You are on page 1of 304

Specification Item Buildup for Dhaka Zone, Mymensingh Zone & Cumilla Zone

Division 1 - General & Site Facilities

Overhead for GSF: 3.00% VAT= 7%


Overhead for Earthwork: 3.00% IT= 7%
Overhead for Pavement work: 3.00% Total VAT-IT= 14%
Overhead for Foundation work: 3.00% Profit= 5% ###
Overhead for Structure work: 3.00%
Overhead for Incidentals: 3.00%
Item Code 01/01/01
Item Name : Maintenance and Protection of Traffic
Unit of Measurement : Lump Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category : Primary Item
Item Type : Equipment
1-3KVA Mobile Generator no. 19,800.00 2.00 39,600.00 39,600.00
Flashing Light Units (mains power) no. 1,000.00 6.00 6,000.00 6,000.00
Flood Light (Pole mounted) no. 2,000.00 2.00 4,000.00 4,000.00
Traffic Signs with pole & support for Traffic Management no. 8,000.00 6.00 48,000.00 48,000.00
Item Type : Labour
Foreman day 850.00 1.00 850.00 850.00
Semi-skilled labourer day 500.00 4.00 2,000.00 2,000.00
Unskilled labourer day 450.00 5.00 2,250.00 2,250.00
Item Type : Material
Plastic Tape Pkt 262.00 5.00 1,310.00 1,310.00
Steel Box for Traffic Management no. 100.00 110.00 11,000.00 11,000.00
Basic Unit Price of Specification Item : 115,010.00
Plus Profit at 5% 5,750.50
Plus Overhead at 3.00% 3,450.30
Sub-Total : 124,210.80
Plus Tax & VAT at 16.2791% 20,220.36
Total Unit Price of Specification Item : 144,431.16

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Say 144,431.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/01/02
Item Name Provision for Maintain Temp.Structures & Equipment for the Maintenance and Protection of Traffic
Unit of Measurement day
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category : Primary Item
Item Type : Equipment
Small hand tools (2) day 50.00 3.00 150.00 150.00
Item Type : Labour 0.00 0.00
Unskilled labourer day 450.00 3.00 1,350.00 1,350.00
Item Type : Material 0.00 0.00
Petrol ltr 86.00 3.09 265.83 265.83
Basic Unit Price of Specification Item : 1,765.83
Plus Profit at 5% 88.29
Plus Overhead at 3.00% 52.97
Sub-Total : 1,907.09
Plus Tax & VAT at 16.2791% 310.46
Total Unit Price of Specification Item : 2,217.55
Say 2,218.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/02/01
Item Name Supply, Erect and Remove Field Office for Engineer
Unit of Measurement Lump Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category Primary Item
Item Type Equipment
Engineer's Field Office lump sum 203,000.00 1.00 203,000.00 203,000.00
Basic Unit Price of Specification Item : 203,000.00
Plus Profit at 5% 10,150.00
Plus Overhead at 3.00% 6,090.00
Sub-Total : 219,240.00
Plus Tax & VAT at 16.2791% 35,690.23
Total Unit Price of Specification Item : 254,930.23
254,930.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/02/02
Item Name Maintenance, Staffing, Security and Cleaning of the
Field Office for the Engineer
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour
Maintenance of Engineers office month 40,000.00 1.00 40,000.00 40,000.00
Basic Unit Price of Specification Item : 40,000.00
Plus Profit at 5% 2,000.00
Plus Overhead at 3.00% 1,200.00
Sub-Total : 43,200.00
Plus Tax & VAT at 16.2791% 7,032.56
Total Unit Price of Specification Item : 50,232.56
50,233.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/02/03
Item Name Provision of Office Equipment and Consumables
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Provision of Office consumables month 6,265.00 1.00 6,265.00 6,265.00
Basic Unit Price of Specification Item : 6,265.00
Plus Profit at 5% 313.25
Plus Overhead at 3.00% 187.95
Sub-Total : 6,766.20
Plus Tax & VAT at 16.2791% 1,101.47
Total Unit Price of Specification Item : 7,867.67
7,868.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/02/04
Item Name
Provision, Maintenance and Removal of Sign Boards

Unit of Measurement Lump Sum


Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Provision, maintain & remove Signs month 7,200.00 1.00 7,200.00 7,200.00
Basic Unit Price of Specification Item : 7,200.00
Plus Profit at 5% 360.00
Plus Overhead at 3.00% 216.00
Sub-Total : 7,776.00
Plus Tax & VAT at 16.2791% 1,265.86
Total Unit Price of Specification Item : 9,041.86
9,042.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/02/05
Item Name Provision and Maintenance of Survey Equipment
Unit of Measurement month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Provision & Maintain Survey Equipment month 730.00 1.00 730.00 730.00
Basic Unit Price of Specification Item : 730.00
Plus Profit at 5% 36.50
Plus Overhead at 3.00% 21.90
Sub-Total : 788.40
Plus Tax & VAT at 16.2791% 128.34
Total Unit Price of Specification Item : 916.74
917.00
Assumption : This is an average rate from Periodic Maintenance Contract for year 2010-11.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/02/07
Item Name Progress Photographs
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Progress Photographs month 814.00 1.00 814.00 814.00
Basic Unit Price of Specification Item : 814.00
Plus Profit at 5% 40.70
Plus Overhead at 3.00% 24.42
Sub-Total : 879.12
Plus Tax & VAT at 16.2791% 143.11
Total Unit Price of Specification Item : 1,022.23
say: 1,022.00
Assumption : This is an avarage rate taken from recent Periodic Maitenance Contracts.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/03/01
Item Name Provide and Remove Site Laboratory & Equipment
Unit of Measurement Lump Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Site Laboratory lump sum 270,000.00 1.00 270,000.00 270,000.00
Basic Unit Price of Specification Item : 270,000.00
Plus Profit at 5% 13,500.00
Plus Overhead at 3.00% 8,100.00
Sub-Total : 291,600.00
Plus Tax & VAT at 16.2791% 47,469.77
Total Unit Price of Specification Item : 339,069.77
say: 339,070.00

Assumption : This is an avarage rate taken from recent Periodic Maitenance Contracts.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/03/02
Item Name Maintain Site Laboratory
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour
Maintenance of Site Laboratory month 6,264.00 1.00 6,264.00 6,264.00
Basic Unit Price of Specification Item : 6,264.00
Plus Profit at 5% 313.20
Plus Overhead at 3.00% 187.92
Sub-Total : 6,765.12
Plus Tax & VAT at 16.2791% 1,101.30
Total Unit Price of Specification Item : 7,866.42
7,866.00

Assumption : This is an avarage rate taken from recent Periodic Maitenance Contracts.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/03/03
Item Name Special or Additional Tests
Unit of Measurement Provisional Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00

Assumption : This is an avarage rate taken from recent Periodic Maitenance Contracts.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/04/01
Item Name Provision, Operation and Maintenance of Saloon Car
(1200cc Capacity)
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Saloon Car month 50,000.00 1.00 50,000.00 50,000.00
Operation & Maintenance month 45,000.00 1.00 45,000.00 45,000.00
Basic Unit Price of Specification Item : 95,000.00
Plus Profit at 5% 4,750.00
Plus Overhead at 3.00% 2,850.00
Sub-Total : 102,600.00
Plus Tax & VAT at 16.2791% 16,702.33
Total Unit Price of Specification Item : 119,302.33
119,302.00

Assumption : For Saloon car, it is assumed a brand new car will be provided. The government allowance for buying car in case of Deputy Secreataries is the basis of the
calculation. The economic life of the car is assumed to be 60 months. For maintenance, governement allowance given to the Deputy Secretaries of the
government has been taken as the basis.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/04/02
Item Name Provision, Operation and Maintenance of Pick- up with
canopy (Double Cab)
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Pick up Double Cap rent month 75,000.00 1.00 75,000.00 75,000.00
Operation & Maintenance month 60,000.00 1.00 60,000.00 60,000.00
Basic Unit Price of Specification Item : 135,000.00
Plus Profit at 5% 6,750.00
Plus Overhead at 3.00% 4,050.00
Sub-Total : 145,800.00
Plus Tax & VAT at 16.2791% 23,734.88
Total Unit Price of Specification Item : 169,534.88
169,535.00

Assumption : This is an avarage rate taken from recent Periodic Maitenance Contracts.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/04/03
Item Name Provision, Operation and Maintenance of Four Wheel
Drive Vehicle Min. 6 seats
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
4 WD Jeep month 160,000.00 1.00 160,000.00 160,000.00
Four Wheel Drive Vehicle Min 6 seats no. 75,000.00 1.00 75,000.00 75,000.00
Basic Unit Price of Specification Item : 235,000.00
Plus Profit at 5% 11,750.00
Plus Overhead at 3.00% 7,050.00
Sub-Total : 253,800.00
Plus Tax & VAT at 16.2791% 41,316.28
Total Unit Price of Specification Item : 295,116.28
295,116.00
Assumption : This is an avarage rate taken from recent Periodic Maitenance Contracts.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/04/04
Item Name Motor Cycle 125cc
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Motor cycle month 2,000.00 1.00 2,000.00 2,000.00
Operation & Maintenance month 2,500.00 1.00 2,500.00 2,500.00
Basic Unit Price of Specification Item : 4,500.00
Plus Profit at 5% 225.00
Plus Overhead at 3.00% 135.00
Sub-Total : 4,860.00
Plus Tax & VAT at 16.2791% 791.16
Total Unit Price of Specification Item : 5,651.16
5,651.00

Assumption : The economic life of a motor cycle has been taken as 60 months

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/04/05
Item Name Motor Boat min 5m length
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Motor Boat Min 5m length no. 13,425.00 1.00 13,425.00 13,425.00
Basic Unit Price of Specification Item : 13,425.00
Plus Profit at 5% 671.25
Plus Overhead at 3.00% 402.75
Sub-Total : 14,499.00
Plus Tax & VAT at 16.2791% 2,360.30
Total Unit Price of Specification Item : 16,859.30
16,859.00

Assumption :

Item Code 01/04/06


Item Name Provision, Operation and Maintenance of Micrbus Min.
10 seats
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Microbus 10 seater month 75,000.00 1.00 75,000.00 75,000.00
Operation & Maintenance month 57,500.00 1.00 57,500.00 57,500.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Basic Unit Price of Specification Item : 132,500.00
Plus Profit at 5% 6,625.00
Plus Overhead at 3.00% 3,975.00
Sub-Total : 143,100.00
Plus Tax & VAT at 16.2791% 23,295.35
Total Unit Price of Specification Item : 166,395.35
166,395.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 01/04/07
Item Name Provision, Operation and Maintenance of Micrbus Min.
7 seats
Unit of Measurement Month
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Microbus 7 seater month 65,000.00 1.00 65,000.00 65,000.00
Operation & Maintenance month 55,000.00 1.00 55,000.00 55,000.00
Basic Unit Price of Specification Item : 120,000.00
Plus Profit at 5% 6,000.00
Plus Overhead at 3.00% 3,600.00
Sub-Total : 129,600.00
Plus Tax & VAT at 16.2791% 21,097.67
Total Unit Price of Specification Item : 150,697.67
150,698.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Division 2 - Earthworks

Item Code 02/01/01


Item Name Clearing and Grubbing
Unit of Measurement sq. metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 9.00 450.00 4.50
Item Type Labour 0.00
Semi-skilled labourer day 500.00 1.50 750.00 7.50
Unskilled labourer day 450.00 7.00 3,150.00 31.50
Basic Unit Price of Specification Item : 43.50
Plus Profit at 5% 2.18
Plus Overhead at 3.00% 1.31
Sub-Total : 46.98
Plus Tax & VAT at 16.2791% 7.65
Total Unit Price of Specification Item : 54.63
55.00

Assumption : Assumes that only a small number of trees have to be moved and that material is moved < 50m to the onsite stockpile.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/02/01
Item Name Roadway Excavation in Unsuitable Soil
Unit of Measurement cu metre
Quantity for Estimation 300.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools day 50.00 1.50 75.00 0.25
Excavator day 12,000.00 1.00 12,000.00 40.00
Dump Truck day 10,000.00 3.00 30,000.00 100.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 5.00 2,500.00 8.33
Unskilled labourer day 450.00 10.00 4,500.00 15.00
Basic Unit Price of Specification Item : 163.58
Plus Profit at 5% 8.18
Plus Overhead at 3.00% 4.91
Sub-Total : 176.67
Plus Tax & VAT at 16.2791% 28.76
Total Unit Price of Specification Item : 205.43
205.00

Assumption : Assumes excavation by an Excavation and material is carried a distance of 2km from point of excavation to point of diposition and the forming of a stockpile.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/02/02
Item Name Roadway Excavation in Suitable Soil
Unit of Measurement cu metre
Quantity for Estimation 450.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 34.00 1,700.00 3.78
Excavator day 12,000.00 1.00 12,000.00 26.67
Vibratory roller ( 7-10tonne) day 10,000.00 1.00 10,000.00 22.22
Water tanker day 7,000.00 1.00 7,000.00 15.56
Item Type Labour
Semi-skilled labourer day 500.00 4.00 2,000.00 4.44
Unskilled labourer day 450.00 30.00 13,500.00 30.00
Item Type Material
Water cu. metre 12.00 450.00 5,400.00 12.00
Basic Unit Price of Specification Item : 114.67
Plus Profit at 5% 5.73
Plus Overhead at 3.00% 3.44
Sub-Total : 123.84
Plus Tax & VAT at 16.2791% 20.16
Total Unit Price of Specification Item : 144.00
144.00

Assumption : Payment for suitable Material is only made for excess material which has not been able to be used in the new works. It is assumed that the material is left by
the contractor, in a shaped stockpile on site, for RHD's later use. It is assumed that the same resources would have been used as for 2/2/1.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/02/03
Item Name Roadway Excavation in Existing Pavement ( not
reinforced concrete)
Unit of Measurement cu metre
Quantity for Estimation 30.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 4.00 200.00 6.67
Excavator day 12,000.00 0.33 3,960.00 13.20
Dump Truck day 10,000.00 0.10 1,000.00 3.33
Item Type Labour 0.00
Semi-skilled labourer day 500.00 1.00 500.00 16.67
Unskilled labourer day 450.00 3.00 1,350.00 45.00
Basic Unit Price of Specification Item : 84.87
Plus Profit at 5% 4.24
Plus Overhead at 3.00% 2.55
Sub-Total : 91.66
Plus Tax & VAT at 16.2791% 14.92
Total Unit Price of Specification Item : 106.58
107.00

Assumption : It assumed excavation will be done by equipment only, labour is for loading the dump truck

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/02/04
Item Name Roadway Excavation in Existing Reinforced Concrete
Pavement
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 4.00 200.00 20.00
Excavator day 12,000.00 0.33 3,960.00 396.00
Dump Truck day 10,000.00 0.30 3,000.00 300.00
Item Type Labour
Semi-skilled labourer day 500.00 1.00 500.00 50.00
Unskilled labourer day 450.00 8.00 3,600.00 360.00
Basic Unit Price of Specification Item : 1,126.00
Plus Profit at 5% 56.30
Plus Overhead at 3.00% 33.78
Sub-Total : 1,216.08
Plus Tax & VAT at 16.2791% 197.97
Total Unit Price of Specification Item : 1,414.05
1,414.00

Assumption : Assumes 2 No u.s & 0.5 No ss digging and breaking with 1 No us removing material to tip onsite. The rate does not include for any reworking of the material
to render it fully suitable for reuse in the works.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/02/05
Item Name Deduction of Value of Suitable Soil Recovered from
Existing Road
Unit of Measurement cu metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Soil cu. metre 210.00 1.00 210.00 210.00

Basic Unit Price of Specification Item : 210.00


210.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/2/06
Item Name Deduction of Value of Pavement Materials Recovered from existing Road Pavement
Unit of Measurement cu metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Sand FM>1.0 cu. metre 640.00 0.50 320.00 320.00
Stone Brick Khoa < 40mm cu. metre 3,900.00 0.50 1,950.00 1,950.00
Basic Unit Price of Specification Item : 2,270.00
2,270.00
Assumption : It is assuimed that the recovered material can be reused as sub-base material.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/04/01
Item Name Channel Excavation in Unsuitable Materials
Unit of Measurement cu metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 37.00 1,850.00 18.50
Item Type Labour 0.00
Semi-skilled labourer day 500.00 7.00 3,500.00 35.00
Unskilled labourer day 450.00 25.50 11,475.00 114.75
Basic Unit Price of Specification Item : 168.25
Plus Profit at 5% 8.41
Plus Overhead at 3.00% 5.05
Sub-Total : 181.71
Plus Tax & VAT at 16.2791% 29.58
Total Unit Price of Specification Item : 211.29
211.00
Assumption : It is assuimed that the same output per man of 2.5 cum perday is achieved in digging unsuitable material for channel as for roadway Item 2/2/1.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/04/02
Item Name Channel Excavation in Suitable Material
Unit of Measurement cu metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 37.00 1,850.00 18.50
Item Type Labour 0.00
Semi-skilled labourer day 500.00 7.00 3,500.00 35.00
Unskilled labourer day 450.00 25.50 11,475.00 114.75
Basic Unit Price of Specification Item : 168.25
Plus Profit at 5% 8.41
Plus Overhead at 3.00% 5.05
Sub-Total : 181.71
Plus Tax & VAT at 16.2791% 29.58
Total Unit Price of Specification Item : 211.29
211.00
Assumption : It is assumed that the same resources as Item 2/4/1(a) apply to this item of work. Payment is only made for excess material which is to be stockpiled at site as
directed by the Engineer.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/05/01
Item Name Excavation and Backfill for Structures
Unit of Measurement cu metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Plate Compactor day 1,200.00 3.00 3,600.00 36.00
Small hand tools (1) day 50.00 60.00 3,000.00 30.00
Water tanker day 7,000.00 0.25 1,750.00 17.50
Item Type Labour 0.00
Semi-skilled labourer day 500.00 5.00 2,500.00 25.00
Unskilled labourer day 450.00 55.00 24,750.00 247.50
Basic Unit Price of Specification Item : 356.00
Plus Profit at 5% 17.80
Plus Overhead at 3.00% 10.68
Sub-Total : 384.48
Plus Tax & VAT at 16.2791% 62.59
Total Unit Price of Specification Item : 447.07
447.00

Assumption : The rate will be dependant on the scope of work for the particular structure. This rate has assumed a plan area of escavation of 40 sqm with a depth of 3m
and construction of a pile cap 3mx3mx1.5m. The rate also assumes that the excavated material is suitable for backfilling upto top of pile cap, if not then sand
backfill must be imported. No account has been taken for provision of shoring works, which depending on the site and soil condition may be required for safe
working. It is also assumed that backfill will take some five days to complete as each layer (150-200mm thickness) has to properly compacted and tested.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/05/02
Item Name Concrete Backfill for Structures
Unit of Measurement cu metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.06 120.00 120.00
Small hand tools (1) day 50.00 2.33 116.50 116.50
Item Type Labour 0.00
Masons day 700.00 0.33 231.00 231.00
Unskilled labourer day 450.00 2.00 900.00 900.00
Item Type Material 0.00
Cement tonne 9,000.00 0.21 1,912.50 1,912.50
Crushed boulder/gravel aggregate <38mm cu. metre 6,750.00 0.90 6,075.00 6,075.00
Sand FM>1.8 cu. metre 1,250.00 0.50 625.00 625.00
Basic Unit Price of Specification Item : 9,980.00
Plus Profit at 5% 499.00
Plus Overhead at 3.00% 299.40
Sub-Total : 10,778.40
Plus Tax & VAT at 16.2791% 1,754.62
Total Unit Price of Specification Item : 12,533.02
12,533.00

Assumption : The concrete mixure is located <50m from point of deposition and rate is based on assumed average production and placement of concrete of 2.83 cum/6-7
men gang/day. No allowance has been made in the rate for any shuttering works.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/05/03
Item Name Sand Backfill for Structures
Unit of Measurement cu metre
Quantity for Estimation 20.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Plate Compactor day 1,200.00 0.75 894.00 44.70
Small hand tools (1) day 50.00 17.00 850.00 42.50
Water tanker day 7,000.00 0.10 700.00 35.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 3.00 1,500.00 75.00
Unskilled labourer day 450.00 12.00 5,400.00 270.00
Item Type Material 0.00
Sand FM >0.80 cu. metre 500.00 23.00 11,500.00 575.00
Basic Unit Price of Specification Item : 1,042.20
Plus Profit at 5% 52.11
Plus Overhead at 3.00% 31.27
Sub-Total : 1,125.58
Plus Tax & VAT at 16.2791% 183.23
Total Unit Price of Specification Item : 1,308.81
1,309.00

Assumption : Assumes sand material (FM>0.80) is delivered direct to site. Assumes bulking factor of 15% means that 20 cum compacted = 23 cum loose. It is also
assumed that 20 cum equites to 3-4 layers (150-200mm thickness) therefore labour filling can not work continuously, say, 25% down time for compacting and
75% time for filling.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/06/01(a)
Item Name Embankment Fill from Excavation on site.
Unit of Measurement cu metre
Quantity for Estimation 450.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 34.00 1,700.00 3.78
Excavator day 12,000.00 1.00 12,000.00 26.67
Vibratory roller ( 7-10tonne) day 10,000.00 1.00 10,000.00 22.22
Water tanker day 7,000.00 1.00 7,000.00 15.56
Item Type Labour 0.00
Semi-skilled labourer day 500.00 4.00 2,000.00 4.44
Unskilled labourer day 450.00 30.00 13,500.00 30.00
Item Type Material 0.00
Water cu. metre 12.00 450.00 5,400.00 12.00
Basic Unit Price of Specification Item : 114.67
Plus Profit at 5% 5.73
Plus Overhead at 3.00% 3.44
Sub-Total : 123.84
Plus Tax & VAT at 16.2791% 20.16
Total Unit Price of Specification Item : 144.00
144.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/06/01(b)
Item Name Embankment Fill from Excavation in Borrow pit within
the Right -of-way
Unit of Measurement cu metre
Quantity for Estimation 300.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 38.00 1,900.00 6.33
Excavator day 12,000.00 1.00 12,000.00 26.67
Vibratory roller ( 7-10tonne) day 10,000.00 1.00 10,000.00 33.33
Water tanker day 7,000.00 1.00 7,000.00 23.33
Item Type Labour 0.00
Semi-skilled labourer day 500.00 4.00 2,000.00 6.67
Skilled Labour day 550.00 4.00 2,200.00 7.33
Unskilled labourer day 450.00 30.00 13,500.00 45.00
Item Type Material 0.00
Water cu. metre 12.00 600.00 7,200.00 24.00
Basic Unit Price of Specification Item : 172.67
Plus Profit at 5% 8.63
Plus Overhead at 3.00% 5.18
Sub-Total : 186.48
Plus Tax & VAT at 16.2791% 30.36
Total Unit Price of Specification Item : 216.84
217.00
Assumption : Rate is for new road construction using labour intensive methods for escavation, placing, spreading and watering of fill material. It is also assumes that the
roller is working effeciently producing 4000sqm/day for a 150mm compacted layer.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/06/02
Item Name Embankment fill from borrow pit in contractor's
Arranged land
Unit of Measurement cu metre
Quantity for Estimation 600.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 28.00 1,400.00 2.33
Excavator day 12,000.00 0.50 6,000.00 13.33
Dozer day 11,000.00 1.00 11,000.00 24.44
Vibratory roller ( 7-10tonne) day 10,000.00 2.00 20,000.00 33.33
Water tanker day 7,000.00 1.00 7,000.00 11.67
Item Type Labour 0.00
Semi-skilled labourer day 500.00 4.00 2,000.00 3.33
Skilled Labour day 550.00 4.00 2,200.00 3.67
Unskilled labourer day 450.00 20.00 9,000.00 15.00
Item Type Material 0.00
Imported suitable bulk fill (off site) cu. metre 210.00 600.00 126,000.00 210.00
Water cu. metre 12.00 450.00 5,400.00 9.00
Basic Unit Price of Specification Item : 326.11
Plus Profit at 5% 16.31
Plus Overhead at 3.00% 9.78
Sub-Total : 352.20
Plus Tax & VAT at 16.2791% 57.33
Total Unit Price of Specification Item : 409.53
410.00
Assumption : It is assumed, the basic materials price of bulk fill includes carrying up to site. The excavator is assumed to be deployed in other works too.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/06/03
Item Name Sand Backfill to Swamp
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 1.50 75.00 7.50
Dozer day 11,000.00 0.02 220.00 22.00
Vibratory roller ( 7-10tonne) day 10,000.00 0.02 200.00 20.00
Water Pump day 1,200.00 0.25 300.00 30.00
Item Type Labour 0.00
Unskilled labourer day 450.00 1.50 675.00 67.50
Item Type Material 0.00
Sand FM>0.5 cu. metre 420.00 11.50 4,830.00 483.00
Basic Unit Price of Specification Item : 630.00
Plus Profit at 5% 31.50
Plus Overhead at 3.00% 18.90
Sub-Total : 680.40
Plus Tax & VAT at 16.2791% 110.76
Total Unit Price of Specification Item : 791.16
791.00
Assumption : The rate assumes a sand fill of FM>1.0 and the average depth of fill is 1m with allowances made for pumping out prior to and during filling and the removal of
sludge.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/07/01
Item Name Preparation of Subgrade 300 mm Depth
Unit of Measurement sq. metre
Quantity for Estimation 2500.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 25.00 1,250.00 0.50
Motor Grader day 10,000.00 1.00 10,000.00 4.00
Vibratory roller ( 7-10tonne) day 10,000.00 1.00 10,000.00 4.00
Water tanker day 7,000.00 1.00 7,000.00 2.80
Item Type Labour 0.00
Semi-skilled labourer day 500.00 5.00 2,500.00 1.00
Unskilled labourer day 450.00 20.00 9,000.00 3.60
Item Type Material 0.00
Water cu. metre 12.00 750.00 9,000.00 3.60
Basic Unit Price of Specification Item : 19.50
Plus Profit at 5% 0.98
Plus Overhead at 3.00% 0.59
Sub-Total : 21.06
Plus Tax & VAT at 16.2791% 3.43
Total Unit Price of Specification Item : 24.49
24.00

Assumption : The subgrade is defined as the earthwork layer immidiately beneath the road pavement layers which include the improved subgrade layer. The rate analysis
assumes the insitu material is suitable and only requires to be scarified, watered and compacted. Watering is by water tanker and rolling by Vibroll. The rate
assumes that both items of Plant (roller and water Tanker) are being fully utilised.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/07/02
Item Name Preparation of Subgrade 450 mm depth
Unit of Measurement sq. metre
Quantity for Estimation 1500.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 12.00 600.00 0.40
Motor Grader day 10,000.00 1.00 10,000.00 6.67
Vibratory roller ( 7-10tonne) day 10,000.00 1.00 10,000.00 6.67
Water tanker day 7,000.00 1.00 7,000.00 4.67
Item Type Labour 0.00
Semi-skilled labourer day 500.00 5.00 2,500.00 1.67
Unskilled labourer day 450.00 20.00 9,000.00 6.00
Item Type Material 0.00
Water cu. metre 12.00 675.00 8,100.00 5.40
Basic Unit Price of Specification Item : 31.47
Plus Profit at 5% 1.57
Plus Overhead at 3.00% 0.94
Sub-Total : 33.98
Plus Tax & VAT at 16.2791% 5.53
Total Unit Price of Specification Item : 39.52
40.00

Assumption : The rate analysis assumes that the insitu subgrade material is suitable and therefore the top 150mm layer is cut and set aside for reuse. Then the bottom
150mm layer is scarified, watered, mixed and compacted following which the set aside material, after removal of any deleterious materials, is then replaced
watered, mixed and compacted to the required levels and grades. Again as with item 2/7/1 no allowance has been made for non productive use of the roller
and water tanker, which would not be the case if working on a live road, where only sectional half width working should be carried.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/08/01
Item Name Improved Subgrade
Unit of Measurement cu metre
Quantity for Estimation 600.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 30.00 1,500.00 2.50
Dozer day 11,000.00 1.00 11,000.00 18.33
Vibratory roller ( 7-10tonne) day 10,000.00 1.00 10,000.00 16.67
Water tanker day 7,000.00 4.00 28,000.00 46.67
Item Type Labour
Semi-skilled labourer day 500.00 4.00 2,000.00 3.33
Unskilled labourer day 450.00 26.00 11,700.00 19.50
Item Type Material 0.00
Sand FM >0.80 cu. metre 640.00 670.00 428,800.00 714.67
Water cu. metre 12.00 450.00 5,400.00 9.00
Basic Unit Price of Specification Item : 830.67
Plus Profit at 5% 41.53
Plus Overhead at 3.00% 24.92
Sub-Total : 897.12
Plus Tax & VAT at 16.2791% 146.04
Total Unit Price of Specification Item : 1,043.16
1,043.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/09/01
Item Name Dismantling Existing Structure including disposal of spoil and backfilling.
Unit of Measurement Lump Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/09/02
Item Name Dismanting Portions of Existing Structure including stockpiling of materials.
Unit of Measurement Lump Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/09/03(a)
Item Name Deduction of the Value of Recovered Materials from
Structures
Unit of Measurement Lump Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/09/03(b)
Item Name Deduction of the Value of Recovered Materials(Reinforcing Steel) from Structures
Unit of Measurement Lump Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/10/01
Item Name Construction of Soil Earthen Shoulders
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 4.33 216.50 21.65
Payloader day 12,000.00 0.04 480.00 48.00
Dozer day 11,000.00 0.02 220.00 22.00
Dump Truck day 10,000.00 0.05 500.00 50.00
Vibratory roller (1-3 tonne) day 4,000.00 0.04 160.00 16.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 0.33 165.00 16.50
Unskilled labourer day 450.00 3.00 1,350.00 135.00
Item Type Material 0.00
Imported suitable bulk fill (off site) cu. metre 210.00 9.25 1,942.50 194.25
sand (FM>0.50) cu. metre 420.00 3.75 1,575.00 157.50
Water cu. metre 12.00 5.00 60.00 6.00
Basic Unit Price of Specification Item : 666.90
Plus Profit at 5% 33.34
Plus Overhead at 3.00% 20.01
Sub-Total : 720.25
Plus Tax & VAT at 16.2791% 117.25
Total Unit Price of Specification Item : 837.50
838.00
Assumption : It is assumed the basic material price of bulk soil includes costing upto carrying to the base camp/stack yard of the contractor. At base camp, the soil is mixed
with sand (FM>0.50) at 3:1 ratio as the Specification requires material to have CBR 8% at 98% compacted (Standard compaction 2.5kg hammer) . Material is
mixed offsite and transported to site. The roller is assumed to be working at 100% effeciency.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/11/01
Item Name Construction of Hard Shoulders
Unit of Measurement cu metre
Quantity for Estimation 45.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 - #VALUE! #VALUE!
Vibratory roller (1-3 tonne) day 4,000.00 0.50 2,000.00 44.44
Water tanker day 7,000.00 0.20 1,400.00 31.11
Item Type Labour 0.00
Masons day 700.00 3.00 2,100.00 46.67
Semi-skilled labourer day 500.00 5.00 2,500.00 55.56
Unskilled labourer day 450.00 40.00 18,000.00 400.00
Item Type Material 0.00
Crushed boulder/gravel aggregate <40mm cu. metre 3,900.00 10.00 39,000.00 866.67
Sand FM>1.0 cu. metre 640.00 20.00 12,800.00 284.44
Brick Khoa < 40mm cu. metre 3,900.00 30.00 117,000.00 2,600.00
Water cu. metre 12.00 45.00 540.00 12.00
Basic Unit Price of Specification Item : #VALUE!
Plus Profit at 5% #VALUE!
Plus Overhead at 3.00% #VALUE!
Sub-Total : #VALUE!
Plus Tax & VAT at 16.2791% #VALUE!
Total Unit Price of Specification Item : #VALUE!
#VALUE!
Assumption : The rate is for a hard shoulder to be constructed adjacent to an existing road, if it is a new road or reconstruction then shoulder is constructed
concommittantly with the main carriageway using a larger roller.The hard shoulder is constructed with type II Aggregate roadbase. This material must be a
mixture of Stone aggregate:Khoa:sylhet sand (1:3:2) if the specified minimum ACV is to be obtained. Straight Khoa:Sand blends do not comply with the new
Specification. Assume all materials are brought into contractor's yard and are then blended and mixed with water and then taken to site by lorry and spread
and compacted. Haul distance <2km.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 02/12/01
Item Name Subgrade Drains
Unit of Measurement Lin. Metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 1.00 50.00 5.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 0.20 100.00 10.00
Unskilled labourer day 450.00 0.66 297.00 29.70
Item Type Material 0.00
Coarse Sand FM>2.5 cu. metre 1,850.00 0.70 1,295.00 129.50
Geotextile sq. metre 120.00 11.00 1,320.00 132.00
Basic Unit Price of Specification Item : 306.20
Plus Profit at 5% 15.31
Plus Overhead at 3.00% 9.19
Sub-Total : 330.70
Plus Tax & VAT at 16.2791% 53.83
Total Unit Price of Specification Item : 384.53
385.00

Assumption : Assume 10m length of drain which is 0.3m wide x 0.2m deep. The drain material is coarse Sylhet sand and the separator membrane is a geotextile.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Division 3 - Pavement Works

Item Code 03/01/01


Item Name Scarify, Mix and Recompact Existing Pavement and/or Shoulder
Unit of Measurement sq. metre
Quantity for Estimation 1500.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 7.00 350.00 0.23
Motor grader day 10,000.00 1.00 10,000.00 6.67
Vibratory roller ( 7-10tonne) day 10,000.00 1.00 10,000.00 6.67
Water tanker day 7,000.00 1.00 7,000.00 4.67
Item Type Labour 0.00 0.00
Masons day 700.00 4.00 2,800.00 1.87
Unskilled labourer day 450.00 26.00 11,700.00 7.80
Item Type Material 0.00 0.00
Water cu. metre 12.00 300.00 3,600.00 2.40
Basic Unit Price of Specification Item : 30.30
Plus Profit at 5% 1.52
Plus Overhead at 3.00% 0.91
Sub-Total : 32.72
Plus Tax & VAT at 16.2791% 5.33
Total Unit Price of Specification Item : 38.05
38.00

Assumption :
Assumes a standard RHD carpetted road (38mm +12mm sealcoat) with brick khoa roadbase 150mm. The pavement is scarified to a depth of 200mm.
Assumes asphalt layer is removed for separate reworking and the roadbase is broken up and recompacted. and remixed with water.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/01/02
Item Name Repair of Potholes on the Existing Pavement
Unit of Measurement cu metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bitumen Heater (Tar Boiler) day 1,000.00 0.50 500.00 500.00
Richshaw Van day 600.00 0.50 300.00 300.00
Small hand tools (2) day 50.00 6.50 325.00 325.00
Item Type Labour
Asphalt Mistry day 700.00 0.50 350.00 350.00
Semi-skilled labourer day 500.00 1.00 500.00 500.00
Unskilled labourer day 450.00 4.00 1,800.00 1,800.00
Item Type Material 0.00 0.00
Bitumen 80/100 (Drum) tonne 54,000.00 0.10 5,400.00 5,400.00
Coarse Sand FM>2.5 cu. metre 1,850.00 0.35 647.50 647.50
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 0.40 2,800.00 2,800.00
Crushed boulder/gravel aggregate <12mm cu. metre 6,300.00 0.40 2,520.00 2,520.00
Crusher (stone) dust cu. metre 4,000.00 0.35 1,400.00 1,400.00
Firewood tonne 6,000.00 0.09 540.00 540.00
Basic Unit Price of Specification Item : 17,082.50
Plus Profit at 5% 854.13
Plus Overhead at 3.00% 512.48
Sub-Total : 18,449.10
Plus Tax & VAT at 16.2791% 3,003.34
Total Unit Price of Specification Item : 21,452.44
21,452.00

Assumption : Assumes that contractor is working on a section of road doing overlay or surface dressing works so he will carry out repairs concurrently with his other
operations. Repairs carried out using 'Hot Mix'

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/02/01 (a)
Item Name Sub-Base
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Dump Truck day 10,000.00 0.15 1,500.00 150.00
Pay Loader day 12,000.00 0.04 480.00 48.00
Motor Grader day 10,000.00 0.10 1,000.00 100.00
Small hand tools (1) day 50.00 5.00 250.00 25.00
Vibratory roller ( 7-10tonne) day 10,000.00 0.10 1,000.00 100.00
Water Tanker day 7,000.00 0.04 280.00 28.00
Item Type Labour
Masons day 700.00 1.00 700.00 70.00
Unskilled labourer day 450.00 4.00 1,800.00 180.00
Item Type Material
Sand FM>1.0 cu. metre 640.00 4.55 2,912.00 291.20
Brick Khoa < 40mm cu. metre 3,900.00 8.45 32,955.00 3,295.50
Water cu. metre 12.00 10.00 120.00 12.00
Basic Unit Price of Specification Item : 4,299.70
Plus Profit at 5% 214.99
Plus Overhead at 3.00% 128.99
Sub-Total : 4,643.68
Plus Tax & VAT at 16.2791% 755.95
Total Unit Price of Specification Item : 5,399.62
5,400.00

Assumption :
To obtain the specified grading a blend of typically 65:35 (Khoa:Sand) is required. The Khoa must be properly crushed to give a well graded material (ie not
single size material). The precise blending of the two materials(Khoa/Sand) must be dtermined by trials at the suppliers yard prior to delivery to site of the
mixture. No allowance has been made in the rate for additional crushing of the Khoa at site.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/02/01 (b)
Item Name Sub-Base (with Paver)
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Dump Truck day 10,000.00 0.15 1,500.00 150.00
Pay Loader day 12,000.00 0.04 480.00 48.00
Aggregate Base Paver day 30,000.00 0.10 3,000.00 300.00
Small hand tools (1) day 50.00 4.00 200.00 20.00
Vibratory roller ( 7-10tonne) day 10,000.00 0.10 1,000.00 100.00
Water Tanker day 7,000.00 0.04 280.00 28.00
Item Type Labour
Masons day 700.00 1.00 700.00 70.00
Unskilled labourer day 450.00 3.00 1,350.00 135.00
Item Type Material
Sand FM>1.0 cu. metre 640.00 4.55 2,912.00 291.20
Brick Khoa < 40mm cu. metre 3,900.00 8.45 32,955.00 3,295.50
Water cu. metre 12.00 10.00 120.00 12.00
Basic Unit Price of Specification Item : 4,449.70
Plus Profit at 5% 222.49
Plus Overhead at 3.00% 133.49
Sub-Total : 4,805.68
Plus Tax & VAT at 16.2791% 782.32
Total Unit Price of Specification Item : 5,588.00
5,588.00

Assumption :
To obtain the specified grading a blend of typically 65:35 (Khoa:Sand) is required. The Khoa must be properly crushed to give a well graded material (ie not
single size material). The precise blending of the two materials(Khoa/Sand) must be dtermined by trials at the suppliers yard prior to delivery to site of the
mixture. No allowance has been made in the rate for additional crushing of the Khoa at site.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/03/01(a)
Item Name Aggregate Base Type I
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Dump Truck day 10,000.00 0.15 1,500.00 150.00
Pay Loader day 12,000.00 0.04 480.00 48.00
Motor Grader day 10,000.00 0.10 1,000.00 100.00
Small hand tools (1) day 50.00 5.00 250.00 25.00
Vibratory roller ( 7-10tonne) day 10,000.00 0.10 1,000.00 100.00
Water Tanker day 7,000.00 0.04 280.00 28.00
Item Type Labour
Masons day 700.00 1.00 700.00 70.00
Unskilled labourer day 450.00 4.00 1,800.00 180.00
Item Type Material
Crushed boulder <38mm cu. metre 6,750.00 3.89 26,257.50 2,625.75
Crushed boulder<25mm cu. metre 7,000.00 2.43 17,010.00 1,701.00
Crushed boulder<9mm cu. metre 5,700.00 2.43 13,851.00 1,385.10
Sand FM>1.0 cu. metre 640.00 3.25 2,080.00 208.00
Stone Crushings cu. metre 4,000.00 1.00 4,000.00 400.00
Water cu. metre 12.00 10.00 120.00 12.00
Basic Unit Price of Specification Item : 7,032.85
Plus Profit at 5% 351.64
Plus Overhead at 3.00% 210.99
Sub-Total : 7,595.48
Plus Tax & VAT at 16.2791% 1,236.47
Total Unit Price of Specification Item : 8,831.95
8,832.00
Assumption : Type 1 Aggregate Base comprises a 2:1 mixture of Stone aggregate:Sylhet Sand. Assume that all materials are brought to the contractor's stack yard and
then premixed in the required ratio with water before being taken to site by lorry for spreading and rolling. A daily production of 150Cu.m is assumed with the
roller being redeployed to other operations.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/03/01 (b)
Item Name Aggregate Base Type I (with Paver)
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Dump Truck day 10,000.00 0.15 1,500.00 150.00
Pay Loader day 12,000.00 0.04 480.00 48.00
Aggregate Base Paver day 30,000.00 0.10 3,000.00 300.00
Small hand tools (1) day 50.00 4.00 200.00 20.00
Vibratory roller ( 7-10tonne) day 10,000.00 0.10 1,000.00 100.00
Water Tanker day 7,000.00 0.04 280.00 28.00
Item Type Labour
Masons day 700.00 1.00 700.00 70.00
Unskilled labourer day 450.00 3.00 1,350.00 135.00
Item Type Material
Crushed boulder <38mm cu. metre 6,750.00 3.89 26,257.50 2,625.75
Crushed boulder<25mm cu. metre 7,000.00 2.43 17,010.00 1,701.00
Crushed boulder<9mm cu. metre 5,700.00 2.43 13,851.00 1,385.10
Sand FM>1.0 cu. metre 640.00 3.25 2,080.00 208.00
Stone Crushings cu. metre 4,000.00 1.00 4,000.00 400.00
Water cu. metre 12.00 10.00 120.00 12.00
Basic Unit Price of Specification Item : 7,182.85
Plus Profit at 5% 359.14
Plus Overhead at 3.00% 215.49
Sub-Total : 7,757.48
Plus Tax & VAT at 16.2791% 1,262.85
Total Unit Price of Specification Item : 9,020.32
9,020.00
Assumption : Type 1 Aggregate Base comprises a 2:1 mixture of Stone aggregate:Sylhet Sand. Assume that all materials are brought to the contractor's stack yard and
then premixed in the required ratio with water before being taken to site by lorry for spreading and rolling. A daily production of 150Cu.m is assumed with the
roller being redeployed to other operations.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/03/02 (a)
Item Name Aggregate Base Type II
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Dump Truck day 10,000.00 0.15 1,500.00 150.00
Pay Loader day 12,000.00 0.04 480.00 48.00
Motor Grader day 10,000.00 0.10 1,000.00 100.00
Small hand tools (1) day 50.00 5.00 250.00 25.00
Vibratory roller ( 7-10tonne) day 10,000.00 0.10 1,000.00 100.00
Water Tanker day 7,000.00 0.04 280.00 28.00
Item Type Labour 0.00 0.00
Masons day 700.00 1.00 700.00 70.00
Unskilled labourer day 450.00 4.00 1,800.00 180.00
Item Type Material 0.00 0.00
Brick Khoa < 40mm cu. metre 3,900.00 9.75 38,025.00 3,802.50
Sand FM>1.0 cu. metre 640.00 3.25 2,080.00 208.00
Water cu. metre 12.00 10.00 120.00 12.00
Basic Unit Price of Specification Item : 4,723.50
Plus Profit at 5% 236.18
Plus Overhead at 3.00% 141.71
Sub-Total : 5,101.38
Plus Tax & VAT at 16.2791% 830.46
Total Unit Price of Specification Item : 5,931.84
5,932.00

Assumption : The labour and production outputs are the same as for base type I with the only change being in the blend of the material which is khoa: sand in a ratio of
75% : 25%. Again the roller is considered to be efficiently redeployed to other operation.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/03/02 (b)
Item Name Aggregate Base Type II (with Paver)
Unit of Measurement cu metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Dump Truck day 10,000.00 0.15 1,500.00 150.00
Pay Loader day 12,000.00 0.04 480.00 48.00
Aggregate Base Paver day 30,000.00 0.10 3,000.00 300.00
Small hand tools (1) day 50.00 4.00 200.00 20.00
Vibratory roller ( 7-10tonne) day 10,000.00 0.10 1,000.00 100.00
Water Tanker day 7,000.00 0.04 280.00 28.00
Item Type Labour 0.00 0.00
Masons day 700.00 1.00 700.00 70.00
Unskilled labourer day 450.00 3.00 1,350.00 135.00
Item Type Material 0.00 0.00
Brick Khoa < 40mm cu. metre 3,900.00 9.75 38,025.00 3,802.50
Sand FM>1.0 cu. metre 640.00 3.25 2,080.00 208.00
Water cu. metre 12.00 10.00 120.00 12.00
Basic Unit Price of Specification Item : 4,873.50
Plus Profit at 5% 243.68
Plus Overhead at 3.00% 146.21
Sub-Total : 5,263.38
Plus Tax & VAT at 16.2791% 856.83
Total Unit Price of Specification Item : 6,120.21
6,120.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/06/01a
Item Name Bituminous Prime Coat (Plant Placed)
Unit of Measurement sq. metre
Quantity for Estimation 1500.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bitumen Distributor day 8,000.00 0.75 6,000.00 4.00
Bitumen Heater day 2,000.00 2.00 4,000.00 2.67
Small hand tools (1) day 50.00 10.00 500.00 0.33
Tyre roller PTR day 6,000.00 0.13 780.00 0.52
Water tanker day 7,000.00 0.13 910.00 0.61
Air Blower day 5,000.00 0.13 650.00 0.43
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 2.00 1,400.00 0.93
Semi-skilled labourer day 500.00 1.00 500.00 0.33
Unskilled labourer day 450.00 7.00 3,150.00 2.10
Item Type Material 0.00 0.00
Bitumen (60/70) Bulk tonne 56,000.00 1.30 72,800.00 48.53
Firewood tonne 6,000.00 0.60 3,600.00 2.40
Kerosene ltr 65.00 650.00 42,250.00 28.17
Basic Unit Price of Specification Item : 91.03
Plus Profit at 5% 4.55
Plus Overhead at 3.00% 2.73
Sub-Total : 98.31
Plus Tax & VAT at 16.2791% 16.00
Total Unit Price of Specification Item : 114.31
114.00
Assumption : A Bitumen Distributor will normally only be used on a new road project or surface dressing works, where good daily production can be achieved. In the case of
working on an exisiting road an arbitrary rate of production of only 1000sqm per day is assumed ( i.e it is constrained by the road base production and traffic
managenent criteria).

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/06/01b
Item Name Bituminous Prime Coat (hand placed)
Unit of Measurement sq. metre
Quantity for Estimation 160.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bitumen Heater (Tar Boiler) day 1,000.00 0.25 250.00 1.56
Small hand tools (2) day 50.00 2.50 125.00 0.78
Tyre roller PTR day 6,000.00 0.01 60.00 0.37
Water tanker day 7,000.00 0.01 70.00 0.44
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 0.50 350.00 2.19
Unskilled labourer day 450.00 1.34 603.00 3.77
Item Type Material 0.00 0.00
Bitumen 80/100 (Drum) tonne 54,000.00 0.14 7,678.80 47.99
Firewood tonne 6,000.00 0.03 150.00 0.94
Kerosene ltr 65.00 70.00 4,550.00 28.44
Basic Unit Price of Specification Item : 86.48
Plus Profit at 5% 4.32
Plus Overhead at 3.00% 2.59
Sub-Total : 93.40
Plus Tax & VAT at 16.2791% 15.20
Total Unit Price of Specification Item : 108.60
109.00
Assumption : Assume 80/100pen Bitumen is cutback with kerosene at ratio of 50(K):100(B) and the spray rate is 1.5Ltr/sqm. Spraying is done manually.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/07/01a
Item Name Bituminous Tack Coat (Plant Work)
Unit of Measurement sq. metre
Quantity for Estimation 1000.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bitumen Distributor day 8,000.00 0.75 6,000.00 6.00
Bitumen Heater day 2,000.00 1.00 2,000.00 2.00
Small hand tools (2) day 50.00 7.00 350.00 0.35
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 1.00 700.00 0.70
Semi-skilled labourer day 500.00 1.00 500.00 0.50
Unskilled labourer day 450.00 5.00 2,250.00 2.25
Item Type Material 0.00 0.00
Bitumen 60/70 Bulk tonne 56,000.00 0.50 28,000.00 28.00
Firewood tonne 6,000.00 0.09 540.00 0.54
Kerosene ltr 65.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 40.34
Plus Profit at 5% 2.02
Plus Overhead at 3.00% 1.21
Sub-Total : 43.57
Plus Tax & VAT at 16.2791% 7.09
Total Unit Price of Specification Item : 50.66
51.00
Assumption : Tack coat is usually sprayed 1hr ahead of laying of asphalt when using an emulsion. Only that area that can be covered by the days production of asphalt will
be sprayed. Therefore area to be sprayed in a day is fixed by size and production rate of the asphalt plant. An arbitray rate of production of 10 tonnes per hour
for the asphalt plant has been assumed working a 10hr day.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/07/01b
Item Name Bituminous Tack Coat (Labour intensive work)
Unit of Measurement sq. metre
Quantity for Estimation 1000.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bitumen Heater (Tar Boiler) day 1,000.00 1.00 1,000.00 1.00
Hand operated bitumen distributor day 1,200.00 0.75 900.00 0.90
Small hand tools (2) day 50.00 9.00 450.00 0.45
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 1.00 700.00 0.70
Semi-skilled labourer day 500.00 1.00 500.00 0.50
Unskilled labourer day 450.00 5.00 2,250.00 2.25
Item Type Material 0.00 0.00
Bitumen 80/100 drum tonne 54,000.00 0.55 29,700.00 29.70
Firewood tonne 6,000.00 0.09 540.00 0.54
Kerosene ltr 65.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 36.04
Plus Profit at 5% 1.80
Plus Overhead at 3.00% 1.08
Sub-Total : 38.92
Plus Tax & VAT at 16.2791% 6.34
Total Unit Price of Specification Item : 45.26
45.00
Assumption : Same as Item 3/7/1a with the exception of hand operated distributor instead of tanker distributor.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/08/01
Item Name Primer seal
Unit of Measurement sq. metre
Quantity for Estimation 1500.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bitumen Distributor day 8,000.00 0.75 6,000.00 4.00
Bitumen Heater (Tar Boiler) day 1,000.00 1.00 1,000.00 0.67
Small hand tools (2) day 50.00 53.00 2,650.00 1.77
Tyre roller PTR day 6,000.00 0.75 4,500.00 3.00
Water Pump day 1,200.00 1.00 1,200.00 0.80
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 2.00 1,400.00 0.93
Semi-skilled labourer day 500.00 13.00 6,500.00 4.33
Skilled Labour day 550.00 11.00 6,050.00 4.03
Unskilled labourer day 450.00 27.00 12,150.00 8.10
Item Type Material 0.00 0.00
Bitumen 80/100 Drum tonne 54,000.00 1.16 62,640.00 41.76
Firewood tonne 6,000.00 0.57 3,420.00 2.28
Gravel (as dug) cu. metre 2,470.00 9.50 23,465.00 15.64
Kerosene ltr 65.00 60.00 3,900.00 2.60
Basic Unit Price of Specification Item : 89.92
Plus Profit at 5% 4.50
Plus Overhead at 3.00% 2.70
Sub-Total : 97.11
Plus Tax & VAT at 16.2791% 15.81
Total Unit Price of Specification Item : 112.92
113.00
Assumption : Primer Seal is applied to an existing asphalt surface. Assume that the daily production is 1000sqm. Specification states the bituminous material is 80/100 pen
cutback by 4% Diesel and a rate of application of 1ltr/sqm.The applied aggregate is washed and dried peagravel of size 2.4mm to 6.3mm with a rate of spread

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/9/01(a)
Item Name Single Bituminous Surface Treatment 14mm nominal size aggregate (Machine Method) (Grade 80/100)
Unit of Measurement Sq Metre
Quantity for Estimation 8,000 (All Prices Are in Taka)
(Considering one day work)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Aggregate Spreader day 5,000.00 1.00 5,000.00 0.63
Bitumen Distributor day 8,000.00 1.00 8,000.00 1.00
Concrete Mixer (7/5) day 2,000.00 3.00 6,000.00 0.75
Small hand tools (2) day 50.00 80.00 4,000.00 0.50
Steel Wheel Roller (5-6 Tonne) day 8,000.00 0.00 0.00 0.00
Dump Truck* day 10,000.00 3.00 30,000.00 3.75
Bitumen Heater (Tar Boiler)* day 1,000.00 1.00 1,000.00 0.13
Air Blower/Power Brush/Drag Brush* day 5,000.00 1.00 5,000.00 0.63
Pay Loader* day 12,000.00 0.50 6,000.00 0.75
Tyre roller PTR day 6,000.00 2.00 12,000.00 1.50
Water Pump/Gen. day 1,200.00 1.00 1,200.00 0.15
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 6.00 4,200.00 0.53
Foreman day 850.00 2.00 1,700.00 0.21
Semi-skilled labourer day 500.00 10.00 5,000.00 0.63
Skilled Labour day 550.00 6.00 3,300.00 0.41
Unskilled labourer day 450.00 30.00 13,500.00 1.69
Item Type Material 0.00 0.00
Bitumen 80/100 Bulk tonne 54,000.00 9.84 531,360.00 66.42
Diesel ltr 65.00 590.00 38,350.00 4.79
Kerosene ltr 65.00 1,776.00 115,440.00 14.43
Stone Chippings (pakur stone) 14mm cu. metre 7,800.00 87.67 683,826.00 85.48
Basic Unit Price of Specification Item : 184.36
Plus Profit at 5% 9.22
Plus Overhead at 3.00% 5.53
Sub-Total : 199.11
Plus Tax & VAT at 16.2791% 32.41
Total Unit Price of Specification Item : 231.52

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


232.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/9/01(b)
Item Name Single Bituminous Surface Treatment 14mm nominal size aggregate (Machine Method) (Bitumen Grade
60/70)
Unit of Measurement Sq Metre
Quantity for Estimation 8,000 (All Prices Are in Taka)
(Considering one day work)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Aggregate Spreader day 5,000.00 1.00 5,000.00 0.63
Bitumen Distributor day 8,000.00 1.00 8,000.00 1.00
Concrete Mixer (7/5) day 2,000.00 3.00 6,000.00 0.75
Small hand tools (2) day 50.00 80.00 4,000.00 0.50
Steel Wheel Roller (5-6 Tonne) day 8,000.00 0.00 0.00 0.00
Dump Truck* day 10,000.00 3.00 30,000.00 3.75
Bitumen Heater (Tar Boiler)* day 1,000.00 1.00 1,000.00 0.13
Air Blower/Power Brush/Drag Brush* day 5,000.00 1.00 5,000.00 0.63
Pay Loader* day 12,000.00 0.50 6,000.00 0.75
Tyre roller PTR day 6,000.00 2.00 12,000.00 1.50
Water Pump/Gen. day 1,200.00 1.00 1,200.00 0.15
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 6.00 4,200.00 0.53
Foreman day 850.00 2.00 1,700.00 0.21
Semi-skilled labourer day 500.00 10.00 5,000.00 0.63
Skilled Labour day 550.00 6.00 3,300.00 0.41
Unskilled labourer day 450.00 30.00 13,500.00 1.69
Item Type Material 0.00 0.00
Bitumen 60/70 Bulk tonne 56,000.00 9.84 551,040.00 68.88
Diesel ltr 65.00 590.00 38,350.00 4.79
Kerosene ltr 65.00 1,776.00 115,440.00 14.43
Stone Chippings (pakur stone) 14mm cu. metre 7,800.00 87.67 683,826.00 85.48
Basic Unit Price of Specification Item : 186.82
Plus Profit at 5% 9.34
Plus Overhead at 3.00% 5.60
Sub-Total : 201.77
Plus Tax & VAT at 16.2791% 32.85
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Total Unit Price of Specification Item : 234.61
235.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/09/02a
Item Name Double Bituminous Surface Treatment-20mm nominal size aggregate followed by 10mm (Machine Method) (Grade 80/100)
Unit of Measurement Sq Metre
Quantity for Estimation 8,000 (All Prices Are in Taka)
(Considering one day work)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Aggregate Spreader day 5,000.00 2.00 10,000.00 1.25
Bitumen Distributor day 8,000.00 2.00 16,000.00 2.00
Concrete Mixer (7/5) day 2,000.00 6.00 12,000.00 1.50
Dump Truck* day 10,000.00 6.00 60,000.00 7.50
Bitumen Heater (Tar Boiler)* day 1,000.00 2.00 2,000.00 0.25
Air Blower/Power Brush/Drag Brush* day 10,000.00 2.00 20,000.00 2.50
Pay Loader* day 12,000.00 1.00 12,000.00 1.50
Small hand tools (1) day 50.00 150.00 7,500.00 0.94
Steel Wheel Roller (5-6 Tonne) day 8,000.00 1.00 8,000.00 1.00
Tyre roller PTR day 6,000.00 4.00 24,000.00 3.00
Water Pump/Gen. day 1,200.00 2.00 2,400.00 0.30
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 10.00 7,000.00 0.88
Foreman day 850.00 3.00 2,550.00 0.32
Semi-skilled labourer day 500.00 18.00 9,000.00 1.13
Skilled Labour day 550.00 11.00 6,050.00 0.76
Unskilled labourer day 450.00 54.00 24,300.00 3.04
Item Type Material 0.00 0.00
Bitumen 80/100 Bulk tonne 54,000.00 17.45 942,300.00 117.79
Diesel ltr 65.00 1,180.00 76,700.00 9.59
Kerosene ltr 65.00 3,504.00 227,760.00 28.47
Stone Chippings (pakur stone) 10mm cu. metre 7,500.00 48.00 360,000.00 45.00
Stone Chippings (pakur stone) 20mm cu. metre 8,100.00 106.50 862,650.00 107.83
Basic Unit Price of Specification Item : 336.53
Plus Profit at 5% 16.83
Plus Overhead at 3.00% 10.10
Sub-Total : 363.45
Plus Tax & VAT at 16.2791% 59.17
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Total Unit Price of Specification Item : 422.61
423.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/09/02(b)
Item Name Double Bituminous Surface Treatment-20mm nominal size aggregate followed by 10mm (Machine Method) (Bitumen Grade 60/70)
Unit of Measurement Sq Metre
Quantity for Estimation 8,000 (All Prices Are in Taka)
(Considering one day work)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Aggregate Spreader day 5,000.00 2.00 10,000.00 1.25
Bitumen Distributor day 8,000.00 2.00 16,000.00 2.00
Concrete Mixer (7/5) day 2,000.00 6.00 12,000.00 1.50
Dump Truck* day 10,000.00 6.00 60,000.00 7.50
Bitumen Heater (Tar Boiler)* day 1,000.00 2.00 2,000.00 0.25
Air Blower/Power Brush/Drag Brush* day 10,000.00 2.00 20,000.00 2.50
Pay Loader* day 12,000.00 1.00 12,000.00 1.50
Small hand tools (1) day 50.00 150.00 7,500.00 0.94
Steel Wheel Roller (5-6 Tonne) day 8,000.00 1.00 8,000.00 1.00
Tyre roller PTR day 6,000.00 4.00 24,000.00 3.00
Water Pump/Gen. day 1,200.00 2.00 2,400.00 0.30
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 10.00 7,000.00 0.88
Foreman day 850.00 3.00 2,550.00 0.32
Semi-skilled labourer day 500.00 18.00 9,000.00 1.13
Skilled Labour day 550.00 11.00 6,050.00 0.76
Unskilled labourer day 450.00 54.00 24,300.00 3.04
Item Type Material 0.00 0.00
Bitumen 60/70 Bulk tonne 56,000.00 17.45 977,200.00 122.15
Diesel ltr 65.00 1,180.00 76,700.00 9.59
Kerosene ltr 65.00 3,504.00 227,760.00 28.47
Stone Chippings (pakur stone) 10mm cu. metre 7,500.00 48.00 360,000.00 45.00
Stone Chippings (pakur stone) 20mm cu. metre 8,100.00 106.50 862,650.00 107.83
Basic Unit Price of Specification Item : 340.89
Plus Profit at 5% 17.04
Plus Overhead at 3.00% 10.23
Sub-Total : 368.16
Plus Tax & VAT at 16.2791% 59.93
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Total Unit Price of Specification Item : 428.09
428.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/09/02 ©
Item Name Double Bituminous Surface Treatment-14mm nominal size aggregate followed by 10mm (Machine Method)(Bitumen grade 80/100)
Unit of Measurement Sq Metre
Quantity for Estimation 8,000 (All Prices Are in Taka)
(Considering one day work)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Aggregate Spreader day 5,000.00 2.00 10,000.00 1.25
Bitumen Distributor day 8,000.00 2.00 16,000.00 2.00
Concrete Mixer (7/5) day 2,000.00 6.00 12,000.00 1.50
Dump Truck* day 10,000.00 6.00 60,000.00 7.50
Bitumen Heater (Tar Boiler)* day 1,000.00 2.00 2,000.00 0.25
Air Blower/Power Brush/Drag Brush* day 10,000.00 2.00 20,000.00 2.50
Pay Loader* day 12,000.00 1.00 12,000.00 1.50
Small hand tools (1) day 50.00 150.00 7,500.00 0.94
Steel Wheel Roller (5-6 Tonne) day 8,000.00 1.00 8,000.00 1.00
Tyre roller PTR day 6,000.00 4.00 24,000.00 3.00
Water Pump/Gen. day 1,200.00 2.00 2,400.00 0.30
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 10.00 7,000.00 0.88
Foreman day 850.00 3.00 2,550.00 0.32
Semi-skilled labourer day 500.00 18.00 9,000.00 1.13
Skilled Labour day 550.00 11.00 6,050.00 0.76
Unskilled labourer day 450.00 54.00 24,300.00 3.04
Item Type Material 0.00 0.00
Bitumen 80/100 Bulk tonne 54,000.00 14.42 778,680.00 97.34
Diesel ltr 65.00 1,180.00 76,700.00 9.59
Kerosene ltr 65.00 3,440.00 223,600.00 27.95
Stone Chippings (pakur stone) 10mm cu. metre 7,500.00 48.00 360,000.00 45.00
Stone Chippings (pakur stone) 14mm cu. metre 7,800.00 87.67 683,826.00 85.48
Basic Unit Price of Specification Item : 293.20
Plus Profit at 5% 14.66
Plus Overhead at 3.00% 8.80
Sub-Total : 316.66
Plus Tax & VAT at 16.2791% 51.55

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Total Unit Price of Specification Item : 368.21
368.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/09/02(d)
Item Name Double Bituminous Surface Treatment-14mm nominal size aggregate followed by 10mm (Machine Method) (Bitumen Grade 60/70)
Unit of Measurement Sq Metre
Quantity for Estimation 8,000 (All Prices Are in Taka)
(Considering one day work)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Aggregate Spreader day 5,000.00 2.00 10,000.00 1.25
Bitumen Distributor day 8,000.00 2.00 16,000.00 2.00
Concrete Mixer (7/5) day 2,000.00 6.00 12,000.00 1.50
Dump Truck* day 10,000.00 6.00 60,000.00 7.50
Bitumen Heater (Tar Boiler)* day 1,000.00 2.00 2,000.00 0.25
Air Blower/Power Brush/Drag Brush* day 10,000.00 2.00 20,000.00 2.50
Pay Loader* day 12,000.00 1.00 12,000.00 1.50
Small hand tools (1) day 50.00 150.00 7,500.00 0.94
Steel Wheel Roller (5-6 Tonne) day 8,000.00 1.00 8,000.00 1.00
Tyre roller PTR day 6,000.00 4.00 24,000.00 3.00
Water Pump/Gen. day 1,200.00 2.00 2,400.00 0.30
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 10.00 7,000.00 0.88
Foreman day 850.00 3.00 2,550.00 0.32
Semi-skilled labourer day 500.00 18.00 9,000.00 1.13
Skilled Labour day 550.00 11.00 6,050.00 0.76
Unskilled labourer day 450.00 54.00 24,300.00 3.04
Item Type Material 0.00 0.00
Bitumen 60/70 Bulk tonne 56,000.00 14.42 807,520.00 100.94
Diesel ltr 65.00 1,180.00 76,700.00 9.59
Kerosene ltr 65.00 3,440.00 223,600.00 27.95
Stone Chippings (pakur stone) 10mm cu. metre 7,500.00 18.00 135,000.00 16.88
Stone Chippings (pakur stone) 14mm cu. metre 7,800.00 87.67 683,826.00 85.48
Basic Unit Price of Specification Item : 268.68
Plus Profit at 5% 13.43
Plus Overhead at 3.00% 8.06
Sub-Total : 290.18
Plus Tax & VAT at 16.2791% 47.24
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Total Unit Price of Specification Item : 337.41
337.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/10/01(a)
Item Name Dense Bituminous Surfacing-Base Course (Plant Method) (Bitumen Grade 80/100)
Unit of Measurement cu metre
Quantity for Estimation 25.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
AC Paver day 10,000.00 0.25 2,500.00 100.00
Asphalt Batch Mixing Plant day 111,360.00 0.25 27,840.00 1,113.60
Bitumen Distributor day 8,000.00 0.25 2,000.00 80.00
Dump Truck day 10,000.00 2.50 25,000.00 1,000.00
Tyre roller PTR day 6,000.00 0.25 1,500.00 60.00
Vibratory Roller ( 6-7.5 tonne) day 10,000.00 0.25 2,500.00 100.00
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 0.75 525.00 21.00
Foreman day 850.00 0.25 212.50 8.50
Semi-skilled labourer day 500.00 1.50 750.00 30.00
Unskilled labourer day 450.00 1.50 675.00 27.00
Item Type Material 0.00 0.00
Angle Iron (62.5x62.5x6mm) using 20 times lin. metre 150.00 20.00 3,000.00 120.00
Bitumen 80/100 Bulk tonne 54,000.00 3.12 168,480.00 6,739.20
Cement kg 9.00 1,200.00 10,800.00 432.00
Crushed boulder <25mm cu. metre 7,000.00 12.00 84,000.00 3,360.00
Crushed boulder <12mm cu. metre 6,300.00 4.00 25,200.00 1,008.00
Crushed boulder <9mm cu. metre 5,700.00 4.00 22,800.00 912.00
Crusher (stone) dust cu. metre 4,000.00 17.50 70,000.00 2,800.00
Diesel ltr 65.00 112.50 7,312.50 292.50
Basic Unit Price of Specification Item : 18,203.80
Plus Profit at 5% 910.19
Plus Overhead at 3.00% 546.11
Sub-Total : 19,660.10
Plus Tax & VAT at 16.2791% 3,200.48
Total Unit Price of Specification Item : 22,860.59
22,861.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/10/01(b)
Item Name Dense Bituminous Surfacing - Base Course (Plant Method) (Bitumen Grade 60/70)
Unit of Measurement cu metre
Quantity for Estimation 25.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
AC Paver day 10,000.00 0.25 2,500.00 100.00
Asphalt Batch Mixing Plant day 111,360.00 0.25 27,840.00 1,113.60
Bitumen Distributor day 8,000.00 0.25 2,000.00 80.00
Dump Truck day 10,000.00 2.50 25,000.00 1,000.00
Tyre roller PTR day 6,000.00 0.25 1,500.00 60.00
Vibratory Roller ( 6-7.5 tonne) day 10,000.00 0.25 2,500.00 100.00
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 0.75 525.00 21.00
Foreman day 850.00 0.25 212.50 8.50
Semi-skilled labourer day 500.00 1.50 750.00 30.00
Unskilled labourer day 450.00 1.50 675.00 27.00
Item Type Material 0.00 0.00
Angle Iron (62.5x62.5x6mm) using 20 times lin. metre 120.00 20.00 2,400.00 96.00
Bitumen 60/70 Bulk tonne 56,000.00 3.12 174,720.00 6,988.80
Cement kg 9.00 1,200.00 10,800.00 432.00
Crushed boulder <25mm cu. metre 7,000.00 12.00 84,000.00 3,360.00
Crushed boulder <12mm cu. metre 6,300.00 4.00 25,200.00 1,008.00
Crushed boulder <9mm cu. metre 5,700.00 4.00 22,800.00 912.00
Crusher (stone) dust cu. metre 4,000.00 17.50 70,000.00 2,800.00
Diesel ltr 65.00 112.50 7,312.50 292.50
Basic Unit Price of Specification Item : 18,429.40
Plus Profit at 5% 921.47
Plus Overhead at 3.00% 552.88
Sub-Total : 19,903.75
Plus Tax & VAT at 16.2791% 3,240.15
Total Unit Price of Specification Item : 23,143.90
23,144.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/10/02(a)
Item Name DBS - Wearing Course (Bitumen Grade 80/100)
Unit of Measurement cu metre
Quantity for Estimation 25.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
AC Paver day 10,000.00 0.25 2,500.00 100.00
Asphalt Batch Mixing Plant day 111,360.00 0.25 27,840.00 1,113.60
Bitumen Distributor day 8,000.00 0.25 2,000.00 80.00
Dump Truck day 10,000.00 2.50 25,000.00 1,000.00
Tyre roller PTR day 6,000.00 0.25 1,500.00 60.00
Vibratory Roller ( 6-7.5 tonne) day 10,000.00 0.25 2,500.00 100.00
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 0.75 525.00 21.00
Foreman day 850.00 0.25 212.50 8.50
Semi-skilled labourer day 500.00 1.50 750.00 30.00
Unskilled labourer day 450.00 1.50 675.00 27.00
Item Type Material 0.00 0.00
Angle Iron (62.5x62.5x6mm) using 20 times lin. metre 150.00 20.00 3,000.00 120.00
Bitumen 80/100 Bulk tonne 54,000.00 3.50 189,000.00 7,560.00
Cement kg 9.00 1,200.00 10,800.00 432.00
Crushed boulder <25mm cu. metre 7,000.00 12.00 84,000.00 3,360.00
Crushed boulder <12mm cu. metre 6,300.00 4.00 25,200.00 1,008.00
Crushed boulder <9mm cu. metre 5,700.00 4.00 22,800.00 912.00
Crusher (stone) dust cu. metre 4,000.00 17.50 70,000.00 2,800.00
Diesel ltr 65.00 137.50 8,937.50 357.50
Basic Unit Price of Specification Item : 19,089.60
Plus Profit at 5% 954.48
Plus Overhead at 3.00% 572.69
Sub-Total : 20,616.77
Plus Tax & VAT at 16.2791% 3,356.22
Total Unit Price of Specification Item : 23,972.99
23,973.00
Assumption : The same comments apply as for Base Course Item 03/10/01.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/10/02(b)
Item Name DBS - Wearing Course (Bitumen Grade 60/70)
Unit of Measurement cu metre
Quantity for Estimation 25.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
AC Paver day 10,000.00 0.25 2,500.00 100.00
Asphalt Batch Mixing Plant day 111,360.00 0.25 27,840.00 1,113.60
Bitumen Distributor day 8,000.00 0.25 2,000.00 80.00
Dump Truck day 10,000.00 2.50 25,000.00 1,000.00
Tyre roller PTR day 6,000.00 0.25 1,500.00 60.00
Vibratory Roller ( 6-7.5 tonne) day 10,000.00 0.25 2,500.00 100.00
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 0.75 525.00 21.00
Foreman day 850.00 0.25 212.50 8.50
Semi-skilled labourer day 500.00 1.50 750.00 30.00
Unskilled labourer day 450.00 1.50 675.00 27.00
Item Type Material 0.00 0.00
Angle Iron (62.5x62.5x6mm) using 20 times lin. metre 150.00 20.00 3,000.00 120.00
Bitumen 60/70 Bulk tonne 56,000.00 3.50 196,000.00 7,840.00
Cement kg 9.00 1,200.00 10,800.00 432.00
Crushed boulder<25mm cu. metre 7,000.00 12.00 84,000.00 3,360.00
Crushed boulder<12mm cu. metre 6,300.00 4.00 25,200.00 1,008.00
Crushed boulder<9mm cu. metre 5,700.00 4.00 22,800.00 912.00
Crusher (stone) dust cu. metre 4,000.00 17.50 70,000.00 2,800.00
Diesel ltr 65.00 137.50 8,937.50 357.50
Basic Unit Price of Specification Item : 19,369.60
Plus Profit at 5% 968.48
Plus Overhead at 3.00% 581.09
Sub-Total : 20,919.17
Plus Tax & VAT at 16.2791% 3,405.45
Total Unit Price of Specification Item : 24,324.61
24,325.00
Assumption : The same comments apply as for Base Course Item 03/10/01.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/11/01
Item Name Premix Bituminous Carpeting (Bitumen Grade 80/100)
Unit of Measurement cu metre
Quantity for Estimation 25.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bitumen Heater (Tar Boiler) day 1,000.00 1.00 1,000.00 40.00
Richshaw Van day 600.00 3.00 1,800.00 72.00
Small hand tools (2) day 50.00 83.00 4,150.00 166.00
Tyre roller PTR day 6,000.00 1.00 6,000.00 240.00
Vibratory roller (1-3 tonne) day 4,000.00 1.00 4,000.00 160.00
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 14.00 9,800.00 392.00
Masons day 700.00 4.00 2,800.00 112.00
Semi-skilled labourer day 500.00 18.00 9,000.00 360.00
Unskilled labourer day 450.00 47.00 21,150.00 846.00
Item Type Material 0.00 0.00
Angle Iron (62.5x62.5x6mm) using 20 times lin. metre 150.00 20.00 3,000.00 120.00
Bitumen 80/100 Drum tonne 54,000.00 2.43 131,220.00 5,248.80
Coarse Sand FM>2.5 cu. metre 1,850.00 3.75 6,937.50 277.50
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 15.00 105,000.00 4,200.00
Crushed boulder/gravel aggregate <12mm cu. metre 6,300.00 11.25 70,875.00 2,835.00
Crusher (stone) dust cu. metre 4,000.00 7.50 30,000.00 1,200.00
Firewood tonne 6,000.00 1.36 8,160.00 326.40
Basic Unit Price of Specification Item : 16,595.70
Plus Profit at 5% 829.79
Plus Overhead at 3.00% 497.87
Sub-Total : 17,923.36
Plus Tax & VAT at 16.2791% 2,917.76
Total Unit Price of Specification Item : 20,841.11
20,841.00
Assumption : Rate has been calculated for 50mm thickness of compacted pavement layer (mat). In order to achieve the specified grading a blend of at least 3-4 different
types of aggregates and sands is required, which for this exercise has been taken as crusher dust:Sylhet sand : 12mm crushed gravel : 25mm crushed gravel
blended together in a ratio of 20%:10%:30%:40%.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/12/02
Item Name 12 mm Compacted Premix Bituminous Seal Coat (Bitumen Grade 80/100)
Unit of Measurement sq. metre
Quantity for Estimation 1500.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
2/3 wheel static roller 8-12 tonnes day 8,000.00 0.75 6,000.00 4.00
Bitumen Heater (Tar Boiler) day 1,000.00 1.50 1,500.00 1.00
Richshaw Van day 600.00 1.50 900.00 0.60
Small hand tools (2) day 50.00 72.00 3,600.00 2.40
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 6.00 4,200.00 2.80
Semi-skilled labourer day 500.00 12.00 6,000.00 4.00
Unskilled labourer day 450.00 12.00 5,400.00 3.60
Item Type Material 0.00 0.00
Bitumen 80/100 Drum tonne 54,000.00 2.04 110,160.00 73.44
Coarse Sand FM>2.5 cu. metre 1,850.00 2.00 3,700.00 2.47
Crusher (stone) dust (6mm down) cu. metre 4,000.00 4.00 16,000.00 10.67
Pea Gravels cu. metre 2,850.00 16.00 45,600.00 30.40
9mm downgrade stone chips cu. metre 5,700.00 2.00 11,400.00 7.60
Firewood tonne 6,000.00 1.02 6,120.00 4.08
Basic Unit Price of Specification Item : 147.05
Plus Profit at 5% 7.35
Plus Overhead at 3.00% 4.41
Sub-Total : 158.82
Plus Tax & VAT at 16.2791% 25.85
Total Unit Price of Specification Item : 184.67
185.00

Assumption : Assume the material requirements and labour for heating aggregates etc are pro rata from those resources needed for 7mm thick seal coat. Only cleaning
labour remains the same.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/12/03
Item Name 15 mm Compacted Premix Bituminous Seal Coat (Bitumen Grade 80/100)
Unit of Measurement sq. metre
Quantity for Estimation 1500.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
2/3 wheel static roller 8-12 tonnes day 8,000.00 0.75 6,000.00 4.00
Bitumen Heater (Tar Boiler) day 1,000.00 2.00 2,000.00 1.33
Richshaw Van day 600.00 2.00 1,200.00 0.80
Small hand tools (2) day 50.00 91.00 4,550.00 3.03
Item Type Labour 0.00 0.00
Asphalt Mistry day 700.00 6.00 4,200.00 2.80
Semi-skilled labourer day 500.00 12.00 6,000.00 4.00
Unskilled labourer day 450.00 12.00 5,400.00 3.60
Item Type Material 0.00 0.00
Bitumen 80/100 Drum tonne 54,000.00 2.55 137,700.00 91.80
Coarse Sand FM>2.5 cu. metre 1,850.00 2.50 4,625.00 3.08
Crusher (stone) dust (6mm down) cu. metre 4,000.00 5.00 20,000.00 13.33
Pea Gravels cu. metre 2,850.00 20.00 57,000.00 38.00
9mm downgrade stone chips cu. metre 5,700.00 2.50 14,250.00 9.50
Firewood tonne 6,000.00 1.42 8,520.00 5.68
Basic Unit Price of Specification Item : 180.96
Plus Profit at 5% 9.05
Plus Overhead at 3.00% 5.43
Sub-Total : 195.44
Plus Tax & VAT at 16.2791% 31.82
Total Unit Price of Specification Item : 227.26
227.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/13/01 (a)
Item Name 125mm Thick Brick on End Edging (1st Class)
Unit of Measurement Lin. Metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 4.00 200.00 2.00
Item Type Labour 0.00 0.00
Masons day 700.00 1.00 700.00 7.00
Unskilled labourer day 450.00 3.00 1,350.00 13.50
Item Type Material 0.00 0.00
Brick 1st Class no. 10.00 1,350.00 13,500.00 135.00
Sand FM>0.5 cu. metre 420.00 0.20 84.00 0.84
Basic Unit Price of Specification Item : 158.34
Plus Profit at 5% 7.92
Plus Overhead at 3.00% 4.75
Sub-Total : 171.01
Plus Tax & VAT at 16.2791% 27.84
Total Unit Price of Specification Item : 198.85
199.00
Assumption : Rate is based on a production of 100 lin.m.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/13/01 (b)
Item Name 125mm Thick Brick on End Edging (Machine Made)
Unit of Measurement Lin. Metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 4.00 200.00 2.00
Item Type Labour 0.00 0.00
Masons day 700.00 1.00 700.00 7.00
Unskilled labourer day 450.00 3.00 1,350.00 13.50
Item Type Material 0.00 0.00
Brick Auto Machine Made no. 12.00 1,350.00 16,200.00 162.00
Sand FM>0.5 cu. metre 420.00 0.20 84.00 0.84
Basic Unit Price of Specification Item : 185.34
Plus Profit at 5% 9.27
Plus Overhead at 3.00% 5.56
Sub-Total : 200.17
Plus Tax & VAT at 16.2791% 32.59
Total Unit Price of Specification Item : 232.75
233.00
Assumption : Rate is based on a production of 100 lin.m.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/13/02 (a)
Item Name Single Layer Brick Flat Soling i/c 75mm thick compacted sand cushion (1st Class)
Unit of Measurement sq. metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Plate Compactor day 1,200.00 0.25 300.00 3.00
Small hand tools (2) day 50.00 10.50 525.00 5.25
Water Pump day 1,200.00 0.13 150.00 1.50
Item Type Labour 0.00 0.00
Masons day 700.00 3.50 2,450.00 24.50
Semi-skilled labourer day 500.00 1.00 500.00 5.00
Unskilled labourer day 450.00 7.00 3,150.00 31.50
Item Type Material 0.00 0.00
Brick P.J. no. 10.00 3,228.00 32,280.00 322.80
Sand FM>0.5 cu. metre 420.00 11.50 4,830.00 48.30
Basic Unit Price of Specification Item : 441.85
Plus Profit at 5% 22.09
Plus Overhead at 3.00% 13.26
Sub-Total : 477.20
Plus Tax & VAT at 16.2791% 77.68
Total Unit Price of Specification Item : 554.88
555.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/13/02 (b)
Item Name Single Layer Brick Flat Soling i/c 75mm thick compacted sand cushion (Machine Made)
Unit of Measurement sq. metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Plate Compactor day 1,200.00 0.25 300.00 3.00
Small hand tools (2) day 50.00 10.50 525.00 5.25
Water Pump day 1,200.00 0.13 150.00 1.50
Item Type Labour 0.00 0.00
Masons day 700.00 3.50 2,450.00 24.50
Semi-skilled labourer day 500.00 1.00 500.00 5.00
Unskilled labourer day 450.00 7.00 3,150.00 31.50
Item Type Material 0.00 0.00
Brick Machine Made no. 12.00 3,228.00 38,736.00 387.36
Sand FM>0.5 cu. metre 420.00 11.50 4,830.00 48.30
Basic Unit Price of Specification Item : 506.41
Plus Profit at 5% 25.32
Plus Overhead at 3.00% 15.19
Sub-Total : 546.92
Plus Tax & VAT at 16.2791% 89.03
Total Unit Price of Specification Item : 635.96
636.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/13/03 (a)
Item Name Herring Bond Brick Pavement i/c 12mm sand cushion (1st Class)
Unit of Measurement sq. metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 13.00 650.00 6.50
Water Pump day 1,200.00 0.13 150.00 1.50
Item Type Labour 0.00
Masons day 700.00 4.00 2,800.00 28.00
Semi-skilled labourer day 500.00 1.00 500.00 5.00
Unskilled labourer day 450.00 8.00 3,600.00 36.00
Item Type Material 0.00
Brick 1st Class no. 10.00 5,380.00 53,800.00 538.00
Sand FM>0.5 cu. metre 420.00 1.50 630.00 6.30
Basic Unit Price of Specification Item : 621.30
Plus Profit at 5% 31.07
Plus Overhead at 3.00% 18.64
Sub-Total : 671.00
Plus Tax & VAT at 16.2791% 109.23
Total Unit Price of Specification Item : 780.24
780.00

Assumption : Assume that a mason can lay 25sqm/day of herringbone bricks.This rate is lower than for flat soling because of the need to maintain the pattern, attain good
interlock and level control. Rate is based on 100sqm/day and assumes efficient mason output.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/13/03 (b)
Item Name Herring Bond Brick Pavement i/c 12mm sand cushion (Machine Made)
Unit of Measurement sq. metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 13.00 650.00 6.50
Water Pump day 1,200.00 0.13 150.00 1.50
Item Type Labour 0.00
Masons day 700.00 4.00 2,800.00 28.00
Semi-skilled labourer day 500.00 1.00 500.00 5.00
Unskilled labourer day 450.00 8.00 3,600.00 36.00
Item Type Material 0.00
Brick Machine Made no. 12.00 5,380.00 64,560.00 645.60
Sand FM>0.5 cu. metre 420.00 1.50 630.00 6.30
Basic Unit Price of Specification Item : 728.90
Plus Profit at 5% 36.45
Plus Overhead at 3.00% 21.87
Sub-Total : 787.21
Plus Tax & VAT at 16.2791% 128.15
Total Unit Price of Specification Item : 915.36
915.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/14/1(a)
Item Name Dry Lean Concrete Class 10 (Concrete Mixure)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.170 339.84 120.00
Concrete Poker Vibrator day 600.00 0.170 102.00 36.02
Small hand tools (1) day 50.00 2.00 100.00 35.31
Water bowser for curing day 7,000.00 0.14 980.00 346.05
Water pump with accessories day 2,000.00 0.14 280.00 98.87
Item Type Labour 0.00
Labour cost for fixing and Removing shutter for foundation sq. metre 150.00 3.02 453.00 159.96
Masons day 700.00 0.48 336.00 118.64
Semi-skilled labourer day 500.00 1.40 700.00 247.18
Unskilled labourer day 450.00 2.80 1,260.00 444.92
Item Type Material 0.00
Cement tonne 9,000.00 0.60 5,400.00 1,906.78
Diesel/Fuel Ltr 65.00 3.00 195.00 68.86
Cost of wooden shutter for concrete using 6 times sq. metre 125.00 3.02 377.50 133.30
Nail kg 200.00 0.50 100.00 35.31
Sand FM >1.5 cu. metre 1,250.00 1.27 1,587.50 560.56
Brick Khoa < 25mm cu. metre 4,000.00 2.55 10,200.00 3,601.69
Basic Unit Price of Specification Item : 7,913.43
Plus Profit at 5% 395.67
Plus Overhead at 3.00% 237.40
Sub-Total : 8,546.51
Plus Tax & VAT at 16.2791% 1,391.29
Total Unit Price of Specification Item : 9,937.80
9,938.00

Assumption : Class 10 concrete is assumed to be 'Blinding Concrete' and as such brick chips can be used as coarse aggregates.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/14/1(b)
Item Name Dry Lean Concrete Class 10 (Batching Plant without Concrete Paver).
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck/ Transit mixure truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.35 2,450.00 865.11
Water pump with accessories day 2,000.00 1.19 2,380.00 840.40
Item Type Labour 0.00
Labour cost for fixing and Removal of shutter sq. metre 150.00 3.02 453.00 159.96
Foreman/skilled labour 850.00 0.08 68.00 24.01
Masons day 700.00 0.16 112.00 39.55
Semi-skilled labourer day 500.00 0.48 240.00 84.75
Unskilled labourer day 450.00 1.00 450.00 158.90
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 10.00 650.00 229.52
Cement tonne 9,000.00 0.60 5,400.00 1,906.78
Cost of wooden shutter for concrete using 6 times sq. metre 125.00 3.02 377.50 133.30
Nail kg 125.00 0.50 62.50 22.07
Sand FM >1.5 cu. metre 1,250.00 1.27 1,587.50 560.56
Brick Khoa < 25mm cu. metre 4,000.00 2.55 10,200.00 3,601.69
Basic Unit Price of Specification Item : 10,265.71
Plus Profit at 5% 513.29
Plus Overhead at 3.00% 307.97
Sub-Total : 11,086.97
Plus Tax & VAT at 16.2791% 1,804.86
Total Unit Price of Specification Item : 12,891.83
12,892.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Assumption : Class 10 concrete is assumed to be 'Blinding Concrete' and as such brick chips can be used as coarse aggregates.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/14/1(c)
Item Name Dry Lean Concrete Class 10 (Batching Plant with Concrete Paver).
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Concrete Paver day 30,000.00 0.02 600.00 211.86
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.35 2,450.00 865.11
Water pump with accessories day 2,000.00 1.19 2,380.00 840.40
Item Type Labour 0.02 0.00
Labour cost for fixing and Removal of shutter sq. metre 150.00 3.02 453.00 159.96
Foreman/skilled labour 1,000.00 0.04 40.00 14.12
Masons day 700.00 0.08 56.00 19.77
Semi-skilled labourer day 500.00 0.20 100.00 35.31
Unskilled labourer day 450.00 0.40 180.00 63.56
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 15.00 975.00 344.28
Cement tonne 9,000.00 0.60 5,400.00 1,906.78
Cost of wooden shutter for concrete using 6 times sq. metre 125.00 3.02 377.50 133.30
Nail kg 125.00 0.50 62.50 22.07
Sand FM >1.5 cu. metre 1,250.00 1.27 1,587.50 560.56
Brick Khoa < 25mm cu. metre 4,000.00 2.55 10,200.00 3,601.69
Basic Unit Price of Specification Item : 10,417.90
Plus Profit at 5% 520.90
Plus Overhead at 3.00% 312.54
Sub-Total : 11,251.33
Plus Tax & VAT at 16.2791% 1,831.61
Total Unit Price of Specification Item : 13,082.95
13,083.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Assumption : Class 10 concrete is assumed to be 'Blinding Concrete' and as such brick chips can be used as coarse aggregates.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/14/2(a)
Item Name Dry Lean Concrete Class 20 (Concrete Mixure)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.170 339.84 120.00
Concrete Poker Vibrator day 600.00 0.170 102.00 36.02
Small hand tools (1) day 50.00 2.00 100.00 35.31
Water bowser for curing day 7,000.00 0.01 70.00 24.72
Water pump with accessories day 2,000.00 0.01 20.00 7.06
Item Type Labour 0.00
Labour cost for fixing and Removing shutter for foundation sq. metre 150.00 3.02 453.00 159.96
Masons day 700.00 0.48 336.00 118.64
Semi-skilled labourer day 500.00 1.40 700.00 247.18
Unskilled labourer day 450.00 2.80 1,260.00 444.92
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Diesel/Fuel Ltr 65.00 3.00 195.00 68.86
Cost of wooden shutter for concrete using 6 times sq. metre 125.00 3.02 377.50 133.30
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Nail kg 125.00 0.50 62.50 22.07
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 11,117.00
Plus Profit at 5% 555.85
Plus Overhead at 3.00% 333.51
Sub-Total : 12,006.36
Plus Tax & VAT at 16.2791% 1,954.52
Total Unit Price of Specification Item : 13,960.88
13,961.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/14/2(b)
Item Name Dry Lean Concrete Class 20 (Batching Plant without Concrete Paver).
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck/ Transit mixure truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.01 70.00 24.72
Water pump with accessories day 2,000.00 0.01 20.00 7.06
0.00
Item Type Labour 0.00
Labour cost for fixing and Removal of shutter sq. metre 150.00 3.02 453.00 159.96
Foreman/skilled labour 850.00 0.08 68.00 24.01
Masons day 700.00 0.16 112.00 39.55
Semi-skilled labourer day 500.00 0.48 240.00 84.75
Unskilled labourer day 450.00 1.00 450.00 158.90
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 10.00 650.00 229.52
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Cost of wooden shutter for concrete using 6 times sq. metre 125.00 3.02 377.50 133.30
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Nail kg 125.00 0.50 62.50 22.07
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 12,221.93
Plus Profit at 5% 611.10
Plus Overhead at 3.00% 366.66
Sub-Total : 13,199.68
Plus Tax & VAT at 16.2791% 2,148.79
Total Unit Price of Specification Item : 15,348.47
15,348.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/14/2(c)
Item Name Dry Lean Concrete Class 20 (Batching Plant with Concrete Paver).
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Concrete Paver day 30,000.00 0.02 600.00 211.86
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.01 70.00 24.72
Water pump with accessories day 2,000.00 0.01 20.00 7.06
Item Type Labour 0.00
Labour cost for fixing and Removal of shutter sq. metre 150.00 3.02 453.00 159.96
Foreman/skilled labour 850.00 0.04 34.00 12.01
Masons day 700.00 0.08 56.00 19.77
Semi-skilled labourer day 500.00 0.20 100.00 35.31
Unskilled labourer day 450.00 0.40 180.00 63.56
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 15.00 975.00 344.28
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Cost of wooden shutter for concrete using 6 times sq. metre 125.00 3.02 377.50 133.30
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Nail kg 125.00 0.50 62.50 22.07
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 12,372.00
Plus Profit at 5% 618.60
Plus Overhead at 3.00% 371.16
Sub-Total : 13,361.76
Plus Tax & VAT at 16.2791% 2,175.17
Total Unit Price of Specification Item : 15,536.93
15,537.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/01(a)
Item Name Cement Concrete Pavement (Concrete Class - 25) (Concrete Mixure)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category
Primary Item

Item Type Equipment

Concrete Mixer (7/5) day 2,000.00 0.170 339.60 120.00


Concrete Poker Vibrator day 600.00 0.170 102.00 36.04
Small hand tools (1) day 50.00 2.00 100.00 35.34
Water bowser for curing day 7,000.00 0.28 1,960.00 692.58
Water pump with accessories day 2,000.00 0.28 560.00 197.88
Saw cutter day 2,000.00 0.02 40.00 14.13
Item Type Labour 0.00
Labour for fixing and removing sq. metre 150.00 4.00 600.00 212.01
Masons day 700.00 0.48 336.00 118.73
Semi-skilled labourer day 500.00 1.40 700.00 247.35
Unskilled labourer day 450.00 2.80 1,260.00 445.23
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,498.23
Diesel/Fuel Ltr 65.00 3.00 195.00 68.90
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,763.25
Admixture Liter 200.00 2.20 440.00 155.48
Cost of wooden shutter for concrete using 6 times sq. metre 125.00 4.00 500.00 176.68
Nail kg 125.00 0.50 62.50 22.08
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.78
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.86 628.22

Expansion/Contraction/Construction Joints, Joint filler, Seperator joint


sealent etc (excluding dowel bar, tie bar and other reinforceent). L.S 200.00
Basic Unit Price of Specification Item : 13,148.93
Plus Profit at 5% 657.45
Plus Overhead at 3.00% 394.47
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Sub-Total : 14,200.84
Plus Tax & VAT at 16.2791% 2,311.76
Total Unit Price of Specification Item : 16,512.60
16,513.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/01(b)
Item Name Cement Concrete Pavement (Concrete Class - 25) (Batching Plant without Concrete Paver).
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck/ Transit mixure truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour cost for fixing and Removal of shutter sq. metre 150.00 4.00 600.00 211.86
Foreman/skilled labour 850.00 0.08 68.00 24.01
Masons day 700.00 0.16 112.00 39.55
Semi-skilled labourer day 500.00 0.48 240.00 84.75
Unskilled labourer day 450.00 1.00 450.00 158.90
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 10.00 650.00 229.52
Cement tonne 9,000.00 1.10 9,900.00 3,495.76
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Admixture Liter 200.00 2.20 440.00 155.37
Cost of wooden shutter for concrete using 6 times sq. metre 150.00 4.00 484.00 170.90
Nail kg 125.00 0.50 62.50 22.07
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.42
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint sealent etc L.S 200.00
(excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 14,239.49
Plus Profit at 5% 711.97
Plus Overhead at 3.00% 427.18

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Sub-Total : 15,378.65
Plus Tax & VAT at 16.2791% 2,503.50
Total Unit Price of Specification Item : 17,882.15
17,882.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/01(c)
Item Name Cement Concrete Pavement (Concrete Class - 25) (Batching Plant with Concrete Paver).
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Concrete Paver day 30,000.00 0.02 600.00 211.86
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 4.00 600.00 211.86
Foreman/skilled labour 850.00 0.04 34.00 12.01
Masons day 700.00 0.08 56.00 19.77
Semi-skilled labourer day 500.00 0.20 100.00 35.31
Unskilled labourer day 450.00 0.40 180.00 63.56
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 20.00 1,300.00 459.04
Cement tonne 9,000.00 1.10 9,900.00 3,495.76
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Hire cost of shuttering material for concreting-6 times sq. metre 125.00 4.00 500.00 176.55
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.42
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
L.S
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint sealent etc 200.00
(excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 14,509.97
Plus Profit at 5% 725.50
Plus Overhead at 3.00% 435.30
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Sub-Total : 15,670.76
Plus Tax & VAT at 16.2791% 2,551.05
Total Unit Price of Specification Item : 18,221.82
18,222.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/01(d)
Item Name Precast RCC Pavement slab (Concrete Class -25) (Batching Plant)
Unit of Measurement cu metre (All Prices Are in Taka)
Quantity for Estimation 2.68
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 746.27
Concrete Poker Vibrator day 600.00 0.17 102.00 38.06
Pay loader day 12,000.00 0.05 600.00 223.88
Agitator Truck/ Transit mixure truck day 12,000.00 0.04 480.00 179.10
Lifting Crane (Capacity-25 MT) day 40,000.00 0.04 1,600.00 597.01
Flat bed trailor (Capacity-30 MT) day 25,000.00 0.02 500.00 186.57
Tining machine day 5,000.00 0.06 300.00 111.94
Finisher roller day 5,000.00 0.06 300.00 111.94
Water pump with accessories day 2,000.00 0.28 560.00 208.96
Saw cutter day 2,000.00 0.02 40.00 14.93
Item Type Labour 0.00
Labour for fixing/Removal of prefabricated steel shutter sq. metre 200.00 4.00 800.00 298.51
Foreman/skilled labour 850.00 0.16 136.00 50.75
Masons day 700.00 0.24 168.00 62.69
Semi-skilled labourer day 500.00 0.48 240.00 89.55
Unskilled labourer day 450.00 1.00 450.00 167.91
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 30.00 1,950.00 727.61
Cement tonne 9,000.00 1.10 9,900.00 3,694.03
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 6,085.82
Cost of prefabricated steel shutter (using 50 times) sq. metre 900.00 4.00 3,600.00 1,343.28
Lifting anchorage No. 500.00 4.00 2,000.00 746.27
Admixture Liter 200.00 2.20 440.00 164.18
Nail kg 125.00 0.50 62.50 23.32
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 545.71
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
Provision for Joints, Joint filler, Seperator, Epoxy, Grout, Sealant etc. L.S 500.00
Basic Unit Price of Specification Item : 17,546.40
Plus Profit at 5% 877.32

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Plus Overhead at 3.00% 526.39
Sub-Total : 18,950.11
Plus Tax & VAT at 16.2791% 3,084.90
Total Unit Price of Specification Item : 22,035.02
22,035.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/02(a)
Item Name Cement Concrete Pavement (Concrete Class -30) (Concrete Mixure)
Unit of Measurement cu metre (All Prices Are in Taka)
Quantity for Estimation 2.83
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.170 339.84 120.00
Concrete Poker Vibrator day 600.00 0.170 102.00 36.02
Small hand tools (1) day 50.00 2.00 100.00 35.31
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing and removing sq. metre 150.00 4.00 600.00 211.86
Masons day 700.00 0.48 336.00 118.64
Semi-skilled labourer day 500.00 1.40 700.00 247.18
Unskilled labourer day 450.00 2.80 1,260.00 444.92
Item Type Material 0.00
Cement tonne 9,000.00 1.24 11,160.00 3,940.68
Diesel/Fuel Ltr 65.00 3.00 195.00 68.86
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.41 16,870.00 5,956.92
Cost of wooden shutter for concrete using 6 times sq. metre 150.00 4.00 600.00 211.86
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>1.8 cu. metre 1,250.00 1.21 1,512.50 534.07
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
L.S 200.00
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint
sealent etc (excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 13,835.83
Plus Profit at 5% 691.79
Plus Overhead at 3.00% 415.07
Sub-Total : 14,942.70
Plus Tax & VAT at 16.2791% 2,432.53

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Total Unit Price of Specification Item : 17,375.23
17,375.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/02(b)
Item Name Cement Concrete Pavement (Concrete Class -30) (Batching Plant without Concrete Paver).
Unit of Measurement cu metre (All Prices Are in Taka)
Quantity for Estimation 2.83
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck/ Transit mixure truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 100.00 4.00 400.00 141.24
Foreman/skilled labour 850.00 0.08 68.00 24.01
Masons day 600.00 0.16 96.00 33.90
Semi-skilled labourer day 450.00 0.48 216.00 76.27
Unskilled labourer day 400.00 1.00 400.00 141.24
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 10.00 650.00 229.52
Cement tonne 9,000.00 1.24 11,160.00 3,940.68
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.41 16,870.00 5,956.92
Cost of wooden shutter for concrete using 6 times sq. metre 150.00 4.00 600.00 211.86
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>1.8 cu. metre 1,250.00 1.21 1,512.50 534.07
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
L.S 200.00
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint sealent etc
(excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 14,838.36
Plus Profit at 5% 741.92
Plus Overhead at 3.00% 445.15
Sub-Total : 16,025.43

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Plus Tax & VAT at 16.2791% 2,608.79
Total Unit Price of Specification Item : 18,634.22
18,634.00
Assumption : Considering per day's (8 hour) production of 75 cum, using water pump for curing by ponding, cutting grooves by saw cutter.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/02(c)
Item Name Cement Concrete Pavement (Concrete Class -30) (Batching Plant with Concrete Paver).
Unit of Measurement cu metre (All Prices Are in Taka)
Quantity for Estimation 2.83
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Concrete Paver day 30,000.00 0.02 600.00 211.86
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 100.00 4.00 400.00 141.24
Foreman/skilled labour 850.00 0.04 34.00 12.01
Masons day 600.00 0.08 48.00 16.95
Semi-skilled labourer day 450.00 0.20 90.00 31.78
Unskilled labourer day 400.00 0.40 160.00 56.50
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 20.00 1,300.00 459.04
Cement tonne 9,000.00 1.24 11,160.00 3,940.68
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.41 16,870.00 5,956.92
Hire cost of shuttering material for concreting-6 times sq. metre 150.00 4.00 600.00 211.86
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>1.8 cu. metre 1,250.00 1.21 1,512.50 534.07
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint L.S
200.00
sealent etc (excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 15,121.55
Plus Profit at 5% 756.08
Plus Overhead at 3.00% 453.65

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Sub-Total : 16,331.27
Plus Tax & VAT at 16.2791% 2,658.58
Total Unit Price of Specification Item : 18,989.85
Assumption : 18,990.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/02(d)
Item Name Precast RCC Pavement slab (Concrete Class -30) (Batching Plant)
Unit of Measurement cu metre (All Prices Are in Taka)
Quantity for Estimation 2.68
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 746.27
Concrete Poker Vibrator day 600.00 0.17 102.00 38.06
Pay loader day 12,000.00 0.05 600.00 223.88
Agitator Truck/ Transit mixure truck day 12,000.00 0.04 480.00 179.10
Lifting Crane (Capacity-25 MT) day 40,000.00 0.04 1,600.00 597.01
Flat bed trailor (Capacity-30 MT) day 25,000.00 0.02 500.00 186.57
Tining machine day 5,000.00 0.06 300.00 111.94
Finisher roller day 5,000.00 0.06 300.00 111.94
Water pump with accessories day 2,000.00 0.28 560.00 208.96
Saw cutter day 2,000.00 0.02 40.00 14.93
Item Type Labour 0.00
Labour for fixing/Removal of prefabricated steel shutter sq. metre 200.00 4.00 800.00 298.51
Foreman/skilled labour 850.00 0.16 136.00 50.75
Masons day 700.00 0.24 168.00 62.69
Semi-skilled labourer day 500.00 0.48 240.00 89.55
Unskilled labourer day 450.00 1.00 450.00 167.91
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 30.00 1,950.00 727.61
Cement tonne 9,000.00 1.24 11,160.00 4,164.18
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.41 16,870.00 6,294.78
Cost of prefabricated steel shutter (using 50 times) sq. metre 900.00 4.00 3,600.00 1,343.28
Lifting anchorage No. 500.00 4.00 2,000.00 746.27
Admixture Liter 200.00 2.20 440.00 164.18
Nail kg 125.00 0.50 62.50 23.32
Sand FM>1.8 cu. metre 1,250.00 1.21 1,512.50 564.37
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
Provision for Joints, Joint filler, Seperator, Epoxy, Grout, Sealant etc. L.S 500.00
Basic Unit Price of Specification Item : 18,244.16
Plus Profit at 5% 912.21
Plus Overhead at 3.00% 547.32
Sub-Total : 19,703.70
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Plus Tax & VAT at 16.2791% 3,207.58
Total Unit Price of Specification Item : 22,911.27
22,911.00

Assumption : Panel size: 3.66 m x 3.66 m x 0.20 m . Production capacity: 28 nos casted per day ( 8 hour), Rainforcement and Dowel bars not included but all other
accessories are included. Loading, unloding, transportation, lifting arrangement, placement, fitting-fixing, receiving end block supply, fitting, fixing, use of

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/03(a)
Item Name Cement Concrete Pavement (Concrete Class -35) (Concrete Mixure)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.170 339.84 120.00
Concrete Poker Vibrator day 600.00 0.170 102.00 36.02
Small hand tools (1) day 50.00 2.00 100.00 35.31
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing and removing sq. metre 200.00 4.00 800.00 282.49
Masons day 700.00 0.48 336.00 118.64
Semi-skilled labourer day 500.00 1.40 700.00 247.18
Unskilled labourer day 450.00 2.80 1,260.00 444.92
Item Type Material 0.00
Cement tonne 9,000.00 1.36 12,240.00 4,322.03
Diesel/Fuel Ltr 65.00 3.00 195.00 68.86
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Cost of wooden shutter for concrete using 6 times sq. metre 125.00 4.00 500.00 176.55
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>2.5 cu. metre 1,250.00 1.12 1,400.00 494.35
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
L.S 200.00
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint
sealent etc (excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 14,015.03
Plus Profit at 5% 700.75
Plus Overhead at 3.00% 420.45
Sub-Total : 15,136.23
Plus Tax & VAT at 16.2791% 2,464.04

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Total Unit Price of Specification Item : 17,600.27
17,600.00
Assumption : Considering per day's (8 hour) production of 50 cum, using water pump for curing by ponding, cutting grooves by saw cutter.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/03(b)
Item Name Cement Concrete Pavement (Concrete Class -35) (Batching Plant without Concrete Paver).
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck/ Transit mixure truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 100.00 4.00 400.00 141.24
Foreman/skilled labour 850.00 0.08 68.00 24.01
Masons day 600.00 0.16 96.00 33.90
Semi-skilled labourer day 450.00 0.48 216.00 76.27
Unskilled labourer day 400.00 1.00 400.00 141.24
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 10.00 650.00 229.52
Cement tonne 9,000.00 1.36 12,240.00 4,322.03
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Cost of wooden shutter for concrete using 6 times sq. metre 150.00 4.00 600.00 211.86
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>2.5 cu. metre 1,250.00 1.12 1,400.00 494.35
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint L.S 200.00
sealent etc (excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 14,982.25
Plus Profit at 5% 749.11
Plus Overhead at 3.00% 449.47

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Sub-Total : 16,180.83
Plus Tax & VAT at 16.2791% 2,634.09
Total Unit Price of Specification Item : 18,814.92
18,815.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/03(c )
Item Name Cement Concrete Pavement (Concrete Class -35) (Batching Plant with Concrete Paver).
Unit of Measurement cu metre (All Prices Are in Taka)
Quantity for Estimation 2.83
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Concrete Paver day 30,000.00 0.02 600.00 211.86
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck/ Transit mixure truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 100.00 4.00 400.00 141.24
Foreman/skilled labour 850.00 0.04 34.00 12.01
Masons day 600.00 0.08 48.00 16.95
Semi-skilled labourer day 450.00 0.20 90.00 31.78
Unskilled labourer day 400.00 0.40 160.00 56.50
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 20.00 1,300.00 459.04
Cement tonne 9,000.00 1.36 12,240.00 4,322.03
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Hire cost of shuttering material for concreting-6 times sq. metre 150.00 4.00 600.00 211.86
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>2.5 cu. metre 1,250.00 1.12 1,400.00 494.35
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint L.S 200.00
sealent etc (excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 15,265.44
Plus Profit at 5% 763.27
Plus Overhead at 3.00% 457.96

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Sub-Total : 16,486.68
Plus Tax & VAT at 16.2791% 2,683.88
Total Unit Price of Specification Item : 19,170.55
19,171.00

Assumption : Considering per day's (8 hour) production of 142 cum, using water pump & water bowser for curing by ponding, cutting grooves by saw cutter.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/03(d)
Item Name Precast RCC Pavement slab (Concrete Class -35) (Batching Plant)
Unit of Measurement cu metre (All Prices Are in Taka)
Quantity for Estimation 2.68
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 746.27
Concrete Poker Vibrator day 600.00 0.17 102.00 38.06
Pay loader day 12,000.00 0.05 600.00 223.88
Agitator Truck/ Transit mixure truck day 12,000.00 0.04 480.00 179.10
Lifting Crane (Capacity-25 MT) day 40,000.00 0.04 1,600.00 597.01
Flat bed trailor (Capacity-30 MT) day 25,000.00 0.02 500.00 186.57
Tining machine day 5,000.00 0.06 300.00 111.94
Finisher roller day 5,000.00 0.06 300.00 111.94
Water pump with accessories day 2,000.00 0.28 560.00 208.96
Saw cutter day 2,000.00 0.02 40.00 14.93
Item Type Labour 0.00
Labour for fixing/Removal of prefabricated steel shutter sq. metre 200.00 4.00 800.00 298.51
Foreman/skilled labour 850.00 0.16 136.00 50.75
Masons day 700.00 0.24 168.00 62.69
Semi-skilled labourer day 500.00 0.48 240.00 89.55
Unskilled labourer day 450.00 1.00 450.00 167.91
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 30.00 1,950.00 727.61
Cement tonne 9,000.00 1.36 12,240.00 4,567.16
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 6,085.82
Cost of prefabricated steel shutter (using 50 times) sq. metre 900.00 4.00 3,600.00 1,343.28
Lifting anchorage No. 500.00 4.00 2,000.00 746.27
Admixture Liter 200.00 2.20 440.00 164.18
Nail kg 125.00 0.50 62.50 23.32
Sand FM>2.5 cu. metre 1,850.00 1.12 2,072.00 773.13
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
Provision for Joints, Joint filler, Seperator, Epoxy, Grout, Sealant etc. L.S 500.00
Basic Unit Price of Specification Item : 18,646.96
Plus Profit at 5% 932.35
Plus Overhead at 3.00% 559.41
Sub-Total : 20,138.72
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Plus Tax & VAT at 16.2791% 3,278.40
Total Unit Price of Specification Item : 23,417.11
23,417.00
Assumption : Panel size: 3.66 m x 3.66 m x 0.20 m . Production capacity: 28 nos casted per day ( 8 hour), Rainforcement and Dowel bars not included but all other
accessories are included. Loading, unloding, transportation, lifting arrangement, placement, fitting-fixing, receiving end block supply, fitting, fixing, use of

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/03(e)
Item Name Cement Concrete Pavement (Concrete Class -40) (Batching Plant without Concrete Paver).
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck/ Transit mixure truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 100.00 4.00 400.00 141.24
Foreman/skilled labour 850.00 0.08 68.00 24.01
Masons day 600.00 0.16 96.00 33.90
Semi-skilled labourer day 450.00 0.48 216.00 76.27
Unskilled labourer day 400.00 1.00 400.00 141.24
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 10.00 650.00 229.52
Cement tonne 9,000.00 1.42 12,780.00 4,512.71
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Cost of wooden shutter for concrete using 6 times sq. metre 150.00 4.00 600.00 211.86
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>2.5 cu. metre 1,250.00 1.12 1,400.00 494.35
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint L.S 200.00
sealent etc (excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 15,172.93
Plus Profit at 5% 758.65
Plus Overhead at 3.00% 455.19

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Sub-Total : 16,386.76
Plus Tax & VAT at 16.2791% 2,667.61
Total Unit Price of Specification Item : 19,054.37
19,054.00
Assumption : Panel size: 3.66 m x 3.66 m x 0.20 m . Production capacity: 28 nos casted per day ( 8 hour), Rainforcement and Dowel bars not included but all other
accessories are included. Loading, unloding, transportation, lifting arrangement, placement, fitting-fixing, receiving end block supply, fitting, fixing, use of

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 03/15/03(f)
Item Name Cement Concrete Pavement (Concrete Class -40) (Batching Plant with Concrete Paver).
Unit of Measurement cu metre (All Prices Are in Taka)
Quantity for Estimation 2.83
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Concrete Paver day 30,000.00 0.02 600.00 211.86
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck/ Transit mixure truck day 12,000.00 0.12 1,440.00 508.47
Pump with pipe and accessories day 10,000.00 0.05 500.00 176.55
Water bowser for curing day 7,000.00 0.28 1,960.00 692.09
Water pump with accessories day 2,000.00 0.28 560.00 197.74
Saw cutter day 2,000.00 0.02 40.00 14.12
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 100.00 4.00 400.00 141.24
Foreman/skilled labour 850.00 0.04 34.00 12.01
Masons day 600.00 0.08 48.00 16.95
Semi-skilled labourer day 450.00 0.20 90.00 31.78
Unskilled labourer day 400.00 0.40 160.00 56.50
Item Type Material 0.00
Diesel/Fuel Ltr 65.00 20.00 1,300.00 459.04
Cement tonne 9,000.00 1.42 12,780.00 4,512.71
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Hire cost of shuttering material for concreting-6 times sq. metre 150.00 4.00 600.00 211.86
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM>2.5 cu. metre 1,250.00 1.12 1,400.00 494.35
High yield reinforcing bars (Dowel bar, tie bar) kg 72.62 24.48 1,777.57 628.12
L.S
Expansion/Contraction/Construction Joints, Joint filler, Seperator joint 200.00
sealent etc (excluding dowel bar, tie bar and other reinforceent).
Basic Unit Price of Specification Item : 15,456.12
Plus Profit at 5% 772.81
Plus Overhead at 3.00% 463.68
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Sub-Total : 16,692.61
Plus Tax & VAT at 16.2791% 2,717.40
Total Unit Price of Specification Item : 19,410.01
19,410.00

Assumption : Considering per day's (8 hour) production of 142 cum, using water pump & water bowser for curing by ponding, cutting grooves by saw cutter.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Division 4 - Foundation Works

Item Code 04/01/01a


Item Name Bored Cast in Place Piles (dia. 400mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 25.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bored Pile Equipment (400mm) day 6,000.00 1.00 6,000.00 240.00
Concrete Mixer (7/5) day 2,000.00 1.00 2,000.00 80.00
Pile Integrity Test No. 1,000.00 1.00 1,000.00 40.00
Item Type Labour 0.00 0.00
Foreman day 850.00 0.50 425.00 17.00
Masons day 700.00 1.00 700.00 28.00
Semi-skilled labourer day 500.00 4.00 2,000.00 80.00
Un-skilled labourer day 450.00 6.00 2,700.00 108.00
Item Type Material 0.00 0.00
Bentonite (50kg) bag 1,000.00 3.00 3,000.00 120.00
Cement tonne 9,000.00 1.20 10,800.00 432.00
Coarse Sand FM>2.5 cu. metre 1,850.00 1.28 2,368.00 94.72
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.57 17,990.00 719.60
Basic Unit Price of Specification Item : 1,959.32
Plus Profit at 5% 97.97
Plus Overhead at 3.00% 58.78
Sub-Total : 2,116.07
Plus Tax & VAT at 16.2791% 344.48
Total Unit Price of Specification Item : 2,460.54
2,461.00
Assumption : The diameter and length of the piles will be dependent on the individual bridge design and must be given on the contract drawings. For this rate exercise a
pile length of 25m has been considered with diameter of 400mm.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/01b
Item Name Bored Cast in Place Piles [dia 600mm]
Unit of Measurement Lin. Metre
Quantity for Estimation 11.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bored Pile Equipment (600mm) day 6,000.00 1.00 6,000.00 545.45
Concrete Mixer (7/5) day 2,000.00 1.00 2,000.00 181.82
Pile Integrity Test No. 1,000.00 1.00 1,000.00 90.91
Item Type Labour 0.00 0.00
Foreman day 850.00 0.50 425.00 38.64
Masons day 700.00 1.00 700.00 63.64
Semi-skilled labourer day 500.00 4.00 2,000.00 181.82
Un-skilled labourer day 450.00 6.00 2,700.00 245.45
Item Type Material 0.00 0.00
Bentonite (50kg) bag 1,000.00 3.00 3,000.00 272.73
Cement tonne 9,000.00 1.20 10,800.00 981.82
Coarse Sand FM>2.5 cu. metre 1,850.00 1.28 2,368.00 215.27
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.57 17,990.00 1,635.45
Basic Unit Price of Specification Item : 4,453.00
Plus Profit at 5% 222.65
Plus Overhead at 3.00% 133.59
Sub-Total : 4,809.24
Plus Tax & VAT at 16.2791% 782.90
Total Unit Price of Specification Item : 5,592.14
5,592.00
Assumption : The length and diameter of the piles is 11m by 600mm dia.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/01c
Item Name Bored pile cast in place piles (dia 750 mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 7.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bored pile equipment (750 mm) day 6,500.00 1.00 6,500.00 928.57
Concrete Mixer (7/5) day 2,000.00 1.00 2,000.00 285.71
Pile Integrity Test No. 1,000.00 1.00 1,000.00 142.86
Item Type Labour 0.00 0.00
Foreman day 850.00 0.50 425.00 60.71
Masons day 700.00 1.00 700.00 100.00
Semi-skilled labourer day 500.00 4.00 2,000.00 285.71
Un-skilled labourer day 450.00 6.00 2,700.00 385.71
Item Type Material 0.00 0.00
Bentonite (50kg) bag 1,000.00 3.00 3,000.00 428.57
Cement tonne 9,000.00 1.20 10,800.00 1,542.86
Coarse Sand FM>2.5 cu. metre 1,850.00 1.25 2,316.20 330.89
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.53 17,710.00 2,530.00
Basic Unit Price of Specification Item : 7,021.60
Plus Profit at 5% 351.08
Plus Overhead at 3.00% 210.65
Sub-Total : 7,583.33
Plus Tax & VAT at 16.2791% 1,234.50
Total Unit Price of Specification Item : 8,817.82
8,818.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/01d
Item Name Bored cast in place Piles (dia 900mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 4.60 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bored Pile equipment (900mm) day 7,000.00 1.00 7,000.00 1,521.74
Concrete Mixer (7/5) day 2,000.00 1.00 2,000.00 434.78
Pile Integrity Test No. 1,000.00 1.00 1,000.00 217.39
Item Type Labour 0.00 0.00
Foreman day 850.00 0.50 425.00 92.39
Masons day 700.00 1.00 700.00 152.17
Semi-skilled labourer day 500.00 4.00 2,000.00 434.78
Un-skilled labourer day 450.00 6.00 2,700.00 586.96
Item Type Material 0.00 0.00
Bentonite (50kg) bag 1,000.00 3.00 3,000.00 652.17
Cement tonne 9,000.00 1.15 10,350.00 2,250.00
Coarse Sand FM>2.5 cu. metre 1,850.00 1.19 2,201.50 478.59
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.39 16,716.00 3,633.91
Basic Unit Price of Specification Item : 10,454.89
Plus Profit at 5% 522.74
Plus Overhead at 3.00% 313.65
Sub-Total : 11,291.28
Plus Tax & VAT at 16.2791% 1,838.12
Total Unit Price of Specification Item : 13,129.40
13,129.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/01e
Item Name Bored cast in Place Piles (dia 1000mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 4.25 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bored Pile equipment (1000mm) day 7,000.00 1.00 7,000.00 1,647.06
Concrete Mixer (7/5) day 2,000.00 1.00 2,000.00 470.59
Pile Integrity Test No. 1,000.00 1.00 1,000.00 235.29
Item Type Labour 0.00 0.00
Foreman day 850.00 0.50 425.00 100.00
Masons day 700.00 1.00 700.00 164.71
Semi-skilled labourer day 500.00 4.00 2,000.00 470.59
Un-skilled labourer day 450.00 6.00 2,700.00 635.29
Item Type Material 0.00 0.00
Bentonite (50kg) bag 1,000.00 3.00 3,000.00 705.88
Cement tonne 9,000.00 1.30 11,700.00 2,752.94
Coarse Sand FM>2.5 cu. metre 1,850.00 1.36 2,516.00 592.00
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.73 19,096.00 4,493.18
Basic Unit Price of Specification Item : 12,267.53
Plus Profit at 5% 613.38
Plus Overhead at 3.00% 368.03
Sub-Total : 13,248.93
Plus Tax & VAT at 16.2791% 2,156.80
Total Unit Price of Specification Item : 15,405.73
15,406.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/01f
Item Name Bored cast in Place Piles (dia 1200mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 2.87 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bored Pile equipment (1200mm) day 7,000.00 1.00 7,000.00 2,439.02
Concrete Mixer (7/5) day 2,000.00 1.00 2,000.00 696.86
Pile Integrity Test No. 1,000.00 1.00 1,000.00 348.43
Item Type Labour 0.00 0.00
Foreman day 850.00 0.50 425.00 148.08
Masons day 700.00 1.00 700.00 243.90
Semi-skilled labourer day 500.00 4.00 2,000.00 696.86
Un-skilled labourer day 450.00 6.00 2,700.00 940.77
Item Type Material 0.00 0.00
Bentonite (50kg) bag 1,000.00 3.00 3,000.00 1,045.30
Cement tonne 9,000.00 1.30 11,700.00 4,076.65
Coarse Sand FM>2.5 cu. metre 1,850.00 1.36 2,516.00 876.66
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.73 19,096.00 6,653.66
Basic Unit Price of Specification Item : 18,166.20
Plus Profit at 5% 908.31
Plus Overhead at 3.00% 544.99
Sub-Total : 19,619.50
Plus Tax & VAT at 16.2791% 3,193.87
Total Unit Price of Specification Item : 22,813.37
22,813.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/01g
Item Name Bored cast in Place Piles (dia 1500mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 1.61 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bored Pile equipment (1500mm) day 7,000.00 1.00 7,000.00 4,347.83
Concrete Mixer (7/5) day 2,000.00 1.00 2,000.00 1,242.24
Pile Integrity Test No. 1,000.00 1.00 1,000.00 621.12
Item Type Labour 0.00 0.00
Foreman day 850.00 0.50 425.00 263.98
Masons day 700.00 1.00 700.00 434.78
Semi-skilled labourer day 500.00 4.00 2,000.00 1,242.24
Un-skilled labourer day 450.00 6.00 2,700.00 1,677.02
Item Type Material 0.00 0.00
Bentonite (50kg) bag 1,000.00 3.00 3,000.00 1,863.35
Cement tonne 9,000.00 1.30 11,700.00 7,267.08
Coarse Sand FM>2.5 cu. metre 1,850.00 1.36 2,516.00 1,562.73
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.73 19,096.00 11,860.87
Basic Unit Price of Specification Item : 32,383.23
Plus Profit at 5% 1,619.16
Plus Overhead at 3.00% 971.50
Sub-Total : 34,973.89
Plus Tax & VAT at 16.2791% 5,693.42
Total Unit Price of Specification Item : 40,667.31
40,667.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/04
Item Name High Yield Deformed Steel Reinforcing Bars
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 14.00 700.00 700.00
Item Type Labour 0.00 0.00
Semi-skilled labourer day 500.00 5.00 2,500.00 2,500.00
Steel fixers day 700.00 4.00 2,800.00 2,800.00
Unskilled labourer day 450.00 5.00 2,250.00 2,250.00
Item Type Material 0.00 0.00
G.I wire, nails etc kg 120.00 10.00 1,200.00 1,200.00
Reinforcing bar grade 60 tonne 62,500.00 1.03 64,375.00 64,375.00
Basic Unit Price of Specification Item : 73,825.00
Plus Profit at 5% 3,691.25
Plus Overhead at 3.00% 2,214.75
Sub-Total : 79,731.00
Plus Tax & VAT at 16.2791% 12,979.46
Total Unit Price of Specification Item : 92,710.46
92,710.00

Assumption : Same labour as for Item 4/1/3 will normally apply.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05a
Item Name Permanent steel Casing ( 6mm thick ,dia 400mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 177.47 1,774.70 591.57
Cost for driving steel casing 6mm thick 400mm dia lin. metre 600.00 3.00 1,800.00 600.00
Item Type Material 0.00 0.00
6mm thick steel plate kg 85.00 177.47 15,084.95 5,028.32
Paint ltr 250.00 1.82 455.00 151.67
Basic Unit Price of Specification Item : 6,371.55
Plus Profit at 5% 318.58
Plus Overhead at 3.00% 191.15
Sub-Total : 6,881.27
Plus Tax & VAT at 16.2791% 1,120.21
Total Unit Price of Specification Item : 8,001.48
8,001.00

Assumption : The rate will be dependent on the particular bridge design and details of permanent casing must be shown on the drawings.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05b
Item Name Permanent steel casing (6mm thick,dia 600mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 266.20 2,662.00 887.33
Cost for driving steel casing 6mm thick 600mm dia lin. metre 600.00 3.00 1,800.00 600.00
Item Type Material 0.00 0.00
6mm thick steel plate kg 85.00 266.20 22,627.00 7,542.33
Paint ltr 250.00 2.73 682.50 227.50
Basic Unit Price of Specification Item : 9,257.17
Plus Profit at 5% 462.86
Plus Overhead at 3.00% 277.72
Sub-Total : 9,997.74
Plus Tax & VAT at 16.2791% 1,627.54
Total Unit Price of Specification Item : 11,625.28
11,625.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05c
Item Name Permanent steel casing (6mm thick, dia750mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 332.20 3,322.00 1,107.33
Cost for driving steel casing 6mm thick 750mm dia lin. metre 700.00 3.00 2,100.00 700.00
Item Type Material 0.00 0.00
6mm thick steel plate kg 85.00 332.20 28,237.00 9,412.33
Paint ltr 250.00 3.64 910.00 303.33
Basic Unit Price of Specification Item : 11,523.00
Plus Profit at 5% 576.15
Plus Overhead at 3.00% 345.69
Sub-Total : 12,444.84
Plus Tax & VAT at 16.2791% 2,025.90
Total Unit Price of Specification Item : 14,470.74
14,471.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05d
Item Name Permanent steel casing (10mm thick, 600mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 443.68 4,436.80 1,478.93
Cost for driving steel casing 10mm thick 600mm dia lin. metre 600.00 3.00 1,800.00 600.00
Item Type Material 0.00 0.00
10mm thick steel plate kg 85.00 443.68 37,712.80 12,570.93
Paint ltr 250.00 2.73 682.50 227.50
Basic Unit Price of Specification Item : 14,877.37
Plus Profit at 5% 743.87
Plus Overhead at 3.00% 446.32
Sub-Total : 16,067.56
Plus Tax & VAT at 16.2791% 2,615.65
Total Unit Price of Specification Item : 18,683.20
18,683.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05e
Item Name Permanent steel casing (10mm thick, 750mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 554.60 5,546.00 1,848.67
Cost for driving 10mm steel casing (750mm dia) lin. metre 700.00 3.00 2,100.00 700.00
Item Type Material 0.00 0.00
10mm thick steel plate kg 85.00 554.60 47,141.00 15,713.67
Paint ltr 250.00 3.64 910.00 303.33
Basic Unit Price of Specification Item : 18,565.67
Plus Profit at 5% 928.28
Plus Overhead at 3.00% 556.97
Sub-Total : 20,050.92
Plus Tax & VAT at 16.2791% 3,264.10
Total Unit Price of Specification Item : 23,315.02
23,315.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05f
Item Name Permanent steel casing (10mm thick, 900mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 665.52 6,655.20 2,218.40
Cost for driving (10mm thick) steel casing 900mm dia lin. metre 800.00 3.00 2,400.00 800.00
Item Type Material 0.00 0.00
10mm thick steel plate kg 85.00 665.52 56,569.20 18,856.40
Paint ltr 250.00 4.09 1,022.50 340.83
Basic Unit Price of Specification Item : 22,215.63
Plus Profit at 5% 1,110.78
Plus Overhead at 3.00% 666.47
Sub-Total : 23,992.88
Plus Tax & VAT at 16.2791% 3,905.82
Total Unit Price of Specification Item : 27,898.70
27,899.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05g
Item Name Permanent steel casing (10 mm thick, 1000mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 739.47 7,394.70 2,464.90
Cost for driving (10mm thick) steel casing 1000mm dia lin. metre 800.00 3.00 2,400.00 800.00
Item Type Material 0.00 0.00
10mm thick steel plate kg 85.00 739.47 62,854.95 20,951.65
Paint ltr 250.00 4.55 1,136.50 378.83
Basic Unit Price of Specification Item : 24,595.38
Plus Profit at 5% 1,229.77
Plus Overhead at 3.00% 737.86
Sub-Total : 26,563.01
Plus Tax & VAT at 16.2791% 4,324.21
Total Unit Price of Specification Item : 30,887.22
30,887.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05h
Item Name Permanent steel casing (10 mm thick, 1200mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 887.82 8,878.20 2,959.40
Cost for driving (10mm thick) steel casing 1200mm dia lin. metre 900.00 3.00 2,700.00 900.00
Item Type Material 0.00 0.00
10mm thick steel plate kg 85.00 887.82 75,464.70 25,154.90
Paint ltr 250.00 5.50 1,375.00 458.33
Basic Unit Price of Specification Item : 29,472.63
Plus Profit at 5% 1,473.63
Plus Overhead at 3.00% 884.18
Sub-Total : 31,830.44
Plus Tax & VAT at 16.2791% 5,181.70
Total Unit Price of Specification Item : 37,012.14
37,012.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/01/05i
Item Name Permanent steel casing (10 mm thick, 1500mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 3.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour, Tools and Equipment
Cost for cutting,bending , welding & painting steel plate kg 10.00 1,109.78 11,097.80 3,699.27
Cost for driving (10mm thick) steel casing 1500mm dia lin. metre 900.00 3.00 2,700.00 900.00
Item Type Material 0.00 0.00
10mm thick steel plate kg 85.00 1,109.78 94,331.30 31,443.77
Paint ltr 250.00 7.25 1,812.50 604.17
Basic Unit Price of Specification Item : 36,647.20
Plus Profit at 5% 1,832.36
Plus Overhead at 3.00% 1,099.42
Sub-Total : 39,578.98
Plus Tax & VAT at 16.2791% 6,443.09
Total Unit Price of Specification Item : 46,022.07
46,022.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/02/01a
Item Name Driven Pre-cast Piles (a) 300x300mm
Unit of Measurement Lin. Metre (All Prices Are in Taka)
Quantity for Estimation 15.00
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.13 250.00 16.67
Concrete Poker Vibrator day 600.00 0.13 75.00 5.00
Mobilization/Demobilization for pre cast pile driving Equipment lump sum 1,500.00 1.00 1,500.00 100.00
Pile Diving Equipment (concrete piles) day 4,500.00 0.50 2,250.00 150.00
Small hand tools (1) day 50.00 7.75 387.50 25.83
Water Pump day 1,200.00 0.13 150.00 10.00
Item Type Labour 0.00
Foreman day 850.00 0.50 425.00 28.33
Labour for manufacturing pre-cast pile shutter using 16 times sq. metre 30.00 4.91 9.20 0.61
Masons day 700.00 1.38 962.50 64.17
Pre-cast pile shutter fixing and removing sq. metre 90.00 4.91 441.81 29.45
Semi-skilled labourer day 500.00 0.38 187.50 12.50
Unskilled labourer day 450.00 7.25 3,262.50 217.50
Item Type Material 0.00
Angle Iron (b) 38x38x5mm for pre cast pile shutter using 16 times tonne 60,000.00 0.13 487.50 32.50
Cement tonne 9,000.00 0.52 4,725.00 315.00
Coarse Sand FM>2.5 cu. metre 1,850.00 0.55 1,017.50 67.83
Cost of platform (pre-cast pile) using 5 times sq. metre 60.00 6.36 76.32 5.09
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 1.10 7,700.00 513.33
Diesel ltr 65.00 30.00 1,950.00 130.00
F I bar (b) 38x5mm for pre cast pile shutter using 16 times tonne 60,000.00 0.01 26.25 1.75
Nut bolt for pre cast pile shutter using 16 times kg 100.00 1.09 6.81 0.45
Polythene sheet sq. metre 18.00 6.80 122.40 8.16
Pre-cast pile shoe (0.3x0.3m pile) No 300.00 1.00 300.00 20.00
Steel Plate 2mm for pre cast pile shutter using 16 time tonne 85,000.00 0.08 425.00 28.33
Basic Unit Price of Specification Item : 1,782.52
Plus Profit at 5% 89.13
Plus Overhead at 3.00% 53.48
Sub-Total : 1,925.12
Plus Tax & VAT at 16.2791% 313.39

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Total Unit Price of Specification Item : 2,238.51
2,239.00
Assumption : As with Cast insitu Piles the precise type of piles (length, x-sectional area, Class of concrete etc) will be dependent on the Bridge design and cost estimates should be derived
at the time of designing the Bridge. For this rate exercise the following assumptions have been made:- (a) length of Pile is 15m. (b) X-sectional area of pile is 0.35mx0.35m. (c)

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/02/01b
Item Name Driven Precast Piles (b) 350x350mm
Unit of Measurement Lin. Metre (All Prices Are in Taka)
Quantity for Estimation 15.00
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.13 250.00 16.67
Concrete Poker Vibrator day 600.00 0.13 75.00 5.00
Mobilization/Demobilization for pre cast pile driving Equipment lump sum 1,500.00 1.00 1,500.00 100.00
Pile Diving Equipment (concrete piles) day 4,500.00 0.63 2,812.50 187.50
Small hand tools (1) day 50.00 12.00 600.00 40.00
Water Pump day 1,200.00 0.13 150.00 10.00
Item Type Labour 0.00 0.00
Foreman day 850.00 0.63 531.25 35.42
Labour for manufacturing pre-cast pile shutter using 16 times sq. metre 30.00 5.72 10.72 0.71
Masons day 700.00 1.75 1,225.00 81.67
Pre-cast pile shutter fixing and removing sq. metre 90.00 5.72 514.80 34.32
Semi-skilled labourer day 500.00 0.50 250.00 16.67
Unskilled labourer day 450.00 9.18 4,131.00 275.40
Item Type Material 0.00 0.00
Angle Iron (b) 38x38x5mm for pre cast pile shutter using 16 times tonne 60,000.00 0.14 525.00 35.00
Cement tonne 9,000.00 0.70 6,300.00 420.00
Coarse Sand FM>2.5 cu. metre 1,850.00 0.75 1,387.50 92.50
Cost of platform (pre-cast pile) using 5 times sq. metre 60.00 6.82 81.82 5.45
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 1.50 10,500.00 700.00
Diesel ltr 65.00 35.00 2,275.00 151.67
F I bar (b) 38x5mm for pre cast pile shutter using 16 times tonne 60,000.00 0.01 30.00 2.00
Nut bolt for pre cast pile shutter using 16 times kg 100.00 1.09 6.81 0.45
Polythene sheet sq. metre 18.00 7.18 129.24 8.62
Pre-cast Pile shoe (350x350mm pile) no. 300.00 1.00 300.00 20.00
Steel Plate 2mm for pre cast pile shutter using 16 time tonne 85,000.00 0.08 425.00 28.33
Basic Unit Price of Specification Item : 2,267.38
Plus Profit at 5% 113.37
Plus Overhead at 3.00% 68.02
Sub-Total : 2,448.77
Plus Tax & VAT at 16.2791% 398.64
Total Unit Price of Specification Item : 2,847.40
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
2,847.00
Assumption : The pile driving equipment is hired on a daily basis and it is assumed that 2No 15 lin.m piles can be driven in a day.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/02/01c
Item Name Driven Pre-cast Pile (c) 400x400mm
Unit of Measurement Lin. Metre (All Prices Are in Taka)
Quantity for Estimation 15.00
Specification Item Components
Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.16 312.00 20.80
Concrete Poker Vibrator day 600.00 0.16 93.60 6.24
Mobilization/Demobilization for pre cast pile driving Equipment lump sum 1,500.00 1.00 1,500.00 100.00
Pile Diving Equipment (concrete piles) day 4,500.00 0.70 3,150.00 210.00
Small hand tools (1) day 50.00 14.00 700.00 46.67
Water Pump day 1,200.00 0.13 150.00 10.00
Item Type Labour 0.00 0.00
Foreman day 850.00 0.70 595.00 39.67
Labour for manufacturing pre-cast pile shutter using 16 times sq. metre 30.00 6.54 12.26 0.82
Masons day 700.00 2.00 1,400.00 93.33
Pre-cast pile shutter fixing and removing sq. metre 90.00 6.54 588.60 39.24
Semi-skilled labourer day 500.00 0.50 250.00 16.67
Unskilled labourer day 450.00 11.00 4,950.00 330.00
Item Type Material 0.00 0.00
Angle Iron (b) 38x38x5mm for pre cast pile shutter using 16 times tonne 60,000.00 0.15 562.50 37.50
Cement tonne 9,000.00 0.93 8,325.00 555.00
Coarse Sand FM>2.5 cu. metre 1,850.00 0.98 1,813.00 120.87
Cost of platform (pre-cast pile) using 5 times sq. metre 60.00 7.27 87.24 5.82
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 1.96 13,720.00 914.67
Diesel ltr 65.00 35.00 2,275.00 151.67
F I bar (b) 38x5mm for pre cast pile shutter using 16 times tonne 60,000.00 0.01 33.75 2.25
Nut bolt for pre cast pile shutter using 16 times kg 100.00 1.09 6.81 0.45
Polythene sheet sq. metre 18.00 7.27 130.86 8.72
Pre cast pile shoe (400mmx400mm) No 300.00 1.00 300.00 20.00
Steel Plate 2mm for pre cast pile shutter using 16 time tonne 85,000.00 0.08 425.00 28.33
Basic Unit Price of Specification Item : 2,758.71
Plus Profit at 5% 137.94
Plus Overhead at 3.00% 82.76
Sub-Total : 2,979.41

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Plus Tax & VAT at 16.2791% 485.02
Total Unit Price of Specification Item : 3,464.42
3,464.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/02/02
Item Name Driven Precast Pilot Piles
Unit of Measurement Lin. Metre
Quantity for Estimation 15.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Pile Diving Equipment (concrete piles) day 4,500.00 1.00 4,500.00 300.00
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 56.67
Unskilled labourer day 450.00 4.00 1,800.00 120.00
Item Type Material 0.00
Diesel ltr 65.00 30.00 1,950.00 130.00
Basic Unit Price of Specification Item : 606.67
Plus Profit at 5% 30.33
Plus Overhead at 3.00% 18.20
Sub-Total : 655.20
Plus Tax & VAT at 16.2791% 106.66
Total Unit Price of Specification Item : 761.86
762.00

Assumption : The rate for the Pilot Pile will be similar to the rate for a standard driven Precast Pile (aka' working piles') since the pile size and method of construction are
the same.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/2/04
Item Name High Yield Deformed Steel Reinforcing Bars
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 14.00 700.00 700.00
Item Type Labour 0.00 0.00
Semi-skilled labourer day 500.00 5.00 2,500.00 2,500.00
Steel fixers day 700.00 4.00 2,800.00 2,800.00
Unskilled labourer day 450.00 5.00 2,250.00 2,250.00
Item Type Material 0.00 0.00
G.I wire, nails etc kg 120.00 10.00 1,200.00 1,200.00
M. S. bar 60 grade tonne 62,500.00 1.03 64,375.00 64,375.00
Basic Unit Price of Specification Item : 73,825.00
Plus Profit at 5% 3,691.25
Plus Overhead at 3.00% 2,214.75
Sub-Total : 79,731.00
Plus Tax & VAT at 16.2791% 12,979.46
Total Unit Price of Specification Item : 92,710.46
92,710.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/03/01
Item Name King Post
Unit of Measurement Lin. Metre
Quantity for Estimation 300.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (14/10) day 2,500.00 3.00 7,500.00 25.00
Concrete Poker Vibrator day 600.00 2.00 1,200.00 4.00
Hire Charge for mobile Generator/welding machine day 3,000.00 2.00 6,000.00 20.00
Pile Diving Equipment (concrete piles) day 4,500.00 3.00 13,500.00 45.00
Item Type Labour 0.00
Skilled Labour day 550.00 12.00 6,600.00 22.00
Unskilled labourer day 450.00 20.00 9,000.00 30.00
Item Type Material 0.00
Cement tonne 9,000.00 4.86 43,740.00 145.80
Coarse Sand FM>2.5 cu. metre 1,850.00 5.17 9,557.10 31.86
Steel Shutter (use 10 times) sq. metre 500.00 300.00 15,000.00 50.00
Stone Chippings (pakur stone) 20mm cu. metre 8,100.00 10.33 83,689.20 278.96
Basic Unit Price of Specification Item : 652.62
Plus Profit at 5% 32.63
Plus Overhead at 3.00% 19.58
Sub-Total : 704.83
Plus Tax & VAT at 16.2791% 114.74
Total Unit Price of Specification Item : 819.57
820.00
Assumption : The rate for this item will be dependent upon the design of the retaining works and must be derived as part of the overall design of the works.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/03/02
Item Name Raker Piles (including Tie Bars)
Unit of Measurement Lin. Metre
Quantity for Estimation 200.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (14/10) day 2,500.00 3.00 7,500.00 37.50
Concrete Poker Vibrator day 600.00 2.00 1,200.00 6.00
Hire Charge for mobile Generator/welding machine day 3,000.00 2.00 6,000.00 30.00
Pile Diving Equipment (concrete piles) day 4,500.00 3.00 13,500.00 67.50
Item Type Labour 0.00
Skilled Labour day 550.00 12.00 6,600.00 33.00
Unskilled labourer day 450.00 20.00 9,000.00 45.00
Item Type Material 0.00
Cement tonne 9,000.00 4.82 43,380.00 216.90
Coarse Sand FM>2.5 cu. metre 1,850.00 4.92 9,102.00 45.51
Steel Shutter (use 10 times) sq. metre 500.00 200.00 10,000.00 50.00
Stone Chippings (pakur stone) 20mm cu. metre 8,100.00 9.84 79,704.00 398.52
Basic Unit Price of Specification Item : 929.93
Plus Profit at 5% 46.50
Plus Overhead at 3.00% 27.90
Sub-Total : 1,004.32
Plus Tax & VAT at 16.2791% 163.49
Total Unit Price of Specification Item : 1,167.82
1,168.00

Assumption : The rate for this item will be dependent upon the design of the retaining works and must be derived as part of the overall design of the works.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/03/03
Item Name Precast Planks (including Reinforcement Steel)
Unit of Measurement Sq Metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (14/10) day 2,500.00 2.00 5,000.00 50.00
Concrete Poker Vibrator day 600.00 2.00 1,200.00 12.00
Hire Charge for mobile Generator/welding machine day 3,000.00 2.00 6,000.00 60.00
Pile Diving Equipment (concrete piles) day 4,500.00 2.00 9,000.00 90.00
Item Type Labour 0.00
Skilled Labour day 550.00 12.00 6,600.00 66.00
Unskilled labourer day 450.00 20.00 9,000.00 90.00
Item Type Material 0.00
Angle Iron (50x50x4 mm) tonne 60,000.00 0.40 24,000.00 240.00
Cement tonne 9,000.00 2.68 24,165.00 241.65
Coarse Sand FM>2.5 cu. metre 1,850.00 4.13 7,636.80 76.37
Nut Bolts (12 mm Dia 125 mm L) tonne 100,000.00 0.05 5,025.00 50.25
Reinforcing bar grade 40 tonne 62,500.00 1.60 100,000.00 1,000.00
Steel Shutter (use 10 times) sq. metre 500.00 100.00 5,000.00 50.00
Stone Chippings (pakur stone) 20mm cu. metre 8,100.00 8.26 66,873.60 668.74
Basic Unit Price of Specification Item : 2,695.00
Plus Profit at 5% 134.75
Plus Overhead at 3.00% 80.85
Sub-Total : 2,910.60
Plus Tax & VAT at 16.2791% 473.82
Total Unit Price of Specification Item : 3,384.42
3,384.00

Assumption : The rate for this item will be dependent upon the design of the retaining works and must be derived as part of the overall design of the works.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/03/05
Item Name High Yield Deformed Steel Reinforcing Bars to King Posts and Raker Piles
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 14.00 700.00 700.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 5.00 2,500.00 2,500.00
Steel fixers day 700.00 4.00 2,800.00 2,800.00
Unskilled labourer day 450.00 5.00 2,250.00 2,250.00
Item Type Material 0.00
G.I wire, nails etc kg 120.00 10.00 1,200.00 1,200.00
M. S. bar 60 grade tonne 62,500.00 1.03 64,375.00 64,375.00
Basic Unit Price of Specification Item : 73,825.00
Plus Profit at 5% 3,691.25
Plus Overhead at 3.00% 2,214.75
Sub-Total : 79,731.00
Plus Tax & VAT at 16.2791% 12,979.46
Total Unit Price of Specification Item : 92,710.46
92,710.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/04/01a
Item Name Load Test on Cast In Place Working Pile (Proof Load to be specified in BoQ)50 Ton
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Execution and Reporting of Pile Load Test no. 2,500.00 1.00 2,500.00 2,500.00
Hire Charge for Pile Load Testing Equipment per load test 5,000.00 1.00 5,000.00 5,000.00
Lighting Equipment per load test 1,000.00 1.00 1,000.00 1,000.00
Mobilization of Pile Load Test Equipment lump sum 5,500.00 1.00 5,500.00 5,500.00
Small hand tools (1) day 50.00 35.00 1,750.00 1,750.00
Item Type Labour 0.00
Ganger day 850.00 1.00 850.00 850.00
Masons day 700.00 2.00 1,400.00 1,400.00
Semi-skilled labourer day 500.00 3.00 1,500.00 1,500.00
Unskilled labourer day 450.00 75.00 33,750.00 33,750.00
Item Type Material 0.00
Diesel ltr 65.00 30.00 1,950.00 1,950.00
Gunny Bag (for load test used twice) No 10.00 1,667.00 16,670.00 16,670.00
Sand 0.5 F.M ii (used 2 times for load test) cu. metre 420.00 35.00 7,350.00 7,350.00
Basic Unit Price of Specification Item : 79,220.00
Plus Profit at 5% 3,961.00
Plus Overhead at 3.00% 2,376.60
Sub-Total : 85,557.60
Plus Tax & VAT at 16.2791% 13,927.98
Total Unit Price of Specification Item : 99,485.58
99,486.00

Assumption : The rate has been derived for a pile test of 100 tonne on a working pile, using average rates obtained from several piling contractors in Dhaka.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/04/01b
Item Name Load test on cast in place piles (For 100 Ton)
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Execution and Reporting of Pile Load Test no. 2,500.00 1.00 2,500.00 2,500.00
Hire Charge for Pile Load Testing Equipment per load test 5,000.00 1.00 5,000.00 5,000.00
Lighting Equipment per load test 1,000.00 1.00 1,000.00 1,000.00
Mobilization of Pile Load Test Equipment lump sum 5,500.00 1.00 5,500.00 5,500.00
Small hand tools (1) day 50.00 70.00 3,500.00 3,500.00
Item Type Labour 0.00
Ganger day 850.00 1.00 850.00 850.00
Masons day 700.00 2.00 1,400.00 1,400.00
Semi-skilled labourer day 500.00 4.00 2,000.00 2,000.00
Unskilled labourer day 450.00 150.00 67,500.00 67,500.00
Item Type Material 0.00
Diesel ltr 65.00 30.00 1,950.00 1,950.00
Gunny Bag (for load test used twice) No 10.00 3,333.00 33,330.00 33,330.00
Sand 0.5 F.M ii (used 2 times for load test) cu. metre 420.00 70.00 14,700.00 14,700.00
Basic Unit Price of Specification Item : 139,230.00
Plus Profit at 5% 6,961.50
Plus Overhead at 3.00% 4,176.90
Sub-Total : 150,368.40
Plus Tax & VAT at 16.2791% 24,478.58
Total Unit Price of Specification Item : 174,846.98
174,847.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/04/01c
Item Name Load Test on cast in place piles (For 200 Ton)
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Execution and Reporting of Pile Load Test no. 2,500.00 1.00 2,500.00 2,500.00
Hire Charge for Pile Load Testing Equipment per load test 5,000.00 1.00 5,000.00 5,000.00
Lighting Equipment per load test 1,000.00 1.00 1,000.00 1,000.00
Mobilization of Pile Load Test Equipment lump sum 5,500.00 1.00 5,500.00 5,500.00
Small hand tools (1) day 50.00 120.00 6,000.00 6,000.00
Item Type Labour 0.00
Ganger day 850.00 1.00 850.00 850.00
Masons day 700.00 6.00 4,200.00 4,200.00
Semi-skilled labourer day 500.00 6.00 3,000.00 3,000.00
Unskilled labourer day 450.00 250.00 112,500.00 112,500.00
Item Type Material 0.00
Diesel ltr 65.00 30.00 1,950.00 1,950.00
Gunny Bag (for load test used twice) No 10.00 6,667.00 66,670.00 66,670.00
Sand 0.5 F.M ii (used 2 times for load test) cu. metre 420.00 140.00 29,400.00 29,400.00
Basic Unit Price of Specification Item : 238,570.00
Plus Profit at 5% 11,928.50
Plus Overhead at 3.00% 7,157.10
Sub-Total : 257,655.60
Plus Tax & VAT at 16.2791% 41,943.93
Total Unit Price of Specification Item : 299,599.53
299,600.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/04/02
Item Name Load Test on Cast in Place Pilot Pile( Proof load to be specified in BoQ)
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/04/03
Item Name Load Test on Pilot Driven Pile (Proof load to be specified in the BoQ)
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/05/01
Item Name Bitumen Slip Layer to Concrete Piles
Unit of Measurement Sq Metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 1.00 50.00 5.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 0.25 125.00 12.50
Unskilled labourer day 450.00 0.38 168.75 16.88
Item Type Material 0.00
Bitumen tonne 54,000.00 0.03 1,355.40 135.54
Brush (for cleaning pile using 2 times) No 50.00 1.00 25.00 2.50
Wooden runner (using 6 times) cu. metre 6,500.00 0.04 43.33 4.33
Basic Unit Price of Specification Item : 176.75
Plus Profit at 5% 8.84
Plus Overhead at 3.00% 5.30
Sub-Total : 190.89
Plus Tax & VAT at 16.2791% 31.07
Total Unit Price of Specification Item : 221.96
222.00

Assumption : Assume the pile has cross-sectional area of 0.35m x 0.35m and length giving a suface area of 21sqm. Assume only the top 7m of the pile needs to be coated.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/06/01a
Item Name Driven Bullah Piles ( Dimensions to be stated in BoQ) 125-150mm
Unit of Measurement Lin. Metre
Quantity for Estimation 60.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire of Piling Winch (Bullah Piles) day 1,200.00 1.00 1,200.00 20.00
Small hand tools (1) day 50.00 17.00 850.00 14.17
Item Type Labour 0.00
Carpenters day 700.00 1.00 700.00 11.67
Foreman day 850.00 1.00 850.00 14.17
Semi-skilled labourer day 500.00 2.00 1,000.00 16.67
Unskilled labourer day 450.00 6.00 2,700.00 45.00
Item Type Material 0.00
Bullah pile 6m long (Dia 125-150mm) No. 2,400.00 10.00 24,000.00 400.00
Bullah piling metal shoe (For 125-150mm Bullah) No 200.00 10.00 2,000.00 33.33
Diesel ltr 65.00 20.00 1,300.00 21.67
Basic Unit Price of Specification Item : 576.67
Plus Profit at 5% 28.83
Plus Overhead at 3.00% 17.30
Sub-Total : 622.80
Plus Tax & VAT at 16.2791% 101.39
Total Unit Price of Specification Item : 724.19
724.00
Assumption : Assume rate applies to a standard 6m long wood pile and that 10No such piles are driven in an 8hr working day.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/06/01b
Item Name Deriven Bullah Pile (150-175mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 60.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire of Piling Winch (Bullah Piles) day 1,200.00 1.00 1,200.00 20.00
Small hand tools (1) day 50.00 19.00 950.00 15.83
Item Type Labour 0.00
Carpenters day 700.00 1.00 700.00 11.67
Foreman day 850.00 1.00 850.00 14.17
Semi-skilled labourer day 500.00 2.00 1,000.00 16.67
Unskilled labourer day 450.00 8.00 3,600.00 60.00
Item Type Material 0.00
Bullah Pile 6m Long (Dia 150-175mm) No. 2,700.00 10.00 27,000.00 450.00
Bullah Piling Metal Shoe (For 150-175,175-200,200-225mm Bullah) no. 200.00 10.00 2,000.00 33.33
Diesel ltr 65.00 20.00 1,300.00 21.67
Basic Unit Price of Specification Item : 643.33
Plus Profit at 5% 32.17
Plus Overhead at 3.00% 19.30
Sub-Total : 694.80
Plus Tax & VAT at 16.2791% 113.11
Total Unit Price of Specification Item : 807.91
808.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/06/01c
Item Name Driven Bullah Pile (175-200mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 60.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire of Piling Winch (Bullah Piles) day 1,200.00 1.50 1,800.00 30.00
Small hand tools (1) day 50.00 19.00 950.00 15.83
Item Type Labour 0.00
Carpenters day 700.00 1.00 700.00 11.67
Foreman day 850.00 1.00 850.00 14.17
Semi-skilled labourer day 500.00 3.00 1,500.00 25.00
Unskilled labourer day 450.00 10.00 4,500.00 75.00
Item Type Material 0.00
Bullah Pile 6m long (175-200mm) No 3,300.00 10.00 33,000.00 550.00
Bullah Piling Metal Shoe (For 150-175,175-200,200-225mm Bullah) no. 200.00 10.00 2,000.00 33.33
Diesel ltr 65.00 20.00 1,300.00 21.67
Basic Unit Price of Specification Item : 776.67
Plus Profit at 5% 38.83
Plus Overhead at 3.00% 23.30
Sub-Total : 838.80
Plus Tax & VAT at 16.2791% 136.55
Total Unit Price of Specification Item : 975.35
975.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/06/01d
Item Name Driven Bullah Pile (200-225mm dia)
Unit of Measurement Lin. Metre
Quantity for Estimation 60.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire of Piling Winch (Bullah Piles) day 1,200.00 1.00 1,200.00 20.00
Small hand tools (1) day 50.00 19.00 950.00 15.83
Item Type Labour 0.00
Carpenters day 700.00 2.00 1,400.00 23.33
Foreman day 850.00 1.00 850.00 14.17
Semi-skilled labourer day 500.00 4.00 2,000.00 33.33
Unskilled labourer day 450.00 15.00 6,750.00 112.50
Item Type Material 0.00
Bullah Pile 6m long (200-225mm) No 3,900.00 10.00 39,000.00 650.00
Bullah Piling Metal Shoe (For 150-175,175-200,200-225mm Bullah) no. 200.00 10.00 2,000.00 33.33
Diesel ltr 65.00 25.00 1,625.00 27.08
Basic Unit Price of Specification Item : 929.58
Plus Profit at 5% 46.48
Plus Overhead at 3.00% 27.89
Sub-Total : 1,003.95
Plus Tax & VAT at 16.2791% 163.43
Total Unit Price of Specification Item : 1,167.38
1,167.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/01
Item Name Cutting Edge (Well Shoe)
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire Charge for mobile Generator/welding machine day 2,000.00 0.50 1,000.00 1,000.00
Small hand Tools day 50.00 17.00 850.00 850.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 6.00 3,000.00 3,000.00
Steel Fixures day 650.00 4.00 2,600.00 2,600.00
Un-skilled labourer day 450.00 6.00 2,700.00 2,700.00
Item Type Material 0.00
Electrode and other accessories, etc. kg. 110.00 15.00 1,650.00 1,650.00
MS Bar 60 grade ton 62,500.00 0.06 3,750.00 3,750.00
MS Plate 60 grade ton 70,000.00 1.03 72,100.00 72,100.00
Basic Unit Price of Specification Item : 87,650.00
Plus Profit at 5% 4,382.50
Plus Overhead at 3.00% 2,629.50
Sub-Total : 94,662.00
Plus Tax & VAT at 16.2791% 15,410.09
Total Unit Price of Specification Item : 110,072.09
110,072.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/02
Item Name Class 20 Concrete for RCC Well.
Unit of Measurement cum
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.31
Concrete Poker Vibrator day 600.00 0.17 99.60 35.19
Small hand tools (1) day 50.00 8.00 400.00 141.34
Water Pump day 1,200.00 0.13 150.00 53.00
Item Type Labour 0.00 0.00
Labour for fixing/Removal of shutter sq. metre 85.00 18.81 1,598.85 564.96
Masons day 700.00 0.67 469.00 165.72
Semi-skilled labourer day 500.00 1.00 500.00 176.68
Unskilled labourer day 450.00 6.25 2,812.50 993.82
Item Type Material 0.00 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,862.19
Cost of scaffolding material for vertical member using 6 times lump sum 200.00 1.00 200.00 70.67
Crushed boulder/gravel aggregate <20mm cu. metre 5,970.00 2.54 15,163.80 5,358.23
Hire cost of shuttering material sq. metre 110.00 18.81 2,069.10 731.13
Nail kg 100.00 1.00 100.00 35.34
Sand FM>1.8 cu. metre 1,200.00 1.27 1,524.00 538.52
Basic Unit Price of Specification Item : 11,844.12
Plus Profit at 5% 592.21
Plus Overhead at 3.00% 355.32
Sub-Total : 12,791.65
Plus Tax & VAT at 16.2791% 2,082.36
Total Unit Price of Specification Item : 14,874.01
14,874.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/03
Item Name Concrete in Top/Bottom Plugging.
Unit of Measurement cum
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.170 340.00 120.14
Concrete Poker Vibrator day 600.00 0.170 102.00 36.04
Small hand tools (1) day 50.00 7.00 350.00 123.67
Water Pump day 1,200.00 0.13 156.00 55.12
Item Type Labour 0.00
Masons day 700.00 0.67 469.00 165.72
Semi-skilled labourer day 500.00 1.00 500.00 176.68
Unskilled labourer day 450.00 6.00 2,700.00 954.06
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,862.19
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,282.69
Sand FM>1.8 cu. metre 1,200.00 1.27 1,524.00 538.52
Nail Kg 80.00 20.00 1,600.00 565.37
Basic Unit Price of Specification Item : 11,880.21
Plus Profit at 5% 594.01
Plus Overhead at 3.00% 356.41
Sub-Total : 12,830.63
Plus Tax & VAT at 16.2791% 2,088.71
Total Unit Price of Specification Item : 14,919.34
14,919.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(a)
Item Name Labour for Well Sinking (Size 5000mm X 10000mm); Depth 0m-6m
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 15.00 750.00 125.00
Winch Machine with Grab day 3,000.00 22.00 66,000.00 11,000.00
Water pump day 1,200.00 0.50 600.00 100.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 10.00 5,000.00 833.33
Skilled Labour day 550.00 2.00 1,100.00 183.33
Unskilled labourer day 450.00 52.00 23,400.00 3,900.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 20,000.00 1.00 20,000.00 3,333.33
Basic Unit Price of Specification Item : 19,475.00
Plus Profit at 5% 973.75
Plus Overhead at 3.00% 584.25
Sub-Total : 21,033.00
Plus Tax & VAT at 16.2791% 3,423.98
Total Unit Price of Specification Item : 24,456.98
24,457.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(b)
Item Name Labour for Well Sinking (Size 5000mm X 10000mm); Depth 6m-12m
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 5.00 250.00 41.67
Winch Machine with Grab day 3,000.00 44.00 132,000.00 22,000.00
Water pump day 1,200.00 5.00 6,000.00 1,000.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 15.00 7,500.00 1,250.00
Skilled Labour day 550.00 8.00 4,400.00 733.33
Unskilled labourer day 450.00 20.00 9,000.00 1,500.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 20,000.00 20,000.00 3,333.33
Basic Unit Price of Specification Item : 29,858.33
Plus Profit at 5% 1,492.92
Plus Overhead at 3.00% 895.75
Sub-Total : 32,247.00
Plus Tax & VAT at 16.2791% 5,249.51
Total Unit Price of Specification Item : 37,496.51
37,497.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(c)
Item Name Labour for Well Sinking (Size 5000mm X 10000mm); Depth 12m-18m
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 15.00 750.00 125.00
Winch Machine with Grab day 3,000.00 50.00 150,000.00 25,000.00
Water pump day 1,200.00 5.00 6,000.00 1,000.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 15.00 7,500.00 1,250.00
Skilled Labour day 550.00 8.00 4,400.00 733.33
Unskilled labourer day 450.00 20.00 9,000.00 1,500.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 25,000.00 25,000.00 4,166.67
Basic Unit Price of Specification Item : 33,775.00
Plus Profit at 5% 1,688.75
Plus Overhead at 3.00% 1,013.25
Sub-Total : 36,477.00
Plus Tax & VAT at 16.2791% 5,938.12
Total Unit Price of Specification Item : 42,415.12
42,415.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(d)
Item Name Labour for Well Sinking (Size 5000mm X 10000mm); Depth 18m-24m
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 15.00 750.00 125.00
Winch Machine with Grab day 3,000.00 65.00 195,000.00 32,500.00
Water pump day 1,200.00 10.00 12,000.00 2,000.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 18.00 9,000.00 1,500.00
Skilled Labour day 550.00 8.00 4,400.00 733.33
Unskilled labourer day 450.00 25.00 11,250.00 1,875.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 25,000.00 25,000.00 4,166.67
Basic Unit Price of Specification Item : 42,900.00
Plus Profit at 5% 2,145.00
Plus Overhead at 3.00% 1,287.00
Sub-Total : 46,332.00
Plus Tax & VAT at 16.2791% 7,542.42
Total Unit Price of Specification Item : 53,874.42
53,874.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(e)
Item Name Labour for Well Sinking (Size 5000mm X 10000mm); Depth above 24m.
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 15.00 750.00 125.00
Winch Machine with Grab day 3,000.00 80.00 240,000.00 40,000.00
Water pump day 1,200.00 10.00 12,000.00 2,000.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 18.00 9,000.00 1,500.00
Skilled Labour day 550.00 8.00 4,400.00 733.33
Unskilled labourer day 450.00 25.00 11,250.00 1,875.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 30,000.00 30,000.00 5,000.00
Basic Unit Price of Specification Item : 51,233.33
Plus Profit at 5% 2,561.67
Plus Overhead at 3.00% 1,537.00
Sub-Total : 55,332.00
Plus Tax & VAT at 16.2791% 9,007.53
Total Unit Price of Specification Item : 64,339.53
64,340.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(f)
Item Name Labour for Well Sinking (Size 4270mm X 7940mm); Depth 0m-6m
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 10.00 500.00 83.33
Winch Machine with Grab day 3,000.00 15.00 45,000.00 7,500.00
Water pump day 1,200.00 0.35 420.00 70.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 7.00 3,500.00 583.33
Skilled Labour day 550.00 1.00 550.00 91.67
Unskilled labourer day 450.00 35.00 15,750.00 2,625.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 13,500.00 13,500.00 2,250.00
Basic Unit Price of Specification Item : 13,203.33
Plus Profit at 5% 660.17
Plus Overhead at 3.00% 396.10
Sub-Total : 14,259.60
Plus Tax & VAT at 16.2791% 2,321.33
Total Unit Price of Specification Item : 16,580.93
16,581.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(g)
Item Name Labour for Well Sinking (Size 4270mm X 7940mm); Depth 6m-12m
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 4.00 200.00 33.33
Winch Machine with Grab day 3,000.00 30.00 90,000.00 15,000.00
Water pump day 1,200.00 4.00 4,800.00 800.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 10.00 5,000.00 833.33
Skilled Labour day 550.00 5.00 2,750.00 458.33
Unskilled labourer day 450.00 14.00 6,300.00 1,050.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 13,500.00 13,500.00 2,250.00
Basic Unit Price of Specification Item : 20,425.00
Plus Profit at 5% 1,021.25
Plus Overhead at 3.00% 612.75
Sub-Total : 22,059.00
Plus Tax & VAT at 16.2791% 3,591.00
Total Unit Price of Specification Item : 25,650.00
25,650.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(h)
Item Name Labour for Well Sinking ((Size 4270mm X 7940mm); Depth 12m-18m
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 10.00 500.00 83.33
Winch Machine with Grab day 3,000.00 34.00 102,000.00 17,000.00
Water pump day 1,200.00 4.00 4,800.00 800.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 10.00 5,000.00 833.33
Skilled Labour day 550.00 5.00 2,750.00 458.33
Unskilled labourer day 450.00 13.00 5,850.00 975.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 16,000.00 16,000.00 2,666.67
Basic Unit Price of Specification Item : 22,816.67
Plus Profit at 5% 1,140.83
Plus Overhead at 3.00% 684.50
Sub-Total : 24,642.00
Plus Tax & VAT at 16.2791% 4,011.49
Total Unit Price of Specification Item : 28,653.49
28,653.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(i)
Item Name Labour for Well Sinking (Size 4270mm X 7940mm); Depth 18m-24m
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 10.00 500.00 83.33
Winch Machine with Grab day 3,000.00 44.00 132,000.00 22,000.00
Water pump day 1,200.00 7.00 8,400.00 1,400.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 12.00 6,000.00 1,000.00
Skilled Labour day 550.00 5.00 2,750.00 458.33
Unskilled labourer day 450.00 17.00 7,650.00 1,275.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 16,000.00 16,000.00 2,666.67
Basic Unit Price of Specification Item : 28,883.33
Plus Profit at 5% 1,444.17
Plus Overhead at 3.00% 866.50
Sub-Total : 31,194.00
Plus Tax & VAT at 16.2791% 5,078.09
Total Unit Price of Specification Item : 36,272.09
36,272.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/04(j)
Item Name Labour for Well Sinking (Size 4270mm X 7940mm); Depth above 24m.
Unit of Measurement Meter
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 10.00 500.00 83.33
Winch Machine with Grab day 3,000.00 54.00 162,000.00 27,000.00
Water pump day 1,200.00 7.00 8,400.00 1,400.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 12.00 6,000.00 1,000.00
Skilled Labour day 550.00 6.00 3,300.00 550.00
Unskilled labourer day 450.00 17.00 7,650.00 1,275.00
Item Type Material 0.00
Sand bag, joist wire rope etc. L.S. 20,000.00 20,000.00 3,333.33
Basic Unit Price of Specification Item : 34,641.67
Plus Profit at 5% 1,732.08
Plus Overhead at 3.00% 1,039.25
Sub-Total : 37,413.00
Plus Tax & VAT at 16.2791% 6,090.49
Total Unit Price of Specification Item : 43,503.49
43,503.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 04/7/05
Item Name Sand Filling (for Well)
Unit of Measurement cum
Quantity for Estimation 20.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Plate Compactor day 1,200.00 0.750 900.00 45.00
Small hand tools (1) day 50.00 17.00 850.00 42.50
Water Tanker day 7,000.00 0.10 700.00 35.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 3.00 1,500.00 75.00
Unskilled labourer day 450.00 12.00 5,400.00 270.00
Item Type Material 0.00
Sand FM>0.80 cu. metre 500.00 23.00 11,500.00 575.00
Basic Unit Price of Specification Item : 1,042.50
Plus Profit at 5% 52.13
Plus Overhead at 3.00% 31.28
Sub-Total : 1,125.90
Plus Tax & VAT at 16.2791% 183.29
Total Unit Price of Specification Item : 1,309.19
1,309.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 4/7/06
Item Name High Yield Reinforcement Bars
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 14.00 700.00 700.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 5.00 2,500.00 2,500.00
Steel fixers day 650.00 4.00 2,600.00 2,600.00
Unskilled labourer day 450.00 5.00 2,250.00 2,250.00
Item Type Material 0.00
G.I wire, nails etc kg 120.00 20.00 2,400.00 2,400.00
M. S. bar 60 grade tonne 62,500.00 1.03 64,375.00 64,375.00
Basic Unit Price of Specification Item : 74,825.00
Plus Profit at 5% 3,741.25
Plus Overhead at 3.00% 2,244.75
Sub-Total : 80,811.00
Plus Tax & VAT at 16.2791% 13,155.28
Total Unit Price of Specification Item : 93,966.28
93,966.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Division 5 - Structures

Item Code 05/01/01


Item Name Single Layer Brick Flat Soling
Unit of Measurement sq. metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 10.00 500.00 5.00
Item Type Labour 0.00 0.00
Masons day 700.00 3.00 2,100.00 21.00
Unskilled labourer day 450.00 7.00 3,150.00 31.50
Item Type Material 0.00 0.00
1st Class Brick no. 10.00 3,228.00 32,280.00 322.80
Sand FM>0.5 cu. metre 420.00 9.50 3,990.00 39.90
Basic Unit Price of Specification Item : 420.20
Plus Profit at 5% 21.01
Plus Overhead at 3.00% 12.61
Sub-Total : 453.82
Plus Tax & VAT at 16.2791% 73.88
Total Unit Price of Specification Item : 527.69
528.00
Assumption : Brick Flat Soling is carried out at the base of a piled foundation to give a clean working area. Rate has been derived based on 100sqm of brick soling.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02a
Item Name Concrete Class as Detailed on Drawings ( Class10)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.23
Small hand tools (2) day 50.00 7.00 350.00 123.59
Water Pump day 1,200.00 0.13 150.00 52.97
Item Type Labour 0.00
Labour cost for fixing and Removing shutter for foundation sq. metre 150.00 4.02 603.00 212.92
Masons day 700.00 0.67 469.00 165.61
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 5.60 2,520.00 889.83
Item Type Material 0.00
Cement tonne 9,000.00 0.60 5,400.00 1,906.78
Cost of wooden shutter for concrete using 6 times sq. metre 94.00 0.12 11.56 4.08
Nail kg 125.00 0.50 62.50 22.07
Sand FM >1.5 cu. metre 1,250.00 1.27 1,587.50 560.56
Brick Khoa < 40mm cu. metre 3,900.00 2.55 9,945.00 3,511.65
Basic Unit Price of Specification Item : 7,743.84
Plus Profit at 5% 387.19
Plus Overhead at 3.00% 232.32
Sub-Total : 8,363.35
Plus Tax & VAT at 16.2791% 1,361.48
Total Unit Price of Specification Item : 9,724.83
9,725.00

Assumption : Class 10 concrete is assumed to be 'Blinding Concrete' and as such brick chips can be used as coarse aggregates.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02b
Item Name Concrete class-20 (Foundation)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.23
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Small hand tools (1) day 50.00 7.00 350.00 123.59
Water Pump day 1,200.00 0.13 150.00 52.97
Item Type Labour 0.00
Labour cost for fixing and Removing shutter for foundation sq. metre 150.00 3.02 453.00 159.96
Masons day 700.00 0.67 469.00 165.61
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 6.00 2,700.00 953.39
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Cost of wooden shutter for concrete using 6 times sq. metre 94.00 0.12 11.28 3.98
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 11,531.56
Plus Profit at 5% 576.58
Plus Overhead at 3.00% 345.95
Sub-Total : 12,454.09
Plus Tax & VAT at 16.2791% 2,027.41
Total Unit Price of Specification Item : 14,481.49
14,481.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02c
Item Name Concrete class - 20 (Vertical member col. pier,
abutment / wing wall,culvert etc.)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.31
Concrete Poker Vibrator day 600.00 0.17 99.60 35.19
Small hand tools (1) day 50.00 8.00 400.00 141.34
Water Pump day 1,200.00 0.13 150.00 53.00
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 18.81 2,821.50 997.00
Masons day 700.00 0.67 469.00 165.72
Semi-skilled labourer day 500.00 1.00 500.00 176.68
Unskilled labourer day 450.00 6.25 2,812.50 993.82
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,862.19
Cost of scaffolding material for vertical member using 6 times lump sum 220.00 1.00 220.00 77.74
Crushed boulder/gravel aggregate <20mm cu. metre 7,000.00 2.54 17,780.00 6,282.69
Hire cost of shuttering material sq. metre 150.00 18.81 2,821.50 997.00
Nail kg 125.00 1.00 125.00 44.17
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.95
Basic Unit Price of Specification Item : 13,504.81
Plus Profit at 5% 675.24
Plus Overhead at 3.00% 405.14
Sub-Total : 14,585.19
Plus Tax & VAT at 16.2791% 2,374.33
Total Unit Price of Specification Item : 16,959.52
16,960.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02d
Item Name Concrete class-20 (Girder, cross girder,diaphram,beam
etc)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.23
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Small hand tools (1) day 50.00 9.00 450.00 158.90
Water Pump day 1,200.00 0.13 150.00 52.97
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 23.55 3,532.50 1,247.35
Masons day 700.00 0.67 469.00 165.61
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.00 3,150.00 1,112.29
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Cost of scaffolding material for Girdre/beam using bullah sq. metre 660.00 6.00 3,960.00 1,398.31
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Hire cost of shuttering material sq. metre 150.00 23.55 3,532.50 1,247.35
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 15,454.84
Plus Profit at 5% 772.74
Plus Overhead at 3.00% 463.65
Sub-Total : 16,691.22
Plus Tax & VAT at 16.2791% 2,717.18
Total Unit Price of Specification Item : 19,408.40
19,408.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02e
Item Name Concrete class-20 (Deck slab,side walk,wheel
guard,curb etc
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.23
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Small hand tools (1) day 50.00 9.00 450.00 158.90
Water Pump day 1,200.00 0.13 150.00 52.97
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 14.16 2,124.00 750.00
Masons day 700.00 0.67 469.00 165.61
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.00 3,150.00 1,112.29
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Hire cost of scaffolding materials (Deck slab) sq. metre 132.00 14.16 1,869.12 660.00
Hire cost of shuttering material sq. metre 150.00 14.16 2,124.00 750.00
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 13,721.83
Plus Profit at 5% 686.09
Plus Overhead at 3.00% 411.65
Sub-Total : 14,819.58
Plus Tax & VAT at 16.2791% 2,412.49
Total Unit Price of Specification Item : 17,232.06
17,232.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02f
Item Name Concrete class -20 (rail & post)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.23
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Small hand tools (1) day 50.00 9.00 450.00 158.90
Water Pump day 1,200.00 0.13 150.00 52.97
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 50.00 7,500.00 2,648.31
Masons day 700.00 0.67 469.00 165.61
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.25 3,262.50 1,152.01
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Hire cost of shuttering material sq. metre 150.00 50.00 7,500.00 2,648.31
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 16,898.16
Plus Profit at 5% 844.91
Plus Overhead at 3.00% 506.94
Sub-Total : 18,250.02
Plus Tax & VAT at 16.2791% 2,970.93
Total Unit Price of Specification Item : 21,220.95
21,221.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02g
Item Name Concrete Class - 25 (Foundation)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.23
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Small hand tools (1) day 50.00 8.00 400.00 141.24
Water Pump day 1,200.00 0.13 150.00 52.97
Item Type Labour 0.00
Labour cost for fixing and Removing shutter for foundation sq. metre 150.00 3.02 453.00 159.96
Masons day 700.00 0.67 469.00 165.61
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 6.00 2,700.00 953.39
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,495.76
Cost of wooden shutter for concrete using 6 times sq. metre 94.00 0.12 11.28 3.98
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.42
Basic Unit Price of Specification Item : 11,621.60
Plus Profit at 5% 581.08
Plus Overhead at 3.00% 348.65
Sub-Total : 12,551.33
Plus Tax & VAT at 16.2791% 2,043.24
Total Unit Price of Specification Item : 14,594.57
14,595.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02h
Item Name Concrete class -25 (Vertical member col,
pier,abutment/wing wall,culvert etc)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.23
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Small hand tools (1) day 50.00 8.00 400.00 141.24
Water Pump day 1,200.00 0.13 150.00 52.97
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 18.81 2,821.50 996.29
Masons day 700.00 0.67 469.00 165.61
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 6.25 2,812.50 993.11
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,495.76
Cost of scaffolding material for vertical member using 6 times lump sum 240.00 1.00 240.00 84.75
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Hire cost of shuttering material sq. metre 150.00 18.81 2,821.50 996.29
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.42
Basic Unit Price of Specification Item : 13,574.72
Plus Profit at 5% 678.74
Plus Overhead at 3.00% 407.24
Sub-Total : 14,660.69
Plus Tax & VAT at 16.2791% 2,386.62
Total Unit Price of Specification Item : 17,047.32
17,047.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02i
Item Name Concrete class - 25 (Girder,beam,cross girder,and
diaphram etc)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.31
Concrete Poker Vibrator day 600.00 0.17 99.60 35.19
Small hand tools (1) day 50.00 9.00 450.00 159.01
Water Pump day 1,200.00 0.13 150.00 53.00
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 23.55 3,532.50 1,248.23
Masons day 700.00 0.67 469.00 165.72
Semi-skilled labourer day 500.00 1.00 500.00 176.68
Unskilled labourer day 450.00 7.00 3,150.00 1,113.07
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,498.23
Cost of scaffolding material for Girdre/beam using bullah sq. metre 720.00 6.00 4,320.00 1,526.50
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,763.25
Hire cost of shuttering material sq. metre 150.00 23.55 3,532.50 1,248.23
Nail kg 125.00 1.00 125.00 44.17
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.78
Basic Unit Price of Specification Item : 15,665.41
Plus Profit at 5% 783.27
Plus Overhead at 3.00% 469.96
Sub-Total : 16,918.64
Plus Tax & VAT at 16.2791% 2,754.20
Total Unit Price of Specification Item : 19,672.84
19,673.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02j
Item Name Concrete class - 25 (RCC/CC Pavement Work)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 332.00 117.31
Concrete Poker Vibrator day 600.00 0.17 99.60 35.19
Small hand tools (1) day 50.00 9.00 450.00 159.01
Water Pump day 1,200.00 0.13 150.00 53.00
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 23.55 3,532.50 1,248.23
Masons day 700.00 0.67 469.00 165.72
Semi-skilled labourer day 500.00 1.00 500.00 176.68
Unskilled labourer day 450.00 7.00 3,150.00 1,113.07
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,498.23
Cost of scaffolding material for Girdre/beam using bullah sq. metre 72.00 3.00 216.00 76.33
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,763.25
Hire cost of shuttering material sq. metre 150.00 23.55 3,532.50 1,248.23
Nail kg 125.00 1.00 125.00 44.17
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.78
Basic Unit Price of Specification Item : 14,215.23
Plus Profit at 5% 710.76
Plus Overhead at 3.00% 426.46
Sub-Total : 15,352.45
Plus Tax & VAT at 16.2791% 2,499.24
Total Unit Price of Specification Item : 17,851.68
17,852.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02k
Item Name Concrete class-30 (Deck slab,side walk,wheel
guard,curb etc
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.17 340.00 120.06
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Small hand tools (1) day 50.00 9.00 450.00 158.90
Water Pump day 1,200.00 0.125 150.00 52.97
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 14.16 2,124.00 750.00
Masons day 700.00 0.67 469.00 165.61
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.00 3,150.00 1,112.29
Item Type Material 0.00
Cement tonne 9,000.00 1.24 11,160.00 3,940.68
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.41 16,870.00 5,956.92
Hire cost of scaffolding materials (Deck slab) sq. metre 144.00 14.16 2,039.04 720.00
Hire cost of shuttering material sq. metre 150.00 14.16 2,124.00 750.00
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.21 1,512.50 534.07
Basic Unit Price of Specification Item : 14,518.20
Plus Profit at 5% 725.91
Plus Overhead at 3.00% 435.55
Sub-Total : 15,679.65
Plus Tax & VAT at 16.2791% 2,552.50
Total Unit Price of Specification Item : 18,232.16
18,232.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02l
Item Name Concrete Class - 35
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.166 332.00 117.23
Concrete Poker Vibrator day 600.00 0.166 99.60 35.17
Small hand tools (1) day 50.00 9.00 450.00 158.90
Staging with M. S. pipe (pc girder bridge) sq. metre 2,500.00 7.00 17,500.00 6,179.38
Item Type Labour 0.00
Labour cost for Staging (p.c girder bridge) sq. metre 630.00 7.00 4,410.00 1,557.20
Labour for fixing and removing steel form (pc girder) sq. metre 170.00 24.50 4,165.00 1,470.69
Masons day 700.00 0.83 581.00 205.16
Semi-skilled labourer day 500.00 1.33 665.00 234.82
Unskilled labourer day 450.00 7.50 3,375.00 1,191.74
Item Type Material 0.00
Cement tonne 9,000.00 1.25 11,250.00 3,972.46
Coarse Sand FM>2.5 cu. metre 1,850.00 1.12 2,072.00 731.64
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.24 15,680.00 5,536.72
Sica lump sum 500.00 1.00 500.00 176.55
Steel form work (pc girder bridge) sq. metre 150.00 24.50 3,675.00 1,297.67
Basic Unit Price of Specification Item : 22,865.32
Plus Profit at 5% 1,143.27
Plus Overhead at 3.00% 685.96
Sub-Total : 24,694.55
Plus Tax & VAT at 16.2791% 4,020.04
Total Unit Price of Specification Item : 28,714.59
28,715.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02m
Item Name Concrete Class - 40 (Pre-stressed Girder)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.166 332.00 117.23
Concrete Poker Vibrator day 600.00 0.166 99.60 35.17
Small hand tools (1) day 50.00 9.00 450.00 158.90
Stagging with M. S. pipe (pc girder bridge) sq. metre 2,500.00 7.00 17,500.00 6,179.38
Item Type Labour 0.00
Labour cost for Staging (p.c girder bridge) sq. metre 630.00 7.00 4,410.00 1,557.20
Labour for fixing and removing steel form (pc girder) sq. metre 170.00 24.50 4,165.00 1,470.69
Masons day 700.00 0.83 581.00 205.16
Semi-skilled labourer day 500.00 1.33 665.00 234.82
Unskilled labourer day 450.00 7.50 3,375.00 1,191.74
Item Type Material 0.00
Cement tonne 9,000.00 1.36 12,240.00 4,322.03
Coarse Sand FM>2.5 cu. metre 1,850.00 1.11 2,053.50 725.11
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.17 15,190.00 5,363.70
Sica lump sum 500.00 2.00 1,000.00 353.11
Steel form work (pc girder bridge) sq. metre 150.00 24.50 3,675.00 1,297.67
Basic Unit Price of Specification Item : 23,211.90
Plus Profit at 5% 1,160.59
Plus Overhead at 3.00% 696.36
Sub-Total : 25,068.85
Plus Tax & VAT at 16.2791% 4,080.98
Total Unit Price of Specification Item : 29,149.83
29,150.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


05/01/03a
Item Name Concrete Class as Detailed on Drawings ( Class10)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour cost for fixing and Removing shutter for foundation sq. metre 150.00 4.02 603.00 212.92
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 5.60 2,520.00 889.83
Item Type Material 0.00
Cement tonne 9,000.00 0.60 5,400.00 1,906.78
Cost of wooden shutter for concrete using 6 times sq. metre 94.00 0.12 11.56 4.08
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 0.50 62.50 22.07
Sand FM >1.5 cu. metre 1,250.00 1.27 1,587.50 560.56
Brick Khoa < 40mm cu. metre 3,000.00 2.55 7,650.00 2,701.27
Basic Unit Price of Specification Item : 8,368.49
Plus Profit at 5% 418.42
Plus Overhead at 3.00% 251.05
Sub-Total : 9,037.97
Plus Tax & VAT at 16.2791% 1,471.30
Total Unit Price of Specification Item : 10,509.27
10,509.00
Assumption : Class 10 concrete is assumed to be 'Blinding Concrete' and as such brick chips can be used as coarse aggregates.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03b
Item Name Concrete class-20 (Foundation)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour cost for fixing and Removing shutter for foundation sq. metre 150.00 3.02 453.00 159.96
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 6.00 2,700.00 953.39
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Cost of wooden shutter for concrete using 6 times sq. metre 94.00 0.12 11.28 3.98
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 12,966.59
Plus Profit at 5% 648.33
Plus Overhead at 3.00% 389.00
Sub-Total : 14,003.92
Plus Tax & VAT at 16.2791% 2,279.71
Total Unit Price of Specification Item : 16,283.62
16,284.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03c
Item Name Concrete class - 20 (Vertical member col. pier,
abutment / wing wall,culvert etc.)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 18.81 2,821.50 996.29
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 6.25 2,812.50 993.11
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Cost of scaffolding material for vertical member using 6 times lump sum 220.00 1.00 220.00 77.68
Crushed boulder/gravel aggregate <20mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Hire cost of shuttering material sq. metre 150.00 18.81 2,821.50 996.29
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 14,912.64
Plus Profit at 5% 745.63
Plus Overhead at 3.00% 447.38
Sub-Total : 16,105.65
Plus Tax & VAT at 16.2791% 2,621.85
Total Unit Price of Specification Item : 18,727.50
18,728.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03d
Item Name Concrete class-20 (Girder, cross girder,diaphram,beam
etc)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 23.55 3,532.50 1,247.35
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.00 3,150.00 1,112.29
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Cost of scaffolding material for Girdre/beam using bullah sq. metre 660.00 6.00 3,960.00 1,398.31
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Hire cost of shuttering material sq. metre 150.00 23.55 3,532.50 1,247.35
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 16,854.55
Plus Profit at 5% 842.73
Plus Overhead at 3.00% 505.64
Sub-Total : 18,202.92
Plus Tax & VAT at 16.2791% 2,963.27
Total Unit Price of Specification Item : 21,166.18
21,166.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03e
Item Name Concrete class-20 (Deck slab,side walk,wheel
guard,curb etc
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 14.16 2,124.00 750.00
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.00 3,150.00 1,112.29
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Hire cost of scaffolding materials (Deck slab) sq. metre 132.00 14.16 1,869.12 660.00
Hire cost of shuttering material sq. metre 150.00 14.16 2,124.00 750.00
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 15,121.55
Plus Profit at 5% 756.08
Plus Overhead at 3.00% 453.65
Sub-Total : 16,331.27
Plus Tax & VAT at 16.2791% 2,658.58
Total Unit Price of Specification Item : 18,989.85
18,990.00

Assumption :
Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018
Item Code 05/01/03f
Item Name Concrete class -20 (rail & post)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 50.00 7,500.00 2,648.31
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.25 3,262.50 1,152.01
Item Type Material 0.00
Cement tonne 9,000.00 0.90 8,100.00 2,860.17
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.54 17,780.00 6,278.25
Hire cost of shuttering material sq. metre 150.00 50.00 7,500.00 2,648.31
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.27 1,587.50 560.56
Basic Unit Price of Specification Item : 18,297.88
Plus Profit at 5% 914.89
Plus Overhead at 3.00% 548.94
Sub-Total : 19,761.71
Plus Tax & VAT at 16.2791% 3,217.02
Total Unit Price of Specification Item : 22,978.73
22,979.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03g
Item Name Concrete Class - 25 (Foundation)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 1,800.00 635.59
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour cost for fixing and Removing shutter for foundation sq. metre 150.00 3.02 453.00 159.96
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 6.00 2,700.00 953.39
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,495.76
Cost of wooden shutter for concrete using 6 times sq. metre 94.00 0.12 11.28 3.98
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.42
Basic Unit Price of Specification Item : 12,968.35
Plus Profit at 5% 648.42
Plus Overhead at 3.00% 389.05
Sub-Total : 14,005.82
Plus Tax & VAT at 16.2791% 2,280.02
Total Unit Price of Specification Item : 16,285.84
16,286.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03h
Item Name Concrete class -25 (Vertical member col,
pier,abutment/wing wall,culvert etc)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 18.81 2,821.50 996.29
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 6.25 2,812.50 993.11
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,495.76
Cost of scaffolding material for vertical member using 6 times lump sum 240.00 1.00 240.00 84.75
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Hire cost of shuttering material sq. metre 150.00 18.81 2,821.50 996.29
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.42
Basic Unit Price of Specification Item : 14,992.09
Plus Profit at 5% 749.60
Plus Overhead at 3.00% 449.76
Sub-Total : 16,191.46
Plus Tax & VAT at 16.2791% 2,635.82
Total Unit Price of Specification Item : 18,827.28
18,827.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03i
Item Name Concrete class - 25 (Girder,beam,cross girder,and
diaphram etc)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 23.55 3,532.50 1,247.35
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.00 3,150.00 1,112.29
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,495.76
Cost of scaffolding material for Girdre/beam using bullah sq. metre 720.00 6.00 4,320.00 1,525.42
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Hire cost of shuttering material sq. metre 150.00 23.55 3,532.50 1,247.35
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.42
Basic Unit Price of Specification Item : 17,054.06
Plus Profit at 5% 852.70
Plus Overhead at 3.00% 511.62
Sub-Total : 18,418.39
Plus Tax & VAT at 16.2791% 2,998.34
Total Unit Price of Specification Item : 21,416.73
21,417.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03j
Item Name Concrete class - 25 (RCC/CC Pavement Work)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 99.60 35.17
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 23.55 3,532.50 1,247.35
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.00 3,150.00 1,112.29
Item Type Material 0.00
Cement tonne 9,000.00 1.10 9,900.00 3,495.76
Cost of scaffolding material for Girdre/beam using bullah sq. metre 72.00 3.00 216.00 76.27
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.33 16,310.00 5,759.18
Hire cost of shuttering material sq. metre 150.00 23.55 3,532.50 1,247.35
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.17 1,462.50 516.42
Basic Unit Price of Specification Item : 15,604.91
Plus Profit at 5% 780.25
Plus Overhead at 3.00% 468.15
Sub-Total : 16,853.30
Plus Tax & VAT at 16.2791% 2,743.56
Total Unit Price of Specification Item : 19,596.86
19,597.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03k
Item Name Concrete class-30 (Deck slab, side walk,wheel guard,curb etc
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.17 102.00 36.02
Pump with pipe and exessories day 10,000.00 0.05 500.00 176.55
Pay loader day 12,000.00 0.05 600.00 211.86
Agitator Truck day 12,000.00 0.12 1,440.00 508.47
Item Type Labour 0.00
Labour for fixing/Removal of shutter sq. metre 150.00 14.16 2,124.00 750.00
Masons day 700.00 0.55 385.00 135.95
Semi-skilled labourer day 500.00 1.00 500.00 176.55
Unskilled labourer day 450.00 7.00 3,150.00 1,112.29
Item Type Material 0.00
Cement tonne 9,000.00 1.24 11,160.00 3,940.68
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.41 16,870.00 5,956.92
Hire cost of scaffolding materials (Deck slab) sq. metre 144.00 14.16 2,039.04 720.00
Hire cost of shuttering material sq. metre 150.00 14.16 2,124.00 750.00
Admixture Liter 200.00 2.20 440.00 155.37
Nail kg 125.00 1.00 125.00 44.14
Sand FM>1.8 cu. metre 1,250.00 1.21 1,512.50 534.07
Basic Unit Price of Specification Item : 15,915.09
Plus Profit at 5% 795.75
Plus Overhead at 3.00% 477.45
Sub-Total : 17,188.30
Plus Tax & VAT at 16.2791% 2,798.10
Total Unit Price of Specification Item : 19,986.39
19,986.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/03l
Item Name Concrete Class - 35
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.166 99.60 35.17
Small hand tools (1) day 50.00 9.00 450.00 158.90
Staging with M. S. pipe (pc girder bridge) sq. metre 2,500.00 7.00 17,500.00 6,179.38
Item Type Labour 0.00
Labour cost for Staging (p.c girder bridge) sq. metre 630.00 7.00 4,410.00 1,557.20
Labour for fixing and removing steel form (pc girder) sq. metre 170.00 24.50 4,165.00 1,470.69
Masons day 600.00 0.83 498.00 175.85
Semi-skilled labourer day 450.00 1.33 598.50 211.33
Unskilled labourer day 400.00 7.50 3,000.00 1,059.32
Item Type Material 0.00
Cement tonne 9,000.00 1.25 11,250.00 3,972.46
Coarse Sand FM>2.5 cu. metre 1,850.00 1.12 2,072.00 731.64
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.24 15,680.00 5,536.72
Sica lump sum 500.00 1.00 500.00 176.55
Steel form work (pc girder bridge) sq. metre 150.00 24.50 3,675.00 1,297.67
Basic Unit Price of Specification Item : 23,269.10
Plus Profit at 5% 1,163.46
Plus Overhead at 3.00% 698.07
Sub-Total : 25,130.63
Plus Tax & VAT at 16.2791% 4,091.03
Total Unit Price of Specification Item : 29,221.66
29,222.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/01/02m
Item Name Concrete Class - 40 (Pre-stressed Girder)
Unit of Measurement cu metre
Quantity for Estimation 2.83 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Batching Plant with Generator day 40,000.00 0.05 2,000.00 706.21
Concrete Poker Vibrator day 600.00 0.166 99.60 35.17
Small hand tools (1) day 50.00 9.00 450.00 158.90
Stagging with M. S. pipe (pc girder bridge) sq. metre 2,500.00 7.00 17,500.00 6,179.38
Item Type Labour 0.00
Labour cost for Staging (p.c girder bridge) sq. metre 630.00 7.00 4,410.00 1,557.20
Labour for fixing and removing steel form (pc girder) sq. metre 170.00 24.50 4,165.00 1,470.69
Masons day 600.00 0.83 498.00 175.85
Semi-skilled labourer day 450.00 1.33 598.50 211.33
Unskilled labourer day 400.00 7.50 3,000.00 1,059.32
Item Type Material 0.00
Cement tonne 9,000.00 1.36 12,240.00 4,322.03
Coarse Sand FM>2.5 cu. metre 1,850.00 1.11 2,053.50 725.11
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 2.17 15,190.00 5,363.70
Sica lump sum 500.00 2.00 1,000.00 353.11
Steel form work (pc girder bridge) sq. metre 150.00 24.50 3,675.00 1,297.67
Basic Unit Price of Specification Item : 23,615.68
Plus Profit at 5% 1,180.78
Plus Overhead at 3.00% 708.47
Sub-Total : 25,504.93
Plus Tax & VAT at 16.2791% 4,151.97
Total Unit Price of Specification Item : 29,656.90
29,657.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/02/02
Item Name High Yield Reinforcement Bars
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 17.00 850.00 850.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 4.00 2,000.00 2,000.00
Steel fixers day 650.00 3.00 1,950.00 1,950.00
Unskilled labourer day 450.00 5.00 2,250.00 2,250.00
Item Type Material 0.00
G.I wire, nails etc kg 120.00 10.00 1,200.00 1,200.00
M. S. bar 60 grade tonne 62,500.00 1.03 64,375.00 64,375.00
Basic Unit Price of Specification Item : 72,625.00
Plus Profit at 5% 3,631.25
Plus Overhead at 3.00% 2,178.75
Sub-Total : 78,435.00
Plus Tax & VAT at 16.2791% 12,768.49
Total Unit Price of Specification Item : 91,203.49
91,203.00

Assumption : The same comment as Item 05/02/01 applies except that for simple structures the same rate as Item 04/01/04 may be used.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/02/03
Item Name Wire Mesh Reinforcement
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire Charge for mobile Generator/welding machine day 3,000.00 0.15 450.00 450.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 0.05 25.00 25.00
Steel fixers day 650.00 0.06 39.00 39.00
Unskilled labourer day 450.00 0.25 112.50 112.50
Welder day 750.00 0.25 187.50 187.50
Item Type Material 0.00
Reinforcing bar grade 40 tonne 62,500.00 1.05 65,625.00 65,625.00
Basic Unit Price of Specification Item : 66,439.00
Plus Profit at 5% 3,321.95
Plus Overhead at 3.00% 1,993.17
Sub-Total : 71,754.12
Plus Tax & VAT at 16.2791% 11,680.90
Total Unit Price of Specification Item : 83,435.02
83,435.00
Assumption : Typically in Bangladesh the Wire mesh is manufactured at site by spot welding 3mm to 8mm diameter straight bar to the required shape.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/03/01
Item Name Prestressing Wire or Strand
Unit of Measurement Tonne
Quantity for Estimation 2.30 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire cost of grouting machine with labour for PC girder. lump sum 2,300.00 1.00 2,300.00 1,000.00
Hire charge of jacking equipments with all fitting and shifting equipments lump sum 23,000.00 1.00 23,000.00 10,000.00
Item Type Labour 0.00
Labour for Prestressing tonne 5,000.00 2.51 12,540.00 5,452.17
Item Type Material 0.00
Cement tonne 9,000.00 1.00 9,000.00 3,913.04
Grouting Material Pkt 200.00 20.00 4,000.00 1,739.13
Prestressing Anchorage system set 11,500.00 8.00 92,000.00 40,000.00
Prestressing wire metal sheathing lin. metre 175.00 171.00 29,925.00 13,010.87
Prestressing wire/Strand tonne 146,500.00 2.30 337,457.61 146,720.70
Basic Unit Price of Specification Item : 221,835.92
Plus Profit at 5% 11,091.80
Plus Overhead at 3.00% 6,655.08
Sub-Total : 239,582.79
Plus Tax & VAT at 16.2791% 39,001.85
Total Unit Price of Specification Item : 278,584.64
278,585.00

Assumption : Rate has been built up from information given by the Engineers Company and assumes a 2m high by 40m long beam with 12T13 Tendeon used to form one
tendon.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/04/01
Item Name Modification to Existing Concrete
Unit of Measurement cu metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Repair to existing concrete cu. metre 8,050.00 1.00 8,050.00 8,050.00
Basic Unit Price of Specification Item : 8,050.00
Plus Profit at 5% 402.50
Plus Overhead at 3.00% 241.50
Sub-Total : 8,694.00
Plus Tax & VAT at 16.2791% 1,415.30
Total Unit Price of Specification Item : 10,109.30
10,109.00
Assumption : As is the case with most structural concrete work the rate is very dependant on the specifics of the type of work to be carried out, both with regard to nature,
scope and location. For the purpose of deriving a rate the case of repairing/ replacing concrete post and rail on a existing bridge.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/04/02
Item Name Concrete Surface Repair Works (Superstructures)
Unit of Measurement sq. metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Concrete surface repair (superstructure) sq. metre 173.00 1.00 173.00 173.00
Basic Unit Price of Specification Item : 173.00
Plus Profit at 5% 8.65
Plus Overhead at 3.00% 5.19
Sub-Total : 186.84
Plus Tax & VAT at 16.2791% 30.42
Total Unit Price of Specification Item : 217.26
217.00

Assumption : The rate for this Item will be dependent on the particular nature of the work to be carried out. The rate that has been given is based on average rates for
repairing a bridge deck slab.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/04/03
Item Name Concrete Surface Repair Works (Substructures)
Unit of Measurement sq. metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Concrete surface repair (substructure) sq. metre 230.00 1.00 230.00 230.00
Basic Unit Price of Specification Item : 230.00
Plus Profit at 5% 11.50
Plus Overhead at 3.00% 6.90
Sub-Total : 248.40
Plus Tax & VAT at 16.2791% 40.44
Total Unit Price of Specification Item : 288.84
289.00

Assumption : The rate will be dependent on the individual structure and the extent of the repair works to be carried out.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/04/04
Item Name Resin Repair Mortars
Unit of Measurement Kg
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption : Assume that a mason with helper can clean and fill 1m of joint in half an hour.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/04/05
Item Name Cement Mortar in Cracks
Unit of Measurement Lin. Metre
Quantity for Estimation 24.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 2.00 100.00 4.17
Item Type Labour 0.00
Masons day 700.00 1.00 700.00 29.17
Semi-skilled labourer day 500.00 1.00 500.00 20.83
Item Type Material 0.00
Cement tonne 9,000.00 0.0025 22.50 0.94
Sand FM<1.5 cum 1,250.00 0.0073 9.13 0.38
Basic Unit Price of Specification Item : 55.48
Plus Profit at 5% 2.77
Plus Overhead at 3.00% 1.66
Sub-Total : 59.92
Plus Tax & VAT at 16.2791% 9.75
Total Unit Price of Specification Item : 69.68
70.00
Assumption : Brick Flat Soling is carried out at the base of a piled foundation to give a clean working area. Rate has been derived based on 100sqm of brick soling.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/04/06
Item Name Anchor and Tie Bars
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Angle (75x75x5)mm (Using 30 times) Tonne 48,000.00 1.00 1,600.00 1,600.00
Basic Unit Price of Specification Item : 1,600.00
Plus Profit at 5% 80.00
Plus Overhead at 3.00% 48.00
Sub-Total : 1,728.00
Plus Tax & VAT at 16.2791% 281.30
Total Unit Price of Specification Item : 2,009.30
2,009.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/05/01
Item Name New and Extended Brickwork
Unit of Measurement cu metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Scaffolding for Brickwork sq. metre 58.00 2.00 116.00 116.00
Small hand tools (2) day 50.00 2.80 140.00 140.00
Item Type Labour 0.00
Masons day 700.00 0.50 350.00 350.00
Semi-skilled labourer day 500.00 0.33 165.00 165.00
Unskilled labourer day 450.00 2.00 900.00 900.00
Item Type Material 0.00
1st Class Brick no. 10.00 390.00 3,900.00 3,900.00
Cement tonne 9,000.00 0.11 1,012.50 1,012.50
Sand FM >1.5 cu. metre 1,250.00 0.40 500.00 500.00
Basic Unit Price of Specification Item : 7,083.50
Plus Profit at 5% 354.17
Plus Overhead at 3.00% 212.50
Sub-Total : 7,650.18
Plus Tax & VAT at 16.2791% 1,245.38
Total Unit Price of Specification Item : 8,895.56
8,896.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/05/02
Item Name Brick Drainage Layer
Unit of Measurement cu metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour
Masons day 700.00 0.50 350.00 350.00
Unskilled labourer day 450.00 1.00 450.00 450.00
Item Type Material 0.00
Brick P.J. no. 10.00 390.00 3,900.00 3,900.00
Basic Unit Price of Specification Item : 4,700.00
Plus Profit at 5% 235.00
Plus Overhead at 3.00% 141.00
Sub-Total : 5,076.00
Plus Tax & VAT at 16.2791% 826.33
Total Unit Price of Specification Item : 5,902.33
5,902.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/05/03
Item Name Replacement of Defective Existing brick
Unit of Measurement cu metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Scaffolding for Brickwork sq. metre 58.00 4.00 232.00 232.00
Small hand tools (2) day 50.00 9.00 450.00 450.00
Item Type Labour 0.00
Masons day 700.00 4.50 3,150.00 3,150.00
Unskilled labourer day 450.00 4.50 2,025.00 2,025.00
Item Type Material 0.00 0.00
1st Class Brick no. 10.00 390.00 3,900.00 3,900.00
Cement tonne 9,000.00 0.13 1,170.00 1,170.00
Sand FM >1.5 cu. metre 1,250.00 0.30 375.00 375.00
Basic Unit Price of Specification Item : 11,302.00
Plus Profit at 5% 565.10
Plus Overhead at 3.00% 339.06
Sub-Total : 12,206.16
Plus Tax & VAT at 16.2791% 1,987.05
Total Unit Price of Specification Item : 14,193.21
14,193.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/05/04
Item Name Repointing of Existing Brickwork Joints
Unit of Measurement sq. metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Scaffolding for Brickwork sq. metre 58.00 1.00 58.00 58.00
Small hand tools (2) day 50.00 0.57 28.50 28.50
Item Type Labour 0.00
Masons day 700.00 0.38 266.00 266.00
Unskilled labourer day 450.00 0.19 85.50 85.50
Item Type Material 0.00
Cement tonne 9,000.00 0.00 22.50 22.50
Sand FM >1.5 cu. metre 1,250.00 0.03 35.00 35.00
Basic Unit Price of Specification Item : 495.50
Plus Profit at 5% 24.77
Plus Overhead at 3.00% 14.86
Sub-Total : 535.14
Plus Tax & VAT at 16.2791% 87.12
Total Unit Price of Specification Item : 622.26
622.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/05/05
Item Name Steel Tie Bars and Pattress Plates
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/06/01
Item Name Preparation and Painting of Existing Structures
Unit of Measurement sq. metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Scaffolding for painting sq. metre 87.00 10.00 870.00 87.00
Small hand tools (2) day 50.00 5.50 275.00 27.50
Item Type Labour 0.00
Masons day 700.00 1.00 700.00 70.00
Semi-skilled labourer day 500.00 4.00 2,000.00 200.00
Item Type Material 0.00
Paint- finish coat ltr 173.00 1.70 294.10 29.41
Paint- Primecoat ltr 150.00 2.50 375.00 37.50
Paint- Undercoat ltr 173.00 1.40 242.20 24.22
Basic Unit Price of Specification Item : 475.63
Plus Profit at 5% 23.78
Plus Overhead at 3.00% 14.27
Sub-Total : 513.68
Plus Tax & VAT at 16.2791% 83.62
Total Unit Price of Specification Item : 597.30
597.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/07/01
Item Name Carriage of Bridge Steelwork from Port to Site
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/07/02
Item Name Fixing of bearings for Unit Bridging
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/07/03
Item Name Supply and Fixing of Elastomeric Bearings for
Composite Bridge Construction
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/07/04
Item Name Asssembly and Installation of Unit Bridging
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/07/05
Item Name Installation of Steelwork for Composite Bridge
Construction.
Unit of Measurement Tonne
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/07/06
Item Name Installation of Steel Post and Barrier Parapet to
Reinforced Concrete Deck Slab
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/08/01
Item Name Expansion Joint complete as detailed on the Drawings
in the location described in the BoQ.
Unit of Measurement Lin. Metre
Quantity for Estimation 3.66 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire Charge for mobile Generator/welding machine day 3,000.00 0.50 1,500.00 409.84
Item Type Labour 0.00
Semi-skilled labourer day 500.00 0.50 250.00 68.31
Welder day 750.00 0.50 375.00 102.46
Item Type Material 0.00
Angle (75x75x5)mm metre 473.00 7.21 3,410.33 931.78
Electrode and other accessories, etc. L.S. 1,150.00 1.00 1,150.00 314.21
Steel Plate (150x6)mm metre 518.00 3.66 1,895.88 518.00
Basic Unit Price of Specification Item : 2,344.59
Plus Profit at 5% 117.23
Plus Overhead at 3.00% 70.34
Sub-Total : 2,532.16
Plus Tax & VAT at 16.2791% 412.21
Total Unit Price of Specification Item : 2,944.37
2,944.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/08/02
Item Name Bridge Deck Joint Complete as detailed on the
Drawings.
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/09/01
Item Name Provision and Fixing of drainage to structures as
detailed on the Drawings.
Unit of Measurement Lump sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/10/01
Item Name Embedment of Inserts and Fittings
Unit of Measurement Lump Sum
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/12/01(a)
Item Name Supply and Installation of Pot bearings (Size : 500mm X 500mm X 72mm)
Unit of Measurement No.
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/12/01(b)
Item Name Supply and Installation of Pot bearings (Size : 500mm X 450mm X 72mm)
Unit of Measurement No.
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/12/01(c)
Item Name Supply and Installation of Pot bearings (Size : 400mm X 300mm X 72mm)
Unit of Measurement No.
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/12/2
Item Name Supply and Installation of Shock Transmission units
Unit of Measurement No.
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/13/01(a)
Item Name Neoprene rubber bearing or Elastomeric bearing supplying & fitting fixing, etc.
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hydraulic Jack day 500.00 0.25 125.00 125.00

Item Type Labour 0.00


Foreman day 850.00 1.00 850.00 850.00
Unskilled labourer day 450.00 2.00 900.00 900.00
Item Type Material 0.00
Neoprene rubber bearing or Elastomeric bearing ; size : upto 350mm 11,500.00 1.00 11,500.00
x 500mm. No 11,500.00
Wooden sleeper L.S. 358.33 1.00 358.33 358.33
Basic Unit Price of Specification Item : 13,733.33
Plus Profit at 5% 686.67
Plus Overhead at 3.00% 412.00
Sub-Total : 14,832.00
Plus Tax & VAT at 16.2791% 2,414.51
Total Unit Price of Specification Item : 17,246.51
17,247.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/13/01(b)
Item Name Neoprene rubber bearing or Elastomeric bearing supplying & fitting fixing, (b) , etc.
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hydraulic Jack day 500.00 0.25 125.00 125.00
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 850.00
Unskilled labourer day 450.00 2.00 900.00 900.00
Item Type Material 0.00
Neoprene rubber bearing or Elastometric bearing ; size : above No 13,700.00 1.00 13,700.00
350mm x 500mm . 13,700.00
Wooden sleeper L.S. 358.33 1.00 358.33 358.33
Basic Unit Price of Specification Item : 15,933.33
Plus Profit at 5% 796.67
Plus Overhead at 3.00% 478.00
Sub-Total : 17,208.00
Plus Tax & VAT at 16.2791% 2,801.30
Total Unit Price of Specification Item : 20,009.30
20,009.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/14/01(b)
Item Name Double Single Bailey Bridge or Acrow panel (Erecting and Assembling).
Unit of Measurement Lin. Metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Flat Bed truck (5tons) day 7,000.00 1.00 7,000.00 700.00
Hire Charge for mobile Generator/welding machine day 3,000.00 1.00 3,000.00 300.00
Hydraulic Jack day 500.00 4.00 2,000.00 200.00
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 85.00
Scaffolding for steel member fitting fixing, etc. sq. metre 87.00 66.00 5,742.00 574.20
Steel fixers day 650.00 11.00 7,150.00 715.00
Unskilled labourer day 450.00 10.00 4,500.00 450.00
Basic Unit Price of Specification Item : 3,024.20
Plus Profit at 5% 151.21
Plus Overhead at 3.00% 90.73
Sub-Total : 3,266.14
Plus Tax & VAT at 16.2791% 531.70
Total Unit Price of Specification Item : 3,797.83
3,798.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/14/01(c)
Item Name Calender Hamilton Truss Bridge (Erecting and Assembling)
Unit of Measurement Lin. Metre
Quantity for Estimation 5.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Flat Bed truck (5tons) day 7,000.00 1.00 7,000.00 1,400.00
Hire Charge for mobile Generator/welding machine day 3,000.00 1.00 3,000.00 600.00
Hydraulic Jack day 500.00 4.00 2,000.00 400.00
Kato Crane 20tonnes (truck mounted) no. 12,650.00 1.00 12,650.00 2,530.00
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 170.00
Scaffolding for steel member fitting fixing, etc. sq. metre 87.00 100.00 8,700.00 1,740.00
Steel fixers day 650.00 16.00 10,400.00 2,080.00
Unskilled labourer day 450.00 15.00 6,750.00 1,350.00
Basic Unit Price of Specification Item : 10,270.00
Plus Profit at 5% 513.50
Plus Overhead at 3.00% 308.10
Sub-Total : 11,091.60
Plus Tax & VAT at 16.2791% 1,805.61
Total Unit Price of Specification Item : 12,897.21
12,897.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/14/02(b)
Item Name Double Single Bailey Bridge or Acrow panel (Delaunching).
Unit of Measurement Lin. Metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Flat Bed truck (5tons) day 7,000.00 1.00 7,000.00 700.00
Hire Charge for mobile Generator/welding machine day 3,000.00 1.00 3,000.00 300.00
Hydraulic Jack day 500.00 4.00 2,000.00 200.00
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 85.00
Scaffolding for steel member fitting fixing, etc. sq. metre 87.00 38.00 3,306.00 330.60
Steel fixers day 650.00 4.00 2,600.00 260.00
Unskilled labourer day 450.00 4.00 1,800.00 180.00
Basic Unit Price of Specification Item : 2,055.60
Plus Profit at 5% 102.78
Plus Overhead at 3.00% 61.67
Sub-Total : 2,220.05
Plus Tax & VAT at 16.2791% 361.40
Total Unit Price of Specification Item : 2,581.45
2,581.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/14/02(c)
Item Name Calender Hamilton Truss Bridge (Delaunching).
Unit of Measurement Lin. Metre
Quantity for Estimation 5.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Flat Bed truck (5tons) day 7,000.00 0.50 3,500.00 700.00
Hire Charge for mobile Generator/welding machine day 3,000.00 1.00 3,000.00 600.00
Hydraulic Jack day 500.00 4.00 2,000.00 400.00
Kato Crane 20tonnes (truck mounted) no. 15,000.00 1.00 15,000.00 3,000.00
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 170.00
Scaffolding for steel member fitting fixing, etc. sq. metre 87.00 50.00 4,350.00 870.00
Skilled Labour day 550.00 5.00 2,750.00 550.00
Unskilled labourer day 450.00 9.00 4,050.00 810.00
Basic Unit Price of Specification Item : 7,100.00
Plus Profit at 5% 355.00
Plus Overhead at 3.00% 213.00
Sub-Total : 7,668.00
Plus Tax & VAT at 16.2791% 1,248.28
Total Unit Price of Specification Item : 8,916.28
8,916.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/15/01
Item Name Mobilization for railing type work, etc.
Unit of Measurement Lin. Metre
Quantity for Estimation 5.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Flat Bed truck (5tons) day 7,000.00 1.00 7,000.00 1,400.00
Item Type Labour 0.00
Flagman day 550.00 2.00 1,100.00 220.00
Item Type Material 0.00
Construction warning signs, etc. L.S. 2,300.00 1.00 2,300.00 460.00
Basic Unit Price of Specification Item : 2,080.00
Plus Profit at 5% 104.00
Plus Overhead at 3.00% 62.40
Sub-Total : 2,246.40
Plus Tax & VAT at 16.2791% 365.69
Total Unit Price of Specification Item : 2,612.09
2,612.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 5/16/01
Item Name Dismantling of deck slab, thickness 175mm.
Unit of Measurement Sq Metre
Quantity for Estimation 7.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Gas Cutting Set No 575.00 3.00 1,725.00 246.43
Hire Charge for mobile Generator/welding machine day 2,000.00 1.00 2,000.00 285.71
Small hand tools (2) day 20.00 30.00 600.00 85.71
Item Type Labour 0.00
Skilled Labour day 550.00 1.00 550.00 78.57
Unskilled labourer day 450.00 70.00 31,500.00 4,500.00
Item Type Material 0.00
Contingency L.S. 1,150.00 1.00 1,150.00 164.29
Hire cost of scaffolding materials (Deck slab) sq. metre 138.00 1.00 138.00 19.71
Basic Unit Price of Specification Item : 5,380.43
Plus Profit at 5% 269.02
Plus Overhead at 3.00% 161.41
Sub-Total : 5,810.86
Plus Tax & VAT at 16.2791% 945.95
Total Unit Price of Specification Item : 6,756.82
6,757.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 05/16/02
Item Name Steel Beam (W 530 x 167)
Unit of Measurement Lin. Metre
Quantity for Estimation 20.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hydraulic Jack day 325.00 4.00 1,300.00 65.00
Kato Crane (upto 5 tonne) no. 4,600.00 1.00 4,600.00 230.00
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 42.50
Skilled Labour day 550.00 4.00 2,200.00 110.00
Unskilled labourer day 450.00 8.00 3,600.00 180.00
Item Type Material 0.00
Steel Beam (W530 x 167) metre 50,000.00 3.34 167,150.00 8,357.50
Wooden sleeper L.S. 358.33 1.00 358.33 17.92
Basic Unit Price of Specification Item : 9,002.92
Plus Profit at 5% 450.15
Plus Overhead at 3.00% 270.09
Sub-Total : 9,723.15
Plus Tax & VAT at 16.2791% 1,582.84
Total Unit Price of Specification Item : 11,305.99
11,306.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Division 6 - Incidentals

Item Code 06/01/01


Item Name Grouted Riprap Pavement
Unit of Measurement sq. metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 0.50 25.00 25.00
Item Type Labour 0.00
Masons day 700.00 0.25 175.00 175.00
Unskilled labourer day 450.00 0.25 112.50 112.50
Item Type Material 0.00
Cement tonne 9,000.00 0.04 315.00 315.00
Coarse Sand FM>2.5 cu. metre 1,850.00 0.05 92.50 92.50
Gravel (as dug) cu. metre 2,850.00 0.10 285.00 285.00
Sylhet boulders 100-200mm cu. metre 6,500.00 0.20 1,300.00 1,300.00
Basic Unit Price of Specification Item : 2,305.00
Plus Profit at 5% 115.25
Plus Overhead at 3.00% 69.15
Sub-Total : 2,489.40
Plus Tax & VAT at 16.2791% 405.25
Total Unit Price of Specification Item : 2,894.65
2,895.00

Assumption : The rate is based on supply and placement of boulders on a prepared bed of 50-100mm free draining sand or gravel. The the joints are filled with mortar.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/01/02
Item Name Concrete Slope Protection
Unit of Measurement sq. metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 0.13 260.00 26.00
Small hand tools (2) day 50.00 2.00 100.00 10.00
Item Type Labour 0.00
Masons day 700.00 0.38 262.50 26.25
Unskilled labourer day 450.00 1.63 731.25 73.13
Item Type Material 0.00
Cement tonne 9,000.00 0.28 2,475.00 247.50
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 0.77 5,425.00 542.50
G.I wire, nails etc kg 120.00 1.00 120.00 12.00
Polythene sheet sq. metre 18.00 10.00 180.00 18.00
Reinforcing bar grade 60 tonne 62,500.00 0.06 3,843.75 384.38
Sand FM>1.0 cu. metre 640.00 0.45 213.75 21.38
Basic Unit Price of Specification Item : 1,361.12
Plus Profit at 5% 68.06
Plus Overhead at 3.00% 40.83
Sub-Total : 1,470.01
Plus Tax & VAT at 16.2791% 239.30
Total Unit Price of Specification Item : 1,709.32
1,709.00

Assumption : Concrete Slope protection must be carried out as detailed on the drawings. For this Rate build up the following assumptions have been made:- (1) Class of
Concrete is 20N/sq.mm. (2) Thickness of concrete layer is 100mm (3) reinforcement taken as 10mm bar spanning 2way at 200mm c/c. The slope to be

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/01/03
Item Name Loose stone Riprap Protection
Unit of Measurement cu metre
Quantity for Estimation 15.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Country Boat (1 ton capacity) day 2,000.00 1.00 2,000.00 133.33
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 56.67
Unskilled labourer day 450.00 5.00 2,250.00 150.00
Item Type Material 0.00
Sylhet boulders 100-200mm cu. metre 6,500.00 15.00 97,500.00 6,500.00
Basic Unit Price of Specification Item : 6,840.00
Plus Profit at 5% 342.00
Plus Overhead at 3.00% 205.20
Sub-Total : 7,387.20
Plus Tax & VAT at 16.2791% 1,202.57
Total Unit Price of Specification Item : 8,589.77
8,590.00

Assumption : Hire a country boat of 1 ton capacity & dumping the boulder of not less than 10 kg. each to the spot by the above mentioned labour, material and equipment,
etc.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/01/04
Item Name Concrete Cut-Off
Unit of Measurement cu metre
Quantity for Estimation 20.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Concrete Mixer (7/5) day 2,000.00 1.00 2,000.00 100.00
Concrete Poker Vibrator day 600.00 1.00 600.00 30.00
Small hand tools (2) day 50.00 131.00 6,550.00 327.50
Water Pump day 1,200.00 5.00 6,000.00 300.00
Item Type Labour 0.00
Masons day 700.00 32.00 22,400.00 1,120.00
Semi-skilled labourer day 500.00 13.00 6,500.00 325.00
Unskilled labourer day 450.00 86.00 38,700.00 1,935.00
Item Type Material 0.00
Cement tonne 9,000.00 6.20 55,800.00 2,790.00
Coarse Sand FM>2.5 cu. metre 1,850.00 4.20 7,770.00 388.50
Crushed boulder/gravel aggregate <25mm cu. metre 7,000.00 17.00 119,000.00 5,950.00
G.I wire, nails etc kg 120.00 16.55 1,986.00 99.30
Reinforcing bar grade 60 tonne 62,500.00 0.53 33,125.00 1,656.25
Wooden form work using 4 times cu. metre 80.00 4.00 320.00 16.00
Basic Unit Price of Specification Item : 15,037.55
Plus Profit at 5% 751.88
Plus Overhead at 3.00% 451.13
Sub-Total : 16,240.55
Plus Tax & VAT at 16.2791% 2,643.81
Total Unit Price of Specification Item : 18,884.36
18,884.00

Assumption : In order to calculate the rate for the cut off wall assumptions must be made as to how the area is made dry. In summer the river maybe naturally dry but this
would be a rare case. Otherwise this maybe achieved by forming a bund in the river and then baling out the area, excavating, casting concrete and then after

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/02/01
Item Name Reinforced Concrete Culvert Pipe - Class A bedding
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 0.75 37.50 37.50
Item Type Labour 0.00
Masons day 700.00 0.25 175.00 175.00
Semi-skilled labourer day 500.00 0.33 166.50 166.50
Unskilled labourer day 450.00 0.50 225.00 225.00
Item Type Material 0.00
Brick flat soling sq. metre 478.00 1.00 478.00 478.00
Cement Concrete Class 20 cu. metre 17,232.06 0.16 2,688.20 2,688.20
RCC pipe 600mm dia lin. metre 1,000.00 1.00 1,000.00 1,000.00
Basic Unit Price of Specification Item : 4,770.20
Plus Profit at 5% 238.51
Plus Overhead at 3.00% 143.11
Sub-Total : 5,151.82
Plus Tax & VAT at 16.2791% 838.67
Total Unit Price of Specification Item : 5,990.49
5,990.00

Assumption : Class A Bedding is assummed to be brick flat soling overlaid by 150mm thick concrete bed and the concrete surround is up to 1/3rd of diameter of pipe and
the bed and surround extends from the edge of the pipe upto the trench face - allow 200mm each side. This assumes that the trench has been carefully

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/02/02
Item Name Reinforced Concrete Culvert Pipe - Class B bedding
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (2) day 50.00 1.50 75.00 75.00
Item Type Labour 0.00
Masons day 700.00 0.50 350.00 350.00
Unskilled labourer day 450.00 1.00 450.00 450.00
Item Type Material 0.00
Coarse Sand FM>2.5 cu. metre 1,850.00 0.20 370.00 370.00
R.C.C Pipe dia 600mm (wall 50mm) lin. metre 1,000.00 1.00 1,000.00 1,000.00
Basic Unit Price of Specification Item : 2,245.00
Plus Profit at 5% 112.25
Plus Overhead at 3.00% 67.35
Sub-Total : 2,424.60
Plus Tax & VAT at 16.2791% 394.70
Total Unit Price of Specification Item : 2,819.30
2,819.00

Assumption : Class B bedding is assumed to be sylhet sand bed 200mm thick.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/03/01
Item Name Manhole (Diameter to be stated in the BoQ)
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/03/02
Item Name Catch Basin (Diameter to be stated in the BoQ)
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/03/03
Item Name Concrete Side Ditch/ U-Drain
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/03/04
Item Name Brick Headwall to Culvert Pipe ( Pipe diameter to be
stated in the BoQ)
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/04/01
Item Name Concrete Kerb (as detailed on the drawings)
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/04/02
Item Name Combined Concrete Kerb and Gutter (as detailed on
the drawings)
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/05/01
Item Name Road Marking Thermoplastic Material (by spray) 3mm Thick.
Unit of Measurement sq.m
Quantity for Estimation 350.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Boiler/Heater (1) day 8,000.00 1.00 8,000.00 22.86
Spreader day 8,000.00 1.00 8,000.00 22.86
Truck (5 Tonne) day 7,000.00 1.00 7,000.00 20.00
Item Type Labour 0.00
Foreman day 850.00 3.00 2,550.00 7.29
Skilled labourer day 550.00 7.00 3,850.00 11.00
Unskilled labourer day 450.00 10.00 4,500.00 12.86
Item Type Material 0.00
Tharmoplastic Materials kg 121.40 2,100.00 254,940.00 728.40
Glass beads kg 121.40 175.00 21,245.00 60.70
Chalk Powder, brush etc. L.S 500.00 1.43
Basic Unit Price of Specification Item : 887.39
Plus Profit at 5% 44.37
Plus Overhead at 3.00% 26.62
Sub-Total : 958.38
Plus Tax & VAT at 16.2791% 156.01
Total Unit Price of Specification Item : 1,114.39
1,114.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/05/02
Item Name Road Marking - Road marking Paint
Unit of Measurement Sq Metre
Quantity for Estimation 100.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment

Item Type Labour


Painter day 700.00 1.00 700.00 7.00
Painter Helper day 550.00 2.00 1,100.00 11.00
Unskilled labourer day 450.00 2.00 900.00 9.00
Item Type Material 0.00
Paint (Road Marking Berger brand) Lit. 725.00 50.00 36,250.00 362.50
Thiner (Jensolin T-4) Berger brand Lit. 230.00 2.50 575.00 5.75
Chalk Powder, Ware brush, Cowar Brush, Scraper, etc. L.S 200.00 2.00
Basic Unit Price of Specification Item : 397.25
Plus Profit at 5% 19.86
Plus Overhead at 3.00% 11.92
Sub-Total : 429.03
Plus Tax & VAT at 16.2791% 69.84
Total Unit Price of Specification Item : 498.87
499.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/05/03
Item Name Reflecting Road Studs
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Reflecting Road Studs No. 730.00 1.00 730.00 730.00
Basic Unit Price of Specification Item : 730.00
Plus Profit at 5% 36.50
Plus Overhead at 3.00% 21.90
Sub-Total : 788.40
Plus Tax & VAT at 16.2791% 128.34
Total Unit Price of Specification Item : 916.74
917.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/05/04
Item Name Application of Ballotini
Unit of Measurement Sq Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Ballotini kg 200.00 0.50 100.00 100.00
Basic Unit Price of Specification Item : 100.00
Plus Profit at 5% 5.00
Plus Overhead at 3.00% 3.00
Sub-Total : 108.00
Plus Tax & VAT at 16.2791% 17.58
Total Unit Price of Specification Item : 125.58
126.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/06/01
Item Name Topsoil
Unit of Measurement cu metre
Quantity for Estimation 5.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 2.00 100.00 20.00
Item Type Labour 0.00
Semi-skilled labourer day 500.00 0.30 150.00 30.00
Unskilled labourer day 450.00 2.00 900.00 180.00
Item Type Material 0.00
Topsoil cu. metre 210.00 5.00 1,050.00 210.00
Basic Unit Price of Specification Item : 440.00
Plus Profit at 5% 22.00
Plus Overhead at 3.00% 13.20
Sub-Total : 475.20
Plus Tax & VAT at 16.2791% 77.36
Total Unit Price of Specification Item : 552.56
553.00

Assumption : The rate is an average all in rate from recent RHD contracts.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/07/01
Item Name Grass Sodding
Unit of Measurement Sq Metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour
Unskilled labourer day 450.00 0.75 337.50 33.75
Basic Unit Price of Specification Item : 33.75
Plus Profit at 5% 1.69
Plus Overhead at 3.00% 1.01
Sub-Total : 36.45
Plus Tax & VAT at 16.2791% 5.93
Total Unit Price of Specification Item : 42.38
42.00

Assumption : The rate quoted is an average all in rate, inclusive of all material, labour and plant costs, taken from recent RHD contracts.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/07/02
Item Name Grass Turfing
Unit of Measurement Sq Metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour
Unskilled labourer day 450.00 0.75 337.50 33.75
Basic Unit Price of Specification Item : 33.75
Plus Profit at 5% 1.69
Plus Overhead at 3.00% 1.01
Sub-Total : 36.45
Plus Tax & VAT at 16.2791% 5.93
Total Unit Price of Specification Item : 42.38
42.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/08/01
Item Name Guardrail
Unit of Measurement Lin. Metre
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/09/01
Item Name Concrete Monument
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/09/02
Item Name Concrete Post
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Unit of Quantity
Item Name Unit Rate Price for Estimation QuantityU nit Price
Measurement Required
Item Category :
Item Type :
0.00 0.00 0.00 0.00
Basic Unit Price of Specification Item : 0.00
Plus Profit at 5% 0.00
Plus Overhead at 3.00% 0.00
Sub-Total : 0.00
Plus Tax & VAT at 16.2791% 0.00
Total Unit Price of Specification Item : 0.00
0.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/10/01
Item Name Traffic Signs
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Traffic Sign no. 4,500.00 1.00 4,500.00 4,500.00
Basic Unit Price of Specification Item : 4,500.00
Plus Profit at 5% 225.00
Plus Overhead at 3.00% 135.00
Sub-Total : 4,860.00
Plus Tax & VAT at 16.2791% 791.16
Total Unit Price of Specification Item : 5,651.16
5,651.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/10/02
Item Name Sign Post
Unit of Measurement Number
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Sign post (50/75mm dia Wall thickness 2mm minmum) no. 2,500.00 1.00 2,500.00 2,500.00
Basic Unit Price of Specification Item : 2,500.00
Plus Profit at 5% 125.00
Plus Overhead at 3.00% 75.00
Sub-Total : 2,700.00
Plus Tax & VAT at 16.2791% 439.53
Total Unit Price of Specification Item : 3,139.53
3,140.00

Assumption : The rate is an average rate for recent RHD Contracts

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/11/01
Item Name Rumble strips (Bituminous Concrete Volume)
Unit of Measurement cum
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Bitumen Heater (Ter Boiler) day 1,000.00 2 2,000.00 200.00
Rickshaw Van day 600.00 2 1,200.00 120.00
Small hand tools (2) day 50.00 33 1,650.00 165.00
Item Type Labour 0.00
Asphalt Mistry day 700.00 6 4,200.00 420.00
Masons day 700.00 2 1,400.00 140.00
Semi skilled labourer day 500.00 7 3,500.00 350.00
Unskilled labourer day 450.00 19 8,550.00 855.00
Item Type Material 0.00
Bitumen tonne 54,000.00 0.97 52,380.00 5,238.00
Sand FM>2.5 cu. metre 1,850.00 5.25 9,712.50 971.25
Crushed stone (with maximum graded size 6-8mm) cu. metre 5,700.00 6.50 37,050.00 3,705.00
Crusher (stone) dust cu. metre 4,000.00 1.25 5,000.00 500.00
Firewood tonne 6,000.00 0.54 3,240.00 324.00
Basic Unit Price of Specification Item : 12,988.25
Plus Profit at 5% 649.41
Plus Overhead at 3.00% 389.65
Sub-Total : 14,027.31
Plus Tax & VAT at 16.2791% 2,283.52
Total Unit Price of Specification Item : 16,310.83
16,311.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/11/02
Item Name Road Marking Thermoplastic Material (by spray)
Unit of Measurement sq.m
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Type Material
sq. metre 858.67 1 858.67 858.67
Thermoplastic paint (Asparagus) (3mm) the cost includes all material,
labour, suface cleaning, heating, machanical application device etc.
Basic Unit Price of Specification Item : 858.67
Plus Profit at 5% 42.93
Plus Overhead at 3.00% 25.76
Sub-Total : 927.36
Plus Tax & VAT at 16.2791% 150.97
Total Unit Price of Specification Item : 1,078.33
1,078.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 6/12/01
Item Name Geotextile Filter Fabric (as detailed on the Drawings)
Unit of Measurement Sq Metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Plate Compactor day 900.00 0.13 112.50 11.25
Small hand tools (2) day 50.00 0.50 25.00 2.50
Item Type Labour 0.00
Masons day 700.00 0.19 131.25 13.13
Unskilled labourer day 450.00 0.31 140.63 14.06
Item Type Material 0.00
Geotextile sq. metre 120.00 11.00 1,320.00 132.00
Basic Unit Price of Specification Item : 172.94
Plus Profit at 5% 8.65
Plus Overhead at 3.00% 5.19
Sub-Total : 186.77
Plus Tax & VAT at 16.2791% 30.40
Total Unit Price of Specification Item : 217.18
217.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 6/12/02
Item Name Furnishing and installing Matress (as detailed on the drawings)
Unit of Measurement Sq Metre
Quantity for Estimation 12.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Small hand tools (1) day 50.00 5.00 250.00 20.83
Item Type Labour 0.00
Masons day 700.00 1.00 700.00 58.33
Unskilled labourer day 450.00 3.00 1,350.00 112.50
Item Type Material 0.00
1st Class Brick no. 8.00 906.00 7,248.00 604.00
G.I wire, nails etc kg 100.00 1.00 100.00 8.33
Matressing sq. metre 100.00 27.00 2,700.00 225.00
Reinforcing bar grade 60 tonne 62,500.00 0.05 2,941.25 245.10
Basic Unit Price of Specification Item : 1,274.10
Plus Profit at 5% 63.71
Plus Overhead at 3.00% 38.22
Sub-Total : 1,376.03
Plus Tax & VAT at 16.2791% 224.01
Total Unit Price of Specification Item : 1,600.04
1,600.00

Assumption : GI woven Mesh Matresses are an imported item in Bangladesh and as such the rate will depend not only on the quantity of work to be done but also the
current market prices for the matresses.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 6/13/01(a)
Item Name Bullah Palisiding
Unit of Measurement Lin. Metre
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire of Piling Winch (Bullah Piles) day 1,100.00 1.00 1,100.00 183.33
Small hand tools (1) day 50.00 23.00 1,150.00 191.67
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 141.67
Masons day 700.00 3.00 2,100.00 350.00
Semi-skilled labourer day 500.00 5.00 2,500.00 416.67
Unskilled labourer day 450.00 14.00 6,300.00 1,050.00
Item Type Material 0.00
Bullah Pile 6m Long (Dia 150-175mm) No. 2,700.00 11.00 29,700.00 4,950.00
Bullah pile 4m long (Dia. 150-200mm) No. 1,500.00 1.50 2,250.00 375.00
Drum Sheet No 130.00 7.00 910.00 151.67
Nail kg 120.00 2.50 300.00 50.00
Nut bolt 16mm No 35.00 22.00 770.00 128.33
Basic Unit Price of Specification Item : 7,988.33
Plus Profit at 5% 399.42
Plus Overhead at 3.00% 239.65
Sub-Total : 8,627.40
Plus Tax & VAT at 16.2791% 1,404.46
Total Unit Price of Specification Item : 10,031.86
10,032.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 6/13/01b
Item Name Bullah Palisiding (Local Bullah: 150mm-200mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 6.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Hire of Piling Winch (Bullah Piles) day 1,100.00 1.00 1,100.00 183.33
Small hand tools (1) day 50.00 23.00 1,150.00 191.67
Item Type Labour 0.00
Foreman day 850.00 1.00 850.00 141.67
Masons day 700.00 3.00 2,100.00 350.00
Semi-skilled labourer day 500.00 5.00 2,500.00 416.67
Unskilled labourer day 450.00 14.00 6,300.00 1,050.00
Item Type Material 0.00
Bullah Pile 6m Long (Dia 150-200mm) No. 1,700.00 11.00 18,700.00 3,116.67
Bullah pile 4m long (Dia. 150-200mm) No. 1,100.00 1.50 1,650.00 275.00
Drum Sheet No 130.00 7.00 910.00 151.67
Nail kg 120.00 2.50 300.00 50.00
Nut bolt 16mm No 35.00 22.00 770.00 128.33
Basic Unit Price of Specification Item : 6,055.00
Plus Profit at 5% 302.75
Plus Overhead at 3.00% 181.65
Sub-Total : 6,539.40
Plus Tax & VAT at 16.2791% 1,064.55
Total Unit Price of Specification Item : 7,603.95
7,604.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 6/14/01
Item Name Mobilization for deck slab repairing work, etc
Unit of Measurement Lin. Metre
Quantity for Estimation 10.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Equipment
Flat Bed truck (5 tons) day 7,000.00 1.00 7,000.00 700.00
Item Type Labour 0.00
Flagman day 550.00 2.00 1,100.00 110.00
Item Type Material 0.00
Construction warning signs, etc L.S. 1,200.00 1.00 1,200.00 120.00
Basic Unit Price of Specification Item : 930.00
Plus Profit at 5% 46.50
Plus Overhead at 3.00% 27.90
Sub-Total : 1,004.40
Plus Tax & VAT at 16.2791% 163.51
Total Unit Price of Specification Item : 1,167.91
1,168.00

Assumption : Considering the mobilization for 10 sq. meter of deck slab repairing work can do in a day by the above mentioned equipment, labour and material, etc.

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/15/01
Item Name Concrete Guide Post (1.6 m long, 200mm dia)
Unit of Measurement No.
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Concrete cum 21,220.95 0.0502 1,065.29 1,065.29
Reinforcement tonne 62500.00 0.0075 468.75 468.75
Painting sqm 150.00 0.6280 94.2000 94.20
Placing No. 250.00 1.00 250.00 250.00
Basic Unit Price of Specification Item : 1,878.24
Plus Profit at 5% 93.91
Plus Overhead at 3.00% 56.35
Sub-Total : 2,028.50
Plus Tax & VAT at 16.2791% 330.22
Total Unit Price of Specification Item : 2,358.72
2,359.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/16/01
Item Name Concrete Kilometer Post (As per drawing)
Unit of Measurement No.
Quantity for Estimation 1.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Material
Roadway Excavation in unsuitable Material cum 163.58 0.5060 82.77 82.77
Sand Backfill for Structures cum 1,042.20 0.1518 158.21 158.21
Single Layer Brick Flat Soling sqm 420.20 1.0120 425.2424 425.24
Concrete Class10 cum 9,724.83 0.1012 984.15 984.15
Concrete Class 20 cum 14,481.00 0.2854 4132.88 4,132.88
Mild Steel Reinforcement Bars tonne 62,500.00 0.0077 481.25 481.25
6 mm thick cement sand(F.M1.2) plaster sqm 150.00 1.8288 274.32 274.32
Painting to post etc. 2(two) coat sqm 200.00 1.8288 365.76 365.76
Lettering on both side of km post with 10cm size L.S. 1.50 200.0000 300.00 300.00
Basic Unit Price of Specification Item : 7,204.58
Plus Profit at 5% 360.23
Plus Overhead at 3.00% 216.14
Sub-Total : 7,780.95
Plus Tax & VAT at 16.2791% 1,266.67
Total Unit Price of Specification Item : 9,047.61
9,048.00

Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/17/01(a)
Item Name RCC Palisiding (4m post, 200mm X 200mm)
Unit of Measurement Lin. Metre
Quantity for Estimation 45.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour
i) Skilled labour nos 550.00 36.00 19,800.00 440.00
ii) Ordinary labour nos 450.00 108.00 48,600.00 1,080.00
Item Type Equipment 0.00
Hire charge of monkey with driving arrangement. L.S. 3200.00 1.00 3,200.00 71.11
Item Type Material 0.00
Concrete Class 25 cum 12,968.35 12.89 167,097.25 3,713.27
Mild Steel Reinforcement Bars tonne 72,625.00 1.697 123,244.62 2,738.77
Nuts, bolts, washers etc nos 80.00 102.0000 8160.00 181.33
Basic Unit Price of Specification Item : 8,224.49
Plus Profit at 5% 411.22
Plus Overhead at 3.00% 246.73
Sub-Total : 8,882.44
Plus Tax & VAT at 16.2791% 1,445.98
Total Unit Price of Specification Item : 10,328.42
10,328.00
Assumption :

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/17/01(b)
Item Name RCC Palisiding (3m post, 150mm X 150mm)
Unit of Measurement Linear Metre
Quantity for Estimation 45.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour
i) Skilled labour nos 550.00 36.00 19,800.00 440.00
ii) Ordinary labour nos 450.00 108.00 48,600.00 1,080.00
Item Type Equipment 0.00
Hire charge of monkey with driving arrangement. L.S. 3200.00 1.00 3,200.00 71.11
Item Type Material 0.00
Concrete Class 25 cum 12,968.35 8.17 105,919.03 2,353.76
High Yield Reinforcement tonne 72,625.00 0.803 58,317.87 1,295.95
Nuts, bolts, washers etc nos 80.00 102.0000 8160.00 181.33
Basic Unit Price of Specification Item : 5,422.15
Plus Profit at 5% 271.11
Plus Overhead at 3.00% 162.66
Sub-Total : 5,855.93
Plus Tax & VAT at 16.2791% 953.29
Total Unit Price of Specification Item : 6,809.22
6,809.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


Item Code 06/17/01(c)
Item Name RCC Palisiding (8m post, 300mm X 300mm)
Unit of Measurement Linear Metre
Quantity for Estimation 45.00 (All Prices Are in Taka)

Specification Item Components


Price for
Unit of Quantity
Item Name Unit Rate Estimation Unit Price
Measurement Required
Quantity
Item Category Primary Item
Item Type Labour
i) Skilled labour nos 550.00 36.00 19,800.00 440.00
ii) Ordinary labour nos 450.00 108.00 48,600.00 1,080.00
Item Type Equipment 0.00
Hire charge of monkey with driving arrangement. L.S. 3200.00 1.00 3,200.00 71.11
Item Type Material 0.00
Concrete Class 25 cum 12,968.35 46.06 597,289.98 13,273.11
Mild Steel Reinforcement Bars tonne 72,625.00 7.5 544,687.49 12,104.17
Nuts, bolts, washers etc nos 80.00 102.0000 8160.00 181.33
Basic Unit Price of Specification Item : 27,149.72
Barisal Zone did not provide any reasonable drawing,
estimate or Analysis for this item Plus Profit at 5% 1,357.49
Plus Overhead at 3.00% 814.49
Sub-Total : 29,321.70
Plus Tax & VAT at 16.2791% 4,773.30
Total Unit Price of Specification Item : 34,095.00
34,095.00

Dhaka_Mymensingh_Cumilla Zone Rate Analysis 2018


RHD Schedule of Rates 2018 for Dhaka, Mymensingh & Cumilla Zone
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Division 1 - General & Site Facilities


1 1/1/01 Maintenance and Protection of Traffic Lump Sum 80,257.00 144,431.00 79.96%

Maintain Temp.Structures & Equipment for the


2 1/1/02 day 1,913.00 2,218.00 15.94%
Maintenance and Protection of Traffic

3 1/2/01 Supply, Erect and Remove Field Office for Engineer Lump Sum 249,497.00 254,930.00 2.18%

Maintenance, Staffing, Security and Cleaning of the


4 1/2/02 Month 11,000.00 50,233.00 356.66%
Field Office for the Engineer

5 1/2/03 Provision of Office Equipment and Consumables Month 7,700.00 7,868.00 2.18%

6 1/2/04 Provision, Maintenance and Removal of Sign Boards Lump Sum 8,849.00 9,042.00 2.18%

7 1/2/05 Provision and Maintenance of Survey Equipment month 897.00 917.00 2.23%

8 1/2/07 Progress Photographs Month 1,000.00 1,022.00 2.20%

9 1/3/01 Provide and Remove Site Laboratory & Equipment Lump Sum 331,843.00 339,070.00 2.18%

10 1/3/02 Maintain Site Laboratory Month 7,699.00 7,866.00 2.17%

11 1/3/03 Special or Additional Tests Pro. Sum - -

12 1/4/01 Saloon Car 1200cc Capacity Month 55,000.00 119,302.00 116.91%

13 1/4/02 Pick- up (Double Cab) Month 66,000.00 169,535.00 156.87%

14 1/4/03 Four Wheel Drive Vehicle Min. 6 seats Month 77,799.00 295,116.00 279.33%

15 1/4/04 Motor Cycle 125cc Month 4,425.00 5,651.00 27.71%

16 1/4/05 Motor Boat min 5m length Month 16,500.00 16,859.00 2.18%

Provision, Operation and Maintenance of Micrbus Min.


17 01/04/06 Month 166,395.00
10 seats
Provision, Operation and Maintenance of Micrbus Min.
18 01/04/07 Month 150,698.00
7 seats
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Division 2 – Earthwork
1 2/1/01 Clearing and Grubbing sq. metre 45.00 55.00 22.22%

2 2/2/01 Roadway Excavation in Unsuitable Soil cu metre 171.00 205.00 19.88%

3 2/2/02 Roadway Excavation in Suitable Soil cu metre 171.00 144.00 -15.79%

Roadway Excavation in Existing Pavement ( not


4 2/2/03 cu metre 265.00 107.00 -59.62%
reinforced concrete)
Roadway Excavation in Existing Reinforced Concrete
5 2/2/04 cu metre 1,198.00 1,414.00 18.03%
Pavement
Deduction of Value of Suitable Soil Recovered from
6 2/2/05 cu metre 92.00 210.00 128.26%
Existing Road
Deduction of Value of Materials Recovered from
7 2/2/06 cu metre 2,212.00 2,270.00 2.62%
existing Road Pavement

8 2/4/01 Channel Excavation in Unsuitable Materials cu metre 173.00 211.00 21.97%

9 2/4/02 Channel Excavation in Suitable Material cu metre 173.00 211.00 21.97%

10 2/5/01 Excavation and Backfill for Structures cu metre 360.00 447.00 24.17%

11 2/5/02 Concrete Backfill for Structures cu metre 10,197.00 12,533.00 22.91%

12 2/5/03 Sand Backfill for Structures cu metre 1,174.00 1,309.00 11.50%

13 2/06/1(a) Embankment Fill from Excavation on site. cu metre 245.00 144.00 -41.22%

Embankment Fill from Excavation in Borrow pit within


14 2/06/1(b) cu metre 235.00 217.00 -7.66%
the Right -of-way
Embankment fill from borrow pit in contractor's
15 2/6/02 cu metre 309.00 410.00 32.69%
Arranged land

16 2/6/03 Sand Backfill to Swamp cu metre 468.00 791.00 69.02%

17 2/7/01 Preparation of Subgrade 300 mm Depth sq. metre 69.00 24.00 -65.22%

18 2/7/02 Preparation of Subgrade 450 mm depth sq. metre 103.00 40.00 -61.17%

19 2/8/01 Improved Subgrade cu metre 916.00 1,043.00 13.86%

Dismantling Existing Structure including disposal of


20 * 2/9/01 Lump Sum
spoil and backfilling.
Dismanting Portions of Existing Structure including
21 * 2/9/02 Lump Sum
stockpiling of materials.
Deduction of the Value of Recovered Materials from
22 * 2/09/3(a) Lump Sum
Structures
Deduction of the Value of Recovered Materials from
23 * 2/09/3(b) Lump Sum
Structures

24 2/10/01 Construction of Soil Earthen Shoulders cu metre 259.00 838.00 223.55%

25 2/12/01 Subgrade Drains Lin. Metre 270.00 385.00 42.59%

* Rate for this Item shall be analysed as per actual


requirement
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Division 3 – Pavement work


Scarify, Mix and Recompact Existing Pavement and/or
1 3/1/01 sq. metre 48.00 38.00 -20.83%
Shoulder
2 3/1/02 Repair of Potholes on the Existing Pavement cu metre 15,733.00 21,452.00 36.35%
3 03/02/01 a Sub-Base cu metre 4,361.00 5,400.00 23.82%
4 03/02/01 b Sub-Base (with Paver) cu metre 5,588.00
5 03/03/01 a Aggregate Base Type I cu metre 6,566.00 8,832.00 34.51%
6 03/03/01 b Aggregate Base Type I (with Paver) cu metre 9,020.00
7 03/03/02 a Aggregate Base Type II cu metre 4,732.00 5,932.00 25.36%
8 03/03/02 b Aggregate Base Type II (with Paver) cu metre 6,120.00
9 03/06/1a Bituminous Prime Coat (Plant Placed) sq. metre 123.00 114.00 -7.32%
10 03/06/1b Bituminous Prime Coat (hand placed) sq. metre 121.00 109.00 -9.92%
11 03/07/1a Bituminous Tack Coat (Plant Work) sq. metre 48.00 51.00 6.25%
12 03/07/1b Bituminous Tack Coat (Labour intensive work) sq. metre 44.00 45.00 2.27%
13 3/8/01 Primer seal sq. metre 111.00 113.00 1.80%
Single Bituminous Surface Treatment 14mm nominal
14 03/09/1(a) size aggregate (Machine Method) (Bitumen Grade Sq Meter 204.00 232.00 13.73%
80/100)

Single Bituminous Surface Treatment 14mm nominal


15 03/09/1(b) size aggregate (Machine Method) (Bitumen Grade Sq Meter 211.00 235.00 11.37%
60/70)

Double Bituminous Surface Treatment-20mm nominal


16 3/09/02(a) size aggregate followed by 10mm (Machine Method) Sq Meter 395.00 423.00 7.09%
(Bitumen Grade 80/100)

Double Bituminous Surface Treatment-20mm nominal


17 3/09/2(b) size aggregate followed by 10mm (Machine Method) Sq Meter 407.00 428.00 5.16%
(Bitumen Grade 60/70)

Double Bituminous Surface Treatment-14mm nominal


18 3/09/02(c) size aggregate followed by 10mm (Machine Method) Sq Meter 330.00 368.00 11.52%
(Bitumen Grade 80/100)

Double Bituminous Surface Treatment-14mm nominal


19 3/09/2(d) size aggregate followed by 10mm (Machine Method) Sq Meter 340.00 337.00 -0.88%
(Bitumen Grade 60/70)

Dense Bituminous Surfacing-Base Course (Plant


20 03/10/1(a) cu meter 17,176.00 22,861.00 33.10%
Method) (Bitumen Grade 80/100)
Dense Bituminous Surfacing-Base Course (Plant
21 03/10/1(b) cu meter 19,906.00 23,144.00 16.27%
Method) (Bitumen Grade 60/70)
Dense Bituminous Surfacing - Wearing Course (Plant
22 03/10/2(a) cu meter 19,227.00 23,972.99 24.68%
Method) (Bitumen Grade 80/100)
Dense Bituminous Surfacing - Wearing Course (Plant
23 03/10/2(b) cu meter 19,906.00 24,325.00 22.20%
Method) (Bitumen Grade 60/70)
24 3/11/01 Premix Bituminous Carpeting cu metre 16,013.00 20,841.00 30.15%
25 3/12/02 12 mm Compacted Premix Bituminous Seal Coat sq. metre 166.00 185.00 11.45%
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %


26 3/12/03 15 mm Compacted Premix Bituminous Seal Coat sq. metre 215.00 227.00 5.58%
125 mm Thick Brick on End Edging
27 3/13/01 (a) Lin. Metre 103.00 199.00 93.20%
(1st Class)
125 mm Thick Brick on End Edging
28 3/13/01 (b) Lin. Metre 233.00
(Machine Made)
Single Layer Brick Flat Soling i/c 75mm thick
29 3/13/02 (a) sq. metre 478.00 555.00 16.11%
compacted sand cushion (1st Class)
Single Layer Brick Flat Soling i/c 75mm thick
30 3/13/02 (b) sq. metre 636.00
compacted sand cushion (Machine Made)
Herring Bond Brick Pavement i/c 12mm sand cushion
31 3/13/03 (a) sq. metre 633.00 780.00 23.22%
(1st Class)
Herring Bond Brick Pavement i/c 12mm sand cushion
32 3/13/03 (b) sq. metre 915.00
(Machine Made)
33 03/14/2(a) Dry Lean Concrete Class-20 (Concrete Mixture). cu meter 11,902.00 13,961.00 17.30%
Dry Lean Concrete Class-20 (Batching Plant without
34 03/14/2(b) cu meter 14,473.00 15,348.00 6.05%
Concrete Paver).
Dry Lean Concrete Class-20 (Batching Plant with
35 03/14/2(c) cu meter 14,688.00 15,537.00 5.78%
Concrete Paver).
Cement Concrete Pavement (Concrete Class-25)
36 03/15/1(a) cu meter 13,240.00 16,513.00 24.72%
(Concrete Mixture).
Cement Concrete Pavement (Concrete Class-25)
37 03/15/1(b) cu meter 17,142.00 17,882.00 4.32%
(Batching Plant without Concrete Paver).
Cement Concrete Pavement (Concrete Class-25)
38 03/15/1(c) cu meter 17,467.00 18,222.00 4.32%
(Batching Plant with Concrete Paver).
Precast RCC Pavement slab (Concrete Class-25)
39 03/15/1(d) cu meter 20,125.00 22,035.00 9.49%
(Batching Plant)
Cement Concrete Pavement (Concrete Class-30)
40 03/15/2(a) cu meter 14,107.00 17,375.00 23.17%
(Concrete Mixture).
Cement Concrete Pavement (Concrete Class-30)
41 03/15/2(b) cu meter 17,981.00 18,634.00 3.63%
(Batching Plant without Concrete Paver).
Cement Concrete Pavement (Concrete Class-30)
42 03/15/2(c) cu meter 18,343.00 18,990.00 3.53%
(Batching Plant with Concrete Paver).
Precast RCC Pavement slab (Concrete Class-30)
43 03/15/2(d) cu meter 21,381.00 22,911.00 7.16%
(Batching Plant)
Cement Concrete Pavement (Concrete Class-35)
44 03/15/3(a) cu meter 14,419.00 17,600.00 22.06%
(Concrete Mixture).
Cement Concrete Pavement (Concrete Class-35)
45 03/15/3(b) cu meter 18,329.00 18,815.00 2.65%
(Batching Plant without Concrete Paver).
Cement Concrete Pavement (Concrete Class-35)
46 03/15/3(c) cu meter 18,690.00 19,171.00 2.57%
(Batching Plant with Concrete Paver).
Precast RCC Pavement slab (Concrete Class-35)
47 03/15/3(d) cu meter 22,004.00 23,417.00 6.42%
(Batching Plant)
Cement Concrete Pavement (Concrete Class-40)
48 03/15/3(e) cu meter 19,054.00
(Batching Plant without Concrete Paver).
Cement Concrete Pavement (Concrete Class-40)
49 03/15/3(f) cu meter 19,410.00
(Batching Plant with Concrete Paver).
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Division 4 – Foundation work


1 04/01/1a Bored Cast in Place Piles (dia. 400mm) Lin. Metre 2,022.00 2,461.00 21.71%
2 04/01/1b Bored Cast in Place Piles [dia 600mm] Lin. Metre 4,595.00 5,592.00 21.70%
3 04/01/1c Bored pile cast in place piles (dia 750 mm) Lin. Metre 7,214.00 8,818.00 22.23%
4 04/01/1d Bored cast in place Piles (dia 900mm) Lin. Metre 10,651.00 13,129.00 23.27%
5 04/01/1e Bored cast in Place Piles (dia 1000mm) Lin. Metre 12,551.00 15,406.00 22.75%
6 04/01/1f Bored cast in Place Piles (dia 1200mm) Lin. Metre 18,585.00 22,813.00 22.75%
7 04/01/1g Bored cast in Place Piles (dia 1500mm) Lin. Metre 33,131.00 40,667.00 22.75%
9 4/1/04 High Yield Deformed Steel Reinforcing Bars Tonne 95,236.00 92,710.00 -2.65%
10 04/01/5a Permanent steel Casing (6mm thick ,dia 400mm) Lin. Metre 7,104.00 8,001.00 12.63%
11 04/01/5b Permanent steel casing (6mm thick,dia 600mm) Lin. Metre 10,287.00 11,625.00 13.01%
12 04/01/5c Permanent steel casing (6mm thick, dia750mm) Lin. Metre 12,801.00 14,471.00 13.05%
13 04/01/5d Permanent steel casing (10mm thick, 600mm dia) Lin. Metre 16,467.00 18,683.00 13.46%
14 04/01/5e Permanent steel casing (10mm thick, 750mm dia) Lin. Metre 20,546.00 23,315.00 13.48%
15 04/01/05f Permanent steel casing (10mm thick, 900mm dia) Lin. Metre 24,578.00 27,899.00 13.51%
16 04/01/5g Permanent steel casing (10 mm thick, 1000mm dia) Lin. Metre 27,199.00 30,887.00 13.56%
17 04/01/5h Permanent steel casing (10 mm thick, 1200mm dia) Lin. Metre 32,586.00 37,012.00 13.58%
18 04/01/5i Permanent steel casing (10 mm thick, 1500mm dia) Lin. Metre 40,495.00 46,022.00 13.65%
19 04/02/1a Driven Pre-cast Piles (a) 300x300mm Lin. Metre 1,892.00 2,239.00 18.34%
20 04/02/1b Driven Precast Piles (b) 350x350mm Lin. Metre 2,406.00 2,847.00 18.33%
21 04/02/1c Driven Pre-cast Pile (c) 400x400mm Lin. Metre 2,931.46 3,464.42 18.18%
22 4/2/02 Driven Precast Pilot Piles Lin. Metre 651.00 762.00 17.05%
24 4/2/04 High Yield Reinforcement Bars Tonne 95,236.00 92,710.00 -2.65%
25 4/3/01 King Post Lin. Metre 703.00 820.00 16.64%
26 4/3/02 Raker Piles (including Tie Bars) Lin. Metre 1,000.00 1,168.00 16.80%
27 4/3/03 Precast Planks (including Reinforcement Steel) Sq Metre 3,047.00 3,384.00 11.06%
High Yield Deformed Steel Reinforcing Bars to King
29 4/3/05 Tonne 95,236.00 92,710.00 -2.65%
Posts and Raker Piles
Load Test on Cast In Place Working Pile (Proof Load to
30 04/04/1a Number 91,730.00 99,486.00 8.46%
be specified in BoQ)50 Ton
31 04/04/1b Load test on cast in place piles (For 100 Ton) Number 160,170.00 174,847.00 9.16%
32 04/04/1c Load Test on cast in place piles (For 200 Ton) Number 274,951.00 299,600.00 8.96%
Load Test on Cast in Place Pilot Pile (Proof load to be
33 4/4/02 Number - -
specified in BoQ)
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Load Test on Pilot Driven Pile (Proof load to be


34 4/4/03 Number - -
specified in the BoQ)
35 4/5/01 Bitumen Slip Layer to Concrete Piles Sq Metre 254.00 222.00 -12.60%
Driven Bullah Piles ( Dimensions to be stated in BoQ)
36 04/06/1a Lin. Metre 688.00 724.00 5.23%
(125-150mm)
37 04/06/1b Driven Bullah Pile (150-175mm dia) Lin. Metre 767.00 808.00 5.35%
38 04/06/1c Driven Bullah Pile (175-200mm dia) Lin. Metre 928.00 975.00 5.06%
39 04/06/1d Driven Bullah Pile (200-225mm dia) Lin. Metre 1,108.00 1,167.00 5.32%
40 4/7/01 Cutting Edge (Well Shoe) Ton 106,348.00 110,072.00 3.50%
41 4/7/02 Class-20 Concrete for RCC Well cum 14,841.00 14,874.00 0.22%
42 4/7/03 Concrete in Top/Bottom Plugging cum 12,474.00 14,919.00 19.60%
Labor for Well Sinking (Size 5000mmX10000mm)
43 4/07/4(a) Metre 17,775.00 24,457.00 37.59%
Depth 0m-6m
Labor for Well Sinking (Size 5000mmX10000mm)
44 4/07/4(b) Metre 25,236.00 37,497.00 48.59%
Depth 6m-12m
Labor for Well Sinking (Size 5000mmX10000mm)
45 4/07/4(c) Metre 28,514.00 42,415.00 48.75%
Depth 12m-18m
Labor for Well Sinking (Size 5000mmX10000mm)
46 4/07/4(d) Metre 35,704.00 53,874.00 50.89%
Depth 18m-24m
Labor for Well Sinking (Size 5000mmX10000mm)
47 4/07/4(e) Metre 42,259.00 64,340.00 52.25%
Depth Above 24m
Labor for Well Sinking (Size 4270mmX7940mm) Depth
48 4/07/4(f) Metre 12,031.00 16,581.00 37.82%
0m-6m
Labor for Well Sinking (Size 4270mm X 7940mm)
49 4/07/4(g) Metre 17,254.00 25,650.00 48.66%
Depth 6m-12m
Labor for Well Sinking (Size 4270mmX7940mm) Depth
50 4/07/4(h) Metre 19,183.00 28,653.00 49.37%
12m-18m
Labor for Well Sinking (Size 4270mm X 7940mm)
51 4/07/4(i) Metre 23,966.00 36,272.00 51.35%
Depth 18m-24m
Labor for Well Sinking (Size 4270mm X 7940mm)
52 4/07/4(j) Metre 28,586.00 43,503.00 52.18%
Depth Above 24m
53 4/7/05 Sand Filling cum 1,175.00 1,309.00 11.40%
54 4/7/06 High Steel Reinforcement Bars Ton 95,236.00 93,966.00 -1.33%
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Division 5 -Structures
1 5/1/01 Single Layer Brick Flat Soling sq. metre 468.00 528.00 12.82%
Concrete Class as Detailed on Drawings (Class10)
2 05/01/2a cu metre 8,466.00 9,725.00 14.87%
(Concrete Mixer)
3 05/01/2b Concrete class-20 (Foundation) (Concrete Mixer) cu metre 11,925.00 14,481.00 21.43%
Concrete class - 20 (Vertical member col. pier,
4 05/01/2c cu metre 15,054.00 16,960.00 12.66%
abutment / wing wall,culvert etc.) (Concrete Mixer)
Concrete class-20 (Girder, cross girder,diaphram,beam
5 05/01/2d cu metre 15,989.00 19,408.00 21.38%
etc) (Concrete Mixer)
Concrete class-20 (Deck slab,side walk,wheel
6 05/01/2e cu metre 14,177.00 17,232.00 21.55%
guard,curb etc (Concrete Mixer)
7 05/01/02f Concrete class -20 (rail & post) (Concrete Mixer) cu metre 16,862.00 21,221.00 25.85%
8 05/01/2g Concrete Class - 25 (Foundation) (Concrete Mixer) cu metre 12,379.00 14,595.00 17.90%
Concrete class -25 (Vertical member col,
9 05/01/2h cu metre 14,224.00 17,047.00 19.85%
pier,abutment/wing wall,culvert etc) (Concrete Mixer)
Concrete class - 25 (Girder, beam, cross girder,and
10 05/01/02i cu metre 16,581.00 19,673.00 18.65%
diaphram etc) (Concrete Mixer)
Concrete class - 25 (RCC/CC Pavement work)
11 05/01/02j cu metre 14,799.00 17,852.00 20.63%
(Concrete Mixer)
Concrete class-30 (Deck slab, side walk, wheel
12 05/01/2k cu metre 15,526.00 18,232.00 17.43%
guard,curb etc (Concrete Mixer)
13 05/01/02l Concrete Class – 35 (Concrete Mixer) cu metre 24,067.00 28,715.00 19.31%
Concrete Class – 40 (Pre-stressed Girder) (Concrete
14 05/01/2m cu metre 24,558.00 29,150.00 18.70%
Mixer)
Concrete Class as Detailed on Drawings (Class10)
15 05/01/3a cu metre 10,131.00 10,509.00 3.73%
(Batching Plant)
16 05/01/3b Concrete class-20 (Foundation) (Batching Plant) cu metre 13,583.00 16,284.00 19.89%
Concrete class - 20 (Vertical member col. pier,
17 05/01/3c cu metre 15,390.00 18,728.00 21.69%
abutment / wing wall,culvert etc.) (Batching Plant)
Concrete class-20 (Girder, cross girder,diaphram,beam
18 05/01/3d cu metre 17,598.00 21,166.00 20.28%
etc) (Batching Plant)
Concrete class-20 (Deck slab,side walk,wheel
19 05/01/3e cu metre 15,790.00 18,990.00 20.27%
guard,curb etc) (Batching Plant)
20 05/01/3f Concrete class -20 (rail & post) (Batching Plant) cu metre 18,460.00 22,979.00 24.48%
21 05/01/3g Concrete Class - 25 (Foundation) (Batching Plant) cu metre 14,028.00 16,286.00 16.10%
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Concrete class -25 (Vertical member col,


22 05/01/3h cu metre 15,844.00 18,827.00 18.83%
pier,abutment/wing wall,culvert etc) (Batching Plant)
Concrete class - 25 (Girder, beam, cross girder,and
23 05/01/03i cu metre 18,199.00 21,417.00 17.68%
diaphram etc) (Batching Plant)
Concrete class - 25 (RCC/CC Pavement work)
24 05/01/03j cu metre 16,418.00 19,597.00 19.36%
(Batching Plant)
Concrete class-30 (Deck slab, side walk, wheel
25 05/01/03k cu metre 17,151.00 19,986.00 16.53%
guard,curb etc) (Batching Plant)
26 05/01/03l Concrete Class – 35 (Batching Plant) cu metre 24,795.00 29,222.00 17.85%
Concrete Class – 40 (Pre-stressed Girder) (Batching
27 05/01/3m cu metre 25,285.00 29,657.00 17.29%
Plant)
29 5/2/02 High Yield Reinforcement Bars Tonne 95,236.00 91,203.00 -4.23%
30 5/2/03 Wire Mesh Reinforcement Tonne 85,456.00 83,435.00 -2.36%
31 5/3/01 Prestressing Wire or Strand Tonne 273,590.00 278,585.00 1.83%
32 5/4/01 Modification to Existing Concrete cu metre 9,894.00 10,109.00 2.17%
33 5/4/02 Concrete Surface Repair Works (Superstructures) sq. metre 213.00 217.00 1.88%
34 5/4/03 Concrete Surface Repair Works (Substructures) sq. metre 283.00 289.00 2.12%
35 5/4/04 Resin Repair Mortars Kg
36 5/4/05 Cement Mortar in Cracks Lin. Metre 58.00 70.00 20.69%
37 5/4/06 Anchor and Tie Bars Tonne 1,966.00 2,009.00 2.19%
38 5/5/01 New and Extended Brickwork cu metre 7,408.00 8,896.00 20.09%
39 5/5/02 Brick Drainage Layer cu metre 4,444.00 5,902.00 32.81%
40 5/5/03 Replacement of Defective Existing brick cu metre 11,783.00 14,193.00 20.45%
41 5/5/04 Repointing of Existing Brickwork Joints sq. metre 533.00 622.00 16.70%

42 5/5/05 Steel Tie Bars and Pattress Plates Tonne - - -

43 5/6/01 Preparation and Painting of Existing Structures sq. metre 527.00 597.00 13.28%
44 5/7/01 Carriage of Bridge Steelwork from Port to Site Tonne - - -

45 5/7/02 Fixing of bearings for Unit Bridging Number - - -

Supply and Fixing of Elastomeric Bearings for


46 5/7/03 Number - - -
Composite Bridge Construction

47 5/7/04 Asssembly and Installation of Unit Bridging Lin. Metre - - -

Installation of Steelwork for Composite Bridge


48 5/7/05 Tonne - - -
Construction.
Installation of Steel Post and Barrier Parapet to
49 5/7/06 Lin. Metre - - -
Reinforced Concrete Deck Slab

Expansion Joint complete as detailed on the Drawings


50 5/8/01 in the location described in the BoQ. (Updated with Lin. Metre 2,680.00 2,944.00 9.85%
new drawing/2014)
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Bridge Deck Joint Complete as detailed on the


51 5/8/02 Lin. Metre - -
Drawings.
Provision and Fixing of drainage to structures as
52 5/9/01 Lump sum - -
detailed on the Drawings.

53 5/10/01 Embedment of Inserts and Fittings Lump Sum - -

Supply and Installation of Pot bearings (Size-


54 5/12/1(a) Number - -
500X500X72)
Supply and Installation of Pot bearings (Size-
55 5/12/1(b) Number - -
500X450X72)
Supply and Installation of Pot bearings (Size-
56 5/12/1(c) Number - -
400X300X72)

57 5/12/02 Supply and Installation of Shock Transmission units Number - -

Neoprene rubber bearing or Elastomeric bearing


58 5/13/1(a) Number 16,631.00 17,247.00 3.70%
supplying & fitting fixing, etc.
Neoprene rubber bearing or Elastomeric bearing
59 5/13/1(b) Number 19,334.00 20,009.00 3.49%
supplying & fitting fixing, (b) , etc.
Double Single Bailey Bridge or Acrow panel (Erecting
60 5/14/1(b) Lin. Metre 3,065.00 3,798.00 23.92%
and Assembling).
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Calender Hamilton Truss Bridge (Erecting and


61 5/14/1(c) Lin. Metre 11,197.00 12,897.00 15.18%
Assembling)
Double Single Bailey Bridge or Acrow panel
62 5/14/2(b) Lin. Metre 1,955.00 2,581.00 32.02%
(Delaunching).
63 5/14/2(c) Calender Hamilton Truss Bridge (Delaunching). Lin. Metre 7,301.00 8,916.00 22.12%
64 5/15/01 Mobilization for railing type work, etc. Lin. Metre 1,868.00 2,612.00 39.83%
65 5/16/01 Dismantling of deck slab, thickness 175mm. Sq Metre 5,998.00 6,757.00 12.65%
66 5/16/02 Steel Beam (W 530 x 167) Lin. Metre 11,037.00 11,306.00 2.44%
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %

Division 6 - Incidental
1 6/1/01 Grouted Riprap Pavement sq. metre 2,178.00 2,895.00 32.92%
2 6/1/02 Concrete Slope Protection sq. metre 1,499.00 1,709.00 14.01%
3 6/1/03 Loose stone Riprap Protection cu metre 5,309.00 8,590.00 61.80%
4 6/1/04 Concrete Cut-Off cu metre 15,990.00 18,884.00 18.10%
5 6/2/01 Reinforced Concrete Culvert Pipe - Class A bedding Lin. Metre 4,983.00 5,990.00 20.21%
6 6/2/02 Reinforced Concrete Culvert Pipe - Class B bedding Lin. Metre 2,360.00 2,819.00 19.45%
7 6/3/01 Manhole (Diameter to be stated in the BoQ) Number - -
8 6/3/02 Catch Basin (Diameter to be stated in the BoQ) Number - -
9 6/3/03 Concrete Side Ditch/ U-Drain Lin. Metre - -
Brick Headwall to Culvert Pipe ( Pipe diameter to be
10 6/3/04 Number - -
stated in the BoQ)
11 6/4/01 Concrete Kerb (as detailed on the drawings) Lin. Metre - -
Combined Concrete Kerb and Gutter (as detailed on
12 6/4/02 Lin. Metre - -
the drawings)
Road Marking-Thermoplastic Material (indicate if
13 6/5/01 Sq Metre 1,069.00 1,114.00 4.21%
screed or spray application)
14 6/5/02 Road Marking - Road marking Paint Sq Metre 412.00 499.00 21.12%
15 6/5/03 Reflecting Road Studs Number 897.00 917.00 2.23%
16 6/5/04 Application of Ballotini Sq Metre 349.00 126.00 -63.90%
17 6/6/01 Topsoil cu metre 332.00 553.00 66.57%
18 6/7/01 Grass Sodding Sq Metre 37.00 42.00 13.51%
19 6/7/02 Grass Turfing Sq Metre 37.00 42.00 13.51%
20 6/8/01 Guardrail Lin. Metre - -
21 6/9/01 Concrete Monument Number - -
22 6/9/02 Concrete Post Number - -
23 6/10/01 Traffic Signs Number 6,901.00 5,651.00 -18.11%
24 6/10/02 Sign Post Number 3,073.00 3,140.00 2.18%
25 6/11/01 Rumble strips (Bituminous Concrete Volume) cum 14,717.00 16,311.00 10.83%
26 6/11/02 Road Marking Thermoplastic Material (by spray) 1,055.00 1,078.00 2.18%
27 6/12/01 Geotextile Filter Fabric (as detailed on the Drawings) Sq Metre 179.00 217.00 21.23%
Furnishing and installing Matress (as detailed on the
28 6/12/02 Sq Metre 1,540.00 1,600.00 3.90%
drawings)
29 6/13/1(a) Bullah Palisiding (150mm – 175mm) Lin. Metre 9,410.00 10,032.00 6.61%
30 6/13/1(b) Bullah Palisiding (Local Bullah : 150mm – 200mm) Lin. Metre 7,034.00 7,604.00 8.10%
Sl. Item Description. Unit RHD SoR RHD SoR Change in
No Code 2015 2018 Unit Rates
Dhaka with respect
to 2015

Unit Rate (Tk.) Rate (Tk.) %


31 6/14/01 Mobilization for deck slab repairing work, etc. Sq Metre 799.00 1,168.00 46.18%
32 6/15/01 Concrete Guide Post (1.6 m long, 200mm dia) No. 2,068.00 2,359.00 14.07%
33 6/16/01 Concrete Kilometer Post (As per drawing) No. 8,656.00 9,048.00 4.53%
34 6/17/1(a) RCC Palisiding (4m post, 200mm X 200mm) Lin. Metre 10,037.00 10,328.00 2.90%
35 6/17/1(b) RCC Palisiding (3m post, 150mm X 150mm) Lin. Metre 6,602.00 6,809.00 3.14%
Comparison of Unit Rate of Materials for Dhaka, Mymenisngh & Cumilla Zone

Sl. Basic Item Category Unit Rate 2015 Rate 2018 % Change
No. (Taka) (Taka) with respect
to RHD 2015
rate

FM = 0.5 Cum 450.00 420.00 -6.67%


FM = 0.8 Cum 500.00 500.00 0.00%
1 Sand FM = 1.0 Cum 600.00 640.00 6.67%
FM = 1.8 Cum 1200.00 1250.00 4.17%
FM = 2.5 Cum 1700.00 1850.00 8.82%
2 Cement OPC Ton 10764.00 9000.00 -16.39%

3 Reinforcement 60 grade Ton 65640.00 62500.00 -4.78%

80/100 (Bulk) Ton 68500.00 54000.00 -21.17%

60/70 (Bulk) Ton 73000.00 56000.00 -23.29%

4 Bitumen
80/100 (Drum) Ton 68500.00 54000.00 -21.17%

60/70
Ton 73000.00 56000.00 -23.29%
(Drum)

5 Brick 1st Class Per 1000 7477.00 10000.00 33.74%

Machine Made Per 1000 12000.00

7 Brick Chips 40mm cum 3000.00 3900.00 30.00%

Brick Chips <25mm cum 3000.00 4000.00 33.33%

Brick P.J. Nos 8.00 10.00 25.00%


25mm, LAA<25 cum 4800.00 7000.00 45.83%
14mm, LAA<25 cum 4600.00 6300.00 36.96%
12mm, LAA<25 cum 4400.00 6300.00 43.18%
9mm, LAA<25 cum 3500.00 5700.00 62.86%
8 Stone Chips/ Gravel 38mm, LAA<25 cum 6750.00
25mm, LAA<30 cum -
14mm, LAA<30 cum -
12mm, LAA<30 cum -
9mm, LAA<30 cum -
20mm, LAA<25 cum 5970.00 8100.00 35.68%
9 Stone Chippings (Chattak/Pakur) 14mm, LAA<25 cum 4800.00 7800.00 62.50%
10mm, LAA<25 cum 4600.00 7500.00 63.04%
Crusher (stone) dust cum 650.00 4000.00 515.38%
Sylhet boulders 100-200mm cum 4000.00 6500.00 62.50%

10 Pea gravels cum 2500.00 2850.00 14.00%

Gravels (as dug) cum 1700.00 2470.00 45.29%


11 Fire Wood Ton 5000.00 6000.00 20.00%
Wooden runner (using 6 times) cum 6000.00 6500.00 8.33%
Wooden Sleper LS 350.00 358.33 2.38%
6m long (Dia 150 –
Bullah Pile Lin. meter 500.00 700.00 40.00%
175mm)
12
6m long (Dia 150 –
Lin. meter 550.00 800.00 45.45%
200mm)
13 Petrol ltr 96.00 86.00 -10.42%
Diesel ltr 68.00 65.00 -4.41%
Kerosene ltr 68.00 65.00 -4.41%
Sl. Basic Item Category Unit Rate 2015 Rate 2018 % Change
No. (Taka) (Taka) with respect
to RHD 2015
rate

14 Soil cu. metre 75.00 210.00 180.00%


15 Imported suitable bulk fill cu. metre 75.00 210.00 180.00%
16 Plastic Tape Pks Pks 240.00 262.00 9.17%

17 Steel Box for Traffic Management Nos Nos 60.00 100.00 66.67%

18 Water Cum 10.00 12.00 20.00%


19 Geotextile sq. metre 100.00 122.00 22.00%
20 G.I wire, nails etc kg 100.00 120.00 20.00%
Sl. Basic Item Category Unit Rate 2015 Rate 2018 % Change
No. (Taka) (Taka) with respect
to RHD 2015
rate

21 Polythene sheet sq. metre 15.00 18.00 20.00%

22 Wooden form work using 4 times cu. metre 6250.00 10000.00 60.00%

23 Nuts, bolts, washers etc nos 65.00 80.00 23.08%

24 Paint (Road Marking Berger brand) Lit. 610.00 725.00 18.85%

25 Thiner (Jensolin T-4) Berger brand Lit. 165.00 230.00 39.39%

26 Bentonite (50kg) bag 850.00 1000.00 17.65%


27 6mm thick steel plate kg 75.00 85.00 13.33%
28 Paint ltr 250.00 250.00 0.00%

29 Angle Iron (b) 38x38x5mm for pre


tonne 48000.00 60000.00 25.00%
cast pile shutter using 16 times

30 Cost of platform (pre-cast pile) sq. metre 48.00 60.00 25.00%


using 5 times

31 F I bar (b) 38x5mm for tonne 45000.00 60000.00 33.33%


pre cast pile shutter using 16 times

32 Nut bolt for pre cast pile shutter kg 80.00 100.00 25.00%
using 16 times

33 Pre-cast pile shoe No 285.00 300.00 5.26%


(0.3x0.3m pile)

Steel Plate 2mm


34 for pre cast pile shutter using 16
tonne 80000.00 85000.00 6.25%
time

35 Nut Bolts tonne 90000.00 100000.00 11.11%


(12 mm Dia 125 mm L)

36 Angle Iron (62.5x62.5x6mm) lin. metre 335.00 370.00 10.45%


using 20 times

37 Cost of wooden shutter sq. metre 120.00 150.00 25.00%


for concrete using 6 times
38 Nail kg 100.00 125.00 25.00%
39 Admixture Liter 160.00 200.00 25.00%

40 Cost of prefabricated sq. metre 827.00 900.00 8.83%


steel shutter (using 50 times)
41 Lifting anchorage No. 500.00 600.00 20.00%
42 Sica LS 300.00 500.00 66.67%

43 Hire cost of sq. metre 121.00 150.00 23.97%


shuttering material
ITEM TYPE : EQUIPMENT

Item Name Unit of Meas. Unit Price Including


Fooding & Fuel
(As Per Present Market Value of
2018)

Concrete Batching Plant with Generator day 40,000.00


1-3KVA Mobile Generator no. 19,800.00
Flashing Light Units (mains power) no. 1,000.00
Flood Light (Pole mounted) no. 2,000.00
Traffic Signs with pole & support for Traffic Man no. 8,000.00
Small hand tools (1) day 50.00
Small hand tools (2) day 50.00
Plate Compactor day 1,200.00
Vibratory roller (1-3 tonne) day 4,000.00
Steel Wheel Roller (5-6 Tonne) day 8,000.00
Vibratory roller ( 7-10tonne) day 10,000.00
Concrete Poker Vibrator day 600.00
Water Pump day 1,200.00
Water tanker day 7,000.00
Water bowser for curing day 7,000.00
Water pump with accessories day 2,000.00
Saw cutter day 2,000.00
Concrete Mixer (7/5) day 2,000.00
Concrete Mixer (14/10) day 2,500.00
Bitumen Heater day 2,000.00
Bitumen Heater (Tar Boiler) day 1,000.00
Flat Bed truck (5tons) day 7,000.00
Truck (5 Tonne) day 7,000.00
Aggregate Spreader day 5,000.00
Bitumen Distributor day 8,000.00
Hand operated bitumen distributor day 1,200.00
Tyre roller PTR day 6,000.00
AC Paver day 10,000.00
Asphalt Plant day 10,000.00
Dump Truck day 10,000.00
Air Blower/Power Brush/Drag Brush* day 5,000.00
Pay Loader day 12,000.00
2/3 wheel static roller 8-12 tonnes day 8,000.00
Bored Pile Equipment (400mm) day 6,000.00
Bored Pile Equipment (600mm) day 6,000.00
Bored Pile Equipment (750mm) day 6,500.00
Bored Pile Equipment (900mm) day 7,000.00
Bored Pile Equipment (1000mm) day 7,000.00
Pile Integrity Test No. 1,000.00
Richshaw Van day 600.00
Winch Machine with Grab day 3,000.00
Staging with M. S. pipe (pc girder bridge) sq. metre 2,500.00
Agitator Truck/ Transit mixure truck day 12,000.00
Concrete Paver day 30,000.00
Mobilization/Demobilization for pre cast pile driv L.S. 1,500.00
Pile Diving Equipment (concrete piles) day 4,500.00
Hire Charge for mobile Generator/welding machin day 3,000.00
Hire charge of monkey with driving arrangement. L.S. 3,200.00
Boiler/Heater (1) day 8,000.00
Spreader day 8,000.00
R.C.C Pipe dia 600mm (wall 50mm) lin. metre 1,000.00
Pump with pipe and accessories day 9,500.00
Water bowser for curing day 6,500.00
Batching Plant with Generator day 40,000.00
Pump with pipe and exessories day 10,000.00
Agitator Truck day 12,000.00
Hire Charge for mobile Generator/welding machin day 3,000.00
Hydraulic Jack day 500.00
Kato Crane 20tonnes (truck mounted) day 15,000.00
Agitator Truck/ Transit mixure truck day 12,000.00
Lifting Crane (Capacity-25 MT) day 40,000.00
Flat bed trailor (Capacity-30 MT) day 25,000.00
Tining machine day 5,000.00
Finisher roller day 5,000.00
Excavator day 12,000.00
Motor Grader day 10,000.00
Asphalt Batching Plant with Generator day 111,360.00
Dozer day 11,000.00
Aggregate Base Paver day 30,000.00
Unit Rate
(As Per 2015)

36,000.00
15,250.00
650.00
1,750.00
5000.00
20.00
20.00
900.00
2,700.00
3,200.00
5,000.00
450.00
950.00
4,500.00
4,300.00
2,000.00
2,000.00
750.00
1,250.00
1,500.00
600.00
4,500.00
4,500.00
4,000.00
3,750.00
500.00
4,000.00
6,000.00
10,000.00
5,000.00
4,500.00
10,000.00
4,200.00
4,500.00
4,500.00
4,700.00
4,800.00
4,800.00
700.00
350.00
1,800.00
1,760.00
10,000.00
30,000.00
1,000.00
3,500.00
2,000.00
3,200.00
7,000.00
6,000.00
850.00
7,500.00
4,300.00
36,000.00
7,500.00
10,000.00
2,000.00
325.00
12,650.00
10,000.00
30,000.00
20,000.00
3,000.00
2,000.00
Unit Rate of Labour (Dhaka, Mymensigh & Cumilla Zone)

Sl. No. Category Unit Recommended Recommended


Rate 2018 Rate 2015
(Taka) (Taka)

1 Ganger Per day/person 850 800


2 Fore man Per day/person 850 800
3 Carpenter Per day/person 700 600
4 Asphalt Mistry Per day/person 700 600
5 Mason Per day/person 700 600
6 Steel fixers Per day/person 650 600
7 Welder Per day/person 750 600
8 Painter Per day/person 700 600
9 Painter Helper Per day/person 550 500
10 Skilled Per day/person 550 550
11 Semi-skilled Per day/person 500 450
12 Un-skilled Per day/person 450 400
13 Flag Man Per day/person 550 400
Labour cost for fixing and
14 Removing shutter for sq. metre
foundation 150 100
Sl. No. Category Unit Recomm Recomm BBS
ended ended August
Rate Rate 2014
2011 2014 Rate
1 Ganger Per day/person
2 Fore man Per day/person 700 800 -
3 Carpenter Per day/person
4 Asphalt Mistry Per day/person 500 600
5 Mason Per day/person 500 600 -
6 Steel fixers Per day/person
7 Welder Per day/person
8 Painter Per day/person
9 Painter Helper Per day/person
10 Skilled Per day/person 500 550 -
11 Semi-skilled Per day/person 400 450 -
12 Un-skilled Per day/person 300 400 -
13 Flag Man Per day/person
Labour cost for fixing and
14 Removing shutter for sq. metre 100
foundation
Remarks Recommended
Rate 2015

800
800
600
600
600
600
BBS-Gi 600
cwimsL¨vb 600
ey‡jwUb-G
Abyiƒc AvB‡Ug 500
bv _vKvq `i 550
cvIqv hvqwb|
450
400
400

100
Engineer's Estimate
for
Construction of 2 lane National Highway for Dhaka Zone, Mymensingh Zone & Cu

Width: Carriageway 7.30m + 2x1.50m Hardshoulder


Note: Dhaka Zone 2018 is the basis

Construction of Flexible Pavement


Location Length
LENGTH Total Length = 1.000
Effective Length for Construction of Flexible Pavement = 1.000
Item Code Item Description & Measurement Quantity Unit Unit Price
RHD
2018
02/07/01 Preparation of Subgrade 300mm depth

1000.00 x 10.300 = 10300.00 sqm 10,300.00 Sqm 24.00


02/08/01 Improved Sub-grade

1000.00 x 10.300
0.300 = 3090.00 cum 3,090.00 cum 1,043.00
03/02/01 Sub-Base
1000.00 x 10.300
x 0.300 = 3090.00 cum 3,090.00 cum 5,400.00
03/03/01 Aggregate Base Type-I
1000.00 x 10.300
x 0.250 = 2575.00 cum 2,575.00 cum 8,832.00
03/03/02 Aggregate Base Type-II
1000.00 x 10.300
x 0.200 = 2060.00 cum 2,060.00 cum 5,932.00
03/06/01a Bituminous Prime Coat (Plant Placed)
1000.00 x 10.300 = 10300.00 Sqm 10,300.00 Sqm 114.00
03/10/01b Dense Bituinous Surfacing - Base Course
(Plant Method )(Bitumen Grade 60/70)
1000.00 x 10.30
x 0.100 = 1030.00 cum 1,030.00 cum 23,144.00
03/07/01a Bituminous Tack Coat (Plant Placed)
1000.00 x 7.300 = 7300.00 Sqm 7,300.00 Sqm 51.00
03/10/02b Dense Bituinous Surfacing - Wearing Course
(Plant Method )(Bitumen Grade 60/70)
1000.00 x 7.30
x 0.060 = 438.00 cum 438.00 cum 24,325.00
03/13/01 (b)125mm Thick Brick on End Edging (Machine Made)
2 x 1000.00 = 2000.00 LM 2,000.00 LM 233.00
Sub-Total :

Cost for 1.00 KM of Construction of Flexible Pavement (Tk.) : 916.24


in 2018 rate
22%

For Minor PMP (12mm Seal Coat) 11.45%


For Major PMP (DBS Binder & Wearing Course) 18.24%
Engineer's Estimate
for
al Highway for Dhaka Zone, Mymensingh Zone & Cumilla Zone

( Amount in Taka)

km
km
Amount Unit Price Amount
2018 RHD 2015
2015

247,200.00 69.00 710,700.00

3,222,870.00 916.00 2,830,440.00

16,686,000.00 4,361.00 13,475,490.00

22,742,400.00 6,566.00 16,907,450.00

12,219,920.00 4,732.00 9,747,920.00

1,174,200.00 123.00 1,266,900.00

23,838,320.00 19,906.00 20,503,180.00

372,300.00 48.00 350,400.00

10,654,350.00 20,118.00 8,811,684.00

466,000.00 103.00 206,000.00


91,623,560.00 74,810,164.00

Lac 748.10 Lac


in 2018 rate in 2015 rate
rise in cost

rise in cost
rise in cost
Engineer's Estimate
for
Construction of 2 lane Regional Highway for Dhaka Zone

Width: Carriageway 7.30m + 2x1.50m Hardshoulders


Note: Dhaka Zone 2018 is the basis
Construction of Flexible Pavement
Location Length
LENGTH 1 Total Length = 1.000
Effective Length for Construction of Flexible Pavement = 1.000
Item Code Item Description & Measurement Quantity Unit Unit Price
RHD
2018

02/07/01 Preparation of Subgrade 300mm depth

1000.00 x 10.300 = 10300.00 sqm 10,300.00 Sqm 24.00


02/08/01 Improved Sub-grade

1000.00 x 10.300
0.300 = 3090.00 cum 3,090.00 cum 1,043.00
03/02/01 Sub-Base
1000.00 x 10.300
x 0.250 = 2575.00 cum 2,575.00 cum 5,400.00
03/03/01 Aggregate Base Type-I
1000.00 x 10.300
x 0.200 = 2060.00 cum 2,060.00 cum 8,832.00
03/03/02 Aggregate Base Type-II
1000.00 x 10.300
x 0.200 = 2060.00 cum 2,060.00 cum 5,932.00
03/06/01a Bituminous Prime Coat (Plant Placed)
1000.00 x 10.300 = 10300.00 Sqm 10,300.00 Sqm 114.00
03/10/01b Dense Bituinous Surfacing - Base Course
(Plant Method )(Bitumen Grade 60/70)
1000.00 x 10.30
x 0.070 = 721.00 cum 721.00 cum 23,144.00
03/07/01a Bituminous Tack Coat (Plant Placed)
1000.00 x 7.300 = 7300.00 Sqm 7,300.00 Sqm 51.00
03/10/02b Dense Bituinous Surfacing - Wearing Course
(Plant Method )(Bitumen Grade 60/70)
1000.00 x 7.30
x 0.050 = 365.00 cum 365.00 cum 24,325.00
03/13/01 Brick on End Edging
2 x 1000.00 = 2000.00 LM 2,000.00 LM 233.00
Sub-Total :

Cost for 1.00 KM of Construction of Flexible Pavement (Tk.) : 753.67


in 2018 rate
22%
Engineer's Estimate
for
n of 2 lane Regional Highway for Dhaka Zone

( Amount in Taka)

km
km
Amount Unit Price Amount
2018 RHD 2015
2015

247,200.00 69.00 710,700.00

3,222,870.00 916.00 2,830,440.00

13,905,000.00 4,361.00 11,229,575.00

18,193,920.00 6,566.00 13,525,960.00

12,219,920.00 4,732.00 9,747,920.00

1,174,200.00 123.00 1,266,900.00

16,686,824.00 19,906.00 14,352,226.00

372,300.00 48.00 350,400.00

8,878,625.00 20,118.00 7,343,070.00

466,000.00 103.00 206,000.00


75,366,859.00 61,563,191.00

Lac 615.63 Lac


in 2018 rate in 2015 rate
rise in cost
RHD SCHEDULE OF RATES 2018
(DRAFT)

ROADS & HIGHWAYS DEPARTMENT


GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH
EFFECTIVE FROM 01 JULY 2018

You might also like