Projects's Name Start Date End Date


Duration
The New Philippine National Bank Headquarters:
A Mixed-Use Development Integrating Eco-Tech 102 Nov. 12, '18 Feb. 23, '19
Architecture

W1 W2 W3 W4 W5 W6 W7
# of
Task Start Date End Date

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Workdays

1 Research 13 12-Nov 24-Nov


1.1 Additional Case Studies 3 12-Nov 14-Nov
1.2 Allocation of spaces 1 14-Nov 14-Nov
1.3 Space Programming 3 14-Nov 16-Nov
1.4 Environmental Systems 3 17-Nov 19-Nov
1.5 Development cost 1 20-Nov 20-Nov
1.6 Improvement of all chapters 3 21-Nov 23-Nov
1.7 Finalizing of book 1 24-Nov 24-Nov
2 Preliminary 14 25-Nov 8-Dec
2.1 Study on building laws and standards 2 25-Nov 26-Nov
2.2 Concept 2 27-Nov 28-Nov
2.3 Site Development Plan 3 29-Nov 1-Dec
2.4 Massing 2 2-Dec 3-Dec
2.5 Schematic Plans 5 3-Dec 8-Dec
3 Design Process 36 9-Dec 20-Jan
3.1 Floor Plans 23 9-Dec 31-Dec
3.2 Elevations 11 26-Dec 5-Jan
3.3 Sections 9 2-Jan 9-Jan
3.4 Bay Section 7 6-Jan 12-Jan
3.5 Utility Systems 7 10-Jan 16-Jan
3.6 Structural Details 7 14-Jan 20-Jan
4 Required Outputs 22 14-Jan 4-Feb
4.1 3D Modeling & Rendering 9 14-Jan 22-Jan
4.2 Interiors 6 21-Jan 26-Jan
4.3 Layout for boards 6 24-Jan 29-Jan
4.4 Finalize book and boards 3 30-Jan 1-Feb
4.5 Printing 3 2-Feb 4-Feb
5 Other Outputs 17 7-Feb 23-Feb
5.1 Powerpoint 5 7-Feb 11-Feb
5.2 Walkthrough 7 10-Feb 16-Feb
5.3 Scaled Model 14 9-Feb 23-Feb
MERRY CHRIS TMAS! ###
###

W7
###
###
###
###
###
HAPPY NEW YEAR! ###
### W8
###
###
###
###
###
###
###
W9

###
###
###
###
###
###
###
W10

###
###
###
###
###
###
###
W11

###
###
###
###
###
###
###
W12

###
###
###
###
###
###
SUBMISSION??? ###
W13

###
###
###
###
###
###
###
W14

###
###
###
###
###
###
###
W15

###
###
###
###
###
###
###
W16

###
###
###