Professional Documents
Culture Documents
3/4, 2010
Wafik Hachicha*
Unit of Mechanic, Modelling and Production (U2MP),
Engineering School of Sfax,
B.P. 1173, Sfax 3038, Tunisia
and
Department of Industrial Management,
High Institute of Industrial Management of Sfax (ISGI),
B.P. 954, Sfax 3018, Tunisia
Email: wafik_hachicha@yahoo.fr
*Corresponding author
Ahmed Ammeri
Unit of Logistic, Industrial and Quality Management (LOGIQ),
High Institute of Industrial Management of Sfax,
B.P. 954, Sfax 3018, Tunisia
Email: ammariahmed@yahoo.fr
Faouzi Masmoudi
Unit of Mechanic, Modelling and Production (U2MP),
Department of Mechanical Engineering,
Engineering School of Sfax,
B. P.W, Sfax 3038, Tunisia
Fax: + 216-74-274-088
Email: faouzi.masmoudi@enis.rnu.tn
Habib Chabchoub
Unit of Logistic, Industrial and Quality Management (LOGIQ),
University of Economic Sciences and Management,
Sfax, Tunisia
Email: habib.chabchoub@fsegs.rnu.tn
constrained and stochastic parameters such as lot arrivals order, transit time,
set-up time, processing time, etc. The objective of the proposed approach is to
determine the fixed optimal lot size for each manufacturing product type that
will ensure OMFT target value for each finished product type. The study
results illustrate that the LSP in MTO sector is viable and provide a prototype
for further research on simulation optimisation approaches.
Reference to this paper should be made as follows: Hachicha, W., Ammeri, A.,
Masmoudi, F. and Chabchoub, H. (2010) ‘A multi-product lot size in make-to-
order supply chain using discrete event simulation and response surface
methodology’, Int. J. Services, Economics and Management, Vol. 2, Nos. 3/4,
pp.246–266.
1 Introduction
A Supply Chain (SC) is a network of facilities and distribution entities such as materials
vendors, manufacturers, distributors, wholesalers and retailers that performs the functions
of procurement of raw materials, transformation of raw materials into intermediate and
finished products and distribution of finished products to customers. A SC is typically
characterised by a forward flow of materials and a backward flow of information. End-
user demand information suffers from delay and distortion as it moves upstream in a SC.
248 W. Hachicha et al.
The coordination between organisations in the SC, through sharing of demand information,
is a possible solution to counter this distortion. Consequently, enterprises have shown
a growing interest for an integrated SC management. An important issue in integrated
logistic network management is to control the inventory at different entities while
meeting end-customer service level requirements, therefore quantifying the trade-off
between inventory investment and end-customer service levels. The dynamic nature of
complex logistic chains causes that this trade-off will change over time.
The coordination between different entities in the SC is not an easy task because each
one is involved in efforts to reduce costs and maximise profits. However, the various
entities may have conflicting objectives and the profits of the entire SC may suffer if the
different stakeholders cannot be brought into agreement and coordination. Traditional
production planning methods, such as Material Requirement Planning (MRP), consider
only the availability of materials when organising demands and totally ignore such
factors as capacity limits and SC configurations. For this reason, MRP cannot provide
feasible production plans since such plans require that capacity limits and multiple
objectives are taken into account. To cope with these challenges, Advance Planning and
Scheduling (APS) methods were developed to integrate the planning activities of the
entire SC, providing powerful planning procedures and methodologies that are able to
react quickly to exceptions and variability.
In addition, each entity of the SC that has the ability to fill customer orders quickly,
as well as offer custom products has the benefit of a competitive advantage. However,
the need to have high product variety and quick response time places conflicting demands
on the production system. For this reason, businesses that compete on response time
focus on producing a limited portfolio of products. Items which are produced ahead of
demand and are kept in stock are ready to be shipped upon receipt of orders. Producing to
stock becomes costly when the number of products is large. It is also risky when demand
is highly variable and/or products have short life cycles. Therefore, an increasing number
of companies have been shifting its production from the Make-to-Stock (MTS) to the
Make-to-Order (MTO) sector such as Dell, BMW, Compaq and Gateway (Gunasekaran
and Ngai, 2009). In addition, the thrust in today’s manufacturing environment is to move
towards Just-in-Time philosophy. However, most of the literature research on MRP and
APS approaches concentrates on MTS systems. As a consequence, many researchers
provide excellent surveys of models and methods for the deterministic and the stochastic
demand cases (Karimi et al., 2003). The MTO area has not received the same degree of
attention. In particular, there are only a handful of research papers that explicitly talk
about the Lot-Sizing Problem (LSP) in MTO sector. In this case, methods based only on
queueing network models have been proposed in the literature. Though, these existing
analytical models are not able to handle all the dynamically changes in SC and they
require many simplification assumptions and constraints. Some authors proposed to
apply stochastic simulation techniques to solve LSP based on queueing model equations.
In fact, this proposed technique has made analytically possible the analysis of further
complex SC although they preserved some disadvantages as mentioned of the analytical
models.
Modelling and analysing SC are not an easy task, as they contain multiple echelons
and are faced with uncertain demand and lead times. Therefore, methodologies based on
Discrete Event Simulation (DES) models are attractive when dealing with SC systems.
They allow both material and information flow to be modelled as well as sophisticated
decision logic for planning and control. DES can also deal with stochastic environments,
A multi-product lot size in make-to-order supply chain 249
2 Theoretical background
This paper presents a simulation optimisation approach to address LSPs in the MTO
supply chain sector. That is why the current theoretical background subsection is organised
as follows. First, MTO and MTS production strategy are briefly presented. Secondly,
lot-sizing models and methods are provided. Finally, DES methodology is described.
Supply chain complexity, accuracy and Solve Lot sizing approaches (dynamic
robustness of the solution… programming, queueing method,
simulation…
discrete time case the Markov process model can be used. Only a few papers exist for the
continuous time case. Most of them use a queueing theory formulation. This group of
models deals commonly with MTO production strategy.
After building the suitable lot-sizing model, there is a need to solve the obtained
LSP based on SC complexity, preferred accuracy of the final solution and others. Many
lot-sizing approaches are presented in the literature, such as dynamic programming,
heuristics, meta-heuristics, queueing network method, simulation based on queueing
models and DES. This paper deals with the MTO strategy which a Fixed-Economic-
Order-Quantity is selected.
Presently, there are some studies to advance the activities of simulation and to obtain
optimum performance. Tekin and Ihsen (2004) presented a comprehensive survey on
techniques for simulation optimisation with emphasis given to recent developments.
They classified the existing techniques according to problem characteristics such as
shape of the response surface (global as compared to local optimisation), objective
functions (single or multiple objectives) and parameter spaces (discrete or continuous
parameters). They discussed the major advantages (such as rapid convergence rate, high
search efficiency and robustness, easily applied by well-known statistics tools) and
possible drawbacks (such as local extrema, restriction of the region under investigation,
requirement of prior knowledge about the shape of the response surface) of the different
techniques
3 Literature overview
relationships to determine lot sizes that minimise costs for the single and multiple product
cases when the production rate is specified. Finally, Dong and Chen (2005) presented an
analytical modelling framework for integrated logistic chains. They developed a network
of inventory-queue models for performance analysis for three cases: base stock policy,
batch-ordering policy and for the LSP. The validity of their analytical model is illustrated
by comparing the results from DES study. However, their framework is used for single
product logistic chains and their performance analysis only. Recently, Liu and Lian
(2009) considered a two-stage distributed manufacturing system under base stock policy.
For modelling, they used a network of inventory-queue model to evaluate the inventory
cost and service level achievable for given inventory control policy. For resolution, they
derived an algorithm to find the optimal inventory control policy that minimises the
overall inventory holding cost and satisfies the given service level requirements.
Some authors allow simulation technique category (not DES techniques) for LSP
solutions. Anupindi and Tayur (1998) used a simulation technique to find good base
stock levels. They combined infinitesimal perturbation analysis with gradient search
which is considered as optimisation tool. Kämpf and Köchel (2006) proposed a
conventional queueing theory models and considered their obtained formulation as too
complex for an analytical solution. Thus, firstly they simplify and restructure their model
by few parameters. Secondly, they applied a simulation technique combined with an
optimisation tool (genetic algorithm) to determine optimal lot sizes solution. As well, the
employ of simulation technique attempt to evaluate each feasible solution. This kind of
simulation technique is different with the DES used in this paper.
The objective of this work is to develop a DES optimisation method for solving the
LSP in MTO supply chain. For this purpose, a DES model was firstly implemented as a
tool in estimating OMFT performance. Secondly, multi-objective desirability optimisation
is achieved by integrating Design of Experiment, Analysis of Variance and desirability
function.
A qualitative description or analysis of the simulation results does not provide a deep
understanding of the SC behaviour and could lead to erroneous conclusions in the
decision-making process. Experiments are natural part of the engineering and scientific
process because they help us in understanding how systems and processes work.
The validity of the decisions taken after an experiment depends strongly on how the
experiment was conducted and how the results were analysed. For these reasons, as
mentioned in Figure 3, the proposed approach suggests to use simulation technique
jointly with the Response Surface Methodology (RSM) and the multi-objective desirability
optimisation. Simulation models are flexible and solve real problems without making too
many restricting assumptions as in most analytical models. The major benefit of using
RSM in post-simulation analysis is the significant reduction in the number of simulation
runs needed (Myers and Montgomery, 1995). The use of RSM allows some
generalisations to be made about the output of the simulation.
A multi-product lot size in make-to-order supply chain 255
2 CCDs are very efficient, providing much information on experiment variable effects
and overall experimental error in a minimum number of required runs.
3 CCDs are very flexible. The availability of several varieties of CCDs enables their
use under different experimental regions of interest and operability.
The broad aims of RSM are to investigate the nature of the response surface over a
region of interest and to identify operating conditions associated with maximum or
minimum responses. Several authors have discussed the underlying philosophy and use
of RSM (e.g. Mead and Pike, 1975; Myers et al., 1989; Hood and Welch, 1993; Box and
Liu, 1999; Del Castillo et al., 1999; Myers and Montgomery, 2002; Yang and Tseng,
2002). The methodology involves the use of a variety of statistical techniques, including
experimental design and linear regression, to efficiently discover the unknown relationship
between the factors and the response or to estimate the levels of the treatments (factors)
that optimise the mean system response.
RSM is generally conducted in two phases, as emphasised by Myers and Montgomery
(2002). Phase 1 is concerned with the location of optimum operating conditions by
conducting a sequence of suitable experiments and Phase 2 involves the fitting of an
appropriate empirical model, usually a second-order polynomial model, in order to
examine the nature of the response surface in the vicinity of the optimum.
⎪d = ⎜ y − A ⎟ If A ≤ y∧ ≤ B
⎪ i ⎜ B−A ⎟
⎪ ⎝ ⎠
⎪⎪ ∧
⎨d i = 1 If y B (1)
⎪ ∧
⎪d i = 0 If y ≺ A
⎪
⎪
⎪⎩
desirability functions are then combined into a single composite response, the so-called
global desirability function D, defined as the geometric mean of the different di -values as
indicated in equation (2).
1
⎛ n ⎞n
D = ⎜ ∏ d ipi ⎟ (2)
⎝ i =1 ⎠
A value of D different from zero implies that all responses are in a desirable range
simultaneously and, consequently, for a value of D close to 1, the combination of the
different criteria is globally optimum, so the response values are near the target values.
In equation (2), pi is the relative importance assigned to the response i. The relative
importance pi is a comparative scale for weighting each of the resulting di in the overall
desirability product and it varies from the least important (pi = 1) to the most important
(pi = 5). It is noteworthy that the outcome of the overall desirability D depends on the pi
value that offers users flexibility in the definition of desirability functions.
The SC configuration investigated in this research is shown in Figure 4. Firstly, Enns and
Suwanruji (2005) provided the same case study in MTS sector. Their problem has been
revised and considerably modified to take into consideration MTO environment.
For specificity, this research makes the following assumptions concerning the
simulation parameters. For all part types, it was assumed that the required lot size order
quantity was not available from the upstream supplier before shipments could be released
(i.e. lot splitting is allowed).
Furthermore, for assembly operations it was assumed that the required lot-size
quantities of all components were not also available before any components were
released for shipment. A common transit time was then applied to all components so
arrival at the assembly location was simultaneous. The transit times are shown along side
the arrows in Figure 4. Moreover, when there are a capacity constraints, lots arriving at
manufacturing locations must undergo a set-up time and a lot processing time. Mean
set-up and part processing times for processed and assembled parts are displayed in
Table 1.
The lot set-up times are stochastic and follow a normal distribution with a coefficient of
variation of 0.3. The lot processing times are deterministic and based on multiplying the
lot size times the fixed part processing time. Processing of all lots in queue is based on
FCFS. Transit times, also shown in Table 1, are defined as the time to move an available
lot of inventory from an upstream location to a downstream location. The transit times
for all part types were assumed to be stochastic and follow a gamma distribution with a
coefficient of variation of 0.1. No capacity constraints were assumed for inventory
transportation.
Furthermore, customer’s order which consists of fixed lot size of same product type
follows a gamma distribution with a mean of 4000 units per week. One week is assumed
to be equal to five working days. Times are given in hours, using the assumption there
are 40 hours per week (or 8 hours per day. Daily order variation is determined on
the basis of having a week order coefficient of variation of 0.1. Based on customer
requirements and specifications, lot sizes for product types P1, P2 and P3 are compulsory
fixed at 200 units, 200 units and 300 units, respectively.
260 W. Hachicha et al.
Location 1 Location 4
Create P2 order Assign P2 attributes Dispose P2 order
Location 2 Location 5
Once a simulation model of SC system has been built and verified, it can be used for
analysing the SC performance according to factorial experimental design.
equation (2). The composite desirability for all these three variables is 1.0. To obtain this
desirability, we would set the factor levels at the values shown under global solution in
the Figure 8. That is, Lot size of P4 would be set at 562 units. Lot size of P5 would be set
at 77.5 units, Lot size of P6 would be set at 274 units, Lot size of P7 would be set at
212.5 units and Lot size of P8 would be set at 675 units.
Figure 7 Main effect plots and interaction plots for OMFT: case of product P1
(see online version for colours)
Main Effects Plot (data means) for p1
p8 p7 p6
68
66
64
62
Mean of p1
60
0,5 1,0 1,5 2,0 2,5 0,5 1,0 1,5 2,0 2,5 0,5 1,0 1,5 2,0 2,5
p5 p4
68
66
64
62
60
0,5 1,0 1,5 2,0 2,5 0,5 1,0 1,5 2,0 2,5
64 1, 0
1, 5
p7 2, 0
60 2, 5
68
p6
0, 5
64 1, 0
1, 5
p6 2, 0
60 2, 5
68
p5
0, 5
64 1, 0
1, 5
p5 2, 0
60 2, 5
68
p4
0, 5
64 1, 0
1, 5
p4 2, 0
60 2, 5
0,5 1,0 1,5 2,0 2,5 0,5 1,0 1,5 2,0 2,5 0,5 1,0 1,5 2,0 2,5
Table 3
Manufacturing part lot levels MFT for each Finished parts (hr) Manufacturing part lot levels MFT for each Finished parts (hr)
Exp. P4 P5 P6 P7 P8 P1 P2 P3 Exp. P4 P5 P6 P7 P8 P1 P2 P3
1 1 1 2 2 1 60.49 64.96 55.06 27 1 1 1 2 2 63.14 63.33 54.84
2 1 1 2 1 1 61.89 63.99 55.15 28 1.5 0.31 1.5 1.5 1.5 63.29 65.04 56.48
3 1 1 1 1 1 60.72 65.65 55.96 29 2 1 1 2 1 60.48 64.92 58.22
4 1.5 1.5 1.5 0.31 1.5 62.38 64.80 63.08 30 2 2 2 1 1 60.70 64.68 58.66
5 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55 31 1 2 2 2 1 60.03 64.20 55.21
6 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55 32 1.5 1.5 0.31 1.5 1.5 62.40 66.33 59.17
7 1 2 2 1 2 60.23 66.29 55.77 33 2 2 2 2 1 61.50 65.24 55.19
8 2 1 1 1 1 60.75 64.83 59.08 34 1 2 1 1 2 61.38 65.66 54.89
9 1 2 2 1 1 60.23 66.29 55.77 35 2 2 1 1 1 61.57 65.42 59.44
10 1 1 1 2 1 63.14 63.33 54.84 36 1 1 2 1 2 61.89 63.99 55.15
The 25 response surface design
11 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55 37 1 2 1 2 2 60.30 65.25 55.25
12 1 2 1 1 1 61.38 65.66 54.89 38 1 1 2 2 2 60.49 64.96 55.06
13 2 1 2 1 1 60.35 64.34 56.18 39 1.5 1.5 1.5 1.5 0.31 60.98 63.34 56.55
14 2 1 1 1 2 60.75 64.83 59.08 40 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55
15 2.7 1.5 1.5 1.5 1.5 59.37 64.77 61.06 41 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55
16 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55 42 1.5 1.5 2.7 1.5 1.5 60.51 66.01 57.35
17 1 2 1 2 1 59.67 64.01 58.08 43 1.5 2.7 1.5 1.5 1.5 61.85 61.42 56.40
18 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55 44 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55
19 2 2 1 2 1 59.67 64.01 58.08 45 2 1 2 2 2 60.22 64.16 57.23
A multi-product lot size in make-to-order supply chain
20 2 2 1 2 2 59.67 64.01 58.08 46 1.5 1.5 1.5 2.7 1.5 59.69 64.63 56.66
21 2 2 2 1 2 60.70 64.68 58.66 47 2 1 2 1 2 60.35 64.34 56.18
22 1 2 2 2 2 60.03 64.20 55.21 48 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55
23 2 2 1 1 2 61.57 65.42 59.44 49 1.5 1.5 1.5 1.5 1.5 60.98 63.34 56.55
24 0.31 1.5 1.5 1.5 1.5 63.54 72.14 56.24 50 2 1 1 2 2 60.48 64.92 58.22
25 2 2 2 2 2 61.50 65.24 55.19 51 1.5 1.5 1.5 1.5 2.7 60.98 63.34 56.55
26 2 1 2 2 1 60.22 64.16 57.23 52 1 1 1 1 2 60.72 65.65 55.96
263
264 W. Hachicha et al.
7 Conclusion
This paper presents a new approach for the LSP in MTO supply chain. The proposed
approach is based on combining discrete event simulation and response surface
methodology for a multi-objective desirability optimisation. The supply chain under
study which operates in MTO environment (no possibility for stock keeping and limited
production capacity) is characterised by multi-product, multi-stage, multi-location
production planning with capacity-constrained and stochastic parameters such as lot
arrivals order, transit time, set-up time, processing time, etc.
The proposed approach is a logical and methodical to solve LSP, which makes it
easily portable into practice. For that reason, design of experiment, analyse of variance
and desirability optimisation tool are available in many commercial software packages
including Minitab, Statistica and others.
Our perspective should give more extensive testing on different problems to support
the proposed approach application in supply chain management. Details and others real
benefits of the application of the metamodel-based simulation optimisation approach into
real-life case study will be presented at our subsequent publications.
A multi-product lot size in make-to-order supply chain 265
References
Anupindi, R. and Tayur, S. (1998) ‘Managing stochastic multi-product systems: model measures,
and analysis’, Operations Research, Vol. 46, pp.98–111.
Bertrand, J.W.M. (1985) ‘Multi product optimal batch sizes with in-process inventories and multi
work centers’, IIE Transactions, Vol. 17, No. 2, pp.157–163.
Box, G.E.P. and Liu, P.Y.T. (1999) ‘Statistics as a catalyst to learning by scientific method
part I – an example’, Journal of Quality Technology, Vol. 31, No. 1, pp.1–15.
Chan, F.T.S. and Chan, H.K. (2005) ‘Simulation modeling for comparative evaluation of supply
chain management strategies’, International Journal of Advanced Manufacturing and
Technology, Vol. 25, pp.998–1006.
Choi, S. and Enns, S.T. (2004) ‘Multi-product capacity-constrained lot sizing with economic
objectives’, International Journal of Production Economics, Vol. 91, pp.47–62.
Dellaert, N.P. and Melo, M.T. (1996) ’Production strategies for a stochastic lot-sizing problem with
constant capacity’, European Journal of Operational Research, Vol. 92, pp.281–301.
Derringer, G.C. and Suich, R. (1980) ‘Simultaneous optimization of several response variables’,
Journal of Quality Technology, Vol. 12, pp.214–219.
Del Castillo, E., Fan, S.K. and Semple, J. (1999) ‘Optimization of dual response systems:
a comprehensive procedure for degenerate and no degenerate problems’, European Journal of
Operational Research, Vol. 112, No. 1, pp.174–186.
Dong, M. and Chen, F.F. (2005) ‘Performance modeling and analysis of integrated logistic chains:
an analytic framework’, European Journal of Operational Research, Vol. 162, pp.83–98.
Enns, S.T. and Suwanruji, P. (2005) ‘Lot-sizing within capacity constrained manufacturing
systems using time-phased planning’, Proceedings of the 2005 Winter Simulation Conference,
pp.1433–1440.
Ettl, M., Feigin, G.E., Lin, G.Y. and Yao, D.D. (2000) ‘A supply network model with base-stock
control and service requirements’, Operations Research, Vol. 48, pp.216–232.
Gunasekaran, A. and Ngai, E.W.T. (2009) ‘Modeling and analysis of build-to-order supply chains’,
European Journal of Operational Research, Vol. 195, No. 2, pp.319–334.
Graves, S.C., Rinnooy Kan, A.H.G. and Zipkin, P.H. (1993) Logistics of Production and Inventory,
Handbooks in Operations Research and Management Science, Elsevier Science, Holland.
Harrington, J. (1965) ‘The desirability function’, Industrial Quality Control, Vol. 21, pp.494–498.
Ho, C. (1993) ‘Evaluating lot-sizing performance in multilevel MRP systems: a comparative
analysis of multiple performance measures’, International Journal of Operations and
Production Management, Vol. 13, No. 11, pp.52–79.
Hood, S.J. and Welch, P.D. (1993) ‘Response surface methodology and its application in
simulation’, in Evans, G.W., Mollaghasemi, M., Rusell, E.C. and Biles, W.E. (Eds):
Proceedings of the 1993 Winter Simulation Conference, pp.115–122.
Jammernegg, W. and Reiner, G. (2007) ‘Performance improvement of supply chain processes
by coordinated inventory and capacity management’, International Journal of Production
Economics, Vol. 108, pp.183–190.
Karimi, B., Ghomi, S.M.F.T. and Wilson, J.M. (2003) ‘The capacitated lot sizing problem:
a review of models and algorithms’, Omega, Vol. 31, pp.365–378.
Kämpf, M. and Köchel, P. (2006) ‘Simulation-based sequencing and lot size optimization for a
production-and-inventory system with multiple items’, International Journal of Production
Economics, Vol. 104, pp.191–200.
Law, A.M. and Kelton, W.D. (2000) Simulation Modeling and Analysis, McGraw Hill, New York.
Lee, Y.H., Cho, M.K., Kim, S.J. and Kim, Y.B. (2002) ‘Supply chain simulation with discrete
continuous combined modeling’, Computer and Industrial Engineering, Vol. 43, pp.375–392.
266 W. Hachicha et al.
Lee, C.Y., Cetinkaya, S. and Jaruphongsa, W. (2003) ‘A dynamic model for inventory lot-sizing
and outbound shipment scheduling at a third-party warehouse’, Operations Research, Vol. 51,
No. 5, pp.735–747.
Li, J., González, M. and Zhu, Y. (2009) ‘A hybrid simulation optimization method for production
planning of dedicated remanufacturing’, International Journal of Production Economics,
Vol. 117, No. 2, pp.286–301.
Liu, X. and Lian, Z. (2009) ‘Cost-effective inventory control in a value-added manufacturing
system’, European Journal of Operational Research, Vol. 196, pp.534–543.
Longo, F. and Mirabelli, G. (2008) ‘An advanced supply chain management tool based on
modeling and simulation’, Computers and Industrial Engineering, Vol. 54, pp.570–588.
Mead, R. and Pike, D.J. (1975) ‘A review of response surface methodology from a biometric
viewpoint’, International Biometric Society, Vol. 31, pp.803–851.
Missbauer, H. (2002) ‘Lot sizing in workload control systems’, Production Planning and Control,
Vol. 13, No. 7, pp.649–664.
Montgomery, D.C. (2005) Design and Analysis of Experiments, 6th ed., Wiley & Sons, Inc.,
pp.160–335.
Myers, R.H. and Montgomery, D.C. (2002) Response Surface Methodology: Process and Product
Optimization Using Designed Experiments, 2nd ed., Wiley, New York.
Myers, R.H., Khuri, A.I. and Carter Jr., W.H. (1989) ‘Response surface methodology:1966–1988’,
Technometrics, Vol. 31, No. 2, pp.137–157.
Persson, F. and Olhager, J. (2002) ‘Performance simulation of supply chain designs’, International
Journal of Production Economics, Vol. 77, pp.231–245.
Reiner, G. (2005) ‘Customer-oriented improvement and evaluation of supply chain processes
supported by simulation models’, International Journal of Production Economics, Vol. 96,
pp.381–395.
Srinivasa Raghavan, N.R. (2001) ‘Generalized queuing network analysis of integrated supply
chains’, International Journal of Production Research, Vol. 39, No. 2, pp.205–224.
Tekin, E. and Ihsan, S. (2004) ‘Simulation optimization: a comprehensive review on theory and
applications’, IIE Transactions, Vol. 36, pp.1067–1081.
Tsai, C.S. (2002) ‘Evaluation and optimization of integrated manufacturing system operations
using Taguch’s experiment design in computer simulation’, Computers and Industrial
Engineering, Vol. 43, pp.591–604.
Wang, Q. and Ingham, N. (2008) ‘A discrete event modeling approach for supply chain
simulation’, International Journal of Simulation Modeling, Vol. 7, No. 3, pp.124–134.
Williams, T.M. (1984) ‘Special products and uncertainty in production/inventory systems’,
European Journal of Operational Research, Vol. 15, pp.46–54.
Woon, K.N., Piplani, R. and Viswanathan, S. (2003) ‘Simulation workbench for analyzing
multi-echelon supply chains’, Integrated Manufacturing Systems, Vol. 14, No. 5, pp.449–457.
Yang, T. and Tseng, L. (2002) ‘Solving a multi-objective simulation model using a hybrid response
surface method and a lexicographical goal programming approach-a case study on
integrated circuit ink-marking machines’, European Journal of Operational Research,
Vol. 53, pp.211–221.