You are on page 1of 12

GEAFOL Cast-Resin Transformers

Operating Instructions

Answers for energy.


Contents
Range covered 3 Temperature monitoring 9
General 9
Application 3 Description 9
Version with PTC 9
Description 4 Version with PT 100 9
Core 4 Evaluation devices 9
Windings 4
Insulation 4 Commissioning 10
Supports 4
Recommendations for
Installation 5 cleaning and inspection 11
Unloading, handling, unpacking, Cleaning transformers 11
inspection, cleaning and storage 5 Cleaning method 11
Setting up 5 Checking the torque values of bolted
Housings 6 connections 11
Minimum clearances 6 Checking warning facilities 11
Checking fitted fans 11
Connecting 7 Protective housings 11
Surface preparation 7 Faults 11
Fastenings 7
Contact pressure 8
Earthing 8

2 |
Low-voltage Upper clamping
terminal

Lifting lugs
Connection for temperature
monitoring system
Lashing lugs

Cast high-voltage winding


High-voltage terminal

Delta connection
High-voltage
tappings
(these may also
be on the
low-voltage
terminal side)
Earthing terminal
Pulling lugs
Lower clamping

Wheels, can be turned through 90°

Fig. 1: 630 kVA GEAFOL cast-resin transformer 10 ± 2 x 2.5 %/0.4 kV low-voltage connection side

Range covered Application


These operating instructions are applicable GEAFOL cast-resin transformers are par-
to all GEAFOL® cast-resin transformers of ticularly suitable for applications where
three-phase and single-phase design, fire or ground-water regulations would
including special versions such as rectifier involve additional expense if liquid-im-
and star-point transformers. mersed transformers were used, e.g. in
ships, offshore and wind power plants,
department stores, underground railways,
sports stadiums and meeting halls, pump-
ing stations and water catchment areas.
They are also being used more frequently
in industrial applications for load center
substations and supply feeder stations
because, with cast-resin transformers,
there are no civil works costs for oil catch
pits and fire protection. This also greatly
facilitates relocation of the transformers
should it be necessary.

| 3
Description
Core Insulation
Only grain-oriented, cold-rolled plates The insulation structure is dimensioned
insulated on both sides are used for the on the basis of the impulse voltage distri-
iron core. bution. It ensures freedom from partial
discharge up to twice the rated voltage,
The leg and yoke cross-sections are as well as thermal and mechanical
staggered by different lamination widths. strength.
The outer legs have miter joints and the
middle leg a double miter joint at the Supports
yoke junction. A clamping arrangement designed specifi-
cally for the characteristics of the strip
Windings windings and flexible bracing of the coils
The high-voltage winding is made of alu- ensure both high short-circuit strength
minum strips and high-quality insulating and also a very low noise level.
film. Each phase winding is formed from
several separate coils connected in series
which are encapsulated in resin under a
vacuum. The winding ends and tappings
are routed to threaded bushes and are
encapsulated with the remainder of the
winding. The low-voltage winding is
made of aluminum strips and cast-resin
impregnated insulating film (prepreg).

4 |
max. 45°

max. 45°

Fig. 2: Lifting of the transformer

Installation
Unloading, handling, unpacking, If signs prohibiting transport by fork-lift The transformer must be packed in a
inspection, cleaning and storage are attached near the bottom of the trans- protective foil when being transported
GEAFOL transformers may only be un- former, transport of the transformer by on-site or being stored. This effectively
loaded and transported by means of the fork-lift is absolutely prohibited! prevents the ingress of dust and foreign
lifting lugs provided on the upper con- matter. In order to prevent condensation
structional cross beam (see Fig. 1). In forming, an adequate quantity of desiccant
general four individual cords have to be agent (such as Silicagel) must be enclosed
used. The information about pulling at in the packaging.
an angle provided on the labels on the GEAFOL transformers should be unpacked
lifting lugs must be observed (see Fig. 2). in a covered area and inspected immedi- Setting up
If a transformer is moved on its rollers, ately for transportation damage. Any GEAFOL cast-resin transformers should
the points of action are the pulling lugs damage visible on delivery must be noted only be installed in a roofed room or cell
provided in the lower cross beams (see in the transport papers and confirmed by that is dry and protected from sunlight,
Fig. 1) or on the truck. the supplier. The sender must be informed where the degree of protection assured is
immediately so that a suitable loss adjust- at least IP 23. If appropriately coated with
Do not push or pull on the high-voltage ment procedure can be initiated, if neces- special paint and if an outdoor housing is
windings or their connecting tubes. sary with the participation of the transport used they are also suitable for installation
insurance company. outdoors. GEAFOL cast-resin transformers
GEAFOL cast-resin transformers may only need an adequate supply of fresh air to
be transported by fork-lift truck if the If necessary, the transformer must be dissipate the heat losses. Approx. 200 m3
transporting party ensures that cleaned before commissioning (see recom- of fresh air per hour and for each kW of
■ the transformer is adequately secured mendations for cleaning and checking heat loss is the recommended value;
against the risk of tipping and/or falling GEAFOL cast-resin transformers on further information can be found in the
and Page 11). GEAFOL planning notes).
■ damage to the iron core between the
cross beams and any attached accesso- If the transformer is not commissioned
ries such as fans or make-proof earthing straight away, it must be stored in a roofed
switches is reliably prevented. room that is dry and protected from sun-
light. The room’s temperature must not
drop below –25 °C (unless otherwise
agreed). It is not recommended to cover
it with plastic film, owing to the risk of
condensation.

| 5
c c

b a b a

Fig. 3: Minimum clearances around GEAFOL Fig. 4: Minimum clearances around GEAFOL
cast-resin transformers with switching strip (1) cast-resin transformers with contact tubes (2)

Also make sure that the clearances from If operated normally, the transformer Housings
the surface of the cast-resin coils to the should attain its expected service life. In When using housings, note that all bolted
walls, busbars, earthed parts, etc. satisfy particular, the average annual tempera- connections must be firmly tightened
the applicable installation and safety ture and the load crucially influence the during installation, thus avoiding damage
regulations (see Fig. 3 and 4). service life. to the transformer, e.g. as a result of nuts
falling out.
Cast-resin transformers are not safe to GEAFOL cast-resin transformers for instal-
touch. The power must be shut off before lation at high altitudes over 1,000 m above Minimum clearances
work is carried out on the transformer. mean sea level are identified on the rat- Adequate space must always be ensured
Applicable regulations must be observed. ing plate with the maximum permissible around the transformer to enable con-
installation altitude. When installed ac- nections to be made and also to keep to
Transformers are designed in accordance cordingly the minimum clearances listed the necessary electrical clearances. The
with the applicable standards for the fol- in Table 1 must be increased by 1 % for minimum distances to prevent flashover
lowing cooling air values: each 100 m above the altitude of 1,000 m. are shown in Table 1 in conjunction with
■ 40 °C maximum the sketch in Fig. 3 or 4.
■ 30 °C daily average
■ 20 °C annual average

Maximum voltage for Rated lightning impulse Minimum clearances


equipment Um1) (rms value) withstand voltage ULI1)
List 1 List 2 a b c d
kV kV kV mm mm mm mm
12 – 75 120 * 50 40
24 95 – 160 * 80 50
24 – 125 220 * 100 70
36 145 – 270 * 120 90
36 – 170 320 * 160 110
1) See IEC 60071
* If there are high-voltage taps on this side, the value in column a applies to the clearance b; otherwise, the value in column c applies.
Table 1
6 |
Methods of bolting Expansion
Example strap

Busbar

Transformer table
4 Busbar
1 2
b 2

1 Hexagon screw,
ISO 4014 or ISO 4017
3
2 Conical spring washer
DIN 6796
3 Hexagon nut, ISO 4032
1 Bare tap 4 Washer, DIN 7349 4

Fig. 5: Minimum clearance for cable connection; Fig. 6: Transformer connection with busbar
see Table 1

Connecting
On the high-voltage side, the transformer Surface preparation Fastenings
is connected to the the surfaces of the Before making any bolted or terminal Corrosion-proof parts must be used for
connecting tubes or the terminals provided connection, it is necessary to remove the bolted connections. Preference should be
on the strip (delta connection), or to the thin, invisible layer of oxide from the alu- given to bolts belonging to strength class
cast-on post insulators of the high-voltage minum surface, which is a poor conductor 8.8 or 10.9. In order to transmit the bolt-
pottings (Y connection). When connecting of electricity. ing force to the largest possible contact
by means of cables, make sure that they surface, stiffened washers should be
feature adequate strain relief and are For this purpose, the contact surfaces inserted under the bolt head and the nut.
routed so that the voltage clearances are must be polished bare metal. Every time Spring elements are also necessary to
maintained in line with relevant regula- a point of contact is opened, the alumi- accommodate heat-generated tension
tions. The minimum clearances for cable num contact surface must be subjected resiliently, so as to compensate for plastic
connections must be observed as shown to the whole preparation process again deformation and to thus maintain the
in Table 1 and Fig. 5. before it is screwed back together. If the required minimum contact pressure at all
transformer is installed indoors in a room times. Both conditions are met by conical
On the low-voltage end, the transformer where condensation is frequently to be spring washers to DIN 6796, which are
is connected to the aluminum bars pro- expected or where corrosive gases are widely used particularly for conductor bar
vided for this purpose (in special cases, present, an aluminum sheet copper-plated threaded fastenings.
to copper bars). The following guidelines on one side (known by the trade name
must be observed when connecting con- “Cupal”, for example,) must be inserted
ductor bars via expansion straps. between Cu-Al contact points so that the
aluminum side is in contact with the alu-
minum bar and the copper side is in con-
tact with the copper terminal. All edges
of this sheet must protrude some milli-
meters so as to ensure that any corrosion
occurring in the transition area remains
outside the contact zone. Corrosion can
be largely avoided by applying a protective
coating to the cut edges of this “Cupal”
sheet. Tinned terminals can be combined
with bare copper, aluminum or silver-
plated surfaces.

| 7
Expansion
strap

2 3

1 4
1

1 Washer, ISO 7089


2 Hexagon screw, ISO 4014 or ISO 4017
3 Hexagon nut, ISO 4032
4 Conical spring washer, DIN 6796

Fig. 7: Transformer connection with cable lug Fig. 8: GEAFOL cast-resin transformers
Low-voltage end connection

Contact pressure If the low-voltage connection is estab-


The bolts should be tightened with a lished with busbars, an expansion strap
torque wrench. This ensures that the bolt (flexible connection element) must be
connections are made with adequate installed between the transformer and
contact pressure. the busbars. This keeps mechanical
stresses away from the transformer
To eliminate any settling in the joints, (see Fig. 8) and largely prevents trans-
it is advisable to retighten the bolts after mission of structure-borne transformer
a few hours. However, the torque then noise. Detailed information on bolted
applied should not be greater than the busbar connections can be found in
torque applied during the first installation. DIN 43673.
We recommend the tightening torque
values listed in Table 2 for tightening Earthing
the ungreased (dry) bolted joints. Make sure that the necessary earthing
connection is established on accessories
installed on the transformer after installa-
Bolt Torque [Nm] tion. Transformer housings must also be
dry
earthed in accordance with the known
M6 10 earthing specifications.
M8 20
M10 40
M12 75
M16 140

Table 2: Tightening torque values for


the phase connections and tapping links

8 |
Temperature monitoring
General Version with PTC Evaluation devices
The measuring sensors of the temperature At least one PTC thermistor is installed For the function and connection of the
monitoring system record the winding in one of the low-voltage windings to be evaluation devices refer to the particular
temperature. This acts as overload protec- monitored. This is provided for triggering. operating instructions. Information about
tion against excessive heat generation in Further systems can be installed, likely- the devices can be found at
the transformer winding. This protection wise retrospectively, e.g. for warning www.ziehl.de and www.tecsystem.it
does not prevent increased rate of service (coil temperature) and controlling fans.
life consumption if the cooling air temper- The PTCs of the particular functional The setting values for the corresponding
atures are not kept within specified limits stage are connected in series and are trigger device in the case of PT 100 tem-
(see list, page 6). The following versions routed to a terminal strip (max. 2.5 mm2) perature monitoring can be found on the
or combinations can be installed: on the upper pressed metal sheet. information plate attached to the trans-
former.
Description Version with PT 100
The temperature monitoring system for At least one resistance thermometer
GEAFOL cast resin transformers consists of (PT 100) is installed in each of low voltage
PTC thermistor, DIN 44082-compliant tem- winding to be monitored. The warning,
perature sensors or platimum resistance triggering or fan control functions must
thermometers (PT100) in accordance be set on the evaluation device. The cor-
with IEC 60751 and the associated evalu- responding setting values can be found
ation devices. Positioning of the overload on the information plate attached to the
protection is identical for both systems. transformer. By default the PT 100s are
The evaluation devices must be designed routed in a three-conductor circuit to a
for processing the signals from the par- terminal strip (max. 2.5 mm2) on the upper
ticular system. pressed metal sheet.

| 9
Commissioning
The transformer must have been cleaned Due to the low attenuation, it may take the
and it must not contain any foreign matter switch-on currents of GEAFOL cast-resin
(see also Installation, Page 5). transformers some time to decay. Refer
■ Check technical data on the rating to the test report for the exact values.
plate attached to the transformer This must be borne in mind when selecting
against the customer’s requirements. fuses and relay times.
■ Tighten all contact connections to the
torque stated in Table 2. If protection settings are wrong, the
■ Adjust any connecting brackets on the transformer will be switched off during
high-voltage tappings to the prevalent the power-on current surge. This will lead
voltage. to high excess voltages in the transformer
windings, where they may cause damage.
When large idling transformers are
switched on, in isolated cases visible
sparks may occur on the outside
(particularly in the area of the core
and the clamped parts), but these will
soon subside. This effect occurs for
reasons of physics and has no influence
on operating safety; it is not a defect.

10 |
Faults
In case of faults that cannot be cleared
by the customer itself, a service department
of Siemens AG should be notified.

Phone: +49 (0) 7021/508-549


+49 (0) 7021/508-512
Fax: +49 (0) 7021/508-588
+49 (0) 7021/508-514
Mobile: +49 (0) 172/622 4291
+49 (0) 172/765 5074
E-mail: weber.guenther@siemens.com
daniel.tiefenthaeler@siemens.com

Recommendations for cleaning and inspection


GEAFOL cast-resin transformers are prac- Cleaning method Checking warning facilities
tically maintenance-free. If they are oper- ■ Rub the soiled surface with a cloth The “Inspection” function for the evaluation
ated in very dusty installations, e.g. in soaked in a conventional tenside-based devices can be carried out as specified in
rolling mills, we recommend cleaning cleaning agent. Then wipe over with a the operating instructions. Visual inspec-
several times a year. dry cloth. tion of the terminal connections on the
■ Use a vacuum cleaner to remove loose transformer is recommended.
In parallel, generally once every year, parts and dirt in the cooling ducts as
the contact bolts, warning facilities and far as they are accessible. Checking fitted fans
functioning of any fitted fans should If possible, the functioning and running
be checked. Checking the torque values characteristics of fitted fans should be
of bolted connections checked once every year.
The transformer must be switched off on The torque values of the transformers’
all sides before maintenance work is be- earthing terminals (and above all the Please note:
gun. All terminals must be shortcircuited bolted connections of all electrical termi- On delivery, the default setting of the
and earthed. The safety regulations must nals), the high-voltage tappings, and the monitoring system types T154 and
be observed. connections from one system to another NT935 includes a functional test for fans.
in the case of double-tier transformers If run in the factory standard setting,
Cleaning transformers should be checked once every year. Use a every 96 hours the fans will undergo
Particular care must be paid to cleaning torque wrench or a force-limiting spanner a short test lasting 5 –10 minutes.
all horizontal surfaces and support blocks to check bolted connections against the
in the area between the low-voltage and values listed in Table 2. Protective housings
high-voltage coils where, according to ex- Protective housings can be cleaned in the
perience, dirt can accumulate very easily. same way as control cabinets. Ensure par-
ticularly that air inlet and outlet openings
are clean of dust and dirt deposits.

| 11
Published by and copyright © 2010:
Siemens AG
Energy Sector
Freyeslebenstrasse 1
91058 Erlangen, Germany

Transformatorenwerk Kirchheim
Power Transmission Division
Transformers
Hegelstrasse 20
73230 Kirchheim/Teck, Germany
Phone: +49 (0) 7021 508-0
Fax: +49 (0) 7021 508-495

Siemens Transzformátor Kft.


1214 Budapest
II. Rákóczi Ferenc u.189.
Hungary
Phone: +36 (1) 278 5300
Fax: +36 (1) 278 5335

For more information, please contact


our Customer Support Center.
Phone: +49 180/524 70 00
Fax: +49 180/524 24 71
(Charges depending on provider)
E-mail: support.energy@siemens.com

Power Transmission Division


Order No. E50001-G640-A121-X-4A00
Printed in Germany
Dispo 19201, c4bs No. 7481
TH 101-100359 470194 BA 04105.0

Printed on elementary chlorine-free bleached paper.

All rights reserved.


Trademarks mentioned in this document
are the property of Siemens AG, its affiliates,
or their respective owners.

Subject to change without prior notice.


The information in this document contains general
descriptions of the technical options available, which
may not apply in all cases. The required technical
options should therefore be specified in the contract.

www.siemens.com/energy

You might also like