RATE
WITH
SITE CLEARING PROFIT
EXCAVATION
EARTH FILLING
Add. tools
3 % of Labour cost Rs. 7.50
257.50
Add.
Overheads & Profit 25.75
Labour
Add tools
3 % of Labour cost Rs. 18.75
Rs. 643.75
Add
Overheads & Profit Rs. 64.38
Cost for one sqr. with overheads and profit Rs. 708.13
Labour
Cost for one cube with overheads and profit Rs. 991.38
Labour
Add. tools
3 % of Labour cost Rs. 30.00
1,030.00
Add.
Overheads & Profit Rs. 103.00
Cost for one cube with overheads and profit Rs. 1,133.00
A. 05 Excavate trench for wall foundation in ordinary soil and
part return fill in ram, and depoisting
surplus excavated material within site as directed.
( exceeding 5' 0" but not exceeding 10' 0" deep ) 1 cube,
Labour
Add. tools
3 % of Labour cost Rs. 37.50
1,287.50
Add.
Overheads & Profit Rs. 128.75
Cost for one cube with overheads and profit Rs. 1,416.25
Labour
Add. tools
3 % of Labour cost Rs. 33.75
1,158.75
Add.
Overheads & Profit Rs. 115.88
Cost for one cube with overheads and profit Rs. 1,274.63
A. 07 Excavate pit for column foundation in any material except rock
requiring blasting, part return fill in ram, and depoisting
surplus excavated material within site as directed.
( exceeding 5' 0" but not exceeding 10' 0" deep ) 1 cube
Labour
Add. tools
3 % of Labour cost Rs. 41.25
1,416.25
Add.
Overheads & Profit Rs. 141.63
Cost for one cube with overheads and profit Rs. 1,557.88
Labour
Transporting earth
Add. tools
3 % of Labour cost Rs. 37.50
1,537.50
Add.
Overheads & Profit Rs. 153.75
Cost for one cube with overheads and profit Rs. 1,691.25
Labour
Add. tools
3 % of Labour cost Rs. 22.50
772.50
Add.
Overheads & Profit Rs. 77.25
Cost for one cube with overheads and profit Rs. 849.75
A. 10 Filling under floors with gravel or other approved quality
of filling, spread, watered and well rammed in 3" thick
layers. ( earth not available at site ) 1 cube.
Materials
Labour
Add. tools
3% of Labour cost Rs. 22.50
1,515.00
Add.
Overheads & Profit Rs. 151.50
Cost for one cube with overheads and profit Rs. 1,666.50
Materials
Labour
1.5 day Un skilled labour at. Rs. 500.00 Rs. 750.00
Add. tools
3% of Labour cost Rs. 22.50
1,515.00
Add.
Overheads & Profit Rs. 151.50
Cost for one cube with overheads and profit Rs. 1,666.50
Note
Consider trench 12' 0" long 3' 0" wide and 5' 0" deep
open planking to both side. ( Class 11 timber )
Materials
Rs. 9,055.00
3 % Westege Rs. 271.65
cost for 4 uses Rs. 9,326.65
Rs. 3,272.95
Note
Consider trench 10' 0" long 3' 0" wide and 5' 0" deep
close planking to both side. ( class 11 timber )
Materials
Labour
Add
tools
3% of labour cost Rs. 39.38
Rs. 5,555.63
Note
Consider trench 10' 0" long 4' 0" wide and 10' 0" deep
close planking to both side.
Materials
Labour
tools
Rs. 11,644.15
Rs. 12,808.57
Cost for one sqr. with overheads and profit Rs. 6,404.28
( close planking )