You are on page 1of 6

TABLE OF CONTENTS

Description Page

0.0 Table of Contents 1

1.0 Organizational Charts 2

2.0 Scope of Works 3

3.0 Objective 3

4.0 Quality Control 3

5.0 Safety 3

6.0 Tool and Materials 3

7.0 Work Method Statement 3-7

1|Page
1.0 ORGANIZATIONAL CHART

Mr. Numata Makoto


General Manager

Mr. Jovel Burgos

Deputy General Manager

Mr. Joy Lora

Head Office Project Director

Project Site
Mr. Elmer Guiral Mr. Hiroshi Toriumi

Project Manager / PIC Japanese Project Manager

Mr. Angelo Castro Mr. Angelo Aguirre


Mr. Simms Mark Villamar
Project Engineer – Electrical Safety Officer/First Aid
Project Engineer – Mechanical
QA/QC
QA /QC

Mr. Augusto Reyes


Mr. Herson Garay Mr. Felix Flores
Supervisor – Electrical
Supervisor – Plumbing & Fire Supervisor – Air conditioning
Pro System & Ventilation

Mr. Roberto Alvarina


Mr. Edwin Casuela Mr. Adelson Fadullo
Foreman / Leadman
Leadman Foreman

WORKERS
WORKERS WORKERS
Edgardo Lasala
Jayson Alcaraz Jomar Maloloy-on
Richard Orogo
Edwin Mendoza Joebert Solsona
Renato Vacnot
Rodelio Villanueva Ronie Ranchez

Ernesto Panawan Lorenzo Candido

Randy Candido

2|Page
2.0 Scope of Work
Installation of Electrical Feeder.

3.0 Objective
To provide Power Supply to all equipments, devices & electrically operated fixtures.

4.0 Quality Control


Modair Manila Co. Ltd., Inc. shall be responsible for the quality of work and shall
develop and propose programs and methods of construction and testing as to achieve
the specified quality to the approval of the Client / Consultant.

5.0 Safety
Modair Manila Co. Ltd., Inc. is to ensure that all the work requirements are
fulfilled and complying with safety procedure as set in project safety plan .e.g. if
required a job hazard analysis is conducted prior to the start of the activities that
environmental requirements are implemented and all personnel wear the required proper
PPE.

6.0 Tools and Materials


1. Threading Machine / Manual Threader
2. Hydraulic Bending Machine / Manual Pipe Bender
3. Welding Machine
4. Speed Cutter
5. Grinder
6. Chipping Gun
7. Coring Machine
8. Hand Drill / Hammer Drill
9. Bench Drill Press
10. Combination & Adjustable Wrenches
11. Pipe Wrench
12. Hacksaw and Wood saw
13. Heat Gun / PVC Pipe Heater
14. Wire Splicer
15. Pliers
16. Screw Driver
17. Vacuum
18. Ladder
19. Scaffolds, Plat form & Body harness
20. Fire Extinguisher

3|Page
7.0 Work Method Statement

7.1 General

7.1.1 Ensure that only approved material required to carry-out the work will be

available.

7.1.2 Prior to commencement of work areas and access will be inspected to

confirm the site/location is ready for the work to commence.

7.1.3 All the relevant documentation (e.g. shop drawings, method of

statement, inspection checklist and Inspection Work Request) and

material applicable to a particular section.

7.1.4 Engineer / Supervisors also ensures that all tools and equipment are

available in good and safe working condition.

7.2 Site and Safety Preparation

7.2.3 Prepare Safety Protection and Signage on the affected areas.

7.2.4 Provide all necessary materials, equipment and tools to be used prior for

activity or test.

7.2.5 Once it is ready, inform the owner’s representative to witness the work

activity.

7.3 Execution Procedures: Installation of Electrical Feeder

7.3.1 Conduct toolbox meeting or briefing about the scope of work. Ensure all required
work permits are signed before starting.

7.3.2 Survey / inspect working area before doing the task to eliminate potential hazard.

7.3.3 Review and print out approved shopdrawings for reference on site ahead of time.

7.3.4 Prepare all materials & tools needed before start of work.

4|Page
7.3.5 Wear proper PPES such as hard hat, safety goggles, safety shoes, dust mask, and
cotton gloves. Use proper tools and equipment with sticker inspected by SMCC
representative.

7.3.6 Barricade working area and put necessary warning signs. Always work buddy-
budy system. Close all windows nearby when working on an area(open small
portion to avoid asphyxiation).

7.3.7 Inspection and approval of manpower, tools and equipment with SMCC safety and
QA/QC. Make sure only skilled and certified workers will be deployed for the job.

7.3.8 Electrical Feeder installation steps:

 Preparation of Hanger & Supports.

1. Measure / Sum up all diameter of conduit included in specific area


together with the approved spacing of pipes.

2. Fabricate / Cut the measured hanger to be used in specific area. For angle
bar hanger and support, paint it with primer epoxy paint for first coating
and gray quick dry enamel for final coating. For unistrut channel in
hanger and support, silver paint quick dry enamel.

 Installation of Hanger & Supports.

1 Mark, drill and install anchor bolts based on approved spacing of hanger
depending on loads.

2 Install & level the threaded rod & channel or angle bars.

 Installation of Pipes.

1 Install the pipes based on arrangement or schedule.

 Wires Installation / Cable pulling

1. Clean the area beforehand where the cable pulling will take place.

2. Erect scaffold for firm and rigid stand bellow pullbox locations for 6ft
high & main feeder cable pulling.

3. Use ladder small power, lightings & mechanical equipments provision


cable pulling.

4. Use cable pulling lubricant gel for easier cable pulling & to retain the
good insulation of wires.

5|Page
5. Housekeeping after the activity.

 Initial Inspection

1. Inspect and supervised every activity to ensure the quality of work and
to lessen the reworks & wastages of materials.

 Testing

1. Continuity Test

2. Insulation Resistance Test

7.3.9 Housekeeping beforehand and subsequentialy.

6|Page

You might also like