NOC for 66kV Mandasar Substation Date: 20/07/2018

Points Status
1.    Control Room:
a.    Office Room:
 i.   One tube light is not working. Pending
b.   Battery Room:
 i.   One tube light is not working. Pending
ii.   4 air vents missing and 2 air vents are damaged. Attended
iii.   Cell No. 55 and No. 8 are weak. Attended
c.    Laboratory Area:
 i.   RO plant not working. Pending
ii.   One tube light is not working. Pending
d.   Toilet area:
 i.   2 Nos. out of 3 Lamps is not working in gent’s toilet. Attended
ii.   1 Nos of Lamp is not working in ladies toilet.   Pending
e.   Control Room:
 i.   Control Room Door is damaged. Attended
ii.   DC Leakage Lamps are not available. Pending
iii.   3 CRP (11KV Panel) Keys are damaged out of 6 Nos. Pending
f.     Tube well & Motor
 i.   Submersible borewell motor is not working. Attended
ii.   Submersible underground tank motor is not working.Attended
g.    Testing Reports are missing (last results available from 2015). Provided in soft copy
2.    11KV Control Panels
a.    Main Incomer-1
 i.   Panel light not working. Attended
ii.   MW meter is not working. Pertain to GETCO
b.   Station TR
 i.   MW meter is not working. Pertain to GETCO
c.    SARSANA AG 
 i.   Test Position indication lamp is not working. Attended
ii.   Test Service Mechanical indication is not working. Attended
iii.   MW Meter is not working. Pertain to GETCO
iv.   Panel light not working. Attended
d.   Hirana JGY
 i.   Test Position indication lamp is not working. Attended
ii.   Test Service Mechanical indication is not working. Attended
iii.   MW Meter is not working. Pertain to GETCO
iv.   Panel light not working. Attended
e.   Mandasar JGY
 i.   Test and Service indication lamps are ON at same time. Attended
ii.   Test Service Mechanical indication is not working. Attended
iii.   MW Meter is not working. Pertain to GETCO
iv.   Panel light not working. Attended
v.   Spring Charge indication lamp is not working. Attended
f.     Vijaliya AG
 i.   Test Service Mechanical indication is not working. Attended
ii.   MW Meter is not working. Pertain to GETCO
iii.   Panel light not working. Attended
g.    Mothalia AG
 i.   MW meter not working. Pertain to GETCO
ii.   Test Service Mechanical indication is not working. Attended
h.   Bus coupler
 i.   Panel light lamp is missing. Attended
i.      Main Incomer-2
 i.   AC fail indication lamp is not working. Attended
3.    LT panel
 i.   R & B indication lamp is not working. Attended
4.    Battery Charger
 i.   Alarm test system is not working. Pending
ii.   Leakage current is 15mA. Pending
5.    RTCC
a.    RTCC-1
 i.   B phase LED not working. Pending
ii.   Tap changing in process LED and Hooter is not working. Pending
iii.   Remote operation is not working. Attended
iv.   Tap indicator is not working. Attended
b.   RTCC-2
 i.   Tap changing in progress Hooter is not working.
6.    66KV CRP
a.    66kV Lunasar - Mandasar Line
 i.   AC fail indication in Annuciator is always ON. Pending
ii.   Isolator Semaphore is not working. Pending
iii.   MW meter is not working. Pertain to GETCO
 iv.   Glass of MW meter and KV meter is damaged. Pending
b.   66/11kV 15MVA TR-1
 i.   Panel door lock is damaged. Pending
ii.   Panel light is not working. Attended
c.    66/11kV 15MVA TR-2
 i.   Isolator semaphore is not working. Pending
7.    Fire fighting system
a.    Dry powder - 2 Nos – Refilled in Feb. Attended
b.   CO2- 22 kg – 2 Nos – Refilling Pending. Attended
c.    CO2- 6.5 kg – 2 Nos – Refilling Pending. Attended
d.   Mechanical Form – 50 lit. – 1 Nos – Refilling Pending. Attended
8.    Switchyard
a.    TR-1 Bay
 i.   LV cable support structure need to be painted. Pending
ii.   Y phase CT bellow position is above normal mark. Pertain to GETCO
b.   TR-2 Bay
 i.   Radiator Bottom valve is having minor oil leakage inn TR.
Pending
ii.    LV cable support structure need to be painted. Pending
iii.   OLTC breather Silica Gel need to replace. Attended
 iv.   Oil cup in breather is missing. Attended
c.    66kV Lunasar - Mandasar Line Bay
 i.   B Phase CT bellow position is above normal mark. Pertain to GETCO
d.   Store
 i.   One tube light is not working. Attended
ii.   One distribution board is damaged. Attended
e.   All earth strip need to be painted. Attended
f.     3 nos earthpit cover is missing. Pending
g.    All earth pit covers, Fencing, Entry gate, street light pole, 
       Support structure of MK box & ACDB box. Earth pit-ok fencing-ok Gate-ok Street light pole-pending, mk box& acdb box-ok
h.   6 Nos out of 12 Flood light are not working. Pending
i.      2 Doom lights of gate are not working. Pending
j.     All street light are not working. Pending
k.    5 Nos. of Wall fixtures are not working. Attended
l.      Cable trench lamps are not working. Attended
9.    Quarter
a.    Quarter – 1
 i.   4 Nos lamps are missing. Attended
b.   Quarter – 2
 i.   1 Nos. Fan is not working properly. Pending
ii.   6 Nos. Lamps are missing. Attended
iii.   3 Nos. Tube lights are not properly working. Pending
c.    One lamp is missing in staircase lobby. Attended 