TULANGAN KOLOM ARAH - X (M33)

Lebar kolom (b) = 400 mm


Tebal kolom (h) = 400 mm
Tebal selimut beton = 40 mm
Kuat tekan beton (fc') = 30 Mpa >>>
Fy = 400 Mpa
Φ tulangan lentur = 19 mm
Φ tulangan sengkang = 12 mm

d' = 61.5 mm
d (h-d') = 338.5 mm

Dari SAP
Pu = 159676.13 kg
= 1566422.84 N
Mu = 11872.93 kgm
= 116473443.30 Nmm
e (Mu/Pu) = 74.36 mm
e min (0,1 h) = 40 mm

Dicoba menggunakan 4D20


As = 1701.1724219189 mm2
rho (As/bd) = 0.0125640504 >>>

cb (600/(600+fy))*d = 203.10 mm
ab (B1 . Cb) = 172.64 mm
fs'((cb-d') . 600/cb) = 418.32 Mpa >>>

Pnb
0,85 . Fc' . B . Ab + (As' . Fs') - (As . Fy) = 1760877.00 N

Mnb
0,85 . Fc' . B . Ab . (h/2-ab/2) + (As' . Fs') . = 200180899.55 Nmm
(h/2 - d') - (As . Fy) . (d - h/2)

eb (Mnb/Pnb) = 113.6825 mm

Karena eb > e maka keruntuhan "DESAK" , perhitungan menggunakan


Pn
As . Fy / (e/d-d') + b . H . Fc' / (3 . H . e/d2) = 3336105.34 N
+ 1,18

Pr = 2168468.47 N >>>

Syarat
0,1 b . H . Fc' = 480000 N >>>
OLOM ARAH - X (M33)

B1 = 0.85

0,01 ≤ rho ≤ 0,08 >> OK (SNI 2002)

fs' > fy maka fs' = fy = 400 Mpa

DESAK" , perhitungan menggunakan rumus WHITNEY

Pr > Pu
OK

Pr > 0,1 b . H . Fc'


OK
TULANGAN KOLOM ARAH - Y (M22)

Lebar kolom (b) = 400 mm


Tebal kolom (h) = 400 mm
Tebal selimut beton = 40 mm
Kuat tekan beton (fc') = 30 Mpa >>>
Fy = 400 Mpa
Φ tulangan lentur = 19 mm
Φ tulangan sengkang = 12 mm

d' = 61.5 mm
d (h-d') = 338.5 mm

Dari SAP
Pu = 159676.13 kg
= 1566422.84 N
Mu = 11796.55 kgm
= 115724155.50 Nmm
e (Mu/Pu) = 73.88 mm
e min (0,1 h) = 40 mm

Dicoba menggunakan 4D20


As = 1701.1724219189 mm2
rho (As/bd) = 0.0125640504 >>>

cb (600/(600+fy))*d = 203.10 mm
ab (B1 . Cb) = 172.64 mm
fs'((cb-d') . 600/cb) = 418.32 Mpa >>>

Pnb
0,85 . Fc' . B . Ab + (As' . Fs') - (As . Fy) = 1760877.00 N

Mnb
0,85 . Fc' . B . Ab . (h/2-ab/2) + (As' . Fs') . = 200180899.55 Nmm
(h/2 - d') - (As . Fy) . (d - h/2)

eb (Mnb/Pnb) = 113.6825 mm

Karena eb > e maka keruntuhan "DESAK" , perhitungan menggunakan rum


Pn
As . Fy / (e/d-d') + b . H . Fc' / (3 . H . e/d2) = 3344383.48 N
+ 1,18

Pr = 2173849.26 N >>>
Syarat
0,1 b . H . Fc' = 480000 N >>>
OLOM ARAH - Y (M22)

B1 = 0.85

0,01 ≤ rho ≤ 0,08 >> OK (SNI 2002)

fs' > fy maka fs' = fy = 400 Mpa

DESAK" , perhitungan menggunakan rumus WHITNEY

Pr > Pu
OK
Pr > 0,1 b . H . Fc'
OK