You are on page 1of 2

Activity ID Activity Name Start Finish Original Physical % Responsibility Nov 18 Nov 25 Dec 02 Dec 09 Dec 16 Dec 23 Dec 30

Complete S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
20-Nov-18 A 30-Dec-18 Duration
35
UTRs and TSS 06 Dismantling
General Work 20-Nov-18 A 08-Dec-18 19
DIS GEN 1000 Site visit and survey. 20-Nov-18 A 20-Nov-18 A 1 100% SIE& LCQ Site visit and survey.
DIS GEN 1010 Preparation of work permit at UTR 14,16,13,10,09 and 04. 27-Nov-18 A 27-Nov-18 A 2 100% SIE Preparation of work permit at UTR 14,16,13,10,09 and 04.
DIS GEN 1020 Preparation of work permit at TSS 06. 27-Nov-18 A 27-Nov-18 A 2 100% SIE Preparation of work permit at TSS 06.
DIS GEN 1030 Backfilling of the area for access at UTR 14. 28-Nov-18 A 28-Nov-18 A 1 100% LCQ Backfilling of the area for access at UTR 14.
DIS GEN 1040 Backfilling of the area for access at UTR 16. 27-Nov-18 A 27-Nov-18 A 2 100% LCQ Backfilling of the area for access at UTR 16.
DIS GEN 1050 Backfilling of the area for access at UTR 13. 28-Nov-18 A 01-Dec-18 A 2 100% LCQ Backfilling of the area for access at UTR 13.
DIS GEN 1060 Backfilling of the area for access at UTR 10. 03-Dec-18 04-Dec-18 2 0% LCQ Backfilling of the area for access at UTR 10.
DIS GEN 1070 Backfilling of the area for access at UTR 09. 01-Dec-18 A 01-Dec-18 A 2 100% LCQ Backfilling of the area for access at UTR 09.
DIS GEN 1080 Backfilling of the area for access at UTR 04. 05-Dec-18 06-Dec-18 2 0% LCQ Backfilling of the area for access at UTR 04.
DIS GEN 1090 Backfilling of the area for access at TSS 06. 29-Nov-18 A 08-Dec-18 2 35% LCQ Backfilling of the area for access at TSS 06.
UTRs and TSS 06 Panel dismantling 26-Nov-18 A 30-Dec-18 35
UTR 14 26-Nov-18 A 06-Dec-18 17
DIS UTR14 1000 Cleaning and house keeping at UTR 14. 26-Nov-18 A 26-Nov-18 A 1 100% LCQ Cleaning and house keeping at UTR 14.
DIS UTR14 1010 Removing of internal cable at UTR 14. 28-Nov-18 A 29-Nov-18 A 1 100% SIE Removing of internal cable at UTR 14.
DIS UTR14 1020 Installation of temporary platform at UTR 14. 01-Dec-18 A 02-Dec-18 A 2 100% LCQ Installation of temporary platform at UTR 14.
DIS UTR14 1030 Labeling and identification and dismantling panel at UTR 14. 02-Dec-18 A 03-Dec-18 A 1 100% SIE Labeling and identification and dismantling panel at UTR 14.
DIS UTR14 1040 Transportation of panel from site and unloading container. 03-Dec-18 A 03-Dec-18 A 1 100% SIE Transportation of panel from site and unloading container.
DIS UTR14 1050 Electrical equipments dismantling and transport to container. 02-Dec-18 A 04-Dec-18 3 40% LCQ Electrical equipments dismantling and transport to container.
DIS UTR14 1060 HVAC System dismantling and transport to container. 01-Dec-18 A 04-Dec-18 3 80% LCQ HVAC System dismantling and transport to container.
DIS UTR14 1070 NOVEC System dismantling and transport to container. 03-Dec-18 06-Dec-18 4 0% LCQ NOVEC System dismantling and transport to container.
UTR 13 26-Nov-18 A 09-Dec-18 19
DIS UTR16 1000 Cleaning and house keeping at UTR 13. 26-Nov-18 A 27-Nov-18 A 1 100% LCQ Cleaning and house keeping at UTR 13.
DIS UTR16 1010 Removing of internal cable at UTR 13. 28-Nov-18 A 29-Nov-18 A 1 100% SIE Removing of internal cable at UTR 13.
DIS UTR16 1020 Installation of temporary platform at UTR 13. 02-Dec-18 A 03-Dec-18 A 2 100% LCQ Installation of temporary platform at UTR 13.
DIS UTR16 1030 Labeling and identification and dismantling panel at UTR 13. 03-Dec-18 03-Dec-18 1 0% SIE Labeling and identification and dismantling panel at UTR 13.
DIS UTR16 1040 Transportation of panel from site and unloading container. 04-Dec-18 04-Dec-18 1 0% SIE Transportation of panel from site and unloading container.
DIS UTR16 1050 Electrical equipments dismantling and transport to container. 05-Dec-18 08-Dec-18 3 0% LCQ Electrical equipments dismantling and transport to container.
DIS UTR16 1060 HVAC System dismantling and transport to container. 05-Dec-18 08-Dec-18 3 0% LCQ HVAC System dismantling and transport to container.
DIS UTR16 1070 NOVEC System dismantling and transport to container. 05-Dec-18 09-Dec-18 4 0% LCQ NOVEC System dismantling and transport to container.
UTR 16 29-Nov-18 A 11-Dec-18 9
DIS UTR13 1000 Cleaning and house keeping at UTR 16. 29-Nov-18 A 29-Nov-18 A 1 100% LCQ Cleaning and house keeping at UTR 16.
DIS UTR13 1010 Removing of internal cable at UTR 16. 02-Dec-18 A 02-Dec-18 A 1 100% SIE Removing of internal cable at UTR 16.
DIS UTR13 1020 Installation of temporary platform at UTR 16. 03-Dec-18 A 04-Dec-18 2 70% LCQ Installation of temporary platform at UTR 16.
DIS UTR13 1030 Labeling and identification and dismantling panel at UTR 16. 05-Dec-18 05-Dec-18 1 0% SIE Labeling and identification and dismantling panel at UTR 16.
DIS UTR13 1040 Transportation of panel from site and unloading container. 06-Dec-18 06-Dec-18 1 0% SIE Transportation of panel from site and unloading container.
DIS UTR13 1050 Electrical equipments dismantling and transport to container. 08-Dec-18 10-Dec-18 3 0% LCQ Electrical equipments dismantling and transport to container.
DIS UTR13 1060 HVAC System dismantling and transport to container. 02-Dec-18 A 09-Dec-18 3 50% LCQ HVAC System dismantling and transport to container.
DIS UTR13 1070 NOVEC System dismantling and transport to container. 08-Dec-18 11-Dec-18 4 0% LCQ NOVEC System dismantling and transport to container.
UTR 10 03-Dec-18 15-Dec-18 11
DIS UTR10 1000 Removing of existing rise floor at UTR 10 03-Dec-18 04-Dec-18 2 0% LCQ Removing of existing rise floor at UTR 10
DIS UTR10 1010 Cleaning and house keeping at UTR 10. 04-Dec-18 04-Dec-18 1 0% LCQ Cleaning and house keeping at UTR 10.
DIS UTR10 1020 Removing of internal cable at UTR 10. 05-Dec-18 05-Dec-18 1 0% SIE Removing of internal cable at UTR 10.
DIS UTR10 1030 Installation of temporary platform at UTR 10. 06-Dec-18 08-Dec-18 2 0% LCQ Installation of temporary platform at UTR 10.
DIS UTR10 1040 Labeling and identification and dismantling panel at UTR 10. 09-Dec-18 09-Dec-18 1 0% SIE Labeling and identification and dismantling panel at UTR 10.
DIS UTR10 1050 Transportation of panel from site and unloading container. 10-Dec-18 10-Dec-18 1 0% SIE Transportation of panel from site and unloading container.
DIS UTR10 1060 Electrical equipments dismantling and transport to container. 11-Dec-18 13-Dec-18 3 0% LCQ Electrical equipments dismantling and transport to container.
DIS UTR10 1070 HVAC System dismantling and transport to container. 11-Dec-18 13-Dec-18 3 0% LCQ HVAC System dismantling and transport to container.
DIS UTR10 1080 NOVEC System dismantling and transport to container. 11-Dec-18 15-Dec-18 4 0% LCQ NOVEC System dismantling and transport to container.
UTR 09 05-Dec-18 17-Dec-18 11
DIS UTR09 1000 Removing of existing rise floor at UTR 09 05-Dec-18 06-Dec-18 2 0% LCQ Removing of existing rise floor at UTR 09
DIS UTR09 1010 Cleaning and house keeping at UTR 09. 06-Dec-18 06-Dec-18 1 0% LCQ Cleaning and house keeping at UTR 09.
DIS UTR09 1020 Removing of internal cable at UTR 09. 08-Dec-18 08-Dec-18 1 0% SIE Removing of internal cable at UTR 09.
DIS UTR09 1030 Installation of temporary platform at UTR 09. 09-Dec-18 10-Dec-18 2 0% LCQ Installation of temporary platform at UTR 09.
DIS UTR09 1040 Labeling and identification and dismantling panel at UTR 09. 11-Dec-18 11-Dec-18 1 0% SIE Labeling and identification and dismantling panel at UTR 09.
DIS UTR09 1050 Transportation of panel from site and unloading container. 12-Dec-18 12-Dec-18 1 0% SIE Transportation of panel from site and unloading container.
DIS UTR09 1060 Electrical equipments dismantling and transport to container. 13-Dec-18 16-Dec-18 3 0% LCQ Electrical equipments dismantling and transport to container.
DIS UTR09 1070 HVAC System dismantling and transport to container. 13-Dec-18 16-Dec-18 3 0% LCQ HVAC System dismantling and transport to container.
DIS UTR09 1080 NOVEC System dismantling and transport to container. 13-Dec-18 17-Dec-18 4 0% LCQ NOVEC System dismantling and transport to container.
UTR 04 08-Dec-18 20-Dec-18 11
DIS UTR04 1000 Removing of existing rise floor at UTR 04 08-Dec-18 09-Dec-18 2 0% LCQ Removing of existing rise floor at UTR 04
DIS UTR04 1010 Cleaning and house keeping at UTR 04. 09-Dec-18 09-Dec-18 1 0% LCQ Cleaning and house keeping at UTR 04.

Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
Activity ID Activity Name Start Finish Original Physical % Responsibility Nov 18 Nov 25 Dec 02 Dec 09 Dec 16 Dec 23 Dec 30
Complete S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
DIS UTR04 1020 Removing of internal cable at UTR 04. 10-Dec-18 10-Dec-18 Duration
1 0% SIE Removing of internal cable at UTR 04.
DIS UTR04 1030 Installation of temporary platform at UTR 04. 11-Dec-18 12-Dec-18 2 0% LCQ Installation of temporary platform at UTR 04.
DIS UTR04 1040 Labeling and identification and dismantling panel at UTR 04. 13-Dec-18 13-Dec-18 1 0% SIE Labeling and identification and dismantling panel at UTR 04.
DIS UTR04 1050 Transportation of panel from site and unloading container. 15-Dec-18 15-Dec-18 1 0% SIE Transportation of panel from site and unloading container.
DIS UTR04 1060 Electrical equipments dismantling and transport to container 16-Dec-18 19-Dec-18 3 0% LCQ Electrical equipments dismantling and transport to container
DIS UTR04 1070 HVAC System dismantling and transport to container. 16-Dec-18 19-Dec-18 3 0% LCQ HVAC System dismantling and transport to container.
DIS UTR04 1080 NOVEC System dismantling and transport to container. 16-Dec-18 20-Dec-18 4 0% LCQ NOVEC System dismantling and transport to container.
TSS 06 Panel dismantling 10-Dec-18 30-Dec-18 16
DIS TSS06 1000 Removing of existing rise floor at TSS 06 10-Dec-18 12-Dec-18 3 0% LCQ Removing of existing rise floor at TSS 06
DIS TSS06 1020 Cleaning and house keeping at TSS 06. 12-Dec-18 12-Dec-18 1 0% LCQ Cleaning and house keeping at TSS 06.
DIS TSS06 1030 Removing of internal cable at TSS 06. 13-Dec-18 13-Dec-18 1 0% SIE Removing of internal cable at TSS 06.
DIS TSS06 1040 Installation of temporary platform at TSS 06. 15-Dec-18 17-Dec-18 3 0% LCQ Installation of temporary platform at TSS 06.
DIS TSS06 1050 Labeling and identification and dismantling panel at TSS 06. 17-Dec-18 19-Dec-18 2 0% SIE Labeling and identification and dismantling panel at TSS 06.
DIS TSS06 1060 Transformer transportation from site and storage. 20-Dec-18 20-Dec-18 1 0% SIE Transformer transportation from site and storage.
DIS TSS06 1070 Transportation of panel from site and unloading container. 22-Dec-18 22-Dec-18 1 0% SIE Transportation of panel from site and unloading container.
DIS TSS06 1080 Electrical equipments dismantling and transport to container 23-Dec-18 30-Dec-18 6 0% LCQ Electrical equipments dismantling and transport to container
DIS TSS06 1090 HVAC System dismantling and transport to container. 23-Dec-18 30-Dec-18 6 0% LCQ HVAC System dismantling and transport to container.
DIS TSS06 1100 NOVEC System dismantling and transport to container. 23-Dec-18 30-Dec-18 6 0% LCQ NOVEC System dismantling and transport to container.

Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation