RENCANA ANGGARAN BIAYA

PEMBANGUNAN SARANA OLAH RAGA


KELURAHAN PADURAKSA
KECAMATAN PEMALANG KABUPATEN PEMALANG

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp)

PEKERJAAN LAPANGAN
1 Urugan Tanah 7.46 m3 Rp 82,100
2 Plesteran 59.40 m2 Rp 63,500
3 Urugan Peninggian 41.48 m3 Rp 81,400
Jumlah Total Pekerjaan Lapangan Volly
PEKERJAAN TALUD
1 Urugan Pasir 1.43 m3 Rp 134,706
1 Pasangan Batu Kali 4.68 m3 Rp 801,944
Jumlah Total Pekerjaan Talud
PEKERJAAN TAMBAHAN
<> Pagar
1 Galian Tanah 45.12 m3 Rp 38,775
2 Anstamping 5.64 m3 Rp 410,465
3 Urugan Pasir 1.692 m3 Rp 134,706
4 Pasangan Batu Kali 24.53 m3 Rp 801,944
5 Pasangan Batu Bata 172.91 m2 Rp 114,461
6 Urugan Tanah Kembali 15.04 m3 Rp 9,350
7 Plesteran Tembok 345.82 m2 Rp 49,543
8 Acian 345.82 m2 Rp 21,717
9 Pemasangan Rel Pintu Geser 4 bh Rp 266,728
a. Kusen Aluminium Pintu 1 6.12 m Rp 123,364
b. Kusen Aluminium Pintu 2 10.20 m Rp 123,364
10 Daun Pintu Harga
a. Sliding Door Besi 8.94 m2 Rp 305,000
11 Sloof 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
12 Kolom 2.81 m3 Rp 825,358
Besi 12 ( tulangan utama ) 445.00 kg Rp 11,293
Besi 8 ( begel ) 162.50 kg Rp 11,293
13 Ringbalk 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
14 Urugan Peninggian 2.69 m3 Rp 235,500
15 Cat Tembok 345.82 m2 Rp 16,588

<> WC dan Kamar Ganti


1 Galian Tanah 8.8125 m3 Rp 38,775
2 Urugan Pasir 0.47 m3 Rp 134,706
3 Anstamping 1.175 m3 Rp 410,465
4 Pasangan Batu Kali 4.7 m3 Rp 801,944
5 Urugan Tanah Kembali 3.134 m3 Rp 9,350
6 Pasangan Batu Bata 49.10 m2 Rp 114,461
7 Plesteran Tembok 98.19 m2 Rp 49,543
8 Acian 98.19 m2 Rp 21,717
9 Cat Tembok 98.19 m2 Rp 16,588
10 Kusen 0.16 m3 Rp 11,588,088
11 Daun Pintu 4.68 m2 Rp 629,860
12 Sloof 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
13 Kolom 0.693 m3 Rp 825,358
Besi 12 ( tulangan utama ) 109.65 kg Rp 11,293
Besi 8 ( begel ) 40.04 kg Rp 11,293
14 Ringbalk 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
15 Urugan Peninggian 1.17 m3 Rp 81,400
16 Urugan Pasir 0.78 m3 Rp 134,706
17 Keramik
a) Keramik 30x30cm 7.29 m2 Rp 160,176
b) Keramik 50x50cm 7.90 m2 Rp 191,224
18 Atap Dak 2.85 m3 Rp 825,358
Besi 12 ( tulangan utama ) 182.90 kg Rp 11,293
Besi 10 76.94 kg Rp 11,293
19 Pekerjaan Instalasi Listrik Harga
Box listrik 2 group 1 bh Rp 210,000
Saklar In Bauw seri 8 bh Rp 12,500
Saklar In Bauw engkel 2 bh Rp 11,000
Stop Kontak 4 bh Rp 14,700
Kabel 2x2x1/2 mm2 NYY PRIMA 31 m Rp 14,000
Kabel 2x4 mm2 NYY PRIMA 20 m Rp 25,000
Kap 8 bh Rp 7,300
Steker 2 bh Rp 7,600
20 Pekerjaan Sanitasi
Septick tank 15.54 m2 Rp 122,073
Dudukan Closet 4.32 m2 Rp 122,073
Dudukan Sanyo 0.72 m2 Rp 122,073
Pipa PVC DN 20(1/2") AW JIS 19 m Rp 14,513
Pipa PVC DN 63(2") 24 m Rp 30,129
Pipa PVC DN 90(3") 11.5 m Rp 53,390
Kran Air 4 bh Rp 27,434
Harga
Sanyo Shimizu 100watt 1 bh Rp 233,600
Closet Jongkok 2 bh Rp 324,000
Harga
Seal Tape 3 bh Rp 3,600
Floor Drain 4 bh Rp 18,100

Lain-lain
Pekerjaan Pemasangan Jaring Harga
1 Jaring-Jaring 148 m2 Rp 14,010
Rangka Jaring-jaring 36 m Rp 13,000

Pekerjaan Tribun
2 Kerangka Tribun 331.50 m Rp 19,500

Jumlah Total Pekerjaan Tambahan


Jumlah Total Pekerjaan Sarana Olah Raga
Jumlah Total Pekerjaan Talud
Pajak PPN (10%)
Pajak PPH (3%)
Jumblah Total Pekerjaan Fisik Bangunan
Perencanaan
Pelaksanaan
Pengawasan
Jumlah Total Pekerjaan

Terbilang
Dua Ratus Tujuh Juta Empat Belas Ribu Rupiah
DISAHKAN OLEH
KEPALA UPPU WILAYAH VI
DPU KABUPATEN PEMALANG

JAJURI,ST
NIP. 19610828 198809 1 001
DIKETAHUI
PPKOM

TITIK WIDYASTUTI,S.Sos.,M.Si
NIP. 19741028 199303 2 002
CANA ANGGARAN BIAYA
GUNAN SARANA OLAH RAGA
LURAHAN PADURAKSA
EMALANG KABUPATEN PEMALANG

JUMLAH HARGA (Rp)

Rp 612,056
Rp 3,771,900
Rp 3,376,472
Rp 7,760,428

Rp 191,956
Rp 3,753,098
Rp 3,945,054

Rp 1,749,528
Rp 2,315,020
Rp 227,923
Rp 19,674,894
Rp 19,791,136
Rp 140,624
Rp 17,132,864
Rp 7,510,000
Rp 1,066,912
Rp 754,987
Rp 1,258,312

Rp 2,725,480
Rp 2,793,013
Rp 4,534,747
Rp 1,954,017
Rp 2,321,321
Rp 5,025,207
Rp 1,835,048
Rp 2,793,013
Rp 4,534,747
Rp 1,954,017
Rp 633,495
Rp 5,736,244

Rp 341,705
Rp 63,312
Rp 482,296
Rp 3,769,137
Rp 29,303
Rp 5,619,576
Rp 4,864,775
Rp 2,132,420
Rp 1,628,772
Rp 1,823,038
Rp 2,947,745
Rp 581,878
Rp 944,739
Rp 407,087
Rp 571,973
Rp 1,238,211
Rp 452,172
Rp 581,878
Rp 944,739
Rp 407,087
Rp 95,604
Rp 105,020

Rp 1,167,680
Rp 1,510,192
Rp 2,349,795
Rp 2,065,360
Rp 868,875
Rp 210,000
Rp 100,000
Rp 22,000
Rp 58,800
Rp 434,000
Rp 500,000
Rp 58,400
Rp 15,200

Rp 1,897,015
Rp 527,356
Rp 87,893
Rp 275,752
Rp 723,105
Rp 613,984
Rp 109,736

Rp 233,600
Rp 648,000

Rp 10,800
Rp 72,400

Rp 2,073,480
Rp 468,013

Rp 6,464,250

Rp 162,060,698
Rp 7,760,428
Rp 3,945,054
Rp 20,701,400
Rp 6,210,420
Rp 200,678,000
Rp 1,584,000
Rp 3,168,000
Rp 1,584,000
Rp 207,014,000

Terbilang
Tujuh Juta Empat Belas Ribu Rupiah
POKMAS SEMANGAT

ANDI RUSTONO
RENCANA PENGGUNAAN DANA ( RPD ) 100 %
PEMBANGUNAN SARANA OLAH RAGA
KELURAHAN PADURAKSA
KECAMATAN PEMALANG KABUPATEN PEMALANG

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp)

PEKERJAAN LAPANGAN
1 Urugan Tanah 7.46 m3 Rp 82,100
2 Plesteran 59.40 m2 Rp 63,500
3 Urugan Peninggian 41.48 m3 Rp 81,400
Jumlah Total Pekerjaan Lapangan Volly
PEKERJAAN TALUD
1 Urugan Pasir 1.43 m3 Rp 134,706
1 Pasangan Batu Kali 4.68 m3 Rp 801,944
Jumlah Total Pekerjaan Talud
PEKERJAAN TAMBAHAN
<> Pagar
1 Galian Tanah 45.12 m3 Rp 38,775
2 Anstamping 5.64 m3 Rp 410,465
3 Urugan Pasir 1.692 m3 Rp 134,706
4 Pasangan Batu Kali 24.53 m3 Rp 801,944
5 Pasangan Batu Bata 172.91 m2 Rp 114,461
6 Urugan Tanah Kembali 15.04 m3 Rp 9,350
7 Plesteran Tembok 345.82 m2 Rp 49,543
8 Acian 345.82 m2 Rp 21,717
9 Pemasangan Rel Pintu Geser 4 bh Rp 266,728
a. Kusen Aluminium Pintu 1 6.12 m Rp 123,364
b. Kusen Aluminium Pintu 2 10.20 m Rp 123,364
10 Daun Pintu Harga
a. Sliding Door Besi 8.94 m2 Rp 305,000
11 Sloof 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
12 Kolom 2.81 m3 Rp 825,358
Besi 12 ( tulangan utama ) 445.00 kg Rp 11,293
Besi 8 ( begel ) 162.50 kg Rp 11,293
13 Ringbalk 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
14 Urugan Peninggian 2.69 m3 Rp 235,500
15 Cat Tembok 345.82 m2 Rp 16,588

<> WC dan Kamar Ganti


1 Galian Tanah 8.8125 m3 Rp 38,775
2 Urugan Pasir 0.47 m3 Rp 134,706
3 Anstamping 1.175 m3 Rp 410,465
4 Pasangan Batu Kali 4.7 m3 Rp 801,944
5 Urugan Tanah Kembali 3.134 m3 Rp 9,350
6 Pasangan Batu Bata 49.10 m2 Rp 114,461
7 Plesteran Tembok 98.19 m2 Rp 49,543
8 Acian 98.19 m2 Rp 21,717
9 Cat Tembok 98.19 m2 Rp 16,588
10 Kusen 0.16 m3 Rp 11,588,088
11 Daun Pintu 4.68 m2 Rp 629,860
12 Sloof 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
13 Kolom 0.693 m3 Rp 825,358
Besi 12 ( tulangan utama ) 109.65 kg Rp 11,293
Besi 8 ( begel ) 40.04 kg Rp 11,293
14 Ringbalk 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
15 Urugan Peninggian 1.17 m3 Rp 81,400
16 Urugan Pasir 0.78 m3 Rp 134,706
17 Keramik
a) Keramik 30x30cm 7.29 m2 Rp 160,176
b) Keramik 50x50cm 7.90 m2 Rp 191,224
18 Atap Dak 2.85 m3 Rp 825,358
Besi 12 ( tulangan utama ) 182.90 kg Rp 11,293
Besi 10 76.94 kg Rp 11,293
19 Pekerjaan Instalasi Listrik Harga
Box listrik 2 group 1 bh Rp 210,000
Saklar In Bauw seri 8 bh Rp 12,500
Saklar In Bauw engkel 2 bh Rp 11,000
Stop Kontak 4 bh Rp 14,700
Kabel 2x2x1/2 mm2 NYY PRIMA 31 m Rp 14,000
Kabel 2x4 mm2 NYY PRIMA 20 m Rp 25,000
Kap 8 bh Rp 7,300
Steker 2 bh Rp 7,600
20 Pekerjaan Sanitasi
Septick tank 15.54 m2 Rp 122,073
Dudukan Closet 4.32 m2 Rp 122,073
Dudukan Sanyo 0.72 m2 Rp 122,073
Pipa PVC DN 20(1/2") AW JIS 19 m Rp 14,513
Pipa PVC DN 63(2") 24 m Rp 30,129
Pipa PVC DN 90(3") 11.5 m Rp 53,390
Kran Air 4 bh Rp 27,434
Harga
Sanyo Shimizu 100watt 1 bh Rp 233,600
Closet Jongkok 2 bh Rp 324,000
Harga
Seal Tape 3 bh Rp 3,600
Floor Drain 4 bh Rp 18,100

Lain-lain
Pekerjaan Pemasangan Jaring Harga
1 Jaring-Jaring 148 m2 Rp 14,010
Rangka Jaring-jaring 36 m Rp 13,000

Pekerjaan Tribun
2 Kerangka Tribun 331.50 m Rp 19,500

3 Pajak PPN (10%) Rp 20,701,400


4 Pajak PPH (3%) Rp 6,210,420
5 Biaya Perencanaan Rp 1,584,000
6 Biaya Pelaksanaan Rp 3,168,000
7 Biaya Pengawasan Rp 1,584,000

JUMBLAH TOTAL PENGGUNAAN RPD 100 %

Terbilang
Dua Ratus Tujuh Juta Empat Belas Ribu Rupiah

DISAHKAN OLEH
KEPALA UPPU WILAYAH VI
DPU KABUPATEN PEMALANG

JAJURI,ST
NIP. 19610828 198809 1 001
DIKETAHUI
PPKOM

TITIK WIDYASTUTI,S.Sos.,M.Si
NIP. 19741028 199303 2 002
ENGGUNAAN DANA ( RPD ) 100 %
GUNAN SARANA OLAH RAGA
LURAHAN PADURAKSA
EMALANG KABUPATEN PEMALANG

JUMLAH HARGA (Rp)

Rp 612,056
Rp 3,771,900
Rp 3,376,472

Rp 191,956
Rp 3,753,098

Rp 1,749,528
Rp 2,315,020
Rp 227,923
Rp 19,674,894
Rp 19,791,136
Rp 140,624
Rp 17,132,864
Rp 7,510,000
Rp 1,066,912
Rp 754,987
Rp 1,258,312

Rp 2,725,480
Rp 2,793,013
Rp 4,534,747
Rp 1,954,017
Rp 2,321,321
Rp 5,025,207
Rp 1,835,048
Rp 2,793,013
Rp 4,534,747
Rp 1,954,017
Rp 633,495
Rp 5,736,244

Rp 341,705
Rp 63,312
Rp 482,296
Rp 3,769,137
Rp 29,303
Rp 5,619,576
Rp 4,864,775
Rp 2,132,420
Rp 1,628,772
Rp 1,823,038
Rp 2,947,745
Rp 581,878
Rp 944,739
Rp 407,087
Rp 571,973
Rp 1,238,211
Rp 452,172
Rp 581,878
Rp 944,739
Rp 407,087
Rp 95,604
Rp 105,020

Rp 1,167,680
Rp 1,510,192
Rp 2,349,795
Rp 2,065,360
Rp 868,875
Rp 210,000
Rp 100,000
Rp 22,000
Rp 58,800
Rp 434,000
Rp 500,000
Rp 58,400
Rp 15,200

Rp 1,897,015
Rp 527,356
Rp 87,893
Rp 275,752
Rp 723,105
Rp 613,984
Rp 109,736

Rp 233,600
Rp 648,000

Rp 10,800
Rp 72,400

Rp 2,073,480
Rp 468,013

Rp 6,464,250

Rp 20,701,400
Rp 6,210,420
Rp 1,584,000
Rp 3,168,000
Rp 1,584,000

Rp 207,014,000

Terbilang
Tujuh Juta Empat Belas Ribu Rupiah

POKMAS SEMANGAT
ANDI RUSTONO
RENCANA PENGGUNAAN DANA ( RPD ) TAHAP I 40 %
PEMBANGUNAN SARANA OLAH RAGA
KELURAHAN PADURAKSA
KECAMATAN PEMALANG KABUPATEN PEMALANG

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp)

PEKERJAAN LAPANGAN
1 Urugan Tanah 7.46 m3 Rp 82,100
2 Plesteran 59.40 m2 Rp 63,500
3 Urugan Peninggian 41.48 m3 Rp 81,400
Jumlah Total Pekerjaan Lapangan Volly
PEKERJAAN TALUD
1 Urugan Pasir 1.43 m3 Rp 134,706
1 Pasangan Batu Kali 4.68 m3 Rp 801,944
Jumlah Total Pekerjaan Talud
PEKERJAAN TAMBAHAN
<> Pagar
1 Galian Tanah 45.12 m3 Rp 38,775
2 Anstamping 5.64 m3 Rp 410,465
3 Urugan Pasir 1.692 m3 Rp 134,706
4 Pasangan Batu Kali 24.53 m3 Rp 801,944
5 Pasangan Batu Bata 172.91 m2 Rp 114,461
6 Urugan Tanah Kembali 15.04 m3 Rp 9,350
7 Plesteran Tembok 345.82 m2 Rp 49,543
8 Acian 345.82 m2 Rp 21,717
9 Pemasangan Rel Pintu Geser 4 bh Rp 266,728
a. Kusen Aluminium Pintu 1 6.12 m Rp 123,364
b. Kusen Aluminium Pintu 2 10.20 m Rp 123,364
10 Daun Pintu Harga
a. Sliding Door Besi 8.94 m2 Rp 305,000
11 Sloof 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
12 Kolom 2.81 m3 Rp 825,358
Besi 12 ( tulangan utama ) 445.00 kg Rp 11,293
Besi 8 ( begel ) 162.50 kg Rp 11,293
13 Ringbalk 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
14 Urugan Peninggian 2.69 m3 Rp 235,500
15 Cat Tembok 345.82 m2 Rp 16,588

<> WC dan Kamar Ganti


1 Galian Tanah 8.8125 m3 Rp 38,775
2 Urugan Pasir 0.47 m3 Rp 134,706
3 Anstamping 1.175 m3 Rp 410,465
4 Pasangan Batu Kali 4.7 m3 Rp 801,944
5 Urugan Tanah Kembali 3.134 m3 Rp 9,350
6 Pasangan Batu Bata 49.10 m2 Rp 114,461
7 Plesteran Tembok 98.19 m2 Rp 49,543
8 Acian 98.19 m2 Rp 21,717
9 Cat Tembok 98.19 m2 Rp 16,588
10 Kusen 0.16 m3 Rp 11,588,088
11 Daun Pintu 4.68 m2 Rp 629,860
12 Sloof 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
13 Kolom 0.693 m3 Rp 825,358
Besi 12 ( tulangan utama ) 109.65 kg Rp 11,293
Besi 8 ( begel ) 40.04 kg Rp 11,293
14 Ringbalk 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
15 Urugan Peninggian 1.17 m3 Rp 81,400
16 Urugan Pasir 0.78 m3 Rp 134,706
17 Keramik
a) Keramik 30x30cm 7.29 m2 Rp 160,176
b) Keramik 50x50cm 7.90 m2 Rp 191,224
18 Atap Dak 2.85 m3 Rp 825,358
Besi 12 ( tulangan utama ) 182.90 kg Rp 11,293
Besi 10 76.94 kg Rp 11,293
19 Pekerjaan Instalasi Listrik Harga
Box listrik 2 group 1 bh Rp 210,000
Saklar In Bauw seri 8 bh Rp 12,500
Saklar In Bauw engkel 2 bh Rp 11,000
Stop Kontak 4 bh Rp 14,700
Kabel 2x2x1/2 mm2 NYY PRIMA 31 m Rp 14,000
Kabel 2x4 mm2 NYY PRIMA 20 m Rp 25,000
Kap 8 bh Rp 7,300
Steker 2 bh Rp 7,600
20 Pekerjaan Sanitasi
Septick tank 15.54 m2 Rp 122,073
Dudukan Closet 4.32 m2 Rp 122,073
Dudukan Sanyo 0.72 m2 Rp 122,073
Pipa PVC DN 20(1/2") AW JIS 19 m Rp 14,513
Pipa PVC DN 63(2") 24 m Rp 30,129
Pipa PVC DN 90(3") 11.5 m Rp 53,390
Kran Air 4 bh Rp 27,434
Harga
Sanyo Shimizu 100watt 1 bh Rp 233,600
Closet Jongkok 2 bh Rp 324,000
Harga
Seal Tape 3 bh Rp 3,600
Floor Drain 4 bh Rp 18,100

Lain-lain
Pekerjaan Pemasangan Jaring Harga
1 Jaring-Jaring 148 m2 Rp 14,010
Rangka Jaring-jaring 36 m Rp 13,000

Pekerjaan Tribun
2 Kerangka Tribun 331.50 m Rp 19,500

3 Pajak PPN (10%) Rp 20,701,400


4 Pajak PPH (3%) Rp 6,210,420
5 Perencanaan Rp 1,584,000
6 Pelaksanaan Rp 3,168,000
7 Pengawasan Rp 1,584,000
1
JUMBLAH TOTAL PENGGUNAAN RPD 40 %

Terbilang
Delapan Puluh Dua Juta Tujuh Ratus Enam Puluh Tujuh Ribu Tiga Ratus Empat Belas Rupiah
DISAHKAN OLEH
KEPALA UPPU WILAYAH VI
DPU KABUPATEN PEMALANG

JAJURI,ST
NIP. 19610828 198809 1 001
DIKETAHUI
PPKOM

TITIK WIDYASTUTI,S.Sos.,M.Si
NIP. 19741028 199303 2 002
GUNAAN DANA ( RPD ) TAHAP I 40 %
GUNAN SARANA OLAH RAGA
LURAHAN PADURAKSA
EMALANG KABUPATEN PEMALANG

JUMLAH HARGA (Rp)

-
-
-

-
-

Rp 1,749,528
Rp 2,315,020
Rp 227,923
Rp 19,674,894
-
Rp 140,624
-
-
-
-
-

Rp 2,725,480
Rp 2,793,013
Rp 4,534,747
Rp 1,954,017
Rp 2,321,321
Rp 5,025,207
Rp 1,835,048
Rp 2,793,013
Rp 4,534,747
Rp 1,954,017
Rp 633,495
Rp 5,736,244

Rp 341,705
Rp 63,312
Rp 482,296
Rp 3,769,137
-
-
-
-
-
-
-
Rp 581,878
Rp 944,739
Rp 407,087
-
-
-
-
-
-
Rp 95,604
Rp 105,020

-
-
-
-
-
-
-
-
-
Rp 434,000
-
Rp 58,400
Rp 15,200

-
Rp 527,356
-
-
Rp 723,105
Rp 613,984
Rp 109,736

-
-

-
-

-
-

-
Rp 6,210,420
Rp 1,584,000
Rp 3,168,000
Rp 1,584,000

Rp 82,767,314

Terbilang
us Enam Puluh Tujuh Ribu Tiga Ratus Empat Belas Rupiah
POKMAS SEMANGAT

ANDI RUSTONO
RENCANA PENGGUNAAN DANA ( RPD ) TAHAP I 40
PEMBANGUNAN SARANA OLAH RAGA
KELURAHAN PADURAKSA
KECAMATAN PEMALANG KABUPATEN PEMALANG

SATUAN VOLUME
NO URAIAN
Total Dari APBD Dari Swadaya
(1} (2) (3} (4) (5} (6)
PEKERJAAN LAPANGAN
1 Urugan Tanah m3 7.46
2 Plesteran m2 59.40
3 Urugan Peninggian m3 41.48
Jumlah Total Pekerjaan Lapangan Volly
PEKERJAAN TALUD
1 Urugan Pasir m3 1.43
1 Pasangan Batu Kali m3 4.68
Jumlah Total Pekerjaan Talud
PEKERJAAN TAMBAHAN
<> Pagar
1 Galian Tanah m3 45.12
2 Anstamping m3 5.64
3 Urugan Pasir m3 1.692
4 Pasangan Batu Kali m3 24.53
5 Pasangan Batu Bata m2 172.91
6 Urugan Tanah Kembali m3 15.04
7 Plesteran Tembok m2 345.82
8 Acian m2 345.82
9 Pemasangan Rel Pintu Geser bh 4
a. Kusen Aluminium Pintu 1 m 6.12
b. Kusen Aluminium Pintu 2 m 10.20
10 Daun Pintu
a. Sliding Door Besi m2 8.94
11 Sloof m3 3.38
Besi 12 ( tulangan utama ) kg 401.57
Besi 8 ( begel ) kg 173.04
12 Kolom m3 2.81
Besi 12 ( tulangan utama ) kg 445.00
Besi 8 ( begel ) kg 162.50
13 Ringbalk m3 3.38
Besi 12 ( tulangan utama ) kg 401.57
Besi 8 ( begel ) kg 173.04
14 Urugan Peninggian m3 2.69
15 Cat Tembok m2 345.82

<> WC dan Kamar Ganti


1 Galian Tanah m3 8.8125
2 Urugan Pasir m3 0.47
3 Anstamping m3 1.175
4 Pasangan Batu Kali m3 4.7
5 Urugan Tanah Kembali m3 3.134
6 Pasangan Batu Bata m2 49.10
7 Plesteran Tembok m2 98.19
8 Acian m2 98.19
9 Cat Tembok m2 98.19
10 Kusen m3 0.16
11 Daun Pintu m2 4.68
12 Sloof m3 0.71
Besi 12 ( tulangan utama ) kg 83.66
Besi 8 ( begel ) kg 36.05
13 Kolom m3 0.693
Besi 12 ( tulangan utama ) kg 109.65
Besi 8 ( begel ) kg 40.04
14 Ringbalk m3 0.71
Besi 12 ( tulangan utama ) kg 83.66
Besi 8 ( begel ) kg 36.05
15 Urugan Peninggian m3 1.17
16 Urugan Pasir m3 0.78
17 Keramik
a) Keramik 30x30cm m2 7.29
b) Keramik 50x50cm m2 7.90
18 Atap Dak m3 2.85
Besi 12 ( tulangan utama ) kg 182.90
Besi 10 kg 76.94
19 Pekerjaan Instalasi Listrik
Box listrik 2 group bh 1
Saklar In Bauw seri bh 8
Saklar In Bauw engkel bh 2
Stop Kontak bh 4
Kabel 2x2x1/2 mm2 NYY PRIMA m 31
Kabel 2x4 mm2 NYY PRIMA m 20
Kap bh 8
Steker bh 2
20 Pekerjaan Sanitasi
Septick tank m2 15.54
Dudukan Closet m2 4.32
Dudukan Sanyo m2 0.72
Pipa PVC DN 20(1/2") AW JIS m 19
Pipa PVC DN 63(2") m 24
Pipa PVC DN 90(3") m 11.5
Kran Air bh 4

Sanyo Shimizu 100watt bh 1


Closet Jongkok bh 2

Seal Tape bh 3
Floor Drain bh 4

Lain-lain
Pekerjaan Pemasangan Jaring
1 Jaring-Jaring m2 148
Rangka Jaring-jaring m 36

Pekerjaan Tribun
2 Kerangka Tribun m 331.50

3 Pajak PPN (10%)


4 Pajak PPH (3%)
5 Perencanaan
6 Pelaksanaan
7 Pengawasan
1
JUMBLAH TOTAL PENGG

Terbilang
Delapan Puluh Dua Juta Tujuh Ratus Enam Puluh Tujuh Ribu Tiga Ratus Em
DISAHKAN OLEH
KEPALA UPPU WILAYAH VI
DPU KABUPATEN PEMALANG

JAJURI,ST
NIP. 19610828 198809 1 001
DIKETAHUI
PPKOM

TITIK WIDYASTUTI,S.Sos.,M.Si
NIP. 19741028 199303 2 002
GUNAAN DANA ( RPD ) TAHAP I 40 %
GUNAN SARANA OLAH RAGA
LURAHAN PADURAKSA
EMALANG KABUPATEN PEMALANG

VOLUME JUMLAH BIAYA (Rp)


HARGA SATUAN
Dari Sumber (Rp)
Dari Swadaya Dari APBD
Lain
(7} (8) (9) = (6) X (8) (9) = (5) X (8)

Rp 82,100 -
Rp 63,500 -
Rp 81,400 -
an Lapangan Volly

Rp 134,706 -
Rp 801,944 -
kerjaan Talud

Rp 38,775 Rp 1,749,528
Rp 410,465 Rp 2,315,020
Rp 134,706 Rp 227,923
Rp 801,944 Rp 19,674,894
Rp 114,461 -
Rp 9,350 Rp 140,624
Rp 49,543 -
Rp 21,717 -
Rp 266,728 -
Rp 123,364 -
Rp 123,364 -
Harga
Rp 305,000 Rp 2,725,480
Rp 825,358 Rp 2,793,013
Rp 11,293 Rp 4,534,747
Rp 11,293 Rp 1,954,017
Rp 825,358 Rp 2,321,321
Rp 11,293 Rp 5,025,207
Rp 11,293 Rp 1,835,048
Rp 825,358 Rp 2,793,013
Rp 11,293 Rp 4,534,747
Rp 11,293 Rp 1,954,017
Rp 235,500 Rp 633,495
Rp 16,588 Rp 5,736,244

Rp 38,775 Rp 341,705
Rp 134,706 Rp 63,312
Rp 410,465 Rp 482,296
Rp 801,944 Rp 3,769,137
Rp 9,350 -
Rp 114,461 -
Rp 49,543 -
Rp 21,717 -
Rp 16,588 -
Rp 11,588,088 -
Rp 629,860 -
Rp 825,358 Rp 581,878
Rp 11,293 Rp 944,739
Rp 11,293 Rp 407,087
Rp 825,358 -
Rp 11,293 -
Rp 11,293 -
Rp 825,358 -
Rp 11,293 -
Rp 11,293 -
Rp 81,400 Rp 95,604
Rp 134,706 Rp 105,020

Rp 160,176 -
Rp 191,224 -
Rp 825,358 -
Rp 11,293 -
Rp 11,293 -
Harga
Rp 210,000 -
Rp 12,500 -
Rp 11,000 -
Rp 14,700 -
Rp 14,000 Rp 434,000
Rp 25,000 -
Rp 7,300 Rp 58,400
Rp 7,600 Rp 15,200

Rp 122,073 -
Rp 122,073 Rp 527,356
Rp 122,073 -
Rp 14,513 -
Rp 30,129 Rp 723,105
Rp 53,390 Rp 613,984
Rp 27,434 Rp 109,736
Harga
Rp 233,600 -
Rp 324,000 -
Harga
Rp 3,600 -
Rp 18,100 -

Harga
Rp 14,010 -
Rp 13,000 -

Rp 19,500 -

Rp 20,701,400 -
Rp 6,210,420 Rp 6,210,420
Rp 1,584,000 Rp 1,584,000
Rp 3,168,000 Rp 3,168,000
Rp 1,584,000 Rp 1,584,000

JUMBLAH TOTAL PENGGUNAAN RPD 40 % Rp 82,767,314

Terbilang
us Enam Puluh Tujuh Ribu Tiga Ratus Empat Belas Rupiah
POKMAS SEMANGAT

ANDI RUSTONO

DIKETAHUI
PPKOM

TITIK WIDYASTUTI,S.Sos.,M.Si
NIP. 19741028 199303 2 002
RENCANA PENGGUNAAN DANA ( RPD ) TAHAP II 30 %
PEMBANGUNAN SARANA OLAH RAGA
KELURAHAN PADURAKSA
KECAMATAN PEMALANG KABUPATEN PEMALANG

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp)

PEKERJAAN LAPANGAN
1 Urugan Tanah 7.46 m3 Rp 82,100
2 Plesteran 59.40 m2 Rp 63,500
3 Urugan Peninggian 41.48 m3 Rp 81,400
Jumlah Total Pekerjaan Lapangan Volly
PEKERJAAN TALUD
1 Urugan Pasir 1.43 m3 Rp 134,706
1 Pasangan Batu Kali 4.68 m3 Rp 801,944
Jumlah Total Pekerjaan Talud
PEKERJAAN TAMBAHAN
<> Pagar
1 Galian Tanah 45.12 m3 Rp 38,775
2 Anstamping 5.64 m3 Rp 410,465
3 Urugan Pasir 1.692 m3 Rp 134,706
4 Pasangan Batu Kali 24.53 m3 Rp 801,944
5 Pasangan Batu Bata 172.91 m2 Rp 114,461
6 Urugan Tanah Kembali 15.04 m3 Rp 9,350
7 Plesteran Tembok 345.82 m2 Rp 49,543
8 Acian 345.82 m2 Rp 21,717
9 Pemasangan Rel Pintu Geser 4 bh Rp 266,728
a. Kusen Aluminium Pintu 1 6.12 m Rp 123,364
b. Kusen Aluminium Pintu 2 10.20 m Rp 123,364
10 Daun Pintu Harga
a. Sliding Door Besi 8.94 m2 Rp 305,000
11 Sloof 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
12 Kolom 2.81 m3 Rp 825,358
Besi 12 ( tulangan utama ) 445.00 kg Rp 11,293
Besi 8 ( begel ) 162.50 kg Rp 11,293
13 Ringbalk 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
14 Urugan Peninggian 2.69 m3 Rp 235,500
15 Cat Tembok 345.82 m2 Rp 16,588

<> WC dan Kamar Ganti


1 Galian Tanah 8.8125 m3 Rp 38,775
2 Urugan Pasir 0.47 m3 Rp 134,706
3 Anstamping 1.175 m3 Rp 410,465
4 Pasangan Batu Kali 4.7 m3 Rp 801,944
5 Urugan Tanah Kembali 3.134 m3 Rp 9,350
6 Pasangan Batu Bata 49.10 m2 Rp 114,461
7 Plesteran Tembok 98.19 m2 Rp 49,543
8 Acian 98.19 m2 Rp 21,717
9 Cat Tembok 98.19 m2 Rp 16,588
10 Kusen 0.16 m3 Rp 11,588,088
11 Daun Pintu 4.68 m2 Rp 629,860
12 Sloof 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
13 Kolom 0.693 m3 Rp 825,358
Besi 12 ( tulangan utama ) 109.65 kg Rp 11,293
Besi 8 ( begel ) 40.04 kg Rp 11,293
14 Ringbalk 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
15 Urugan Peninggian 1.17 m3 Rp 81,400
16 Urugan Pasir 0.78 m3 Rp 134,706
17 Keramik
a) Keramik 30x30cm 7.29 m2 Rp 160,176
b) Keramik 50x50cm 7.90 m2 Rp 191,224
18 Atap Dak 2.85 m3 Rp 825,358
Besi 12 ( tulangan utama ) 182.90 kg Rp 11,293
Besi 10 76.94 kg Rp 11,293
19 Pekerjaan Instalasi Listrik Harga
Box listrik 2 group 1 bh Rp 210,000
Saklar In Bauw seri 8 bh Rp 12,500
Saklar In Bauw engkel 2 bh Rp 11,000
Stop Kontak 4 bh Rp 14,700
Kabel 2x2x1/2 mm2 NYY PRIMA 31 m Rp 14,000
Kabel 2x4 mm2 NYY PRIMA 20 m Rp 25,000
Kap 8 bh Rp 7,300
Steker 2 bh Rp 7,600
20 Pekerjaan Sanitasi
Septick tank 15.54 m2 Rp 122,073
Dudukan Closet 4.32 m2 Rp 122,073
Dudukan Sanyo 0.72 m2 Rp 122,073
Pipa PVC DN 20(1/2") AW JIS 19 m Rp 14,513
Pipa PVC DN 63(2") 24 m Rp 30,129
Pipa PVC DN 90(3") 11.5 m Rp 53,390
Kran Air 4 bh Rp 27,434
Harga
Sanyo Shimizu 100watt 1 bh Rp 233,600
Closet Jongkok 2 bh Rp 324,000
Harga
Seal Tape 3 bh Rp 3,600
Floor Drain 4 bh Rp 18,100

Lain-lain
Pekerjaan Pemasangan Jaring Harga
1 Jaring-Jaring 148 m2 Rp 14,010
Rangka Jaring-jaring 36 m Rp 13,000

Pekerjaan Tribun
2 Kerangka Tribun 331.50 m Rp 19,500

3 Pajak PPN (10%) Rp 20,701,400


4 Pajak PPH (3%) Rp 6,210,420
5 Biaya Perencanaan Rp 1,584,000
6 Biaya Pelaksanaan Rp 3,168,000
7 Biaya Pengawasan Rp 1,584,000

JUMBLAH TOTAL PENGGUNAAN RPD 30 %

Terbilang
Enam Puluh Dua Juta Delapan Ratus Lima Puluh Empat Ribu Delapan Ratus Delapan Puluh Tiga Rup
DISAHKAN OLEH
KEPALA UPPU WILAYAH VI
DPU KABUPATEN PEMALANG

JAJURI,ST
NIP. 19610828 198809 1 001
DIKETAHUI
PPKOM

TITIK WIDYASTUTI,S.Sos.,M.Si
NIP. 19741028 199303 2 002
GUNAAN DANA ( RPD ) TAHAP II 30 %
GUNAN SARANA OLAH RAGA
LURAHAN PADURAKSA
EMALANG KABUPATEN PEMALANG

JUMLAH HARGA (Rp)

Rp 612,056
Rp 3,771,900
Rp 3,376,472

Rp 191,956
Rp 3,753,098

-
-
-
-
Rp 19,791,136
-
-
Rp 7,510,000
Rp 1,066,912
Rp 754,987
Rp 1,258,312

-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
Rp 29,303
Rp 5,619,576
Rp 4,864,775
Rp 2,132,420
Rp 1,628,772
Rp 1,823,038
-
-
-
-
Rp 571,973
Rp 1,238,211
Rp 452,172
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
Rp 500,000
-
-

Rp 1,897,015
-
-
-
-
-
-

-
-

Rp 10,800
-

-
-

-
-
-
-
-

Rp 62,854,883

Terbilang
ma Puluh Empat Ribu Delapan Ratus Delapan Puluh Tiga Rupiah
POKMAS SEMANGAT

ANDI RUSTONO
RENCANA PENGGUNAAN DANA ( RPD ) TAHAP III 30 %
PEMBANGUNAN SARANA OLAH RAGA
KELURAHAN PADURAKSA
KECAMATAN PEMALANG KABUPATEN PEMALANG

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp)

PEKERJAAN LAPANGAN
1 Urugan Tanah 7.46 m3 Rp 82,100
2 Plesteran 59.40 m2 Rp 63,500
3 Urugan Peninggian 41.48 m3 Rp 81,400
Jumlah Total Pekerjaan Lapangan Volly
PEKERJAAN TALUD
1 Urugan Pasir 1.43 m3 Rp 134,706
1 Pasangan Batu Kali 4.68 m3 Rp 801,944
Jumlah Total Pekerjaan Talud
PEKERJAAN TAMBAHAN
<> Pagar
1 Galian Tanah 45.12 m3 Rp 38,775
2 Anstamping 5.64 m3 Rp 410,465
3 Urugan Pasir 1.692 m3 Rp 134,706
4 Pasangan Batu Kali 24.53 m3 Rp 801,944
5 Pasangan Batu Bata 172.91 m2 Rp 114,461
6 Urugan Tanah Kembali 15.04 m3 Rp 9,350
7 Plesteran Tembok 345.82 m2 Rp 49,543
8 Acian 345.82 m2 Rp 21,717
9 Pemasangan Rel Pintu Geser 4 bh Rp 266,728
a. Kusen Aluminium Pintu 1 6.12 m Rp 123,364
b. Kusen Aluminium Pintu 2 10.20 m Rp 123,364
10 Daun Pintu Harga
a. Sliding Door Besi 8.94 m2 Rp 305,000
11 Sloof 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
12 Kolom 2.81 m3 Rp 825,358
Besi 12 ( tulangan utama ) 445.00 kg Rp 11,293
Besi 8 ( begel ) 162.50 kg Rp 11,293
13 Ringbalk 3.38 m3 Rp 825,358
Besi 12 ( tulangan utama ) 401.57 kg Rp 11,293
Besi 8 ( begel ) 173.04 kg Rp 11,293
14 Urugan Peninggian 2.69 m3 Rp 235,500
15 Cat Tembok 345.82 m2 Rp 16,588

<> WC dan Kamar Ganti


1 Galian Tanah 8.8125 m3 Rp 38,775
2 Urugan Pasir 0.47 m3 Rp 134,706
3 Anstamping 1.175 m3 Rp 410,465
4 Pasangan Batu Kali 4.7 m3 Rp 801,944
5 Urugan Tanah Kembali 3.134 m3 Rp 9,350
6 Pasangan Batu Bata 49.10 m2 Rp 114,461
7 Plesteran Tembok 98.19 m2 Rp 49,543
8 Acian 98.19 m2 Rp 21,717
9 Cat Tembok 98.19 m2 Rp 16,588
10 Kusen 0.16 m3 Rp 11,588,088
11 Daun Pintu 4.68 m2 Rp 629,860
12 Sloof 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
13 Kolom 0.693 m3 Rp 825,358
Besi 12 ( tulangan utama ) 109.65 kg Rp 11,293
Besi 8 ( begel ) 40.04 kg Rp 11,293
14 Ringbalk 0.71 m3 Rp 825,358
Besi 12 ( tulangan utama ) 83.66 kg Rp 11,293
Besi 8 ( begel ) 36.05 kg Rp 11,293
15 Urugan Peninggian 1.17 m3 Rp 81,400
16 Urugan Pasir 0.78 m3 Rp 134,706
17 Keramik
a) Keramik 30x30cm 7.29 m2 Rp 160,176
b) Keramik 50x50cm 7.90 m2 Rp 191,224
18 Atap Dak 2.85 m3 Rp 825,358
Besi 12 ( tulangan utama ) 182.90 kg Rp 11,293
Besi 10 76.94 kg Rp 11,293
19 Pekerjaan Instalasi Listrik Harga
Box listrik 2 group 1 bh Rp 210,000
Saklar In Bauw seri 8 bh Rp 12,500
Saklar In Bauw engkel 2 bh Rp 11,000
Stop Kontak 4 bh Rp 14,700
Kabel 2x2x1/2 mm2 NYY PRIMA 31 m Rp 14,000
Kabel 2x4 mm2 NYY PRIMA 20 m Rp 25,000
Kap 8 bh Rp 7,300
Steker 2 bh Rp 7,600
20 Pekerjaan Sanitasi
Septick tank 15.54 m2 Rp 122,073
Dudukan Closet 4.32 m2 Rp 122,073
Dudukan Sanyo 0.72 m2 Rp 122,073
Pipa PVC DN 20(1/2") AW JIS 19 m Rp 14,513
Pipa PVC DN 63(2") 24 m Rp 30,129
Pipa PVC DN 90(3") 11.5 m Rp 53,390
Kran Air 4 bh Rp 27,434
Harga
Sanyo Shimizu 100watt 1 bh Rp 233,600
Closet Jongkok 2 bh Rp 324,000
Harga
Seal Tape 3 bh Rp 3,600
Floor Drain 4 bh Rp 18,100

Lain-lain
Pekerjaan Pemasangan Jaring Harga
1 Jaring-Jaring 148 m2 Rp 14,010
Rangka Jaring-jaring 36 m Rp 13,000

Pekerjaan Tribun
2 Kerangka Tribun 331.50 m Rp 19,500

3 Pajak PPN (10%) Rp 20,701,400


4 Pajak PPH (3%) Rp 6,210,420
5 Biaya Perencanaan Rp 1,584,000
6 Biaya Pelaksanaan Rp 3,168,000
7 Biaya Pengawasan Rp 1,584,000

JUMBLAH TOTAL PENGGUNAAN RPD 30 %

Terbilang
Enam Puluh Satu Juta Tiga Ratus Sembilan Puluh Satu Ribu Delapan Ratus Tiga Rupiah
DISAHKAN OLEH
KEPALA UPPU WILAYAH VI
DPU KABUPATEN PEMALANG

JAJURI,ST
NIP. 19610828 198809 1 001
DIKETAHUI
PPKOM

TITIK WIDYASTUTI,S.Sos.,M.Si
NIP. 19741028 199303 2 002
GUNAAN DANA ( RPD ) TAHAP III 30 %
GUNAN SARANA OLAH RAGA
LURAHAN PADURAKSA
EMALANG KABUPATEN PEMALANG

JUMLAH HARGA (Rp)

-
-
-

-
-

-
-
-
-
-
-
Rp 17,132,864
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
Rp 2,947,745
-
-
-
-
-
-
Rp 581,878
Rp 944,739
Rp 407,087
-
-

Rp 1,167,680
Rp 1,510,192
Rp 2,349,795
Rp 2,065,360
Rp 868,875
Rp 210,000
Rp 100,000
Rp 22,000
Rp 58,800
-
-
-
-

-
-
Rp 87,893
Rp 275,752
-
-
-

Rp 233,600
Rp 648,000

-
Rp 72,400

Rp 2,073,480
Rp 468,013

Rp 6,464,250

Rp 20,701,400
-
-
-
-

Rp 61,391,803

Terbilang
s Sembilan Puluh Satu Ribu Delapan Ratus Tiga Rupiah
POKMAS SEMANGAT

ANDI RUSTONO
VOLUME

PEKERJAAN TAMBAHAN

1 Pagar
1. Galian Tanah 112.8 x 0.5 x 0.8
2. Pasir Urug 112.8 x 0.5 x 0.03
3. Anstamping 112.8 x 0.5 x 0.1
4. Pasangan Batu Kali 0.25 + 0.5 x 0.58
2
5. Pas. Batu Bata 94.8 x 1.5
21.2 x 2

6. Urugan Tanah Kembali 1/3 galian

Pengurangan
P1 2.36 x 1.8 x 1
P2 2.16 x 1.7 x 2

Luas dinding

7. Plesteran 2x luas tembok

8. Acian

9. Rel Pintu Geser


P1
P2
b. Kusen Aluminium Pintu 1 6.52
c. Kusen Aluminium Pintu 2 6.02

10. Daun Pintu


P1 2.24 x 1.8 x 1
P2 2.04 x 1.7 x 2
a. Terali besi 1.00 x 0.4 x 14

11. Sloof
A.beton 112.80 x 0.2 x 0.15
jml berat
B.besi 12 112.80 x 4 x 0.89

C.besi 8 0.59 x 752 x 0.39

12. Kolom
a.. Kolom 1 5 x 0.15 x 0.15
b.. Kolom 2 3 x 0.15 x 0.15

1.besi 12 5.00 x 4 x 0.89

1.besi 8 0.50 x 33.3333 x 0.39

2.besi 12 3.00 x 4 x 0.89

2.besi 8 0.50 x 20 x 0.39

total besi 12
total besi 8
13. Ringbalk
A.beton 112.80 x 0.2 x 0.15
jml berat
B.besi 12 112.80 x 4 x 0.89

C.besi 8 0.59 x 752 x 0.39

14. Urugan Peninggian 26.9 x 0.1


43.10 x 0.90

15. Cat Tembok

2 WC dan Kamar Ganti


1. Galian Tanah 23.5 x 0.5 x 0.75
2. Pasir Urug 23.5 x 0.5 x 0.04
3. Anstamping 23.5 x 0.5 x 0.1
4. Pasangan Batu Kali 0.3 + 0.5 x 0.5
2
5. Urugan Tanah Kembali 1/3 galian

6. Pas. Batu Bata 25.5 x 2.15

Pengurangan
P3 1.86 x 0.77 x 4

Luas dinding

7. Plesteran 2x luas tembok

8. Acian

9. Kusen
P1 4.37 x 0.15 x 0.06
10. Daun Pintu
P1 1.80 x 0.65 x 1

11. Sloof
A.beton 23.50 x 0.2 x 0.15
jml berat
B.besi 12 23.50 x 4 x 0.89
C.besi 8 0.59 x 156.667 x 0.39

12. Kolom
a.. Kolom 1 2.8 x 0.15 x 0.15
1.besi 12 2.80 x 4 x 0.89

1.besi 8 0.50 x 18.6667 x 0.39

13. Ringbalk
A.beton 23.50 x 0.2 x 0.15
jml berat
B.besi 12 23.50 x 4 x 0.89

C.besi 8 0.59 x 156.667 x 0.39

14. Urugan Peninggian


5.85 x 1.35 x 0.1
2.85 x 1.35 x 0.1
15. Urugan Pasir
5.85 x 1.35 x 0.05
2.85 x 1.35 x 0.05

16. Keramik
a. keramik ukuran 30x30 1.35 x 1.35 x 4
b. keramik ukuran 50x50 5.85 x 1.35 x 1
total

17. Cat Tembok

18. Atap Dak


a. Beton 6.50 x 3.65 x 0.12

a. Besi 12 6.85 x 30 x 0.89

b. Besi 10 3.65 x 34 x 0.62

19. Septick Tank


1. septick tank 2.40 x 2.1 x 2
1.30 x 2.1 x 2

2. dudukan sanyo 0.60 x 0.6 x 2

3. dudukan closet 1.35 x 0.8 x 2

3 Tribun
6.90 x 4 x 3
6.90 x 3 x 1
5.00 x 4 x 3
4.00 x 4 x 3

4 Talud
1. Urugan Pasir 57.00 x 0.5 x 0.05

2. Pasangan Batu Kali 0.4 x 0.3


0.2 + 0.4 x 0.4
2
VOLUME

PEKERJAAN TAMBAHAN

45.12 m3
1.692 m3
5.64 m3
112.8 24.534 m3

142.2 m2
42.3 m2
total 184.5 m2
total 15.04 m3

4.25
7.34
total 11.59 m2
total 172.91 m2

total 345.82 m2

total 345.82 m2

2.00 bh
4.00 bh
1 6.52 m
2 12.04 m

2.00 m2
6.94 m2
5.60 m2
total 8.94 m2

3.38 m3

401.57 kg

173.04 kg
10 1.125 m3
25 1.6875
total 2.81 m3
178.00 kg

65.00 kg

267.00 kg

97.50 kg

total besi 12 445.00 kg


total besi 8 162.50 kg
3.38 m3

401.57 kg

173.04 kg

2.69 m3
38.79 m3
total 41.48 m3

total 345.82 m2

8.8125 m3
0.47 m3
1.175 m3
23.5 4.7 m3

2.9375 m3

54.825 m2
total 54.825 m2

5.73
total 5.73 m2
total 49.10 m2

total 98.19 m2

total 98.19 m2

4 0.16 m3

4 4.68 m3

0.71 m3

83.66 kg
36.05 kg

11 0.693 m3
109.65 kg

40.04 kg

0.71 m3

83.66 kg

36.05 kg

0.79 m3
0.38 m3

total 1.17 m3
0.39 m3
2 0.38 m3
total 0.78 m3

7.29
7.90
total 15.19 m2

total 98.19 m2

2.85 m3

182.90 kg

76.94 kg

1 10.08 m2
1 5.46 m2
total 15.54 m2

1 0.72 m2

2 4.32 m2

82.80
20.70
3 180.00
1 48.00
total 331.50 m

1.43 m3

19.5 2.34 m3
19.5 2.34 m3
total 4.68 m3
DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG
EDISI MEI 2010

NO. PERALATAN SATUAN MAKSIMUM KET.


(Rp)

1 Dump Truck Jam


2 Truk Bak Terbuka Jam
3 Truk Tanki Air Jam
4 Bulldozer Jam
5 Motor Grader Jam
6 Wheel Loader Jam
7 Excavator Jam
8 Crane Jam
9 Trailler Jam
10 Mesin Gilas Tandem 6 - 10 ton Jam
11 Mesin Gilas 3 roda 6 - 10 ton Jam
12 Mesin Gilas Roda Karet 8 - 10 ton Jam
13 Vibratory Roller Jam
14 Vibro roller 1 ton Jam
15 Water Pump Jam
16 Asphalt Sprayer Jam
17 Pick Up Jam
18 AMP Jam
19 Asphalt Finisher Jam
20 Concrete Vibrator Jam
21 Compressor Jam
22 Concrete Mixer Jam
23 Stamper Jam
24 Genset Jam
25 Alat Pengecat Marka Jam
26 Mesin Las hari 70,000.00
URAIAN PERSENTASE ( % ) PENGGUNAAN RPD
PEMBANGUNAN SARANA OLAH RAGA
Kelurahan Paduraksa , Kecamatan Pemalang, Kabupaten Pemalang

PROSEN
NO URAIAN PEKERJAAN TOTAL HARGA
TASE (%)
1 Jumlah Total Pekerjaan Lapangan Volly Rp 7,760,428 0.04 %
2 Jumlah Total Pekerjaan Talud Rp 3,945,054 1.91 %
3 Jumlah Total Pekerjaan Pagar,dan Kamar Ganti Rp 146,456,916 70.75 %
4 Jumlah Total Pekerjaan Instalasi Listrik Rp 1,398,400 0.68 %
5 Jumlah Total Pekerjaan Sanitasi / Plumbing Rp 5,199,640 2.51 %
6 Jumlah Total Pekerjaan Jaring Atas Pagar Rp 2,541,493 1.23 %
7 Jumlah Total Pekerjaan Tribun Penonton Rp 6,464,250 3.12 %
8 Jumlah Total Pajak PPN Rp 20,701,400 10.00 %
9 Jumlah Total Pajak PPH Rp 6,210,420 3.00 %
10 Jumlah Total Perencanaan Rp 1,584,000 0.77 %
11 Jumlah Total Pelaksanaan Rp 3,168,000 1.53 %
12 Jumlah Total Pengawasan Rp 1,584,000 0.77 %
Jumlah Total Semua Pekerjaan Rp 207,014,000 100.00 %
DAFTAR HARGA SATUAN UPAH
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN PEMALANG
TAHUN ANGGARAN 2017

NO. URAIAN SATUAN HARGA (Rp)

1 Pekerja Hr 45,000.00

2 Mandor Hr 60,000.00

3 Tukang Listrik Hr 60,000.00

4 Tukang Kayu Hr 60,000.00

5 Tukang Batu Hr 60,000.00

6 Tukang Besi Hr 60,000.00

7 Tukang Cat Hr 60,000.00

8 Kepala Tukang Hr 60,000.00

9 Tukang Las Hr 60,000.00

10 Tukang Plitur Hr 60,000.00

11 T u k a n g j a l a n Hr 60,000.00

12 Tukang Gali Hr 45,000.00

13 Tukang masak aspal Hr 45,000.00

14 Tukang Leideng Hr 60,000.00

HSPK Cipta Karya_2016P Page 61 of 328 Daftar Harga Upah


H
ABUPATEN PEMALANG

KETERANGAN

6,428.57 / Jam

8,571.43 / Jam

8,571.43 / Jam

8,571.43 / Jam

8,571.43 / Jam

8,571.43 / Jam

8,571.43 / Jam

8,571.43 / Jam

8,571.43 / Jam

8,571.43 / Jam

8,571.43 / Jam

6,428.57 / Jam

6,428.57 / Jam

8,571.43 / Jam

HSPK Cipta Karya_2016P Page 62 of 328 Daftar Harga Upah


DAFTAR HARGA SATUAN BAHAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN PEMALANG
TAHUN ANGGARAN 2017

HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 201,200
Bulat Belah m3 225,800

2 KERIKIL Sirtu m3 158,400


Beton 2/3 m3 244,000
Abu batu m3 243,000

3 BATU BATA ex lokal bh 860

4 PASIR Urug m3 90,300


Pasang m3 240,000
Beton ( Ex Semaya ) m3 322,500
Beton ( Muntilan ) m3 360,000

5 TANAH Padas m3 81,400


Liat m3 82,100

6 KAPUR Pasang m3 160,000


Semen Merah m3 160,000

7 PORTLAND CEMENT
40 Kg zak 49,500
50 Kg zak 54,500
Semen Putih 40 kg zak 94,600

HSPK Cipta Karya_2016P Page 63 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

Semen Putih 50 kg zak 104,200


Semen warna kg 13,300

II BAHAN PENUTUP ATAP


1 SIRAP (100 lbr) pak 180,000
2 GENTENG BETON Genteng Beton Warna standard bh 3,900
Genteng Beton Warna Special bh 5,600
Genteng Beton Warna Khusus bh 5,800
Kerpus Beton Warna Standard bh 6,300
Kerpus Beton Warna Special bh 7,900
Kerpus Beton Warna Khusus bh 11,200
3 GENTENG TANAH LIAT
Vlaam bh 2,200
Kodok bh 2,550
Kodok Glasur bh 3,300
Nok kerpus Kodok bh 5,200
Nok kerpus Kodok Glasur bh 7,900
Plentong super besar bh 2,900
Nok kerpus plentong super bh 6,000
4 GENTENG KACA
Vlaam tebal 2 mm bh 8,000
Vlaam tebal 3 mm bh 8,400
Kodok tebal 2 mm bh 8,700
Kodok tebal 3 mm bh 9,200

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 78,500
. 250 cm X 102 cm X 5 mm bh 92,000
. 225 cm X 102 cm X 5 mm bh 87,000
. 200 cm X 102 cm X 6 mm bh 80,700

HSPK Cipta Karya_2016P Page 64 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

. 225 cm X 102 cm X 6 mm bh 91,000


. 250 cm X 102 cm X 6 mm bh 96,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 28,800
. 180 cm X 105 cm X 4 mm bh 33,000
. 210 cm X 105 cm X 4 mm bh 37,800
. 240 cm X 105 cm X 4 mm bh 43,200
. 270 cm X 105 cm X 4 mm bh 43,000
. 300 cm X 105 cm X 4 mm bh 69,700
. 150 cm X 105 cm X 3 mm bh 23,000
. 180 cm X 105 cm X 3 mm bh 32,600
. 210 cm X 105 cm X 3 mm bh 37,300
. 240 cm X 105 cm X 3 mm bh 42,300

6 ASBES PLAT . 100cm X 100 cm X 3 mm bh 17,200


. 100cm X 100 cm X 4 mm bh 17,900
. 50 cm X 200 cm X 3 mm bh 15,000
. 40 cm X 200 cm X 3 mm bh 13,200
Gyproc unt dinding 120 cm x 240 cm x 1,2 cm lbr 60,000
/ plafond 120 cm x 240 cm x 0,9 cm lbr 50,000
NOK/KERPUS
. Kerpus Genteng bh 15,630
. Stel Besar bh 37,500
. Paten Besar bh 39,700
Nokstel gelombang
. Stel Besar bh 40,500
. Patent Besar bh 26,500
. Plat besar bh 48,000
Ondovilla 40 cm x 106 cm x 0,3 cm lbr

HSPK Cipta Karya_2016P Page 65 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

7 FIBRE GLASS
180 X 92 cm bh 48,800
200 X 92 cm bh 64,700
250 X 92 cm bh 75,000
180 X 105 cm bh 63,000
210 X 105 cm bh 74,400
250 X 105 cm bh 82,700
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 17,500
BJLS 0,20 lebar 55 cm m' 19,600
BJLS 0,28 lebar 55 cm m' 35,500
BJLS 0,30 lebar 55 cm m' 33,700
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 57,500
BJLS 0,20 panjang 180 cm lbr 44,800
BJLS 0,30 panjang 180 cm lbr 61,200
BJLS 0,40 panjang 180 cm lbr 74,700

III . B A H A N K A Y U
1 JATI Papan m3 22,000,000
Balok/pesagen m3 19,800,000

2 KAMPER Papan m3 8,150,000


Balok/pesagen m3 7,525,000

3 KRUING Papan m3 6,866,000


Balok/pesagen m3 6,100,000

4 KEMPAS Papan m3 6,333,000


Balok/pesagen m3 5,150,000
Usuk dan reng m3

HSPK Cipta Karya_2016P Page 66 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

5 MERANTI Papan m3 4,700,000


Balok/pesagen m3 4,066,000
Usuk dan reng m3

6 LANAN Papan m3 2,050,000


Balok/pesagen m3 1,725,000

7 BENGKIRAI Papan m3 10,966,000


Balok/pesagen m3 9,741,000

8 DOLKEN Sedang 8 x 10 x 400 cm bt 23,400


Kecil 6 x 7 x 400 cm bt 21,000
Besar 10 x 12 x 400 cm bt 33,700
Bambu bt 9,000

9 Papan cor/bekisting Papan cor 0.18x18x180 cm lbr -


Papan cor (m )
3
m3 1,850,000

IV . BAHAN PENUTUP DINDING / LANTAI


1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 38,100
20 X 20 cm m2 39,600
PC warna 30 X 30 cm m2 40,100
20 X 20 cm m2 38,600
Teraso 30 X 30 cm m2 54,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,300

HSPK Cipta Karya_2016P Page 67 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

PC abu-abu 15 x 20 bh 5,700

4 UBIN PORSELIN
Lokal 11 X 11 putih dos 40,000
11 X 11 warna dos 43,500
Lokal 15 X 15 putih dos 46,500
15 X 15 warna dos 47,500
5 MOZAIK PORSELIN
10 X 20 cm m2 54,500
15 X 15 cm m2 53,500
20 X 20 cm m2 53,500
20 X 25 cm m2 53,500

6 Keramik 20 X 20 cm m2 51,100
20 X 25 cm m2 52,600
20 X 30 cm m2 59,000
20 X 40 cm m2 61,600
25 x 40 cm m2 -
25 x 25 cm m2 56,800
30 X 30 cm m2 43,800
40 X 40 cm m2 47,600
50 X 50 cm m2 69,300
60 X 60 cm m2 98,300

7 Parquet Jati m2 230,000

8 Batu Paros m2 127,500

9 Batu Tempel Hitam m2 119,100

10 GRANITO 40 x 40 cm m2 260,000
30 x 30 cm m2 305,000
11 Marmer buah 461,200

V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 33,500
Ø 20 cm - 100 cm bh 62,500
Ø 30 cm - 100 cm bh 75,000

HSPK Cipta Karya_2016P Page 68 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

Ø 50 cm - 100 cm bh 107,500
Ø 60 cm - 100 cm bh 150,000
Ø 70 cm - 100 cm bh 172,500
Ø 80 cm - 25 cm bh 70,000
Ø 90 cm - 25 cm bh
U 10 cm - 100 cm bh 22,500
U 15 cm - 100 cm bh 34,500
U 20 cm - 100 cm bh 45,700
U 30 cm - 100 cm bh 48,700

HSPK Cipta Karya_2016P Page 69 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

2 LUBANG ANGIN (ROSTER) PC + PASIR


10 X 20 cm bh 9,000
20 X 20 cm bh 9,000
25 X 25 cm bh 10,800
30 X 30 cm bh 17,500
15 X 25 cm bh 15,000
15 X 30 cm bh 20,000

VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 8,800
besi beton prestress kg 13,500
besi beton ulir kg 9,600

2 BESI PLAT Besi Strip kg 13,200

3 BESI PROFIL Besi Profil kg 14,000

4 JARING - JARING BAJA


Diameter 4 - 15 kg 15,500
Diameter 6 - 15 kg 15,700

5 BESI SIKU L 40 X 40 X 4 btg 75,800


L 50 X 50 X 5 btg 112,500
L 60 X 60 X 6 btg 166,600

6 KAWAT - Ikat beton/bendrat kg 15,000


- Harmonika 12 X 45 mm m2 17,700
- Harmonika 12 X 24 mm m2 18,600
- Harmonika 14 X 30 mm m2 19,500
- Harmonika 14 X 35 mm m2 18,200
- Kawat Nyamuk Nylon m2 17,100
- Kawat Kasa m2 16,200
- Saringan pasir m2 16,200
- Kawat loket m2 13,300
- Kawat duri rol 69,300
- Kawat bronjong 3 mm kg 15,400

HSPK Cipta Karya_2016P Page 70 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

- Kawat bronjong 4 mm kg 14,300

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 19,370
Pipa PVC DN 25 ( ¾" ) AW JIS btg 25,630
Pipa PVC DN 32 ( 1" ) AW JIS btg 35,580
Pipa PVC DN 40 ( 1½" ) btg 50,910
Pipa PVC DN 63 ( 2" ) btg 73,000
Pipa PVC DN 90 ( 3" ) btg 138,330

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,500
30 X 60 lbr 13,500
60 X 120 lbr 41,000
List kayu profil m' 3,600
List gypsum m' 13,000

2 SOFT BOARD-uk: 4'X 8'


Kalsiboard 240 cm x 120 cm t =6 mm lbr 60,000
Gypsum tebal 6 mm lbr
Gypsum tebal 9 mm lbr 59,300

3 HARD BOARD-uk: 4'X 8' lbr 64,500

4 PLY WOOD
Teakwood
. 90 x 210 3 mm lbr 65,000
. 90 x 210 4 mm lbr 72,500

Tripleks
. 120 X 240 X 3 mm lbr 51,400
. 120 X 240 X 4 mm lbr 63,900
. 120 X 240 X 6 mm lbr 73,000
Multipleks
. 120 X 240 X 9 mm lbr 117,500
. 120 X 240 X 12 mm lbr 151,200
. 120 X 240 X 15 mm lbr 197,500

HSPK Cipta Karya_2016P Page 71 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

. 120 X 240 X 18 mm lbr 222,500


Formika ukuran pintu lbr 56,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 22,100
Dempul plamur kg 27,500
Amplas lbr 4,400
Batu Apung kg 18,500
Cat dasar kg 34,200
. Avian kg 51,500
. Yunior 66 (nippon paint) kg 54,700
. Deculux kg 56,000
. Siralax ons 19,400
. Spiritus ltr 11,400
. Plitur jadi ltr 50,700
. Teak Oil ltr 41,000
. Vernis ltr 25,000

2 TEMBOK
Kalkarium kg 4,400
Kapur sirih kg 4,600
Plamur kg 29,500
Cat Tembok Dasar kg 16,800
Sintex 5 kg 87,000
Danabride 5 kg 90,500
Catylac 5 kg 110,600
Mowilex 5 kg 197,500
Decolith 5 kg 100,800

3 BESI
Menie kg 25,600
Cat mengkilat kg 51,000
Cat kg 44,000
Thinner A ltr 23,600
Minyak cat ltr 11,400
Thinner Super ltr 20,000

HSPK Cipta Karya_2016P Page 72 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

Residu ter drum 119,300

X.BAHAN KACA
1 POLOS 3 mm m2 81,800
5 mm m2 95,100

2 ES KABUR 3 mm m2 89,100
5 mm m2 106,200

3 RAY BAND 3 mm m2 87,600


5 mm m2 109,200

4 GLASS BLOCK bh

XI . BAHAN INSTALASI LISTRIK


1 KABEL LISTRIK
N YA : . 1 X 1 1/2 mm2 m' 3,300
SPLN LMK 1 X 2 1/2 mm2 m' 3,600
. 1X4 mm2 m' 5,500
1X6 mm2 m' 8,400
NYY :. 2 X 1 1/2 mm2 m' 8,500
PRIMA 2 X 2 1/2 mm2 m' 14,000
. 2X4 mm2 m' 25,000
2X6 mm2 m' 34,000
3 X 1 1/2 mm2 m' 12,500
3 X 2 1/2 mm2 m' 19,000
3X4 mm2 m' 34,000
3X6 mm2 m' 48,000
NYM :. 2 X 1 1/2 mm2 m' 6,800
PRIMA 2 X 2 1/2 mm2 m' 10,500
. 2X4 mm2 m' 21,000
3 X 1 1/2 mm2 m' 12,000
3 X 2 1/2 mm2 m' 18,500
3X4 mm2 m' 31,000
3X6 mm2 m' 43,000

2 SKAKELAR
Out bauw . Seri bh 14,800

HSPK Cipta Karya_2016P Page 73 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

. Engkel bh 12,600
In bauw . Seri bh 12,500
. Engkel bh 11,000

3 FUSE BOX (SEKERING KASA)


1 group bh 120,000
2 group bh 210,000
3 group bh 241,000

4 STEKER - Biasa bh 7,600


Arde bh 15,000
T Biasa bh 73,000
T dengan Arde bh 11,000

5 FITING Flaon bh 10,700


Gantung bh 5,300
Kap bh 7,300
Kombinasi bh 10,000

6 STOP KONTAK - Arde Outbow putih bh 14,700


Arde Outbow hitam bh 5,000
Arde IB bh 12,000
Arde Putar bh 35,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 50,000
2 X slag bh 72,500
Yale : 1 X slag bh 77,500
2 X slag bh 130,000
Kuda : 1 X slag bh 65,800
2 X slag bh 78,300

2 ENGSEL DAN GERENDEL


Engsel Angin bh 5,700
Kupu-kupu biasa bh 4,600
Nylon kupu-kupu bh 7,000
Espagnoled - dalam negeri bh 26,400
Grendel Tanam luar negeri bh 7,800
Kunci Lemari bh 5,000

HSPK Cipta Karya_2016P Page 74 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

Grendel biasa bh 6,700


Kait Angin bh 9,100
Door Stop bh 21,300
Engsel jendela bh 12,300

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,467,800
2 KLOSET JONGKOK bh 133,500
3 WASTAFEL PEDESTAL 7,5 liter bh 465,800
4 WASTAFEL MEJA OVAL bh 537,500
5 WASTAFEL GANTUNG BULAT bh 285,000
6 WASTAFEL GANTUNG SUDUT bh 260,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 220,000
8 WASTAFEL BAK CUCI bh 164,500
9 TEMPAT SABUN GANTUNG bh 40,600
10 TEMPAT SABUN TANAM bh 45,700
11 LAIN - LAIN
Kran Air bh 17,500
Seal tape bh 3,600
Floor drain bh 18,100

XIV . ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4" kg 13,300
PAKU - ukuran 12 cm bh 13,300
2 PAKU - payung kg 20,700
3 PAKU - sekrup kg 36,000
4 PAKU - beton Kg 21,200
5 MUR BAUT (kuda-kuda) kg 14,800
6 ANGKUR BAUT bh 13,300
7 LEM KAYU kg 12,000
8 Tali Ijuk kg 6,500

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 340,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 427,500
Fuji 250 watt bh 975,000
Shimizu . 125 watt bh 390,000

HSPK Cipta Karya_2016P Page 75 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

. 100 watt bh 235,000


. 90 watt bh 288,400
Dab . 125 watt bh 320,000
. 175 watt bh 510,400

XVI . PAVING BLOCK


1 SQUARE Abu-abu m2 63,500
Merah/hitam m2 72,700
2 HOLLAND Abu-abu m2 52,000
Merah/hitam m2 65,000
3 UNIDECOR Abu-abu m2 52,000
Merah/hitam m2 65,000
4 UNI Abu-abu m2 52,000
Merah/hitam m2 65,000
5 TRIHEX Abu-abu m2 59,700
Merah/hitam m2 57,600
6 OLYMPIA HEXA Abu-abu m2 60,400
7 HEXAGONAL Abu-abu m2 72,000
Merah/hitam m2 82,000
8 CASTLE Abu-abu m2 57,600
9 TRAPEZ Abu-abu m2 57,600
10 TRAPEZ GRASS BLOCK
Abu-abu m2 60,000
11 STANDARD GRASS BLOCK ABU-ABU m2 34,800
12 BATACO m2 3,700
13 KANSTEEN m' 22,000

XVII. L A I N - L A I N
1 KREI 25 MM m2 42,500
2 Sliding Pintu J4 bh 221,200
3 Naco per Daun bh 11,000

HSPK Cipta Karya_2016P Page 76 of 328 Daftar Harga Bahan


HARGA SATUAN
NO. URAIAN SATUAN
(Rp)

4 Rolling door Besi m2 335,000


Rolling door Almunium m2 375,000
5 Awning Almunium m2 159,600
6 Kusen Almunium 4" Putih m' 97,500
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,250,000
8 Rel pintu dorong Bh 200,000
9 ASPAL.
Aspal Pertamina Pen 60/70 drum 1,150,000
10 PAGAR BRC. Pagar BRC 90 A2 /lb 212,000
Pagar BRC 120 A2 /lb 282,100
11 Minyak Beton & bekisting ltr 14,500
12 Sunscreen Allumunim m2 272,500
13 Allumunium Foil m2 7,950
14 Allumunium Strip m1 4,500
15 Karpet m2 125,000
16 Soda api kg 12,700
17 Sabun kg 13,000
18 Air m3 13,700
19 Kuas bh 7,500
20 Koas Alang-alang ikat 2,200
21 Bilik Bambu m2 21,800
22 Fiber glass (tangki air) kapasitas 550 liter. Buah 985,000
23 Fiber glass (tangki air) kapasitas 1100 liter. Buah 1,615,000
24 Lem Aica Aibon kg 31,700
25 Kawat Las kg 24,000.00
26 Pintu lipat besi m2 350,000.00
27 Solar liter 5,150.00
28 Premium liter 6,450.00
29 Pelumas liter 25,000.00

HSPK Cipta Karya_2016P Page 77 of 328 Daftar Harga Bahan


EN PEMALANG

KETERANGAN

HSPK Cipta Karya_2016P Page 78 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 79 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 80 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 81 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 82 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 83 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 84 of 328 Daftar Harga Bahan


KETERANGAN

panjang 6 m
panjang 6 m
panjang 6 m

HSPK Cipta Karya_2016P Page 85 of 328 Daftar Harga Bahan


KETERANGAN

panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m
panjang 4 m

HSPK Cipta Karya_2016P Page 86 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 87 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 88 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 89 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 90 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 91 of 328 Daftar Harga Bahan


KETERANGAN

HSPK Cipta Karya_2016P Page 92 of 328 Daftar Harga Bahan


DAFTAR HARGA SATUAN PEKERJAAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN PEMALA
TAHUN ANGGARAN 2017

NO. SNI URAIAN PEKERJAAN

I A.2.2.1 PEKERJAAN PERSIAPAN


1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank
3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran
4 A.2.2.1.7 Pembuatan Gudang Semen dan Alat-alat
5 A.2.2.1.9 Membersihkan Lapangan dan Perataan
6 A.2.2.1.10 Pembuatan Steger dari Bambu Uk. 40 x 50 x 20 cm
7 A.2.2.1.13 Bongkaran Beton Bertulang
8 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah

II A.2.3.1 PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m
2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m
3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m
4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m
5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m
6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m
7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m
8 A.2.3.1.8 MembuangTanah sejauh 30 m'
9 A.2.3.1.9 Urugan Kembali (dihitung 1/3 kali indeks pekerjaan galian)
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm)
11 A.2.3.1.11 Urugan Pasir
12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL
13 A.2.3.1.13 Pemasangan Lapisan Ijuk tebal 10 cm
14 A.2.3.1.14 Mengurug Sirtu

III A.3.2.1 PEKERJAAN PONDASI

HSPK Cipta Karya_2016P Page 93 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

1 A.3.2.1.1 Memasang Pondasi Batu Kali 1Pc : 3 PP


2 A.3.2.1.2 Memasang Pondasi Batu Kali 1Pc : 4 PP
3 A.3.2.1.3 Memasang Pondasi Batu Kali 1Pc : 5 PP
4 A.3.2.1.4 Memasang Pondasi Batu Kali 1Pc : 6 PP
5 A.3.2.1.5 Memasang Pondasi Batu Kali 1Pc : 8 PP
6 A.3.2.1.6 Memasang Pondasi Batu Kali 1Kp : 1Sm : 2Pp
7 A.3.2.1.7 Memasang Pondasi Batu Kali, 1 Pc : 3 Kp : 10 PP
8 A.3.2.1.8 Memasang Pondasi Batu Kali, ¼ Pc : 1Kp : 4 PP
9 A.3.2.1.9 Pasang Pondasi Batu Kosong
Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR &
10 A.3.2.1.10
40% Batu Belah
11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm

IV A.4.4.1 PEKERJAAN DINDING

Memasang Dinding Bata Merah ukuran (5x11x22) cm Tebal 1


1 A.4.4.1.1
bata Camp. 1Pc : 2Pp

Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1


2 A.4.4.1.2
Bata Camp. 1Pc : 3PP

Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1


3 A.4.4.1.3
Bata Camp. 1Pc : 4PP

Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1


4 A.4.4.1.4
Bata Camp. 1Pc : 5PP

Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1


5 A.4.4.1.5
Bata Camp. 1Pc : 6PP

Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1


6 A.4.4.1.6
Bata Camp. 1Pc : 3 KP :10PP

Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2


7 A.4.4.1.7
Bata Camp. 1Pc : 2PP

Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2


8 A.4.4.1.8
Bata Camp. 1Pc : 3PP

Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2


9 A.4.4.1.9
Bata Camp. 1Pc : 4PP

HSPK Cipta Karya_2016P Page 94 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2


10 A.4.4.1.10
Bata Camp. 1Pc : 5PP

Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2


11 A.4.4.1.11
Bata Camp. 1Pc : 6PP

Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2


12 A.4.4.1.12
Bata Camp. 1Pc : 8PP

Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2


13 A.4.4.1.13
Bata Camp. 1Pc : 3KP : 10PP

V A.4.4.2 PEKERJAAN PLESTERAN


1 A.4.4.2.1 Memasang Plesteran 1 Pc : 1 Pp Tebal 15 mm
2 A.4.4.2.2 Memasang Plesteran 1 Pc : 2 Pp Tebal 15 mm
3 A.4.4.2.3 Memasang Plesteran 1 Pc : 3 Pp Tebal 15 mm
4 A.4.4.2.4 Memasang Plesteran 1 Pc : 4 Pp Tebal 15 mm
5 A.4.4.2.5 Memasang Plesteran 1 Pc : 5 Pp Tebal 15 mm
6 A.4.4.2.6 Memasang Plesteran 1 Pc : 6 Pp Tebal 15 mm
7 A.4.4.2.7 Memasang Plesteran 1 Pc : 7 Pp Tebal 15 mm
8 A.4.4.2.8 Memasang Plesteran 1 Pc : 8 Pp Tebal 15 mm
9 A.4.4.2.9 Memasang Plesteran 1 Pc : 1/2 Kp : 3 Pp Tebal 15 mm
10 A.4.4.2.10 Memasang Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm
11 A.4.4.2.11 Memasang Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm
12 A.4.4.2.12 Memasang Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm
13 A.4.4.2.13 Memasang Plesteran 1 Pc : 2 Pp Tebal 20 mm
14 A.4.4.2.14 Memasang Plesteran 1Pc : 3Pp Tebal 20 mm
15 A.4.4.2.15 Memasang Plesteran 1 Pc : 4 Pp Tebal 20 mm
16 A.4.4.2.16 Memasang Plesteran 1Pc : 5Pp Tebal 20 mm
17 A.4.4.2.17 Memasang Plesteran 1Pc : 6Pp Tebal 20 mm
18 A.4.4.2.18 Memasang Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm
19 A.4.4.2.19 Memasang Berapen 1 Pc : 5Pp Tebal 15 mm
20 A.4.4.2.20 Memasang Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm
21 A.4.4.2.23 Memasang Plesteran Ciprat 1Pc : 2 Pp
22 A.4.4.2.24 Memasang Finishing Siar Pasangan Dinding Bata Merah (=20 m')

HSPK Cipta Karya_2016P Page 95 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

23 A.4.4.2.25 Memasang Finishing Siar Pasangan Dinding Conblock ekspose (=8


24 A.4.4.2.26 Memasang Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp
25 A.4.4.2.27 Memasang Acian

VI A.4.6.1 PEKERJAAN KAYU


Pembuatan dan Pemasangan Kosen Pintu & Jendela Kayu klas I
1 A.4.6.1.1

Pembuatan dan Pemasangan Kosen Pintu & Jendela Kayu klas


2 A.4.6.1.2
II
Pembuatan dan Pemasangan Pintu Klamp Standard Kayu Klas
3 A.4.6.1.3
II (Kayu Kamfer)
4 A.4.6.1.5 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Klas II

5 A.4.6.1.6 Pembuatan dan Pemasangan Pintu & Jendela Kaca Kayu Klas II

Pembuatan dan Pemasangan Pintu & Jendela Jalusi Kayu Klas I


6 A.4.6.1.7

Pembuatan dan Pemasangan Pintu kayu lapis (Plywood)


7 A.4.6.1.8
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)
Pembuatan dan Pemasangan Pintu Plywood rangkap, rangka
8 A.4.6.1.9
expose kayu klas II
9 A.4.6.1.10 Pembuatan dan Pemasangan Jalusi mati Kosen Kayu Klas I
Pembuatan dan Pemasangan Pintu Teakwood Rangkap,
10 A.4.6.1.11
Rangka Expose Kayu Klas I
Pembuatan dan Pemasangan Pintu Teakwood Rangkap Lapis
11 A.4.6.1.12
Formika,Rangka expose Kayu Klas II
Pembuatan dan Pemasangan Konstruksi Kuda-kuda
12 A.4.6.1.13
Konvensional Kayu I; II & III Bentang 6 meter
Pembuatan dan Pemasangan Konstruksi Kuda-kuda Expose,
13 A.4.6.1.14
Kayu Klas I
14 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II
15 A.4.6.1.16 Pemasangan Rangka Atap Genteng Keramik, Kayu Klas II
16 A.4.6.1.17 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II
17 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II
18 A.4.6.1.19 Pemasangan Rangka Langit-langit (0,50x1,00) m, kayu Klas II
19 A.4.6.1.20 Pemasangan Rangka Langit-langit (60x60) cm, kayu Klas II

HSPK Cipta Karya_2016P Page 96 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

20 A.4.6.1.21 Pemasangan Listplank Uk. (3x20)cm Kayu klas I


21 A.4.6.1.22 Pemasangan Listplank Uk. (3x30)cm Kayu klas II
Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu klas
22 A.4.6.1.23
II
Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu
23 A.4.6.1.24
Klas II
24 A.4.6.1.26 Pemasangan Dinding Lambriziring dari Papan klas I
Pemasangan Dinding Lambriziring dari Plywood ukuran
25 A.4.6.1.27
(120x240) cm
26 A.4.6.1.28 Pemasangan Dinding Bilik, Rangka Kayu Klas III

VII A.4.1.1 PEKERJAAN BETON


Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c =
1 A.4.1.1.1
0,87
Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c =
2 A.4.1.1.2
0,78
Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c =
3 A.4.1.1.3
0,72
Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-
4 A.4.1.1.4
6)cm, w/c = 0,87
Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c
5 A.4.1.1.5
= 0,66
Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c
6 A.4.1.1.6
= 0,61
Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c
7 A.4.1.1.7
= 0,58
Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c
8 A.4.1.1.8
= 0,56
Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum
9 A.4.1.1.9
(12±2)cm, w/c = 0,53
Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c
10 A.4.1.1.10
= 0,52
Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c
11 A.4.1.1.11
= 0,49
Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c
12 A.4.1.1.12
= 0,48
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir

HSPK Cipta Karya_2016P Page 97 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

14 A.4.1.1.18 Kabel Presstresed Polos/strand


15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh
16 A.4.1.1.20 Memasang Bekisting untuk Pondasi
17 A.4.1.1.21 Memasang Bekisting untuk Sloof
18 A.4.1.1.22 Memasang Bekisting untuk Kolom
19 A.4.1.1.23 Memasang Bekisting untuk Balok
20 A.4.1.1.24 Memasang Bekisting untuk Lantai
21 A.4.1.1.25 Memasang Bekisting untuk Dinding
22 A.4.1.1.26 Memasang Bekisting untuk Tangga
23 A.4.1.1.27 Memasang Jembatan Cor
24 A.4.1.1.28 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting)
25 A.4.1.1.29 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting)
26 A.4.1.1.30 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting)
27 A.4.1.1.31 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting)
28 A.4.1.1.32 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting)
29 A.4.1.1.33 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting)
30 A.4.1.1.34 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting)
31 A.4.1.1.35 Membuat Kolom Penguat Beton Bertulang (11 x 11) cm
32 A.4.1.1.36 Membuat Ring Balok Beton Bertulang (10 x 15) cm

VIII A.4.5.2 PEKERJAAN PENUTUP ATAP


1 A.4.5.2.1 Pasang Atap Genteng Plentong Kecil
2 A.4.5.2.2 Pasang Atap Genteng Kodok / Glasur
3 A.4.5.2.3 Pasang Atap Genteng Plentong Super / Besar
4 A.4.5.2.4 Pasang Genteng Bubung Plentong
5 A.4.5.2.5 Pasang Genteng Bubung Kodok / Glasur
6 A.4.5.2.6 Pasang Genteng Bubung Plentong Besar
7 A.4.5.2.9 Pasang Atap Asbes Gelombang (2,25x0,92 m) x 5 mm
8 A.4.5.2.10 Pasang Atap Asbes Gelombang (2,00x0,92 m) x 5 mm
9 A.4.5.2.12 Pasang Atap Asbes Gelombang (3,00x1,05 m) x 4 mm
10 A.4.5.2.15 Pasang Atap Asbes Gelombang (2,10x1,05 m) x 4 mm
11 A.4.5.2.30 Pasang Atap Genteng Beton

HSPK Cipta Karya_2016P Page 98 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

12 A.4.5.2.33 Pasang Atap Sirap


13 A.4.5.2.34 Pasang Nok Genteng Beton
14 A.4.5.2.37 Pasang Nok Sirap
15 A.4.5.2.38 Pasang Atap Seng Gelombang
16 A.4.5.2.39 Pasang Atap Nok Seng
17 A.4.5.2.42 Pasang Allumunium Foil / Sisalation

IX A.4.5.1 PEKERJAAN LANGIT-LANGIT


1 A.4.5.1.1 Memasang Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm
2 A.4.5.1.2 Memasang Langit-langit Akustik Ukuran (30x30) cm
3 A.4.5.1.3 Memasang Langit-langit Akustik Ukuran (30x60) cm
4 A.4.5.1.5 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm,
5 A.4.5.1.6 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm
6 A.4.5.1.7 Memasng Langit-langit Gypsu Board, Uk (120x240) tebal 9 mm
7 A.4.5.1.10 List Langit-Langit Kayu Profil

X A.5.1.1 PEKERJAAN SANITASI


1 A.5.1.1.1 Memasang Closet Duduk / Mono Blok
2 A.5.1.1.2 Memasang Closet Jongkok Porselen
3 A.5.1.1.4 Memasang Urinoir
4 A.5.1.1.5 Memasang Wastafel
5 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3
6 A.5.1.1.35 Memasang Pipa Beton, Ø 20 cm
7 A.5.1.1.36 Memasang Pipa Beton, Ø 100 cm
8 A.5.1.1.25 Memasang Pipa PVC type AW Ø ½"
9 A.5.1.1.29 Memasang Pipa PVC type AW Ø 2"
10 A.5.1.1.31 Memasang Pipa PVC type AW Ø 3"
11 A.5.1.1.12 Memasang Bak Cuci Piring Stainles Steel
12 A.5.1.1.19 Memasang Kran Ø ¾" atau ½"
13 A.5.1.1.14 Memasang Floor Drain

XI A.4.2.1 PEKERJAAN BESI & ALLUMUNIUM

HSPK Cipta Karya_2016P Page 99 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

1 A.4.2.1.1 Memasang Besi Profil


2 A.4.2.1.2 Memasang Rangka Kuda-kuda Baja IWF
3 A.4.2.1.3 Mengerjakan Pekerjaan Perakitan (Kuda-kuda Baja)
4 A.4.2.1.4 Membuat Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Si
5 A.4.2.1.5 Mengerjakan Pengelasan dengan Las Listrik
6 A.4.2.1.7 Memasang Pintu Rolling Door Besi
7 A.4.2.1.8 Memasang Pintu Lipat (Folding Door)
8 A.4.2.1.9 Sunscreen Allumunium
9 A.4.2.1.10 Memasang Rolling Door Allumunium
10 A.4.2.1.1 Memasang Kusen Pintu Allumunium

10 A.4.2.1.12 Memasang Pintu Allumunium Strip Lebar 8 cm

11 Memasang Pintu Kaca Rangka Allumunium


12 Memasang Venetions Blinds & Vertical Blinds
11 A.4.2.1.15 Memasang Terali Besi Strip (2x3) cm
12 A.4.2.1.16 Memasang Kawat Nyamuk
13 A.4.2.1.12 Memasang Jendela Nako & Tralis
13 A.4.2.1.18 Memasang Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm
Memasang Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30
14 A.4.2.1.19
Lebar 45 cm

XII A.4.6.2 PEKERJAAN KUNCI & KACA


1 A.4.6.2.2 Memasang Kunci Tanam Biasa
2 A.4.6.2.3 Memasang Kunci Kamar Mandi
3 A.4.6.2.4 Memasang Kunci Selinder
4 A.4.6.2.5 Memasang Engsel Pintu
5 A.4.6.2.6 Pasang Engsel Jendela Kupu-kupu
6 A.4.6.2.7 Pasang Engsel Angin
7 A.4.6.2.9 Pasang Kait Angin
8 A.4.6.2.10 Pasang Door Closer

HSPK Cipta Karya_2016P Page 100 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

9 A.4.6.2.11 Pasang Kunci Selot


10 A.4.6.2.13 Pasang Door Stop
11 A.4.6.2.14 Pasang Rel Pintu Dorong
12 A.4.6.2.15 Pasang Kunci Lemari
13 A.4.6.2.16 Pasang Kaca tebal 3 mm
14 A.4.6.2.17 Pasang Kaca tebal 5 mm
15 A.4.6.2.18 Pasang Kaca Cermin tebal 5 mm

XIII A.4.4.3 PEKERJAAN PENUTUP LANTAI & DINDING


1 A.4.4.3.3 Memasang lantai Ubin PC Abu-abu Uk. 20 x 20 cm
2 A.4.4.3.9 Memasang lantai Ubin Granito Uk. 40 x 40 cm
3 A.4.4.3.16 Pasang Plint Ubin PC Warna Uk. 10 x 20 cm
4 A.4.4.3.35 Memasang Lantai Keramik 30 x 30 cm
5 A.4.4.3.36 Pasang Lantai Keramik 20 x 20 cm
6 A.4.4.3.39 Memasang Plint Keramik Ukuran 10x20 cm
7 A.4.4.3.40 Memasang Plint Keramik Ukuran 10x10 cm
8 A.4.4.3.43 Memasang Lantai Marmer Ukuran 1.00x1.00 cm
9 A.4.4.3.44 Memasang Lantai Karpet
10 A.4.4.3.46 Memasang Lantai Parquet Jati
11 A.4.4.3.49 Memasang Dinding Keramik 10x20 cm,
12 A.4.4.3.50 Memasang Dinding Keramik 20x20 cm,
13 A.4.4.3.55 Memasang Dinding Marmer Ukuran 1.00x1.00 cm
14 A.4.4.3.58 Memasang Dinding Batu Paros / Batu Tempel Hitam
15 A.4.4.3.63 Memasang Plint Kayu Klas II Ukuran 2x10 cm

XIV A.4.7.1 PEKERJAAN PENGECATAN


1 A.4.7.1.1 Mengikis / Mengerok Permukaan Cat Tembok Lama
2 A.4.7.1.2 Mencuci Bidang Permukaan Tembok yang Pernah dicat
3 A.4.7.1.3 Mengerok Karat Cat Lama permukaan Baja dg cara manual

HSPK Cipta Karya_2016P Page 101 of 328 Harga Sat. Pekerjaan


NO. SNI URAIAN PEKERJAAN

Pengecatan Bidang Kayu Baru (1 lap.Plamir) 1 lap.Cat Dasar & 2


4 A.4.7.1.4
lap.Cat Penutup
Pengecatan Bidang Kayu Baru (1 lap.Plamir) 1 lap.Cat Dasar & 3
5 A.4.7.1.5
lap.Cat Penutup
6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil
7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur
8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter
9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis
Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat
10 A.4.7.1.10
Penutup)
11 A.4.7.1.11 Pengecat Tembok Lama (1lap.Plamir, 2lap Cat Penutup)
12 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi
13 A.4.7.1.17 Pengecatan Permukaan Baja dg Meni Besi & Perancah

HSPK Cipta Karya_2016P Page 102 of 328 Harga Sat. Pekerjaan


ERJAAN
G KABUPATEN PEMALANG
7

HARGA SATUAN
SATUAN
(Rp)

m' 639,783.65
m' 146,220.80
m2 960,715.80
m2 779,531.50
m2 8,250.00
m2 211,704.90
m3 703,989.00
m3 332,194.50

m3 38,775.00
m3 47,520.00
m3 56,397.00
m3 51,612.00
m3 78,210.00
m3 62,370.00
m2 2,805.00
m3 16,995.00
m3
m3 28,050.00
m3 134,706.00
m3 187,184.80
m2 51,315.00
m3 223,113.00

HSPK Cipta Karya_2016P Page 103 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

m3 801,944.00
m3 764,423.00
m3 738,386.00
m3 720,093.00
m3 694,991.00
m3 581,306.00
m3 660,605.00
m3 633,809.00
m3 410,464.56

m3 2,077,411.60

m3 765,404.20

m2 251,916.50

m2 242,171.05

m2 235,025.45

m2 232,185.80

m2 233,029.50

m2 219,985.92

m2 122,073.05

m2 117,109.63

m2 114,460.50

HSPK Cipta Karya_2016P Page 104 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

m2 112,806.32

m2 112,231.68

m2 110,313.50

m2 110,555.50

m2 49,543.30
m2 44,268.58
m2 42,125.42
m2 40,547.76
m2 39,809.62
m2 39,152.78
m2 38,841.26
m2 38,529.74
m2 38,586.24
m2 45,550.79
m2 33,264.00
m2 34,144.00
m2 59,244.77
m2 48,863.23
m2 54,195.68
m2 53,299.49
m2 52,335.71
m2 47,124.00
m2 26,510.62
m' 37,295.50
m2 29,863.68
m2 17,157.49

HSPK Cipta Karya_2016P Page 105 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

m2 8,221.40
m2 37,499.66
m2 21,716.75

m3 25,883,687.50

m3 11,588,087.50

m2 454,074.50

m2 629,860.00

m2 435,600.00

m2 1,826,000.00

m2 500,333.90

m2 532,772.90

m2 1,654,669.50

m2 905,628.90

m2 566,212.90

m3 10,513,778.00

m3 28,275,148.00

m3 10,042,780.00
m2 161,881.50
m2 191,680.50
m2 133,859.00
m2 164,554.50
m2 170,920.75

HSPK Cipta Karya_2016P Page 106 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

m' 282,623.00
m' 119,146.50

m2 274,587.50

m2 350,564.50

m2 339,163.00

m2 70,995.00

m2 117,447.44

m3 825,358.44

m3 852,324.93

m3 873,547.61

m3 783,562.64

m3 898,424.07

m3 922,647.30

m3 960,813.45

m3 973,112.79

m3 994,643.34

m3 1,001,193.69

m3 1,055,413.04

m3 1,064,162.58

10 Kg 112,926.00

HSPK Cipta Karya_2016P Page 107 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

10 Kg 163,878.00
1 Kg 177,820.50
m2 133,716.00
m2 143,891.00
m2 346,615.50
m2 366,745.50
m2 449,575.50
m2 409,755.50
m2 325,468.00
m2 86,955.00
m3 3,279,265.00
m3 4,015,594.00
m3 7,477,899.00
m3 5,907,550.00
m3 5,558,454.00
m3 5,457,936.00
m3 5,387,129.00
m' 57,198.90
m' 78,769.35

m2 83,556.00
m2 104,181.00
m2 51,711.00
m' 81,092.00
m' 95,942.00
m' 78,892.00
m2 73,088.40
m2 72,626.40
m2 42,040.90
m2 36,214.20
m2 65,448.90

HSPK Cipta Karya_2016P Page 108 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

m2 89,221.00
m' 82,023.70
m' 48,546.30
m2 58,108.60
m' 25,203.20
m2 18,877.50

m2 28,636.30
m2 88,379.50
m2 99,401.50
m2 42,885.15
m2 463,466.30
m2 37,009.72
m' 10,607.30

Unit 1,958,030.80
Unit 414,744.00
Unit 546,084.00
Unit 863,929.00
Unit 1,129,540.00
m' 131,252.00
m' 550,140.47
m' 14,513.26
m' 30,129.37
m' 53,389.88
Buah 385,264.00
Buah 27,434.00
Buah 27,995.00

HSPK Cipta Karya_2016P Page 109 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

Kg 26,923.60
kg 25,234.00
100 kg 81,961.00
m2 840,213.00
10cm 17,989.95
m2 515,416.00
m2 440,176.00
m2 362,054.00
m2 537,900.00
m' 123,363.90

m2 554,825.70

m2 -
m2 -
m2 352,663.50
m2 80,132.84
m2 -
m' 178,061.95
m' 76,062.80

Buah 177,485.0
Buah 88,742.5
Buah 176,742.5
Buah 19,827.5
Buah 13,145.0
Buah 22,440.0
Buah 21,692.0
Buah 62,370.00

HSPK Cipta Karya_2016P Page 110 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

Buah 22,946.00
Buah 31,218.00
Buah 266,728.00
Buah 24,970.00
m2 110,660.00
m2 126,753.00
m2 314,182.00

m2 94,646.20
m2 179,694.50
m' 45,839.86
m2 160,175.60
m2 191,224.00
m' 20,198.31
m' 20,564.06
m2 631,338.51
m2 177,930.50
m2 348,942.00
m2 199,872.20
m2 186,855.90
m2 728,548.15
m2 239,973.25
m' 43,923.00

m2 8,288.50
m2 8,305.00
m2 8,305.00

HSPK Cipta Karya_2016P Page 111 of 328 Harga Sat. Pekerjaan


HARGA SATUAN
SATUAN
(Rp)

m2 36,570.60

m2 47,873.10

m2 26,697.00
m2 43,972.94
m2 7,642.53
m2 25,905.00

m2 16,587.56

m2 10,439.88
m2 18,146.70
m2 36,439.70

HSPK Cipta Karya_2016P Page 112 of 328 Harga Sat. Pekerjaan


DAFTAR ANALISA PEKERJAAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN P
TAHUN ANGGARAN 2017

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

I A.2.2.1 PEKERJAAN PERSIAPAN

A.2.2.1.2 6.2 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m

6.2.1 Bahan
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm
2.5 Kg Portalnd Semen
1.2 Lbr Seng Gelombang 3" - 5"
0.005 m3 Pasir Beton
0.009 m3 Koral Beton
0.072 m3 Kayu 5/7X4m Kayu Kruing
0.06 Kg Paku Biasa 2" - 5"
0.45 Kg Meni Besi

6.2.2 Tenaga
0.2 OH Tukang Kayu
0.4 OH Pekerja
0.02 OH Kepala Tukang
0.02 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.2.2.1.4 6.4 1 m' Pengukuran dan Pemasangan Bouwplank

6.4.1 Bahan
0.012 m3 Kayu 5/7x 4m Kayu Kruing
0.02 Kg Paku Biasa 2" - 5"
0.007 m3 Kayu Papan 3/20 Kruing

6.4.2 Tenaga

HSPK Cipta Karya_2016P Page 113 of 328 Analisa Pek. Persiapan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.1 OH Tukang Kayu


0.1 OH Pekerja
0.01 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.2.2.1.5 6.5 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran

6.5.1 Bahan
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m
0.18 m3 Kayu
0.85 Kg Paku Biasa 2" - 5"
1.1 Kg Besi Strip
35 Kg Portland Sement
0.15 m3 Pasir pasang
0.1 m3 Pasir Beton
0.15 m3 Koral Beton
30 buah Batu bata Merah
0.25 Lbr Seng Plat
2 buah Jendela Naco
0.08 m2 Kaca Polos
0.15 buah Kunci Tanam
0.3 buah Engsel
0.06 Lbr Plywood 4 mm

6.5.2 Tenaga
2 OH Tukang Kayu
1 OH Tukang Batu
2 OH Pekerja
0.3 OH Kepala Tukang
0.05 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 114 of 328 Analisa Pek. Persiapan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.2.2.1.7 6.6 1 m2 Pembuatan Gudang Semen dan Alat-alat

6.6.1 Bahan
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm
0.21 m3 Kayu
0.3 Kg Paku Biasa 2" - 5"
10.5 Kg Portland Semen
0.03 m3 Pasir Beton
0.05 m3 Koral Beton
1.5 Lbr Seng Gelombang BJLS 32

6.6.2 Tenaga
2 OH Tukang Kayu
1 OH Pekerja
0.2 OH Kepala Tukang
0.05 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.2.2.1.9 6.8 1 m2 Membersihkan Lapangan dan Perataan

6.8.2 Tenaga
0.1 OH Pekerja
0.05 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.2.1.10 6.11 1 m2 Pembuatan Steger dari Bambu Uk. 40 x 50 x 20 cm

6.11.1 Bahan
1.25 Btg Bambu diameter 6 - 8 / 600 cm
0.186 Kg Tali Ijuk

6.11.2 Tenaga
2.00 OH Tukang Kayu

HSPK Cipta Karya_2016P Page 115 of 328 Analisa Pek. Persiapan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1.00 OH Pekerja
0.200 OH Kepala Tukang
0.0500 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.2.2.1.13 6.13 1 m3 Bongkaran Beton Bertulang

6.13.2 Tenaga
13.334 OH Pekerja
0.666 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.2.1.14 6.14 1 m3 Bongkaran Dinding Tembok Bata Merah

6.14.2 Tenaga
6.667 OH Pekerja
0.033 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 116 of 328 Analisa Pek. Persiapan


SA PEKERJAAN
AAN RUANG KABUPATEN PEMALANG
GARAN 2017

HARGA JUMLAH
PAKERJAAN BAHAN/UPAH HARGA
Rp Rp

ng Gelombang Tinggi 2,00 m 639,783.65

549,221.50
23,400.00 29,250.00
1,090.00 2,725.00
61,200.00 73,440.00
322,500.00 1,612.50
244,000.00 2,196.00
6,100,000.00 439,200.00
13,300.00 798.00
25,600.00 11,520.00

32,400.00
60,000.00 12,000.00
45,000.00 18,000.00
60,000.00 1,200.00
60,000.00 1,200.00

581,621.50
58,162.15
639,783.65

ngan Bouwplank 146,220.80

121,528.00
6,100,000.00 73,200.00
13,300.00 266.00
6,866,000.00 48,062.00

11,400.00

HSPK Cipta Karya_2016P Page 117 of 328 Analisa Pek. Persiapan


HARGA JUMLAH
PAKERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 6,000.00
45,000.00 4,500.00
60,000.00 600.00
60,000.00 300.00

132,928.00
13,292.80
146,220.80

ntara dg Lantai Plesteran 960,715.80

582,378.00
23,400.00 29,250.00
1,725,000.00 310,500.00
13,300.00 11,305.00
13,200.00 14,520.00
1,090.00 38,150.00
240,000.00 36,000.00
322,500.00 32,250.00
244,000.00 36,600.00
860.00 25,800.00
17,500.00 4,375.00
11,000.00 22,000.00
81,800.00 6,544.00
65,800.00 9,870.00
4,600.00 1,380.00
63,900.00 3,834.00

291,000.00
60,000.00 120,000.00
60,000.00 60,000.00
45,000.00 90,000.00
60,000.00 18,000.00
60,000.00 3,000.00

873,378.00
87,337.80
960,715.80

HSPK Cipta Karya_2016P Page 118 of 328 Analisa Pek. Persiapan


HARGA JUMLAH
PAKERJAAN BAHAN/UPAH HARGA
Rp Rp

en dan Alat-alat 779,531.50

528,665.00
23,400.00 39,780.00
1,725,000.00 362,250.00
13,300.00 3,990.00
1,090.00 11,445.00
240,000.00 7,200.00
244,000.00 12,200.00
61,200.00 91,800.00

180,000.00
60,000.00 120,000.00
45,000.00 45,000.00
60,000.00 12,000.00
60,000.00 3,000.00

708,665.00
70,866.50
779,531.50

dan Perataan 8,250.00

7,500.00
45,000.00 4,500.00
60,000.00 3,000.00

7,500.00
750.00
8,250.00

ambu Uk. 40 x 50 x 20 cm 211,704.90

12,459.00
9,000.00 11,250.00
6,500.00 1,209.00

180,000.00
60,000.00 120,000.00

HSPK Cipta Karya_2016P Page 119 of 328 Analisa Pek. Persiapan


HARGA JUMLAH
PAKERJAAN BAHAN/UPAH HARGA
Rp Rp

45,000.00 45,000.00
60,000.00 12,000.00
60,000.00 3,000.00

192,459.00
19,245.90
211,704.90

703,989.00

639,990.00
45,000.00 600,030.00
60,000.00 39,960.00

639,990.00
63,999.00
703,989.00

ok Bata Merah 332,194.50

301,995.00
45,000.00 300,015.00
60,000.00 1,980.00

301,995.00
30,199.50
332,194.50

HSPK Cipta Karya_2016P Page 120 of 328 Analisa Pek. Persiapan


0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

II A.2.3.1 PEKERJAAN TANAH

A.2.3.1.1 6.1 1 m3 Menggali Tanah Biasa Sedalam 1 m

6.1.2 Tenaga
0.75 OH Pekerja
0.025 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.2 6.2 1 m3 Menggali Tanah Biasa Sedalam 2 m

6.2.2 Tenaga
0.90 OH Pekerja
0.045 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.3 6.3 1 m3 Menggali Tanah Biasa Sedalam 3 m

6.3.2 Tenaga
1.05 OH Pekerja
0.067 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.4 6.4 1 m3 Menggali Tanah Keras Sedalam 1 m

6.4.2 Tenaga
1.000 OH Pekerja
0.032 OH Mandor

HSPK Cipta Karya_2016P


Page 121 of 328 Analisa Pek. Tanah
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

II A.2.3.1 PEKERJAAN TANAH


Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.5 6.5 1 m3 Menggali Tanah Cadas Sedalam 1 m

6.5.2 Tenaga
1.50 OH Pekerja
0.060 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.6 6.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m

6.6.2 Tenaga
1.200 OH Pekerja
0.045 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.7 6.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m

6.7.2 Tenaga
0.05 OH Pekerja
0.005 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total
HSPK Cipta Karya_2016P
Page 122 of 328 Analisa Pek. Tanah
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

II A.2.3.1 PEKERJAAN TANAH

A.2.3.1.8 6.8 1 m3 Membuang Tanah sejauh 30 m'

6.8.2 Tenaga
0.330 OH Pekerja
0.010 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.9 6.9 1 m3 Urugan Kembali (dihitung 1/3 kali indeks pekerjaan galia

Tenaga
0.500 OH Pekerja
0.050 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.10 6.10 1 m3 Pemadatan Tanah (per 20 cm)

6.10.2 Tenaga
0.5 OH Pekerja
0.05 OH Mandor

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

A.2.3.1.11 6.11 1 m3 Urugan Pasir

6.11.1 Bahan
1.2 m3 Pasir Urug

HSPK Cipta Karya_2016P


Page 123 of 328 Analisa Pek. Tanah
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

II A.2.3.1 PEKERJAAN TANAH

6.11.2 Tenaga
0.3 OH Pekerja
0.01 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.2.3.1.12 6.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL

6.12.1 Bahan
0.135 m3 Pasir Pasang
0.400 m3 Kapur Padam
0.080 m3 Tanah Liat

6.12.2 Tenaga
0.800 OH Pekerja
0.400 OH Tukang Batu
0.04 OH Kepala Tukang
0.080 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.2.3.1.13 6.14 1 m2 Pemasangan Lapisan Ijuk tebal 10 cm

6.14.1 Bahan
6.0 kg Ijuk

6.14.2 Tenaga
0.15 OH Pekerja
0.015 OH Mandor

HSPK Cipta Karya_2016P


Page 124 of 328 Analisa Pek. Tanah
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

II A.2.3.1 PEKERJAAN TANAH

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.2.3.1.14 6.15 1 m3 Mengurug Sirtu

6.15.1 Bahan
1.2 m3 Sirtu

6.15.2 Tenaga
0.25 OH Pekerja
0.025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P


Page 125 of 328 Analisa Pek. Tanah
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

38,775.00

35,250.00
45,000.00 33,750.00
60,000.00 1,500.00

35,250.00
3,525.00
38,775.00

47,520.00

43,200.00
45,000.00 40,500.00
60,000.00 2,700.00

43,200.00
4,320.00
47,520.00

56,397.00

51,270.00
45,000.00 47,250.00
60,000.00 4,020.00

51,270.00
5,127.00
56,397.00

51,612.00

46,920.00
45,000.00 45,000.00
60,000.00 1,920.00

HSPK Cipta Karya_2016P


Page 126 of 328 Analisa Pek. Tanah
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

46,920.00
4,692.00
51,612.00

78,210.00

71,100.00
45,000.00 67,500.00
60,000.00 3,600.00

71,100.00
7,110.00
78,210.00

Sedalam 1 m 62,370.00

56,700.00
45,000.00 54,000.00
60,000.00 2,700.00

56,700.00
5,670.00
62,370.00

ing Setinggi 1 m 2,805.00

2,550.00
45,000.00 2,250.00
60,000.00 300.00

2,550.00
255.00
2,805.00
HSPK Cipta Karya_2016P
Page 127 of 328 Analisa Pek. Tanah
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

16,995.00

15,450.00
45,000.00 14,850.00
60,000.00 600.00

15,450.00
1,545.00
16,995.00

1/3 kali indeks pekerjaan galian) 9,350.00

25,500.00
45,000.00 22,500.00
60,000.00 3,000.00

25,500.00
2,550.00
28,050.00

28,050.00

25,500.00
45,000.00 22,500.00
60,000.00 3,000.00

25,500.00
2,550.00
28,050.00

134,706.00

108,360.00
90,300.00 108,360.00

HSPK Cipta Karya_2016P


Page 128 of 328 Analisa Pek. Tanah
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

14,100.00
45,000.00 13,500.00
60,000.00 600.00

122,460.00
12,246.00
134,706.00

187,184.80

102,968.00
240,000.00 32,400.00
160,000.00 64,000.00
82,100.00 6,568.00

67,200.00
45,000.00 36,000.00
60,000.00 24,000.00
60,000.00 2,400.00
60,000.00 4,800.00

170,168.00
17,016.80
187,184.80

tebal 10 cm 51,315.00

6,500.00 39,000.00
6,500.00 39,000.00

7,650.00
45,000.00 6,750.00
60,000.00 900.00

HSPK Cipta Karya_2016P


Page 129 of 328 Analisa Pek. Tanah
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

46,650.00
4,665.00
51,315.00

223,113.00

190,080.00
158,400.00 190,080.00

12,750.00
45,000.00 11,250.00
60,000.00 1,500.00

202,830.00
20,283.00
223,113.00

HSPK Cipta Karya_2016P


Page 130 of 328 Analisa Pek. Tanah
0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

III A.3.2.1 PEKERJAAN PONDASI

A.3.2.1.1 1 m3 Memasang Pondasi Batu Kali 1Pc : 3 PP

Bahan
1.2 m3 Batu Belah 15/20
202 Kg Portland Sement
0.485 m3 Pasir Pasang

Tenaga
1.5 OH Pekerja
0.750 OH Tukang Batu
0.075 OH Kepala Tukang
0.075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.3.2.1.2 1 m3 Memasang Pondasi Batu Kali 1Pc : 4 PP

Bahan
1.2 m3 Batu Belah 15/20
163 Kg Portland Sement
0.52 m3 Pasir Pasang

Tenaga
1.5 OH Pekerja
0.750 OH Tukang Batu
0.075 OH Kepala Tukang
0.075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.3.2.1.3 1 m3 Memasang Pondasi Batu Kali 1Pc : 5 PP

HSPK Cipta Karya_2016P


Page 131 of 328 Analisa Pek. Pondasi
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
1.2 m3 Batu Belah 15/20
136 Kg Portland Sement
0.544 m3 Pasir Pasang

Tenaga
1.5 OH Pekerja
0.750 OH Tukang Batu
0.075 OH Kepala Tukang
0.075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.3.2.1.4 1 m3 Memasang Pondasi Batu Kali 1Pc : 6 PP

Bahan
1.2 m3 Batu Belah 15/20
117 Kg Portland Sement
0.561 m3 Pasir Pasang

Tenaga
1.5 OH Pekerja
0.750 OH Tukang Batu
0.075 OH Kepala Tukang
0.075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.3.2.1.5 1 m3 Memasang Pondasi Batu Kali 1Pc : 8 PP

Bahan
1.2 m3 Batu Belah 15/20
91 Kg Portland Sement
0.584 m3 Pasir Pasang

Tenaga

HSPK Cipta Karya_2016P


Page 132 of 328 Analisa Pek. Pondasi
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1.5 OH Pekerja
0.750 OH Tukang Batu
0.075 OH Kepala Tukang
0.075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total
A.3.2.1.6 1 m3 Memasang Pondasi Batu Kali 1Kp : 1Sm : 2Pp

Bahan
1.2 m3 Batu Belah 15/20
0.17 m3 Kapur Pasang (KP)
0.17 Kg Semen Merah (SM)
0.340 m3 Pasir Pasang

Tenaga
1.5 OH Pekerja
0.750 OH Tukang Batu
0.075 OH Kepala Tukang
0.075 OH Mandor
Jumlah Bahan dan Tenaga
Overhead + Profit 10%
Jumlah Total

A.3.2.1.7 1 m3 Memasang Pondasi Batu Kali, 1 Pc : 3 Kp : 10 PP

Bahan
1.2 m3 Batu Belah 15/20
61 kg Portland Sement
0.147 m3 Kapur Pasang
0.492 m3 Pasir

Tenaga
. 1.5 OH Pekerja
0.750 OH Tukang Batu
0.075 OH Kepala Tukang
0.075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P


Page 133 of 328 Analisa Pek. Pondasi
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

A.3.2.1.8 1 m3 Memasang Pondasi Batu Kali, ¼ Pc : 1Kp : 4 PP

Bahan
1.2 m3 Batu Belah 15/20
41 kg Portland Sement
0.131 m3 Kapur Pasang
0.492 m3 Pasir

Tenaga
. 1.5 OH Pekerja
0.750 OH Tukang Batu
0.075 OH Kepala Tukang
0.075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.3.2.1.9 1 m3 Pasang Pondasi Batu Kosong

Bahan
1.2 m3 Batu Belah 15/20
0.432 m3 Pasir Urug

Tenaga
. 0.78 OH Pekerja
0.39 OH Tukang Batu
0.039 OH Kepala Tukang
0.039 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

1 m3 Pasang Pondasi Siklop, 60% Beton Camp.


A.3.2.1.10 1PC : 2PB : 3KR & 40% Batu Belah

Bahan

HSPK Cipta Karya_2016P


Page 134 of 328 Analisa Pek. Pondasi
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.480 m3 Batu Belah 15/20 cm


126 Kg Besi Beton
194 Kg Portland Semen
0.312 m3 Pasir Beton
0.468 m3 Koral Beton
1.8 Kg Kawat Beton

Tenaga
3.4 OH Pekerja
0.85 OH Tukang Batu
0.085 OH Kepala Tukang
0.15 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm

Bahan
0.45 m3 Batu Belah 15/20 cm
194 Kg Portland Semen
0.312 m3 Pasir Beton
0.468 m3 Koral Beton

Tenaga
2.40 OH Pekerja
0.8 OH Tukang Batu
0.08 OH Kepala Tukang
0.119 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P


Page 135 of 328 Analisa Pek. Pondasi
HARGA JUMLAH
RJAAN BAHAN/UPAH HARGA
Rp Rp

li 1Pc : 3 PP 801,944.00

607,540.00
225,800.00 270,960.00
1,090.00 220,180.00
240,000.00 116,400.00

121,500.00
45,000.00 67,500.00
60,000.00 45,000.00
60,000.00 4,500.00
60,000.00 4,500.00

729,040.00
72,904.00
801,944.00

li 1Pc : 4 PP 764,423.00

573,430.00
225,800.00 270,960.00
1,090.00 177,670.00
240,000.00 124,800.00

121,500.00
45,000.00 67,500.00
60,000.00 45,000.00
60,000.00 4,500.00
60,000.00 4,500.00

694,930.00
69,493.00
764,423.00

li 1Pc : 5 PP 738,386.00

HSPK Cipta Karya_2016P


Page 136 of 328 Analisa Pek. Pondasi
HARGA JUMLAH
RJAAN BAHAN/UPAH HARGA
Rp Rp

549,760.00
225,800.00 270,960.00
1,090.00 148,240.00
240,000.00 130,560.00

121,500.00
45,000.00 67,500.00
60,000.00 45,000.00
60,000.00 4,500.00
60,000.00 4,500.00

671,260.00
67,126.00
738,386.00

li 1Pc : 6 PP 720,093.00

533,130.00
225,800.00 270,960.00
1,090.00 127,530.00
240,000.00 134,640.00

121,500.00
45,000.00 67,500.00
60,000.00 45,000.00
60,000.00 4,500.00
60,000.00 4,500.00

654,630.00
65,463.00
720,093.00

li 1Pc : 8 PP 694,991.00

510,310.00
225,800.00 270,960.00
1,090.00 99,190.00
240,000.00 140,160.00

121,500.00

HSPK Cipta Karya_2016P


Page 137 of 328 Analisa Pek. Pondasi
HARGA JUMLAH
RJAAN BAHAN/UPAH HARGA
Rp Rp

45,000.00 67,500.00
60,000.00 45,000.00
60,000.00 4,500.00
60,000.00 4,500.00

631,810.00
63,181.00
694,991.00
li 1Kp : 1Sm : 2Pp 581,306.00

406,960.00
225,800.00 270,960.00
160,000.00 27,200.00
160,000.00 27,200.00
240,000.00 81,600.00

121,500.00
45,000.00 67,500.00
60,000.00 45,000.00
60,000.00 4,500.00
60,000.00 4,500.00
528,460.00
52,846.00
581,306.00

li, 1 Pc : 3 Kp : 10 PP 660,605.00

479,050.00
225,800.00 270,960.00
1,090.00 66,490.00
160,000.00 23,520.00
240,000.00 118,080.00

121,500.00
45,000.00 67,500.00
60,000.00 45,000.00
60,000.00 4,500.00
60,000.00 4,500.00

600,550.00
60,055.00

HSPK Cipta Karya_2016P


Page 138 of 328 Analisa Pek. Pondasi
HARGA JUMLAH
RJAAN BAHAN/UPAH HARGA
Rp Rp

660,605.00

li, ¼ Pc : 1Kp : 4 PP 633,809.00

454,690.00
225,800.00 270,960.00
1,090.00 44,690.00
160,000.00 20,960.00
240,000.00 118,080.00

121,500.00
45,000.00 67,500.00
60,000.00 45,000.00
60,000.00 4,500.00
60,000.00 4,500.00

576,190.00
57,619.00
633,809.00

410,464.56

309,969.60
225,800.00 270,960.00
90,300.00 39,009.60

63,180.00
45,000.00 35,100.00
60,000.00 23,400.00
60,000.00 2,340.00
60,000.00 2,340.00

373,149.60
37,314.96
410,464.56

% Beton Camp.
u Belah 2,077,411.60

1,670,456.00

HSPK Cipta Karya_2016P


Page 139 of 328 Analisa Pek. Pondasi
HARGA JUMLAH
RJAAN BAHAN/UPAH HARGA
Rp Rp

225,800.00 108,384.00
8,800.00 1,108,800.00
1,090.00 211,460.00
322,500.00 100,620.00
244,000.00 114,192.00
15,000.00 27,000.00

218,100.00
45,000.00 153,000.00
60,000.00 51,000.00
60,000.00 5,100.00
60,000.00 9,000.00

1,888,556.00
188,855.60
2,077,411.60

iameter 100 cm 765,404.20

527,882.00
225,800.00 101,610.00
1,090.00 211,460.00
322,500.00 100,620.00
244,000.00 114,192.00

167,940.00
45,000.00 108,000.00
60,000.00 48,000.00
60,000.00 4,800.00
60,000.00 7,140.00

695,822.00
69,582.20
765,404.20

HSPK Cipta Karya_2016P


Page 140 of 328 Analisa Pek. Pondasi
0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

IV A.4.4.1 P E K E R JAAN DINDING

A.4.4.1.1 1 m2 Memasang Dinding Bata Merah ukuran (5x11x22)


cm Tebal 1 bata Camp. 1Pc : 2Pp

Bahan
140 Buah Bata Merah
43.5 Kg Portland Semen (PC)
0.08 m3 Pasir Pasang (PP)

Tenaga
0.6 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.03 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.1.2 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)


cm Tebal 1 Bata Camp. 1Pc : 3PP

Bahan
140 Buah Bata Merah
32.95 Kg Portland Semen (PC)
0.091 m3 Pasir Pasang (PP)

Tenaga
0.6 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.03 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 141 of 328 Analisa Pek. Dinding


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.4.1.3 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)


cm Tebal 1 Bata Camp. 1Pc : 4PP

Bahan
140 Buah Bata Merah
26.55 Kg Portland Semen (PC)
0.093 m3 Pasir Pasang (PP)

Tenaga
0.6 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.03 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.1.4 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)


cm Tebal 1 Bata Camp. 1Pc : 5PP

Bahan
140 Buah Bata Merah
22.2 Kg Portland Semen (PC)
0.102 m3 Pasir Pasang (PP)

Tenaga
0.6 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.03 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.1.5 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)


cm Tebal 1 Bata Camp. 1Pc : 6PP

HSPK Cipta Karya_2016P Page 142 of 328 Analisa Pek. Dinding


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
140 Buah Bata Merah
18.5 Kg Portland Semen (PC)
0.122 m3 Pasir Pasang (PP)

Tenaga
0.6 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.03 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.1.6 1 m2 Memasang Dinding Bata Merah Ukuran (5x11x22)


cm Tebal 1 Bata Camp. 1Pc : 3 KP :10PP

Bahan
140 Buah Bata Merah
10.08 Kg Portland Semen (PC)
0.0925 m3 Pasir Pasang (PP)
0.0275 m3 Kapur Pasang (KP)

Tenaga
0.6 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.03 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 143 of 328 Analisa Pek. Dinding


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.4.1.7 1 m2 Memasang Dinding Bata Merah Ukuran


(5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 2PP

Bahan
70 Buah Bata Merah 5 x 11 x 22
18.95 Kg Portland Semen
0.038 m3 Pasir Pasang

Tenaga
0.30 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.1.8 1 m2 Memasang Dinding Bata Merah Ukuran


(5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 3PP

Bahan
70 Buah Bata Merah 5 x 11 x 22
14.37 Kg Portland Semen
0.04 m3 Pasir Pasang

Tenaga
0.30 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga

HSPK Cipta Karya_2016P Page 144 of 328 Analisa Pek. Dinding


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Overhead + Profit 10%


Jumlah Total

A.4.4.1.9 1 m2 Memasang Dinding Bata Merah Ukuran


(5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 4PP

Bahan
70 Buah Bata Merah 5 x 11 x 22
11.50 Kg Portland Semen
0.043 m3 Pasir Pasang

Tenaga
0.30 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.1.10 1 m2 Memasang Dinding Bata Merah Ukuran


(5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 5PP

Bahan
70 Buah Bata Merah 5 x 11 x 22
9.68 Kg Portland Semen
0.045 m3 Pasir Pasang

Tenaga
0.30 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 145 of 328 Analisa Pek. Dinding


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.4.1.11 1 m2 Memasang Dinding Bata Merah Ukuran


(5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 6PP

Bahan
70 Buah Bata Merah 5 x 11 x 22
8.32 Kg Portland Semen
0.049 m3 Pasir Pasang

Tenaga
0.30 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.1.12 1 m2 Memasang Dinding Bata Merah Ukuran


(5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 8PP

Bahan
70 Buah Bata Merah 5 x 11 x 22
6.50 Kg Portland Semen
0.05 m3 Pasir Pasang

Tenaga
0.30 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.1.13 1 m2 Memasang Dinding Bata Merah Ukuran


(5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 3KP :
10PP

HSPK Cipta Karya_2016P Page 146 of 328 Analisa Pek. Dinding


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
70 Buah Bata Merah 5 x 11 x 22
4.5 Kg Portland Semen
0.05 m3 Pasir Pasang
0.015 m3 Kapur Padam

Tenaga
0.30 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 147 of 328 Analisa Pek. Dinding


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

251,916.50

187,015.00
860.00 120,400.00
1,090.00 47,415.00
240,000.00 19,200.00

42,000.00
45,000.00 27,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,800.00

229,015.00
22,901.50
251,916.50

242,171.05

178,155.50
860.00 120,400.00
1,090.00 35,915.50
240,000.00 21,840.00

42,000.00
45,000.00 27,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,800.00

220,155.50
22,015.55
242,171.05

HSPK Cipta Karya_2016P Page 148 of 328 Analisa Pek. Dinding


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

235,025.45

171,659.50
860.00 120,400.00
1,090.00 28,939.50
240,000.00 22,320.00

42,000.00
45,000.00 27,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,800.00

213,659.50
21,365.95
235,025.45

232,185.80

169,078.00
860.00 120,400.00
1,090.00 24,198.00
240,000.00 24,480.00

42,000.00
45,000.00 27,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,800.00

211,078.00
21,107.80
232,185.80

233,029.50

HSPK Cipta Karya_2016P Page 149 of 328 Analisa Pek. Dinding


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

169,845.00
860.00 120,400.00
1,090.00 20,165.00
240,000.00 29,280.00

42,000.00
45,000.00 27,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,800.00

211,845.00
21,184.50
233,029.50

219,985.92

157,987.20
860.00 120,400.00
1,090.00 10,987.20
240,000.00 22,200.00
160,000.00 4,400.00

42,000.00
45,000.00 27,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,800.00

199,987.20
19,998.72
219,985.92

HSPK Cipta Karya_2016P Page 150 of 328 Analisa Pek. Dinding


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

122,073.05

89,975.50
860.00 60,200.00
1,090.00 20,655.50
240,000.00 9,120.00

21,000.00
45,000.00 13,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 900.00

110,975.50
11,097.55
122,073.05

117,109.63

85,463.30
860.00 60,200.00
1,090.00 15,663.30
240,000.00 9,600.00

21,000.00
45,000.00 13,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 900.00

106,463.30

HSPK Cipta Karya_2016P Page 151 of 328 Analisa Pek. Dinding


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

10,646.33
117,109.63

114,460.50

83,055.00
860.00 60,200.00
1,090.00 12,535.00
240,000.00 10,320.00

21,000.00
45,000.00 13,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 900.00

104,055.00
10,405.50
114,460.50

112,806.32

81,551.20
860.00 60,200.00
1,090.00 10,551.20
240,000.00 10,800.00

21,000.00
45,000.00 13,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 900.00

102,551.20
10,255.12
112,806.32

HSPK Cipta Karya_2016P Page 152 of 328 Analisa Pek. Dinding


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

112,231.68

81,028.80
860.00 60,200.00
1,090.00 9,068.80
240,000.00 11,760.00

21,000.00
45,000.00 13,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 900.00

102,028.80
10,202.88
112,231.68

110,313.50

79,285.00
860.00 60,200.00
1,090.00 7,085.00
240,000.00 12,000.00

21,000.00
45,000.00 13,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 900.00

100,285.00
10,028.50
110,313.50

110,555.50

HSPK Cipta Karya_2016P Page 153 of 328 Analisa Pek. Dinding


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

79,505.00
860.00 60,200.00
1,090.00 4,905.00
240,000.00 12,000.00
160,000.00 2,400.00

21,000.00
45,000.00 13,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 900.00

100,505.00
10,050.50
110,555.50

HSPK Cipta Karya_2016P Page 154 of 328 Analisa Pek. Dinding


0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

V A.4.4.2 PEKERJAAN PLESTERAN

A.4.4.2.1 1 m2 Memasang Plesteran 1 Pc : 1 Pp Tebal 15 mm

Bahan
15.504 Kg Portland Semen
0.016 m3 Pasir Pasang

Tenaga
0.3 OH Pekerja
0.15 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.2 1 m2 Memasang Plesteran 1 Pc : 2 Pp Tebal 15 mm

Bahan
10.224 Kg Portland Semen
0.020 m3 Pasir Pasang

Tenaga
0.3 OH Pekerja
0.15 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.3 1 m2 Memasang Plesteran 1 Pc : 3 Pp Tebal 15 mm

Bahan

HSPK Cipta Karya_2016P Page 155 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

7.776 Kg Portland Semen


0.023 m3 Pasir Pasang

Tenaga
0.3 OH Pekerja
0.15 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.4 1 m2 Memasang Plesteran 1 Pc : 4 Pp Tebal 15 mm

Bahan
6.240 Kg Portland Semen
0.024 m3 Pasir Pasang

Tenaga
0.3 OH Pekerja
0.15 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.5 1 m2 Memasang Plesteran 1 Pc : 5 Pp Tebal 15 mm

Bahan
5.184 Kg Portland Semen
0.026 m3 Pasir Pasang

Tenaga
0.3 OH Pekerja
0.15 OH Tukang Batu

HSPK Cipta Karya_2016P Page 156 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.015 OH Kepala Tukang


0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.6 1 m2 Memasang Plesteran 1 Pc : 6 Pp Tebal 15 mm

Bahan
4.416 Kg Portland Semen
0.027 m3 Pasir Pasang

Tenaga
0.3 OH Pekerja
0.15 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.7 1 m2 Memasang Plesteran 1 Pc : 7 Pp Tebal 15 mm

Bahan
3.936 Kg Portland Semen
0.028 m3 Pasir Pasang

Tenaga
0.3 OH Pekerja
0.15 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 157 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.4.2.8 1 m2 Memasang Plesteran 1 Pc : 8 Pp Tebal 15 mm

Bahan
3.456 Kg Portland Semen
0.029 m3 Pasir Pasang

Tenaga
0.30 OH Pekerja
0.15 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.9 1 m2 Memasang Plesteran 1 Pc : 1/2 Kp : 3 Pp Tebal 15 mm

Bahan
5.760 Kg Portland Semen
0.003 m3 Kapur Pasang
0.013 m3 Pasir Pasang

Tenaga
0.36 OH Pekerja
0.12 OH Tukang Batu
0.012 OH Kepala Tukang
0.018 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.10 1 m2 Memasang Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm

Bahan
3 kg Portland Semen
0.005 m3 Kapur Pasang

HSPK Cipta Karya_2016P Page 158 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.020 m3 Pasir Pasang

Tenaga
0.36 OH Pekerja
0.12 OH Tukang Batu
0.012 OH Kepala Tukang
0.018 OH Mandor
\
Jumlah Bahan dan Tenaga
Overhead + Profit 10%
Jumlah Total

A.4.4.2.11 1 m2 Memasang Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm

Bahan
0.009 m3 Semen Merah
0.009 m3 Kapur Pasang
0.009 m3 Pasir Pasang

Tenaga
0.36 OH Pekerja
0.12 OH Tukang Batu
0.012 OH Kepala Tukang
0.018 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.12 1 m2 Memasang Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm

Bahan
0.007 m3 Semen Merah
0.007 m3 Kapur Pasang
0.015 m3 Pasir Pasang

HSPK Cipta Karya_2016P Page 159 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.36 OH Pekerja
0.12 OH Tukang Batu
0.012 OH Kepala Tukang
0.018 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.13 1 m2 Memasang Plesteran 1 Pc : 2 Pp Tebal 20 mm

Bahan
13.632 kg Portland Semen
0.027 m3 Pasir Pasang

Tenaga
0.40 OH Pekerja
0.20 OH Tukang Batu
0.020 OH Kepala Tukang
0.022 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.14 1 m2 Memasang Plesteran 1Pc : 3Pp Tebal 20 mm

Bahan
10.368 Kg Portland Semen
0.031 m3 Pasir Pasang

Tenaga
0.26 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.013 OH Mandor

HSPK Cipta Karya_2016P Page 160 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.15 1 m2 Memasang Plesteran 1 Pc : 4 Pp Tebal 20 mm

Bahan
8.320 kg Portland Semen
0.032 m3 Pasir Pasang

Tenaga
0.40 OH Pekerja
0.20 OH Tukang Batu
0.020 OH Kepala Tukang
0.022 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.16 1 m2 Memasang Plesteran 1Pc : 5Pp Tebal 20 mm

Bahan
6.912 Kg Portland Semen
0.035 m3 Pasir Pasang

Tenaga
0.400 OH Pekerja
0.200 OH Tukang Batu
0.020 OH Kepala Tukang
0.022 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.17 1 m2 Memasang Plesteran 1Pc : 6Pp Tebal 20 mm

HSPK Cipta Karya_2016P Page 161 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
5.888 Kg Portland Semen
0.036 m3 Pasir Pasang

Tenaga
0.40 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.022 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.18 1 m2 Memasang Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm

Bahan
0.009 m3 Semen Merah
0.009 m3 Kapur Pasang
0.018 m3 Pasir Pasang

Tenaga
0.440 OH Pekerja
0.22 OH Tukang Batu
0.022 OH Kepala Tukang
0.022 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.19 1 m2 Memasang Berapen 1 Pc : 5Pp Tebal 15 mm

Bahan
5.184 Kg Portland Semen

HSPK Cipta Karya_2016P Page 162 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.026 m3 Pasir Pasang

Tenaga
0.15 OH Pekerja
0.075 OH Tukang Batu
0.008 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.20 1 m' Memasang Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm

Bahan
0.5 Kg Portland Semen
0.013 m3 Pasir Pasang

Tenaga
0.080 OH Pekerja
0.40 OH Tukang Batu
0.040 OH Kepala Tukang
0.004 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.23 1 m2 Memasang Plesteran Ciprat 1Pc : 2 Pp

Bahan
4.32 Kg Portland Semen
0.006 m3 Pasir Pasang

Tenaga
0.30 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.015 OH Mandor

HSPK Cipta Karya_2016P Page 163 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

Memasang Finishing Siar Pasangan Dinding Bata


A.4.4.2.24 1 m2
Merah (=20 m')

Bahan
3.108 Kg Portland Semen

Tenaga
0.15 OH Pekerja
0.075 OH Tukang Batu
0.008 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.25 1 m2 Memasang Finishing Siar Pasangan Dinding


Conblock ekspose (=8 m')
Bahan
1.600 Kg Portland Semen

Tenaga
0.070 OH Pekerja
0.035 OH Tukang Batu
0.004 OH Kepala Tukang
0.004 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.26 1 m2 Memasang Finishing Siar Pas.Batu Kali Adukan 1Pc : 2P

Bahan

HSPK Cipta Karya_2016P Page 164 of 328 Analisa Pek. Plesteran


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

6.34 Kg Pc
0.012 m3 PP

Tenaga
0.3 OH Pekerja
0.15 OH Tukang Batu
0.015 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.2.27 1 m2 Memasang Acian

Bahan
3.25 Kg Portland Semen

Tenaga
0.20 OH Pekerja
0.10 OH Tukang Batu
0.010 OH Kepala Tukang
0.010 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 165 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

: 1 Pp Tebal 15 mm 49,543.30

20,739.36
1,090.00 16,899.36
240,000.00 3,840.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 900.00

45,039.36
4,503.94
49,543.30

: 2 Pp Tebal 15 mm 44,268.58

15,944.16
1,090.00 11,144.16
240,000.00 4,800.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 900.00

40,244.16
4,024.42
44,268.58

: 3 Pp Tebal 15 mm 42,125.42

13,995.84

HSPK Cipta Karya_2016P Page 166 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

1,090.00 8,475.84
240,000.00 5,520.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 900.00

38,295.84
3,829.58
42,125.42

: 4 Pp Tebal 15 mm 40,547.76

12,561.60
1,090.00 6,801.60
240,000.00 5,760.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 900.00

36,861.60
3,686.16
40,547.76

: 5 Pp Tebal 15 mm 39,809.62

11,890.56
1,090.00 5,650.56
240,000.00 6,240.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00

HSPK Cipta Karya_2016P Page 167 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 900.00
60,000.00 900.00

36,190.56
3,619.06
39,809.62

: 6 Pp Tebal 15 mm 39,152.78

11,293.44
1,090.00 4,813.44
240,000.00 6,480.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 900.00

35,593.44
3,559.34
39,152.78

: 7 Pp Tebal 15 mm 38,841.26

11,010.24
1,090.00 4,290.24
240,000.00 6,720.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 900.00

35,310.24
3,531.02
38,841.26

HSPK Cipta Karya_2016P Page 168 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

: 8 Pp Tebal 15 mm 38,529.74

10,727.04
1,090.00 3,767.04
240,000.00 6,960.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 900.00

35,027.04
3,502.70
38,529.74

: 1/2 Kp : 3 Pp Tebal 15 mm 38,586.24

9,878.40
1,090.00 6,278.40
160,000.00 480.00
240,000.00 3,120.00

25,200.00
45,000.00 16,200.00
60,000.00 7,200.00
60,000.00 720.00
60,000.00 1,080.00

35,078.40
3,507.84
38,586.24

: 2 Kp : 8 Pp Tebal 15 mm 45,550.79

5,769.81
1,090.00 9.81
160,000.00 1,440.00

HSPK Cipta Karya_2016P Page 169 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

240,000.00 4,320.00

35,640.00
45,000.00 19,800.00
60,000.00 13,200.00
60,000.00 1,320.00
60,000.00 1,320.00

41,409.81
4,140.98
45,550.79

M : 1 Kp : 1 Pp Tebal 15 mm 33,264.00

5,040.00
160,000.00 1,440.00
160,000.00 1,440.00
240,000.00 2,160.00

25,200.00
45,000.00 16,200.00
60,000.00 7,200.00
60,000.00 720.00
60,000.00 1,080.00

30,240.00
3,024.00
33,264.00

M : 1 Kp : 2 Pp Tebal 15 mm 34,144.00

5,840.00
160,000.00 1,120.00
160,000.00 1,120.00
240,000.00 3,600.00

HSPK Cipta Karya_2016P Page 170 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

25,200.00
45,000.00 16,200.00
60,000.00 7,200.00
60,000.00 720.00
60,000.00 1,080.00

31,040.00
3,104.00
34,144.00

: 2 Pp Tebal 20 mm 59,244.77

21,338.88
1,090.00 14,858.88
240,000.00 6,480.00

32,520.00
45,000.00 18,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,320.00

53,858.88
5,385.89
59,244.77

: 3Pp Tebal 20 mm 48,863.23

18,741.12
1,090.00 11,301.12
240,000.00 7,440.00

25,680.00
45,000.00 11,700.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 780.00

HSPK Cipta Karya_2016P Page 171 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

44,421.12
4,442.11
48,863.23

: 4 Pp Tebal 20 mm 54,195.68

16,748.80
1,090.00 9,068.80
240,000.00 7,680.00

32,520.00
45,000.00 18,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,320.00

49,268.80
4,926.88
54,195.68

: 5Pp Tebal 20 mm 53,299.49

15,934.08
1,090.00 7,534.08
240,000.00 8,400.00

32,520.00
45,000.00 18,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,320.00

48,454.08
4,845.41
53,299.49

: 6Pp Tebal 20 mm 52,335.71

HSPK Cipta Karya_2016P Page 172 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

15,057.92
1,090.00 6,417.92
240,000.00 8,640.00

32,520.00
45,000.00 18,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,320.00

47,577.92
4,757.79
52,335.71

M : 2 Kp : 2 Pp Tebal 20 mm 47,124.00

7,200.00
160,000.00 1,440.00
160,000.00 1,440.00
240,000.00 4,320.00

35,640.00
45,000.00 19,800.00
60,000.00 13,200.00
60,000.00 1,320.00
60,000.00 1,320.00

42,840.00
4,284.00
47,124.00

: 5Pp Tebal 15 mm 26,510.62

11,890.56
1,090.00 5,650.56

HSPK Cipta Karya_2016P Page 173 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

240,000.00 6,240.00

12,210.00
45,000.00 6,750.00
60,000.00 4,500.00
60,000.00 480.00
60,000.00 480.00

24,100.56
2,410.06
26,510.62

ning 1 Pc : 2Pp, lebar 10 mm 37,295.50

3,665.00
1,090.00 545.00
240,000.00 3,120.00

30,240.00
45,000.00 3,600.00
60,000.00 24,000.00
60,000.00 2,400.00
60,000.00 240.00

33,905.00
3,390.50
37,295.50

at 1Pc : 2 Pp 29,863.68

6,148.80
1,090.00 4,708.80
240,000.00 1,440.00

21,000.00
45,000.00 13,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 900.00

HSPK Cipta Karya_2016P Page 174 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

27,148.80
2,714.88
29,863.68

Pasangan Dinding Bata


17,157.49

3,387.72
1,090.00 3,387.72

12,210.00
45,000.00 6,750.00
60,000.00 4,500.00
60,000.00 480.00
60,000.00 480.00

15,597.72
1,559.77
17,157.49

Pasangan Dinding 8,221.40

1,744.00
1,090.00 1,744.00

5,730.00
45,000.00 3,150.00
60,000.00 2,100.00
60,000.00 240.00
60,000.00 240.00

7,474.00
747.40
8,221.40

Pas.Batu Kali Adukan 1Pc : 2Pp 37,499.66

9,790.60

HSPK Cipta Karya_2016P Page 175 of 328 Analisa Pek. Plesteran


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

1,090.00 6,910.60
240,000.00 2,880.00

24,300.00
45,000.00 13,500.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 900.00

34,090.60
3,409.06
37,499.66

21,716.75

3,542.50
1,090.00 3,542.50

16,200.00
45,000.00 9,000.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 600.00

19,742.50
1,974.25
21,716.75

HSPK Cipta Karya_2016P Page 176 of 328 Analisa Pek. Plesteran


0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

VI A.4.6.1 PEKERJAAN K A Y U

A.4.6.1.1 1 m3 Pembuatan dan Pemasangan Kosen Pintu &


Jendela Kayu klas I

Bahan
1.1 m3 Kayu Klas I (Jati) , Balok
1.25 kg Paku Biasa 2" - 5 "
1 kg Lem Kayu

Tenaga
7 OH Pekerja
21 OH Tukang Kayu
2.10 OH Kepala Tukang
0.35 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.2 1 m3 Pembuatan dan Pemasangan Kosen Pintu &


Jendela Kayu klas II

Bahan
1.2 m3 Kayu Klas II (Kamfer) , Balok
1.25 kg Paku Biasa 2" - 5 "
1 kg Lem Kayu

Tenaga
6.00 OH Pekerja
18.00 OH Tukang Kayu
1.80 OH Kepala Tukang
0.30 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 177 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

A.4.6.1.3 1 m2 Pembuatan dan Pemasangan Pintu Klamp


Standard Kayu Klas II (Kayu Kamfer)

Bahan
0.040 m3 Kayu Klas II (Kamfer), papan
0.05 Kg Paku Biasa 2" - 5 "

Tenaga
0.35 OH Pekerja
1.05 OH Tukang Kayu
0.105 OH Kepala Tukang
0.018 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.5 1 m2 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kl

Bahan
0.04 m3 Kayu Klas II (Kamfer), papan
0.050 kg Lem Kayu

Tenaga
1 OH Pekerja
3.0 OH Tukang Kayu
0.30 OH Kepala Tukang
0.05 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

Pembuatan dan Pemasangan Pintu & Jendela


A.4.6.1.6 1 m2
Kaca Kayu Klas II

HSPK Cipta Karya_2016P Page 178 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
0.024 m3 Kayu Klas II (Kamfer), papan
0.300 kg Lem Kayu

Tenaga
0.800 OH Pekerja
2.400 OH Tukang Kayu
0.240 OH Kepala Tukang
0.040 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

Pembuatan dan Pemasangan Pintu & Jendela


A.4.6.1.7 1 m2
Jalusi Kayu Klas I

Bahan
0.064 m3 Kayu Klas I (Jati), papan
0.5 kg Lem Kayu

Tenaga
1 OH Pekerja
3 OH Tukang Kayu
0.3 OH Kepala Tukang
0.05 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

Pembuatan dan Pemasangan Pintu kayu lapis (Plywood


A.4.6.1.8 1 m2
rangka Kayu Klas II (lbr s/d 90 cm)

Bahan
0.025 m3 Kayu Klas II (Kamfer), papan
0.030 Kg Paku Biasa 1/2" - 1"
0.500 Ltr Lem Kayu

HSPK Cipta Karya_2016P Page 179 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1.000 Lbr Plywood tebal 4 mm uk.90x220cm

Tenaga
0.700 OH Pekerja
2.100 OH Tukang Kayu
0.210 OH Kepala Tukang
0.035 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.9 1 m2 Pembuatan dan Pemasangan Pintu Plywood


rangkap, rangka expose kayu klas II

Bahan
0.0256 m3 Kayu Klas II (Kamfer), papan
0.03 Kg Paku Biasa 1/2" - 1"
0.5 Kg Lem Kayu
1 Lbr Plywood tebal 4 mm uk.90x220cm

Tenaga
0.800 OH Pekerja
2.400 OH Tukang Kayu
0.240 OH Kepala Tukang
0.040 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.10 1 m2 Pembuatan dan Pemasangan Jalusi mati Kosen Kayu K

Bahan
0.06 m3 Kayu Klas I (Jati), papan
0.15 Kg Paku Biasa 1/2" - 1"

Tenaga
0.670 OH Pekerja

HSPK Cipta Karya_2016P Page 180 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

2.000 OH Tukang Kayu


0.200 OH Kepala Tukang
0.335 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.11 1 m2 Pembuatan dan Pemasangan Pintu Teakwood


Rangkap, Rangka Expose Kayu Klas I

Bahan
0.025 m3 Kayu Klas I (Jati), papan
0.03 Kg Paku Biasa 1/2" - 1"
0.3 kg Lem Kayu
1 Lbr Teakwood (90 x 220) cm x 4 mm

Tenaga
0.80 OH Pekerja
2.40 OH Tukang Kayu
0.24 OH Kepala Tukang
0.04 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.12 1 m2 Pembuatan dan Pemasangan Pintu Teakwood Rangkap


Formika,Rangka expose Kayu Klas II

Bahan
0.025 m3 Kayu Klas II (Kamfer), papan
0.03 Kg Paku Biasa 1/2" - 1"
0.08 kg Lem Kayu

HSPK Cipta Karya_2016P Page 181 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1 Lbr Teakwood (90 x 220) cm x 4 mm


0.5 Lbr Formika

Tenaga
0.850 OH Pekerja
2.550 OH Tukang Kayu
0.255 OH Kepala Tukang
0.043 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.13 1 m3 Pembuatan dan Pemasangan Konstruksi Kuda-kuda Ko


Kayu I; II & III Bentang 6 meter

Bahan
1.1 m3 Kayu Kamfer, balok
15 Kg Besi Strip
5.6 Kg Paku Biasa 2" - 5"

Tenaga
4 OH Pekerja
12 OH Tukang Kayu
1.2 OH Kepala Tukang
0.2 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

Pembuatan dan Pemasangan Konstruksi Kuda-


A.4.6.1.14 1 m3
kuda Expose, Kayu Klas I

Bahan
1.2 m3 Kayu Klas I (jati), balok
15 Kg Besi Strip
5.6 Kg Paku Biasa 2" - 5"

HSPK Cipta Karya_2016P Page 182 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
6.7 OH Pekerja
20.1 OH Tukang Kayu
2.01 OH Kepala Tukang
0.335 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II

Bahan
1.1 m3 Kayu Klas II (Kamfer), balok
15 Kg Besi Strip
3 Kg Paku Biasa 2" - 5"

Tenaga
2.4 OH Pekerja
7.2 OH Tukang Kayu
0.72 OH Kepala Tukang
0.12 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.16 1 m2 Pemasangan Rangka Atap Genteng Keramik, Kayu Klas

Bahan
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm
0.0036 m3 Reng (2x3) cm
0.25 Kg Paku Biasa 2" - 5"

Tenaga

HSPK Cipta Karya_2016P Page 183 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.1 OH Pekerja
0.1 OH Tukang Kayu
0.01 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.17 1 m2 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II

Bahan
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm
0.0072 m3 Reng (2x3) cm
0.25 Kg Paku Biasa 2" - 5"

Tenaga
0.1 OH Pekerja
0.1 OH Tukang Kayu
0.01 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II

Bahan
0.014 m3 Kayu Klas II (Kamfer), balok
0.2 Kg Paku Biasa 2" - 5"

Tenaga
0.12 OH Pekerja
0.12 OH Tukang Kayu
0.012 OH Kepala Tukang
0.006 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 184 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

A.4.6.1.19 1 m2 Pemasangan Rangka Langit-langit (0,50x1,00) m,


kayu Klas II

Bahan
0.0154 m3 Kayu Klas II (Kamfer), balok
0.2 Kg Paku Biasa 2" - 5"

Tenaga
0.15 OH Pekerja
0.30 OH Tukang Kayu
0.030 OH Kepala Tukang
0.075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.20 1 m2 Pemasangan Rangka Langit-langit (60x60) cm, kayu Kla

Bahan
0.0163 m3 Kayu Klas II (Kamfer), balok
0.25 Kg Paku Biasa 2" - 5"

Tenaga
0.2 OH Pekerja
0.3 OH Tukang Kayu
0.03 OH Kepala Tukang
0.01 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.21 1 m' Pemasangan Listplank Uk. (3x20)cm Kayu klas I

Bahan
0.0108 m3 Kayu klas I (Jati), papan

HSPK Cipta Karya_2016P Page 185 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.10 Kg Paku Biasa 2" - 5"

Tenaga
0.1 OH Pekerja
0.2 OH Tukang Kayu
0.020 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.22 1 m' Pemasangan Listplank Uk. (3x30)cm Kayu klas II

Bahan
0.011 m3 Kayu klas II (Kamfer), papan
0.05 Kg Paku Biasa 2" - 5"

Tenaga
0.1 OH Pekerja
0.2 OH Tukang Kayu
0.02 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.23 1 m2 Pemasangan Rangka Dinding Pemisah (60x120)


cm Kayu klas II

Bahan
0.028 m3 Kayu klas II (Kamfer), balok
0.15 Kg Paku Biasa 2" - 5"

Tenaga
0.15 OH Pekerja

HSPK Cipta Karya_2016P Page 186 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.45 OH Tukang Kayu


0.045 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.24 1 m2 Pemasangan Dinding Pemisah Teakwood


Rangkap Rangka Kayu Klas II

Bahan
0.028 m3 Kayu klas II (Kamfer), balok
0.15 Kg Paku Biasa 2" - 5"
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm
0.56 Ltr Lem

Tenaga
0.15 OH Pekerja
0.45 OH Tukang Kayu
0.045 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan klas I

Bahan
0.007 m3 Kayu klas I (Jati), papan
0.1 Kg Paku Biasa 2" - 5"
0.15 Kg Paku Sekrup 3,5"

Tenaga
0.6 OH Pekerja
1.8 OH Tukang Kayu
0.18 OH Kepala Tukang
0.03 OH Mandor

HSPK Cipta Karya_2016P Page 187 of 328 Analisa Pek. Kayu


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.27 1 m2 Pemasangan Dinding Lambriziring dari Plywood


ukuran (120x240) cm

Bahan
0.4 Lbr Plywood (120 X 240) cm x 4mm
0.05 Kg Paku Biasa 1/2" - 1"

Tenaga
0.025 OH Pekerja
0.075 OH Tukang Kayu
0.0080 OH Kepala Tukang
0.0010 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.1.28 1 m2 Pemasangan Dinding Bilik, Rangka Kayu Klas III

Bahan
1.500 m2 Bilik Bambu
0.014 m3 Kayu Klas III (Meranti)
0.012 Kg Paku Biasa 1/2" - 1"
0.003 m' List Kayu 2/4

Tenaga
0.1 OH Pekerja
0.05 OH Tukang Kayu
0.005 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 188 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

gan Kosen Pintu &


25,883,687.50

21,808,625.00
19,800,000.00 21,780,000.00
13,300.00 16,625.00
12,000.00 12,000.00

1,722,000.00
45,000.00 315,000.00
60,000.00 1,260,000.00
60,000.00 126,000.00
60,000.00 21,000.00

23,530,625.00
2,353,062.50
25,883,687.50

gan Kosen Pintu &


11,588,087.50

9,058,625.00
7,525,000.00 9,030,000.00
13,300.00 16,625.00
12,000.00 12,000.00

1,476,000.00
45,000.00 270,000.00
60,000.00 1,080,000.00
60,000.00 108,000.00
60,000.00 18,000.00

10,534,625.00
1,053,462.50

HSPK Cipta Karya_2016P Page 189 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

11,588,087.50

gan Pintu Klamp 454,074.50


yu Kamfer)

326,665.00
8,150,000.00 326,000.00
13,300.00 665.00

86,130.00
45,000.00 15,750.00
60,000.00 63,000.00
60,000.00 6,300.00
60,000.00 1,080.00

412,795.00
41,279.50
454,074.50

gan Daun Pintu Panel Kayu Klas II 629,860.00

326,600.00
8,150,000.00 326,000.00
12,000.00 600.00

246,000.00
45,000.00 45,000.00
60,000.00 180,000.00
60,000.00 18,000.00
60,000.00 3,000.00

572,600.00
57,260.00
629,860.00

gan Pintu & Jendela


435,600.00

HSPK Cipta Karya_2016P Page 190 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

199,200.00
8,150,000.00 195,600.00
12,000.00 3,600.00

196,800.00
45,000.00 36,000.00
60,000.00 144,000.00
60,000.00 14,400.00
60,000.00 2,400.00

396,000.00
39,600.00
435,600.00

gan Pintu & Jendela


1,826,000.00

1,414,000.00
22,000,000.00 1,408,000.00
12,000.00 6,000.00

246,000.00
45,000.00 45,000.00
60,000.00 180,000.00
60,000.00 18,000.00
60,000.00 3,000.00

1,660,000.00
166,000.00
1,826,000.00

gan Pintu kayu lapis (Plywood) Rangkap


500,333.90
d 90 cm)

282,649.00
8,150,000.00 203,750.00
13,300.00 399.00
12,000.00 6,000.00

HSPK Cipta Karya_2016P Page 191 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

72,500.00 72,500.00

172,200.00
45,000.00 31,500.00
60,000.00 126,000.00
60,000.00 12,600.00
60,000.00 2,100.00

454,849.00
45,484.90
500,333.90

gan Pintu Plywood


532,772.90
ayu klas II

287,539.00
8,150,000.00 208,640.00
13,300.00 399.00
12,000.00 6,000.00
72,500.00 72,500.00

196,800.00
45,000.00 36,000.00
60,000.00 144,000.00
60,000.00 14,400.00
60,000.00 2,400.00

484,339.00
48,433.90
532,772.90

gan Jalusi mati Kosen Kayu Klas I 1,654,669.50

1,321,995.00
22,000,000.00 1,320,000.00
13,300.00 1,995.00

182,250.00
45,000.00 30,150.00

HSPK Cipta Karya_2016P Page 192 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 120,000.00
60,000.00 12,000.00
60,000.00 20,100.00

1,504,245.00
150,424.50
1,654,669.50

gan Pintu Teakwood


905,628.90
Kayu Klas I

626,499.00
22,000,000.00 550,000.00
13,300.00 399.00
12,000.00 3,600.00
72,500.00 72,500.00

196,800.00
45,000.00 36,000.00
60,000.00 144,000.00
60,000.00 14,400.00
60,000.00 2,400.00

823,299.00
82,329.90
905,628.90

gan Pintu Teakwood Rangkap Lapis


Kayu Klas II 566,212.90

305,609.00
8,150,000.00 203,750.00
13,300.00 399.00
12,000.00 960.00

HSPK Cipta Karya_2016P Page 193 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

72,500.00 72,500.00
56,000.00 28,000.00

209,130.00
45,000.00 38,250.00
60,000.00 153,000.00
60,000.00 15,300.00
60,000.00 2,580.00

514,739.00
51,473.90
566,212.90

gan Konstruksi Kuda-kuda Konvensional


meter 10,513,778.00

8,573,980.00
7,525,000.00 8,277,500.00
14,800.00 222,000.00
13,300.00 74,480.00

984,000.00
45,000.00 180,000.00
60,000.00 720,000.00
60,000.00 72,000.00
60,000.00 12,000.00

9,557,980.00
955,798.00
10,513,778.00

gan Konstruksi Kuda-


28,275,148.00

24,056,480.00
19,800,000.00 23,760,000.00
14,800.00 222,000.00
13,300.00 74,480.00

HSPK Cipta Karya_2016P Page 194 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

1,648,200.00
45,000.00 301,500.00
60,000.00 1,206,000.00
60,000.00 120,600.00
60,000.00 20,100.00

25,704,680.00
2,570,468.00
28,275,148.00

Gording, Kayu Klas II 10,042,780.00

8,539,400.00
7,525,000.00 8,277,500.00
14,800.00 222,000.00
13,300.00 39,900.00

590,400.00
45,000.00 108,000.00
60,000.00 432,000.00
60,000.00 43,200.00
60,000.00 7,200.00

9,129,800.00
912,980.00
10,042,780.00

p Genteng Keramik, Kayu Klas II 161,881.50

135,765.00
o-kaso (5x7) cm 7,525,000.00 105,350.00
7,525,000.00 27,090.00
13,300.00 3,325.00

11,400.00

HSPK Cipta Karya_2016P Page 195 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

45,000.00 4,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 300.00

147,165.00
14,716.50
161,881.50

p Genteng Beton, Kayu Klas II 191,680.50

162,855.00
o-kaso (5x7) cm 7,525,000.00 105,350.00
7,525,000.00 54,180.00
13,300.00 3,325.00

11,400.00
45,000.00 4,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 300.00

174,255.00
17,425.50
191,680.50

p Sirap, Kayu Klas II 133,859.00

108,010.00
7,525,000.00 105,350.00
13,300.00 2,660.00

13,680.00
45,000.00 5,400.00
60,000.00 7,200.00
60,000.00 720.00
60,000.00 360.00

121,690.00
12,169.00

HSPK Cipta Karya_2016P Page 196 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

133,859.00

ngit-langit (0,50x1,00) m,
164,554.50

118,545.00
7,525,000.00 115,885.00
13,300.00 2,660.00

31,050.00
45,000.00 6,750.00
60,000.00 18,000.00
60,000.00 1,800.00
60,000.00 4,500.00

149,595.00
14,959.50
164,554.50

git-langit (60x60) cm, kayu Klas II 170,920.75

125,982.50
7,525,000.00 122,657.50
13,300.00 3,325.00

29,400.00
45,000.00 9,000.00
60,000.00 18,000.00
60,000.00 1,800.00
60,000.00 600.00

155,382.50
15,538.25
170,920.75

k. (3x20)cm Kayu klas I 282,623.00

238,930.00
22,000,000.00 237,600.00

HSPK Cipta Karya_2016P Page 197 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

13,300.00 1,330.00

18,000.00
45,000.00 4,500.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 300.00

256,930.00
25,693.00
282,623.00

k. (3x30)cm Kayu klas II 119,146.50

90,315.00
8,150,000.00 89,650.00
13,300.00 665.00

18,000.00
45,000.00 4,500.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 300.00

108,315.00
10,831.50
119,146.50

ding Pemisah (60x120)


274,587.50

212,695.00
7,525,000.00 210,700.00
13,300.00 1,995.00

36,930.00
45,000.00 6,750.00

HSPK Cipta Karya_2016P Page 198 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 27,000.00
60,000.00 2,700.00
60,000.00 480.00

249,625.00
24,962.50
274,587.50

misah Teakwood
as II 350,564.50

281,765.00
7,525,000.00 210,700.00
13,300.00 1,995.00
72,500.00 62,350.00
12,000.00 6,720.00

36,930.00
45,000.00 6,750.00
60,000.00 27,000.00
60,000.00 2,700.00
60,000.00 480.00

318,695.00
31,869.50
350,564.50

mbriziring dari Papan klas I 339,163.00

160,730.00
22,000,000.00 154,000.00
13,300.00 1,330.00
36,000.00 5,400.00

147,600.00
45,000.00 27,000.00
60,000.00 108,000.00
60,000.00 10,800.00
60,000.00 1,800.00

HSPK Cipta Karya_2016P Page 199 of 328 Analisa Pek. Kayu


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

308,330.00
30,833.00
339,163.00

mbriziring dari Plywood


70,995.00

29,665.00
72,500.00 29,000.00
13,300.00 665.00

6,165.00
45,000.00 1,125.00
60,000.00 4,500.00
60,000.00 480.00
60,000.00 60.00

35,165.00
35,830.00
70,995.00

k, Rangka Kayu Klas III 117,447.44

98,670.40
21,800.00 32,700.00
4,700,000.00 65,800.00
13,300.00 159.60
3,600.00 10.80

8,100.00
45,000.00 4,500.00
60,000.00 3,000.00
60,000.00 300.00
60,000.00 300.00

106,770.40
10,677.04
117,447.44

HSPK Cipta Karya_2016P Page 200 of 328 Analisa Pek. Kayu


0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

VII A.4.1.1 PEKERJAAN BETON

A.4.1.1.1 1 m3
Membuat Beton mutu f'c=7,4 Mpa (K100), slum
(12±2)cm, w/c = 0,87

Bahan
247 Kg Portland Semen
869 Kg Pasir Beton
999 Kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
1.65 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

1 m3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum


A.4.1.1.2 (12±2)cm, w/c = 0,78

Bahan
276 Kg Portland Semen
828 kg Pasir Beton
1,012 kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
1.65 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga

HSPK Cipta Karya_2016P Page 201 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Overhead + Profit 10%


Jumlah Total

1 m3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum


A.4.1.1.3 (12±2)cm, w/c = 0,72

Bahan
299 Kg Portland Semen
799 kg Pasir Beton
1,017 kg Kerikil (maksimum 30 mm)
215 ltr Air
Tenaga
1.65 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

1 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa


A.4.1.1.4 (K100), slum (3-6)cm, w/c = 0,87

Bahan
230 Kg Portland Semen
893 kg Pasir Beton
1,027 kg Kerikil (maksimum 30 mm)
200 ltr Air

Tenaga
1.2 OH Pekerja
0.2 OH Tukang Batu
0.02 OH Kepala Tukang
0.006 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 202 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum


A.4.1.1.5 (12±2)cm, w/c = 0,66

Bahan
326 Kg Portland Semen
760 Kg Pasir Beton
1,029 Kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
1.65 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

1 m3 Membuat Beton mutu f'c=16,9 MPa (K200), slum


A.4.1.1.6 (12±2)cm, w/c = 0,61

Bahan
352 Kg Portland Semen
731 Kg Pasir Beton
1,031 Kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
1.650 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 203 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1 m3 Membuat Beton mutu f'c=19,3 MPa (K225), slum


A.4.1.1.7 (12±2)cm, w/c = 0,58

Bahan
371 Kg Portland Semen
698 Kg Pasir Beton ( Muntilan )
1,047 Kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
1.650 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

1 m3 Membuat Beton mutu f'c=21,7 MPa (K250), slum


A.4.1.1.8 (12±2)cm, w/c = 0,56

Bahan
384 Kg Portland Semen
692 Kg Pasir Beton ( Muntilan )
1,039 Kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
1.650 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 204 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1 m3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


A.4.1.1.9 (K275), slum (12±2)cm, w/c = 0,53

Bahan
406 Kg Portland Semen
684 kg Pasir Beton ( Muntilan )
1,026 kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
1.650 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

1 m3 Membuat Beton mutu f'c=26,4 MPa (K300), slum


A.4.1.1.10 (12±2)cm, w/c = 0,52

Bahan
413 Kg Portland Semen
681 Kg Pasir Beton ( Muntilan )
1,021 Kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
1.650 OH Pekerja
0.275 OH Tukang Batu
0.028 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 205 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

1 m3 Membuat Beton mutu f'c=28,8 MPa (K325), slum


A.4.1.1.11 (12±2)cm, w/c = 0,49

Bahan
439 Kg Portland Semen
670 Kg Pasir Beton ( Muntilan )
1,006 Kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
2.1 OH Pekerja
0.35 OH Tukang Batu
0.035 OH Kepala Tukang
0.105 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

1 m3 Membuat Beton mutu f'c=31,2 MPa (K350), slum


A.4.1.1.12 (12±2)cm, w/c = 0,48

Bahan
448 Kg Portland Semen
667 Kg Pasir Beton ( Muntilan )
1,000 Kg Kerikil (maksimum 30 mm)
215 ltr Air

Tenaga
2.10 OH Pekerja
0.350 OH Tukang Batu
0.035 OH Kepala Tukang
0.105 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir

HSPK Cipta Karya_2016P Page 206 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
10.50 Kg Besi Beton (polos/ulir)
0.150 Kg Kawat Beton

Tenaga
0.07 OH Pekerja
0.07 OH Tukang Besi
0.007 OH Kepala Tukang
0.004 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand

Bahan
10.5 Kg Besi presstred polos
0.1 Kg Kawat Beton

Tenaga
0.05 OH Pekerja
0.05 OH Tukang Besi
0.005 OH Kepala Tukang
0.003 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh

Bahan
10.20 Kg Jaring Kawat Baja dilas
0.05 Kg Kawat Beton

Tenaga
0.025 OH Pekerja

HSPK Cipta Karya_2016P Page 207 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.025 OH Tukang Besi


0.002 OH Kepala Tukang
0.001 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi

Bahan
0.04 m3 Kayu Klas III (Terentang)
0.3 Kg Paku Biasa 2" - 5"
0.1 Ltr Minyak Bekisting
Tenaga
0.52 OH Pekerja
0.26 OH Tukang Kayu
0.026 OH Kepala Tukang
0.026 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof

Bahan
0.045 m3 Kayu Klas III (Terentang)
0.3 Kg Paku Biasa 2" - 5"
0.1 Ltr Minyak Bekisting

Tenaga
0.52 OH Pekerja
0.26 OH Tukang Kayu
0.026 OH Kepala Tukang
0.026 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 208 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom

Bahan
0.04 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.015 m3 Balok Kayu Klas II
0.35 Lbr Plywood tebal 9mm
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m

Tenaga
0.66 OH Pekerja
0.33 OH Tukang Kayu
0.033 OH Kepala Tukang
0.033 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok

Bahan
0.04 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.018 m3 Balok Kayu Klas II
0.35 Lbr Plywood tebal 9mm
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m

Tenaga
0.66 OH Pekerja
0.33 OH Tukang Kayu
0.033 OH Kepala Tukang
0.033 OH Mandor

Jumlah Bahan dan Tenaga

HSPK Cipta Karya_2016P Page 209 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Overhead + Profit 10%


Jumlah Total

A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai

Bahan
0.04 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.015 m3 Balok Kayu Klas II (Borneo)
0.35 Lbr Plywood tebal 9mm
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m

Tenaga
0.66 OH Pekerja
0.33 OH Tukang Kayu
0.033 OH Kepala Tukang
0.033 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding

Bahan
0.03 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.2 Ltr Minyak Bekisting
0.02 m3 Balok Kayu Klas II
0.35 Lbr Plywood tebal 9mm
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m
4 Buah Formite/Penjaga jarak / Spacer (alat bantu)

Tenaga
0.66 OH Pekerja

HSPK Cipta Karya_2016P Page 210 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.33 OH Tukang Kayu


0.033 OH Kepala Tukang
0.033 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga

Bahan
0.03 m3 Kayu Klas III (Terentang)
0.4 Kg Paku Biasa 2" - 5"
0.15 Ltr Minyak Bekisting
0.015 m3 Balok Kayu Klas II
0.35 Lbr Plywood tebal 9mm
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m

Tenaga
0.66 OH Pekerja
0.33 OH Tukang Kayu
0.033 OH Kepala Tukang
0.033 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.27 1 m2 Memasang Jembatan Cor

Bahan
0.0264 m3 Kayu Terentang
0.6 kg Paku Biasa 2" - 5"
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m

Tenaga
0.15 OH Pekerja
0.05 OH Tukang Kayu
0.005 OH Kepala Tukang
0.008 OH Mandor

HSPK Cipta Karya_2016P Page 211 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.28 1 m3 Membuat Pondasi Beton Bertulang (150 kg Besi + Beki

Bahan
0.2 m3 Kayu Klas III (Terentang)
1.5 Kg Paku Biasa 2" - 5"
0.4 Ltr Minyak Bekisting
157.5 Kg Besi Beton Polos
2.25 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton

Tenaga
5.3 OH Pekerja
0.275 OH Tukang batu
1.30 OH Tukang Kayu
1.05 OH Tukang Besi
0.262 OH Kepala Tukang
0.265 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.29 1 m3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekistin

Bahan
0.27 m3 Kayu Klas III (Terentang)
2 Kg Paku Biasa 2" - 5"
0.6 Ltr Minyak Bekisting
210 Kg Besi Beton Polos
3 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton

HSPK Cipta Karya_2016P Page 212 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.81 m3 Kerikil Beton

Tenaga
5.65 OH Pekerja
0.275 OH Tukang batu
1.56 OH Tukang Kayu
1.4 OH Tukang Besi
0.323 OH Kepala Tukang
0.283 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.30 1 m3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekist

Bahan
0.4 m3 Kayu Klas III (Terentang)
4 Kg Paku Biasa 2" - 5"
2 Ltr Minyak Bekisting
315 kg Besi Beton Polos
4.5 kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.15 m3 Kayu Klas II Balok
3.5 Lbr Plywood 9 mm
20 Btg Dolken Kayu Galam diameter 8 - 10 / 4 m

Tenaga
7.05 OH Pekerja
0.275 OH Tukang batu
1.65 OH Tukang Kayu
2.1 OH Tukang Besi
0.403 OH Kepala Tukang
0.353 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 213 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.1.1.31 1 m3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisti

Bahan
0.32 m3 Kayu Klas III (Terentang)
3.2 Kg Paku Biasa 2" - 5"
1.6 Ltr Minyak Bekisting
210 Kg Besi Beton Polos
3 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.14 m3 Kayu Klas II Balok
2.8 Lbr Plywood 9 mm
16 Btg Dolken Kayu Galam diameter 8 - 10 / 4 m

Tenaga
6.35 OH Pekerja
0.275 OH Tukang batu
1.65 OH Tukang Kayu
1.4 OH Tukang Besi
0.333 OH Kepala Tukang
0.318 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.32 1 m3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisti

Bahan
0.32 m3 Kayu Klas III (Terentang)
3.2 Kg Paku Biasa 2" - 5"
1.6 Ltr Minyak Bekisting
157.5 Kg Besi Beton Polos
2.25 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.12 m3 Kayu Klas II Balok

HSPK Cipta Karya_2016P Page 214 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

2.8 Lbr Plywood 9 mm


32 Btg Dolken Kayu Galam diameter 8 - 10 / 4 m

Tenaga
5.3 OH Pekerja
0.275 OH Tukang batu
1.3 OH Tukang Kayu
1.05 OH Tukang Besi
0.265 OH Kepala Tukang
0.265 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.33 1 m3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekis

Bahan
0.24 m3 Kayu Klas III (Terentang)
3.2 Kg Paku Biasa 2" - 5"
1.6 Ltr Minyak Bekisting
157.5 Kg Besi Beton Polos
2.25 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.16 m3 Kayu Klas II Balok
2.8 Lbr Plywood 9 mm
24 Btg Dolken Kayu Galam diameter 8 - 10 / 4 m

Tenaga
5.3 OH Pekerja
0.275 OH Tukang batu
1.3 OH Tukang Kayu
1.05 OH Tukang Besi
0.262 OH Kepala Tukang
0.265 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 215 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

A.4.1.1.34 1 m3 Membuat Tangga Beton Bertulang (200 kg Besi + Bekis

Bahan
0.25 m3 Kayu Klas III (Terentang)
3 Kg Paku Biasa 2" - 5"
1.2 Ltr Minyak Bekisting
210 Kg Besi Beton Polos
3 Kg Kawat Beton
336 Kg Portland Semen
0.54 m3 Pasir Beton
0.81 m3 Kerikil Beton
0.105 m3 Kayu Klas II Balok
2.5 Lbr Plywood 9 mm
14 Btg Dolken Kayu Galam diameter 8 - 10 / 4 m

Tenaga
5.65 OH Pekerja
0.275 OH Tukang batu
1.56 OH Tukang Kayu
1.4 OH Tukang Besi
0.323 OH Kepala Tukang
0.283 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.35 1 m' Membuat Kolom Penguat Beton Bertulang (11 x 11) cm

Bahan
0.002 m3 Kayu Klas III (Terentang)
0.01 Kg Paku Biasa 2" - 5"
3 Ltr Besi Beton Polos
0.045 Kg Kawat Beton
4 Kg Portland Semen
0.006 m3 Pasir Beton
0.009 m3 Kerikil Beton

HSPK Cipta Karya_2016P Page 216 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.18 OH Pekerja
0.02 OH Tukang batu
0.02 OH Tukang Kayu
0.02 OH Tukang Besi
0.006 OH Kepala Tukang
0.009 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.1.1.36 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm

Bahan
0.003 m3 Kayu Klas III (Terentang)
0.02 Kg Paku Biasa 2" - 5"
3.6 Ltr Besi Beton Polos
0.05 Kg Kawat Beton
5.5 Kg Portland Semen
0.009 m3 Pasir Beton
0.015 m3 Kerikil Beton

Tenaga
0.297 OH Pekerja
0.033 OH Tukang batu
0.033 OH Tukang Kayu
0.033 OH Tukang Besi
0.01 OH Kepala Tukang
0.015 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 217 of 328 Analisa Pek. Beton


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

HSPK Cipta Karya_2016P Page 218 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

7,4 Mpa (K100), slum 825,358.44

652,915.86
1,090.00 269,230.00
230.36 200,180.36
180.74 180,560.00
13.70 2,945.50

97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

750,325.86
75,032.59
825,358.44

9,8 Mpa (K125), slum


852,324.93

677,430.84
1,090.00 300,840.00
230.36 190,735.71
180.74 182,909.63
13.70 2,945.50

97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

774,840.84

HSPK Cipta Karya_2016P Page 219 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

77,484.08
852,324.93

12,2 Mpa (K150), slum


873,547.61

696,724.19
1,090.00 325,910.00
230.36 184,055.36
180.74 183,813.33
13.70 2,945.50
97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

794,134.19
79,413.42
873,547.61

ton mutu f'c=7,4 MPa


= 0,87 783,562.64

644,769.67
1,090.00 250,700.00
230.36 205,708.93
180.74 185,620.74
13.70 2,740.00

67,560.00
45,000.00 54,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 360.00

712,329.67
71,232.97
783,562.64

HSPK Cipta Karya_2016P Page 220 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

14,5 MPa (K175), slum


898,424.07

719,339.15
1,090.00 355,340.00
230.36 175,071.43
180.74 185,982.22
13.70 2,945.50

97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

816,749.15
81,674.92
898,424.07

16,9 MPa (K200), slum


922,647.30

741,360.28
1,090.00 383,680.00
230.36 168,391.07
180.74 186,343.70
13.70 2,945.50

97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

838,770.28
83,877.03
922,647.30

HSPK Cipta Karya_2016P Page 221 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

19,3 MPa (K225), slum


960,813.45

776,056.77
1,090.00 404,390.00
257.14 179,485.71
180.74 189,235.56
13.70 2,945.50

97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

873,466.77
87,346.68
960,813.45

21,7 MPa (K250), slum


973,112.79

787,237.99
1,090.00 418,560.00
257.14 177,942.86
180.74 187,789.63
13.70 2,945.50

97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

884,647.99
88,464.80
973,112.79

HSPK Cipta Karya_2016P Page 222 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

ton mutu f'c=24,0 MPa


c = 0,53 994,643.34

806,811.21
1,090.00 442,540.00
257.14 175,885.71
180.74 185,440.00
13.70 2,945.50

97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

904,221.21
90,422.12
994,643.34

26,4 MPa (K300), slum


1,001,193.69

812,766.08
1,090.00 450,170.00
257.14 175,114.29
180.74 184,536.30
13.70 2,945.50

97,410.00
45,000.00 74,250.00
60,000.00 16,500.00
60,000.00 1,680.00
60,000.00 4,980.00

910,176.08
91,017.61

HSPK Cipta Karya_2016P Page 223 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

1,001,193.69

28,8 MPa (K325), slum


1,055,413.04

835,566.40
1,090.00 478,510.00
257.14 172,285.71
180.74 181,825.19
13.70 2,945.50

123,900.00
45,000.00 94,500.00
60,000.00 21,000.00
60,000.00 2,100.00
60,000.00 6,300.00

959,466.40
95,946.64
1,055,413.04

31,2 MPa (K350), slum


1,064,162.58

843,520.53
1,090.00 488,320.00
257.14 171,514.29
180.74 180,740.74
13.70 2,945.50

123,900.00
45,000.00 94,500.00
60,000.00 21,000.00
60,000.00 2,100.00
60,000.00 6,300.00

967,420.53
96,742.05
1,064,162.58

atau Besi Ulir 112,926.00

HSPK Cipta Karya_2016P Page 224 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

94,650.00
8,800.00 92,400.00
15,000.00 2,250.00

8,010.00
45,000.00 3,150.00
60,000.00 4,200.00
60,000.00 420.00
60,000.00 240.00

102,660.00
10,266.00
112,926.00

163,878.00

143,250.00
13,500.00 141,750.00
15,000.00 1,500.00

5,730.00
45,000.00 2,250.00
60,000.00 3,000.00
60,000.00 300.00
60,000.00 180.00

148,980.00
14,898.00
163,878.00

177,820.50

158,850.00
15,500.00 158,100.00
15,000.00 750.00

2,805.00
45,000.00 1,125.00

HSPK Cipta Karya_2016P Page 225 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 1,500.00
60,000.00 120.00
60,000.00 60.00

161,655.00
16,165.50
177,820.50

uk Pondasi 133,716.00

79,440.00
1,850,000.00 74,000.00
13,300.00 3,990.00
14,500.00 1,450.00
42,120.00
45,000.00 23,400.00
60,000.00 15,600.00
60,000.00 1,560.00
60,000.00 1,560.00

121,560.00
12,156.00
133,716.00

143,891.00

88,690.00
1,850,000.00 83,250.00
13,300.00 3,990.00
14,500.00 1,450.00

42,120.00
45,000.00 23,400.00
60,000.00 15,600.00
60,000.00 1,560.00
60,000.00 1,560.00

130,810.00
13,081.00

HSPK Cipta Karya_2016P Page 226 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

143,891.00

346,615.50

261,645.00
1,850,000.00 74,000.00
13,300.00 5,320.00
14,500.00 2,900.00
6,100,000.00 91,500.00
117,500.00 41,125.00
er 8 - 10 cm / 4 m 23,400.00 46,800.00

53,460.00
45,000.00 29,700.00
60,000.00 19,800.00
60,000.00 1,980.00
60,000.00 1,980.00

315,105.00
31,510.50
346,615.50

366,745.50

279,945.00
1,850,000.00 74,000.00
13,300.00 5,320.00
14,500.00 2,900.00
6,100,000.00 109,800.00
117,500.00 41,125.00
er 8 - 10 cm / 4 m 23,400.00 46,800.00

53,460.00
45,000.00 29,700.00
60,000.00 19,800.00
60,000.00 1,980.00
60,000.00 1,980.00

333,405.00

HSPK Cipta Karya_2016P Page 227 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

33,340.50
366,745.50

449,575.50

355,245.00
1,850,000.00 74,000.00
13,300.00 5,320.00
14,500.00 2,900.00
6,100,000.00 91,500.00
117,500.00 41,125.00
er 8 - 10 cm / 4 m 23,400.00 140,400.00

53,460.00
45,000.00 29,700.00
60,000.00 19,800.00
60,000.00 1,980.00
60,000.00 1,980.00

408,705.00
40,870.50
449,575.50

409,755.50

319,045.00
1,850,000.00 55,500.00
13,300.00 5,320.00
14,500.00 2,900.00
6,100,000.00 122,000.00
117,500.00 41,125.00
er 8 - 10 cm / 4 m 23,400.00 70,200.00
acer (alat bantu) 5,500.00 22,000.00

53,460.00
45,000.00 29,700.00

HSPK Cipta Karya_2016P Page 228 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 19,800.00
60,000.00 1,980.00
60,000.00 1,980.00

372,505.00
37,250.50
409,755.50

325,468.00

242,420.00
1,850,000.00 55,500.00
13,300.00 5,320.00
14,500.00 2,175.00
6,100,000.00 91,500.00
117,500.00 41,125.00
er 8 - 10 cm / 4 m 23,400.00 46,800.00

53,460.00
45,000.00 29,700.00
60,000.00 19,800.00
60,000.00 1,980.00
60,000.00 1,980.00

295,880.00
29,588.00
325,468.00

86,955.00

68,520.00
1,850,000.00 48,840.00
13,300.00 7,980.00
er 8 - 10 / 4 m 23,400.00 11,700.00

10,530.00
45,000.00 6,750.00
60,000.00 3,000.00
60,000.00 300.00
60,000.00 480.00

HSPK Cipta Karya_2016P Page 229 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

79,050.00
7,905.00
86,955.00

Bertulang (150 kg Besi + Bekisting) 3,279,265.00

2,553,530.00
1,850,000.00 370,000.00
13,300.00 19,950.00
14,500.00 5,800.00
8,800.00 1,386,000.00
15,000.00 33,750.00
1,090.00 366,240.00
322,500.00 174,150.00
244,000.00 197,640.00

427,620.00
45,000.00 238,500.00
60,000.00 16,500.00
60,000.00 78,000.00
60,000.00 63,000.00
60,000.00 15,720.00
60,000.00 15,900.00

2,981,150.00
298,115.00
3,279,265.00

tulang (200 kg Besi + Bekisting) 4,015,594.00

3,165,830.00
1,850,000.00 499,500.00
13,300.00 26,600.00
14,500.00 8,700.00
8,800.00 1,848,000.00
15,000.00 45,000.00
1,090.00 366,240.00
322,500.00 174,150.00

HSPK Cipta Karya_2016P Page 230 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

244,000.00 197,640.00

484,710.00
45,000.00 254,250.00
60,000.00 16,500.00
60,000.00 93,600.00
60,000.00 84,000.00
60,000.00 19,380.00
60,000.00 16,980.00

3,650,540.00
365,054.00
4,015,594.00

ertulang (300 kg Besi + Bekisting) 7,477,899.00

6,193,980.00
1,850,000.00 740,000.00
13,300.00 53,200.00
14,500.00 29,000.00
8,800.00 2,772,000.00
15,000.00 67,500.00
1,090.00 366,240.00
322,500.00 174,150.00
244,000.00 197,640.00
6,100,000.00 915,000.00
117,500.00 411,250.00
er 8 - 10 / 4 m 23,400.00 468,000.00

604,110.00
45,000.00 317,250.00
60,000.00 16,500.00
60,000.00 99,000.00
60,000.00 126,000.00
60,000.00 24,180.00
60,000.00 21,180.00

6,798,090.00
679,809.00
7,477,899.00

HSPK Cipta Karya_2016P Page 231 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

rtulang (200 kg Besi + Bekisting) 5,907,550.00

4,846,190.00
1,850,000.00 592,000.00
13,300.00 42,560.00
14,500.00 23,200.00
8,800.00 1,848,000.00
15,000.00 45,000.00
1,090.00 366,240.00
322,500.00 174,150.00
244,000.00 197,640.00
6,100,000.00 854,000.00
117,500.00 329,000.00
er 8 - 10 / 4 m 23,400.00 374,400.00

524,310.00
45,000.00 285,750.00
60,000.00 16,500.00
60,000.00 99,000.00
60,000.00 84,000.00
60,000.00 19,980.00
60,000.00 19,080.00

5,370,500.00
537,050.00
5,907,550.00

rtulang (150 kg Besi + Bekisting) 5,558,454.00

4,625,340.00
1,850,000.00 592,000.00
13,300.00 42,560.00
14,500.00 23,200.00
8,800.00 1,386,000.00
15,000.00 33,750.00
1,090.00 366,240.00
322,500.00 174,150.00
244,000.00 197,640.00
6,100,000.00 732,000.00

HSPK Cipta Karya_2016P Page 232 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

117,500.00 329,000.00
er 8 - 10 / 4 m 23,400.00 748,800.00

427,800.00
45,000.00 238,500.00
60,000.00 16,500.00
60,000.00 78,000.00
60,000.00 63,000.00
60,000.00 15,900.00
60,000.00 15,900.00

5,053,140.00
505,314.00
5,558,454.00

Bertulang (150 kg Besi + Bekisting) 5,457,936.00

4,534,140.00
1,850,000.00 444,000.00
13,300.00 42,560.00
14,500.00 23,200.00
8,800.00 1,386,000.00
15,000.00 33,750.00
1,090.00 366,240.00
322,500.00 174,150.00
244,000.00 197,640.00
6,100,000.00 976,000.00
117,500.00 329,000.00
er 8 - 10 / 4 m 23,400.00 561,600.00

427,620.00
45,000.00 238,500.00
60,000.00 16,500.00
60,000.00 78,000.00
60,000.00 63,000.00
60,000.00 15,720.00
60,000.00 15,900.00

4,961,760.00
496,176.00

HSPK Cipta Karya_2016P Page 233 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

5,457,936.00

ertulang (200 kg Besi + Bekisting) 5,387,129.00

4,412,680.00
1,850,000.00 462,500.00
13,300.00 39,900.00
14,500.00 17,400.00
8,800.00 1,848,000.00
15,000.00 45,000.00
1,090.00 366,240.00
322,500.00 174,150.00
244,000.00 197,640.00
6,100,000.00 640,500.00
117,500.00 293,750.00
er 8 - 10 / 4 m 23,400.00 327,600.00

484,710.00
45,000.00 254,250.00
60,000.00 16,500.00
60,000.00 93,600.00
60,000.00 84,000.00
60,000.00 19,380.00
60,000.00 16,980.00

4,897,390.00
489,739.00
5,387,129.00

Beton Bertulang (11 x 11) cm 57,198.90

39,399.00
1,850,000.00 3,700.00
13,300.00 133.00
8,800.00 26,400.00
15,000.00 675.00
1,090.00 4,360.00
322,500.00 1,935.00
244,000.00 2,196.00

HSPK Cipta Karya_2016P Page 234 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

12,600.00
45,000.00 8,100.00
60,000.00 1,200.00
60,000.00 1,200.00
60,000.00 1,200.00
60,000.00 360.00
60,000.00 540.00

51,999.00
5,199.90
57,198.90

on Bertulang (10 x 15) cm 78,769.35

50,803.50
1,850,000.00 5,550.00
13,300.00 266.00
8,800.00 31,680.00
15,000.00 750.00
1,090.00 5,995.00
322,500.00 2,902.50
244,000.00 3,660.00

20,805.00
45,000.00 13,365.00
60,000.00 1,980.00
60,000.00 1,980.00
60,000.00 1,980.00
60,000.00 600.00
60,000.00 900.00

71,608.50
7,160.85

HSPK Cipta Karya_2016P Page 235 of 328 Analisa Pek. Beton


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

78,769.35

HSPK Cipta Karya_2016P Page 236 of 328 Analisa Pek. Beton


0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

VIII A.4.5.2 PEKERJAAN PENUTUP ATAP

A.4.5.2.1 1 m2 Pasang Atap Genteng Plentong Kecil

Bahan
25 Buah Genteng Plentong

Tenaga
0.15 OH Pekerja
0.075 OH Tukang Kayu
0.008 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.2 1 m2 Pasang Atap Genteng Kodok / Glasur

Bahan
25 Buah Genteng Kodok / Glasur

Tenaga
0.15 OH Pekerja
0.075 OH Tukang Kayu
0.008 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.3 1 m2 Pasang Atap Genteng Plentong Super / Besar

Bahan
12 Buah Genteng Plentong Super / Besar

HSPK Cipta Karya_2016P Page 237 of 328 Analisa Pek. Penutup Atap
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.15 OH Pekerja
0.075 OH Tukang Kayu
0.008 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.4 1 m' Pasang Genteng Bubung Plentong

Bahan
5 Buah Genteng Bubung Plentong
8 Kg Portland Semen
0.032 m3 Pasir Pasang

Tenaga
0.4 OH Pekerja
0.2 OH Tukang Kayu
0.02 OH Kepala Tukang
0.002 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.5 1 m' Pasang Genteng Bubung Kodok / Glasur

Bahan
5 Buah Genteng Bubung Kodok / Glasur
8 Kg Portland Semen
0.032 m3 Pasir Pasang

Tenaga

HSPK Cipta Karya_2016P Page 238 of 328 Analisa Pek. Penutup Atap
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.4 OH Pekerja
0.2 OH Tukang Kayu
0.02 OH Kepala Tukang
0.002 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.6 1 m' Pasang Genteng Bubung Plentong Besar

Bahan
4 Buah Genteng Bubung Plentong Besar
8 Kg Portland Semen
0.032 m3 Pasir Pasang
Tenaga
0.4 OH Pekerja
0.2 OH Tukang Kayu
0.02 OH Kepala Tukang
0.002 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.9 1 m2 Pasang Atap Asbes Gelombang (2,25x0,92 m) x 5 mm

Bahan
0.6 Lbr Asbes Gelombang
0.12 Kg Paku Pancing 60 x 230

Tenaga
0.14 OH Pekerja
0.075 OH Tukang Kayu
0.008 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 239 of 328 Analisa Pek. Penutup Atap
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

A.4.5.2.10 m2 Pasang Atap Asbes Gelombang (2,00x0,92 m) x 5 mm

Bahan
0.6 Lbr Asbes Gelombang
0.12 Kg Paku Pancing 60 x 230

Tenaga
0.14 OH Pekerja
0.07 OH Tukang Kayu
0.007 OH Kepala Tukang
0.007 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.12 1 m2 Pasang Atap Asbes Gelombang (3,00x1,05 m) x 4 mm

Bahan
0.35 Lbr Asbes Gelombang
0.12 Kg Paku Pancing 60 x 230

Tenaga
0.14 OH Pekerja
0.07 OH Tukang Kayu
0.007 OH Kepala Tukang
0.007 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.15 1 m2 Pasang Atap Asbes Gelombang (2,10x1,05 m) x 4 mm

Bahan
0.51 Lbr Asbes Gelombang
0.12 Kg Paku Pancing 60 x 230

HSPK Cipta Karya_2016P Page 240 of 328 Analisa Pek. Penutup Atap
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.14 OH Pekerja
0.067 OH Tukang Kayu
0.007 OH Kepala Tukang
0.007 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.30 1 m2 Pasang Atap Genteng Beton

Bahan
11 Lbr Genteng Beton Standrad
0.03 Kg Paku Biasa 2" - 5"

Tenaga
0.2 OH Pekerja
0.1 OH Tukang Kayu
0.01 OH Kepala Tukang
0.01 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.33 1 m2 Pasang Atap Sirap

Bahan
30 Lbr Genteng Sirap
0.2 Kg Paku Biasa 1/2" - 1"

Tenaga
0.166 OH Pekerja

HSPK Cipta Karya_2016P Page 241 of 328 Analisa Pek. Penutup Atap
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.25 OH Tukang Kayu


0.025 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.34 1 m' Pasang Nok Genteng Beton

Bahan
3.5 Buah Nok Genteng Beton
0.05 Kg Paku Biasa 2" - 5"
10.8 Kg Portland Semen
0.032 m3 Pasir Pasang
1 Kg Semen Warna

Tenaga
0.4 OH Pekerja
0.2 OH Tukang Kayu
0.02 OH Kepala Tukang
0.02 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.37 1 m' Pasang Nok Sirap

Bahan
0.4 Lbr Seng Plaat 3" x 6" BJLS 28
0.06 Kg Paku Biasa 1/2" - 1"
0.5 Kg Paku Biasa 2" - 5"

Tenaga
0.125 OH Pekerja
0.25 OH Tukang Kayu
0.025 OH Kepala Tukang
0.006 OH Mandor

HSPK Cipta Karya_2016P Page 242 of 328 Analisa Pek. Penutup Atap
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.38 1 m2 Pasang Atap Seng Gelombang


Bahan
0.7 Lbr Seng Gelombang 3" x 6" BJLS 30
0.02 Kg Paku Biasa 1/2" - 1"

Tenaga
0.12 OH Pekerja
0.06 OH Tukang Kayu
0.006 OH Kepala Tukang
0.006 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.39 1 m' Pasang Atap Nok Seng

Bahan
0.3 Lbr Seng Plaat 3" x 6" BJLS 28
0.04 Kg Paku Biasa 1/2" - 1"

Tenaga
0.15 OH Pekerja
0.07 OH Tukang Kayu
0.007 OH Kepala Tukang
0.006 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.2.42 1 m2 Pasang Allumunium Foil / Sisalation

Bahan
1.05 m2 Sisalation / Allumunium Foil

HSPK Cipta Karya_2016P Page 243 of 328 Analisa Pek. Penutup Atap
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.15 OH Pekerja
0.05 OH Tukang Kayu
0.005 OH Kepala Tukang
0.008 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 244 of 328 Analisa Pek. Penutup Atap
HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

83,556.00

63,750.00
2,550.00 63,750.00

12,210.00
45,000.00 6,750.00
60,000.00 4,500.00
60,000.00 480.00
60,000.00 480.00

75,960.00
7,596.00
83,556.00

104,181.00

82,500.00
3,300.00 82,500.00

12,210.00
45,000.00 6,750.00
60,000.00 4,500.00
60,000.00 480.00
60,000.00 480.00

94,710.00
9,471.00
104,181.00

51,711.00

34,800.00
2,900.00 34,800.00

HSPK Cipta Karya_2016P Page 245 of 328 Analisa Pek. Penutup Atap
HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

12,210.00
45,000.00 6,750.00
60,000.00 4,500.00
60,000.00 480.00
60,000.00 480.00

47,010.00
4,701.00
51,711.00

81,092.00

42,400.00
5,200.00 26,000.00
1,090.00 8,720.00
240,000.00 7,680.00

31,320.00
45,000.00 18,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 120.00

73,720.00
7,372.00
81,092.00

95,942.00

55,900.00
7,900.00 39,500.00
1,090.00 8,720.00
240,000.00 7,680.00

31,320.00

HSPK Cipta Karya_2016P Page 246 of 328 Analisa Pek. Penutup Atap
HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

45,000.00 18,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 120.00

87,220.00
8,722.00
95,942.00

78,892.00

40,400.00
6,000.00 24,000.00
1,090.00 8,720.00
240,000.00 7,680.00
31,320.00
45,000.00 18,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 120.00

71,720.00
7,172.00
78,892.00

5x0,92 m) x 5 mm 73,088.40

54,684.00
87,000.00 52,200.00
20,700.00 2,484.00

11,760.00
45,000.00 6,300.00
60,000.00 4,500.00
60,000.00 480.00
60,000.00 480.00

66,444.00
6,644.40

HSPK Cipta Karya_2016P Page 247 of 328 Analisa Pek. Penutup Atap
HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

73,088.40

0x0,92 m) x 5 mm 72,626.40

54,684.00
87,000.00 52,200.00
20,700.00 2,484.00

11,340.00
45,000.00 6,300.00
60,000.00 4,200.00
60,000.00 420.00
60,000.00 420.00

66,024.00
6,602.40
72,626.40

0x1,05 m) x 4 mm 42,040.90

26,879.00
69,700.00 24,395.00
20,700.00 2,484.00

11,340.00
45,000.00 6,300.00
60,000.00 4,200.00
60,000.00 420.00
60,000.00 420.00

38,219.00
3,821.90
42,040.90

0x1,05 m) x 4 mm 36,214.20

21,762.00
37,800.00 19,278.00
20,700.00 2,484.00

HSPK Cipta Karya_2016P Page 248 of 328 Analisa Pek. Penutup Atap
HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

11,160.00
45,000.00 6,300.00
60,000.00 4,020.00
60,000.00 420.00
60,000.00 420.00

32,922.00
3,292.20
36,214.20

65,448.90

43,299.00
3,900.00 42,900.00
13,300.00 399.00

16,200.00
45,000.00 9,000.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 600.00

59,499.00
5,949.90
65,448.90

89,221.00

56,660.00
1,800.00 54,000.00
13,300.00 2,660.00

24,450.00
45,000.00 7,470.00

HSPK Cipta Karya_2016P Page 249 of 328 Analisa Pek. Penutup Atap
HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

60,000.00 15,000.00
60,000.00 1,500.00
60,000.00 480.00

81,110.00
8,111.00
89,221.00

82,023.70

42,167.00
6,300.00 22,050.00
13,300.00 665.00
1,090.00 11,772.00
240,000.00 7,680.00
13,300.00 13,300.00

32,400.00
45,000.00 18,000.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 1,200.00

74,567.00
7,456.70
82,023.70

48,546.30

21,648.00
35,500.00 14,200.00
13,300.00 798.00
13,300.00 6,650.00

22,485.00
45,000.00 5,625.00
60,000.00 15,000.00
60,000.00 1,500.00
60,000.00 360.00

HSPK Cipta Karya_2016P Page 250 of 328 Analisa Pek. Penutup Atap
HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

44,133.00
4,413.30
48,546.30

58,108.60
43,106.00
61,200.00 42,840.00
13,300.00 266.00

9,720.00
45,000.00 5,400.00
60,000.00 3,600.00
60,000.00 360.00
60,000.00 360.00

52,826.00
5,282.60
58,108.60

25,203.20

11,182.00
35,500.00 10,650.00
13,300.00 532.00

11,730.00
45,000.00 6,750.00
60,000.00 4,200.00
60,000.00 420.00
60,000.00 360.00

22,912.00
2,291.20
25,203.20

18,877.50

8,347.50
7,950.00 8,347.50

HSPK Cipta Karya_2016P Page 251 of 328 Analisa Pek. Penutup Atap
HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

10,530.00
45,000.00 6,750.00
60,000.00 3,000.00
60,000.00 300.00
60,000.00 480.00

18,877.50
1,887.75
20,765.25

HSPK Cipta Karya_2016P Page 252 of 328 Analisa Pek. Penutup Atap
0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

IX A.4.5.1 PEKERJAAN LANGIT - LANGIT


Memasang Langit-langit Asbes (1,00x1,00) m,
A.4.5.1.1 1 m2 tebal 4 mm, 5 mm & 6 mm

Bahan
1.1 Lbr Plat Asbes
0.01 Kg Paku

Tenaga
0.03 OH Pekerja
0.07 OH Tukang Kayu
0.007 OH Kepala Tukang
0.004 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.1.2 1 m2 Memasang Langit-langit Akustik Ukuran (30x30) cm

Bahan
12.0 Lbr Akustik Uk.30 x 30 cm
0.05 Kg Paku

Tenaga
0.12 OH Pekerja
0.12 OH Tukang Kayu
0.012 OH Kepala Tukang
0.006 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.1.3 1 m2 Memasang Langit-langit Akustik Ukuran (30x60) cm

HSPK Cipta Karya_2016P Page 253 of 328 Analisa Pek. Langit2


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
5.80 Lbr Akustik
0.05 Kg Paku

Tenaga
0.10 OH Pekerja
0.10 OH Tukang Kayu
0.01 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.1.5 1 m2 Memasang Langit-langit Tripleks Uk (120x240) cm, Teb


4 mm & 6 mm

Bahan
0.375 Lbr Tripleks (4 mm)
0.03 Kg Paku Tripleks

Tenaga
0.10 OH Pekerja
0.10 OH Tukang Kayu
0.01 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6

Bahan
0.015 m3 Kayu Jati,Papan
0.01 Kg Paku

Tenaga
0.8 OH Pekerja

HSPK Cipta Karya_2016P Page 254 of 328 Analisa Pek. Langit2


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.8 OH Tukang Kayu


0.08 OH Kepala Tukang
0.04 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.1.7 1 m2 Memasng Langit-langit Gypsu Board, Uk


(120x240) tebal 9 mm

Bahan
0.364 Lbr Gypsum Board
0.11 Kg Paku Sekrup

Tenaga
0.1 OH Pekerja
0.05 OH Tukang Kayu
0.005 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.5.1.10 1 m1 List Langit-Langit Kayu Profil

Bahan
1.05 m1 List Kayu Profil
0.01 Kg Paku

Tenaga
0.05 OH Pekerja
0.05 OH Tukang Kayu
0.005 OH Kepala Tukang
0.003 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 255 of 328 Analisa Pek. Langit2


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

HSPK Cipta Karya_2016P Page 256 of 328 Analisa Pek. Langit2


HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

Asbes (1,00x1,00) m,
28,636.30

19,823.00
17,900.00 19,690.00
13,300.00 133.00

6,210.00
45,000.00 1,350.00
60,000.00 4,200.00
60,000.00 420.00
60,000.00 240.00

26,033.00
2,603.30
28,636.30

Akustik Ukuran (30x30) cm 88,379.50

66,665.00
5,500.00 66,000.00
13,300.00 665.00

13,680.00
45,000.00 5,400.00
60,000.00 7,200.00
60,000.00 720.00
60,000.00 360.00

80,345.00
8,034.50
88,379.50

Akustik Ukuran (30x60) cm 99,401.50

HSPK Cipta Karya_2016P Page 257 of 328 Analisa Pek. Langit2


HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

78,965.00
13,500.00 78,300.00
13,300.00 665.00

11,400.00
45,000.00 4,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 300.00

90,365.00
9,036.50
99,401.50

ripleks Uk (120x240) cm, Tebal 3 mm,


42,885.15

27,586.50
72,500.00 27,187.50
13,300.00 399.00

11,400.00
45,000.00 4,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 300.00

38,986.50
3,898.65
42,885.15

ambriziring Kayu Jati, tebal 6 mm 463,466.30

330,133.00
22,000,000.00 330,000.00
13,300.00 133.00

91,200.00
45,000.00 36,000.00

HSPK Cipta Karya_2016P Page 258 of 328 Analisa Pek. Langit2


HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 48,000.00
60,000.00 4,800.00
60,000.00 2,400.00

421,333.00
42,133.30
463,466.30

ypsu Board, Uk
37,009.72

25,545.20
59,300.00 21,585.20
36,000.00 3,960.00

8,100.00
45,000.00 4,500.00
60,000.00 3,000.00
60,000.00 300.00
60,000.00 300.00

33,645.20
3,364.52
37,009.72

10,607.30

3,913.00
3,600.00 3,780.00
13,300.00 133.00

5,730.00
45,000.00 2,250.00
60,000.00 3,000.00
60,000.00 300.00
60,000.00 180.00

9,643.00
964.30

HSPK Cipta Karya_2016P Page 259 of 328 Analisa Pek. Langit2


HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

10,607.30

HSPK Cipta Karya_2016P Page 260 of 328 Analisa Pek. Langit2


0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

X A.5.1.1 PEKERJAAN SANITASI

A.5.1.1.1 1 Unit Memasang Closet Duduk / Mono Blok

Bahan
1 Buah Kloset Duduk / Monoblok
0.06 Kelengkapan 6% dari harga Kloset

Tenaga
3.3 OH Pekerja
1.1 OH Tukang Batu
0.001 OH Kepala Tukang
0.16 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.2 1 Unit Memasang Closet Jongkok Porselen

Bahan
1 Buah Kloset Jongkok
6 Kg Portland Semen
0.01 m3 Pasir Pasang

Tenaga
1 OH Pekerja
1.5 OH Tukang Batu
1.5 OH Kepala Tukang
0.16 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.4 1 Unit Memasang Urinoir

HSPK Cipta Karya_2016P Page 261 of 328 Analisa Pek. Sanitasi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
1 Buah Urinoir
0.3 - Perlengkapan 30% Harga Urinoir
6 Kg Portland Semen
0.01 m3 Pasir Pasang

Tenaga
1 OH Pekerja
1 OH Tukang Batu
0.1 OH Kepala Tukang
0.1 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.5 1 Unit Memasang Wastafel

Bahan
1 Buah Wastafel Meja Oval
0.3 - Perlengkapan 30% Harga Wastafel
6 Kg Portland Semen
0.01 m3 Pasir Pasang

Tenaga
1.2 OH Pekerja
0.145 OH Tukang Batu
0.15 OH Kepala Tukang
0.1 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3

Bahan
150.0 bh Batu Bata

HSPK Cipta Karya_2016P Page 262 of 328 Analisa Pek. Sanitasi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

120 Kg Portland Semen


0.3 m3 Pasir Pasang
360 buah Porselen 11 x 11 cm
6 Kg Semen Nat

Tenaga
6 OH Pekerja
3 OH Tukang Batu
0.3 OH Kepala Tukang
0.03 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.35 1 m' Memasang Pipa Beton, Ø 20 cm

Bahan
1.1 Buah Pipa Beton
0.030 m3 Batu Bata
3.92 Kg Portland Semen
0.056 m3 Pasir Pasang
0.024 m3 Pasir Urug

Tenaga
0.14 OH Pekerja
0.07 OH Tukang Batu
0.007 OH Kepala Tukang
0.007 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.36 1 m' Memasang Pipa Beton, Ø 100 cm

Bahan
1.1 Buah Pipa Beton
0.55 m3 Batu Bata

HSPK Cipta Karya_2016P Page 263 of 328 Analisa Pek. Sanitasi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

10.3 Kg Portland Semen


0.061 m3 Pasir Pasang
0.069 m3 Pasir Urug

Tenaga
0.38 OH Pekerja
0.19 OH Tukang Batu
0.019 OH Kepala Tukang
0.019 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.25 1 m' Memasang Pipa PVC type AW Ø ½"

Bahan
1.2 m' Pipa PVC
0.35 Perlengkapan 35% Harga Pipa

Tenaga
0.036 OH Pekerja
0.06 OH Tukang Leideng
0.006 OH Kepala Tukang
0.0018 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.29 1 m' Memasang Pipa PVC type AW Ø 2"

Bahan
1.2 m' Pipa PVC
0.35 Perlengkapan 35% Harga Pipa

Tenaga
0.054 OH Pekerja
0.09 OH Tukang Leideng

HSPK Cipta Karya_2016P Page 264 of 328 Analisa Pek. Sanitasi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.009 OH Kepala Tukang


0.0027 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.31 1 m' Memasang Pipa PVC type AW Ø 3"

Bahan
1.2 m' Pipa PVC
0.35 Perlengkapan 35% Harga Pipa

Tenaga
0.081 OH Pekerja
0.135 OH Tukang Leideng
0.014 OH Kepala Tukang
0.0041 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.12 1 Buah Memasang Bak Cuci Piring Stainles Steel

Bahan
1 Buah Bak Cuci Stainles Steel
1 Set Water Drain & assesories

Tenaga
0.03 OH Pekerja
0.3 OH Tukang Leideng
0.03 OH Kepala Tukang
0.0015 OH Mandor

Jumlah Bahan dan Tenaga

HSPK Cipta Karya_2016P Page 265 of 328 Analisa Pek. Sanitasi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Overhead + Profit 10%


Jumlah Total

A.5.1.1.19 1 Buah Memasang Kran Ø ¾" atau ½"

Bahan
1 Buah Kran Air
0.025 Set Seal Tape

Tenaga
0.01 OH Pekerja
0.1 OH Tukang Leideng
0.01 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.5.1.1.14 1 Buah Memasang Floor Drain

Bahan
1 Buah Floor Drain

Tenaga
0.01 OH Pekerja
0.1 OH Tukang Batu
0.01 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 266 of 328 Analisa Pek. Sanitasi


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

1,958,030.80

1,555,868.00
1,467,800.00 1,467,800.00
1,467,800.00 88,068.00

224,160.00
45,000.00 148,500.00
60,000.00 66,000.00
60,000.00 60.00
60,000.00 9,600.00

1,780,028.00
178,002.80
1,958,030.80

414,744.00

142,440.00
133,500.00 133,500.00
1,090.00 6,540.00
240,000.00 2,400.00

234,600.00
45,000.00 45,000.00
60,000.00 90,000.00
60,000.00 90,000.00
60,000.00 9,600.00

377,040.00
37,704.00
414,744.00

546,084.00

HSPK Cipta Karya_2016P Page 267 of 328 Analisa Pek. Sanitasi


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

379,440.00
285,000.00 285,000.00
285,000.00 85,500.00
1,090.00 6,540.00
240,000.00 2,400.00

117,000.00
45,000.00 45,000.00
60,000.00 60,000.00
60,000.00 6,000.00
60,000.00 6,000.00

496,440.00
49,644.00
546,084.00

863,929.00

707,690.00
537,500.00 537,500.00
537,500.00 161,250.00
1,090.00 6,540.00
240,000.00 2,400.00

77,700.00
45,000.00 54,000.00
60,000.00 8,700.00
60,000.00 9,000.00
60,000.00 6,000.00

785,390.00
78,539.00
863,929.00

1,129,540.00

557,054.55
860.00 129,000.00

HSPK Cipta Karya_2016P Page 268 of 328 Analisa Pek. Sanitasi


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

1,090.00 130,800.00
240,000.00 72,000.00
404.04 145,454.55
13,300.00 79,800.00

469,800.00
45,000.00 270,000.00
60,000.00 180,000.00
60,000.00 18,000.00
60,000.00 1,800.00

1,026,854.55
102,685.45
1,129,540.00

131,252.00

107,980.00
62,500.00 68,750.00
645,000.00 19,350.00
1,090.00 4,272.80
240,000.00 13,440.00
90,300.00 2,167.20

11,340.00
45,000.00 6,300.00
60,000.00 4,200.00
60,000.00 420.00
60,000.00 420.00

119,320.00
11,932.00
131,252.00

550,140.47

469,347.70
75,000.00 82,500.00
645,000.00 354,750.00

HSPK Cipta Karya_2016P Page 269 of 328 Analisa Pek. Sanitasi


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

1,090.00 11,227.00
240,000.00 14,640.00
90,300.00 6,230.70

30,780.00
45,000.00 17,100.00
60,000.00 11,400.00
60,000.00 1,140.00
60,000.00 1,140.00

500,127.70
50,012.77
550,140.47

14,513.26

7,505.88
4,842.50 5,811.00
4,842.50 1,694.88

5,688.00
45,000.00 1,620.00
60,000.00 3,600.00
60,000.00 360.00
60,000.00 108.00

13,193.88
1,319.39
14,513.26

30,129.37

18,858.33
12,166.67 14,600.00
12,166.67 4,258.33

8,532.00
45,000.00 2,430.00
60,000.00 5,400.00

HSPK Cipta Karya_2016P Page 270 of 328 Analisa Pek. Sanitasi


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

60,000.00 540.00
60,000.00 162.00

27,390.33
2,739.03
30,129.37

53,389.88

35,735.25
23,055.00 27,666.00
23,055.00 8,069.25

12,801.00
45,000.00 3,645.00
60,000.00 8,100.00
60,000.00 810.00
60,000.00 246.00

48,536.25
4,853.63
53,389.88

385,264.00

329,000.00
164,500.00 164,500.00
164,500.00 164,500.00

21,240.00
45,000.00 1,350.00
60,000.00 18,000.00
60,000.00 1,800.00
60,000.00 90.00

350,240.00

HSPK Cipta Karya_2016P Page 271 of 328 Analisa Pek. Sanitasi


HARGA JUMLAH
BAHAN/UPAH HARGA
Rp Rp

35,024.00
385,264.00

27,434.00

17,590.00
17,500.00 17,500.00
3,600.00 90.00

7,350.00
45,000.00 450.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 300.00

24,940.00
2,494.00
27,434.00

27,995.00

18,100.00
18,100.00 18,100.00

7,350.00
45,000.00 450.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 300.00

25,450.00
2,545.00
27,995.00

HSPK Cipta Karya_2016P Page 272 of 328 Analisa Pek. Sanitasi


0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XI A.4.2.1 PEKERJAAN BESI & ALLUMUNIUM

A.4.2.1.1 1 Kg Memasang Besi Profil

Bahan
1.15 Kg Besi Profil
0.06 Kg Meni Besi

Tenaga
0.06 OH Pekerja
0.06 OH Tukang Besi
0.006 OH Kepala Tukang
0.003 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.2 1 kg Memasang Rangka Kuda-kuda Baja IWF

Bahan
1.15 kg Besi Baja IWF

Tenaga
0.06 OH Pekerja
0.06 OH Tukang Besi
0.006 OH Kepala Tukang
0.003 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.3 100 kg Mengerjakan Pekerjaan Perakitan (Kuda-kuda Baja)

Bahan
1 ltr Solar
0.1 ltr Minyak Pelumas

HSPK Cipta Karya_2016P Page 273 of 328 Analisa Pek. Besi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.100 OH Pekerja
0.100 OH Tukang Besi
0.001 OH Kepala Tukang
0.005 OH Mandor
0.800 Jam Sewa Alat

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total
1 m2 Membuat Pintu Besi Plat Baja tebal 2 mm rangkap, rangk
A.4.2.1.4 Siku

Bahan
15 Kg Besi Siku L.30.30.3
32.8 Kg Besi Plat Baja
0.05 Kg Kawat Las

Tenaga
1.05 OH Pekerja
1.05 OH Tukang Besi
0.105 OH Kepala Tukang
0.052 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.5 10 cm Mengerjakan Pengelasan dengan Las Listrik

Bahan
0.04 kg Kawat Las
0.03 ltr Solar
0.004 ltr Minyak Pelumas

Tenaga
0.04 OH Pekerja
0.02 OH Tukang Besi
0.002 OH Kepala Tukang

HSPK Cipta Karya_2016P Page 274 of 328 Analisa Pek. Besi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.002 OH Mandor
0.17 Jam Sewa Alat

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.7 1 m2 Memasang Pintu Rolling Door Besi

Bahan
1 m2 Pintu Gulung Besi

Tenaga
1.2 OH Pekerja
1.2 OH Tukang Besi
0.12 OH Kepala Tukang
0.006 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.8 1 m2 Memasang Pintu Lipat (Folding Door)

Bahan
1 m2 Pintu Lipat

Tenaga
0.44 OH Pekerja
0.44 OH Tukang Besi
0.044 OH Kepala Tukang
0.022 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.9 1 m2 Sunscreen Allumunium

Bahan

HSPK Cipta Karya_2016P Page 275 of 328 Analisa Pek. Besi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

1 m2 Sunscreen Allumunium

Tenaga
0.08 OH Pekerja
0.8 OH Tukang Besi
0.08 OH Kepala Tukang
0.004 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.10 1 m2 Memasang Rolling Door Allumunium

Bahan
1 m2 Rolling Allumunium

Tenaga
1 OH Pekerja
1 OH Tukang Besi
0.1 OH Kepala Tukang
0.05 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.11 1 m' Memasang Kusen Pintu Allumunium

Bahan
1.1 m' Profil Allumunium
2 buah Skrup Fixer
0.06 Tube Sealant

Tenaga
0.043 OH Pekerja
0.043 OH Tukang Besi
0.0043 OH Kepala Tukang
0.0021 OH Mandor

Jumlah Bahan dan Tenaga

HSPK Cipta Karya_2016P Page 276 of 328 Analisa Pek. Besi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Overhead + Profit 10%


Jumlah Total

A.4.2.1.12 1 m2 Memasang Pintu Allumunium Strip Lebar 8 cm

Bahan
4.4 m' Profil Allumunium
14.6 m' Allumunium Strip

Tenaga
0.085 OH Pekerja
0.085 OH Tukang Besi
0.0085 OH Kepala Tukang
0.0042 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.15 1 m2 Memasang Terali Besi Strip (2x3) cm

Bahan
6.177 m' Besi Strip 2x3
27.08 cm Pengelasan

Tenaga
1.67 OH Pekerja
1.67 OH Tukang Las
0.167 OH Kepala Tukang
0.083 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.16 1 m2 Memasang Kawat Nyamuk

Bahan
1.1 m2 Kawat Nyamuk nylon
11.11 cm Pengelasan
1.716 kg Baja Strip (0,2x2) cm

HSPK Cipta Karya_2016P Page 277 of 328 Analisa Pek. Besi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.1 OH Pekerja
0.1 OH Tukang Kayu
0.01 OH Kepala Tukang
0.0050 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.2.1.18 1 m' Memasang Talang Datar/Jurai , Seng BJLS 28 Lebar 90 c

Bahan
1.05 Lbr Seng Plaat
0.015 Kg Paku Biasa 1 - 2,5 cm
0.019 m3 Kayu Papan Klas II

Tenaga
0.20 OH Pekerja
0.4 OH Tukang Kayu
0.025 OH Kepala Tukang
0.01 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

1 m' Memasang Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJ


A.4.2.1.19
Lebar 45 cm

Bahan
1.05 Lbr Seng Plaat
0.01 Kg Paku Biasa 1 - 2,5 cm
0.5 Kg Besi strip

Tenaga
0.15 OH Pekerja
0.3 OH Tukang Kayu
0.03 OH Kepala Tukang
0.008 OH Mandor

HSPK Cipta Karya_2016P Page 278 of 328 Analisa Pek. Besi


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 279 of 328 Analisa Pek. Besi


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

26,923.60

17,636.00
14,000.00 16,100.00
25,600.00 1,536.00

6,840.00
45,000.00 2,700.00
60,000.00 3,600.00
60,000.00 360.00
60,000.00 180.00

24,476.00
2,447.60
26,923.60

kuda Baja IWF 25,234.00

16,100.00
14,000.00 16,100.00

6,840.00
45,000.00 2,700.00
60,000.00 3,600.00
60,000.00 360.00
60,000.00 180.00

22,940.00
2,294.00
25,234.00

erakitan (Kuda-kuda Baja) 81,961.00

7,650.00
5,150.00 5,150.00
25,000.00 2,500.00

HSPK Cipta Karya_2016P Page 280 of 328 Analisa Pek. Besi


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

66,860.00
45,000.00 4,500.00
60,000.00 6,000.00
60,000.00 60.00
60,000.00 300.00
70,000.00 56,000.00

74,510.00
7,451.00
81,961.00
Baja tebal 2 mm rangkap, rangka baja 840,213.00

644,160.00
14,000.00 210,000.00
13,200.00 432,960.00
24,000.00 1,200.00

119,670.00
45,000.00 47,250.00
60,000.00 63,000.00
60,000.00 6,300.00
60,000.00 3,120.00

763,830.00
76,383.00
840,213.00

dengan Las Listrik 17,989.95

1,214.50
24,000.00 960.00
5,150.00 154.50
25,000.00 100.00

15,140.00
45,000.00 1,800.00
60,000.00 1,200.00
60,000.00 120.00

HSPK Cipta Karya_2016P Page 281 of 328 Analisa Pek. Besi


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 120.00
70,000.00 11,900.00

16,354.50
1,635.45
17,989.95

515,416.00

335,000.00
335,000.00 335,000.00

133,560.00
45,000.00 54,000.00
60,000.00 72,000.00
60,000.00 7,200.00
60,000.00 360.00

468,560.00
46,856.00
515,416.00

olding Door) 440,176.00

350,000.00
350,000.00 350,000.00

50,160.00
45,000.00 19,800.00
60,000.00 26,400.00
60,000.00 2,640.00
60,000.00 1,320.00

400,160.00
40,016.00
440,176.00

362,054.00

272,500.00

HSPK Cipta Karya_2016P Page 282 of 328 Analisa Pek. Besi


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

272,500.00 272,500.00

56,640.00
45,000.00 3,600.00
60,000.00 48,000.00
60,000.00 4,800.00
60,000.00 240.00

329,140.00
32,914.00
362,054.00

Allumunium 537,900.00

375,000.00
375,000.00 375,000.00

114,000.00
45,000.00 45,000.00
60,000.00 60,000.00
60,000.00 6,000.00
60,000.00 3,000.00

489,000.00
48,900.00
537,900.00

123,363.90

107,250.00
97,500.00 107,250.00
- -
- -

4,899.00
45,000.00 1,935.00
60,000.00 2,580.00
60,000.00 258.00
60,000.00 126.00

112,149.00

HSPK Cipta Karya_2016P Page 283 of 328 Analisa Pek. Besi


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

11,214.90
123,363.90

ium Strip Lebar 8 cm 554,825.70

494,700.00
97,500.00 429,000.00
4,500.00 65,700.00

9,687.00
45,000.00 3,825.00
60,000.00 5,100.00
60,000.00 510.00
60,000.00 252.00

504,387.00
50,438.70
554,825.70

352,663.50

130,253.18
13,200.00 81,536.40
1,799.00 48,716.78

190,350.00
45,000.00 75,150.00
60,000.00 100,200.00
60,000.00 10,020.00
60,000.00 4,980.00

320,603.18
32,060.32
352,663.50

80,132.84

61,448.03
17,100.00 18,810.00
1,799.00 19,986.83
13,200.00 22,651.20

HSPK Cipta Karya_2016P Page 284 of 328 Analisa Pek. Besi


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

11,400.00
45,000.00 4,500.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 300.00

72,848.03
7,284.80
80,132.84

urai , Seng BJLS 28 Lebar 90 cm 178,061.95

126,774.50
35,500.00 37,275.00
13,300.00 199.50
4,700,000.00 89,300.00

35,100.00
45,000.00 9,000.00
60,000.00 24,000.00
60,000.00 1,500.00
60,000.00 600.00

161,874.50
16,187.45
178,061.95

gkaran Ø 15 cm, Seng Plaat BJLS 30 76,062.80

42,118.00
33,700.00 35,385.00
13,300.00 133.00
13,200.00 6,600.00

27,030.00
45,000.00 6,750.00
60,000.00 18,000.00
60,000.00 1,800.00
60,000.00 480.00

HSPK Cipta Karya_2016P Page 285 of 328 Analisa Pek. Besi


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

69,148.00
6,914.80
76,062.80

HSPK Cipta Karya_2016P Page 286 of 328 Analisa Pek. Besi


0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XII A.4.6.2 PEKERJAAN KUNCI dan KACA

A.4.6.2.2 1 Buah Memasang Kunci Tanam Biasa

Bahan
1 Buah Kunci Tanam Biasa

Tenaga
0.01 OH Pekerja
0.5 OH Tukang Kayu
0.01 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.3 1 Buah Memasang Kunci Kamar Mandi

Bahan
1 Buah Kunci Tanam Kamar Mandi

Tenaga
0.005 OH Pekerja
0.5 OH Tukang Kayu
0.005 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.4 1 Buah Memasang Kunci Selinder

Bahan
1 Buah Kunci Selinder / Kunci Tanam Biasa

HSPK Cipta Karya_2016P Page 287 of 328 Analisa Pek. Kunci dan Kaca
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.005 OH Pekerja
0.5 OH Tukang Kayu
0.005 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.5 1 Buah Memasang Engsel Pintu

Bahan
1 Buah Engsel pintu

Tenaga
0.015 OH Pekerja
0.15 OH Tukang Kayu
0.015 OH Kepala Tukang
0.0075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.6 1 Buah Pasang Engsel Jendela Kupu-kupu

Bahan
1 Buah Engsel Jendela

Tenaga
0.01 OH Pekerja
0.1 OH Tukang Kayu

HSPK Cipta Karya_2016P Page 288 of 328 Analisa Pek. Kunci dan Kaca
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.01 OH Kepala Tukang


0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.7 1 Buah Pasang Engsel Angin

Bahan
1 Buah Engsel Angin

Tenaga
0.02 OH Pekerja
0.2 OH Tukang Kayu
0.02 OH Kepala Tukang
0.01 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.9 1 Buah Pasang Kait Angin

Bahan
1 Buah Kait Angin

Tenaga
0.015 OH Pekerja
0.15 OH Tukang Kayu
0.015 OH Kepala Tukang
0.00075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.10 1 Buah Pasang Door Closer

HSPK Cipta Karya_2016P Page 289 of 328 Analisa Pek. Kunci dan Kaca
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
1 Buah Door Closer

Tenaga
0.05 OH Pekerja
0.5 OH Tukang Kayu
0.05 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.11 1 Buah Pasang Kunci Selot

Bahan
1 Buah Kunci Selot

Tenaga
0.02 OH Pekerja
0.2 OH Tukang Kayu
0.02 OH Kepala Tukang
0.001 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.13 1 Buah Pasang Door Stop

Bahan
1 Buah Door Stop

Tenaga
0.01 OH Pekerja
0.1 OH Tukang Kayu
0.01 OH Kepala Tukang
0.0005 OH Mandor

HSPK Cipta Karya_2016P Page 290 of 328 Analisa Pek. Kunci dan Kaca
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.14 1 Buah Pasang Rel Pintu Dorong

Bahan
1 Buah Rel Pintu Dorong

Tenaga
0.06 OH Pekerja
0.6 OH Tukang Kayu
0.06 OH Kepala Tukang
0.003 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.15 1 Buah Pasang Kunci Lemari

Bahan
1 Buah Kunci Lemari

Tenaga
0.025 OH Pekerja
0.25 OH Tukang Kayu
0.025 OH Kepala Tukang
0.00125 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.16 1 m2 Pasang Kaca tebal 3 mm

Bahan
1.1 m2 Kaca tebal 3mm

HSPK Cipta Karya_2016P Page 291 of 328 Analisa Pek. Kunci dan Kaca
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.015 OH Pekerja
0.15 OH Tukang Kayu
0.015 OH Kepala Tukang
0.00075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.17 1 m2 Pasang Kaca tebal 5 mm

Bahan
1.1 m2 Kaca tebal 5mm

Tenaga
0.015 OH Pekerja
0.15 OH Tukang Kayu
0.015 OH Kepala Tukang
0.00075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.6.2.19 1 m2 Pasang Kaca Cermin tebal 5 mm

Bahan
1.1 m2 Kaca Cermin

Tenaga
0.015 OH Pekerja
0.15 OH Tukang Kayu
0.015 OH Kepala Tukang
0.00075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 292 of 328 Analisa Pek. Kunci dan Kaca
HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

177,485.00

130,000.00
130,000.00 130,000.00

31,350.00
45,000.00 450.00
60,000.00 30,000.00
60,000.00 600.00
60,000.00 300.00

161,350.00
16,135.00
177,485.00

88,742.50

50,000.00
50,000.00 50,000.00

30,675.00
45,000.00 225.00
60,000.00 30,000.00
60,000.00 300.00
60,000.00 150.00

80,675.00
8,067.50
88,742.50

176,742.50

130,000.00
130,000.00 130,000.00

HSPK Cipta Karya_2016P Page 293 of 328 Analisa Pek. Kunci dan Kaca
HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

30,675.00
45,000.00 225.00
60,000.00 30,000.00
60,000.00 300.00
60,000.00 150.00

160,675.00
16,067.50
176,742.50

19,827.50

7,000.00
7,000.00 7,000.00

11,025.00
45,000.00 675.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 450.00

18,025.00
1,802.50
19,827.50

13,145.00

4,600.00
4,600.00 4,600.00

7,350.00
45,000.00 450.00
60,000.00 6,000.00

HSPK Cipta Karya_2016P Page 294 of 328 Analisa Pek. Kunci dan Kaca
HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 600.00
60,000.00 300.00

11,950.00
1,195.00
13,145.00

22,440.00

5,700.00
5,700.00 5,700.00

14,700.00
45,000.00 900.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 600.00

20,400.00
2,040.00
22,440.00

21,692.00

9,100.00
9,100.00 9,100.00

10,620.00
45,000.00 675.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 45.00

19,720.00
1,972.00
21,692.00

62,370.00

HSPK Cipta Karya_2016P Page 295 of 328 Analisa Pek. Kunci dan Kaca
HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

21,300.00
21,300.00 21,300.00

35,400.00
45,000.00 2,250.00
60,000.00 30,000.00
60,000.00 3,000.00
60,000.00 150.00

56,700.00
5,670.00
62,370.00

22,946.00

6,700.00
6,700.00 6,700.00

14,160.00
45,000.00 900.00
60,000.00 12,000.00
60,000.00 1,200.00
60,000.00 60.00

20,860.00
2,086.00
22,946.00

31,218.00

21,300.00
21,300.00 21,300.00

7,080.00
45,000.00 450.00
60,000.00 6,000.00
60,000.00 600.00
60,000.00 30.00

HSPK Cipta Karya_2016P Page 296 of 328 Analisa Pek. Kunci dan Kaca
HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

28,380.00
2,838.00
31,218.00

266,728.00

200,000.00
200,000.00 200,000.00

42,480.00
45,000.00 2,700.00
60,000.00 36,000.00
60,000.00 3,600.00
60,000.00 180.00

242,480.00
24,248.00
266,728.00

24,970.00

5,000.00
5,000.00 5,000.00

17,700.00
45,000.00 1,125.00
60,000.00 15,000.00
60,000.00 1,500.00
60,000.00 75.00

22,700.00
2,270.00
24,970.00

110,660.00

89,980.00
81,800.00 89,980.00

HSPK Cipta Karya_2016P Page 297 of 328 Analisa Pek. Kunci dan Kaca
HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

10,620.00
45,000.00 675.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 45.00

100,600.00
10,060.00
110,660.00

126,753.00

104,610.00
95,100.00 104,610.00

10,620.00
45,000.00 675.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 45.00

115,230.00
11,523.00
126,753.00

314,182.00

275,000.00
250,000.00 275,000.00

10,620.00
45,000.00 675.00
60,000.00 9,000.00
60,000.00 900.00
60,000.00 45.00

285,620.00
28,562.00
314,182.00

HSPK Cipta Karya_2016P Page 298 of 328 Analisa Pek. Kunci dan Kaca
0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XIII A.4.4.3 PEKERJAAN PENUTUP LANTAI dan DINDING

A.4.4.3.3 1 m2 Memasang lantai Ubin PC Abu-abu Uk. 20 x 20 cm

Bahan
26.5 Buah Ubin Abu-abu 20x20 cm
10.4 Kg Portland Semen
0.0450 m3 Pasir Pasang

Tenaga
0.27 OH Pekerja
0.135 OH Tukang Batu
0.014 OH Kepala Tukang
0.014 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.9 1 m2 Memasang lantai Ubin Granito Uk. 40

Bahan
6.63 Buah Ubin Granito 60x60 cm
9.8 Kg Portland Semen
0.045 m3 Pasir Pasang
1.300 Kg Semen Warna

Tenaga
0.250 OH Pekerja
0.125 OH Tukang Batu
0.013 OH Kepala Tukang
0.013 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 299 of 328 Analisa Pek. Lantai dan Dinding
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.4.3.19 1 m' Pasang Plint Ubin PC Warna Uk. 10 x 20 cm

Bahan
5.3 Buah Plint Ubin PC Warna 10 x 20 cm
1.14 Kg Portland Semen
0.003 m3 Pasir Pasang
0.1 Kg Semen Warna

Tenaga
0.09 OH Pekerja
0.09 OH Tukang Batu
0.009 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.35 1 m2 Memasang Lantai Keramik 30 x 30 cm

Bahan
11.87 Buah Ubin Keramik 30 x 30 cm
10.00 Kg Portland Semen
0.045 m3 Pasir Pasang
1.50 Kg Semen Warna

Tenaga
0.70 OH Pekerja
0.35 OH Tukang Batu
0.035 OH Kepala Tukang
0.035 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.36 1 m2 Pasang Lantai Keramik 50 x 50 cm

HSPK Cipta Karya_2016P Page 300 of 328 Analisa Pek. Lantai dan Dinding
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Bahan
26.5 Buah Ubin Keramik 50 x 50 cm
10.40 Kg Portland Semen
0.045 m3 Pasir Pasang
1.62 Kg Semen Warna

Tenaga
0.70 OH Pekerja
0.35 OH Tukang Batu
0.035 OH Kepala Tukang
0.035 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.39 1 m' Memasang Plint Keramik Ukuran 10x20 cm

Bahan
5.3 Buah Ubin Keramik 10 x 20 cm
1.14 Kg Portland Semen
0.003 m3 Pasir Pasang
0.025 Kg Semen Warna

Tenaga
0.09 OH Pekerja
0.09 OH Tukang Batu
0.009 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.40 1 m' Memasang Plint Keramik Ukuran 10x10 cm

Bahan
10.6 Buah Ubin Keramik 10 x 10 cm
1.14 Kg Portland Semen

HSPK Cipta Karya_2016P Page 301 of 328 Analisa Pek. Lantai dan Dinding
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.003 m3 Pasir Pasang


0.05 Kg Semen Warna

Tenaga
0.09 OH Pekerja
0.09 OH Tukang Batu
0.009 OH Kepala Tukang
0.005 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.43 1 m2 Memasang Lantai Marmer Ukuran 1.00x1.00 cm

Bahan
1.06 buah Marmer
8.19 kg Portland Semen
0.045 m3 Pasir Pasang
0.65 kg Semen Warna

Tenaga
0.7 OH Pekerja
0.35 OH Tukang Batu
0.035 OH Kepala Tukang
0.035 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.44 1 m2 Memasang Lantai Karpet

Bahan
1.05 m2 Karpet
0.35 kg Lem

Tenaga
0.17 OH Pekerja

HSPK Cipta Karya_2016P Page 302 of 328 Analisa Pek. Lantai dan Dinding
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.17 OH Tukang Batu


0.017 OH Kepala Tukang
0.009 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.46 1 m2 Memasang Lantai Parquet Jati

Bahan
1.05 m2 Parquet Jati
0.6 Kg Lem Vynil

Tenaga
0.70 OH Pekerja
0.35 OH Tukang Batu
0.035 OH Kepala Tukang
0.035 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.49 1 m2 Memasang Dinding Keramik 10x20 cm,

Bahan
53 Buah Keramik
9.3 Kg Portland Semen
0.018 m3 Pasir Pasang
2.75 Kg Semen Warna

Tenaga
0.9 OH Pekerja
0.45 OH Tukang Batu
0.045 OH Kepala Tukang
0.045 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%

HSPK Cipta Karya_2016P Page 303 of 328 Analisa Pek. Lantai dan Dinding
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Total

A.4.4.3.50 1 m2 Memasang Dinding Keramik 20x20 cm,

Bahan
26.5 Buah Keramik
9.3 Kg Portland Semen
0.018 m3 Pasir Pasang
1.94 Kg Semen Warna

Tenaga
0.9 OH Pekerja
0.45 OH Tukang Batu
0.045 OH Kepala Tukang
0.045 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.55 1 m2 Memasang Dinding Marmer Ukuran 1.00x1.00 cm

Bahan
1.06 buah Marmer
3.003 buah Paku 12 cm
12.44 kg Portlan Semen
0.025 m3 Pasir Pasang
0.65 kg Semen Warna

Tenaga
1.3 OH Pekerja
0.65 OH Tukang Batu
0.065 OH Kepala Tukang
0.065 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 304 of 328 Analisa Pek. Lantai dan Dinding
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.4.3.58 1 m2 Memasang Dinding Batu Paros / Batu Tempel Hitam


Bahan
1.10 m2 Batu Paros
11.75 Kg Portland Semen
0.035 m3 Pasir Pasang

Tenaga
0.70 OH Pekerja
0.35 OH Tukang Batu
0.035 OH Kepala Tukang
0.035 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.4.3.63 1 m' Memasang Plint Kayu Klas II Ukuran 2x10 cm


Bahan
0.003 m3 Papan Kayu Klas II
0.05 kg Paku Sekrup 5 cm

Tenaga
0.12 OH Pekerja
0.12 OH Tukang Batu
0.012 OH Kepala Tukang
0.006 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 305 of 328 Analisa Pek. Lantai dan Dinding
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

ANTAI dan DINDING

Abu-abu Uk. 20 x 20 cm 94,646.20

64,112.00
1,584.00 41,976.00
1,090.00 11,336.00
240,000.00 10,800.00

21,930.00
45,000.00 12,150.00
60,000.00 8,100.00
60,000.00 840.00
60,000.00 840.00

86,042.00
8,604.20
94,646.20

60x60cm 179,694.50

143,048.64
15,728.00 104,276.64
1,090.00 10,682.00
240,000.00 10,800.00
13,300.00 17,290.00

20,310.00
45,000.00 11,250.00
60,000.00 7,500.00
60,000.00 780.00
60,000.00 780.00

163,358.64
16,335.86
179,694.50

HSPK Cipta Karya_2016P Page 306 of 328 Analisa Pek. Lantai dan Dinding
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

na Uk. 10 x 20 cm 45,839.86

31,382.60
5,300.00 28,090.00
1,090.00 1,242.60
240,000.00 720.00
13,300.00 1,330.00

10,290.00
45,000.00 4,050.00
60,000.00 5,400.00
60,000.00 540.00
60,000.00 300.00

41,672.60
4,167.26
45,839.86

k 30 x 30 cm 160,175.60

88,914.18
3,981.82 47,264.18
1,090.00 10,900.00
240,000.00 10,800.00
13,300.00 19,950.00

56,700.00
45,000.00 31,500.00
60,000.00 21,000.00
60,000.00 2,100.00
60,000.00 2,100.00

145,614.18
14,561.42
160,175.60

191,224.00

HSPK Cipta Karya_2016P Page 307 of 328 Analisa Pek. Lantai dan Dinding
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

117,140.00
2,772.00 73,458.00
1,090.00 11,336.00
240,000.00 10,800.00
13,300.00 21,546.00

56,700.00
45,000.00 31,500.00
60,000.00 21,000.00
60,000.00 2,100.00
60,000.00 2,100.00

173,840.00
17,384.00
191,224.00

Ukuran 10x20 cm 20,198.31

8,072.10
1,090.00 5,777.00
1,090.00 1,242.60
240,000.00 720.00
13,300.00 332.50

10,290.00
45,000.00 4,050.00
60,000.00 5,400.00
60,000.00 540.00
60,000.00 300.00

18,362.10
1,836.21
20,198.31

Ukuran 10x10 cm 20,564.06

8,404.60
545.00 5,777.00
1,090.00 1,242.60

HSPK Cipta Karya_2016P Page 308 of 328 Analisa Pek. Lantai dan Dinding
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

240,000.00 720.00
13,300.00 665.00

10,290.00
45,000.00 4,050.00
60,000.00 5,400.00
60,000.00 540.00
60,000.00 300.00

18,694.60
1,869.46
20,564.06

Ukuran 1.00x1.00 cm 631,338.51

517,244.10
461,200.00 488,872.00
1,090.00 8,927.10
240,000.00 10,800.00
13,300.00 8,645.00

56,700.00
45,000.00 31,500.00
60,000.00 21,000.00
60,000.00 2,100.00
60,000.00 2,100.00

573,944.10
57,394.41
631,338.51

177,930.50

142,345.00
125,000.00 131,250.00
31,700.00 11,095.00

19,410.00
45,000.00 7,650.00

HSPK Cipta Karya_2016P Page 309 of 328 Analisa Pek. Lantai dan Dinding
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

60,000.00 10,200.00
60,000.00 1,020.00
60,000.00 540.00

161,755.00
16,175.50
177,930.50

348,942.00

260,520.00
230,000.00 241,500.00
31,700.00 19,020.00

56,700.00
45,000.00 31,500.00
60,000.00 21,000.00
60,000.00 2,100.00
60,000.00 2,100.00

317,220.00
31,722.00
348,942.00

mik 10x20 cm, 199,872.20

108,802.00
1,090.00 57,770.00
1,090.00 10,137.00
240,000.00 4,320.00
13,300.00 36,575.00

72,900.00
45,000.00 40,500.00
60,000.00 27,000.00
60,000.00 2,700.00
60,000.00 2,700.00

181,702.00
18,170.20

HSPK Cipta Karya_2016P Page 310 of 328 Analisa Pek. Lantai dan Dinding
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

199,872.20

mik 20x20 cm, 186,855.90

96,969.00
2,140.00 56,710.00
1,090.00 10,137.00
240,000.00 4,320.00
13,300.00 25,802.00

72,900.00
45,000.00 40,500.00
60,000.00 27,000.00
60,000.00 2,700.00
60,000.00 2,700.00

169,869.00
16,986.90
186,855.90

er Ukuran 1.00x1.00 cm 728,548.15

557,016.50
461,200.00 488,872.00
13,300.00 39,939.90
1,090.00 13,559.60
240,000.00 6,000.00
13,300.00 8,645.00

105,300.00
45,000.00 58,500.00
60,000.00 39,000.00
60,000.00 3,900.00
60,000.00 3,900.00

662,316.50
66,231.65
728,548.15

HSPK Cipta Karya_2016P Page 311 of 328 Analisa Pek. Lantai dan Dinding
HARGA JUMLAH
KERJAAN BAHAN/UPAH HARGA
Rp Rp

Paros / Batu Tempel Hitam 239,973.25


161,457.50
127,500.00 140,250.00
1,090.00 12,807.50
240,000.00 8,400.00

56,700.00
45,000.00 31,500.00
60,000.00 21,000.00
60,000.00 2,100.00
60,000.00 2,100.00

218,157.50
21,815.75
239,973.25

s II Ukuran 2x10 cm 43,923.00


26,250.00
8,150,000.00 24,450.00
36,000.00 1,800.00

13,680.00
45,000.00 5,400.00
60,000.00 7,200.00
60,000.00 720.00
60,000.00 360.00

39,930.00
3,993.00
43,923.00

HSPK Cipta Karya_2016P Page 312 of 328 Analisa Pek. Lantai dan Dinding
0

No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

XIV A.4.7.1 PEKERJAAN PENGECATAN

A.4.7.1.1 1 m2 Mengikis / Mengerok Permukaan Cat Tembok Lama

Bahan
0.05 Kg Soda Api

Tenaga
0.15 OH Pekerja
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.2 1 m2 Mencuci Bidang Permukaan Tembok yang Pernah dicat

Bahan
0.05 Kg Sabun

Tenaga
0.15 OH Pekerja
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.3 1 m2 Mengerok Karat Cat Lama permukaan Baja dg cara manua

Bahan
0.05 Kg Sabun

Tenaga
0.15 OH Pekerja
0.0025 OH Mandor

HSPK Cipta Karya_2016P Page 313 of 328 Analisa Pek. Pengecatan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.4 1 m2 Pengecatan Bidang Kayu Baru (1 lap.Plamir)


1 lap.Cat Dasar & 2 lap.Cat Penutup

Bahan
0.2 Kg Cat Meni
0.15 Kg Plamir
0.17 Kg Cat Dasar
0.26 Kg Cat Penutup 2 kali
0.01 Bh Kuas
0.03 Kg Pengencer
0.20 Lbr Amplas

Tenaga
0.07 OH Pekerja
0.009 OH Tukang Cat
0.006 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.5 1 m2 Pengecatan Bidang Kayu Baru (1 lap.Plamir)


1 lap.Cat Dasar & 3 lap.Cat Penutup

Bahan
0.2 Kg Cat Meni
0.15 Kg Plamir
0.17 Kg Cat Dasar
0.35 Kg Cat Penutup 2 kali
0.01 Bh Kuas

HSPK Cipta Karya_2016P Page 314 of 328 Analisa Pek. Pengecatan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

0.03 Kg Pengencer
0.20 Lbr Amplas

Tenaga
0.07 OH Pekerja
0.105 OH Tukang Cat
0.004 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil

Bahan
0.36 Ltr Teak Oil

Tenaga
0.04 OH Pekerja
0.063 OH Tukang Cat
0.063 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur

Bahan
0.15 Ltr Politur
0.372 Ltr Politur Jadi
2 Lbr Amplas

HSPK Cipta Karya_2016P Page 315 of 328 Analisa Pek. Pengecatan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Tenaga
0.06 OH Tukang Cat
0.016 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter

Bahan
0.35 Ltr Residu atau Ter

Tenaga
0.1 OH Pekerja
0.006 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis

Bahan
0.15 Ltr Vernis
0.05 Ltr Dempul
0.1 Lbr Ampelas
0.01 Buah Kuas

Tenaga
0.16 OH Pekerja
0.16 OH Tukang Cat
0.016 OH Kepala Tukang
0.0025 OH Mandor

HSPK Cipta Karya_2016P Page 316 of 328 Analisa Pek. Pengecatan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.10 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


2 lap. Cat Penutup)

Bahan
0.1 Kg Plamir
0.1 Kg Cat Dasar
0.26 Kg Cat Penutup 2 kali

Tenaga
0.02 OH Pekerja
0.063 OH Tukang Cat
0.0063 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.11 1 m2 Pengecat Tembok Lama (1lap.Plamir, 2lap Cat Penutup)

Bahan
0.1 Kg Cat Dasar
0.18 Kg Cat Penutup 2 kali

Tenaga
0.028 OH Pekerja
0.042 OH Tukang Cat
0.0042 OH Kepala Tukang
0.0025 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 317 of 328 Analisa Pek. Pengecatan


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN

A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi

Bahan
0.1 Kg Meni Besi
0.01 Kg Perekat / Lem

Tenaga
0.02 OH Pekerja
0.2 OH Tukang Cat
0.002 OH Kepala Tukang
0.01 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

A.4.7.1.17 1 m2 Pengecatan Permukaan Baja dg Meni Besi & Perancah

Bahan
0.1 Kg Meni Besi
0.01 Kg Perekat / Lem
0.002 m3 Perancah Kayu

Tenaga
0.25 OH Pekerja
0.225 OH Tukang Cat
0.0225 OH Kepala Tukang
0.0075 OH Mandor

Jumlah Bahan dan Tenaga


Overhead + Profit 10%
Jumlah Total

HSPK Cipta Karya_2016P Page 318 of 328 Analisa Pek. Pengecatan


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

mukaan Cat Tembok Lama 8,288.50

635.00
12,700.00 635.00

6,900.00
45,000.00 6,750.00
60,000.00 150.00

7,535.00
753.50
8,288.50

an Tembok yang Pernah dicat 8,305.00

650.00
13,000.00 650.00

6,900.00
45,000.00 6,750.00
60,000.00 150.00

7,550.00
755.00
8,305.00

permukaan Baja dg cara manual 8,305.00

650.00
13,000.00 650.00

6,900.00
45,000.00 6,750.00
60,000.00 150.00

HSPK Cipta Karya_2016P Page 319 of 328 Analisa Pek. Pengecatan


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

7,550.00
755.00
8,305.00

Baru (1 lap.Plamir) 36,570.60

29,046.00
22,100.00 4,420.00
27,500.00 4,125.00
34,200.00 5,814.00
51,500.00 13,390.00
7,500.00 75.00
11,400.00 342.00
4,400.00 880.00

4,200.00
45,000.00 3,150.00
60,000.00 540.00
60,000.00 360.00
60,000.00 150.00

33,246.00
3,324.60
36,570.60

Baru (1 lap.Plamir) 47,873.10

33,681.00
22,100.00 4,420.00
27,500.00 4,125.00
34,200.00 5,814.00
51,500.00 18,025.00
7,500.00 75.00

HSPK Cipta Karya_2016P Page 320 of 328 Analisa Pek. Pengecatan


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

11,400.00 342.00
4,400.00 880.00

9,840.00
45,000.00 3,150.00
60,000.00 6,300.00
60,000.00 240.00
60,000.00 150.00

43,521.00
4,352.10
47,873.10

26,697.00

14,760.00
41,000.00 14,760.00

9,510.00
45,000.00 1,800.00
60,000.00 3,780.00
60,000.00 3,780.00
60,000.00 150.00

24,270.00
2,427.00
26,697.00

43,972.94

35,265.40
50,700.00 7,605.00
50,700.00 18,860.40
4,400.00 8,800.00

HSPK Cipta Karya_2016P Page 321 of 328 Analisa Pek. Pengecatan


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

4,710.00
60,000.00 3,600.00
60,000.00 960.00
60,000.00 150.00

39,975.40
3,997.54
43,972.94

g Cat Residu & Ter 7,642.53

2,087.75
5,965.00 2,087.75

4,860.00
45,000.00 4,500.00
60,000.00 360.00

6,947.75
694.78
7,642.53

25,905.00

5,640.00
25,000.00 3,750.00
27,500.00 1,375.00
4,400.00 440.00
7,500.00 75.00

17,910.00
45,000.00 7,200.00
60,000.00 9,600.00
60,000.00 960.00
60,000.00 150.00

HSPK Cipta Karya_2016P Page 322 of 328 Analisa Pek. Pengecatan


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

23,550.00
2,355.00
25,905.00

lap.Plamir, 1lap Cat Dasar 16,587.56

9,871.60
29,500.00 2,950.00
16,800.00 1,680.00
20,160.00 5,241.60

5,208.00
45,000.00 900.00
60,000.00 3,780.00
60,000.00 378.00
60,000.00 150.00

15,079.60
1,507.96
16,587.56

1lap.Plamir, 2lap Cat Penutup) 10,439.88

5,308.80
16,800.00 1,680.00
20,160.00 3,628.80

4,182.00
45,000.00 1,260.00
60,000.00 2,520.00
60,000.00 252.00
60,000.00 150.00

9,490.80
949.08
10,439.88

HSPK Cipta Karya_2016P Page 323 of 328 Analisa Pek. Pengecatan


HARGA JUMLAH
AKERJAAN BAHAN/UPAH HARGA
Rp Rp

Baja dg Meni Besi 18,146.70

2,877.00
25,600.00 2,560.00
31,700.00 317.00

13,620.00
45,000.00 900.00
60,000.00 12,000.00
60,000.00 120.00
60,000.00 600.00

16,497.00
1,649.70
18,146.70

Baja dg Meni Besi & Perancah 36,439.70

6,577.00
25,600.00 2,560.00
31,700.00 317.00
1,850,000.00 3,700.00

26,550.00
45,000.00 11,250.00
60,000.00 13,500.00
60,000.00 1,350.00
60,000.00 450.00

33,127.00
3,312.70
36,439.70

HSPK Cipta Karya_2016P Page 324 of 328 Analisa Pek. Pengecatan


PEMERINTAH KABUPATEN PEMALANG
KECAMATAN PEMALANG
KELURAHAN PADURAKSA

RENCANA ANGGARAN BIAYA


PEMBANGUNAN SARANA OLAH RAGA

ALAMAT :
Jl. Santadiharaja, Kelurahan Paduraksa, Kec.pemalang
Kabupaten Pemalang
Pekerjaan Urugan ( 50 m3)

Pekerjaan Urugan

A.2.3.1.1 6.1 1 m3 Menggali Tanah Biasa Sedalam 1 m Harga Satuan

6.1.2 Tenaga
0.75 OH Pekerja 45,000.00
0.025 OH Mandor 60,000.00

Jumlah Tenaga
Overhead + Profit 10%
Jumlah Total

2 Pemasangan List Lapngan

a Pekerjaan Pasangan Bata Merah

1) Tenaga kerja

2) Bahan
Bahan
Pasair
Semen

3) Alat
Cangkul
Cetok
Ember

b Pekerjaan Plesteran
Tenaga

Bahan
Pasai
Semen

3
38,775.00

35,250.00
33,750.00
1,500.00

35,250.00
3,525.00
38,775.00
Rekapitulasi
Pekerjan urugan
Pekrejran lapangan Bvvolye

Pe