You are on page 1of 4

TRANSMISSION AND DISTRIBUTION

IEC 61850 Goose applications to


distribution protection schemes
by Alexander Apostlov and Benton Vandiver; Omicron Electronics USA

The distribution industry is going through significant changes due to the increased requirements for improved quality of power supplied by
the utility in order to avoid costly interruptions of manufacturing or other processes caused by voltage sags, swells or unbalanced conditions
when a short circuit fault occurs in the distribution system.

The prolonged effect of short circuit


faults on sensitive equipment supplied
by distribution feeders can lead to their
failure and significant losses. This is pushing
the requirements for the performance of
distribution protection systems and making
them similar to transmission protection
systems requirements.
The improvement of power quality during
short circuit faults can be achieved in
several different ways. Like any other
problem that has to be solved, we need
first to understand the nature of the
problem and its effect on sensitive users.
Fig. 1: Phase voltages for a single-phase-to ground fault (Phase A).
The most common short circuit faults in
the system, single-phase to ground faults,
are characterised by the fact that they
introduce a voltage sag in the faulted
phase, and at the same time they result in
a voltage swell in the two healthy phases.
This is clearly seen in Fig. 1 which shows
the recorded waveform and the voltage
phasor diagram for a single-phase to
ground fault.
The case of two or three-phase faults is
quite different. For three-phase faults all
phases experience a voltage sag, while for
a two-phase fault the two faulted phases
will have lower voltages, with the healthy
Fig. 2: ITI (CBEMA) curve from a
phase having no significant change manufacturing plant.
compared to the pre-fault levels.
Fig. 2 shows a plot of depth vs. duration
of actual cases from a high-volume
manufacturing plant, with some of them
resulting in process shutdown due to
variable speed drives and vacuum pumps
failures.
There are several factors that determine
the voltage level during a short circuit fault
on the transmission or distribution system:
 System configuration
 Fault location
 Fault resistance
The first characteristic of a voltage sag, the
depth, is something that we can't control,
but we have to study in order to be able to
predict or estimate the effects of different
faults on sensitive equipment.
Fig. 3: Distributed function definition in IEC 61850.
The second characteristic of the voltage
sag, the duration, is the parameter
that we can control by properly feeder protection relays. The focus of this in distributed protection schemes that
applying the advanced features of paper is the impact of IEC 61850, and can reduce the fault clearing time in
state-of-the-art multifunctional distribution especially the use of Goose messages distribution substations.

energize - December 2010 - Page 26


TRANSMISSION AND DISTRIBUTION
The functions in the substation can be
distributed between IEDs on the same,
or on different levels of the substation
functional hierarchy. IEC 61850 defines
three such levels:
 Station
 Bay/unit
 Process
These levels and the logical interfaces
are shown by the logical interpretation of
Fig. 4. IEC 61850 focuses on a subset of the
interfaces shown in Fig. 4 with Interface 8
(shown in red) being used for high-speed
peer-to-peer communications.
The logical interfaces IF8 is defined as
direct data exchange between the
bays especially for fast functions like
interlocking.
Fig. 4: Logical interfaces in a substation.
Distribution bus protection
The protection and control in substations
is distributed in nature by the fact that
each protective relay is designed in
general to provide primar y protection
of individual substation equipment such
as transmission and distribution lines,
transformers, capacitor banks, etc.
The only substation equipment that
requires a centralised form of protection
in conventional systems is the busbar.
Transmission buses are typically protected
by bus differential protection relays. They
require current signals from each primary
equipment connected to the bus to be
Fig. 5: High speed peer-to-peer communications based available at the central location of the
distributed bus protection.
bus differential protection. The scheme
becomes much more complicated and
expensive if the current transformer ratios
are different. Things get even worse if the
bus differential protection is used in a
substation where the bus configuration
may change.
Because of the high cost and the increased
requirements for maintenance, in many
cases bus differential protection is not
installed on distribution or sub-transmission
buses. As a result, bus faults are cleared
by back-up relays with longer fault clearing
times caused by the need for time
coordination between the distribution
Fig. 6: Sympathetic trip protection.
feeder relays and the transformer relays.
This becomes a significant power quality
Distributed protection applications peer- functional hierarchy can be located in the problem because of the increased
to-peer communications are used to same physical device, and at the same duration of voltage sags.
perform protection, control, monitoring time different physical devices can be
and recording functions. Any function exchanging data at the same functional Multiple protective IEDs with IEC 61850
can be divided into sub-functions and Goose can be connected to the substation
level.
functional elements. Functional elements LAN and used in distributed bus protection
are the smallest parts of a function that Fig. 3 shows logical connections (LC) - the applications for distribution systems.
can exchange data. In IEC 61850 these communication links between functional
In case of a fault on any of the protected
are called logical nodes. When a function elements, in this case logical nodes
feeders (F1 in Fig. 5), the feeder protection
is executed based on the exchange of of the P and R groups. IEC 61850 also IED will see a fault. The same fault current
communications messages between two defines interfaces that may use dedicated will be seen by the transformer protection
or more devices, it is called "distributed or shared physical connections, the IED. As soon as the overcurrent protection
function". communication links between physical element of the feeder relay starts, the IED
The exchange of data is not only between devices. The allocation of functions will send a Goose message indicating the
functional elements, but also between between different physical devices defines detection of a fault on the feeder. The
different levels of the substation functional the requirements for the physical interfaces, transformer protection IED subscribes to
hierarchy. It should be kept in mind and in some cases may be implemented Goose messages from all feeder relays.
that functions at different levels of the into more than one physical LAN. When it receives the message indicating

energize - December 2010 - Page 27


TRANSMISSION AND DISTRIBUTION
can be use to adjust the sensitive settings
of the relays on the healthy feeders for the
duration of an inrush condition following
the clearing of a fault in a distribution
system with a significant number of motor
loads. Automation systems clearing of
a fault in a distribution system with a
significant number of motor loads.
This is known as a sympathetic trip scheme.
As soon as a relay detects a fault on the
feeder that it is protecting, it sends a
Goose message to all other feeder relays
informing them to expect an inrush as a
Fig. 7: Selective backup tripping.
result of the voltage recovery following
the clearing of the fault. Each of the
relays on the healthy feeders subscribes to
Goose messages from all adjacent feeder
protection IEDs and when it receives a
message indicating adjacent feeder fault,
it adapts its settings for the period of time
that the expected inrush condition is going
to last. Two options are usually available:
 Block the sensitive overcurrent setting
 Reduce the sensitivity by increasing
the pickup setting for the duration of
the inrush
The benefit of using Goose messages
Fig. 8: Breaker failure protection. in such a scheme is that instead of the
large number of required wires between
the binary inputs and relay outputs of all
distribution feeder protection IEDs, the just
need to publish and subscribe to Goose
messages from the adjacent feeders' IEDs.

Selective backup tripping


The common approach that many utilities
have taken is to use a single protection
IED on a feeder. In case of failure of this
relay, faults on the line are cleared by the
backup over-current protection on the
transformer or sectionalising breaker. The
problem with this approach is the long fault
clearing time that may affect sensitive
loads fed by the distribution substation.
A solution that significantly reduces the
duration of the fault is based on the
Fig. 9: Test system/configuration tool, simplified block diagram.
adjustment that the backup relay can
make in its decision to trip based on the
knowledge that a specific IED has failed.
that there is a fault on one of the feeders, of clearing the bus fault with the long
This adaptive form of protection uses
the overcurrent protection element that is time delay of a coordinated backup
the normally closed contacts of the
used for bus protection is blocked. transformer protection, the only time feeder relays that close when the relay
delay required will be the longest possible is not healthy. When the transformer of
If the fault is on the bus (F2 in Fig. 5), no
overcurrent element starting time plus a sectionalising breaker relay sees a fault
feeder IED will see a fault, the transformer
safety margin. and does not get any blocking signal from
protection IED is not going to receive a
Goose message indicating a feeder fault. The benefit of the peer-to-peer any of the feeder relays, it knows that there
This indicates a bus fault and the relay is communications based distributed bus are two possible cases:
going to trip the transformer breaker to protection is that it provides fast fault  The fault is on the feeder with the failed
clear the fault. clearance for distribution bus faults without relay
the need for any additional protection The fault is on the distribution bus
The peer-to-peer communications based 
equipment.
bus protection requires an operating time Since the probability for a fault on a
for the fault detection of about one cycle Sympathetic trip logic distribution feeder is much higher that
for the relays involved. The addition of 0,25 the probability for a distribution bus fault,
cycle (4 – 5 ms) for the communication The changes of fault conditions in the
the. relay first sends a signal (1) to trip the
message and the safety time delay of distribution system impact not only the
breaker of the failed relay. If this does not
0,75 cycle in the transformer protection sensitive loads, but also depending on the
clear the fault, then it is clear that the fault
load may lead to the undesired operation
relay ensures a total operating time of is on the bus and it is cleared by tripping
of protection elements of multifunctional
about two cycles. the source breakers with signals (2).
relays on healthy feeders. Detecting the
The benefit of this scheme is that instead operation of a relay on adjacent feeder The conventional implementation of

energize - December 2010 - Page 28


TRANSMISSION AND DISTRIBUTION
this scheme is based on the use of the Functional testing Of IEC 61850-8-1 and function being tested. For example, if
normally closed contact of an output IEC 61850-9-2 based bay and substation the tested function is based on RMS
relay that closes when the relay fails. level distributed applications values or phasor measurements, the
This implementation requires hardwiring simulation tool may include a sequence
The testing of distributed protection of steps with the analog values in each
between all feeder relays and the
functions that are based on IEC 61850 of the steps defined as phasors with their
dedicated opto inputs of the transformer
Goose are similar functionally to the magnitude and phase angle. Based
relay. The IEC 61850 Goose repetition
testing of hardwired schemes. The main on these configuration parameters the
mechanism can be used to eliminate the
difference is that in this case the test simulation tool will generate the sine
need of the above described hard wiring.
devices need to be able to act as waveforms to be applied as analog
If the transformer protection IED subscribes
IEC 61850 devices, i.e. to be able to signals or in a digital format to the tested
to Goose messages from all feeder
publish and subscribe to Goose messages. components or systems. If the tested
protection IEDs, within the maximum
If the distributed scheme includes devices functions are designed to detect transient
repetition time interval it will receive a conditions or operate based on sub-cycle
located remotely from each other in the
Goose message from all healthy IEDs. set of samples from the waveform, an
substation, we may need multiple test
If one of the feeder protection IEDs fails, devices with virtual simulators or analog electromagnetic transients simulation will
it will stop sending Goose messages. This outputs. The simulation of the substation be more appropriate.
will cause the enabling of the selective and system environment required for the The third component of the test system
backup trip logic in the transformer functional testing of bay and system level is the Virtual IED simulator that is used to
protection IED. functions will require the simulation of represent components of the system that
multiple IEDs. are not available at the time of testing,
Breaker failure protection
for example during factory acceptance
Breaker failure protection is a scheme A test system designed for IEDs or distributed testing. During the testing this module
that is typically used at the transmission applications based on IEC 61850 have send Goose messages that the function
level of the system due to the impact of multiple components that are needed or sub-function under test uses as inputs
such event on the stability of the electric for the testing of the individual functions, that determine its behavior under the test
power system. With the availability of built as well as a complete application. A conditions applied.
in breaker failure protection function in simplified block diagram of such a system
many multifunctional protection IEDs and is shown in Fig. 9. The fourth component of the test system
the increasing requirements for decrease is the test evaluation tool that includes the
in the duration of distribution faults. The The first component of the test system monitoring functions used to evaluate the
distributed breaker protection scheme is the test configuration tool. It takes performance of the tested elements within
can be implementation using two different advantage of one of the key components a distributed sampled analog value based
approaches depending on the location of the IEC 61850 standard – the substation system. Such evaluation tool requires
of the breaker failure detection element. configuration language. The configuration multiple evaluation sub-modules that
tool is used to create the files required for are targeted towards the specifics of the
I n t h e f i r s t c a s e t h e b r e a ke r f a i l u r e configuration of different components function being tested. In our case they are
protection element is in the multifunctional of the test system. It imports different based on monitoring the Goose messages
transformer protection relay. When the from a tested IED.
configuration files defined by part 6 of
distribution feeder protection relay
IEC 61850. The test system Configuration The fifth component of the test system is
operates, it sends a Goose message
Tool reads the information regarding the reporting tool that will generate the test
indicating the change of state of any of
all IEDs, communication configuration reports based on a user defined format
the protection functional elements.
and substation description sections. This and the outputs from the simulation and
The transformer protection relay subscribes information is in a file with. SCD extension evaluation tools.
to this message, and when it receives the (for substation configuration description)
change of value of a feeder protection and is used to configure the set of tests to Conclusions
functional element operate data object to be performed. The application of IEC 61850 Goose
True, initiates the breaker failure protection messages allows significant improvements
function. If the breaker fails to trip, the The overall functionality of any IEC 61850
in the protection of distribution substations
fault current will keep the level of the compliant device is available in a file that
that reduce fault clearing times and
current above the pickup setting of the describes its capabilities. This file has an
minimise the effect of short circuit faults
breaker failure detection element, the extension .ICD for IED capability description.
on sensitive loads. Using such high-speed
timer will time out and the relay will trip The IED configuration tool sends to the messages eliminates the need for multiple
the required breakers to clear the fault as IED information on its instantiation within hard wired connections. In some cases
shown in Fig. 8. a substation automation system (SAS) the implementation of a hard-wired
Another implementation of the scheme project. The communication section of the distribution protection scheme (such as
is based on a built-in breaker failure file contains the current address of the IED. sympathetic trip logic) in a large substation
protection in each of the distribution The substation section related to this IED requires also that all protection IEDs have
feeder protection IEDs. In this second when may be present and then shall have name a significant number of binary opto inputs
the distribution feeder protection relay values assigned according to the project and relay outputs. The publisher/subscriber
operates, it initiates the built-in breaker specific names. This file has an extension. mechanism used with Goose messages
failure protection function. If the breaker CID (for configured IED description). The eliminates this problem.
fails to trip the breaker failure protection second component of such a system is a
function will operate and send a Goose simulation tool that generates the current Acknowledgement
message indicating the change of state and voltage waveforms. The specifics This article was presented at the 2010
of this protection functional element. The of each simulated test condition are S o u t h e r n A f r i c a n Po w e r p r o t e c t i o n
transformer protection relay subscribes determined by the complete, as well as Conference, Gauteng November 2010
to this message, and when it receives the configured functionality of the tested and is reprinted with permission.
the change of value of a breaker failure device or application.
protection function element Operate data Contact Alexander Dierks, Alectrix,
object to True, will trip the required breakers The simulation tool requirements will also Tel 021 790-1665,
to clear the fault as shown in Fig. 8. be different depending on the type of alexander.dierks@alectrix.co.za 

energize - December 2010 - Page 29

You might also like