Mount

Vernon Community School



Brie%ing for Staff & Community






November 19, 2018

Every Student Succeeds


www.acps.k12.va.us
Ac3ons and Progress

ü  Environmental Report – November 2018
No immediate removal of students warranted
Mold remedia3on complete for 12 rooms and areas
Mold remedia3on will con3nue in iden3fied areas un3l all
moisture intrusion issues have been resolved (subject to the
availability of funds)

ü  Roof Replacement
Phase 1: Contract in place
Work star4ng in December – sec4on by sec4on
Phase 2: Proposed for summer 2019 with FY20 CIP request


Every Student Succeeds
www.acps.k12.va.us 2
Ac3ons and Progress

ü  Building Assessment
(Water Intrusion Study)

Complete

ü  Permanent solu3on

Ac3vely planning for long-term solu3on
All informa4on for op4ons, approaches now received


Every Student Succeeds
www.acps.k12.va.us 3
Permanent Solu3on
The Building Assessment Report has iden3fied mul3ple systems
contribu3ng to the issues:
Ø  Roof leaks
Ø  Building Envelope crea4ng wall moisture
Ø  Recurring mold at various loca4ons
Ø  High humidity levels
Ø  HVAC not keeping up
Ø  Aging piping system
Ø  Ground water condi4ons


Every Student Succeeds
www.acps.k12.va.us 4

Full Building Assessment
q Scope of Water Intrusion Study:
•  Peer review of roof replacement design
•  Review and valida4on of recent environmental reports
•  Inves4ga4on of maintenance records and building condi4on;
collec4ng test samples, where necessary
•  Assessment of MVCS architectural construc4on
•  Assessment of building mechanical (HVAC) system
•  Inves4ga4ng any source(s) of water coming into MVCS
•  Temporary and Permanent repair recommenda4ons – op4ons,
approaches, $ es4mates, impacts/considera4ons

Every Student Succeeds


www.acps.k12.va.us 5
Mount Vernon Community School
Water Intrusion Assessment

Every Student Succeeds


www.acps.k12.va.us
November 19, 2018

Findings

1.  Roofing & Drainage

2.  High Humidity & Condensation

3.  Building Envelope

4.  Dual Temperature Piping

5.  HVAC Systems

6.  Mold, Asbestos & Lead

7.  Maintenance

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

Water Damage Diagram

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

Roofing & Drainage

Deteriorated roof membrane.

Clogged roof drain. Holes in roof deck.

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

Roofing & Drainage

Poor stormwater management. Questionable stormwater capacity.

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

High Humidity & Condensation

PTA Meeting - Mt. Vernon Community School Building Assessment


Every Student Succeeds
www.acps.k12.va.us
ACPS Alexandria, Virginia

November 19, 2018

Building Envelope

Poor vapor barrier and no insulation. Uninsulated EIFS infill.

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

Piping Condensation

Poor vapor barrier and no insulation. New pipe insulation.

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

HVAC Systems

Tear in Auditorium return air duct.

Unit ventilator air damper. 21 year old cooling tower.

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

Mold, Asbestos & Lead

Mold on ceiling panels. Potential flaking lead paint.

Mold on pipe insulation. Potential asbestos within adhesive.

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

Maintenance

Exhaust Fan leak.

Exhaust fan dome missing. Water damage.

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

Maintenance

Deferred roof cleaning.

Downspout disconnected from stormline. Broken unit ventilator.

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

November 19, 2018

Recommendations

Roofing Replace the Roofing


[Scheduled to Start December 2018 and finished in August 2019]

Drainage Correct Stormwater Management Issues

Humidity Renovate Exterior Walls & Add Vapor Barrier & Insulation

HVAC Replace the buildings HVAC system with an energy efficient,


modern system that allows better control of outside air and
classroom environments

Mold Reduce Humidity to Stop Mold Growth


[Continue on-going measures to remove mold growth & affected materials]

Maintenance Develop a systematic maintenance program to stay ahead of


maintenance issues

PTA Meeting - Mt. Vernon Community School Building Assessment


ACPS Alexandria, Virginia

Next Steps
§  Next update: December 18, 2018
§  Establishment of MVCS Facili3es
Community Advisory Group
§  Informa3on on summer school/
summer programs at MVCS
§  Playground 3meline and update

Every Student Succeeds


www.acps.k12.va.us 19
Timeline
Dec-18 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18

MVCS Facili5es Advisory Group * * *

Update Mee5ngs * * * * * * *

20
Roof Replacement Phase I

Roof Replacement Phase II

Remedia5on - mold related Con4nuous as needed

H2O Intrusion Correc5on
Planning
H2O Intrusion Correc5on
Acquisi5on Strategy Op5ons
H2O Intrusion Correc5on
Budget
H2O Intrusion Correc5on
Approvals

Every Student Succeeds


www.acps.k12.va.us 20
Alexandria City Public Schools

Operations Department
Of#ice of Educational Facilities
Of#ice of Safety and Security Services

Superintendent School Board Ronnie Campbell Christopher J. Lewis

Every Student Succeeds


Dr. Gregory C. Hutchings, Jr. Ramee A. Gentry, Chair
www.acps.k12.va.us
Cindy Anderson, Vice Chair
William E. Campbell
Hal E. Cardwell
Margaret Lorber
Veronica Nolan
21
Karen A. Graf