A: ESTABLISH PARAMETERS
A0: 3D / PLANS / SECTIONS / SOA
A1: PURPOSE GROUP
A2: CATEGORY OF TOP MOST FLOOR
A3: ACTIVE PROVISIONS (SCHEDULE 10)
B: SITE PLANNING REQUIREMENT
B1: BL 140 (ACCESS ROAD)
B2: BL 225 (EXTERNAL HYDRANT)
C: PASSIVE FIRE FIGHTING
C1: BL 136 (COMPARTMENTATION)
C2: STAIRCASE WIDTH AND NUMBER
C3: TRAVEL DISTANCE
C4: DISTRIBUTION & POSITIONING OF STAIRCASE
C5: SCHEDULE 9 : FRP (FIRE DOORS)
C6: SCHEDULE 8 : CLASS OF MATERIAL
D: ACTIVE FIRE FIGHTING
D1: HOSEREEL
D2: AUTOMATIC FIRE DETECTOR SYSTEM
D3: GENERATORS
D4: SMOKE SPILL SYSTEM

E: SUMMARY OF REQUIREMENT
E1: SUMMARY OF REQUIREMENT
Hydrant
Bomba Legend
CLEAN GAS CONTROL PANEL
CLEAN GAS NOZZLE
CLEAN GAS TANK
CO2/ 2KG CARBON DIOXIDE PORTABLE FIRE EXTINGUISHER
DP/6KG CARBON DIOXIDE PORTABLE FIRE EXTINGUISHER

FOAM PORTABLE FIRE EXTINGUISHER


LOW EXPANSION FOAM TANK AND NOZZLES
HOSE REEL
FIXED INTERNAL HYDRANT SYSTEM

EXHAUST FAN
‘KELUAR’ SIGN LIGHT FITTING c/w nickel cadmium battery for 3 hrs duration

ALARM BELL

BREAKGLASS

HEAT DETECTOR
SMOKE DETECTOR
A0: 3D 
FIRE SAFETY AND PROTECTION
PROPOSED 5 STOREY LIBRARY, UiTM SHAH ALAM

PERSPECTIVE (3D) 

ARK850 – DESIGN THESIS II
NAME
UiTM ID NUMBER
A0: SECTIONS

SECTIONS (showing zoning of purpose group)

ARK850 – DESIGN THESIS II
NAME
UiTM ID NUMBER
A0: PLANS

ALL PLANS (showing zoning of purpose group)

ARK850 – DESIGN THESIS II
NAME
UiTM ID NUMBER
A1: PURPOSE GROUP

1. Please omit the radius (the circles)
2. The colour at fifth schedule must tally 
with the zoning colour on plan
3.     Do   legend for the zoning colour.
A2: CATEGORY OF TOP MOST FLOOR

1. Indicate top most floor in section
2. Indicate “Designated Floor” in section 
(Level of escape / safety)
3.     Indicate in SOA
A2: CATEGORY OF TOP MOST FLOOR

BELOW 18.3 M (5 st & below)
1. External hydrants
2. HR
3. Fire escape staircase
4. Compartmentation

ABOVE 18.3 M & BELOW 30.5 M (5‐8 st)
1. External hydrants
2. HR
3. Internal hydrants and rising main (Dry Riser)
4. Fire escape staircase
5. Compartmentation
6. Fire fighting access lobby
7. Fire fighting staircase
8. Fire lift & Firemen’s switch
9. Designated floor

1. List the requirement for your category (either top most floor below 18.3m OR top most floor above 
18.3m & below 30.5m)
A3: ACTIVE PROVISION (SCHEDULE 10)

1. For different PG stack on top of each other vertically
2.     For design with different PG at different block
B1 : BL 140 BOMBA APPLIANCE ACCESS

Fire Appliances Access By Law 140

Road/Access width – minimum 6m (Maximum


width of appliance is 2.5m) & can withstand
load of fire engines (Maximum weight – 26
tonnes)

Maximum gradient to access is 1:12.

estimated building volume : 45856 cu m

Hydrant Location
•not less than 2m from adjacent buildings and
overhangs
•between 0.61m to 2.4m from Fire Appliance
Access
•away from risks of vehicular damage
•not more than 91.5m apart from each other (in
new building; provide if there is no hydrant in
45m radius)
B2 : BL 225 EXTERNAL HYDRANT

1. Please colour the access road yellow
2. Show distance of road following the road distance. 
Not direct measurement.
3. Please number the hydrant (H1, H2, H3, etc). 
H1 should be at the main entrance to the site near to the building.
C1 : BL 136 COMPARTMENTATION

1. Show schedule 5 and highlight your selection of PG and 
add remark as in the summary above.
2. Show all plans showing your compartmentation zone for the different purpose group
3. If your floor area exceed the maximum area, then compartment the floor.
C2 : STAIRCASE WIDTH AND NUMBER OF STAIRCASE

1. Identify your largest suspended 
floor on plan and section and at 
SOA (highlight in red)
C2 : STAIRCASE WIDTH AND NUMBER OF STAIRCASE

1. Show schedule VII (Capacity Exits) and highlingt your 
capacity exits required.
2. Perform your staircase calculation
C3 : TRAVEL DISTANCE

1. Show Schedule VII table and highlight your travel 
distance required.
C4 : DISTRIBUTION AND POSITIONING OF STAIRCASE

1. Colour your escape staircase (Red)
2. Show the travel distance from one staircase to the other
D1 : HOSEREEL

1. Show your SOA and highlight your total GFA
2. Perform hosereel calculation
3. Locate HR position on plan at a coverage of 30m radius.
4. Draw the travel line of HR following the escape route 
(Not circle because HR cannot travel over wall)
D2 : AUTOMATIC FIRE DETECTOR SYSTEM

1. Show on plan where you locate your control room to monitor the FAS panel
D3 : GENERATOR SET

1. Indicate where you locate your Generator set room on plan.
2.     Ensure you have a service road to service the generator set room
D4 : SMOKE SPILL SYSTEM

1. Show your smoke system on section and on plan
E1 : SUMMARY OF REQUIREMENT

Please list down (complie) all the requirement based on the sequence of A1 to E1.
Elaborate the details of your requirement based on the sequence above.
E1 : SUMMARY OF REQUIREMENT
E1 : SUMMARY OF REQUIREMENT
E1 : SUMMARY OF REQUIREMENT
E1 : SUMMARY OF REQUIREMENT
E1 : SUMMARY OF REQUIREMENT

Please omit the sprinkler lines because you don’t have sprinkler to your project
E1 : SUMMARY OF REQUIREMENT

Please omit the sprinkler lines because you don’t have sprinkler to your project
E1 : SUMMARY OF REQUIREMENT

Please omit the sprinkler lines because you don’t have sprinkler to your project