DOUBLE SUCCESS CONSTRUCTION SDN BHD

6, JALAN PJS 7/20A, BANDAR SUNWAY , 46150 PETALING JAYA , SELANGOR DARUL EHSAN.

Tel : 03 – 5621 8301 Fax : 03 – 5621 6919 email : ds.construction@gmail.com

PROJECT : CADANGAN MEMBINA SEBUAH GUDANG 3 TINGKAT BARANGAN SEJUK


BEKU DAN RUANG PEMBUNGKUSAN , 4 TINGKAT PEJABAT BESERTA SATU TNGKAT
RUANG BAWAH TANAH TEMPAT LETAK KERETA DI ATAS LOT 38557 GRN 55367, NO
17 JALAN DELIMA 1/1, SUBANG HITECH INDUSTRIAL PARK 4000 SHAH ALAM , PEKAN
COUNTRY HEIGHTS, DAERAH PETALING , SELANGOR DARUL EHSAN UNTUK
TETUAN LUXURY PRUDENCE SDN BHD .

_______________________________________________________________________________

FORMWORK INSTALLATION - METHOD STATEMENT :

Objective :
Formwork Installation has several safety requirements that you must comply to not only save
the life of our workers, Safety is of considerable concern for a builder when installing
formwok and components.
1. SCOPE

This procedure applies to the installation of formwork and the controls required during
assembly, erection and final positioning of formwork used in Structural concrete
operations.

2. PROCEDURE

.1 All formwork activities will be carried out in accordance with the specification.

.2 After studying the structural drawings, the Project Engineer will plan for sizes,
numbers and type of formwork to be used in consultation with the Structural Engineer, if
required. Depending upon the programme, the number of repetitions will be decided.
External designers may be used for specific systems.

.3 Availability of formwork will be checked with the Procurement Manager and decision
will be taken to buy, hire or reuse formwork material.

.4 During fabrication of formwork shutters, all dimensions shall be cross-checked with


a view to avoiding corrective action during erection.

.5 Paint reference numbers on all panels to ensure their use in correct positions.

.6 Ensure that the props, shores, waling, bearers, clamps and tie rods are the right
size and at the correct spacings. The Formwork supervisor shall check the falsework
system with respect to load imposed on it and design parameters as laid down in the
specification.

.7 Check that the falsework is securely braced and is on a firm foundation according to
P.E Design .

.8 Forms fastened to previously cast concrete must be tightly fixed to prevent grout
loss. Cellular foam plastic strips can be used to make a seal.

.9 Check quality of shutter lining, tightness of bolts and wedges, built-in items, inserts
and other embedments.

.10 Tie – rod holes to be made in the formwork shall be neat so that they can be
patched or plugged later on.

.12 Particular attention will be paid to the rigidity and line of stop ends and joint
formers.

.13 Remove all tie-wire clippings and nails, which may stain both the formwork and the
concrete.

.14 Ensure that adequate access and working platforms are in place for the concreting
gang and that toe boards and guardrails are provided.

.15 A spreader or lifting beam shall be used to prevent distortion when placing
formwork.

.16 Adjustable steel props shall be erected in plumb and verticality of props checked
using a spirit level.

.17 A prop should not be used if it is bent, creased or, rusted or has a bent head or
base plate, damaged pin etc.

.18 Proper release of agent shall be used so that it can be removed without damaging
the surface finish of the concrete.

.19 New timber and plywood forms shall be given first coat of the appropriate release
agent 36 hours in advance, then a second coat just before they are used. Avoid
excessive use of release agent as this can cause staining or retardation of the concrete.

.20 A close watch should be kept on all wedges and fastenings. Make sure that they
do not work loose. Grout loss is an indication that some movement has occurred.

.21 When unsleeved tie bars are being used, ease them slightly before the concrete
sets, and remove them as soon as it is safe.

.22 Striking the Formwork:

i) Always obtain approval before striking the formwork .

ii) Ensure adequate safety measures while striking formwork.


iii) Cleaning the face of forms shall start as soon as they have been struck.

iv) Good storage is essential to ensure that formwork can be used again.

v) Paint code numbers on them so that they can be readily identified when next
needed.

.23 Safety During Formwork Operations:

1. Joint inspection by COW and Site supervisor on the day of formwork installation
completed. Documented and approved by COW. Inspection must be referred to
formwork PE design attached.

2. Scaffolder Inspector approved the falsework installation within 7 days before the
concreting works start. All works shall comply with safety procedure or instruction set
out in project safety plan and municipality rules and regulations.
3. The weights of large prefabricated sections of formwork should be marked on
them so that the lifting capacity of the crane at the working radius is not
exceeded. Lifting points are usually provided.

4. If necessary, a spreader or lifting beam shall be used to prevent distortion.

5. Where lifting is done by the vertical soldiers, check that they are adequately
connected to the walings.

6. Fire extinguishers in working order shall be in close proximity to the stored


formwork.

Prepared by Approved by

Name Name

Designation Designation

Date : Date :