You are on page 1of 1

VRV INSPECTION AND PRE-COMMISSIONING FORM

VRV SERIES VRV III VRV IV

Please fill in the form for each system that is to be commissioned and send back the document atleast one week prior to the commissioning date.
The signed form shall be sent back to the following email address: techresponse@daikinmcquayme.com (cc: service@daikinmcquayme.com)
Date: Project: Installer:
Installation Data
Address: Contact Person:
Country: Mobile Phone No.:
Proposed Commissioning Date:
System Model (Check applicable model) Checklist (Check the column for items inspected on-site)
VRV-III VRV-IV (NC) VRV-IV (Cont. M) VRV-IV (Cont. S) General Check
RXYQ5P RXYQ8T RYMQ8T RYYQ8T Is the outdoor unit adequately supported according to its weight?
RXYQ8P RXYQ10T RYMQ10T RYYQ10T Is the outdoor unit mounted on good foundation?
RXYQ10P RYMQ12T
RXYQ12T RYYQ12T Is there no risk of air short cycling around the outdoor unit?
RXYQ12P
RXYQ14T RYMQ14T RYYQ14T Outdoor unit service space is provided and sufficient for maintenance?
RXYQ14P
RXYQ16T RYMQ16T RYYQ16T Piping Check
RXYQ16P RXYQ18T RYMQ18T RYYQ18T Uses proper copper pipes able to handle 40 Bar (4 MPa) pressure?
RXYQ18P RXYQ20T RYMQ20T RYYQ20T Are all refrigeration field pipes insulated properly?
RXYQ20P RXYQ22T RYMQ22T Was the pipe brazing done with proper Nitrogen ventilation?
RXYQ22P RXYQ24T RYMQ24T Are the refnet joints and headers correctly installed? (angles and position?)
RXYQ24P RXYQ26T RYMQ26T Was nitrogen pressure test done at 40 Bar for 24 Hrs?
RXYQ26P RXYQ28T
RYMQ28T Was the field piping vacuumed, and kept under vacuum for atleast 1 Hr?
RXYQ28P RXYQ30T RYMQ30T Was vacuum break done w/ R410a to create positive pressure on the piping?
RXYQ30P RXYQ32T RYMQ32T Length of liquid field piping (in meters) 7/8": 1/2":
RXYQ32P RXYQ34T RYMQ34T 3/4": 3/8":
RXYQ34P RXYQ36T RYMQ36T 5/8": 1/4":
RXYQ36P RXYQ38T RYMQ38T Electrical and Field Wiring
RXYQ38P RXYQ40T RYMQ40T
The size power of wires is according to electrical regulation?
RXYQ40P RXYQ42T RYMQ42T
Electrical Breakers are properly rated?
RXYQ42P RXYQ44T RYMQ44T
Properly rated ELCB/RCCB (Earth Leakage Circuit Breakers) are installed?
RXYQ44P RXYQ46T RYMQ46T
RXYQ48T RYMQ48T
Power was witched ON for atleast 6 hours before the commissioning?
RXYQ46P
RXYQ48P RXYQ50T RYMQ50T
F1/F2 and Q1/Q2 cable is sheathed vinyl 0.75-1.25 mm2 cable with 2 cores?
RXYQ50P RXYQ52T RYMQ52T
All indoor units and outdoor units are completely and properly wired?
RXYQ52P RXYQ54T RYMQ54T
Remote controls are properly installed and wired on the system?
RXYQ54P Power supply from mains are available on-site? (Recommended)
Generator is used to start-up the system?(Proper regulated power is required)
The indoor unit power supply is secured from the user (only for service use)?
Please write the complete O.U. model name and serial
Drain Pipe Check
no. in case it does not appear above
Outdoor Unit Model Name Serial No. Are drain pipes completely insulated?
O.U.1 (Master) Slope of drain pipes are correct?
O.U. 2 (Slave1) Leak check on drain pipe has been tested?
O.U. 3 (Slave2) Is there smooth flow of water in the Drain?
Indoor Units Model Name Serial No. Indoor Unit Check
Indoor Unit 1 Indoor unit brackets are strong enough to support the unit?
Indoor Unit 2 Indoor unit mounting and horizontal level is correct?
Indoor Unit 3 Indoor unit spaces are sufficient to create air flow (suction and discharge)?
Indoor Unit 4 Indoor service space provides access to the field piping/Air filter/Indoor PCB?
Indoor Unit 5 Centralized Controller check Central Remote I-Touch I-TManager Not Applicable

Indoor Unit 6 Centralized Controller is properly installed?


Indoor Unit 7 Centralized Wiring has been connected properly?
Indoor Unit 8 No. of Outdoor Units did not exceed limitations?
Indoor Unit 9 No. of Indoor Units did not exceed limitations?
Indoor Unit 10 Communication wires (D-III Net wiring) does not exceed 2000 m?
Indoor Unit 11 Drawing plan and wiring for central control were checked by Daikin?
Indoor Unit 12 Building Management System (BMS) BACNet LonWorks EIB/KNX Not Applicable

Indoor Unit 13 Wiring for BMS have already been completed by the contractor as planned?
Indoor Unit 14 Drawing plan and wiring for Daikin BMS equipment were approved by Daikin?
Indoor Unit 15 Point List (Control and Monitoring) were submitted and checked by Daikin?
Indoor Unit 16 System Integrator is available for integration?
Authorized Signature

Authorized Installer Name and Signature Authorized Inspector Name and Signature

* By signing this Pre-commissioning sheet, the contractor/installer certifies that the installation is based on Daikin Standard installation and practice. Daikin reserves the right to void
warranty in case there is any discrepancy on the information
*Field Electrical Safety components such as ELCB/RCCB are responsibility of the installer and should be installed to avoid risk of fire or human injury.

You might also like