LAB MANUAL
Level : 5
Year: 3
Section :
Signature:
Week 1 Introduction
Experiment No: 1
Objectives
Introduce the lab environment and tools used in the engineering Project
Management lab: PERT Chart and MS project.
Discuss the Project &learn how to write project definition.
1. Outline
Introduction to the lab plan and objectives.
Project definition.
Lab plan
5. In-Class Example
Some examples of problem definition will be presented in the class.
6. Expirements:
Applied by all students .
Applied in their labs.
Try to write (a hypothetical) project definition for it.
7. Deliverables
From each student one project.
Submit their IDs, names, section by Hand in end of semester.
Course: CNE 213 Engineering Project Management
Experiment NO: 2
Objectives
1. Outline
Project work planning.
PERT Chart.
Examples.
2. Background
Project management is the process of planning and controlling the development of a system within a
specified timeframe at a minimum cost with the right functionality.
Duration of task.
Current task status.
Task dependencies.
Key milestone dates.
Experiment: 3
Objectives
Aim1: Using PERT Chart for establishing a timeline and arranging tasks;
1. Creating Tasks:To add a new task in a chart, click and drag with your mouse:
2. Tasks names entry
3. Milestones(outdents,indents)
Entering Information using the Task box on the screen
Experiment: 4
Experiment No: 5
Aim1:Calendar
1.Define the workdays, hours and non working days for a project
Aim2: Managing the tasks in PERT Chart;
1. Resources entry
Experiment No.: 6
Resource: ms_project_2010
(in the dialog box above for Display, Schedule and Advanced tabs)
4. Enter tasks, their information, and durations (don't forget milestones) in the Gantt view
(double-click task name for Task Information box)
6. Set up your resource pool and their details in the Resource Sheet view.
Experiment No.: 7
1. Assign resources to tasks, set their work effort, and add any fixed costs.
3. Review and refine the project schedule and budget to meet requirements
6. To add a milestone the only difference is that the duration of the activity must
~ be zero (below is an example):
Note: By double clicking on a Task or milestone, you can modify its information with
~ a form that prompts.
1. For viewing the schedule showing the Slack go to Views -- More Views --
~ Detailed Gantt View -- Apply.
2. In this click on View -- Table -- Schedule.
3. Slack appears as thin bars to the right of a task, with slack values adjoining
the regular Gantt bars.
4. You can also view the free slack and total slack of a task in the sheet.
5. You can move the activity within the available slack time, to balance the
~ resources, in the cases where over allocation is present.
Course: CNE 213 Engineering Project Management
Experiment No.: 8
1. Critical Path Analysis (CPA) helps you to lay out all tasks that must be completed as part
of a project.
2. CPA helps you to identify the minimum length of time needed to complete a project.
3. For finding CP list all the activities and enter early start, late start, early finish and late finish
~ info of all the activities.
4. You can do this under insert/columns and selecting each terms.
5. Following Screen shot demonstrate how to insert.
6. Project automatically calculates ES, EF, LS and LF based on the starting/ending dates you
~ have provided.
Showing Critical Path:
1. You can show the critical path in multiple ways. You can show critical path using
~ Gantt Chart, Detailed Gantt, Network Diagram, and showing only critical tasks.
2. In Gantt Chart click on Gantt Chart wizard and choose critical path and follow
~ the steps.
3. In Detailed Gantt click on View -- More Views -- Detailed Gantt -- Apply. It shows
the critical path with slack time.
4. In Network Diagram click on View -- More Views -- Network Diagram -- Apply.
5. For showing only the critical tasks, click on Gantt Chart -- Filter -- Critical.
6. The following slides has screenshots of how to show critical path using various
~ methods.
Course: CNE 213 Engineering Project Management
Experiment No.: 9
Draw a Network diagram for the tasks shown in Problem and highlight the
critical path.
Answer:
A suggested answer is provided below.
Experiment No.: 10
Expiremnt no.7
Use MS Project 2010 to create a series of tasks leading to completion of a project. For your project,
you need to:
Experiment No.: 11
Exercise:
Exercise:
Exercise:
Exercise:
Exercise:
Expirements
Student Id:................................................................
Student Name:..........................................................
Experiment no.1
Software required: PERT Chart
Project name: Set-up LAN in a small building
Project start Date:
Project finish Date:
Number of tasks:
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
…………………………………………………………………………………………………………………………………………
Experiment no.2
Software required: PERT Chart
Project name:Web site for CS faculty
Project start Date:
Projects finish Date:
Divide the project in at least 5 tasks, moreover; use of
following must be shown in the project Plan:
Subtasks
Task Duration
Predecessors
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………………….
Experiment no.5
Software required: MS Project 2010
Project name: Airplane
Project start Date:
Projects finish Date:
Divide the project in at least 8 tasks, moreover; use of
following must be shown in the project Plan: