Professional Documents
Culture Documents
(83307-K)
(Formerly known as SapuraKencana HL Sdn. Bhd.)
Plot D1, Lumut Port Industrial Park, Kg Acheh, Mukim of Lumut,
32000 Sitiawan, Perak Darul Ridzuan.
Tel : 05-692 3071 Fax : 05-6922609
HIRARC (Rev:_01_Year:_2018___)
PROJECT NAME: BAKONG DEVELOPMENT PROJECT
ACTIVITY OR PROCESS CRITICAL / COMPLEX LIFTING Date :
Department (HIRARC owner): BAKONG DEVELOPMENT PROJECT HIRARC No :
TANDEM LIFTING OF BAKONG MAIN DECK Location: SECTOR 1
Task/Process : USING 2 UNITS OF MANITOWOC 16000 CRANE (400T) CONFIGURED WITH 72m BOOM LENGTH
Specific Work area: Bakong Topside Consctruction Area
Flammable materials Elevated work platform √ Slippery surface Moving parts Reduced visibility
Combustible materials Potential for difficult rescue Manual handling √ Unauthorized persons √ Communication √
Difficult entry/exit
Hazardous substances Noise - plant & equipment Air emissions - dust, fumes Lighting
✘ ✘ ✘ ✘ ✘ ✘
Penyediaan alatan
mengangkat seperti kren, gear site verification / suggestion on particular site verification / audit
mengangkat, wayar sling dan RISK date by PE, Supervisor or Foreman by HSE
shackles. LIKELIH SEVERI
Specific Activity Hazard Identified Existing Control Measures OOD / TY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
2. Obstruction with fabrication equipment To ensure crane pathway is clear and no
e.g. welding machine, gases rack or other obstruction from any object before lifting activity.
structure. RIGGER
Halangan dari alatan seperti mesin Memastikan laluan kren agar tidak terhalang B 2 RIGGER FOREMAN
welding, rak gas, dan struktur lain. oleh mana-mana objek yang boleh LIFTING SUPERVISOR
mengganggu semasa aktiviti mengangkat
dijalankan.
3. Pinch Point. Those rigger who are involved to have complete
Kecederaan pada jari. PPE before start the activity.impact resistance
glove
RIGGER
Rigger yang terlibat dalam aktiviti ini hendaklah B 2 RIGGER FOREMAN
memakai peralatan perlindungan yang lengkap. LIFTING SUPERVISOR
4. Unfit Crane Operator Crane Operator to do Drug and Alcohol Test prior
Kren Operator tidak layak to Lifting Activity
Performing the lifting and manuevering of load (pick and carry) from initial position onto final position
3 Lifting, manuevering and final 1. Communication Failure. Toolbox & 4 point check briefing shall be conducted Radio communication should be established to dedicated radio
positioning activity of load (Main Komunikasi gagal. before start the lifting activity. channel 3
Deck from temporary support RIGGER
onto main support using 2 units Melakukan "Toolbox & 4 Point Check" sebelum Komunikasi menggunakan radio dengan menggunakan RIGGER FOREMAN
of 400T Crane Boom 72m) aktivity dijalankan. B 4 saluran yang telah ditetapkan channel 3. LIFTING SUPERVISOR
RIGGING ENGINEER
HSE
Aktivity mengangkat,
membawa dan "positioning"
beban (Main Deck daripada 2. Crane breakdown. Ensure the cranes are inspected and accepted as Inspection checklist to be complete, PMA should be valid.
support sementara kepada Kren rosak. per inspection check sheet.
support utama menggunakan Senarai pemeriksaan harus lengkap, PMA harus disahkan . CRANE OPERATOR
2 unit 400T Kren) Pastikan kren telah diperiksa sebelum aktiviti B 4
LIFTING SUPERVISOR
mengangkat dijalankan.
3. Load Discrepancy Analysis vs Actual Test Lift to be conducted prior to Actual Lift, load to Personel from Engineering shall present at site during lifting activity to
Perbezaan berat beban Analisis vs be lifted at minimum height and reading of load acknowledge and approve decision made by Rigging Team to mitigate
Sebenar from Crane LMI shall be established. the Load Discrepency (if any)
RIGGING ENGINEER
"Test Lift" perlu dilakukan sebelum "Actual B 4 Wakil dari Engineering perlu berada di site ketika aktiviti lifting LIFTING SUPERVISOR
Lift", beban diangkat pada ketinggian minima untuk mengesahkan keputusan yang dilakukan oleh Rigging Team ENGINEERING
dan bacaan beban dari LMI Kren harus bagi menangani masalah Perbezaan Beban (jika ada)
dikenalpasti
beban (Main Deck daripada
support sementara kepada
support utama menggunakan
2 unit 400T Kren)
5. Uneven ground may cause unbalanced To ensure sufficient soil bearing capacity at lifting To put steel plate underneath crawler crane track if the soil bearing
condition to the crane during lifting area and determine the levelness of ground to insufficent / soft spot / water ponding.
operation. ensure stability of crane while lifting taken placed. RIGGER
Keadaan permukaan tanah yang tidak Sediakan / gunakan plat besi pada trek kren semasa bekerja di RIGGER FOREMAN
rata mengakibatkan kren tidak stabil Semak dan kenalpasti keadaan kekuatan tanah B 4 kawasan yang tidak rata/ kawsan lopak air atau permukaan tanah LIFTING SUPERVISOR
semasa bekerja mengangkat berdasarkan soil bearing data dan periksa yang lembut. RIGGING ENGINEER
permukaan tanah supaya sesuai dengan kerja
mengangkat
7. Unstable load. a) To ensure the wire slings get the tension first Hold for 2 minutes after lifting at minimum height above ground to
Beban tidak stabil. and trial lifting to check the COG (level of the load) ensure load is stable.
prior to start. RIGGER
Berhenti 2 minit selepas mengangkat beban tinggi minima dari RIGGER FOREMAN
Melakukan percubaan mengangkat dahulu B 3 bawah, untuk memastikan beban stabil. CRANE OPERATOR
beban, untuk melihat kestabilan beban sebelum LIFTING SUPERVISOR
aktiviti diteruskan.
8. Slewing too fast Crane operator need to follow instruction from Load travel at the minimum height (site justification) and speed.
"Slewing" teralu laju Supervisor / Signalman.
Perjalanan & kelajuan beban adalah pada ketinggian & kelajuan
Kren operator perlu mengikut arahan dari yang minimum.
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR
9. Traveling too fast. Crane operator need to follow instruction from Load travel at the minimum speed.
Bergerak terlalu laju. Supervisor / Signalman.
Perjalanan & kelajuan beban dalam kelajuan yang minimum.
Kren operator perlu mengikut arahan dari
Rigging Supervisor/signalman. SIGNALMAN
B 3 CRANE OPERATOR
LIFTING SUPERVISOR
11. Wrong positioning Refference marking/indicator for final positioning Production personel shall be present during Lifting Toolbox to brief the
Salah posisi. shall be done by Prouction Team prior to Lifting team on Cellar Deck Positioning.
Activity
Wakil dari Production perlu hadir untuk Lifting Toolbox dan PRODUCTION
Tanda rujukan untuk kedudukan akhir perlu C 3 menjelaskan kepada Rigging Team berkenaan "Cellar Deck LIFTING ENGINEER
dilakukan oleh Production Team sebelum Positioning" LIFTING SUPERVISOR
aktiviti mengangkat dilakukan
12. Bad weather. Check weather forecast first before perform the Shall worst weather (lightning) during load lift/suspend, all operation
Cuaca buruk. lifting activity. shall stop and Crane Safety Pawls shall be activated.
Pastikan aktiviti mengangkat tidak dijalankan Sekiranya keadaan ribut petir ketika beban sedang diangkat, CRANE OPERATOR
semasa cuaca buruk. Periksa "Weather B 2 semua operasi haruslah dihentikan dan Crane Safety Pawls harus LIFTING SUPERVISOR
Forecast" terlebih dahulu sebelum memulakan digunakan. RIGGING ENGINEER
aktiviti ini.
site verification / suggestion on particular site verification / audit
RISK date by PE, Supervisor or Foreman by HSE
LIKELIH SEVERI
Specific Activity Hazard Identified Existing Control Measures OOD / TY/
RATING Recommendation penilaian / cadangan di tapak kerja pada penilaian / audit oleh
No H/M/L/ tarikh oleh PE, Supervisor atau Foreman HSE
Aktitivi yang khusus Hazad yang ditemui Langkah keselamatan yang sedia ada KEBARAN KETERU
PENILAIAN
Saranan langkah keselamatan
GKALIAN KAN
RISIKO
4 Dismantle the lifting gear after 1. Falling load. Slow down to lower the sling wire & ensure the
the load are secured / safely Beban terjatuh. load are fully secured / safely landing on the
landing on the Main Support support RIGGER
(Rigging Gear shall be release RIGGER FOREMAN
after Strong Back (4 pcs) fully Perlahan-lahan menurunkan wayar sling dan A 2
CRANE OPERATOR
installed pastikan objek sudah selamat & stabil LIFTING SUPERVISOR
diletakkan di atas "support"
Membuka gear mengangkat
selepas beban selamat 2. Pinch point. Those rigger who are involved to have complete
diletakkan di atas Support Kecederaan pada jari. PPE (impact glove) before dismantle the lifting gear
Utama & to avoid touching the load.
(Rigging Gear dilepaskan
selepas "Strong Back" (4 pcs) RIGGER
Rigger yang terlibat dalam aktiviti ini B 3 RIGGER FOREMAN
dipasang sepenuhnya) hendaklah memakai peralatan perlindungan LIFTING SUPERVISOR
yang lengkap & elakkan dari memegang beban.
Completion of activity
5 Lifting activity completed. 1. Trip and fall Conduct proper housekeeping.
Tersadung dan jatuh. RIGGER
Aktiviti mengangkat selesai. Lakukan pembersihan dengan betul. A 1 RIGGER FOREMAN
LIFTING SUPERVISOR
2. Rigging gear left at work area. Supervisor to ensure all riggers to do proper
Alatan tidak si kemas / di simpan. housekeeing and no rigging gear & tools left at
work place.
RIGGER
Supervisor perlu memastikan semua pekerja A 1 RIGGER FOREMAN
melakukan pembersihan dan tiada alatan
mengangkat yang tertinggal di kawasan kerja.
Date :
Date: _________________ Date:
By By By By By By By
Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : _________________________ Oleh : ___________________