You are on page 1of 10

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/238179289

Simplified CPM/PERT simulation model - Closure

Article  in  Journal of Construction Engineering and Management · May 2000


DOI: 10.1061/(ASCE)0733-9364(2000)126:3(219)

CITATIONS READS
71 647

2 authors:

Ming Lu Simaan M. Abourizk


University of Alberta University of Alberta
144 PUBLICATIONS   1,404 CITATIONS    240 PUBLICATIONS   3,724 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Simulation-Based Analytics for Fabrication Quality-Associated Decision Support View project

Sensor-Data-Driven Simulation of Snow Removal Projects View project

All content following this page was uploaded by Ming Lu on 05 February 2016.

The user has requested enhancement of the downloaded file.


Estimating Highway
Construction Production
Rates during Design:
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

Elements of a Useful
Estimation Tool
WAI KIONG CHONG, M.ASCE; SANG-HOON LEE, M.ASCE; AND

JAMES T. O’CONNOR, M.ASCE

ABSTRACT: Construction scheduling for highway projects is an important process dur-


ing the design stage. Numerous research studies have attempted to apply new techniques
to improve the accuracy of construction scheduling. Many of these studies, however,
failed to address the practicality of the scheduling methods and the needs of highway
designers. The authors conducted literature reviews, surveys, and interviews to study the
challenges designers face in estimating production rates for highway construction. We
found that estimation tools for production rates should be flexible, user friendly, and
efficient yet comprehensive. Data should be collected from reliable sources and analyzed
appropriately and efficiently before being applied to a production rate tool. This study
suggested that combining designers’ experience and reliable tools is the most effective
way to develop realistic production rates for highway construction scheduling.

C
onstruction schedule development is Designers do not have control over many productiv-
a critical process during the design ity variables, such as the means and methods of con-
phase of a highway construction struction and the productivity of equipment and
project. Under- or overestimation of labor. Instead, they take the “big picture” approach,
a project schedule can cripple the seeking an ideal schedule, not an exact one. They
smooth progress of a project; a tight aim to develop a logical and reliable schedule that is
schedule may increase the chances of excessive claims based on the limitations normally faced in highway
and delays, whereas a loose schedule may cause construction projects. The contractor’s schedule is nor-
project idling during construction, increasing the mally more thorough and detailed than the designer’s,
chances of material and equipment damage by as contractors need total control in every construction
bad weather and safety hazards for pedestrians and process. As a result, the designer’s approach to schedul-
drivers. ing can be very different from the contractor’s approach.

JULY 2011 258 Leadership and Management in Engineering

Leadership Manage. Eng., 2011, 11(3): 258-266


The scheduling process in the design phase involves work operation into smaller pieces for estimating
three key activities: (1) A production rate is calculated purposes may increase schedule reliability; however,
for individual work items, (2) the production rates limited knowledge of and control over operations
from these work items are consolidated and lead– may prevent designers from doing so. Designers
lag relationships are developed among them, and may not have the luxury of time and information to
(3) a final schedule is developed using the Gantt chart estimate their schedule in such detail. Most designers
or critical path method (CPM). Many departments of break operations down into a size that is manageable
transportation (DOTs) do not have sufficient data enough to increase the schedule’s reliability without
to apply computerized and complicated statistical involving too many variables. Hancher et al.
models to improve the reliability of their estimates, (1992) found that the common practice among design-
and designers typically develop estimates within the
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

ers was to break down their production rates into


boundaries of their knowledge of construction and work items, each of which has its own productivity
the information they readily possess. variables.
The purpose of the research described in this paper Schedule estimates are then based on critical work
was to improve the accuracy of production rate esti- items on a project. CPM involves identifying the criti-
mation for critical highway work items (i.e., the first cal path, which consists of work items that take the
activity mentioned above). This paper examines how longest overall time to complete on a project and thus
designers can improve their production rate estimates normally extend over the project completion time. Ac-
given the boundaries they face. It examines statistical, tivities that fall on the critical path are what designers
computerized, and factor analysis models and the need to schedule for. These activities normally include
quality of the data sources and its impact on the reli- work items with the highest quantities or those that
ability of the scheduling estimates. Interviews and sur- require a lot of lead time. A typical highway project
veys were conducted to study the requirements for a includes more than 100 work items. Given the tight
good scheduling tool at the highway design phase. schedule in most projects, designers do not have the
This research can help schedulers develop a better luxury of estimating every work item. They need to
understanding of the parameters that affect work item identify and concentrate only on the critical work
productivity and that should be considered in calcu- items in their projects.
lating the production rates. Highway construction time estimation methods
adopted by different states, agencies, and districts
can be significantly different from one another.
The Texas DOT, for example, adopted the Construc-
SCHEDULING PRACTICES FOR HIGHWAY tion Time Determination System (CTDS; Hancher
CONSTRUCTION DESIGN et al. 1992), and the New Jersey DOT adopted the
Productivity factors occurring on “normal” and “ab- Capital Program Construction Scheduling Coding
normal” production days may be different (Abdul and Procedures for Designers and Contractors
Majid and McCaffer 1998). Designers seek to estimate Manual. These scheduling methods are quite different.
a normal production day, as an abnormal production For the New Jersey DOT, the production rate for a
day includes variables that cannot be controlled, such cast-in-place (CIP) retaining wall for Type 1 bridge
as rain heavy enough to prevent excavation work, a construction is 20 days/30 meters, given the following
road accident, or unforeseen utility conflicts or soil assumptions: (1) 8-hour working day per crew,
conditions. Excusable delays occur only on abnormal (2) 50% added for one bridge and 25% added for
days, and contractors are normally allowed to claim two, (3) separate estimates for bridges built in differ-
time extensions for these delays. As such, productivity ent stages, (4) additional 30 days required for bridges
factors on normal and abnormal days are separated, built over water, and (5) inclusion of concrete curing
and designers base their estimates on a normal produc- time. In contrast, the Texas CTDS production rate for
tion day. retaining wall construction is 9.3 to 18:5 m2 per day,
One of the most common scheduling practices dur- and soil condition is the only adjustment needed.
ing the design phase is to break down construction Thus, the two methods differ in units (area versus
work into constituent operations and estimate each op- length), productivity factors, and design issues. In
eration individually. There is no standard way of both systems, however, designers’ experiences are
breaking down the operations; it depends on how critical in their decisions regarding the ideal produc-
detailed the designers wish to be. Breaking down each tion rate based on the range given.

Leadership and Management in Engineering 259 JULY 2011

Leadership Manage. Eng., 2011, 11(3): 258-266


The Transportation Research Board conducted a Various productivity factors have different impacts
series of studies between 1981 and 1995 to investigate on materials and components. For example, off-site
and develop systems to improve the reliability of con- fabricated precast concrete has less productivity vari-
tract time estimation of highway construction projects ability during installation but a higher chance of
(National Cooperative Highway Research Program being delayed during transport, whereas CIP concrete
1981; Herbsman and Ellis 1995). In addition, has a higher chance of being delayed by poor weather
Hancher et al. (1992) found in a survey of employees conditions. Other productivity factors include size
in 36 DOTs that 44% of the respondents relied on of equipment (Bhurisith and Touran 2002; Sawhney
personal experience to estimate production rates, and Mund 2002), controllability of soil condition
30% used standard production rates that were usually (Allouche et al. 2001), weather conditions, and losses
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

provided by the DOTs, and 22% used production from learning (Thomas et al. 1999; El-Rayes &
rates from historical records of previously completed Moselhi 2001). For example, it makes sense to link
projects from other sources. Data used to develop these the productivity of foundation, pipeline, and retaining
systems were normally collected either from survey re- wall construction to soil conditions. Alternatively, the
turns or documentation from projects. Some DOTs learning curve and poor weather conditions have a
and several contractors had simplified their production greater effect on highly repetitive work items such
rate estimates into three values—mean, optimistic, as pavement, multiple drilled shafts, and hot-mix as-
and pessimistic values for each work item—and phalt pour. Thomas et al. (1999) found that changing
designers determined a realistic rate from these values weather, erroneous work, poorly coordinated material
based on their experience. delivery, and frequent equipment relocation were
more disruptive to long and continuous production
processes than to less repetitive work items. Stoppage
PRODUCTIVITY FACTORS to a process slows down work momentum and leads to
In production scheduling, productivity factors are productivity losses of other work, which Thomas et al.
used to establish relationships between fluctuating (1999) described as the “ripple effect.” However, be-
production rates and production work items. Design- cause a highway designer cannot accurately predict the
ers must identify relevant productivity variables they chances of having disruptions during construction,
can rely on to improve their estimates. such disruptions are normally excluded from the
Differing geological locations, site conditions, and schedule at the design phase.
other location variables affect work productivity. Con- Design can significantly affect work productivity
structing a drilled shaft on dry soil may be faster than (Poh and Chen 1998). Constructability has been
constructing one nearer a riverbank, assuming the same shown to increase site productivity, and site conges-
crew is used in both operations. Constructing a road on tion can be avoided with designs that use smaller
a mountain may be much slower than constructing one equipment.
on flat land. A sudden change in the weather can dis- Site condition would normally be considered a
rupt or delay construction operation. Construction productivity factor. Construction on mountainous
work has to stop during snowstorms in the warmer re- regions, in tight work spaces, in extreme cold and heat,
gions (e.g., Florida and Texas) but can continue in the on rough terrain, on congested work zones, and in close
colder regions (e.g., Maine and Washington). Rural proximity to adjacent structures would normally slow
highway projects face fewer traffic problems than high- down workers’ productivity (Koehn and Brown 1985).
way projects in metropolitan areas, which face frequent Wideman (1994) showed that the productivity of
traffic congestion, strict environmental regulations, workers varied during different phases of construction.
risky traffic safety, and right-of-way issues that reduce His study found that workers’ productivity was slow
construction productivity. Rural highway construc- during the early phase of construction and slowly sped
tion, however, may face difficulties in acquiring skilled up as construction progressed. Productivity continued
workers and highly productive equipment, driving to rise and plateau between 25% and 75% of project
down productivity (Koehn and Ahmed 2001). Thus, completion, and then fell until project completion. He
the location of the project is not a dependable produc- attributed the initial growth to workers’ learning
tivity factor; in a work zone located in a metropolitan effect and the fall nearing project completion to re-
area that has ample work space, highway congestion duced work amount. Thus, worker productivity
may affect only material delivery and may have mini- should not be treated as uniform throughout the
mal impact on work operations. construction phase.

JULY 2011 260 Leadership and Management in Engineering

Leadership Manage. Eng., 2011, 11(3): 258-266


Most research has found that work productivity is of the data are based on personal opinion. Although
affected by more than one productivity factor. For ex- contractors may collect huge amounts of data from
ample, our literature review indicated that foundation existing records, we question the reliability and use-
construction is affected by many factors, including soil fulness of these data if they are not being recorded for
type, drill type (size, type, and construction method), production rate estimation purposes.
angle of swing, methods of spoil soil removal, pile axis Regression analysis, factor analysis models,
adjustment, depth and size of holes, equipment Monte Carlo simulation, fuzzy logic, schedule algo-
power, operator efficiency, weather conditions, spoil rithms, and neural networks have been applied to
soil removal and space availability, rebar cage instal- scheduling (AbouRizk and Wales 1997; Adeli and
lation procedures, concrete pouring methods, machine Karim 1997; Ben-Haim and Laufer 1998; Jiang
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

availability, job and management conditions, drilling and Shi 2005; Lee 2005; Lee and Arditi 2006). Several
time activity, other time activities, change orders, and attempts have been made to integrate some of these
weather (Zayed and Halpin 2004; Hanna et al. 2002; techniques with standard scheduling software, such
El-Rayes and Moselhi 2001). Furthermore, Thomas as Primavera, Microsoft Project, and SureTrak. Alter-
et al. (1989) emphasized that productivity factors natively, many designers continue to develop project
should be divided into within-project, between- schedules using their own experience. Advanced
project, and regional drivers. Such divisions allow scheduling techniques may improve a schedule esti-
designers to better identify and allocate significant mate’s accuracy, but many departments of transporta-
productivity drivers for different work zone scenarios. tion lack the required infrastructure and information
to use these techniques. In addition, scheduling tools
developed in the past for specific purposes became out-
PRODUCTION RATE DOCUMENTATION AND dated very quickly. Texas DOT’s CTDS (Hancher et al.
ANALYSIS 1992), for example, became obsolete simply because
Developing reliable productivity data documentation there was no way to update the information in the sys-
and analysis processes is critical to the development of tem. Thus, any new scheduling tool should support
a dependable scheduling tool. Data accuracy and popular scheduling software, such as Primavera and
correct analysis are the two critical elements of any Microsoft Project.
successful and reliable information system. Collected Lessons learned from the past have shown that
productivity data should support the following func- schedulers tend to resist a complicated information
tions: (1) identify significant productivity factors, technology system and prefer a flexible system. Be-
(2) examine and establish the relationships between cause most designers use the critical path and Gantt
factors and productivity, (3) develop production rate chart methods to schedule their projects, Primavera
models for scheduling, and (4) study productivity and Microsoft Projects are the most frequently used
improvement methods. Efficiency of data collection scheduling programs. Therefore, production rate esti-
is also critical, though there is a need to balance effi- mation tools should not deviate too much from these
ciency and reliability. Survey forms and existing pro- techniques and software. Production rate information
ductivity databases are the two most common data that is easily integrated with the software and tech-
collection methods. Hancher et al.’s (1992) survey niques will allow designers to spend less time learning
of experienced designers and site personnel in 36 new techniques and software and more time improv-
DOTs indicated that many contractors kept and de- ing the reliability of their estimates. Consequently,
veloped their own production factor and rate informa- any production rate system should be either com-
tion. They gathered most of their productivity pletely independent from or well integrated into
information from daily log books, payment and sched- existing software and estimation techniques.
ule documentation, record books, and information Researchers have successfully applied many tech-
stored on computers. Some contractors required their niques to improve the reliability of production
staffs to input information systematically and kept rate estimates. Some of these techniques include re-
comprehensive records of all their projects. No proce- gression analysis and models, factor analysis models,
dures or standards have been developed for such Monte Carlo simulation, and neural networks. Other,
recording processes; thus, the reliability of the infor- more simplified methods include summing up col-
mation may vary greatly across organizations. Like any lected production rates and averaging them into mean,
research using the survey approach, the reliability of optimistic, and pessimistic values (Hancher et al.
Hancher et al.’s findings cannot be verified, and most 1992). The techniques an organization adopts depend

Leadership and Management in Engineering 261 JULY 2011

Leadership Manage. Eng., 2011, 11(3): 258-266


heavily on the types of obtainable and available infor- the same time. Also, these techniques are applicable
mation within the organization, the predictability of only for measuring relationships between activities
the productivity factors, and the details and accuracy and cannot be used to improve the reliability of
requirements of the production rate estimates. Neural production rates.
network application to estimation requires an exten- Many researchers have applied dynamic and sto-
sive amount of information to develop the network to chastic approaches and developed simulation models
the point where the network would self-learn and cor- that integrate the construction process network using
rect itself. activities at the project level to develop production
Lu and AbouRizk (2000) supplemented PERT rate models that can improve the reliability of dura-
(Program Evaluation and Review Technique) with tion variability estimates of and between activities.
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

statistical and simulation techniques to develop a AbouRizk and Wales (1997) illustrated that such a
six-value estimation technique: minimum duration project simulation model should consist of three com-
(optimistic), maximum duration (pessimistic), mean, ponents: (1) a project network that maintains schedule
standard deviation, confidence interval, and probabil- logic, (2) a stochastic and random particles model that
ity. This technique allows estimators to better under- generates uncertain factors, and (3) a productivity
stand the risks and confidence of their estimates and model that relates uncertainty of productivity factors
eliminates the need to guess. Regression analysis is one to generated project conditions. Each activity could be
of the most common methods applied to examine and simulated individually and combined at a later stage
quantify the relationships between productivity fac- (discrete-event continuous simulation). Discrete
tors and rates (Koehn and Brown 1985; Sanders events could be combined for simultaneous and con-
and Thomas 1993; Hanna et al. 2002). Regression tinuous simulation. Their models relied on historical
analysis is useful to illustrate the continuous relation- data such as weather data from meteorological agen-
ships between numeric productivity factors and cies. Construction processes are broken down into
rates. However, it cannot be used to develop relation- individual activities based on their relationships with
ships between nonnumeric (categorical) productivity various productivity factors. The effect of a productiv-
factors and rates. For such factors, Hancher et al.’s ity factor on an individual activity is measured by the
(1992) method is the most common approach; the simulation process and is later combined into a
contractor determines a productivity rate under nor- schedule.
mal conditions (normally, a mean or median) and Dzeng and Tommelein (1997) suggested breaking
two rates for extreme conditions (normally, optimistic down construction projects into “cases” and automat-
and pessimistic). Other statistical techniques are avail- ing the duration estimating process for each case, and
able to handle nonnumeric factors (categorical factors), they found that their schedule estimates were more ac-
such as box plots and longitudinal data analysis tech- curate. The proposed application of neural networks to
niques (commonly used in social science research). The construction scheduling (Adeli and Karim 1997),
more advanced techniques require special treatment of although seeming to help improve the reliability of
data, like creating artificial variables and splitting data construction scheduling through continuous knowl-
into different components. edge learning, has limited application at the design
Peña-Mora and Li (2001) proposed using the stage, especially on improving the reliability of
GERT (Graphical Evaluation and Review Technique) production rate estimates. Adeli and Karim (1997)
diagramming scheme to calculate the probability of stated that neural dynamic models require breakdown
project duration by measuring the variability of differ- of work into tasks, crews, and segments, and logics and
ent branches and loops of each construction activity, constraints between repetitive tasks have to be devel-
their relationships, and overlaps with other nonrele- oped while each task is simulated individually. Exces-
vant activities. They claimed that such a scheme could sive amounts of data are required to ascertain the
better control or even eliminate variability within a usefulness of neural dynamic models since the accuracy
schedule. Park and Peña-Mora (2004) proposed using of the final estimates heavily depends on inputs to the
reliability control to refine activity buffers and applied system. Such requirements of massive and continuous
simulation to measure and reduce buffer variability information inputs make the neural network ineffi-
between activities. However, designers may not have cient and impractical to be applied at the design phase.
sufficient control and may lack the ability to predict Bonnal et al. (2004) believed that fuzzy logic had
buffer variability between activities during design, become sufficiently mature to be applied to project
and they cannot feasibly apply both techniques at scheduling in real life. They claimed that fuzzy logic

JULY 2011 262 Leadership and Management in Engineering

Leadership Manage. Eng., 2011, 11(3): 258-266


could eliminate calculation imprecision, narrow the the flexibility of using any software they chose. Many
probability of estimates, and improve the plausibility districts preferred user-friendly and flexible systems
and credibility of calculated values. In most produc- that could easily integrate into Primavera, Microsoft
tion rate estimates at the design phase, uncertainties Project, and SureTrak. Indeed, most highlighted the
during production cannot be predicted, and thus tendencies to use CPM and/or Gantt charts for sched-
designers cannot include them in the schedule. Fuzzy uling. They preferred to carry out production rate
and probabilistic statistical techniques can be calculation manually rather than using the software.
extremely complicated. The need to create new vari- Many respondents suggested they would prefer a
ables (including dummy ones) to simulate uncertain- system that would integrate with Microsoft Excel.
ties of individual activities and between them They highlighted that because some of the projects
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

(Vanhoucke 2006; Fan and Tserng 2006) requires de- were small, manual calculation helped speed up the
signers to look at different ways of treating their data. estimation process. The feedback also highlighted that
In real life, these variables do not exist, so it may be accurate production rate information was needed that
difficult for designers to understand and appreciate reflected and represented the situations and conditions
their meanings and purposes. These techniques also in different districts and regions, like calendar day and
require extensive algorithms to estimate other resource working day contracts, rural areas, soil conditions, and
constraints (Jiang and Shi 2005). Algorithms are regional profiles. Many designers highlighted that the
needed to clarify relationships between activities units adopted should be in line with the pay units, as
and allow schedulers to better control variability be- this would reduce their work to convert the units
tween activities. Refinement and reliability of the between schedule and payment.
schedules could be enhanced with algorithms. We selected eight Texas DOT designers for inter-
Construction schedules are dynamic and thus need view with regard to their needs for a better scheduling
to be updated frequently to reflect changes during tool. Their feedback included the following seven
construction. El-Shahhat et al. (1995) found that be- points:
tween 29% and 67% of all construction errors oc-
curred at the design phase, while only 12% to 59% 1. They hoped to separate the production rates and
of errors occurred at the construction phase. Errors scheduling tools from their scheduling software
committed at the design phase may be magnified to make the system more flexible and adaptive
at the construction phase and cause problems during to many situations.
construction operations. Thus, designers cannot rely 2. They wanted more realistic rates that reflected
too much on their personal experience. actual site conditions. Many of their rates were
unrealistic and were not collected from the site.
3. They wanted a system that was user friendly
and did not hamper the contributions of the
A REVIEW OF SCHEDULE ESTIMATION designers. The designers needed to have more
PRACTICES AND NEEDS control over the rates and to be able to adjust
A survey conducted by the Texas Department of the rates accordingly so that they would not
Transportation found that scheduling practices varied be forced to accept unrealistic rates.
across districts and regions (O’Connor et al. 2005). 4. They cited the need to know productivity fac-
Most of the practices were driven by the needs of tors at the design stage and to exclude factors
the districts, the top management, and the demands that cannot be predicted at the design stage.
of the engineers in those districts. Some districts even 5. Most agreed that statistical tools can help im-
developed their own system to handle their unique prove the accuracy of their schedules, but they
needs and situations. Each district had authority over preferred these tools to be relatively simple and
its own scheduling methods, and employees were practical. They noted that complicated statisti-
given the option to adopt anything that suited them. cal and simulation techniques make any tool
Scheduling software used in the Texas DOT included unfriendly and yield information that may be
in-house systems like Primavera, Microsoft Project, difficult to interpret.
and SureTrak. The type of software used depended 6. Because it is impossible to establish good rela-
heavily on the preferences of the employees. Several tionships among the many productivity factors
districts did not use the Texas DOT’s standard system for any work item, they suggested that a system
(i.e., CTDS), as they found that it was inflexible and should not be restrictive in establishing these
that the information was not accurate. They preferred relationships.

Leadership and Management in Engineering 263 JULY 2011

Leadership Manage. Eng., 2011, 11(3): 258-266


7. The most popular scheduling programs were comply with the requirements of the more advanced
Primavera and Microsoft Project, and the most techniques. The designers found that many values
popular techniques were Gantt chart and CPM. generated by these techniques did not mean anything
They did not believe new software was needed. to them and noted that schedules do not need to be
accurate, just realistic and reliable. The more advanced
statistical and simulation techniques help improve the
accuracy of models; however, most project schedules do
RECOMMENDATIONS FOR A PRACTICAL not require this kind of accuracy.
SCHEDULING TOOL It is also important to ensure that data are collected
We identified the following six key components of a efficiently and reliably. The sources of data are critical,
production rate estimation system:
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

and sources need to be properly selected and checked


1. Data collection methodology, before the data are used to develop scheduling tools.
2. Data arrangement, Although breaking down work processes into greater
3. Data analysis methodology, detail can help improve the accuracy of estimates, it is
4. Critical work items analysis, impractical to expect designers to do this. Designers
5. Data recall and information output system, and do not have control over the actual work processes, and
6. Factor and driver analysis. scheduling is one of the many duties they have to do.
Separating the production rates by work items is a
Integrating these components into current schedule more efficient way for designers to break down work
estimation practices is critical; they are consistent with processes. In addition, factors have to be properly de-
existing good schedule estimating practices. In addi- scribed, meaningful to the designers, and foreseeable
tion, several useful schedule estimation techniques at the design stage. The literature reviews also found
are available to estimate and analyze production that productivity estimation tools may present the
rates, such as statistical analysis (normally regression), rates in many ways. The designers preferred to have
neural networking, Monte Carlo simulation, and lin- a tool that presents flexible values or even ranges of
ear programming. values that they could choose from and would allow
Most designers surveyed for this research conducted them to adjust according to their own logic. In short,
their scheduling using the CPM and/or Gantt charts. they demanded controllability, applicability, and flex-
They often relied on Primavera, MS Project, or Sure- ibility in the estimation tool.
Trak, so any scheduling tools should be either inte- Finally, productivity factors should be categorized
grated into or separate from this software. The appropriately and integrated when several factors have
designers wanted to retain the functions of CPM to be considered. Historical information without
and Gantt charts but needed more reliable and useful proper appraisal may not reflect the actual conditions
information on production rates and production vari- when they were collected. Historical information on
ability to develop better estimates. Thus, they were pipeline production, for example, can document rates
looking for reliable and useful production rate and as low as 10 meters per day or as high as 400 meters
variability estimation tools that could easily be inte- per day. Users of such information should have access
grated into or applied to existing CPM or Gantt to reasons, factors, or models to use in deciding
charts. In addition, because it is impossible to collect whether their rates should be 10 or 400. Relying
sufficient data to establish good statistical models for on personal experience to decide a rate will naturally
every factor, designers need some freedom to use their incorporate some psychological effects.
experience to adjust the production rates provided by
these tools in order to estimate more realistic rates.
Relying solely on experience can make production
rates less reliable and unrealistic, as research has shown CONCLUSION
that human memory distorts information easily; like- Literature reviews, surveys, and interviews have high-
wise, scheduling tools alone cannot replace experience. lighted important factors to be considered in design-
Combining experience with reliable scheduling tools ing scheduling tools. The results also highlighted
is the solution to more reliable construction project several important requirements by practitioners that
scheduling. past researchers failed to appreciate. The industry
Scheduling tools should apply only the less compli- needs a practical tool to support designers and inte-
cated statistical and simulation techniques. It is impos- grate their experiences, and this research can be used
sible to collect sufficient and reliable information to to inform future work to develop such a tool.

JULY 2011 264 Leadership and Management in Engineering

Leadership Manage. Eng., 2011, 11(3): 258-266


REFERENCES Jiang, G., and Shi, J. (2005). “Exact algorithm for
Abdul Majid, M. Z., and McCaffer, R. (1998). “Fac- solving project scheduling problems under multi-
tors of non-excusable delays that influence contrac- ple resource constraints.” J. Constr. Eng. Manage.,
tors’ performance.” J. Manage. Eng., 14, 42–49. 131, 986–992.
AbouRizk, S. M., and Wales, R. J. (1997). “Com- Koehn, E., and Ahmed, F. (2001). “Production rates
bined discrete-event/continuous simulation for for urban/rural projects in developing areas.”
project planning.” J. Constr. Eng. Manage., 123, International Transaction INT.03, Association for
11–20. the Advancement of Cost Engineering, Morgan-
Adeli, H., and Karim, A. (1997). “Scheduling/cost town, WV.
optimization and neural dynamics model for con- Koehn, E., and Brown, G. (1985). “Climatic effects
struction.” J. Constr. Eng. Manage., 123, 450–458. on construction.” J. Constr. Eng. Manage., 111,
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

Allouche, E. N., Ariaratnam, S. T., and AbouRizk, S. 129–137.


M. (2001). “Application of horizontal characteri- Lee, D.-E. (2005). “Probability of project completion
zation techniques in trenchless construction.” using stochastic project scheduling simulation.”
J. Constr. Eng. Manage., 127, 476–484. J. Constr. Eng. Manage., 131, 310–318.
Ben-Haim, Y., and Laufer, A. (1998). “Robust reli- Lee, D.-E., and Arditi, D. (2006). “Automated stat-
ability of projects with activity-duration uncer- istical analysis in stochastic project scheduling
tainty.” J. Constr. Eng. Manage., 124, 125–132. simulation.” J. Constr. Eng. Manage., 132,
Bhurisith, L., and Touran, A. (2002). “Case study 268–277.
of obsolescence and equipment productivity.” Lu, M., and AbouRizk, S. M. (2000). “Simplified
J. Constr. Eng. Manage., 128, 357–361. CPM/PERT simulation model.” J. Constr. Eng.
Bonnal, P., Gourc, D., and Lacoste, G. (2004). Manage., 126, 219–226.
“Where do we stand with fuzzy project schedul- National Cooperative Highway Research Program.
ing?” J. Constr. Eng. Manage., 130, 114–123. (1981). “Contract time determination.” Synthesis
Dzeng, R.-J., and Tommelein, I. D. (1997). “Boiler of Highway Practice Rep. 79, Transportation
erection scheduling using product models and Research Board, National Research Council,
case-based reasoning.” J. Constr. Eng. Manage., Washington, DC.
123, 338–347. O’Connor, J. T., Chong, W. K., Huh, Y., and
El-Rayes, K., and Moselhi, O. (2001). “Impact of rain- Kuo, Y. (2005). “Development of improved
fall on the productivity of highway construction.” information for estimating construction time.”
J. Constr. Eng. Manage., 127, 125–131. Rep. No. 0-4416-1, Texas Department of Trans-
El-Shahhat, A. M., Rosowsky, D. V., and Chen, portation, Center for Transportation Research
W. F. (1995). “Accounting for human error dur- (University of Texas, Austin), Austin, TX.
ing design and construction.” J. Archit. Eng., 1, Park, M., and Peña-Mora, F. (2004). “Reliability
84–92. buffering for construction projects.” J. Constr.
Fan, S.-L., and Tserng, H. P. (2006). “Object-oriented Eng. Manage., 130, 626–637.
scheduling for repetitive projects with soft logic.” Peña-Mora, F., and Li, M. (2001). “Dynamic planning
J. Constr. Eng. Manage., 132, 35–48. and control methodology for design/build fast-
Hancher, D. E., McFarland, W. F., and Alabay, R. T. track construction projects.” J. Constr. Eng.
(1992). “Construction contract time determina- Manage., 127, 1–17.
tion.” Research Rep., Texas Department of Trans- Poh, P. S. H., and Chen, J. (1998). “The Singapore
portation, Austin. buildable design appraisal system: A preliminary
Hanna, A. S., Camlic, R., Peterson, P. A., and review of the relationship between buildability,
Nordheim, E. V. (2002). “Quantitative definition site productivity and cost.” Constr. Manage. Econ.,
of projects impacted by change orders.” J. Constr. 16, 681–692.
Eng. Manage., 128, 57–64. Sanders, S. R., and Thomas, R. H. (1993). “Masonry
Herbsman, Z. J., and Ellis, R. (1995). “Determination productivity forecasting model.” J. Constr. Eng.
of contract time for highway construction proj- Manage., 119, 163–179.
ects.” Rep. 215, National Cooperative Highway Sawhney, A., and Mund, A. (2002). “Adoptive
Research Program Synthesis of Highway Practice, probabilistic neural network-based crane type
Transportation Research Board, National Research selection system.” J. Constr. Eng. Manage., 128,
Council, Washington, DC. 265–273.

Leadership and Management in Engineering 265 JULY 2011

Leadership Manage. Eng., 2011, 11(3): 258-266


Thomas, H. R., Riley, D. R., and Sanvido, V. E. Wai Kiong Chong is assistant professor, De-
(1999). “Loss of labor productivity due to delivery partment of Civil, Environmental and Architec-
methods and weather.” J. Constr. Eng. Manage., tural Engineering, University of Kansas, 2150
125, 39–46. Learned Hall, 1530 West 15th St., Rm. 2134-C,
Thomas, H. R., Smith, G. R., and Sanders, S. R. Lawrence, KS 66049. He can be reached at
(1989). “An exploratory study of productivity oswald@ku.edu.
forecasting using the factor model for masonry.”
Rep. 9005, Pennsylvania Transportation Institute,
Pennsylvania State University, University Park,
PA.
Sang-Hoon Lee is assistant professor, Depart-
Vanhoucke, M. (2006). “Work continuity constraints
Downloaded from ascelibrary.org by 54.152.109.166 on 11/05/15. Copyright ASCE. For personal use only; all rights reserved.

ment of Engineering Technology, University of


in project scheduling.” J. Constr. Eng. Manage.,
Houston, Houston, TX.
132, 14–25.
Wideman, M. (1994). “A pragmatic approach to
using resource loading, production and learning
curves on construction projects.” Can. J. Civ.
Eng., 21, 939–953. James T. O’Connor is C. T. Wells Professor,
Zayed, T. M., and Halpin, D. W. (2004). “Quantita- Department of Civil, Architectural and Environ-
tive assessment for piles productivity factors.” mental Engineering, University of Texas–Austin,
J. Constr. Eng. Manage., 130, 405–414. Austin, TX. LME

JULY 2011 266 Leadership and Management in Engineering

View publication stats Leadership Manage. Eng., 2011, 11(3): 258-266

You might also like