You are on page 1of 7

An Industrial Boilers Explosion and How to

Prevent It.
Mr. Misdeh Bin Rasman
Mr. Hassan Bin Abdul Hamid Mr. Moktar Mat Jin
Electric, Control & Instrumentation
Unit Pembangunan Electrical Department
Ranhill Powertron Sdn Bhd
Jabatan Pendidikan Negeri Sabah ILP Kota Kinabalu
Kota Kinabalu, Malaysia
Kota Kinabalu, Malaysia Kota Kinabalu, Malaysia
misdehrpt@gmail.com
aieqal@gmail.com moktarmatjin@gmail.com

Mr. Joye Tingkolou


Mr. Nail Sausin Mr. Jaikol Udar
Electrical Department
Electrical Department Electrical Department
ILP Kota Kinabalu
ILP Kota Kinabalu ILP Kota Kinabalu
Kota Kinabalu, Malaysia
Kota Kinabalu, Malaysia Kota Kinabalu, Malaysia
joyet777@gmail.com
sk8161.ns@gmail.com jaikoludar@yahoo.com
Abstract—This _ Grp Joye After the incident, the inspection data was
shows that some sensors for the control
Keywords—Boilers, Human-Machine Interface (HMI), PLC, element a malfunction or not detected for a few
I/O Module, Dampers, Burner, ID Fan, FD Fan,
minutes before the explosion. The historian
data were recorded also show that control of
I. INTRODUCTION various process variables was resume as normal
This paper is contained of two major parts. The first operation. However, the data for incoming and
part is the background of providing information of the outgoing pressure contamination equipment
equipment associated with the explosion, including the was recorded during interruption. Other than
boilers and descriptions of the control system. The second that, there a no airflow go in to the boiler
part is a summary of incidents and analysis discussing some firebox during the interruption as stated in
of the observations and facts before the accident. The details recorded data.
summary of accident events explain in this part, but has
been familiar with protecting information that is difficult. Based on an error analysis and include all
This is followed by a case study section where we identify data from evidence, calculations and witness
the causes of failure. At the end of this paper we are finished statements we tend to found that the ignition
with the Hazard Analysis section, which introduces this field approached close to abnormal conditions and
and explains how we use technique hazard analysis to help therefore the state of the boiler reached the
plant staff in preventing recurring crashes. However, all gas/air LEL (Explosion Low Explosion). The flow
company names involved with case studies in this paper will of air was reduced within the boiler and also the
be kept confidential. FD, ID dampers closure because of loss of the
control system.
II. BACKGROUND _ GRP JOYE
V. MAJOR EQUIPMENT INVOLVED

III. DOSH INFO__ GRP JOYE Two major parts were involved with the boiler incident
which is boiler equipment and boiler control system. The
boiler equipment are mechanical parts such as feed water
IV. INCIDENT SUMMARY pumps, water drums, burners, fans, valves and boiler tubes.
Often, we hear an explosion happening in the industrial While the PLCs are algorithm and mathematical modelling
boiler. For first example, an accident at a company X last in terms of programming which control the process of boiler
year, whose company name a kept confidential. The operation. The main function for each part will be described
replacement of ignition burner on the boiler has been done in details as below.
recently and the commissioning of a new ignition burner
system still in progress. During the accident, only natural
A. Boiler Equipment
gas ignition was used in boiler and the boiler operator was
aware that he failed to manage the boiler control system. The primary function of a boiler is to generate steam by
Then explosion was occurred in it a few minutes later. No heating a water. Steam produced in a boiler can be used for
injured personnel in the incident, while facilities a variety of purposes including drying, sterilisation, power
damage was limited to nearby equipment, generation, space heating and humidification. Modern boiler
boilers and boilers houses. The main reason for design offers several benefits. In the past, improper design
the explosion in boilers and contributors of boilers has caused explosions which led to the loss of life
resulting in the incident will be mentioned later. and property. Figure 1 show the block flow diagram for air
These case study will focus on boiler control flow and fuel to the boiler. The boiler system consisted of
systems and industrial boiler itself for the primary burner and couple with neutral gas fired ignition
operators. burner.

An observation of the control system and


the end of the control element in the field was
taken a few minutes before the explosion.
Without operator knowledge, the control system
has stopped its operation. The boiler operators
report a failure of the boiler control system and
try to solve the problem. Various control
elements have been observed and only act
immediately to control the signal from the boiler
operator. Field operators report that the control
of these elements not only reacts but operates
in the wrong control with the direction of the
boiler operators. Boiler operators cannot control
the boiler because the control system does not Fig 1. Block Diagram for Burner System
respond.
For the stable combustion, the burners required a additional compendious set for root causes analysis. Several
secondary air feed form the air system. Each burner has of the case studies are mentioned below to produce lessons
installed a natural gas fired igniter complete with air feed learned from the case studies. The summary of case studies
from the wind box to get proper combustion. In additional and root causes analysis are generalized to safeguard any
air stream supplied by forced draft (FD) fan with constant confidential details.
speed. The induced draft (ID) fan were draw the exhaust
gases from the furnace and air pollution control device. The
A. Case Study 1. Lack of PLC Monitored
rate of air flow control by both FD and ID fan dampers. The
discharge of exhaust gases exited to the stack. The first case study is focus on the lack of an external
monitoring for the Boiler Control System has ceased or
function failed. The condition of the PLC is not monitored
B. Boiler Control System due to malfunction or if a standalone review of the system
Basically, boiler control system divided into several has occurred. Such studies may include comparisons to
interfacing components and subsystems, such as Burner current standards and proposals [2]. If the burner monitoring
Management System, Human-machine interfacing (HMI), system able to detect that the system does not control a vital
Combustion Control System and Plant Information System field device, then the burner detection system could act on
this information.
(PI). Those devices communicated via hard-wire signals,
networking and interfacing using a HMI. The Programmable In events of burner malfunction, the Boiler Control
Logic Controller for boiler management system and System ought to be detected by the burner detection system
combustion control system had physical connections to the earlier of any protection sensors activated as a result of
field devices, actuators as know field devices. For historian malfunction or improper operational conditions. For
and data recording system the plant information system was example, the loss of the Boiler Control System would be
used. The standard boiler interlock, sensors and safety tripped the boiler. The management change of the system
functions were represented by boiler management system. could have moderately to prevent the previous accident or
similar accidents with considering the incorporating control
The PLC also consisted of several sub-system such as a specifications, control system testing, procedures and
inspection needs.
main processor, power supply, networking cards and I/O
modules. Basically, the I/O modules will read the value of
sensors state. Also allowed the PLC to control the output B. Case Study 2. Configuration of Input/output (I/O)
Modules
such as actuators, fans, solenoids and etc. Normally PLC
The existing configuration output signal for the I/O
modules will close the induced draft (ID) fan and forced
draft (FD) fan dampers when a PLC malfunction. This is
known as a fail-safe configuration is also taken place if a
functional philosophy had been programmed for the Control
System or if a review of procedures needs the third-party
review for the existing system design has been taken place.
Therefore, a case study should have included a comparison
of recommendations and industry standards, such as a
minimum airflow requirement or maintaining the airflow
with integrating to the logic state operating of the control
system by preventing the dampers from close. Hence, in the
event of a control processor malfunction or stopped, the
logic configuration setting doesn’t cause the dampers to shut
or close.

Fig 2. Programmable Logic Controller C. Case Study 3. Minimum Damper Open Position
Based on historical data analysis, the damper was
located in cabinet complete with key switch. This key permitted to fully close, this is not met the requirement of
switch controls the PLC state functions or modes. For NFPA 85 standard. The third-party investigation regarding
example, run mode will execute the PLC programmed logic, the airflow requirement and installation for the burner
remote mode will allow the operator control the field system should be reviewed for this current issue. In case of
devices from Control Room personal computer and lastly the control system interruption as experienced in the
the program mode use for program execution preparation to previous incident then the administrative control able to
download the new instructions. limit the minimum set-point to the position of the damper is
insufficient. According to NFPA 85 standards, the airflow
VI. CASE STUDY required is not less than 25% level when there is has fuel
flowing to the igniters or burners [1]. Normally, to limit the
The investigations included the root cause analysis, minimum position the function of mechanical stops will take
calculations and the equipment affected as mentioned above. place to ensure the damper system in a safe condition.
Additionally, the analysis can specialise in the PLC
software, PLC hardware and Programming PLC software
system procedures were needed. With refer to detail of the
case study, a group of causative factors was found for any
thought. These sets of causative factors were reduced to an
been securely in service for more than twenty years
preceding the occurrence; along these lines, most of hazard
D. Case Study 4. Airflow Sensors Limit things that might be distinguished by the sooner ways were
The airflow sensor was connected on the terminal screw seemingly already mitigated for the current design. In any
were not functional well, therefore, the Boiler Control case, the incident occurred throughout a structure
System unable to sense a low airflow stage by using the adjustment, which may be utilized to trigger a restricted to
existing sensors. Referring to the NFPA 85 code, such as at handle the new changes.
this condition it must lead to the main fuel tripped [1]. The
analysis of case study was centered on how this situation An efficient variety of methodology hazards analysis can
was developed in the system and remained hidden during be a detailed guidance and checklist of analysis is also found
the upgrade project for the burner system. The history of the in reference [3]. A list could also be a table of things or
monitoring strategy on the boiler for the minimum airflow written list that are accustomed to verify the standing of a
requirement, it was clearly mentioned that this issue was system. An individual checklist is also extremely related to a
developed during a previous control system upgrade. The specific process; however, they are oftentimes used to
modified of this strategy ought to have final verification on ensure the compliance to the standards and pointers [4].
the control system elements however apparently didn't. Most of a list provide criteria against that a given system has
been evaluated. The case studies were found that sensible
success in developing of safety checklist for the boiler to be
VII. SAFETY AND HAZARD_ MOK & HASSAN used within the management of amendment activities when
the existing system upgrades and commission. From a
VIII. ANALYSIS OF HAZARD generic list and rationalization of however this list would
have known the particular root causes are provided below.
An industrial definition of hazard is a chemical and The provisions NFPA 85 checklist-based analysis would
physical unsafe situation that has a potential of causes harm doubtless has observed the possible causes known within
to the environment, human and property [4]. A plant has the previous part once employed by knowledgeable about
boiler is a specific type of process that may involve with a and knowledgeable 4 Copyright © 2015 by ASME
larger process of chemical or as the sources for the power personnel as a part of the facility’s management of
generation. Normally the process hazards from the steam of amendment. For example, attentive consideration of part
the boiler will produce steam, high pressure, high 4.6.3.2.3 of NFPA 85 could have addressed the situations
temperature and combustion together with the machinery. that contribute the main causes for case studies 1, 2 and 3 as
Another hazard is the occupational hazards, such as falling it clearly needs evaluating for failure modes like a
object, rotating machine, slip and electricity. It is strongly malfunction of processors.
recommended by NFPA 85 to review both initial design and
system of boiler safety should be changed. Referring to According to ABMA-Boiler 307 Combustion control
NFPA 85 codes, they provide several prescriptive guidelines guideline for single burner fire-tube, chapter 3.3, the
for commissioning, designing, maintaining and operating of implementing of the checklist was able to detect the lack of
the boiler systems. However, there is no specific hazard a state-of-health monitor between burner and control system
evaluation methods or techniques had mentioned in NFPA (Referring to case study 1). This chapter mentioned that the
85 to comply with safety objectives. control system will send a fault signal to the control system
anytime when there is an internal fault or abnormal
In the process of hazard evaluation, many procedures condition in the burner system to take care of safe operation.
can be applied to identify the potential hazards on the steam
boiler frameworks at the different condition in the existing For case study 4, the minimum airflow sensor non-
cycle of the processing unit. The process unit life-cycle operating may have described in chapter 6.6.5.2.1.1-(14) of
incorporates the phases of designing, commissioning, NFPA 85. This chapter mentioned that a complete functional
maintaining and operating. The different purposes for the test of the interlocks should be carried out after any
process life after beginning commissioning, minor modification and an overhaul on the interlock system. If the
modification might be attempted to electrical, control functional test has been conducted during the system
systems and mechanical that adjust the actual function upgrades before, so that the malfunction of the sensor can be
specification or characteristics. Basically, the minor of detected before the special necessities resulting in the
modifications might fall under the definition of an incident were an occurrence.
organization's administration for the modification
procedures. Normally a process of hazard analysis must be
recommended or suggested for any such changes, be that as IX. CONCLUSION_MOK & HASSAN
it may, the complexity of the progressions ought to be
viewed as while figuring out what sort of process hazard
analysis is to be directed. REFERENCES

Subjective situation driven danger examination methods, [1] National Fire Protection Association, NFPA 85; Boiler and
Combustion System Hazards Code. Pp 26-41, 2015.
for example, Hazard Identification Studies, Preliminary
[2] American Boiler Manufacturers Association (ABMA)– Addressing
Hazard Analyses, Risk and feasibility studies are very Common Issues Impacting Safety & Performance of Boilers, June
importance in the process industries, these are more 2018
qualified to develop a procedure and beginning the system [3] Fecke M, Morrison DR, Martens J, Cowells J. “A guide to developing
designs. The investigation of the boiler in this paper has and implementing safety checklists: Plant steam utilities.” American
Institute of Chemical Engineers, 2010.
[4] CCPS (Center for Chemical Process Safety), Guidelines for Hazard
Evaluation Procedures, 3rd Edition, April 2008.

You might also like