire jump over it.
Length of apron = Length of jump = 5 Y2, where Y2 is the sequent depth.
(2) Stilling basins for Froudes number between 2.5 and 4.5
For this range of Froude number Type I stilling basin has been found to be effective for
dissipating the energy of flow. The basin is provided with chute blocks. The length L of
the stilling basin may be obtained for different values of F1 from the following table:
F1 2 3 4 5
L/Y2 4.3 5.3 5.8 6
In this case due to oscillating jump being developed, wave action is produced which
cnnot be entirely dampened. However in order to suppress the wave action the floor of
the basin should be so set that the tail water depth in the basin is 10 % greater than the
sequent depth Y2. this will also check the tendency of the jump to sweep out of the basin.
(a) when the velocity of incoming flow is less than 15m/s, Type II stilling basin have
been adopted. This basin utilizes CHUTE BLOCKS, BAFFLE BLOCK and an
ENDSILL. The size, spacing and location of the chute and baffles blocks are shown in
figure. The length L of the stilling basin and the heights h3 and h4 of the baffle blocks and
end sill respectively may be obtained for different values of F1 from the following table:
F1 5 6 8 10 12 14 16
L/Y2 2.3 2.5 2.6 2.7 2.8 2.8 2.8
h3 /y 1 1.5 1.7 2.0 2.3 2.7 3.0 3.3
h4 /Y 1 1.2 1.3 1.5 1.6 1.7 1.8 1.9
(b) When the velocity of the incoming velocity exceeds 15 m/s, TYPE III STILLING
BASIN may be adopted. In this basin only chute blocks are provided and instead of a
solid end sill a dentate sill is provide. In this basin baffle blocks are not provided because
(i) Due to high velocity of incoming flows these blocks will be subjected to
excessive large impact forces and
(ii) There is a possibility of cavitation along the downstream face of theses blocks
and adjacent floor of the basin due to large negative pressure developed in the
region.
However, due to baffle blocks being eliminated in this case the dissipation of the energy
is primarily accomplished by hydraulic jump and hence the length of the basin will be
greater than that indicated for the TYPE II BASIN. The length of TYPE III stilling basin
may be obtained for different values of F1 from the following table:
F1 5 6 8 10 12 14
L/Y2 3.85 4.0 4.2 4.3 4.3 4.3
Again in this case also in order to check the tendency of the jump to sweep out of the
basin the floor of the basin is so set that the tail water depth in the basin is 5% greater
than the sequent depth.
The upward deflection of water by the bucket lip creates a high boil on the water surface
and a violent ground roller. This ground roller continuously pulls the loose bed material
backwards and deposits the same against the lip of the bucket. Some of the materials may
move into the bucket, which may get trapped there and damage the surface of the bucket
by abrasion. Moreover due to severe surface boil the turbulent flow persists for a
considerable distance on downstream side thus resulting in the erosion of the river banks.
These drawbacks of the solid roller bucket are removed in slotted roller bucket.
__________
Radius of the Bucket: R= 0.6 H/ *Hd
/
Where H = fall from crest of spillway to bucket invert in meter.
And Hd =Head over crest in meters
Vente Chow‟s Formula R = 0.306 *10k
Where k = (v1+6.4 Hd +4.88)/(3.6 Hd + 19.5)
V1 = velocity of flow at the toe of spillway in m/s
X= (Vo2/g) sin 2
Jet trajectory height is given by Y = h sin2 = (Vo2/2g) sin2
A judicious selection of exit angle is necessary, an exit angle of 30 o to 35o is a good
choice. When the maximum tail water is lower than the bucket lip shape of the lip is kept
flatter for ease of construction. High sub atmospheric pressure at downstream lip has to
be avoided by aeration or provide a curved or sloping lip.
CHAPTER NINE
9. WEIR
9.1 DESIGN OF DIVERSION WEIRS
Site Investigation
I- Social and Economic Aspects
The project planner and the designer, during the first investigations, seek answers to a
few questions which are crucial for deciding the scheme‟s feasibility. These questions
are:
1. Coherence of the farming society.
2. Will the proposed structure create any conflict?
3. The need for miscellaneous structure.
II- Technical Considerations
A design engineer who visits the site, for the first time is seeking answers to the
following vital questions, which directly affect the design.
The answers to the above questions usually give the design engineer sufficient
information to decide what materials should be used and what construction technology
Another important factor in choosing the structure type is the implementation method. If
the project is implemented by farmers themselves one naturally opts materials and low
technology. On the other hand, if it is constructed by constrictors, the economy of the
structure may be only decisive factor.
3. Topography survey
Layout of the river. About one kilometer up and downstream of the structure‟s
location is sufficient.
The topographic survey should extend 250 m to both sides of the river.
Cross section of the river at each 50 m in straight reaches of the river and at 25 m
in bends.
A contour map of an interval not larger than 1 m for the land, 0.50 m for the river
bed and of 0.25 m near the structure.
Layout of the river stretch surveyed should be drawn to a scale not larger than
1:2000. The weir location for a distance 50 m up and downstream of the structure
to be drawn to a scale not less than 1:200.
The horizontal and vertical scale of the river cross section must be the same and
must not exceed 1:50 or 1:100 depending on the size of the river.
4. Soil Investigation
Table 1 Required soil data for the design of hydraulic structures
Data Purpose
1 Soil profile to detect impermeable and soft layers under the foundation
under
the foundation
2 Soil to estimate engineering properties of the soil
classification estimate safe exit hydraulic gradient at the d/s toe of the foundation
design filter under riprap
3 Permeability to estimate seepage rate under the foundation
4 Unit weight, to calculate lateral pressure on retaining walls,
angle of internal estimate the soil bearing capacity
friction, and
cohesion of the
soil.
5 Compressibility to estimate settlement of the structure
and coefficient
of consolidation
of soil layers
Module for holistic exam, hydraulic structures 98
Wolkite university, College of Engineering and Technology, HWRE February 2017
Soil classification
Soil classification and grain size distribution of the foundation soil are needed of (i) safe
hydraulic gradient at the downstream edge of the structure‟s foundation; (ii) design of
filter for under riprap wherever it is used; (iii) estimating roughly the engineering
property of the soil such as coefficient of permeability.
5. Hydrological data
Hydrological data is required at the project area to obtain, after their analysis, the design
discharges. The design discharges, maximum and minimum values, are important figures
which are used by the designer to size the structure. To design the canal network, the
mean discharge of the river is also needed.
The maximum design discharge is the peak river discharge that corresponds to a certain
return period which is usually decided by the designer on economic and engineering
ground. The maximum design discharge is used in the design, to determine the backwater
curve results from constructing the weir in order to predict the highest water level that
occurs, on average once every (T) years, where T is the selected return period of the
discharge.
The behavior of the surface flow is greatly affected by the geometry of the weir and the
geometry of the weir directly affects the design and economy of the structure. Some
important features of the weir and their effects on the design are given in the following
sections.
1. Crest Elevation
The crest elevation of the weir affects the water profile in two ways:
1. The height of the crest affects the discharge coefficient and consequently the
waterhead above the weir and the back water curve.
2. The height of the weir affects the shape and location of the jump and the design of
the basin.
Height of the weir is usually decided with the requirement of the canal intake in mind. To
fulfill the objective of the intake structure the following points should be considered in
deciding the crest elevation:
- The crest level should be so set that the waterhead required to deliver the main
canal‟s discharge design is obtained
- If the entire flow of the river at low flows is diverted, the crest elevation must be
set at a level so that the ponded water gives the required head to apply the canal
with the design flow.
- If the minimum flow in the river exceeds the discharge of the offtake canals, the
crest level of the water can be set lower than the river water level which is
required to deliver the design flow in the canal, to allow for the downstream water
rights.
- The maximum (allowable) upstream water surface elevation must also be
considered in selecting the crest elevation. The maximum allowable water level
depends on the upstream river bank elevation and the infrastructure such as
bridges, roads, buildings, etc. The minimum freeboard at the maximum design
discharge must not be less than 0.50 m, although this cannot be achieved in many
seasonal rivers which overflow annually.
2. Length of the Weir
Length of the weir depends on the physical features of the given site. The effect of the
weir length on the upstream waterhead and sedimentation behind the weir must be
understood.
- A weir with a long crest gives a small discharge per unit length and hence the
required energy dissipation per metre of the crest is smaller than what is needed
for a shorter crest length.
- Constructing a weir longer than the river width causes formation of islands at the
upstream side of the weir. As a result the canals‟ inlets can become cutoff from
the river flow. The formation of the islands upstream of the weir reduces the
effective length of the crest.
As a general rule the crest length should be taken as the average wetted width during the
flood. In taking the average, the upstream and downstream of the proposed location
should be examined and the width at a stable location measured.
3. Shape of the Weir
In deciding the shape of the weir two important factors need to be considered: the
practicality and the economy of the structure. When a weir is designed, the designer
should consider the skill of the people who are expected to implement the structure.
There are weirs of different types and shapes and most of them are constructed to serve
the same purpose. The designer should not impose a weir with a shape which cannot be
constructed easily by the local builders. It is unwise, for example, to impose an Ogee-
shaped weir on farmers in a remote village, just because the discharge coefficient is
slightly better than other alternatives. It is not suggested here that the designer should
sacrifice the efficiency and economy of the structure, altogether, for the sake of
simplicity. However, compromise must not be made on the stability of the structure.
Two types of weirs are very common in small irrigation schemes. These are:
1. concrete weir with vertical upstream and slopes downstream faces,
2. Stepped weir, which is usually constructed from gabion boxes.
A commonly constructed, but slightly complicated, weir is the one developed by the US
Army of Engineers known as the WES weirs (developed at its Waterways Experiment
Station).
Discharge over Weirs
Discharge over weirs is generally expressed as follows (Fig. 9.1):
Q CLH e
3/ 2
where Q = discharge
L = length of the weir
He = height of energy line above the crest
= V2/2g + Hd
C = discharge coefficient
When piers are placed on the crest to support a slab for the river crossing or to operate the
controlled gates:
Q C Lo KNH e H e
3/ 2
(9.1)
Discharge coefficient is related to He/Hd and it varies according to the type of weirs.
Determination of the coefficient C for two common weirs is given in the following
section.
The shape of the Waterways Experiment Stations (WES) weirs, which are presented in
Fig. 5.3 is expressed by:
X n K o H dn1Y (9.2)
Where X and Y are coordinates of the crest profile with the origin at the highest point of
the crest. Hd is the design head excluding the velocity head of the approach flow and K o
and n are parameters depending on the slope of the upstream face. The values of Ko and n
are given in Table 9.1.
Table 9.1 Parameters for the WES weir shape formula (Eq. 9.2)
Q(theoretical) = 1.706LHe3/2
Experiments have shown that for a well rounded upstream edge the discharge is:
Q = 1.673LHe3/2
Bos (1989) concluded that for He/b > 1.5, the weir acts as a suppressed sharp weir and the
discharge formula would be:
Q = 1.84LHe3/2
If, for example the crest width is 0.50 m and the head of water over the crest is 0.75 m,
this last equation applies.
In practice a discharge coefficient C = 1.70 is usually used. Here also the last figure is
recommended. When a weir is designed, engineers deal with the probability and
discharge records that are liable to have many errors. Changing the coefficient C from 1.7
to 1.75, for example, affects the discharge by only 2.9%. While errors in the hydrological
data and the method of estimating the design discharge are undoubtedly much greater.
The equation applied here is:
Q = 1.70LHe3/2
When the crest supports piers, the weir length must be modified according to Eq. (9.1).
9.2 Water Profile at the Weir Site
The engineer who designs a weir is interested in the water profile upstream and
downstream of the weir for the following reasons.
The level of the back water curve is required to be determined for the following reasons:
1. to determine the safe level of the embankment and superstructures,
2. to find out whether the canal intakes for which the weir is built, receive water at
all stages of the river and what type of headwork is needed.
In the following, determination of the water profile upstream and downstream of the weir
is discussed.
1. Water Profile Upstream of the Weir
In the previous sections, it was explained how the level of the weir crest is fixed to give
the required water level upstream of the weir. The required water level may be a level
which guarantees a certain discharge for the offtake canal when the river is at its lowest
discharge. Once the crest level is decided, it is required to draw the water profile for few
possible discharges. Usually the analysis is carried out for Qmax which corresponds to 50
and 100 years return period, 2/3 and 1/3 of Qmax and also for a flow which corresponds to
a certain drought level, for example the minimum discharge which has a return period of
ten years.
Construction of weirs elevates the total energy line upstream of the structure. The
difference between the upstream and downstream energy grade line become very high.
Therefore, the energy must be dissipated before it reaches the natural river course,
otherwise it causes damage to the banks and downstream of the apron. The flow over the
weir is in a supercritical state. Therefore, the energy tends to dissipate through a
hydraulic jump downstream of the weir. To control location of the jump, the apron and
stilling basin are designed to suit a range of river discharges.
(i) to determine the height of the river banks upstream of the weir and,
(ii) to find out whether the water surface is high enough to deliver the
required discharge to the off take canals.
There are several methods to determine the water profile upstream of weirs, but here only
two methods are explained.
This method gives results accurate enough for the preliminary design in channels of
uniform cross-section and constant hydraulic properties. It assumes that the following
equation fits the profile.
XS 2 o 2
Y
4 0
Y = Water rise, at distance X upstream of the weir, above the normal water depth.
X = Distance from the crest to the point where Y is required to be determined.
S = Slope of the river.
o = Rise of water above the normal depth at the weir site (X = 0).
This method does not take into account the geometry and the hydraulic properties of the
channel.
Standard step method
This method is a trial and error procedure by which the water profile upstream or
downstream of a structure can be determined. The trial can start at any location, but it is
advisable to carry the computation upstream if the flow is subcritical and downstream if it
is supercritical. The computations stepwise are as follows:
1. Field works
The river cross section must be surveyed, whenever its geometry and hydraulic properties
significantly change. The sections and river profile must be drawn to appropriate scales.
The distance upstream of the weir which should be covered by the survey, depends on: (i)
the maximum afflux over the weir, and (ii) how significant the installations and
infrastructures on both sides of the river banks are. For example, if it is required only to
find out whether the back water curve hits a bridge at some distance upstream of the weir,
then only the distance between the weir and the bridge needs to be surveyed. It is helpful
to realize that in a channel of uniform cross-sections and constant hydraulic properties,
the effect of the back water curve disappears at a distance X from the weir, where:
2 o
X
S
If for example, o = 1.50 m and S = 0.001, the effect of constructing a weir on the water
profile diminishes at 3000 m away from the structure.
2. Foe each cross section surveyed, determine its area (A) wetted perimeter (P) and the
hydraulic radius (R) at different water depths. Plot the water depth D against A and D
against R. (Table 9.2).
3. Prepare a table with 21 columns as it is shown in Table 9.3. Number of the rows
initially is not known, it depends on the number of river cross sections and initial value of
the water surface assumed in the trial.
The heading of the columns is self explanatory, with the possible exception of column 13
which contains the energy coefficient:
K / ai2
i N
3
i i
i 1
iN
K i / A2
i 1
In the computation, i is not known: it is assumed to be equal to one. Therefore the above
equation becomes
K
i N
3
i i / ai2
i 1
3
iN
K i / A2
i 1
In the computation, I is not known: it is assumed to be equal to one. Therefore the above
equation becomes
K
iN
3
i / ai2
i 1
3
iN
K i / A2
i 1
4. Start of the computation: The computation starts by assuming a water level at the first
section if the actual value is not known. Insert this Figure in column 5 of Table 9.3. From
the given water and bed levels, the water depth is calculated. The figure in columns 7 and
8 are obtained from the graphical relationships of D, A, and R, explained in step 2 above.
5. The figures in columns (14-21) are then calculated systematically by applying the
formulae given in the column headings. The average slope of the energy line S is the
arithmetic mean of the value calculated for the present station (X) and its previous one
(X-X). The total head in column 21 is equal to the total head at the previous station ((X-
X) and the friction loss hf at the current station X. If the value of H calculated in column
21 does not agree with the H value in column 16, a new water level is assumed and
entered in column 5. The procedure must be repeated until the two figures in column 16
and 21 agree closely.
Determination of the tail water depth
Throughout this chapter the tail water depth and its effects on the jump location and the
profile are mentioned several times. How the depth is calculated is now explained.
To determine the tail water depth, the rating curve at the location of the water needs to be
known. The curve is usually constructed from the river stage and discharge measurement
records. Usually, this data is not available at the location of the weir; therefore, a
theoretical rating curve should be constructed. If the stream flow record is not available at
the weir site, the following steps can be taken to draw a rating curve accurate enough for
the design purpose.
1. Surveys should be carried out at the location of the weir to draw the cross section
of the river.
2. The cross section needs to be drawn to a suitable scale. Assume different water
depths in the river, and determine the water area and wetted perimeter
corresponding to each depth.
3. For each depth, determine the flow velocity and discharge by using the Manning
equation (Fig. 5.22).
4. Plot the assumed depths and their corresponding discharges to present the rating
curve.
The rating curve is used to determine the water depth for known values of the river
discharge. Fig. 5.22 is an example on constructing the rating curve.
The purpose of the weir is to create sufficient head to supply the main irrigation canal
with the design discharge. The canal head regulator is usually gated to control the amount
of flow into the canal. The most common types of head regulators are:
1. open intake and
2. Closed or culvert intake.
Each of these cases is explained separately.
Open intake
This consists of the intake mouth, which acts as an orifice or weir, a transition and the
main canal. Fig. 5.25 presents a typical open intake. The intake is usually designed as an
orifice. Discharge through the intake is calculated by using the orifice formula as follows
Q CA 2 gh
C 0.7201 0.0074W
Where h < 5 ft and w < 10 ft, where w is the width of the gate. For h < 1 ft both give
nearly the same answer. In practice C = 0.6 and 0.7 are used for rectangular and circular
orifices respectively.
The hydraulics of the downstream floor of the intake should be treated in the same way as
for the main weir downstream. The floor must be long enough to accommodate the jump
and their weights balance the uplift pressure.
Determination of the water uplift pressure and its distribution under hydraulic structures
is a significant part of their engineering design. Without knowing the uplift pressure at
different points along the foundation, the stability analysis of the structure cannot be
carried out and the structure cannot be dimensioned properly to give the required safety
factor.
Failure of weirs on permeable foundations occurs as a result of one or more of the
following:
Piping or undermining soil under the foundation can cause collapse of the apron and
eventual overturning of the structure.
Uplift pressure. A weir can fail when the uplift pressure creates an overturning moment
in excess of the superstructure‟s balancing moment. To avoid this happening, the uplift
pressure must be estimated correctly and the structure dimensioned properly.
One of the shortcomings of Bligh‟s method is that it does not discriminate between the
horizontal and vertical creeps in estimating the exit hydraulic gradient the above figure
shows how a foundation with vertical seepage faces is dealt with according to the Bligh
method.
The uplift pressure according to the Bligh at point X is determined from the pressure
diagram as follows.
hx H
Leq Lx Leq
Lx 2a t1 L1 2b d
H Leq Lx
hx
Leq
H
Exit gradient ie = < is
Leq
N
Leq V
3
N = Sum of all the horizontal contacts and all the sloping contacts less than 45o
V = Sum of all the vertical contacts and all sloping contacts greater than 45o
To safeguard against piping, the exit gradient must be less than the safe gradient given in
Table 9.6. To demonstrate the method, the pressure at point X, the Fig above is
calculated.
To horizontal distances N = L1 + L2
Total vertical distances V = t1 + 2a + 2b + 2c + t2
1
Leq = (L1 + L2) + (t1 + 2a + 2b + 2c + t2)
3
Horizontal distances from left to (X) = L1 + d
Vertical distances from left to (X) = t1 + 2a + 2b
1
Lx = (L1 + d) + (t1 + 2a + 2b)
3
H ( Leq Lx )
hx
Leq
3. Flow nets
This method is similar to the previous two and assumes that the soil layer under the
foundation is homogenous. The method is the graphical solution of the Laplace equation
for the steady state flow. To illustrate the method, assume a weir retains water to the
height (H) above the ground surface at it is shown in Fig. a. Water will percolate from the
upstream side of the weir to its downstream through the soil along imaginary paths
known as flow lines. Due to the soil resistance, the waterhead decreases as the water
travels downstream. Lines connecting points of equal waterheads on the flow lines are
known as the equiponential lines. The flow and equipotential lines intersect at right
angles, as is demonstrated in Fig. a. By definition, if two piezometers are placed at two
different levels on the same equipotential lines, as shown in Fig. a, the water level in both
of them will be the same.
The flow nets are constructed by dividing the soil profile under the foundation into
arbitrary numbers of equipotential and flow lines. In drawing the lines, the following
criteria must be considered.
(i) the flow and equipotential lines intersect at right angles;
(ii) the flow and equipotential lines are parallel among themselves;
(iii) the side of the squares which will be formed by intersecting the equipotential
and flow lines are equal.
These conditions usually dictate the number of the flow equipotential lines. The larger the
number of the lines, the smaller the size of the square and hence there is a better chance
to fulfill the required criteria. The solution is achieved by trial and error. To draw a flow
net for a weir which has three or four sheet piles, the trial may take several hours until the
required criteria are fulfilled.
There are several boundary conditions which assist in drawing the flow net. The up and
downstream ground surface are equipotential lines. Flow lines are parallel along
impermeable surface and equipotential lines meet these surfaces at right angles.
By understanding the characteristics of the flow nets, one can reach the following
equations:
b1
Q1 KH 1
l1
b2
Q2 KH 2
l2
H
H
Nd
and
H
Q K
Nd
In the number of flow channels is Nf, the total flow or seepage per unit width of the weir
is:
Q N f Q
Nf
Q KH (9.8)
Nd
H H
i
l lN d
and the average seepage per unit volume across any field parallel to the direction of flow
is:
H
Ps i w w
Ndl
If the side slope of the last square at the exit is le, the exit hydraulic gradient is:
H
ie is
le N d
Theoretically when ie less than is is, the structure is safe against piping. As a safety factor
against unexpected increase in the head, the calculated exit gradient should not exceed
the safe hydraulic gradient given in Table 9.8
From the above description of the method one may note that flow lines are constructed by
trial and error until a satisfactory picture is obtained.
Determining the uplift pressure in a foundation with an irregular base and several lines of
cutoff walls by this graphical method can be very time consuming and the flow net
becomes complicated.
While the method is accurate, since it represents the solution of the flow equation, the use
of the method in designing small weirs is not common, because of the involvement of
lengthy trial and error methods in finding the acceptable shape of the flow net.
A question which arises often is: what is the appropriate size of the flow net squares? The
answer is, the smaller the size of the squares the more accurate the result is. The size of
the squares also depends on the shape of the foundation. A foundation which has many
corners, as is the case when several piles are attached to it requires very small squares in
order to fulfill the flow net criteria described above.
Fig. 6.3 is the flow net for the problem in Example 9.1, which was solved by the Bligh
and Lane methods.
The pressure at point X = H-n(H/Nd) = 6-13(6/23) = 2.61 m
n = number of squares from upstream to the point considered
N = Total number of the squares between two flow lines:
When it is necessary to estimate the amount of water which percolates through the
subsoil from one side of the structure to another, for example, when a structure is built to
create a reservoir, the seepage rate is calculated by applying Eq. (9.8).
The approximate value of K is given in Table 9.8. For the given example, assume that the
soil is coarse sand, which has particle size D20 = 0.6 mm, where D20 is the size which
corresponds to 20% of the soil sample finer in the sieve analysis. For the soil
It can be shown by using the flow net that an efficient way to reduce the exit gradient is
to provide a cutoff wall at the end of the apron.
It was explained earlier that construction of a solid apron is required to accommodate the
hydraulic jump. The relation between the exit gradient and length of the apron was also
established. Constructing ordinary horizontal flat aprons to match the required hydraulic
jump and existing gradient criteria usually results in a massive costly structure. The
length of apron can be reduced by introducing cutoff walls, but there is a limit however
for this reduction, since the hydraulic jump must not be allowed to occur outside the
apron. To control location of the jump and reduce the construction cost, energy
dissipaters should be introduced. Design of the energy dissipaters depends on values of
Froude number in pre- and post- jump and the water depths.
Fig. 6.10 presents the design criteria for various types of energy dissipating structures and
stilling basins.
4. The basin selected in step three is adequate to disperse the flow energy and
accommodate the jump, but it does not necessarily give an adequate creep length
to guarantee a safe exit hydraulic gradient. Therefore, the exit gradient should be
calculated for the given basin length. If it is greater than the safe gradient for
particular soil, the basin length must be increased at its end, or intermediate cutoff
walls introduced. However, the distance between the basin blocks and the sill
must not be changed.
The structure must be well protected from the river overflow and water creep along the
walls must be prevented. Construction of wing walls at both ends of the structure is
essential to anchor it into the embankment. The upstream wings are usually constructed at
an angle of 30 – 40o with the river bank, and it should be extended beyond the top line of
the embankment by at least 1.00 m. Type of required protection and height of
embankment, depend on the frequency of the river overflow and the investment cost of
both the structure and the protection work. Fig. 6.11 presents a typical layout of a
structure.
To protect the channel bed from being eroded by the current leaving the solid apron,
usually riprap, is placed. The length, size of stones used, and thickness of the layer must
be carefully chosen according to certain criteria.
Ds = R – D (9.12)
An apron length of 1.5Ds is adequate to protect the structures ends from scouring. By
substituting Eq. (9.11) into Eq. (9.12) and applying the factor 1.5 to the scouring depth,
the resulting apron length would be:
Where Lu and Ld = length of the protection work up and downstream of the solid
apron respectively.
Du and Dd = the water depth corresponding to the design discharge just of
the solid apron at up and downstream of the weir respectively.
Obviously since Eq. (13) is based on the scouring depth, they must always be fulfilled.
Therefore, the designer should use the greatest value results from the two Eq. (9.13) and
(9.14).
Vb 2 gz
1. Determine the minimum size of the riprap stones as was described above and
select a range of stone sizes between the calculated minimum diameter and the
maximum size. The maximum size is the size of stones that can be carried by an
average man without difficulty, if it is placed manually.
2. Soil samples at about 0.50 m below the river bed are to be taken for the sieve
analysis and the result is drawn from the usual sieve analysis curve, Fig. 6.13.
3. Apply the following criteria, to determine the limits of the grain sizes in each
layer.
a. To secure adequate soil permeability
d15upperlayer
L1 L2 (9.16)
d15lowerlayer
where d15 is the particle size which corresponds to 15% passing on the
sieve curve, and where L1 and L2 are the upper and lower limits of the ratio. The limit
values are as follows.
Type of soil L1 L2
Homogeneous grains (gravel) 5 10
Homogeneous angular grains 6 20
(broken gravel rubble)
Well graded grains 12 40
(b) To prevent the filter from clogging by soil particles in each layer should
satisfy
d5 > 0.75 mm
d5 is the particle size which corresponds to 5% passing on the sieve curve.
(c) To prevent fine bed materials from being washed away
d15upperlayer
5
d 85lowerlayer
and
d 50upperlayer
L1 L2 (9.19)
d 50lowerlayer
d85 and d50 are particle sizes corresponding to 85% and 50% passing on the sieve curve
respectively.
The lower and upper limits of Eq. (9.19) are as follows:
Type of soil L1 L2
Homogeneous grains (gravel) 5 10
Homogeneous angular grains 10 30
The boundaries of the filter layers are calculated by applying the above criteria to the
riprap stones and the subgrade (river bed) material and poting the results on the same
sheet of the sieve analysis curves of the soil sample.
Diversion weirs are constructed from a variety of materials. The most commonly used
materials are reinforced concrete, masonry, and gabions. However, whatever materials
are used, the structural analysis remains almost the same.
Acting Forces on Weirs
All external forces acting on a weir are the result of flowing water in the canal or river on
which the structure is constructed. A typical force system of a weir consists of the
following components:
(ii) Approximately draw the water surface and calculate the water weight. Fig. 8.1
shows a typical weir with the rapidly variable flow at their d/s side.
M a 0
H f 0
V f 0
M balance
1.5
M topple
in order to avoid lifting up the structure‟s heel and tension occurrence at the base, the
forces must pass through the middle third of the structures base, i.e.
B
eccentricity e < or
6
B B
e X
2 6
where
X
M
V f
The structure may slide in the flow direction if there is not enough grip between the base
and the foundation. To prevent this happening, the following condition should be
satisfied.
where f is the friction factor between the base and the foundation.
It should be noted that, when the net vertical force is calculated, the foundation reaction
should not be included (Fig. 8.1). The foundation reaction occurs as a result of the
unbalanced moment and the vertical forces, i.e. weight of the structure and the water
uplift pressure. If the soil reaction is included, sum of the vertical forces will be zero.
The friction coefficient (f) depends on the materials used in the construction and nature of
the foundation. The USBR suggest 0.35 for concrete structures on common soils and 0.65
is recommended for the friction between masonry and concrete
w (hx t ) t f
hx w h
t x w
( f w ) fb
hx
t
( f 1)
hx = uplift pressure at point x, (m)
t = thickness of the floor (m)
f density of the floor materials, kg/m3
w densityofw ater (kg / m3)
fb submergeddensityofth efloormatearils f w
Module for holistic exam, hydraulic structures 129