CONSTRUCTION SCHEDULE

45 CALENDAR DAYS
CATEGORY MAY JUNE
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
General Requirements

Site works - Land development Site preparation & layouting

Site works - Structural Demolition & stripping

Masonry concete louver blocks

Metals structural steel & accessories

Wood & Plastics repair of roof trusses

Weather, Thermal & Moisture Waiting for approval - roof Roof tiles installation suspended due to bad
Protection tiles weather

Doors & Windows doors

Finishes restoration of existing finishes,


plaster, ceiling/soffit finishes, painting
Electrical

LEGEND: SUSPENDED
ON-GOING
NO WORK
FINISHED