Professional Documents
Culture Documents
AT NTPC-DADRI ON 10/11/2016
PREAMBLE:
Observations:
Status of Units and Lines of NTPC-Dadri at around 10:45 hrs on 10/11 /2016
Unit U#1 U#2 U#3 U#4 U#5 U#6 GT#1 GT#2 STG HVDC Station
Pole#1
1. Maharanibagh: 370 MW
2. Malerkotla: 198 MW
3. Greater Noida: 645 MW
4. Panipat-1: 210 MW
5. Panipat-2: 206 MW
6. Mandaula-1: 83 MW
7. Mandaula-2: 87 MW
8. Muradnagar: 111 MW
Page 1 of 3
Description of Events:
HVDC Pole#1 is connected to 400 kV Bus#12 & HVDC Pole#2 is connected to 400 kV
Bus#1.
Switchyard Shift Operator was instructed to open the HVDC Pole#2 Bus isolator, to issue
permit to PGCIL. The Operator inadvertently operated the HVDC Pole#1 Bus isolator,
from local, bypassing all interlocks (circuit breaker ON) at Isolator MB. With partial
opening of all three phases of the isolator, heavy arcing started across the isolator
contacts. The Operator ran away from the site and Bus-bar protection of Bus#2 along-
with check zone operated due to Earth fault created because of Isolator arcing at
10:49:42:138 hrs. All breakers connected to Bus#2 tripped. Bus#1 was healthy till that
time, bus after 551 msec, Bus-bar protection of Bus#1 also operated, tripping all breakers
connected to Bus#1, thus making Bus dead.
Unit#5 & 6 tripped due to tripping of their 400 kV Breakers due to Bus-bar protection
operation of both Buses.
Dadri Gas GT#1, 2 & STG tripped on loss of evacuation, due to tripping of ICT#3 & 4.
Other evacuation option available for DGPS is through 220 kV Dari-Railway line#1 was
under shutdown & 220 kV Dadri Line#2 was carrying approx. 20 MW. Hence, due to
mismatch of Generation & load all running units of Dadri Gas tripped on over-frequency
protection, setting at 51.5 Hz.
Dadri Unit#3 tripped due to loss of evacuation from 400 kV side, as there is no
evacuation line on 220 kV voltage level at Dadri.
Safe shutdown of Unit#3, Unit#5 & Unit#6 units took place. All DC drives, DG sets & DC
lights of Stage-1 Units came in to service on auto. DG switchgear charged with closing
and synchronizing of DG breakers. Emergency switchgears of all Stage#1 units
charged from DG switchgear.
Page 2 of 3
Recommendations:
Page 3 of 3