You are on page 1of 7

11. G.R. No. 178610. November 17, 2010.

* MeTC ruled that the nature of HSBCL-SRP’s demands for


payment is civil and has no connection to the ongoing labor
Hongkong and Shanghai Banking Corp., Ltd. Staff Retirement
dispute. Gerong and Editha Broqueza’s termination from
Plan vs. Broqueza
employment resulted in the loss of continued benefits under
CARPIO, J.: their retirement plans. Thus, the loans secured by their future
retirement benefits to which they are no longer entitled are
FACTS:
reduced to unsecured and pure civil obligations. As unsecured
A petition for review assailing the Decision promulgated by the and pure obligations, the loans are immediately demandable.
CA. The appellate court granted the petition filed by Fe Gerong
The Regional Trial Court’s Ruling
(Gerong) and Spouses Bienvenido and EdithaBroqueza (spouses
Broqueza) and dismissed the consolidated complaints filed by The RTC initially denied the joint appeal because of the belated
Hongkong and Shanghai Banking Corporation, Ltd. - Staff filing of Gerong and the spouses Broqueza’s memorandum. The
Retirement Plan (HSBCL-SRP) for recovery of sum of money. RTC later reconsidered the order of denial and resolved the
issues in the interest of justice.The RTC ruled that Gerong and
The HSBCL-SRP is a retirement plan established by HSBC
EdithaBroqueza’s termination from employment disqualified
through its Board of Trustees for the benefit of the employees.
them from availing of benefits under their retirement plans. As a
Petitioner [Editha] Broqueza obtained a car loan in the amount consequence, there is no longer any security for the loans.
of Php175,000.00 and she again applied and was granted an HSBCL-SRP has a legal right to demand immediate settlement
appliance loan in the amount of Php24,000.00. On the other of the unpaid balance because of Gerong and EdithaBroqueza’s
hand, petitioner Gerongapplied and was granted an emergency continued default in payment and their failure to provide new
loan in the amount of Php35,780.00.These loans are paid security for their loans. Moreover, the absence of a period
through automatic salary deduction. within which to pay the loan allows HSBCL-SRP to demand
immediate payment. The loan obligations are considered pure
A labor dispute arose between HSBC and its employees.
obligations, the fulfillment of which are demandable at once.
Majority of HSBC’s employees were terminated, among whom
are petitioners Editha Broqueza and Fe Gerong. The employees Gerong and the spouses Broqueza then filed a Petition for
then filed an illegal dismissal case before the National Labor Review under Rule 42 before the CA.
Relations Commission (NLRC) against HSBC. Because of their
The Ruling of the Court of Appeals
dismissal, petitioners were not able to pay the monthly
amortizations of their respective loans. Thus, respondent The CA ruled that the HSBCL-SRP’s complaints for recovery of
HSBCL-SRP considered the accounts of petitioners delinquent. sum of money against Gerong and the spouses Broqueza are
Demands to pay the respective obligations were made upon premature as the loan obligations have not yet matured.
petitioners, but they failed to pay.”
HSBCL-SRP filed a motion for reconsideration which the CA
The Metropolitan Trial Court’s Ruling denied for lack of merit.
HSBCL-SRP filed a manifestation withdrawing the petition concession covering an area of 2,000 hectares southwest of and
against Gerong because she already settled her obligations.The adjoining the area of the concession subject of the deed of
CA granted the motion, and considered the case against Gerong assignment.
closed and terminated.
Consequently, petitioners, now acting as timber license holders
ISSUE: by virtue of the deed of assignment executed by private
respondent in their favor, entered into a Forest Consolidation
Whether or not the obligation is a pure obligation and is
Agreement with other ordinary timber license holders in Misamis
demandable at once.
Oriental, namely, Vicente L. De Lara, Jr., Salustiano R. Oca and
HELD: Sanggaya Logging Company. Under this consolidation
agreement, they all agreed to pool together and merge their
The SC affirmed the findings of the MeTC and the RTC that
respective forest concessions into a working unit, as envisioned
there is no date of payment indicated in the Promissory Notes.
by the aforementioned directives.The working unit was
The RTC is correct in ruling that since the Promissory Notes do
subsequently incorporated as the North Mindanao Timber
not contain a period, HSBCL-SRP has the right to demand
Corporation, with the petitioners and the other signatories of
immediate payment. Article 1179 of the Civil Code applies. The
the aforesaid Forest Consolidation Agreement as incorporators.
spouses Broqueza’s obligation to pay HSBCL-SRP is a pure
obligation. The fact that HSBCL-SRP was content with the prior For failure of petitioners to pay the balance due under the two
monthly check-off from EdithaBroqueza’s salary is of no deeds of assignment, private respondent filed an action against
moment. Once EdithaBroqueza defaulted in her monthly petitioners, based on the said contracts, for the payment of the
payment, HSBCL-SRP made a demand to enforce a pure amount of P83,138.15 with interest at 6% per annum from April
obligation. 10, 1967 until full payment, plus P12,000.00 for attorney’s fees
and costs.
12. G.R. No. 48194. March 15, 1990.*
Petitioners filed their answer admitting the due execution of the
JOSE M. JAVIER and ESTRELLA F. JAVIER, petitioners, vs.
contracts but interposing the special defense of nullity thereof
COURT OF APPEALS and LEONARDO TIRO, respondents.
since private respondent failed to comply with his contractual
REGALADO, J.: obligations and, further, that the conditions for the
enforceability of the obligations of the parties failed to
FACTS:
materialize. As a counterclaim, petitioners sought the return of
Private respondent is a holder of an ordinary timber license P55,586.00 which private respondent had received from them
issued by the Bureau of Forestry covering 2,535 hectares in the pursuant to an alleged management agreement, plus attorney’s
town of Medina, Misamis Oriental. fees and costs.

At the time the said deed of assignment was executed, private ISSUE:
respondent had a pending application, for an additional forest
Whether or not contract is null and void.
HELD: prayed that he be declared the absolute owner entitled to the
possession of this parcel, that the transfer of the same by the
The SC agreed with petitioners that they cannot be held liable
municipality of Tarlac to the Province of Tarlac be annulled, and
thereon. The efficacy of said deed of assignment is subject to
the transfer certificate issued to the Province of Tarlac
the condition that the application of private respondent for an
cancelled.
additional area for forest concession be approved by the Bureau
of Forestry. Since private respondent did not obtain that The lower court dismissed the complaint.
approval, said deed produces no effect. When a contract is
ISSUE:
subject to a suspensive condition, its birth or effectivity
can take place only if and when the event which Whether or not the termination of the contract is valid.
constitutes the condition happens or is fulfilled. If the
HELD:
suspensive condition does not take place, the parties would
stand as if the conditional obligation had never existed. The plaintiff has no right of action. If he has any, it is only by
virtue of the sale of this parcel made by Concepcion Cirer and
13. [No. 24190. July 13, 1926]
James Hill in his favor, but that sale cannot have any effect,
GEORGE L. PARKS, plaintiff and appellant, vs. PROVINCE OF This parcel having been donated by Concepcion Cirer and
TARLAC, MUNICIPALITY OF TARLAC, CONCEPCION CIRER, and James Hill to the municipality of Tarlac, which donation was
JAMES HILL, her husband, defendants and appellees. accepted by the latter, the title to the property was transferred
to the municipality of Tarlac. It is true that the donation might
AVANCEÑA, C. J.:
have been revoked for the causes, if any, provided by the law,
FACTS: Concepcion Cirer and James Hill, the owners of parcel but the fact is that it was not revoked when Concepcion Cirer
of land No. 2 referred to in the complaint, donated it perpetually and James Hill made the sale of this parcel to the plaintiff. Even
to the municipality of Tarlac, Province of Tarlac, under certain supposing that causes existed for the revocation of this
conditions specified in the public document in which they made donation, still, it was necessary, in order to consider it revoked,
this donation. The donation was accepted by Mr. Santiago de either that the revocation had been consented to by the donee,
Jesus in the same document on behalf of the municipal council the municipality of Tarlac, or that it had been judicially decreed.
of Tarlac of which he was the municipal president. The parcel None of these circumstances existed when Concepcion Cirer and
thus donated was later registered in the name of the donee, the James Hill sold this parcel to the plaintiff. Consequently, when
municipality of Tarlac. the sale was made Concepcion, Cirer and James Hill were no
longer the owners of this parcel and could not have sold it to
The plaintiff, George L. Parks, alleging that the conditions of the
the plaintiff, nor could the latter have acquired it from them.
donation had not been complied with and invoking the sale of
this parcel of land made by Concepcion Cirer and James Hill in The appellant refers to the condition imposed that one of the
his favor, brought this action against the Province of Tarlac, the parcels donated was to be used absolutely and exclusively for
municipality of Tarlac, Concepcion Cirer and James Hill and the erection of a central school and the other for a public park,
the work to commence in both cases within the period of six Respondent Northwestern University (Northwestern), an
months from the date of the ratification by the parties of the educational institution offering maritime-related courses,
document evidencing the donation. It is true that this condition engaged the services of a Quezon City-based firm, petitioner GL
has not been complied with. The allegation, however, that it is a Enterprises, to install a new IBS in Laoag City. The installation
condition precedent is erroneous. The characteristic of a of an IBS, used as the students’ training laboratory, was
condition precedent is that the acquisition of the right is not required by the Commission on Higher Education (CHED) before
effected while said condition is not complied with or is not a school could offer maritime transportation programs.
deemed complied with. Meanwhile nothing is acquired and there
Since its IBS was already obsolete, respondent required
is only an expectancy of right. Consequently, when a condition
petitioner to supply and install specific components in order to
is imposed, the compliance of which cannot be effected except
form the most modern IBS that would be acceptable to CHED
when the right is deemed acquired, such condition cannot be a
and would be compliant with the standards of the International
condition precedent. In the present case the condition that a
Maritime Organization (IMO). For this purpose, the parties
public school be erected and a public park made of the donated
executed two contracts.
land, work on the same to commence within six monthsf rom
the date of the ratification of the donation by the parties, could Subsequently, Northwestern paid P1 million as down payment
not be complied with except after giving effect to the donation. to GL Enterprises. The former then assumed possession of
The donee could not do any work on the donated land if the Northwestern’s old IBS as trade-in payment for its service.
donation had not really been effected, because it would be an Thus, the balance of the contract price remained at P1.97
invasion of another's title, for the land would have continued to million.
belong to the donor so long as the condition imposed was not
Two months after the execution of the contracts, GL Enterprises
complied with.
technicians delivered various materials to the project site.
14. G.R. No. 188986. March 20, 2013.* However, when they started installing the components,
respondent halted the operations. GL Enterprises then asked for
GALILEO A. MAGLASANG, doing business under the name GL
an explanation.
Enterprises, petitioner, vs. NORTHWESTERN UNIVERSITY, INC.,
respondent. Northwestern justified the work stoppage upon its finding that
the delivered equipment were substandard.9 It explained
SERENO, C.J.:
further that GL Enterprises violated the terms and conditions of
FACTS: the contracts, since the delivered components (1) were old; (2)
did not have instruction manuals and warranty certificates; (3)
A petition was filed seeking a review of the Court of Appeals
contained indications of being reconditioned machines; and (4)
(CA). The CA held that petitioner substantially breached its
did not meet the IMO and CHED standards. Thus, Northwestern
contracts with respondent for the installation of an integrated
demanded compliance with the agreement and suggested that
bridge system (IBS).
GL Enterprises meet with the former’s representatives to iron
out the situation.
HELD:
Instead of heeding this suggestion, GL Enterprises filed for
This time, applying Article 1191 of the Civil Code, the CA
breach of contract. Petitioner alleged that Northwestern
declared the rescission of the contracts.
breached the contracts by ordering the work stoppage and thus
preventing the installation of the materials for the IBS. The power to rescind the obligations of the injured party is
implied in reciprocal obligations, such as in this case. On this
Northwestern denied the allegation. Hence, it prayed for the
score, the CA correctly applied Article 1191, which provides
rescission of the contracts and made a compulsory counterclaim
thus:
for actual, moral, and exemplary damages, and attorney’s fees.
The power to rescind obligations is implied in reciprocal ones, in
The RTC held both parties at fault. It found that Northwestern
case one of the obligors should not comply with what is
unduly halted the operations, even if the contracts called for a
incumbent upon him.
completed project to be evaluated by the CHED. In turn, the
breach committed by GL Enterprises consisted of the delivery of The injured party may choose between the fulfillment and the
substandard equipment that were not compliant with IMO and rescission of the obligation, with the payment of damages in
CHED standards as required by the agreement. either case. He may also seek rescission, even after he has
chosen fulfillment, if the latter should become impossible.
Invoking the equitable principle that “each party must bear its
own loss,” the trial court treated the contracts as impossible of Given that petitioner, without justification, supplied substandard
performance without the fault of either party or as having been components for the new IBS, it is thus clear that its violation
dissolved by mutual consent. Consequently, it ordered mutual was not merely incidental, but directly related to the essence of
restitution, which would thereby restore the parties to their the agreement pertaining to the installation of an IBS compliant
original positions as follows:11 with the CHED and IMO standards. Consequently, the CA
correctly found substantial breach on the part of petitioner.
Aggrieved, both parties appealed to the CA, the appellate court
ultimately determined that GL Enterprises was the one guilty of In contrast, Northwestern’s breach, if any, was characterized by
substantial breach and liable for attorney’s fees. the appellate court as slight or casual.By way of negative
definition, a breach is considered casual if it does not
ISSUE:
fundamentally defeat the object of the parties in entering into
Whether or not there is a substantial breach of contract onthe an agreement. Furthermore, for there to be a breach to begin
part of the petitioner. with, there must be a “failure, without legal excuse, to perform
any promise which forms the whole or part of the contract.”
Here, as discussed, the stoppage of the installation was
justified. The action of Northwestern constituted a legal excuse
to prevent the highly possible rejection of the IBS. Hence, just
as the CA concluded, we find that Northwestern exercised follow and remained in force until the end of the contract
ordinary prudence to avert a possible wastage of time, effort, period.
resources and also of the P2.9 million representing the value of
Complaints from EMI employees and workers were pouring in
the new IBS.
that their HMO cards were not being honored by the DLSUMC
15. G.R. No. 162802. October 9, 2013.* and other hospitals and physicians, EMI formally notified HCI
that it was rescinding their Agreement on account of HCI’s
EDS MANUFACTURING, INC., petitioner, vs. HEALTHCHECK
serious and repeated breach of its undertaking including but not
INTERNATIONAL, INC., respondent.
limited to the unjustified non-availability of services. It
PERALTA, J.: demanded a return of premium for the unused period, giving a
ballpark figure of P6 million.
FACTS:
HCI pre-empted EMI’s threat of legal action by instituting the
This is a Petition for Review on Certiorari seeking the reversal of
present case before the Regional Trial Court of Pasig. The cause
the Decisionof the Court of Appeals (CA).
of action it presented was the unlawful pretermination of the
The plaintiff Healthcheck Inc. is a Health Maintenance contract and failure of EMI to submit to a joint reconciliation of
Organization (HMO) that provides prepaid health and medical accounts and deliver such assets as properly belonged to HCI.
insurance coverage to its clients, one of which is the De La Salle EMI responded with an answer alleging that HCI reneged on its
University Medical Center located at Dasmariñas, Cavite. Being duty to provide adequate medical coverage after EMI paid the
within the access of this medical facility, the defendant Eds premium in full. Having rescinded the contract, it claimed that it
Manufacturing Inc. with about 5,000 employees at Imus, Cavite was entitled to the unutilized portion of the premium, and that
saw fit to obtain insurance coverage from it. They entered into the accounting required by HCI could not be undertaken until it
a one-year contract as host of medical services and benefits. submitted the monthly utilization reports mentioned in the
Agreement.
Only two months into the program, problems began to loom in
the horizon. On July 17, HCI notified EMI that its accreditation EMI’s rescission of the Agreement was not done through court
with DLSUMC was suspended and advised it to avail of the action or by a notarial act and was based on casual or slight
services of nearby accredited institutions. breaches of the contract. Moreover, despite the announced
rescission, the employees of EMI continued to avail of HCI’s
Although HCI had yet to settle its accounts with it, DLSUMC
services.
resumed services.In another meeting with EMI, HCI undertook
to settle all its accounts with DLSUMC in order to maintain its ISSUE:
accreditation. Despite this commitment, HCI failed to preserve
Whether or not there was a valid rescission of the Agreement
its credit standing with DLSUMC prompting the latter to suspend
between the parties.
its accreditation for a second. A third suspension was still to
HELD:
There was no valid rescission.The power to rescind obligations submitted by HCI shows entries as late as March 1999,
is implied in reciprocal ones, in case one of the obligors should signifying that EMI employees were availing of the services until
not comply with what is incumbent upon him. the contract period were almost over. The continued use by
them of their privileges under the contract, with the apparent
The injured party may choose between the fulfillment and the
consent of EMI, belies any intention to cancel or rescind it, even
rescission of the obligation, with the payment of damages in
as they felt that they ought to have received more than what
either case. He may also seek rescission, even after he has
they got.
chosen fulfillment, if the latter should become impossible.
The court shall decree the rescission claimed, unless there be
just cause authorizing the fixing of a period.
The general rule is that rescission (more appropriately,
resolution) of a contract will not be permitted for a slight or
casual breach, but only for such substantial and fundamental
violations as would defeat the very object of the parties in
making the agreement.
Consequently, even if the right to rescind is made available to
the injured party, the obligation is not ipso facto erased by the
failure of the other party to comply with what is incumbent
upon him. The party entitled to rescind should apply to the
court for a decree of rescission. The right cannot be exercised
solely on a party’s own judgment that the other committed a
breach of the obligation. The operative act which produces the
resolution of the contract is the decree of the court and not the
mere act of the vendor. Since a judicial or notarial act is
required by law for a valid rescission to take place, the letter
written by respondent declaring his intention to rescind did not
operate to validly rescind the contract.
What is more, it is evident that EMI had not rescinded the
contract at all. As observed by the CA, despite EMI’s
pronouncement, it failed to surrender the HMO cards of its
employees although this was required by the Agreement, and
allowed them to continue using them beyond the date of the
rescission. The in-patient and the out-patient utilization reports

You might also like