You are on page 1of 15

A.

EXCAVATION AND EARTHWORK

Rate for Excavation and Earthwork shall include for :

a. Trimming sides, keeping clean and consolidating bottom of base


and trenches etc. leveling consolidating where required under slabs
or sub floor layers.

b. Back filling with selected excavated materials or with borrowed


materials and disposl of surplus excavated materials from site as
specified and directed.

c. Any necessary additional excavation for working space.

BASIC MATERIALS PRICES

Skilled Labour Rs. 750.00 per day


Un Skilled Labour Rs. 500.00 per day

Dry hard earth Rs. 550.00 per cube

1 1/2" thick plank Rs. 120.00 s. ft.


( class 11 )

2" x 4" joist Rs. 40.00 L. ft.


( class 11 )

2" x 6" joist Rs. 65.00 L. ft.


( class 11 )

Wire nails Rs. 110.00 kg.

Tractor Rs. 1,500.00 per day


Overheads & Profit 10.00 %

A EXCAVATION AND EARTHWORK

RATE
WITH
SITE CLEARING PROFIT

A. 01 Clearing site and grubbing up all small trees


not exceeding 500mm girth and including bushes,
scrubs,undergrowth hedges etc. sqr. Rs. 283.25

EXCAVATION

A. 02 Excavation of top soil of average depth of 6" and carting


away surplus soil. sqr. Rs. 708.13

A. 03 Drains, earth, in any soil except rock requiring


blasting cut to gradient and shape as directed
and depositing soil within site. cube. Rs. 991.38

A. 04 Excavate trench for wall foundation in ordinary soil and


part return fill in ram with and including depoisting
surplus excavated material within site as directed.
( not exceeding 5' 0" deep ) cube, Rs. 1,133.00

A. 05 Excavate trench for wall foundation in ordinary soil and


part return fill in ram with and including depoisting
surplus excavated material within site as directed.
( exceeding 5' 0" but not exceeding 10' 0" deep ) cube, Rs. 1,416.25

A. 06 Excavatne pit for column foundation in any material except rock


requiring blasting, part return fill in ram with and including
depoisting surplus excavated material within site as directed.
( not exceeding 5' 0" deep ) cube, Rs. 1,274.63

A. 07 Excavate pit for column foundation in any material except rock


requiring blasting, part return fill in ram with and including
depoisting surplus excavated material within site as directed.
( exceeding 5' 0" but not exceeding 10' 0" deep ) cube, Rs. 1,557.88

A. 08 Excavation in levlling site in any material except rock


requiring blasting, including transporting up to 1/4 mile
depositing and levelling. cube, Rs. 1,691.25

EARTH FILLING

A. 09 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( earth available at site ) cube. Rs. 849.75

A. 10 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( earth not available at site ) cube. Rs. 1,666.50

A. 11 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( within Colombo Municipal limits ) cube. Rs. 1,666.50

EARTH WORK SUPPORT

A. 12 Earth work support in trenches up to 5' 0" deep


( oping planking ) sqr. Rs. 2,727.46

A. 13 Earth work support in trenches up to 5' 0" deep


( close planking ) sqr. Rs. 6,111.19

A. 14 Earth work support in trenches up to 10' 0" deep


( close planking ) sqr. Rs. 6,404.28
A. 01 Clearing site and grubbing up all small trees
not exceeding 500mm girth and including bushes,
scrubs,undergrowth hedges etc. 1 sqr

0.50 day Un skilled labour at. Rs. 500.00 Rs. 250.00

Add. tools
3 % of Labour cost Rs. 7.50
257.50
Add.
Overheads & Profit 25.75

Cost for one sqr. with overheads and profit 283.25


A. 02 Excavation of top soil of average depth of 6" and carting
away surplus soil. 1 sqr.

Labour

1.25 day Un skilled labour at. Rs. 500.00 Rs. 625.00

Add tools
3 % of Labour cost Rs. 18.75
Rs. 643.75
Add
Overheads & Profit Rs. 64.38

Cost for one sqr. with overheads and profit Rs. 708.13

A. 03 Drains, earth, in any soil except rock requiring


blasting cut to gradient and shape as directed
and depositing soil within site. 1 cube.

Labour

1.75 days Un skilled labour at. Rs. 500.00 Rs. 875.00


Add. tools
3 % of Labour cost Rs. 26.25
Rs. 901.25
Add.
Overheads & Profit Rs. 90.13

Cost for one cube with overheads and profit Rs. 991.38

A. 04 Excavate trench for wall foundation in ordinary soil and


part return fill in ram, and depoisting
surplus excavated material within site as directed.
( not exceeding 5' 0" deep ) 1 cube,

Labour

2.00 days Un skilled labour at. Rs. 500.00 Rs. 1,000.00

Add. tools
3 % of Labour cost Rs. 30.00
1,030.00
Add.
Overheads & Profit Rs. 103.00

Cost for one cube with overheads and profit Rs. 1,133.00
A. 05 Excavate trench for wall foundation in ordinary soil and
part return fill in ram, and depoisting
surplus excavated material within site as directed.
( exceeding 5' 0" but not exceeding 10' 0" deep ) 1 cube,

Labour

2 1/2 days Un skilled labour at. Rs. 500.00 Rs. 1,250.00

Add. tools
3 % of Labour cost Rs. 37.50
1,287.50
Add.
Overheads & Profit Rs. 128.75

Cost for one cube with overheads and profit Rs. 1,416.25

A. 06 Excavate pit for column foundation in any material except rock


requiring blasting, part return fill in ram, and depoisting
surplus excavated material within site as directed.
( not exceeding 5' 0" deep ) 1 cube

Labour

2.25 day Un skilled labour at. Rs. 500.00 Rs. 1,125.00

Add. tools
3 % of Labour cost Rs. 33.75
1,158.75
Add.
Overheads & Profit Rs. 115.88

Cost for one cube with overheads and profit Rs. 1,274.63
A. 07 Excavate pit for column foundation in any material except rock
requiring blasting, part return fill in ram, and depoisting
surplus excavated material within site as directed.
( exceeding 5' 0" but not exceeding 10' 0" deep ) 1 cube

Labour

2.75 day Un skilled labour at. Rs. 500.00 Rs. 1,375.00

Add. tools
3 % of Labour cost Rs. 41.25
1,416.25
Add.
Overheads & Profit Rs. 141.63

Cost for one cube with overheads and profit Rs. 1,557.88

A. 08 Cutting and levlling site in any material except rock


requiring blasting, including transporting up to 1/4 mile
depositing and levelling. 1 cube,

Labour

Cutting and loading earth to tractor


2 1/2 days Un skilled labour at. Rs. 500.00 Rs. 1,250.00

Transporting earth

1/6 day tractor at. Rs. 1,500.00 Rs. 250.00

Add. tools
3 % of Labour cost Rs. 37.50
1,537.50
Add.
Overheads & Profit Rs. 153.75

Cost for one cube with overheads and profit Rs. 1,691.25

A. 09 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( earth available at site ) 1 cube.

Labour

1.5 day Un skilled labour at. Rs. 500.00 Rs. 750.00

Add. tools
3 % of Labour cost Rs. 22.50
772.50
Add.
Overheads & Profit Rs. 77.25

Cost for one cube with overheads and profit Rs. 849.75
A. 10 Filling under floors with gravel or other approved quality
of filling, spread, watered and well rammed in 3" thick
layers. ( earth not available at site ) 1 cube.

Materials

1.35 cube Earth with


transport cost at. Rs. 550.00 Rs. 742.50

Labour

1.5 day Un skilled labour at. Rs. 500.00 Rs. 750.00

Add. tools
3% of Labour cost Rs. 22.50
1,515.00
Add.
Overheads & Profit Rs. 151.50

Cost for one cube with overheads and profit Rs. 1,666.50

A. 11 Filling under floors with gravel or other approved quality


of filling, spread, watered and well rammed in 3" thick
layers. ( within Colombo Municipal limits ) 1 cube.

Materials

1.35 cube Earth with


transport cost at. Rs. 550.00 Rs. 742.50

Labour
1.5 day Un skilled labour at. Rs. 500.00 Rs. 750.00

Add. tools
3% of Labour cost Rs. 22.50
1,515.00
Add.
Overheads & Profit Rs. 151.50

Cost for one cube with overheads and profit Rs. 1,666.50

A. 12 Earth work support in trenches up to 5' 0" deep


( open planking ) 1.20 sqr.

Note
Consider trench 12' 0" long 3' 0" wide and 5' 0" deep
open planking to both side. ( Class 11 timber )

Materials

40.00 s. ft. 1 1/2" thick planks at Rs. 120.00 Rs. 4,800.00

40.00 l. ft. 2" x 6" joist at Rs. 65.00 Rs. 2,600.00

40.00 l. ft. 2" x 4" joist at Rs. 40.00 Rs. 1,600.00

0.50 kg. wire nails at Rs. 110.00 Rs. 55.00

Rs. 9,055.00
3 % Westege Rs. 271.65
cost for 4 uses Rs. 9,326.65

for single use 2,331.66


Rs. 2,331.66
Labour

0.50 Skilled labour at Rs. 750.00 Rs. 375.00

0.50 Un skilled labour at Rs. 500.00 Rs. 250.00


Rs. 625.00
tools
3% of labour cost Rs. 18.75
Rs. 2,975.41
Overheads & Profit Rs. 297.54

Rs. 3,272.95

Cost for one sqr. with overheads and profit


( open planking ) Rs. 2,727.46
A. 13 Earth work support in trenches up to 5' 0" deep
( close planking ) 1 sqr.

Note
Consider trench 10' 0" long 3' 0" wide and 5' 0" deep
close planking to both side. ( class 11 timber )

Materials

110.00 s. ft. 11/2" thick planks at Rs. 120.00 Rs. 13,200.00

40.00 ft, 2" x 6" joist at Rs. 65.00 Rs. 2,600.00

24.00 ft, 2" x 4" joist at Rs. 40.00 Rs. 960.00

0.5 kg. wire nails at Rs. 110.00 Rs. 55.00

Cost for 4 uses Rs. 16,815.00

For single use Rs. 4,203.75

Labour

0.75 day Skilled labour at Rs. 750.00 Rs. 562.50

0.75 day 2 Un skilled labour at Rs. 500.00 Rs. 750.00


Rs. 1,312.50

Add
tools
3% of labour cost Rs. 39.38

Rs. 5,555.63

Overheads & Profit Rs. 555.56


Cost for one sqr. with overheads and profit
( close planking ) Rs. 6,111.19

A. 14 Earth work support in trenches up to 10' 0" deep


( close planking ) 2 sqr.

Note
Consider trench 10' 0" long 4' 0" wide and 10' 0" deep
close planking to both side.

Materials

220.00 s. ft. 11/2" thick planks at Rs. 120.00 Rs. ###

6.00 12' 0" long joist


no 2" x 6" at Rs. 780.00 Rs. 4,680.00

12.00 4' 0" long props


no 2" x 4" at Rs. 160.00 Rs. 1,920.00

2.00 kg. Wire nails at Rs. 110.00 220.00


Rs. ###

Westege 3% Rs. 996.60


Cost for 4 uses Rs. 34,216.60

For single use Rs. 8,554.15

Labour

1 day 2.00 Skilled labour at Rs. 750.00 Rs. 1,500.00

1 day 3.00 Un skilled labour at Rs. 500.00 Rs. 1,500.00


Rs. 3,000.00

tools

3% of labour cost Rs. 90.00

Rs. 11,644.15

Overheads & Profit Rs. 1,164.42

Rs. 12,808.57

Cost for one sqr. with overheads and profit Rs. 6,404.28