FOOTING SCHEDULE (M20:Fe500)

FOOTING DIMENSION FOOTING REINFORCEMENT


FOOTING COLUMN FOOTING
BOTTOM
NUMBERS NUMBERS TYPE STEP L B D1 D2
ALONG B ALONG L
FC7 C7 Pad - 4'-0" 6'-0" 15" - T10@6" C/C T10@6" C/C
FC8 C8 Pad - 5'-0" 6'-0" 16" - T10@6" C/C T10@6" C/C
FC9 C9 Pad - 4'-0" 6'-0" 15" - T10@6" C/C T10@6" C/C
FC4 C4 Pad - 5'-0" 6'-0" 18" - T10@6" C/C T10@6" C/C
FC5 C5 Pad - 6'-0" 7'-0" 21" - T10@5" C/C T10@5" C/C
FC6 C6 Pad - 5'-0" 6'-0" 18" - T10@6" C/C T10@6" C/C
FC1 C1 Pad - 4'-0" 6'-0" 15" - T10@6" C/C T10@6" C/C
FC2 C2 Pad - 5'-0" 6'-0" 16" - T10@6" C/C T10@6" C/C
FC3 C3 Pad - 4'-0" 6'-0" 15" - T10@6" C/C T10@6" C/C