PPTOS

Calendario de Avance Físico de Obra


Obra : Building torres
Ubicacion : AREQUIPA - AREQUIPA - AREQUIPA
Costo A : Nov - 2018 Cliente : Mall Porongoche
HORAS HOMBRE
HH
Item Descripcion Unid Metrado Parcial HH 01 Días 01 Días 01 Días 01 Días 01 Días 01 Días
Unitario

ESTRUCTURAS
01 OBRAS DE CONCRETO ARMADO
01.01 COLUMNAS
01.01.01 COLUMNAS, CONCRETO 210 KG/CM2 M3 53.00 12.16 644.48 107.41 107.41 107.41 - 107.41 107.41

TOTAL HORAS HOMBRE 644.48 107.41 107.41 107.41 - 107.41 107.41


TOTAL ACUMULADO 107.41 214.82 322.23 322.23 429.64 537.05
PORCENTAJE DE AVANCE 16.67% 16.67% 16.67% 0.00% 16.67% 16.67%
PORCENTAJE ACUMULADO 16.67% 33.34% 50.01% 50.01% 66.68% 83.35%

Página 1 de 2
S.A.C

e Avance Físico de Obra

HORAS HOMBRE
Total HH
01 Días
07 Dias

107.43 644.48

107.43 644.48
644.48
16.65%
100.00%

Página 2 de 2