Professional Documents
Culture Documents
h i g h l i g h t s
Poor construction practices and the use of additional tie bars at TCJs are the major causes of premature distress.
Behavior of longitudinal steel and additional tie bars at TCJs is different.
Premature distress at TCJs can decrease as use of relief transverse saw cut joints near TCJs.
a r t i c l e i n f o a b s t r a c t
Article history: The long-term performance of continuously reinforced concrete pavement (CRCP) has been quite satis-
Received 24 September 2013 factory in Texas, providing an important network of highways with heavy truck traffic and minimal main-
Received in revised form 16 January 2014 tenance. However, certain forms of distresses were observed within a few years after construction,
Accepted 16 January 2014
requiring repair of the distresses and causing traffic delays. Distresses at transverse construction joints
Available online 8 February 2014
(TCJs) were one of the most frequently observed distresses, and efforts were made to identify the mech-
anisms of those distresses and develop or improve design standards or specifications. Field evaluations of
Keywords:
concrete and steel behavior near TCJs were made using various gages. The analysis of the data indicates
Continuously reinforced concrete pavement
CRCP
that the current practice of placing additional tie bars at TCJs, along with poor construction practices, are
Punchout the major causes of the distress. There is a large difference in the behavior of reinforcement between
Premature distress additional tie bars and longitudinal steel that is continuous through transverse construction joints. The
Transverse construction joint premise that additional tie bars at TCJs will behave the same way as longitudinal steel, thus reducing steel
stresses of longitudinal steel at TCJs, keeping the joint widths tight, and improving TCJ performance, is not
necessarily correct. Also, the use of additional tie bars makes the consolidation of concrete at TCJs difficult
due to the reduced spacing between longitudinal reinforcing steel. Not placing additional tie bars at TCJs,
and the use of relief transverse saw cut joints near TCJs, along with improved construction practices at
TCJs, will minimize the distresses.
Ó 2014 Elsevier Ltd. All rights reserved.
0950-0618/$ - see front matter Ó 2014 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.conbuildmat.2014.01.042
W. Zhou et al. / Construction and Building Materials 55 (2014) 212–219 213
The test section denoted as BWD-I was constructed in the Brownwood District,
10 miles (16.1 km) east of Ranger, on IH 20 (west bound). The CRCP structure con-
Fig. 2. Typical distress near transverse construction joint. sists of 13 in. (330 mm) of concrete slab on 4 in. (100 mm) of asphalt stabilized
214 W. Zhou et al. / Construction and Building Materials 55 (2014) 212–219
Table 1
Field test section details [1.0 in. = 25.4 mm].
Highway District TCJ ID Slab thickness (in.) Construction date Construction time Construction season
US 82 Lubbock LBB-I 13 11/15/2010 Existing Winter
13 12/15/2011 Morning
LBB-II 13 12/15/2011 Evening Winter
13 12/21/2011 Morning
IH 20 Brownwood BWD-I 13 08/14/2012 Evening Summer
13 08/16/2012 Morning
base. The two CRCP slabs at the TCJ were constructed on August 14, 2012 and Au- temperature analysis. At early ages, the concrete temperature drop
gust 16, 2012. At 6 ft from the inside LCJ and 1 ft and 4 ft from the TCJ, VWSGs were
from December 20, 2011 to December 24, 2011 was 22 °F (12.3 °C)
installed at the mid-depth of the slab in both the morning and evening construction
sides. Six SSGs were also installed in the morning side at BWD-I. Three of these SSGs
overall, decreasing from 62 °F (16.7 °C) to 40 °F (4.4 °C). This drop
were installed on the longitudinal steel and the other 3 on top of additional tie-bars in concrete temperature is rather large. However, the variations
at a distance of 3 ft, 6 ft and 10 ft from the inside LCJ. in steel strains were minimal, which indicates that the steel strains
at TCJ were relieved while the concrete temperature was decreas-
ing, potentially due to creep of concrete and the development of
3. Results and discussion transverse cracks. On the other hand, daily variations in steel
strains follow temperature variations quite well – in the morning
3.1. Behavior of additional and longitudinal steel at transverse when the concrete temperature is getting lower, steel strains move
construction joint to the tension side, while in the afternoon when the concrete tem-
perature increases, steel strains move in the compression direction.
Fig. 4(a) and (b) represents the steel strain behavior at LBB-I in This implies that daily concrete volume changes due to tempera-
the early ages after construction and 3 months after construction, ture variations affected steel stresses at TCJ, while the overall trend
respectively. The legends in Figs. 4–6 consist of two parts: the first of concrete temperature variations during the several days did not
indicates the transverse distance from free edge and the second is
the type of bar (L for longitudinal steel and T for additional tie bar).
Concrete temperature at the mid-depth of slab was used for the
(a) Steel Strain at BWD-I right after construction (c) Steel Strain at BWD-I 5 months after construction
(b) Steel Strain at BWD-I 3 months after construction (d) Steel Strain at BWD-I 7 months after construction
Fig. 6. Steel strain variation with TIME-Long Term, BWD-I [°C = (°F 32)/1.8; 1ft = 0.305 m].
have appreciable effects on steel stresses. It is shown that steel the data analysis. As can be seen in Fig. 5(a), concrete temperature
strains in 2 bars exceeded yield points. As shown in Fig. 4(b), as dropped from 70 °F (21.1 °C) to 55 °F (12.8 °C) from October 1,
the concrete temperature increased from 50 °F (10.0 °C) to 70 °F 2012 to November 30, 2012. However, the steel strains in the lon-
(21.1 °C) from March 21, 2012 to March 25, 2012, which is a rather gitudinal steel, as well as the additional tie-bars, remained rela-
large temperature increase, steel strain variations were relatively tively steady, while experiencing daily variations due to daily
small. Also, it is noted that, compared with steel strains at the early temperature variations, as observed in the LBB-I section. As shown
ages shown in Fig. 4(a), those about 3 months after concrete place- in Fig. 5(b), the steel strains in the longitudinal steel at 3 ft (0.92 m)
ment decreased substantially. Also, comparisons of steel strains at and 6 ft (1.83 m) from the free edge remained steady at around
the same concrete temperature, for example at 60 °F (15.5 °C) 1000 le and 500 le in tension, respectively. However, after the
(December 21, 2011) at the early ages and 3 months later (March temperature increase from March 7, 2012, steel strains in the tie-
21, 2012), indicate significant decrease in steel strains for those bar at 6 ft (1.83 m) moved into compression, as did those at the
3 months. This finding has a technical significance, because in CRCP tie-bars at 3 ft (0.92 m) and 10 ft (3.05 m). On the other hand,
research, it is assumed that steel stresses at transverse cracks or at strains in the longitudinal steel remained in tension, which indi-
concrete discontinuities such as TCJs, are maintained quite high, cates that the behavior of longitudinal steel and additional tie bars
and crack widths could be large enough to decrease load transfer is quite different. The primary reason for this discrepancy in the
efficiency if steel stresses are excessive. This assumption was made behavior appears to be the ‘‘continuity’’ condition of the bars.
with the premise that concrete behavior is elastic. It is well known When the concrete temperature increases, the volumes of both
that concrete exhibits visco-elastic behavior when subjected to concrete and steel bars try to increase as well. In general, there is
slow loading such as gradual temperature variations. The informa- a good bond between longitudinal steel and surrounding concrete,
tion in Fig. 4(a) and (b) indicates that visco-elastic nature of con- and the concrete and longitudinal steel behave as a near composite
crete has an effect on concrete slab behavior in CRCP and should material. On the other hand, additional tie bars are not continuous,
be considered in a mechanistic analysis of CRCP behavior due to and there is a discontinuity at the end of tie bars. When the con-
temperature and moisture variations [8]. crete and tie bar volume expands due to temperature increase,
Fig. 5(a) and (b) illustrates the early and later age behavior of concrete could push tie bars longitudinally towards TCJs, causing
steel strain at BWD-I. SSGs were installed at 3 ft (0.92 m), 6 ft tie bars in compression and, if excessive, tensile stress in concrete
(1.83 m) and 10 ft (3.05 m) from the pavement edge. The gage in- in the vertical direction near the tie bars, potentially resulting in
stalled in the longitudinal steel at 10 ft (3.05 m) from free edge did horizontal cracks or delaminations at the depth of tie bars. This
not provide data after construction and hence was not included in mechanism of horizontal cracking in concrete slabs has been
216 W. Zhou et al. / Construction and Building Materials 55 (2014) 212–219
º
standards, TxDOT has used additional tie bars as early as 1960, and
it is difficult to form a logical or technical justification for the use of
additional tie bars at TCJs. It could be that a premise was made at
that time that additional tie bars would behave the same way as
longitudinal steel and thus ‘‘complement’’ longitudinal steel at
TCJs, reducing stress level in longitudinal steel at TCJs and improv-
ing overall performance. The data from the field experimentation
indicates that the premise may not be valid.
Fig. 6(a)–(d) provides a more exhaustive display of the steel
strains at BWD-I test section from the early age until 7 months
after construction. They show that the variations in steel strains
in longitudinal steel at 3 ft (0.92 m) and 6 ft (1.83 m) from the
pavement edge remained relatively small and in tension, whereas
the steel strains in tie bars gradually moved towards compression. (a) Rate of concrete strain change at LBB-I TCJ
This disparity in steel strains between longitudinal steel and addi-
tional tie bars provides valuable technical information which
should be considered for improved design of TCJs in CRCP.
º
3.2. Concrete strain behavior near transverse construction joint
Fig. 9. Concrete density and modulus on US 287 in Wichita Falls District [1 lb/
ft3 = 16.02 kg/m3; 1 psi = 6.894 kPa].
1. Longitudinal tie bars at TCJs behave quite differently from lon- Based on the conclusions derived from the field testing and
gitudinal steel, primarily because longitudinal steel is continu- investigations conducted, it is recommended that no tie bars be in-
ous while tie bars are terminating at about 25 in. (0.635 m) stalled at TCJs. Also, in order to reduce stresses in longitudinal steel
from TCJs. When the concrete temperature increases substan- at TCJs, it is further recommended that transverse saw cuts be
tially from the setting temperature of concrete, tie bars actually made at 5 ft (1.52 m) and 10 ft (3.05 m) from the TCJs in the morn-
could be in compression, potentially causing horizontal crack- ing placement side.
ing of concrete at the depth of the steel placement and
distresses. References
2. Steel stresses at TCJ decrease over time, potentially due to the
creep of concrete and the development of transverse cracks, [1] Won MC. Just in time technology transfer for Portland cement concrete
pavement construction and rehabilitation. Lubbock (TX): Texas Tech
which might invalidate the benefit of additional tie bars at TCJs.
University; 2012.
3. The placement of additional tie bars at TCJs could interfere with [2] Ryu SW, Saraf S, Won MC. Project level performance database for rigid
concrete consolidation operations near TCJs, creating poor qual- pavements in Texas, Part II. Austin (TX): Texas Department of Transportation;
ity concrete and potentially causing distresses in TCJs. 2012.
[3] Texas Department of Transportation. 2010 Pavement Management
4. The rate of concrete strain variation with temperature near a Information System. Texas Department of Transportation; 2010.
TCJ is higher during the winter than during the summer season, [4] Ryu SW, Choi PG, Zhou W, Saraf S, Senadheera S, Hu J, et al. Optimizing
due to the space available or joint widths at TCJs at different concrete pavement type selection based on aggregate. Austin (TX): Texas
Department of Transportation; 2012.
seasons. In the summer, joint widths get smaller, restricting [5] Ryu SW, Choi PG, Zhou W, Won MC. Improvements of partial and full-depth
the slab displacements when concrete temperature increases. repair Practices for CRCP distresses. Austin (TX): Texas Department of
On the other hand, joint widths get larger in the winter, allow- Transportation; 2012.
[6] ARA Inc., ERES Consultants Division. Guide for mechanistic-empirical design of
ing slab displacements with less restriction. However, this sea- new and rehabilitated pavement structures. Part3-Design analysis.Champaign
sonal effect becomes less with pavement age. (IL); 2004.
5. When there is a significant time difference between the place- [7] Nam JH. Early-age behavior of CRCP and its implications for long-term
performance. Austin (TX): The University of Texas at Austin; 2005.
ments of concrete on either side of the construction joint, the
[8] Yeon JH, Choi S, Ha S, Won MC. Effects of creep and built-in curling on stress
newly placed concrete seems to pull the slab placed earlier on development of Portland cement concrete pavement under environmental
the other side of the TCJ due to drying shrinkage of newly loadings. J Transport Eng 2012;139(2):147–55.
[9] AASHTO. AASHTO guide for design of pavement structures. Washington
placed concrete. Also, the old and new concrete slabs behave
(DC): American Association of State Highway and Transportation Officials;
as a near composite structure with quite a small joint width, 1993.
at least at early ages. [10] Saraf S, Choi PG, Won MC. Minimize premature distresses in continuously
6. Due to the presence of additional steel at TCJs, the consolidation reinforced concrete pavement. Austin (TX): Texas Department of
Transportation; 2012.
of concrete near TCJs is hindered, resulting in formation of air
voids and surface distresses near TCJs.