LARGE DIAMETER PILE FOUNDATIONS FOR RAJIV GANDHI
SEA LINK (BANDRA-WORLI) PROJECT IN MUMBAL
D.B. Deshpande TT Nashikkar ‘SM. Sabnis
President, Joint Managing Director, Chief Engineer, Maharashtra
Indian Roads Congress, Maharashtra State Road State Road Development
(Former Secretary, PWD,
Maharashtra) & Advisor,
MSRDC Ltd. Mumbai
SYNOPSIS
Bandra Worli Sea Link (named now as Rajiv Gandhi
Sea Link) is 4.7 km long eight lane bridge constructed
over the Arabian Sea to facilitate speedy travel between
the westem suburbs and the island city of Mumbai
and the first phase of the West Island Freeway. The
e constructed using pre cast segmental technology
comprises two large cable stayed bridges. The entire
bridge is provided with large diameter pile foundations
socketted in rock. The present Paper describes the
general features of the pile foundations (over 600 piles
of 1.5 and 2 m dia.) including the highlights of the
Osterberg’s Load Cell Test, which was carried out for
the first time in this country.
1 PROJECT PROFILE
‘The Bandra Worli Sea Link Project is the first phase
of the proposed west island freeway aiming to connect,
the suburb of Bandra to the southem business district
at Nariman Point by a freeway abutting the western
coast of Mumbai. The eight lane high speed facility
is a 4,7 km long bridge on the Arabian Sea across the
Mahim bay with the superstructure constructed using
the precast segmental technique. The first four lanes of
the bridge were commissioned on 30th June 2009. The
google map showing the alignment of the bridge, abird’s
eye view of the constructed bridge and the spanning
arrangement is shown in Fig. 1. The index plan of the
bridge highlighting the general arrangement is shown
in Fig.2. The bridge has, for most part, continuous units
Development
Corporation Ltd., Mumbai
Corporation Ltd, Mumbai
Fig. 1A bird's eye view of Bandra Worli Sea Link
INDIAN HIGHWAYS, NOVEMBER 2009
25‘TECHNICAL PAPERS
EE TTT
pf Re
‘Approech Road 8 To 1G Lane State of Art toll plaza wth modern
Pasa ‘at contol and survliancs system
Banara Approach Bago | Precast SegmenialSpan-Span 7a 7 we wa] ts808
Banara 688 Free Balance Cantlover Method mr 7 woo | aaa
na approach bridge | Precast Sognantal Spay Span Tas 7 wo | 090
Wor CoB Free Balance CantloverMothod By 7 a x0 | as
‘Wort aporoach bilge | Precast Sepmeral Spay Span we Fa @ ae aa
Tink Bidar Precast Sagmanal Spanby Span 7a 3 sanoae | a va6re
Conatcton» Preesat gers
Toa for One Carageway wee eae
Fig. 2 Index Plan of Bandra Worli Sealink Project
comprising spans 50 m cle constructed with precast
segmental span by span method (referred to as approach
spans). The bridge also has two cable stayed bridges, a
'500 m span supported on a single central pylon (that is
two spans 25m e/e back to back) and another with a
span of 150 m to facilitate navigation under the bridges
The cable stayed bridges are also constructed using
precast segmental technology by the free cantilever
method. The precast segments themselves are box
type with a fish belly shape. ‘The substructure for the
approach spans comprises hollow reinforced concrete
piers supported on pile caps. The foundations both for
‘the approach spans as well as the cable stayed bridges
are large diameter pile foundations with piles of 1.5
im diameter used for the approach spans and piles of
2 m diameter used for the cable stayed bridges and for
the link bridge at the Worli end. The concrete used for
the superstructure and the substructure was M60 grade
using micorsilica, while the drilled shafts were cast in
M $0 grade concrete using microsilica.
2 PILE FOUNDATIONS
‘Mis Sverdrup Asia Led. and M’s DAR consultants were
entrusted with the design of the approach spans and
the cable stayed spans of the bridge respectively. The
‘geotechnical investigations and foundation proposal
‘were carried out by M/s Conrad Felice & Co. (USA).
‘The current project proposal was conceived around
the year 1999. The project of construction of a large
number of grade separated interchanges was taken up
around the same time in the city of Mumbai to relieve
traffic congestion on the major roads in the city. The
parameters which became determinants in the choice
of foundation type were the incidence of geology in
‘the Mumbai metropolitan region, the desired speed of
construction, presence of large number of utilities on
‘urban roads and the acknowledgement of the availability
of rotary drilling rigs capable of speedy drilling for
piles with diameters of 1.2 m for foundations. Having,
considered these parameters. in their entirety, rock
socketted pile foundations had been made mandatory
26
INDIAN HIGHWAYS, NOVEMBER 2009‘TECHNICAL PAPERS
in the Mumbai flyovers project. A greatly satisfactory
performance of such foundations in the flyovers project
clearly weighed in favour of pile foundations for the
Bandra Worli Sea Link Project. With significantly high
‘working loads ranging upto 25 MN in the project, large
diameter drilled shafts were warranted for the project
further obligating the contractors to deploy reverse
circulation drilling rigs. The choice of pile foundations
involving such large diameter drilled shafts was
mandated also from the consideration that the bridge
alignment for some part, runs within an eco sensitive
zone (CRZ-1) and these foundations are regarded as the
least invasive type.
3 GENERAL ARRANGEMENT OF PILE
FOUNDATIONS
‘The approach bridge structure with units of $0 m spans
are founded on piers rising over pile caps which are in
tum supported on four piles each of 1.5 m diameter. The
main cable stayed bridge stands supported on a central
pylon rising to a height of 128 m above the sea level
and founded on a pylon cap about 2000 sq m plan area
and 6 m deep. The pylon cap is supported by 52 piles
each of 2 m diameter sockeited to 2 length of about 20
m within rock. The Worli cable stayed bridge pylons
are also founded on pile foundations involving 2 m
diameter piles. The working loads on piles are in the
range of 3 MN to 25 MN. The link bridge which is the
connector to Worli Sea Face is provided with pre cast
girders and deck slab type superstructure for a length
of about 500 m with spans of about 25 m c/c and the
four lane carriageway is supported on two piles each
of 2 m diameter. With the exception of the portion of
the link bridge as aforesaid, where pile caps are done
away with, the rest of the pile caps are constructed using
cofferdams since the construction thereof lies below the
high tide level.
4 LOAD TESTING
Working loads on the drilled shafts vary between
3 MN to 25 MN. Carrying out load testing through a
conventional arrangement with use of jacks or weights
for loading a test pile against a reaction frame was ruled
‘out owing both to the high working loads and marine
conditions. The initial load test was performed using the
Osterberg’s load cell. The load cell test was conducted
on four drilled shafts three being of 1.5 m diameter
and one of 2 m diameter. The load testing using the
Osterberg’s method and the results are discussed in the
following paragraphs. The integrity of the constructed
piles was tested using cross-hole sonic logging test.
5 GEOLOGY OF THE AREA
The project is located along the western flank of the
geological formation called “Deccan Trap”. Extensive
research on Mumbai and the surrounding areas has,
shown that a series of volcanic eruptions and ensuing
lava flows covered the project area after the rifting of
plateau basalts while the subcontinent was moving
towards the north east during the cretaceous period
roughly 65 million years ago. These lava flows were
deposited predominantly under sub aqueous conditions
giving rise to spilitic pillow flows and tholeiitic basalt
flows. The rocks of Bombay, Salsette and Trombay
islands are the weathered remnants of these basalt
flows. Rock types consist of basalts, volcanic tufts,
and breccias and some intertrappean deposits. The rock
is overlain by completely weathered rock and residual
soils. These weathered rock beds in some places are
overlain by transported soils, calcareous sandstone,
and thin beds of coarse grained conglomerate. The top
of these strata are covered by soft silty clay in places,
especially in Mahim Bay. The water depth along the
alignment of the bridge ranges from about 3 m to about
8m,
6 ») GEOTECHNICAL INVESTIGATIONS
The subsoil and geotechnical investigations had been
carried out using a jack up platform and drilling rig. The
boring comprised drilling using NW drill rods and a 3.1
1m long triple tube core barrel with a face discharging
diamond core bit. The boringjdrilling was carried out
in all kinds of soil/rock strata with collection of soil
samples at regular intervals as per the specification. After
encountering rock, rock coring was carried out using
NX size Double Tube Core barrel fitted with diamond
Grill bits and reamer shells in the boreholes of varied
depths of 25 m, 40 m and 60 m below seabed. Boring,
‘was carried out at about 200 locations and invariably at
each pier location, Standard tests on undisturbed soil
samples and tests on rock samples were conducted to
appreciate the strata. Tests conducted included inter alia
INDIAN HIGHWAYS, NOVEMBER 2009
277