You are on page 1of 183

Appendix 13:

PSS/E ANALYSES AND RESULTS

Prepared By:
SECI Interconnection Study Task Group (ISTG)

March, 2005
GENERATION INVESTMENT STUDY
Transmission network checking

Draft Report

March, 2005

carried out by

ELECTRICITY COORDINATING CENTER, Ltd


11040 BELGRADE - VOJVODE STEPE 412, SERBIA AND MONTENEGRO

and

ENERGY INSTITUTE ”HRVOJE POŽAR“ - ZAGREB


ZAGREB – SAVSKA CESTA 163, CROATIA

Authors:

Project leaders: Mr. Miroslav Vuković – EKC, Belgrade


Mr. Davor Bajs – Energy Institute Hrvoje Požar, Zagreb

Project coordinators: Mr. Trajce Čerepnalkovski – ESM, Skopje


Mr. Kliment Naumoski – ESM, Skopje
Ms. Marija Stefkova - Secretary

Participants on project: Mr. Predrag Mikša – EKC, Belgrade


Mr. Dobrijević Djordje – EKC, Belgrade
Mr. Nijaz Dizdarevic – Energy Institute Hrvoje Požar, Zagreb
Mr. Goran Majstrovic – Energy Institute Hrvoje Požar, Zagreb

miro@ekc-ltd.com
dbajs@eihp.hr

ii
____________________________________________________________________________

Complete GIS Report

Table of contents

Volume 1 – Executive Summary


1 EXECUTIVE SUMMARY 7
Volume 2 – Main Report - Electricity Demand Forecast
2 ELECTRICITY DEMAND FORECAST 29
2.1 Objectives 29
2.2 What Are We Forecasting? 31
2.3 Background 33
2.4 Approach 40
2.5 Assumptions And Data Sources 44
2.6 Forecasting Model 48
2.7 Results And Validation 51
Volume 3 - Main Report - Generation & Transmission Study
3 GENERATION AND TRANSMISSION STUDY 75
3.1 Introduction 75
3.2 Computer Models 76
3.3 WASP And GTMax Runs 84
3.4 Candidate Plant 87
3.5 Fuel Costs 94
3.6 Fuel Costs – Utility Data 108
3.7 Fuel Costs – Reconciliation, Forecast Study Prices 111
3.8 Base Case Assumptions 116
3.9 Scenario A, B and C Results 121
3.10 Conclusions 163
3.11 Recommendations 172
4 REFERENCES 174
Volume 4 – Electricity Demand Forecast Appendices
Appendix 1: Review of econometric studies into the relationship between GDP per capita and
electricity demand
Appendix 2: Details of the econometric analysis of the relationship between GDP per capita
and net electricity consumption
Appendix 3: Basis for long term GDP per capita growth forecasts
Appendix 4: Load shape adjustments
Appendix 5: Findings from ECA methodology review
Appendix 6: Country electricity demand forecasts
Volume 5 – Generation & Transmission Study Appendices
Appendix 7: Country data profiles
Appendix 8: Specific candidate plant and rehabilitation
Appendix 9: Screening curve analysis and cost of rehabilitation
Appendix 10: Hydro sensitivity analysis
Appendix 11: GTMax Analyses and Results
Appendix 12: Scenario A, B & C results
Volume 6 – PSSE Appendix
Appendix 13: PSSE Appendix

____________________________________________________________________________________
iii
CONTENTS:

ABBREVIATIONS vii

1. INTRODUCTION 1.1

2. STARTING CONDITIONS 2.1


2.1. Description of PSS/E Model 2.2
2.2. Prerequisites and Assumptions 2.4
2.3. Technical Specification of New Transmission Lines Candidates and Substations 2.7
Costs of the New Interconnection Overhead Lines 2.10
Costs of New Substations in 2010 and 2015 2.12
2.4. Remarks on PSS/E Transmission System Model and GTMax Model Harmonization 2.14
Load Demand 2.14
Network Topology 2.14
Production distribution 2.19
Exchange programs-desired interchange 2.38

3. ANALYSED GENERATION, DEMAND AND EXCHANGE SCENARIOS 3.1


3.1. Year 2010 Scenarios 3.2
3.2. Year 2015 Scenarios 3.6

4. LOAD FLOW AND CONTINGENCY ANALYSIS – REFERENCE CASES 4.1


Introduction 4.2
4.1 Scenario 2010 – average hydrology – topology 2010 4.2
4.1.1 Lines Loadings 4.2
4.1.2. Voltage Profile in the Region 4.7
4.1.3. Security (n-1) Analysis 4.8
4.2 Scenario 2010 – dry hydrology – topology 2010 4.11
4.2.1. Lines Loadings 4.11
4.2.2. Voltage Profile in the Region 4.14
4.2.3. Security (n-1) Analysis 4.14
4.3 Scenario 2010 – wet hydrology – topology 2010 4.16
4.3.1. Lines Loadings 4.16
4.3.2. Voltage Profile in the Region 4.20
4.3.3. Security (n-1) Analysis 4.21
4.4 Scenario 2015 - average hydrology – topology 2010 4.24
4.4.1. Lines Loadings 4.24
4.4.2. Voltage Profile in the Region 4.27
4.4.3. Security (n-1) Analysis 4.28
4.5 Scenario 2015 - average hydrology – topology 2015 4.31
4.5.1. Lines Loadings 4.31
4.5.2. Voltage Profile in the Region 4.34
4.5.3. Security (n-1) Analysis 4.35
4.5.4. Summary of Impacts - 2015 topology versus 2010 topology 4.36

iv
4.6 Scenario 2015 - dry hydrology – topology 2010 4.38
4.6.1. Lines Loadings 4.38
4.6.2. Voltage Profile in the Region 4.41
4.6.3. Security (n-1) Analysis 4.42
4.7 Scenario 2015 - dry hydrology – topology 2015 4.44
4.7.1. Lines Loadings 4.44
4.7.2. Voltage Profile in the Region 4.47
4.7.3. Security (n-1) Analysis 4.48
4.7.4. Summary of Impacts - 2015 topology versus 2010 topology 4.50
4.8 Scenario 2015 - wet hydrology – topology 2010 4.51
4.8.1. Lines Loadings 4.51
4.8.2. Voltage Profile in the Region 4.56
4.8.3. Security (n-1) Analysis 4.57
4.9 Scenario 2015 - wet hydrology – topology 2015 4.61
4.9.1. Lines Loadings 4.61
4.9.2. Voltage Profile in the Region 4.66
4.9.3. Security (n-1) Analysis 4.67
4.9.4. Summary of Impacts - 2015 topology versus 2010 topology 4.69

5. LOAD FLOW AND CONTINGENCY ANALYSIS – SENSITIVITY CASES 5.1


Introduction 5.2
5.1 Scenario 2010 – average hydrology import/export – topology 2010 5.2
5.1.1 Lines Loadings 5.2
5.1.2. Voltage Profile in the Region 5.8
5.1.3. Security (n-1) Analysis 5.9
5.2 Scenario 2010 – average hydrology high load – topology 2010 5.11
5.2.1. Lines Loadings 5.11
5.2.2. Voltage Profile in the Region 5.15
5.2.3. Security (n-1) Analysis 5.15
5.3 Scenario 2015 – average hydrology import/export – topology 2010 5.18
5.4 Scenario 2015 – average hydrology import/export – topology 2015 5.20
5.4.1. Lines Loadings 5.20
5.4.2. Voltage Profile in the Region 5.25
5.4.3. Security (n-1) Analysis 5.26
5.4.4. Summary of Impacts - 2015 topology versus 2010 topology 5.27
5.5 Scenario 2015 – average hydrology high load – topology 2010 5.28
5.5.1. Lines Loadings 5.28
5.5.2. Voltage Profile in the Region 5.32
5.5.3. Security (n-1) Analysis 5.33
5.6 Scenario 2015 – average hydrology high load – topology 2015 5.36
5.6.1. Lines Loadings 5.36
5.6.2. Voltage Profile in the Region 5.40
5.6.3. Security (n-1) Analysis 5.40
5.6.4. Summary of Impacts - 2015 topology versus 2010 topology 5.42

6. ANALYSES SUMMARY AND RECOMMENDATIONS 6.1


6.1 Reference cases 6.2
6.1.1. Analyses comparison 6.2
6.1.2. Overview on possible solutions for system relief 6.5

v
6.2 Sensitivity cases 6.7
6.2.1. Analyses comparison 6.7
Import/export sensitivity scenarios 6.7
High load growth rate 6.8
6.2.2. Overview on possible solutions for system relief 6.11
6.3 List of priorities 6.12

LITERATURE 7.1

vi
ABBREVIATIONS

Country codes
country country
Country Name code code
nodes ISO
AUT Österreich O AT
ALB Shqiperia A AL
BUL Bulgarija V BG
BiH Bosna i Hercegovina W BA
SUI Schweiz S CH
GER Deutschland D DE
GRE Hellas G GR
HUN Magyarorszag M HU
CRO Hrvatska H HR
ITA Italia I IT
MKD FYR Makedonija Y MK
ROM Romania R RO
SLO Slovenija L SI
TUR Türkiye T TR
UKR Ukraina U UA
SCG Srbija i Crna Gora J CS
-- Fictitious border node X --

Other abbreviations
AC Alternating current
DC Direct current
CCGT Combined Cycle Gas Turbine
CHP Combined Heat and Power
HPP Hydro-power plant
NPP Nuclear power plant
TPP Thermal power plant
FACTS Flexible AC transmission systems
GDP Gross domestic product
MW/Mvar Megawatt/Megavar
HV High voltage
NTC Net Transfer Capacity
SEE South Eastern European Countries
SECI South East European Cooperation Initiative
RTSM Regional transmission system model
TRM Transmission Reliability Margin
TSO Transmission System Operator
TR Transformer
HL High voltage line
OHL Overhead high voltage line
PSS/E Power System Simulator for Engineering

Abbreviations of Electric power utilities and Transmission system operators:


EPCG Electric power utility of Montenegro
EPS Electric power utility of Serbia
HTSO Hellenic transmission system operator
CENTREL Association of transmission system operators of Czech, Hungary, Poland, and Slovakia
UCTE Union for the Coordination of Transmission of Electricity

vii
1 INTRODUCTION
The main objective of the Generation Investment Study is to assist the EC, IFIs and donors in
identifying an indicative priority list of investments in power generation and related electricity
infrastructure from the regional perspective and in line with the objectives of SEE REM. The study
would determine what the optimal timing, size and location would be of future generating capacity
in the region over the next 15 years (2005 – 2020). It will also identify priority investments in main
transmission interconnections between the countries and sub-regions to help optimize investment
requirements in power generation over the study horizon. The expansion of the generation system
will be optimized over a 15 year horizon (2005 – 2020) for three scenarios (isolated operation of
each power system, regional operation of power systems, market conditions) using the WASP and
GTMax models.

The third scenario includes power system constraints, such as the capacity of the interconnections,
and other constraints such as the maximum amount of import capacity and energy each country will
be willing to depend upon. For the analysis of the third scenario the study team used, in addition to
the WASP model, the Generation and Transmission Maximization Model (GTMax). GTMax was
used to perform modeling of the electricity grid operated under the SEE REM conditions. It took
into account the transfer capabilities of the interconnection lines among the utility systems.

For more detailed view on regional transmission network operation under market conditions SECI
Regional Transmission System Model in PSS/E was used. Input data concerning demand and
production for several scenarios analyzed in GTMax was used in PSS/E Regional Transmission
System Model (PSS/E RTSM) in order to check feasibility of such demand/production scenarios
from transmission network prospective.

PSS/E RTSM was created by SECI (South East Europe Cooperative Initiative) Project Group on the
Regional Transmission System Planning, sponsored by USAID. With a participation of all power
system utilities in South-East Europe, the Project Group finalized PSS/E RTSM for year 2005 and
2010, suitable for load flow, short-circuit and dynamic analysis. The following countries/companies
were involved in PSS/E RTSM creation: Albania – KESH; Bosnia and Herzegovina – ZEKC,
EPBiH, EPRS, EPHZHB; Bulgaria – NEK; Croatia – HEP, EIHP; Macedonia – ESM; Greece –
PPC/HSTO; Hungary – MVM; Romania – Transelectrica; Serbia and Montenegro – EPS, EKC,
EPCG; Slovenia – ELES; Turkey – TEAS. Two models were created for each time horizon: winter
maximum demand and summer minimum demand models for 2005 and 2010.

Analysis on PSS/E RTSM should provide insight to transmission network adequacy and determine
what transmission reinforcements or additions priorities are eventually required to meet GTMax
2010 and 2015 generation dispatch under normal and (n-1) operating conditions.

Total of 14 GTMax scenarios were analyzed on PSS/E RTSM:

Scenario 2010 - topology 2010


- average hydrology
- dry hydrology
- wet hydrology
Scenario 2015
- average hydrology - topology 2010
- topology 2015
- dry hydrology - topology 2010
- topology 2015

1.1
- wet hydrology - topology 2010
- topology 2015

Scenario 2010
– average hydrology import/export – topology 2010
high load – topology 2010
Scenario 2015
– average hydrology import/export – topology 2010
– topology 2015
high load – topology 2010
– topology 2015

PSS/E RTSM was adjusted according to GTMax model concerning network topology, demand,
production and exchange data. SEE Region was observed as self sufficient without any additional
exchanges with UCTE.

For each GTMax scenario steady-state load flows were calculated and contingency analyses (n-1)
were performed. Security criterion based on voltage profile and lines congestions (thermal loadings)
were checked for each analyzed scenario. Special attention was directed on existing and planned
interconnection lines between different SEE power systems (countries).

Possible network bottlenecks were identified and some solutions for transmission system relief
were described. The role of new interconnection lines candidates in bottlenecks removal was
evaluated.

Following chapters describe PSS/E RTSM, analyzed GTMax production, demand and exchange
scenarios, results of load flow and contingency analyses. List of important regional transmission
system infrastructure projects from a viewpoint of support given to analyzed GTMax dispatch
scenarios is presented at the end of this report.

1.2
2. STARTING CONDITIONS

2.1
2.1. Description of PSS/E Model

For all calculations performed in this part of the study, professional software package PSS/E™
(Power System Simulator for Engineering) is used. The Power System Simulator for Engineering
(PSS/E) model is a system of computer programs and structured data files designed to handle the
basic functions of power system performance simulation work, namely:
• Data handling, updating, and manipulation
• Power Flow
• Optimal Power Flow
• Fault Analysis
• Dynamic Simulations + Extended Term dynamic Simulations
• Open network Access and Price calculation
• Equivalent Construction

Since its introduction in 1976, the PSS/E tool has become the most comprehensive, technically
advanced, and widely used commercial program of its type. It is widely recognized as the most
fully featured, time-tested and best performing commercial product available in the market. The
program employs the latest technology and numerical algorithms to efficiently solve networks large
and small.

PSS/E is comprised of the following modules:


PSS/E Power Flow: This module is basic PSS/E program module and it is powerful and easy-to-
use for basic power flow network analysis (Figure 2.1.1). Besides analysis tool this module is also
used for Data handling, updating, and manipulation.

Figure 2.1.1 – PSS/E model Graphical interface

PSS/E Optimal Power Flow (PSS/E OPF): PSS/E Optimal Power Flow (PSS/E OPF) is a
powerful and easy-to-use network analysis tool that goes beyond traditional load flow analysis to
fully optimize and refine a transmission system. This task is achieved with the integration of PSS/E
OPF into the PSS/E load flow program. PSS/E OPF improves the efficiency and throughput of
power system performance studies by adding intelligence to the load flow solution process.
2.2
Whereas the conventional load flow relies on an engineer to systematically investigate a variety of
solutions before arriving at a satisfactory solution, PSS/E OPF directly changes controls to quickly
determine the best solution. From virtually any reasonable starting point, you are assured that a
unique and globally optimal solution will be attained; one that simultaneously satisfies system
limits and minimizes costs or maximizes performance.

PSS/E Balanced or Unbalanced Fault Analysis: The PSS/E Fault Analysis (short circuit)
program is fully integrated with the power flow program. The system model includes exact
treatment of transformer phase shift, and the actual voltage profile from the solved power flow case.

PSS/E Dynamic Simulation: PSS/E offers users uncompromising dynamic simulation capabilities.
It models system disturbances such as faults, generator tripping, motor starting and loss of field.
The program contains an extensive library of generator, exciter, governor, and stabilizer models as
well as relay model including underfrequency, distance and overcurrent relays to accurately
simulate disturbances.

The organization of PSS/E is illustrated in the following figure Figure 2.1.2:

Figure 2.1.2 – Organization of PSS/E model modules


Current version of this software package and version used for calculations is version 30.2.

2.3
2.2. Prerequisites and Assumptions

For more detailed view on regional transmission network operation under market realistic
conditions SECI Regional Transmission System Model (RTSM) in PSS/E is used. Figure 2.1.1
shows which countries and their transmission systems were modeled.

Figure 2.2.1 - SECI Regional Transmission System Model – countries modeled


High voltage transmission network of 750 kV, 400kV, 220kV, 150kV (Greece and Turkey), and
110 kV voltage levels is implemented in the model. Also, all new substations and lines that are
expected to be operational till 2010 (according to the long term development plans) are modeled
too. All generation units that are connected to the transmission voltage level are modeled as they are
in reality (with step-up transformers). Model is designed for load-flow calculations and analysis, but
with adequate data input (already developed and tested) it can be used for other type of analysis too:
• Short-circuit calculations
• Dynamics (transient stability assessment)

Figure 2.2.2 shows the main characteristics of the SECI Regional Transmission System Model.
With adequate changes and appropriate data input this model is used for all calculations and
analyses in this project.
ALBANIA BULGARIA BIH CROATIA HUNGARY GREECE FYRM ROMANIA
AREA
10 20 30 40 45 50 60 70
ELEMENT TYPE # W S # W S # W S # W S # W S # W S # W S # W S
BUSES 97 97 97 635 602 586 236 230 231 247 247 245 47 45 47 993 889 749 117 117 117 1067 1006 963
PLANTS 14 12 14 112 81 65 38 36 36 59 59 59 8 8 8 100 84 56 22 22 22 132 183 139
MACHINES 30 23 13 144 84 49 42 27 10 62 52 32 23 22 12 107 86 54 22 20 3 132 182 87
LOADS 72 72 72 644 606 590 137 131 131 162 147 147 32 32 33 415 379 267 78 76 73 831 711 679
LINES 107 107 107 747 711 709 278 260 261 325 308 308 249 202 202 1051 901 789 145 138 138 1295 1135 1135
400 4 40 13 21 114 96 10 47
220 21 56 39 28 135 3 114
150
110 82 651 226 276 933 132 1134
66 8
30 14
TRANSFORMERS 50 44 39 170 129 110 72 66 65 95 93 93 12 12 12 260 236 208 32 32 32 293 203 158
STEP UP 23 102 38 60 0 94 22 144
NETWORK 27 68 34 35 12 166* 10 149

SLOVENIA TURKEY SERBIA MONTENEGRO SCG UKRAIN UCTE-WEST CENTREL REGIONAL


AREA
75 80 90 91 90 65 55 95 MODEL
ELEMENT TYPE # W S # W S # W S # W S # W S # W S # W S # W S # W S
BUSES 190 190 190 417 408 368 43 39 35 460 447 403 3 3 3 88 88 88 2 2 2 4182 3963 3721
PLANTS 57 48 44 69 63 25 11 7 3 80 70 28 3 3 3 34 32 30 2 2 2 661 640 506
MACHINES 63 54 23 77 71 25 11 7 3 88 78 28 3 3 3 34 31 25 2 2 2 752 664 341
LOADS 111 111 111 251 249 240 19 19 19 270 268 259 0 0 0 72 72 71 0 0 0 2824 2605 2433
LINES 232 231 231 0 502 471 468 50 48 48 552 519 516 5 5 5 156 149 151 2 2 2 5144 4668 4554
400 14 41 5 46 46 451 0 0
220 9 64 11 75 110 590 0 0
150 0 0 0
110 209 397 34 431 4074 0 0
66 8 0 0
30 14 0 0
TRANSFORMERS 75 75 75 0 139 129 92 21 17 13 160 146 105 0 0 0 19 19 19 0 0 0 1238 1055 916
STEP UP 57 72 11 83 0 623 0 0
NETWORK 18 67 10 77 19 615 0 0

# total number of elements


W number of elements with status in in Winter maximum model
S number of elements with status in in Summer minimum model
* - equivalent lines included

Figure 2.2.2 – SECI Regional Transmission System Model – model characteristics

2.4
Input data concerning demand and production for several scenarios analyzed in GTmax are used ase
input data for PSS/E RTSM in order to check feasibility of such demand/production scenarios from
transmission network prospective.

Electric power systems presented on Figure 2.2.3 are more detail modeled according to GTmax
results.

Hungary
Slovenia
Romania
Croatia

B&H Serbia

Bulgaria
Monte
negro Unmik
Mace Turkey
Alba

donia
nia

Greece

Figure 2.2.3: Analyzed electric power systems


For the purpose of network analyses, following network models in PSS/E software tool are
developed according to GTmax:

Reference cases:
Year Hydrology Topology
average
2010 dry 2010
wet
2010
average
2015
2010
2015 dry
2015
2010
wet
2015

Sensitivity cases (average hydrology):


Special
Year Topology
conditions
2010 2010
Import/Export 2010
2015
2015
2010 2010
High load 2010
2015
2015

2.5
For all these models, expected topology and load distribution in corresponding system substations
are modeled. In Regional Transmission Network Model for the years 2010 and 2015 the most
recent information including new planed lines generator units with step-up transformers,
transformers, compensators, phase shift transformers, shunts, etc are included. Generator units are
connected at generator voltage level.
In the models, whole 110 kV and above network is included. Each interconnection line has assigned
an X node which is placed on border of each country (not at middle of tie line). The model for year
2015 is obtained by increasing production and consumption in each electric power system
according to results from GTmax calculation and respect to new planed lines and substations.
Voltage levels, with the upper and lower limits used in the study, are presented in the Table 2.2.1
These limits are used in load-flow calculations as in contingency analysis.
Table 2.2.1: Defined limits for voltage levels

Defined voltage levels


750 kV 400 kV 220 kV 150 kV 110 kV Generator
min max min max min max min max min max min max
kV 712 787 380 420 198 242 135 165 99 121
p.u. 0,95 1,05 0,95 1,05 0,90 1,10 0,90 1,10 0,90 1,10 0,95 1,05

These limits are according to the operational and planning standards used in the monitored region,
and they are used for full topology and "n-1" analyses. Although, in emergency conditions for some
voltage levels wider voltage limits are allowed, these are not taken into consideration.

The system adequacy is checked for operating conditions using “n-1” contingency criterion.
List of contingencies includes:
• all interconnection lines;
• all 400 and 220 kV lines, except lines which outage cause “island” operation (in case of
parallel lines and double circuit lines, outage of one line-circuit is considered);
• all transformers 400/x kV (in case of parallel transformers, outage of one transformer is
considered).
Current thermal limits are used as rated limits for lines and transformers. These limits are
established based on a temperature to which conductor is heated by current above which either the
conductor material would start being softened or the clearance from conductor to ground would
drop beyond permitted limits. For these analyses is used that conductor current must not reach
limits imposed by thermal limit defined for conductors material and cross-section according to
standard the IEC (50) 466: 1995 – International Electro technical Vocabulary - Chapter 466:
Overhead Lines. For transformers, rated installed MVA power is used as thermal limit. Every
branch with current above its thermal limit is treated as overloaded.

All system states in which voltage level is outside permitted limits or branches are loaded beyond
thermal limit (overloaded), by full topology or "n-1" contingency analyses, are treated as "insecure
states" and referenced as such in this study.

2.6
2.3. Technical Specification of New Transmission Lines Candidates and Substations

Interconnection lines between analyzed electric power systems are presented on the Figure 2.3.1
and Table 2.3.1.
CENTREL Slovakia
PIVDENNOUKRAINSKA
West- AES
Ukraina Moldavia
UCTE
Hungary
Austria
HEVIZ
SANDORFALVA VULKANESTI
ARAD
Romania
Slovenia ISACCEA
ZERJAVINEC
KRSKO MRACLIN TANTARENI
ERNESTINOVO SUBOTICA
MELINE TUMBRI MEDJURICDJAKOVO S.MITROVICA
PORTILE de
TUZLA DJERDAP ISALNITA
FIER
PRIJEDOR GRADACAC UGLJEVIK
Croatia (Jajce) Bosnia VISEGRAD
VARDISTE
Hercegovina
RAMA SARAJEVO
ZAKUCAC MOSTAR 220
KONJSKO TREBINJE NIS VARNA
Serbia
- KOZLODUY
PLAT PIVA DOBRUJA
PODGORICA
MONTENEGRO PRIZREN
KOSOVO B
SOFIA
Bulgaria MARITSA 3
PERUCICA
FIERZE
VAU Macedonia BLAGOEVGRAD
DEJES SKOPJE HAMITABAT
BABAESKI
DUBROVO
Albania Turkey
ELBASAN LAGAD

ZEMLAK KARDIA

THESSALONIKI

Greece
Interconnected
750 kV line (3) network of SE
400 kV line (33) countries
220 kV line (22) only border lines - status 2005 year
Italy

Figure 2.3.1: Interconnection lines in Southeast Europe in 2005 year

Planned interconnection lines in Southeastern Europe for years 2010 and 2015 are given in Figure
2.3.2 and Table 2.3.2 and Table 2.3.3. All of these planned interconnection lines are included in
PSS/E models for target years respectively, depending of years of commissioning.

Basic technical data of new interconnection transmission lines candidates which are analyzed in
2015 year as variants only, are shown in Table 2.3.4. It should be noted that new interconnection
transmission lines candidates, which are shown as doted lines, are analyzed in 2015 year as variants
only.

2.7
Table 2.3.1: List of interconnection lines in Southeast Europe in 2005 year

length
Interconnection line Interconnected Voltage Conductors Transfer km
countries level Type Size Number Capacity
(kV) (mm2) per phase (MVA) I to border border to II total
Varna - Isaccea* BG - RO 750 ACSR 300 5 2390 150 85 235
Albertirsa - Zapadoukrainska HU - UA 750 ACSR 400 5 5360 268 254 522
Isaccea - Pivdenoukrainska* RO - UA 750 ACSR 400 5 5360 5 395 400
God - Levice HU - SK 400 ACSR 500/350 2/3 1440 88 36 124
Gyor - Gabcikovo HU - SK 400 ACSR 500/450 2/3 1440 29 15 44
Zemlak - Kardia AL - GR 400 ACSR 500 2 1309 21 80 101
Mostar4 - Konjsko BA - HR 400 ACSR 490 2 1318 41 69 110
Ugljevik - Ernestinovo BA - HR 400 ACSR 490 2 1318 39 53 92
Blagoevgrad - Lagad (Thesaloniki) BG - GR 400 ACSR 500 2 1309 72 102 174
Dobruja - Isaccea BG - RO 400 ACSR 400 3 1715 81 150 231
Maritsa Istok - Hamitabat BG - TR 400 ACSR 400 3 1715 59 90 149
Isaccea - Vulcanesti* RO - MOLD 400 ACSR 400 3 1715 5 54 59
Kozlodui - Tintareni (double) BG - RO 400 ACSR 500/300 2/3 2490 14 102 116
Sofia - Nis BG - SER 400 ACSR 500 2 1330 37 86 123
Maritsa Istok - Babeski BG - TR 400 ACSR 500 2 1309 50 77 127
Zerjavinec - Heviz (double) HR - HU 400 ACSR 490 2 1318 99 69 168
Dubrovo - Thessaloniki MK - GR 400 ACSR 490 2 1330 55 60 115
Skopje - Kosovo B MK - SER 400 ACSR 490 2 1330 36 68 104
Arachtos - Galatina HVDC GR - IT 400 HVDC 500 / / 0
Gyor - Wien Sud (double) HU - AT 400 ACSR 500 2 2563 59 63 122
Podgorica - Trebinje MN - BA 400 ACSR 490 2 1330 60 21 81
Arad - Sandorfalva RO - HU 400 ACSR 450/500 2 1212 5 52 57
Portile de Fier - Djerdap RO - SER 400 ACSR 967 2 1330 1 2 3
Rosiori - Mukachevo RO - UA 400 ACSR 450 2 1212 39 36 75
S. Mitrovica - Ernestinovo SER - HR 400 ACSR 490 2 1330 41 52 93
Subotica - Sandorfalva SER - HU 400 ACSR 490 2 1330 27 21 48
Maribor - Keinchtal (double) SI - AT 400 ACSR 490 2 1330 26 37 63
Divaca - Meline SI - HR 400 ACSR 490 2 1318 41 26 66
Krsko - Tumbri (double) SI - HR 400 ACSR 490 2 1318 16 32 48
Divaca - Redipuglia SI - IT 400 ACSR 490 2 1330 39 10 49
Mukachevo - Sajoszeged UA - HU 400 ACSR 400 2 1386 8 142 150
V.Dejes - Podgorica AL - MN 220 ACSR 360 1 301 47 21 68
Fierze - Prizren AL - SER 220 ACSR 360 1 301 26 45 71
Gradacac - Djakovo BA - HR 220 ACSR 360 1 300 19 27 46
Prijedor - Mraclin BA - HR 220 ACSR 360 1 300 66 66
Mostar4 - Zakucac BA - HR 220 ACSR 360 1 300 49 50 99
Prijedor2 - Medjuric BA - HR 220 ACSR 360 1 300 34 32 66
TE Tuzla - Djakovo BA - HR 220 ACSR 360 1 300 65 27 92
Trebinje - HE Dubrovnik BA - HR 220 ACSR 240 2 491 7 5 12
Trebinje - HE Dubrovnik BA - HR 220 ACSR 240 2 491 7 5 12
Trebinje - HE Perucica BA - MN 220 ACSR 360 1 301 20 42 63
Sarajevo20 - HE Piva** BA - MN 220 ACSR 490 2/1 366 61 23 84
Visegrad - Pozega BA - SER 220 ACSR 360 1 301 18 51 69
Zerjavinec - Cirkovce HR - SI 220 ACSR 360 1 300 19 51 70
Skopje - Kosovo A MK - SER 220 ACSR 360 1 301 18 65 82
Skopje - Kosovo A MK - SER 220 ACSR 360 1 301 18 65 82
Gyor - Wien Sud HU - AT 220 ACSR 360 1 305 59 63 122
Gyor - Neusiedl HU - AT 220 ACSR 360 1 305 55 27 82
Podlog - Obersielach SI - AT 220 ACSR 490 1 366 46 20 65
Divaca - Pehlin SI - HR 220 ACSR 490 1 350 47 6 53
Divaca - Padriciano SI - IT 220 ACSR 490 1 366 10 2 11
Mukachevo - Kisvarda UA - HU 220 ACSR 400 1 308 54 10 64
Mukachevo - Tiszalok UA - HU 220 ACSR 400 1 308 97 35 132
*not in model
**built as 400kV line Sarajevo20 - B.Bijela and 220kV B.Bijela - Piva, but operated as 220kV Sarajevo20 - Piva

2.8
CENTREL
UCTE

Hungary NADAB
PECS Romania
Slovenia
TUMBRI SOMBOR
ERNESTINOVO
S.MITROVICA
BANJA LUKA
UGLJEVIK
Croatia Bosnia
Hercegovina VISEGRAD Serbia

PLJEVLJA
MONTENEGRO
PODGORICA
KOSOVO B
VRANJE Bulgaria MARITSA 3
C.MOGILA

VAU DEJES
Macedonia BABAESKI
SKOPJE
STIP FILIPI
BITOLA
AlbaniaKASHAR KERHOS Turkey

FLORINA
ZEMLAK
2010 2015 candidates Interconnected
Greece
750 kV line network of SE
400 kV line countries
220 kV line planned border lines only
(status 2010 and 2015 year)
Figure 2.3.2: Planned interconnection lines in Southeast Europe in years 2010 and 2015
Table 2.3.2: List of interconnection lines in Southeast Europe, planned to come into operation in year 2010

length
Interconnection line Interconnected Voltage Conductors Transfer km
countries level Type Size Number Capacity
(kV) (mm2) per phase (MVA) I to border border to II total
Ugljevik - S. Mitrovica BA - SER 400 ACSR 490 2 1330 49 29 79
Kashar - Podgorica AL - MN 400 ACSR 490 2 1330 115 30 145
Maritsa Istok - Filipi BG - GR 400 ACSR 400 3 1715 133 110 243
C. Mogila - Stip BG - MK 400 ACSR 490 2 1330 80 70 150
Ernestinovo - Pecs (double) HR - HU 400 ACSR 490/500 2 1330 44 41 85
Bekescaba - Nadab (Oradea) HU - RO 400 ACSR 490 2 1178 31 87 118
Florina - Bitola GR - MK 400 ACSR 490 2 1330 20 18 38
(Filipi) - Kehros - Babaeski GR - TR 400 ACSR 400 3 1715 50 50 100

Table 2.3.3: List of interconnection lines in Southeast Europe, planned to come into operation in year 2015

length
Interconnection line Interconnected Voltage Conductors Transfer km
countries level Type Size Number Capacity
(kV) (mm2) per phase (MVA) I to border border to II total
Zemlak - Bitola AL - MK 400 ACSR 490 2 1330 25 60 85
Kashar (V. Dejes) - Kosovo B AL - SER 400 ACSR 490 2 1330 135 80 215
Skopje - Vranje - (Leskovac) - (Nis) MK - SER 400 ACSR 490 2 1330 55 137 192

Table 2.3.4: New transmission lines candidates

length
Interconnection line Interconnected Voltage Conductors Transfer km
countries level Type Size Number Capacity
(kV) (mm2) per phase (MVA) I to border border to II total
Visegrad - Pljevlja BA - MN 400 ACSR 490 2 1330 30 30 60
Tumbri - Banja Luka HR - BA 400 ACSR 490 2 1330 50 150 200
Pecs - Sombor HU - SER 400 ACSR 490 2 1330 20 60 80

2.9
All interconnection lines candidates that are investigated in the analyses are shown as dotted lines in
Figure 2.3.2. Table 2.3.5 shows typical electrical parameters of different types of lines. These
parameters are used for both the planned lines and interconnection lines candidates in the Study.
Table 2.3.5: Electrical parameters for OHL per phase and kilometer

*Type of conductor A - B* C

ACSR ACSR CARDINAL ACSR


Positive sequence
2x490 mm2 1x490 mm2 3x400 mm2 360 mm2

Series resistance r [Ω/km per phase] 0.0294 0.058 0.0207 0.08

Series reactance x [Ω/km per phase] 0.341 0.427 0.2824 0.436

Charging susceptance b [µS/km per phase] 3.371 2.67 4.056 2.6

Rated current [A] 1920 960 2292 790

* In Turkey and Greece, Canadian-American standards are used

Costs of the New Interconnection Overhead Lines

Electricity towers, and the wires and conductors that they support, are the major way of transmitting
electricity. They are generally a lattice steel structure with a number of cross arms. The type, size,
height and spacing of towers are determined by geographical, operational, safety and environmental
considerations. A typical overhead line route will involve three types of tower:
− suspension (used for straight lines),
− deviation (where the route changes direction),
− terminal (where the lines connect with substations or underground cables).

A suspension tower is typically between 40 to 60 meters in height with a phase to phase spacing of
between 7 and 25 meters, depending on the type of tower. The two principal types are the “pine”
which narrows at the top and the Y shaped “delta”. The width of the tower right of way will depend
on the level of power to be transmitted but typically range between 30 and 50 meters for 400 kV.
For 400 kV, towers are usually spaced around 350 to 450 meters apart and provide ground
clearance of at least seven meters in all weather conditions. Higher clearances usually apply if the
route crosses motorways or high-pressure water hoses and minimum clearance for trees and public
street lighting also apply. Towers for 400 kV are typically made from steel.
In the absence of a defined methodology to calculate capital charges and costs, and in order to
evaluate investments, unit price method is implemented in following review. Given unit price
related to construction costs take into consideration configuration of terrain (flat land, medium
mountain, high mountain). In Table 2.3.6 and Table 2.3.7 average estimated prices for each new
element that is expected to be in operation in 2010 and 2015 year are presented.

Total investment values for lines construction and corresponding elements till 2010 year is
presented in Table 2.3.6 in EUROS. The investments cover total length of transmission lines and
construction of 400 kV transmission line bays in appropriate substations. Total investment costs of
transmission line bays include costs of following elements:
− construction of 400 kV transmission line itself
− transmission line bays (400 kV)
o Breakers
o Disconnectors with blades ground
o Disconnectors without blades
2.10
o Current Measuring Transformers
o Voltage Measuring Transformers
o Lightning Arrester
These total price values of lines do not take into consideration lease of land.

Table 2.3.6: Total investment sum of interconnection lines in Southeast Europe, planned in year 2010
Lines TL Bays Lines & Bays
Interconnected Unit Total Unit Number Total Year of
Interconnection line Length Total price
countries price price price of bays price commisionning
km Euro/km Euro Euro Euro Euro
Ugljevik - S. Mitrovica BA - SER 79 200,000 15,720,000 650,000 2 1,300,000 17,020,000 2005/06
Kashar (V. Dejes) - Podgorica AL - MN 145 235,000 34,075,000 650,000 2 1,300,000 35,375,000 2006/07
Maritsa Istok - Filipi BG - GR 243 235,000 57,105,000 650,000 2 1,300,000 58,405,000 2007/08
C. Mogila - Stip BG - MK 150 220,000 33,000,000 650,000 2 1,300,000 34,300,000 2006/07
Ernestinovo - Pecs (double) HR - HU 85 240,000 20,400,000 650,000 2 1,300,000 21,700,000 2007/08
Bekescaba - Nadab (Oradea) HU - RO 118 250,000 29,500,000 650,000 2 1,300,000 30,800,000 2008
Florina - Bitola GR - MK 38 235,000 8,930,000 650,000 2 1,300,000 10,230,000 2006/07
(Filipi) - Kehros - Babaeski GR - TR 100 240,000 24,000,000 650,000 2 1,300,000 25,300,000 2007/08

Comments:
ƒ Interconnection line 400 kV Ugljevik (BA) – S.Mitrovica (CS).
This tie line should increase system stability, security and transmission capacity
between west and east region and between Bosnia and Serbia and Montenegro. It is
under construction (part in Bosnia is finished) and should be completed by the end of
this year.
ƒ Interconnection line 400 kV Podgorica (CS) – Kashar (V.Dejes) (AL)
This new tie line should increase system stability, security and transmission capacity
between west and east (CS–AL–GR). Feasibility Study was made two years ago.
Participation for construction of this line will be proportional to the length of the line
from the border (27 km in Montenegro and 115 km in Albania). It should be completed
by the year 2006/7. Estimated investment cost is about 35,375 M€.
ƒ Interconnection line 400 kV Maritsa Istok (BG) – Filipi (GR).
Feasibility Study was made 3 two years ago. Participation for construction of this line
will be proportional to the length of the line from the border (133 km in Bulgaria and
110 km in Greece). To be completed by the year 2007/8. Estimated investment cost is
about 58,5 M€ and investor is unknown yet.
ƒ Interconnection line 400 kV C. Mogila (BG) – Stip (MK)
Feasibility Study was made 2-3 two years ago. This new tie line should increase system
stability, reliability, security and transmission capacity between north and south as well
as between Bulgaria and Macedonia. Participation for construction of this line will be
proportional to the length of the line from the border (80 km in Bulgaria and 70 km in
Greece). It should completed by the year 2006/7. Estimated investment cost is about 35
M€. Investor is unknown yet.
ƒ Interconnection line 400 kV Ernestinovo (HR) – Pecs (HU) (double line)
This tie line should increase system stability, security and transmission capacity
between north and south regions and between Croatia and Hungary. It is included
development plans of HEP (Electric Company of Croatia) and MVM (Electric
Company of Hungary). It should be completed by the year 2007/8. Estimated
investment cost is about 21.7 M€. Investor is unknown yet.
ƒ Interconnection line 400 kV Bekescsaba (HU) – Nadab (Oradea) (RO)
Construction Agreement between MVM and Transelectrica is under signing procedure.
It should be completed by the year 2008.

2.11
ƒ Interconnection line 400 kV Florina (GR) – Bitola (MK)
Feasibility Study was made 3 two years ago. This line should increase system security
and transmission capacity between north and south (MK–GR). Participation for
construction of this line will be proportional to the length of the line from the border (20
km in Greece and 18 km in Macedonia). It should be completed by the year 2006/7.
Estimated investment cost is about 10 M€. Investor is unknown yet.
ƒ Interconnection line 400 kV Filipi (Kehros) (GR) – Babaeski (TR)
Feasibility Study was made 2-3 two years ago. Participation for construction of this line
will be proportional to the length of the line from the border (190 km in Greece and 70
km in Turkey). It should be completed by the year 2007/8. Estimated investment cost is
about 25 M€. Investor is unknown yet.

Total investment values for lines construction and corresponding elements till 2015 is presented in
Table 2.3.7 in EUROS. The investments cover total length of transmission line and construction of
400 kV bays in both substations.

Table 2.3.7: Total investment sum of interconnection lines in Southeast Europe, planned in year 2015
Lines TL Bays Lines & Bays
Interconnected Year of
Interconnection line Unit Total Unit Number Total
countries Length Total price commissioning
price price price of bays price
km Euro/km Euro Euro Euro Euro
Zemlak - Bitola AL - MK 85 200,000 17,000,000 650,000 2 1,300,000 18,300,000 2010/15
Kashar (V. Dejes) - Kosovo B AL - SER 215 220,000 47,300,000 650,000 2 1,300,000 48,600,000 2010/15
Skopje - Vranje - (Leskovac) - (Nis) MK - SER 192 240,000 46,080,000 650,000 2 1,300,000 47,380,000 2010/15

Comments:
ƒ Interconnection line 400 kV Zemlak (AL) – Bitola (MK)
It is included in development program of KESH-Albania. Estimated investment cost is
about 18 M€. Investor is unknown yet.
ƒ Interconnection line 400 kV Kashar (V.Dejes) – Kosovo B (CS)
It is included in transmission development program of KEK-Kosovo. Estimated
investment cost is about 48 M€. Investor is unknown yet.
ƒ Interconnection line 400 kV Skopje (MK) – Vranje – (Leskovac – Nis) (CS)
This tie line should increase transmission capacity, system stability and security
between north and south. Feasibility Study was made one year ago. Estimated
investment cost is about 21 M€ (for Skopje – Vranje) plus about 26 M€ (for Vranje –
Leskovac – Nis). Donation of Greece government is expected. First phase of the project
is building of the Skopje–Leskovac–Nis, and in second phase is installing of the
substation Vranje on this line.

Costs of New Substations in 2010 and 2015

The purpose of the substation (or switchyard) is to transform the voltage of electricity or switch
electricity circuits. Substations are usually contained within secure sites to ensure public safety.
Most substations today are unmanned sites although road access is necessary for staff and for the

2.12
transport of equipment, maintenance or repair. Table 2.3.8 and Table 2.3.9 present total investment
costs that include costs of following elements:
− transformer unit
− transformer bays (400 kV, 220 kV, 110 kV)
o Breakers
o Disconnectors without blades
o Current Measuring Transformers
o Voltage Measuring Transformers
o Lightning Arrester

Also these tables show investment cost for all linked lines between existed transmission lines and
new substations.

Table 2.3.8: new SS which will be in operation till 2010 year


2010
Voltage New
Name of Total cost
Country Position* levels transformers Remarks
substation in Euros
kV/kV MVA
Albania 1 Kashar 400/220 2x400 4,100,000
2 Sofia South 220/110 1x250 new transformer only 1,830,000
3 Maritsa East 1 400/220 1x630 phase-shifter 3,600,000
Bulgaria
4 Pleven 220/110 1x200 new transformer only 1,730,000
Total 7,160,000
Croatia 5 Ernestinovo 400/110 1x300 new transformer only 2,730,000
Macedonia 6 Stip 400/110 1x300 3,430,000
7 Nadab 400 no transformer 1,400,000
Romania 8 Oradea 400/110 1x300 new transformer only 2,730,000
Total 4,130,000
9 S. Mitrovica 400/220 1x400 3,150,000
10 Beograd 20 400/110 1x300 new transformer only 2,730,000
Serbia
11 Kolubara B 400/110 2x300 5,930,000
Total 11,810,000
UNMIK 12 Pec 400/110 1x300 4,130,000
*position in geographical map (Figure 2.4.2)

Table 2.3.9: new SS which will be in operation till 2015 year


2015
Voltage New
Name of Total cost
Country Position* levels transformers Remarks
substation in Euros
kV/kV MVA
Albania 13 V. Dejes 400/200 1x400 3,150,000
14 Brasov 400/110 1x300 new transformer only 2,730,000
Romania 15 Suceava 220/110 1x200 new transformer only 1,730,000
Total 4,460,000
16 Nis 400/110 1x300 new transformer only 2,730,000
Serbia 17 Vranje 400/110 1x300 4,130,000
Total 6,860,000
*position in geographical map (Figure 2.4.4)

2.13
2.4. Remarks on PSS/E Transmission System Model and GTmax Model Harmonization

To investigate regional market conditions in region, GTmax software tool is used. Unlike PSS/E,
with this software tool you can not analyze network conditions. Only in rough congestion analyses
is possible. In order to check, whether production distribution, that is result of GTmax analyses is
feasible from transmission system capabilities point of view, results from GTmax analyses has been
used as input for PSS/E regional models, and then full security analysis of thus gained models has
been performed.

Load-demand

GTmax load-demand level is distributed only in few GTmax network buses, unlike PSS/E model
where load distribution corresponds to the real system conditions (substation by substation). Also,
GTmax load-demand level includes transmission network losses, unlike PSS/E model where these
losses are calculated separately. In other words, it was not possible to achieve full load-demand
correspondence between GTmax and PSS/E model.
In order to achieve at least partial correspondence between GTmax load-demand and PSS/E load
(on system by system level), existing load distribution in PSS/E model is scaled so level of PSS/E
load increased for transmission network losses corresponds to GTmax load-demand level. Also, for
some systems, production of units installed on voltage levels lower than 110 kV is included in load-
demand level (load-demand is reduced for this amount). This was done system by system.

Network topology

In order for PSS/E network models to correspond to GTmax model, first step was to adjust network
topology of both PSS/E and GTmax models. Topology of GTmax models for 2010 and 2015 are
shown on Figure 2.4.1 and Figure 2.4.3 and corresponding real network topologies of regional
network shown on Figure 2.4.2 and Figure 2.4.4.
As it can be seen, the internal system topologies are quite rough, unlike topology of system
interconnections (tie lines), which are almost identical (that was one of prerequisites of GTmax
model).
Transmission system model for 2015 was gained using existing model for 2010. All new
interconnection lines that are predicted to be in operation in GTmax's model are also included in
PSS/E model. Also, all internal network reinforcements that are in long term plans of regional TSOs
are modeled too.

2.14
CENTREL UKRAINE
33
<- 0 ->
80
<- 0 ->
17
33
0
Rosiori
Romania
50
SLOVENIA 0 -> Gutinas
270 00
7
<- 2
Sibiu

1330 ->
<- 1330
270 700
<-
0-
2
>
Croatia

< - 0 ->
1350 ->

00
Serbia
<- 1350

Arad

0
27
Zagreb

27
13 Osijek
<- 50
1 3 ->
50 1350
-> <- 1 ->
330 Belgrade
50 50
13 - 13 1330 -> 1250
->
< <- 1330 <- 12
50 Portile
1330-> Bucharest
Rijeka Tuzla Djerdap de Fier

< - ->
B. Luka <- 1680

0
900
80

125 250
Tantareni

<- 1

<- 1250
1250 ->
B&H

0 ->
Sarajevo B. Basta

<- 1 3
1500
66 66
Isaccea

00
<-
0 0

->
Mostar >
0- 300

->
30 300 -
<- 3 >

1500 ->
<- 1300
0 -> <- 00
135 50
3
<- 1 Pljevlja Kozlodui
Trebinje Nis
Split Ribarevina ->
1330 0
163 30

1330
<- 1

-> Kosovo B < - 13


3
0 ->

<- 1 3

<- 20 ->
13
6

30

30
<- 30 ->

13
12
Montenegro 13
30
Sofia
Varna

19 183
<-
30 0
Bulgaria

->
Podgorica
30 >
<- 0 -> 0- Chervena
28 31 300 Skopje
0 <- Mogila Vetren

12
Legend: V. Dejes 0 ->

00
122 220
Macedonia Plovdiv
Alb

<- 1
13 1330

Thermal / Overcurrent
<-

0
30

120

Dubrovo Maritsa
->

Protection Limits in MW Blagoevgrad


1200
an

13 >
< - 1065
1065 ->

< - 00 -
00

31 310
<-
00 0
13
ia

Winter -> Bitola ->

->
12 690 0
2
<- Winter <- 0 -> <- 6
9
12 TURKEY
20
Tirana/Elbasan 1350
->
< - 13
50

GREECE

Figure 2.4.1: GTmax network topology in year 2010

2.15
Figure 2.4.2: Real network topology in year 2010
2.16
CENTREL UKRAINE
33
<- 0 ->
80
<- 0 ->
17
33
0
Rosiori
Romania
50
SLOVENIA 0 -> Gutinas
270 00
7
<- 2
Sibiu

1330 ->
<- 1330
270 700
<-
0-
2
>

Croatia

< - 0 ->
1350 ->

00
Serbia
<- 1350

Arad

0
27
Zagreb

27
13 Osijek
<- 50
1 3 ->
50 1350
-> <- 1 ->
330 Belgrade
50 50
13 - 13 1330 -> 1250
->
< <- 13 30 <- 12
50 Portile
1330-> Bucharest
Rijeka Tuzla Djerdap de Fier

< - ->
B. Luka <- 1680

0
900
80

125 250
Tantareni

<- 1

<- 1250
1250 ->
B&H

0 ->
Sarajevo B. Basta

<- 1 3
1500
66 66 Isaccea

00
<-
0 0

->
Mostar >
-> 0- 300
-
30 300 <- 3 >

1500 ->
<- 1300
0 -> <- 00
135 50
3
<- 1 Pljevlja Kozlodui
Trebinje Nis
Split Ribarevina ->
1330 0
163 30

1330
<- 1

-> Kosovo B < - 13


3
0 ->

<- 1 3

<- 20 ->
13
6

30

30
<- 30 ->

13
12
Montenegro 13
30
Sofia
Varna

19 183
<-
30 0
Bulgaria
->
Podgorica
30 >
<- 0 -> 0- Chervena
28 31 300 Skopje
0 <- Mogila Vetren

12
Legend: V. Dejes 0 ->

00
122 220
Macedonia Plovdiv
Alb

<- 1
13 1330

Thermal / Overcurrent
<-

0
30

120

Dubrovo Maritsa
->

Protection Limits in MW Blagoevgrad


1200
an

13 >
< - 1065
1065 ->

< - 00 -
00

31 310
<-
00 0
13
ia

Winter -> Bitola ->

->
12 690 0
2
<- Winter < - 0 -> <- 6
9
12 TURKEY
20
Tirana/Elbasan 1350
->
< - 13
50

GREECE

Figure 2.4.3: GTmax network topology in year 2015

2.17
Figure 2.4.4: Real network topology in year 2015
2.18
Production distribution

In PSS/E model, all production units connected to 110 kV or higher voltage network are modeled as
they are in reality, generation units plus corresponding step-up transformers. Some of the
production units or plants connected to the network lower than 110 kV are modeled as negative load
in corresponding buses, but most of them are included in corresponding loads in system substations.
Also, in GTmax models, most of the production units are modeled as whole plants, so in order to
achieve full compliance with PSS/E model, it was necessary to distribute this production on the real
units themselves, as they are in PSS/E model. In following figures and tables production
distribution from GTmax to PSS/E model was shown, jurisdiction by jurisdiction, but also how
these units are connected to the GTmax network model, and appropriate network representation in
PSS/E model.
Albania
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
Fier 1 10021 AFIER 9 11.000 1
10022 AFIERV9 6.3000 4
Balsh
10022 AFIERV9 6.3000 5
10052 AULEZ 9 6.3000 1
10052 AULEZ 9 6.3000 2
10052 AULEZ 9 6.3000 3
Ulez+Shkopet
10052 AULEZ 9 6.3000 4
10053 ASHKP19 6.3000 1
10054 ASHKP29 6.3000 1
10490 ABISTRIG 6.3000 G1
10490 ABISTRIG 6.3000 G2
Bistrica
10490 ABISTRIG 6.3000 G3
10490 ABISTRIG 6.3000 G4
10501 AFIERZ91 13.800 1
10502 AFIERZ92 13.800 2
Fierza
10503 AFIERZ93 13.800 3
10504 AFIERZ94 13.800 4
10511 AKOMAN91 13.800 1
10512 AKOMAN92 13.800 2
Komani
10513 AKOMAN93 13.800 3
10514 AKOMAN94 13.800 4
10521 AVDEJA91 10.500 1
10522 AVDEJA92 10.500 2
Vau Dejes 10523 AVDEJA93 10.500 3
10524 AVDEJA94 10.500 4
10525 AVDEJA95 10.500 5
10551 ABABICG1 13.800 1
10552 ABABICG2 13.800 2
Vlore
10553 ABABICG3 13.800 3
10554 ABABICG4 13.800 4

Figure 2.4.5 – GTmax model - Albania

2.19
Figure 2.4.6 – PSS/E model - Albania

2.20
Bulgaria
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
13200 BELM_G0 10.500 H0
13201 BELM_G12 10.500 H1
BELMEKEN 13201 BELM_G12 10.500 H2
13202 BELM_G34 10.500 H3
13202 BELM_G34 10.500 H4
13206 TSF.I.G5 13.800 D5
13207 TSF.I.G4 6.3000 D4
SOFIA HEAT 13208 TSF.I.G3 6.3000 D3
13209 TSF.IG12 6.3000 D1
13209 TSF.IG12 6.3000 D2
13300 TBDOL_G1 15.750 T1
BOBOV DOL 13301 TBDOL_G2 15.750 T2
13302 TBDOL_G3 15.750 T3
13303 HSES.G1 10.500 H1
SESTRIMO
13304 HSES.G2 10.500 H2
13305 HCHA.G12 19.000 H1
13305 HCHA.G12 19.000 H2
CHAIRA
13310 CHA.G34 19.000 H3
13310 CHA.G34 19.000 H4
13306 TREP.G5 10.500 D5
PERNIK CHP 13307 TREP.G34 6.3000 D3
13307 TREP.G34 6.3000 D4
13308 HMKL.G1 10.500 H1
MOMINA KLISURA
13309 HMKL.G2 10.500 H2
KOZLODUY 1 13404 NKOZ_G9 24.000 N9
KOZLODUY 2 13405 NKOZ_G10 24.000 N0
13500 TRUSEG12 6.3000 T1
RUSE 12
13500 TRUSEG12 6.3000 T2
13501 TRUSEG3 13.800 T3
RUSE 34
13502 TRUSEG4 13.800 T4
13503 TRUSEG5 6.3000 T5
RUSE 56
13504 TRUSEG6 6.3000 T6
13505 TSV_G12 6.3000 I1
SOFIA IND P
13505 TSV_G12 6.3000 I2
13600 TVARN_G1 15.750 T1
13601 TVARN_G2 15.750 T2
13603 TVARN_G4 15.750 T4
VARNA THERMAL
13604 TVARN_G5 15.750 T5
13605 TVARN_G6 15.750 T6
13602 TVARN_G3 15.750 T3
13606 TDEV.G3 10.500 I1
VARNA CHP 13607 TDEV_G14 6.3000 I1
13607 TDEV_G14 6.3000 I4
13700 TMI1_G12 6.3000 T1
13700 TMI1_G12 6.3000 T2
PLOVDIV CHP
13701 TMI1_G3 6.3000 T3
13702 TMI1_G4 6.3000 T4
13703 TMI2_G1 18.000 T1
13704 TMI2_G2 18.000 T2
MARITSA EAST 2 1
13705 TMI2_G3 18.000 T3
13706 TMI2_G4 18.000 T4
13707 TMI2_G5 15.750 T5
13708 TMI2_G6 15.750 T6
MARITSA EAST 2 N
13709 TMI2_G7 15.750 T7
13710 TMI2_G8 15.750 T8
13711 TMI3_G1 15.750 T1
13712 TMI3_G2 15.750 T2
MARITSA EAST 3
13713 TMI3_G3 15.750 T3
13714 TMI3_G4 15.750 T4
13715 TBR.G34 6.3000 I3
13715 TBR.G34 6.3000 I4
BRIKEL
13716 TBR.G5 6.3000 I5
13717 TBR.G6 6.3000 I6
13800 HPESHG12 10.500 H1
13800 HPESHG12 10.500 H2
PESTERA 13801 HPESHG34 10.500 H3
13801 HPESHG34 10.500 H4
13802 HPESH.G5 10.500 H5
ORPHEY 13803 HANTG123 10.500 H1
13803 HANTG123 10.500 H2
13803 HANTG123 10.500 H3

2.21
13804 HANT.G4 10.500 H4
13805 HBATG123 10.500 H1
13805 HBATG123 10.500 H2
BATAK
13805 HBATG123 10.500 H3
13806 HBAT_G4 10.500 H4
13807 HKRI.G1 10.500 H1
KRICHIM
13808 HKRI.G2 10.500 H2
13809 DEVIN.G1 10.500 H1
DEVIN
13810 DEVIN.G2 10.500 H2
13811 HTESH.G 10.500 H1
TESHEL
13811 HTESH.G 10.500 H2
MARITSA 3 13812 TMAR3.G3 13.800 T3
13813 HALEKOG3 10.500 H3
ALEKO 13814 HALEKOG2 10.500 H2
13815 HALEKOG1 10.500 H1
13819 HKAR.G12 10.500 H1
13819 HKAR.G12 10.500 H2
KARDJALY
13820 HKAR.G34 10.500 H3
13820 HKAR.G34 10.500 H4
13821 HST.KG12 10.500 H1
13821 HST.KG12 10.500 H2
STUDEN KLADENEC
13822 HST.KG34 10.500 H3
13822 HST.KG34 10.500 H4
13823 HIW.G123 10.500 H1
IVAILOVGRAD 13823 HIW.G123 10.500 H2
13823 HIW.G123 10.500 H3
13906 TMI1_G5 15.750 T5
MARITSA EAST 1 13907 TMI1_G6 15.750 T6
13908 TMI1_G7 15.750 T7
LUKOIL - - - included in total consumption
BUL SMALL HYDRO - - - included in total consumption

Figure 2.4.7 – GTmax model – Bulgaria

2.22
Figure 2.4.8 – PSS/E model - Bulgaria

2.23
BIH
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
UGLJEVIK 14001 TE UGLJE 20.000 1
GACKO 14002 GACKO 20.000 1
14003 HE VISE 15.750 1
VISEGRAD 14003 HE VISE 15.750 2
14003 HE VISE 15.750 3
14004 HE TREB 14.400 1
TREBINJE HYDRO 14004 HE TREB 14.400 2
14004 HE TREB 14.400 3
14006 BOCACG1 10.500 1
BOCAC
14007 BOCACG2 10.500 2
16001 GRAB-G1 10.500 1
GRABOVICA
16002 GRAB-G2 10.500 2
16003 SAL-G1 13.800 1
SALAKOVAC 16004 SAL-G2 13.800 2
16005 SAL-G3 13.800 3
KAKANJ 7 16006 KAK-G7 15.750 7
TUZLA 4 16007 TUZ-G4 15.750 4
TUZLA 5 16008 TUZ-G5 15.750 5
TUZLA 6 16009 TUZ-G6 15.750 6
16011 JAB-G1 6.3000 1
16012 JAB-G2 6.3000 2
16013 JAB-G3 6.3000 3
JABLANICA
16014 JAB-G4 6.3000 4
16015 JAB-G5 6.3000 5
16016 JAB-G6 6.3000 6
KAKANJ 5 16025 KAK-G5 13.800 5
KAKANJ 6 16026 KAK-G6 13.800 6
TUZLA 3 16033 TUZ-G3 10.500 3
18001 RAMA G1 15.650 1
RAMA
18002 RAMA G2 15.650 2
18003 MOST-G1 10.500 1
MOSTAR HYDRO 18004 MOST-G2 10.500 2
18005 MOST-G3 10.500 3
18006 CAPL-G1 15.700 1
CAPLJINA
18007 CAPL-G2 15.700 2
18008 JAJ1-G1 10.500 1
JAJCE 1
18009 JAJ1-G2 10.500 2
18010 JAJ2-G1 6.3000 1
JAJCE 2 18011 JAJ2-G2 6.3000 2
18012 JAJ2-G3 6.3000 3
18015 MLINI-G1 10.500 1
PEC MLINI
18016 MLINI-G2 10.500 2
DUBROVNIK G-2 - - - included in Croatian production
M.BLATO - - - included in total consumption

Figure 2.4.9 – GTmax model - BIH

2.24
Figure 2.4.10 – PSS/E model - BIH

2.25
Croatia
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
ZAGREB EL TO A 20301 EL-TOG1 10.500 1
ZAGREB EL TO H 20302 EL-TOG2 10.500 2
20304 HECAKOG1 6.3000 1
CAKOVEC
20305 HECAKOG2 6.3000 2
DUBROVNIK G-1 20306 HEDUBRG1 6.3000 1
DUBROVNIK G-2 20307 HEDUBRG2 6.3000 2
20308 HEGOJAG1 10.500 1
GOJAK 20309 HEGOJAG2 10.500 2
20310 HEGOJAG3 10.500 3
20313 HEORLOG1 10.500 1
ORLOVAC 20314 HEORLOG2 10.500 2
20315 HEORLOG3 10.000 3
20316 HEPERUG1 10.500 1
PERUCA
20317 HEPERUG2 10.500 2
20318 HERIJEG1 10.500 1
RIJEKA HPP
20319 HERIJEG2 10.500 2
20320 HESENJG1 10.500 1
SENJ 20321 HESENJG2 10.500 2
20322 HESENJG3 10.500 1
SKLOPE 20323 HESKLOG1 10.500 1
20324 HEVINOG1 10.500 1
VINODOL 20325 HEVINOG2 10.500 2
20326 HEVINOG3 10.500 3
20327 HEZAKUG1 16.000 1
20328 HEZAKUG2 16.000 2
ZAKUCAC
20329 HEZAKUG3 16.000 3
20330 HEZAKUG4 16.000 4
20331 JERTOVG1 10.500 1
20332 JERTOVG2 10.500 2
JERTOVEC
20333 JERTOVG3 11.000 3
20334 JERTOVG4 11.000 4
20335 KRALJEVG 3.7000 1
20335 KRALJEVG 3.7000 2
KRALJEVAC
20335 KRALJEVG 3.7000 3
20335 KRALJEVG 3.7000 4
OSIJEK A 20336 TE-TOOG1 10.500 1
20340 HEVARAG1 10.500 1
VARAZDIN
20341 HEVARAG2 10.500 2
20342 HEDUBRG1 14.400 1
DUBRAVA
20343 HEDUBRG2 14.400 1
20344 RHEOBRG1 15.750 1
VELEBIT
20345 RHEOBRG2 15.750 2
PLOMIN 1 20346 TEPLOMG1 13.800 1
PLOMIN 2 20347 TEPLOMG2 13.800 1
RIJEKA THERMAL 20348 TERIJEG1 20.000 1
SISAK 20350 TESISAG2 15.750 1
ZAGREB TE TO A 20351 TE-TOG1 10.500 1
20352 TE-TOG2 10.500 2
ZAGREB ELTO K 20354 TE-TOG4 10.500 4
20355 TE-TOG5 10.500 5
ZAGREB TE TO C 20353 TE-TOG3 12.500 3
20360 HEDJALG1 10.500 1
DJALE
20361 HEDJALG2 10.500 2
20430 KTEOSGT 15.750 1
CC 480 2
20431 KTEOSST 10.500 1
20420 KTESISGT 15.750 1
CC 480
20421 KTESISST 10.500 1
GOLUBIC - - - included in total consumption
MILJACKA - - - included in total consumption
OSIJEK B - - - will not exist in 2010
OZALJ 1 - - - included in total consumption
OZALJ 2 - - - included in total consumption

2.26
Figure 2.4.11 – GTmax model - Croatia

Figure 2.4.12 – PSS/E model - Croatia

2.27
Macedonia
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
BITOLA 1 26301 BT 2 100 15.750 1
BITOLA 2 26302 BT 2 400 15.750 1
BITOLA 3 26303 BT 2 400 15.750 2
OSLOMEJ 26311 OSLOMEJ 13.800 1
NEGOTINO 26321 TPP NEGO 15.750 1
26331 VRUTOK 12.000 1
26332 VRUTOK 12.000 2
VRUTOK
26333 VRUTOK 12.000 3
26334 VRUTOK 12.000 4
26341 GLOBOCIC 10.500 1
GLOBOCICA
26342 GLOBOCIC 10.500 2
26351 SPILJE 10.500 1
SPILJE 26352 SPILJE 10.500 2
26353 SPILJE 10.500 3
26361 TIKVES 10.500 1
26362 TIKVES 10.500 2
TIKVES
26363 TIKVES 10.500 3
26364 TIKVES 10.500 4
26371 KOZJAK 10.500 1
KOZJAK+MAT
26401 MATKA 2 10.500 1
RAVEN - - - included in total consumption
VRBEN - - - included in total consumption

Figure 2.4.13 – GTmax model - Macedonia

2.28
Figure 2.4.14 – PSS/E model - Macedonia

2.29
Montenegro
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
PLJEVLJA THERMAL 36511 JTPLJEG1 15.750 G1
36521 JHPERUG1 10.500 G1
36522 JHPERUG2 10.500 G2
36523 JHPERUG3 10.500 G3
PERUCICA 36524 JHPERUG4 10.500 G4
36525 JHPERUG5 10.500 G5
36526 JHPERUG6 10.500 G6
36527 JHPERUG7 10.500 G7
SMALL HPPS - - - included in total consumption

Figure 2.4.15 – GTmax model - Montenegro

Figure 2.4.16 – PSS/E model - Montenegro

2.30
Serbia
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
35001 JHDJERG1 15.750 G1
35001 JHDJERG1 15.750 G2
35003 JHDJERG3 15.750 G3
35003 JHDJERG3 15.750 G4
35005 JHDJERG5 15.750 G5
35005 JHDJERG5 15.750 G6
35171 JHDJE2G1 6.3000 G1
35171 JHDJE2G1 6.3000 G2
DJER1 AND DJER2
35173 JHDJE2G3 6.3000 G3
35173 JHDJE2G3 6.3000 G4
35175 JHDJE2G5 6.3000 G5
35175 JHDJE2G5 6.3000 G6
35177 JHDJE2G7 6.3000 G7
35177 JHDJE2G7 6.3000 G8
35179 JHDJE2G9 6.3000 G0
35179 JHDJE2G9 6.3000 G9
35011 JTDRMNG1 22.000 G1
KOSTOLAC B
35012 JTDRMNG2 22.000 G2
35021 JTENTAG1 15.750 G1
TENT A 1
35022 JTENTAG2 15.750 G2
35023 JTENTAG3 15.000 G3
35024 JTENTAG4 15.000 G4
TENT A 2
35025 JTENTAG5 15.000 G5
35026 JTENTAG6 15.000 G6
35031 JTENTBG1 21.000 G1
TENT B
35032 JTENTBG2 21.000 G2
35041 JTKOSBG1 24.000 G1
KOSOVO B THERMAL
35042 JTKOSBG2 24.000 G2
35051 JHBBASG1 15.650 G1
35052 JHBBASG2 15.650 G2
BAJINA BASTA
35053 JHBBASG3 15.650 G3
35054 JHBBASG4 15.650 G4
35071 JRHBBAG1 11.000 G1
BAJINA
35072 JRHBBAG2 11.000 G2
35081 JHBISTG1 10.500 G1
35082 JHBISTG2 10.500 G2
BISTRICA KOKIN
35111 JHKBROG1 6.3000 G1
35112 JHKBROG2 6.3000 G2
35093 JTKOSAG3 15.750 G3
KOSOVO A 3-4
35094 JTKOSAG4 15.750 G4
KOSOVO A5 35095 JTKOSAG5 15.750 G5
KOSTOLAC A 1 35101 JTKSTAG1 10.500 G1
KOSTOLAC A 2 35102 JTKSTAG2 15.750 G2
35121 JHPOTPG2 8.8000 G2
POTPEC 35122 JHPOTPG3 8.8000 G3
35131 JHUVACG1 10.500 G1
35141 JHZVORG1 11.000 G1
35142 JHZVORG2 11.000 G2
ZVORNIK
35143 JHZVORG3 11.000 G3
35144 JHZVORG4 11.000 G4
35151 JTKOLUG1 10.500 G1
35152 JTKOLUG2 10.500 G2
KOLUBARA 2
35153 JTKOLUG3 10.500 G3
35154 JTKOLUG4 10.500 G4
KOLUBARA 1 35155 JTKOLUG5 10.500 G5
MORAVA 35161 JTMORAG1 13.500 G1
35181 JHPIROG1 10.500 G1
PIROT
35182 JHPIROG2 10.500 G2
35191 JHVRL1G1 6.3000 G1
35192 JHVRL1G2 6.3000 G2
35193 JHVRL1G3 6.3000 G3
35194 JHVRL1G4 6.3000 G4
VLASINSKE 35201 JHVRL2G1 6.3000 G1
35202 JHVRL2G2 6.3000 G2
35211 JHVRL3G1 6.3000 G1
35212 JHVRL3G2 6.3000 G2
34512 JHVRL35 110.00 2 as negative load
35221 JHGAZIG1 6.3000 G1
GAZIVODE
35222 JHGAZIG2 6.3000 G2
35241 JTTNSAG1 15.750 G1
NOVI SAD CHP
35242 JTTNSAG2 15.750 G2

2.31
ZRENJANIN CHP 35251 JTTZREG1 15.750 G1
35271 JTKOLBG1 22.000 G1
KOLUBARA B
35272 JTKOLBG2 22.000 G2
KOSOVO 2X450 34070 JTKOSB1 400.00 C1
KOSOVO C 2X450 34070 JTKOSB1 400.00 C2
36501 JHPIVAG1 15.750 G1
PIVA 36502 JHPIVAG2 15.750 G2
36503 JHPIVAG3 15.750 G3

Figure 2.4.17 – GTmax model - Serbia

Figure 2.4.18 – GTmax model – Serbia UNMIK

2.32
UNMIK

Figure 2.4.19 – PSS/E model – Serbia and UNMIK

2.33
Romania
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
29110 TURCENI1 24.000 1
TURCENI 1 29112 TURCENI3 24.000 1
29113 TURCENI4 24.000 1
29114 TURCENI5 24.000 1
29115 TURCENI 24.000 1
TURCENI 2
29116 TURCENI6 24.000 1
29117 TURCENI7 24.000 1
29119 ROVIN 5 24.000 1
29120 ROVIN 6 24.000 1
ROVINARI 29121 ROVIN 3 24.000 1
29238 ROVIN 4 24.000 1
29455 ROVIN 7 24.000 1
29125 AREFU 1 10.500 1
29126 AREFU 2 10.500 1
RIURENI
29127 AREFU 3 10.500 1
29128 AREFU 4 10.500 1
29136 BUC.S 5 13.800 1
29137 BUC.S 6 13.800 1
29138 BUC.S 3 10.500 1
BUCURESTI SUD
29139 BUC.S 1 10.500 1
29317 BUC.S 2 10.500 1
29318 BUC.S 4 10.500 1
29140 STUPA I1 10.500 1
29141 STUPA I2 10.500 1
29142 STUPAII6 10.500 1
GOVORA THERMAL
29143 STUPAII5 10.500 1
29144 STUPA I3 10.500 1
29145 STUPA I4 10.500 1
29147 GROZAV 2 10.500 1
GROZAVESTI CHP
29148 GROZAV 1 10.500 1
29149 PROGRS 1 10.500 1
29150 PROGRS4 10.500 1
PROGRESU CHP
29151 PROGRS3 10.500 1
29152 PROGRS 2 10.500 1
29154 BUC.V 2 13.800 1
BUCURESTI VEST
29155 BUC.V 1 13.800 1
29162 RETEZAT1 15.750 1
RETEZAT
29163 RETEZAT2 15.750 1
29164 MARISEL1 15.750 1
MARISELU 29165 MARISEL2 15.750 1
29166 MARISEL3 15.750 1
29167 MINTIA 1 15.750 1
DEVA 1 29168 MINTIA 2 15.750 1
29169 MINTIA 5 15.750 1
29170 GALCEAG1 15.750 1
GILCEAG
29171 GALCEAG2 15.750 1
29172 SUGAG 1 15.750 1
SUGAG
29173 SUGAG 2 15.750 1
29174 ORAD I 4 10.500 1
29175 ORAD II1 10.500 1
29176 ORAD II2 10.500 1
ORADEA
29177 ORAD I 6 10.500 1
29178 ORAD I 5 10.500 1
29179 ORAD II3 10.500 1
ARAD CHP 29181 ARAD 1 10.500 1
29183 RUIENI 1 10.500 1
RUIENI
29248 RUIENI 2 10.500 1
29184 ISALNIT7 24.000 1
ISALNITA 2
29185 ISALNIT8 24.000 1
29189 P.D.F 1 15.750 1
29190 P.D.F 2 15.750 1
29191 P.D.F 3 15.750 1
PORTILE 1
29192 P.D.F 4 15.750 1
29193 P.D.F 5 15.750 1
29250 P.D.F.6 15.750 1
29194 GRUIA12 6.3000 1
29195 GRUIA34 6.3000 1
PORTILE 2
29199 GRUIA56 6.3000 1
29196 GRUIA78 6.3000 1
DROBETA 29197 DROBETA2 10.500 1
29251 DROBETA4 10.500 1

2.34
29252 DROBETA3 10.500 1
29253 DROBETA1 10.500 1
29198 CRAI II2 15.750 1
CRAIOVA
29200 CRAI II1 15.750 1
29201 BORZEST7 15.750 1
BORZESTI
29202 BORZEST8 15.750 1
29203 BORZE I6 10.500 1
BORZESTI CHP 29205 BORZE I4 10.500 1
29206 BORZE I5 10.500 1
29207 STEJARU5 10.500 1
STEJARU 29208 STEJARU6 10.500 1
29209 STEJARU 10.500 1
29210 SUCEAVA1 10.500 1
SUCEAVA
29211 SUCEAVA2 10.500 1
BACAU THERMAL 29212 BACAU 1 10.500 1
29214 FAI II 1 10.500 1
IASI II
29215 FAI II 2 10.500 1
29216 FAI I 4 10.500 1
IASI I
29217 FAI I 3 10.500 1
CERNAVODA 29218 CERNAV.1 24.000 1
BRAILA 1 29219 BRAILA 1 15.750 1
BRAILA 2 29220 BRAILA 2 15.750 1
29221 BARBOSI5 10.500 1
29224 BARBOSI3 10.500 1
29225 SMARDAN6 10.500 1
GALATI CHP
29310 SMARDAN4 10.500 1
29226 PALAS 1 10.500 1
PALAS CHP
29227 PALAS 2 10.500 1
29232 LOTRU 1 15.750 1
LOTRU CIUNGET 29233 LOTRU 2 15.750 1
29234 LOTRU 3 15.750 1
29235 BRASOV 1 10.500 1
BRASOV THERMAL
29236 BRASOV 2 10.500 1
29237 PITEST 4 10.500 1
PITESTI
29305 PITEST 5 10.500 1
29239 BRAZI 5 10.500 1
29267 BRAZI 7 10.500 1
BRAZI CHP
29268 BRAZI 6 10.500 1
29266 BRAZI 10 10.500 1
29259 MINTIA 4 15.750 1
DEVA 2 29260 MINTIA 3 15.750 1
29262 MINTIA 6 15.750 1
29269 PAROSEN1 10.500 1
29270 PAROSEN2 10.500 1
PAROSENI
29271 PAROSEN3 10.500 1
29263 PAROS 4 18.000 1
BRAILA 3 29299 BRAILA 3 15.750 1
29301 DOICEST8 15.750 1
DOICESTI
29302 DOICEST7 15.750 1
CERNAVODA 2 29332 CERNAV.2 24.000 1
CERNAVODA 3 29470 CERNAV.3 24.000 1
ARCESTI 28639 ARCESTI 110.00 1 as negative load
BABENI 28678 BABENI 110.00 1 as negative load
BACAU 28147 BACAU S 110.00 2 as negative load
BERESTI 28320 VERNEST 110.00 2 as negative load
BRADISOR 28564 BRADISO 110.00 1 as negative load
CALBUCET - - - included in total consumption
CALIMANESTI OLT - - - included in total consumption
CALIMANESTI SIRE - - - included in total consumption
CORNETU - - - included in total consumption
DAESTI 28574 DAIESTI 110.00 1 as negative load
DOICESTI - - - included in total consumption
DRAGANESTI 28752 CHE DRAG 110.00 1 as negative load
DRAGASANI 28674 CHE DRG 110.00 1 as negative load
FRUNZARU 28624 FRUNZ. 110.00 1 as negative load
GALBENI - - - included in total consumption
GUIRGIU - - - included in total consumption
GOVORA - - - included in total consumption
IONESTI 28676 IONESTI 110.00 1 as negative load
IPOTESTI - - - included in total consumption
IZBICENI 29261 IZBICEN 110.00 1 as negative load
LUDUS - - - included in total consumption
MOTRU - - - included in total consumption
MUNTENI I 28849 MUNTEAN 110.00 1 as negative load
NEHOUI - - - included in total consumption

2.35
OTHER AUTOPRODUC - - - included in total consumption
RACACIUNI - - - included in total consumption
REMETI 28850 REMETI 110.00 1 as negative load
RIMNICU VILCEA 28597 VILCEL A 110.00 2 as negative load
RUSANESTI - - - included in total consumption
SASCIORI - - - included in total consumption
SLATINA HYDRO - - - included in total consumption
STREJESTI 28645 STRAJ 110.00 1 as negative load
TARNITA - - - included in total consumption
TISMANA - - - included in total consumption
TOTAL UNDER 25 - - - included in total consumption
TOTAL UNDER 25 2 - - - included in total consumption
TOTAL UNDER 25 3 - - - included in total consumption
TOTAL UNDER 25 4 - - - included in total consumption
TOTAL UNDER 25 5 - - - included in total consumption
TURNU 28844 TURNU 110.00 1 as negative load
VADURI 28102 VADURI 110.00 1 as negative load
VIDRARU - - - included in total consumption
ZAVIDENI 28675 ZAVID 110.00 1 as negative load

Figure 2.4.20 – GTmax model – Romania

2.36
Figure 2.4.21 – PSS/E model - Romania

2.37
All these production facilities are analyzed as they will be built till 2010. Besides in sensitivity
analyses for average hydrology high load scenarios in 2010 and 2015, additional production
capacities are analyzed. In following tables is shown in what way these units are modeled.

BIH
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
14010 HEBBG1 15.750 G1
14011 HEBBG2 15.750 G2
14012 HEBBG3 15.750 G3
BUKBSRB
14015 HESRBG 6.3000 G3
14015 HESRBG 6.3000 G2
14015 HESRBG 6.3000 G1
GLAVATICEVO included in total consumption
Bulgaria
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
BELENE 12450 CAREVEC 400.00 1
Montenegro
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
KOMARNICA 36140 JNIKGR51 110.00 1
ANDRIJEVO I ZLAT 36998 JHANDR21 220.00 1
KOSTANICA 36999 JHKOST11 400.00 1
Serbia (UNMIK)
GTmax PSS/E Remarks
Powerplant Bus# Bus Name ID
KOSOVO 3X274 34070 JTKOSB1 400.00 C1
KOSOVO C 5X450 34070 JTKOSB1 400.00 C2
ZHUR 36999 JPRIZ22 220.00 1

Exchange programs-desired interchange

Because of different modeling approach of production and intersystem exchanges between GTmax
and PSS/E, there are some peculiarities that need to be implemented in PSS/E model. This causes
differences between exchange programs in GTmax and PSS/E. So, NPP Krsko is installed in system
of Slovenia, but 50 % it is owned by Croatia. In GTmax this is modeled simply as Croatian power
plant that has half power installed. But in PSS/E model, this plant is modeled as it is, in system of
Slovenia, so Croatian part of energy produced is modeled as export from Slovenia to Croatia.
Similar situation is with HPP Dubrovnik in Croatia, which is owned by Bosnia and Herzegovina. In
case of HPP Piva, there is long term contract between Serbia and Montenegro, by which this plant
operates as plant owned by Serbia in exchange for 105 MW exchange.
In order to achieve correspondence between exchange programs in GTmax and PSS/E model,
following assumptions are made:
Albania: PSS/E program = GTmax program
Bulgaria: PSS/E program = GTmax program
BIH: PSS/E program = GTmax program – production (DUBROVNIK G-2)
Croatia: PSS/E program = GTmax program + production (DUBROVNIK G-2) – 50% production (KRSKO)
Macedonia: PSS/E program = GTmax program
Romania: PSS/E program = GTmax program
Serbia: PSS/E program = GTmax program (Serbia) + GTmax program (UNMIK) – production (PIVA)
Montenegro: PSS/E program = GTmax program + production (PIVA)

In sensitivity cases analyses, new generation facilities are modeled. One of them is HPP Buk Bijela
and HPP Srbinje in Bosnia and Herzegovina. 1/3 of the energy produced by this plants is owned by
Montenegro, so in these cases (2015 average hydrology high load scenarios) exchange program of
BIH and Montenegro is calculated as:
BIH: PSS/E program = GTmax program – production (DUBROVNIK G-2)+ 1/3production(BUKBSRB)
Montenegro: PSS/E program = GTmax program + production (PIVA)-1/3production(BUKBSRB)

2.38
3 ANALYZED GENERATION, DEMAND AND EXCHANGE
SCENARIOS

3.1
This chapter shortly describes analyzed generation, demand and exchange scenarios in WASP and
GTMax and explains how they are modeled in PSS/E. Total number of 10 scenarios were analyzed
from transmission network prospective.

WASP Scenario B results, were discussed and it was decided that WASP Scenario B “Case 1A”
would be used as the Reference Case for GTmax Scenario C, and for PSS/E analyses as Reference
cases. These Reference Cases include medium demand forecast, most likely fuel price forecast for
all fuels and life extension and rehabilitation program as scheduled by the utilities. Within the
extensive GTMax analyses in 2010 and 2015, the distribution of the new generation units to
specific jurisdictions has been done. The specific (named) new generation units have defined sites
and their distribution throughout the region have been done according to defined sites. Distribution
of non-specific new generation units has been solved by taking into account the power balance for
each jurisdiction or their specific needs. On the basis of the WASP results for the Reference Case
and defined distribution of specific and non-specific new generation units, detailed GTMax
simulation of the weekly operation of the regional power system have been done in average, dry
and wet hydrology conditions. The generation of each power plant in peak hour of 2010 and 2015
in average, dry and wet hydrology conditions have been obtained as one of the GTMax results and
have been used as input data for transmission network analyses done using PSS/E software
package. Five scenarios were related to year 2010, and other five scenarios were related to year
2015.

Three scenarios for each year represent base cases and other two extra situations characterized by
high demand and power imports.

3.1. Year 2010 Scenarios

Following tables 3.1.1-3.1.5 include generation and demand data dependent on analyzed
hydrological situations, load level and power imports, related to year 2010. For each country one
row represents GTMax data (white rows) and one row (shaded ones) equivalent data in PSS/E
model according to explanations from Chapter 2. Differences in demand, hydro power plants and
thermal power plants production are caused by plants connected to voltage levels below 110 kV
which are not included into PSS/E model, so their overall production is included reducing demand,
hydro and thermal production. This is the most obvious in Romanian power system characterized
by large number of small hydro power plants connected to low voltage levels so Romanian balance
in PSS/E model is quite different than on GTMax model.

Total power system balances (production minus demand) are different in GTMax and PSS/E
models for Bosnia and Herzegovina (HPP Dubrovnik production is included into Croatian balance
on PSS/E model), Croatia (HPP Dubrovnik is included, NPP Krsko in Slovenia is excluded from
the balance), Montenegro (HPP Piva is included), and Serbia and UNMIK (HPP Piva is excluded
from their balance).

WASP results for the Reference Case show that, for the period 2005-2010, the following new
capacity would be added to the regional power system:
• Cernavoda nuclear unit #2
• Kolubara lignite unit #1, and
• One 500-MW Kosovo lignite plant
and these were included in the PSS/E model for 2010.

3.2
For 2010 year, additional scenarios are analyzed as Sensitivity cases. One of them is the High Load
Forecast with new generation facilities implemented: HPP Zhur connected to the UNMIK node and
there are also one 300 MW and one 500 MW combined cycle plant in Croatia and additional 500
MW unit connected to UNMIK node. This High Demand Forecast Case includes high demand
forecast, most likely fuel price forecast for all fuels and life extension and rehabilitation program as
scheduled by the utilities. On the basis of the WASP results for the High Demand Forecast Case
and defined distribution of specific and non-specific new generation units, detailed GTMax
simulation of the weekly operation of the regional power system have been done in average
hydrology condition. The generations of each power plant in peak hour of 2010 and 2015 in average
hydrology condition have been obtained as one of the GTMax results and have been used as input
data for transmission network analyses done using PSS/E software package.

As second Sensitivity case, additional energy exchanges in the region are analyzed. This
Import/Export Case includes medium demand forecast, most likely fuel price forecast for all fuels,
life extension and rehabilitation program as scheduled by the utilities and net import of 1,500MW
into the region. Following additional exchanges are simulated:
- Import 750 MW from UCTE.
- Import 500 MW from Turkey.
- Export 500 MW to Greece.
- Import 750 MW from Ukraine.

On the basis of the WASP results for the Import/Export Case and defined distribution of specific
and non-specific new generation units, detailed GTMax simulation of the weekly operation of the
regional power system have been done in average hydrology condition. The generations of each
power plant in peak hour of 2010 and 2015 in average hydrology condition have been obtained as
one of the GTMax results and have been used as input data for transmission network analyses done
using PSS/E software package.

After comparison of the GTMax results for this case with the results for Base Case it can be seen
that there is no new TPPs connected to UNMIK node or Mladost node in 2010 (without new TPPs
on Kosovo and without Kolubara B units).

3.3
Table 3.1.1: Demand, Generation and Exchanges in SE Europe for base case - average hydrological scenario in
2010

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1338 757 140 897 -441
Albania
1338 757 140 897 -441
Bosnia and 2077 1591 826 2417 341
Herzegovina 2029 1439 826 2265 236
6193 554 6426 6980 787
Bulgaria
6113 474 6426 6900 787
3217 1018 749 1767 -1450
Croatia
3186 1092 411 1503 -1683
1229 232 730 962 -268
Macedonia
1218 220 730 950 -268
687 228 0 228 -459
Montenegro
687 540 0 540 -147
7797 2996 5730 8726 930
Romania
7022 2256 5696 7952 930
Sebia and 7112 2582 5090 7672 560
UNMIK 7112 2270 5090 7360 248
29649 9958 19691 29649 0
Region Total
28705 9048 19319 28367 -338**
* pumped storage HPP’s included
** half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

Table 3.1.2: Demand, Generation and Exchanges in SE Europe for base case - dry hydrological scenario in 2010

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1338 753 200 953 -384
Albania
1338 753 200 953 -384
Bosnia and 2077 1636 1338 2974 898
Herzegovina 2050 1504 1338 2843 793
6193 373 6426 6799 606
Bulgaria
6103 283 6426 6709 606
3217 924 1632 2555 -661
Croatia
3189 1001 1294 2295 -894
1229 296 730 1026 -203
Macedonia
1224 290 730 1020 -203
687 179 0 179 -508
Montenegro
687 467 0 467 -220
7797 1820 5776 7596 -200
Romania
7128 1185 5742 6927 -200
Sebia and 7112 2476 5090 7566 454
UNMIK 7112 2188 5090 7278 166
29649 8457 21192 29649 0
Region Total
28830 7672 20820 28492 -338*
* pumped storage HPP’s included
** half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

3.4
Table 3.1.3: Demand, Generation and Exchanges in SE Europe for base case - wet hydrological scenario in 2010

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1338 759 140 899 -439
Albania
1338 759 140 899 -439
Bosnia and 2077 1630 570 2200 124
Herzegovina 2019 1468 570 2038 19
6193 686 6346 7032 839
Bulgaria
6103 596 6346 6942 839
3217 1249 749 1998 -1219
Croatia
3187 1324 411 1735 -1452
1229 367 730 1097 -132
Macedonia
1214 352 730 1082 -132
687 244 0 244 -443
Montenegro
687 586 0 586 -101
7797 3744 4684 8428 632
Romania
6706 2653 4684 7337 632
Sebia and 7112 2662 5090 7751 639
UNMIK 7112 2319 5090 7409 297
29649 11341 18309 29649 0
Region Total
28366 10057 17971 28028 -338**
* pumped storage HPP’s included
** half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

Table 3.1.4: Demand, Generation and Exchanges in SE Europe for sensitivity case – high load – average
hydrological scenario in 2010

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1414 790 140 930 -484
Albania
1414 790 140 930 -484
Bosnia and 2114 1693 667 2360 246
Herzegovina 2061 1535 667 2202 141
6492 518 6832 7350 858
Bulgaria
6425 450 6832 7282 858
3371 1001 1507 2508 -863
Croatia
3350 1085 1169 2254 -1096
1262 271 730 1001 -261
Macedonia
1252 261 730 991 -261
704 228 0 228 -476
Montenegro
704 540 0 540 -163
8320 3237 5026 8263 -57
Romania
7533 2484 4992 7476 -57
Sebia and 7346 2774 5608 8382 1036
UNMIK 7346 2462 5608 8070 724
31022 10512 20510 31022 0
Region Total
30085 9379 20138 29747 -338**
* pumped storage HPP’s included
** half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

3.5
Table 3.1.5: Demand, Generation and Exchanges in SE Europe for sensitivity case – power import – average
hydrological scenario in 2010

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1338 757 140 897 -440
Albania
1338 757 140 897 -440
Bosnia and 2077 1734 826 2560 484
Herzegovina 2019 1572 826 2398 379
6193 561 6346 6907 714
Bulgaria
6113 481 6346 6827 714
3217 1218 749 1967 -1250
Croatia
3188 1294 411 1705 -1483
1229 266 730 996 -233
Macedonia
1199 235 730 965 -233
687 228 0 228 -459
Montenegro
687 540 0 540 -147
7797 2936 4756 7692 -105
Romania
6977 2150 4722 6872 -105
Sebia and 7112 2582 4320 6902 -210
UNMIK 7112 2270 4320 6590 -522
29649 10282 17867 28149 -1500
Region Total
28633 8788 17495 26795 -1838**
* pumped storage HPP’s included
** 1500 MW of import plus half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

3.2. Year 2015 Scenarios

Following tables 3.2.1-3.2.5 include generation and demand data dependent on analyzed
hydrological situations, load level and power imports, related to year 2015, using the same
assumptions explained in previous subchapter.

WASP results for the Reference Case show that, for the period 2011-2015, the following new
capacity would be added to the regional power system:
• Cernavoda nuclear unit #3
• Kolubara lignite unit #2
• One 300-MW and two 500-MW Kosovo lignite plants
• Two 100-MW CHP plants, and
• Two 300-MW and one 500-MW combined cycle plants
On the basis of this kind of analyses the following distribution of new non-specific generation units
have been arranged:
- two 100 MW CHP units have been placed in Romania
- two 300 MW and one 500 MW combined cycle units have been placed in Croatia
all these are included in PSS/E model for 2015.

Like for 2010, and for 2015 year, additional scenarios are analyzed as Sensitivity cases. One of
them is the High Load Forecast with new generation facilities implemented:
- HPP Buk Bijela with HPP Srbinje in B&H. Within the results from GTMax it can be seen that
this hydro system is partially connected to Sarajevo node in B&H and partially to Montenegro
node, due to the partial ownership of this hydro system.
- HPP Glavaticevo connected to Mostar node in B&H.
- HPP Dabar connected to Trebinje node in B&H.
- HPP Komarnica connected to Montenegro node.

3.6
- HPP Kostanica connected to Montenegro node.
- HPP Andrijevo and Zlatica connected to Montenegro node.
- NPP Belene nuclear plant connected to Varna node in Bulgaria,
- one 100 MW CHP unit connected to Mladost node in Serbia,
- one 500 MW combined cycle plant connected to node Zagreb in Croatia
- and additional two 300 MW and two 500 MW units connected to UNMIK node.

After comparison of the GTMax results for Export/Import Case (exchanges in/from/to SE Europe
are the same as in 2010) with the results for Base Case in 2015 it can be seen that there is no
Chernavoda Unit 3, no CHP unit connected to SIBIU node, no second 300 MW unit connected to
Zagreb node, only one 500 MW unit connected to UNMIK node, but instead of one now there are
two 300 MW units connected to UNMIK node.

As second Sensitivity case for 2015, additional energy exchanges in the region are analyzed. This
was called Import/Export Case, and following additional exchanges are simulated (same as for
2010):
- Import 750 MW from UCTE.
- Import 500 MW from Turkey.
- Export 500 MW to Greece.
- Import 750 MW from Ukraine.

Table 3.2.1: Demand, Generation and Exchanges in SE Europe for base case - average hydrological scenario in
2015

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1614 978 140 1118 -496
Albania
1614 978 140 1118 -496
Bosnia and 2410 1648 826 2474 64
Herzegovina 2358 1491 826 2317 -41
6688 533 6854 7387 699
Bulgaria
6619 465 6854 7319 699
3752 986 1595 2581 -1171
Croatia
3721 1060 1257 2317 -1404
1438 379 720 1099 -340
Macedonia
1427 367 720 1087 -340
694 230 191 421 -273
Montenegro
694 542 191 733 39
9056 3424 5680 9104 48
Romania
7973 2547 5474 8021 48
Sebia and 7499 2584 6383 8967 1468
UNMIK 7499 2272 6383 8655 1156
33151 10762 22389 33151 0
Region Total
31906 9722 21845 31568 -338**
* pumped storage HPP’s included
** half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

3.7
Table 3.2.2: Demand, Generation and Exchanges in SE Europe for base case - dry hydrological scenario in 2015

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1614 751 143 894 -720
Albania
1614 751 143 894 -720
Bosnia and 2410 1656 1617 3274 864
Herzegovina 2382 1523 1617 3141 759
6688 600 6854 7454 766
Bulgaria
6598 510 6854 7364 766
3752 1177 1721 2898 -853
Croatia
3723 1253 1383 2636 -1086
1438 274 720 994 -444
Macedonia
1429 265 720 985 -444
694 107 191 298 -396
Montenegro
694 395 191 586 -108
9056 2033 6654 8687 -369
Romania
8188 1371 6448 7819 -369
Sebia and 7499 2268 6383 8651 1152
UNMIK 7499 1980 6383 8363 864
33151 8868 24283 33151 0
Region Total
32127 8049 23739 31789 -338**
* pumped storage HPP’s included
** half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

Table 3.2.3: Demand, Generation and Exchanges in SE Europe for base case - wet hydrological scenario in 2015

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1614 984 140 1124 -490
Albania
1614 984 140 1124 -490
Bosnia and 2410 1743 573 2316 -94
Herzegovina 2353 1581 573 2154 -199
6688 899 6744 7643 955
Bulgaria
6598 809 6744 7553 955
3752 1468 1595 3063 -688
Croatia
3721 1543 1257 2800 -921
1438 358 523 881 -557
Macedonia
1427 347 523 870 -557
694 246 191 437 -257
Montenegro
694 588 191 779 85
9056 3445 5488 8933 -123
Romania
8074 2635 5316 7951 -123
Sebia and 7499 2662 6092 8754 1255
UNMIK 7499 2320 6092 8412 913
33151 11805 21346 33151 0
Region Total
31980 10806 20836 31642 -338**
* pumped storage HPP’s included
** half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

3.8
Table 3.2.4: Demand, Generation and Exchanges in SE Europe for sensitivity case – high load – average
hydrological scenario in 2015

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1781 758 140 898 -883
Albania
1781 758 140 898 -883
Bosnia and 2503 1989 630 2619 116
Herzegovina 2433 1814 630 2444 11
7327 552 7674 8226 899
Bulgaria
7259 484 7674 8158 899
4067 1007 1845 2852 -1215
Croatia
4040 1085 1507 2592 -1448
1516 179 720 899 -617
Macedonia
1513 176 720 896 -617
736 922 191 1113 377
Montenegro
736 1234 191 1425 689
10232 3584 5608 9192 -1040
Romania
9175 2698 5436 8135 -1040
Sebia and 8025 2472 7917 10389 2364
UNMIK 8025 2160 7917 10077 2052
36188 11463 24725 36188 0
Region Total
34962 10408 24215 34624 -338**
* pumped storage HPP’s included
** half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

Table 3.2.5: Demand, Generation and Exchanges in SE Europe for sensitivity case – power import – average
hydrological scenario in 2015

Country Demand HPP Generation TPP and NPP Total Generation Surplus(+)/Deficit(-)
(MW) (MW)* Generation (MW) (MW)
1614 886 140 1026 -588
Albania
1614 886 140 1026 -588
Bosnia and 2410 1720 826 2546 136
Herzegovina 2364 1568 826 2395 31
6688 840 6854 7694 1006
Bulgaria
6578 730 6854 7584 1006
3752 1133 1307 2440 -1312
Croatia
3721 1207 969 2176 -1545
1438 379 720 1099 -340
Macedonia
1417 357 720 1077 -340
694 230 191 421 -273
Montenegro
694 542 191 733 39
9056 3030 5054 8084 -972
Romania
8161 2256 4934 7190 -972
Sebia and 7499 2584 5757 8341 842
UNMIK 7499 2272 5757 8029 530
33151 10802 20849 31651 -1500
Region Total
32048 9819 20391 30210 -1838**
* pumped storage HPP’s included
** import of 1500 MW plus half of NPP Krsko (Slovenia) production (scheduled for Croatian power system)

3.9
4 LOAD FLOW AND CONTINGENCY ANALYSIS – REFERENCE
CASES

4.1
Introduction

In this chapter load-flow and security (n-1) analysis for reference cases defined in Chapter 2 is
described. The analyzed network models are:

Year Hydrology Topology


average
2010 dry 2010
wet
2010
average
2015
2010
2015 dry
2015
2010
wet
2015

The load-flow analysis includes line loading and voltage profile analysis, analysis of losses and also
analysis of power flows through interconnection lines.

The system reliability and adequacy is checked using “n-1” contingency criterion. List of
contingencies includes:
• all interconnection lines;
• all 400 and 220 kV lines in analyzed region, except lines which outage cause “island”
operation (in case of parallel and double circuit lines, outage of one line is considered);
• all transformers 400/x kV in analyzed region (in case of parallel transformers, outage of one
transformer is considered).

Current thermal limits are used as rated limits of lines and transformers, as described in Chapter 2.
Voltage limits are defined in Chapter 2, also.
Every branch with current above its thermal limit is treated as overloaded. States with overloaded
branches and/or voltages below or above defined voltage limits are treated as "insecure".

4.1 Scenario 2010 – average hydrology – 2010 topology

This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as Scenario 2010 average hydrology.

4.1.1 Line loadings

Area totals and power exchanges for the 2010-base case-average hydrology scenario are shown in
Figure 4.1.1 and

Table 4.1.1. Power flows along regional interconnection lines and system balances are shown in
Figure 4.1.2. Power flows along interconnection lines are also given in Table 4.1.2, while Figure
4.1.3 shows histogram of tie lines loadings.

4.2
SVK
UKR

4 50

1
54

91
AUT

1
27
HUN
53
0
94

SLO

32
6
ITA ROM

36
30
9

CRO 333
67
4

0
25
330 SRB
BIH

60
3 76
10

2
27
8

MNT BUL
18

10

40

2
5

4
17
MKD

272
TUR
ALB
133

0 24
41
3

GRE
2 50

Figure 4.1.1 - Area exchanges in analyzed electric power systems for 2010-base case-average hydrology scenario

Table 4.1.1 - Area totals in analyzed electric power systems for 2010-base case-average hydrology scenario
Country Generation Load Bus Shunt Line Shunt Losses Net Interchange
(MW) (MW) (Mvar) (Mvar) (MW) (MW)
Albania 896.7 1287.3 0 0 50.4 -441.0
Bulgaria 6900.4 5977.3 0 14.4 121.6 787.0
Bosnia and Herzegovina 2266.1 1971.3 0 0 58.6 236.2
Croatia 1502.9 3136.7 0 0 49.0 -1682.8
Macedonia 950.3 1198.2 0 0 20.1 -268.0
Romania 7939.9 6728.3 0 80.0 201.2 930.4
Serbia and UNMIK 7355.9 6873.1 0 13.6 220.8 248.4
Montenegro 539.8 669.2 0.6 1.6 15.5 -147.0
TOTAL - SE EUROPE 28351.9 27841.4 0.6 109.5 737.1 -336.7

4.3
GABICK1400.0 LEVIC 1400.0

CENTREL

251
116

200
143
450.0 MW
346 350
MAISA 7 UZUKRA01
803 299

UCTE OWIEN 1 MGYOR 4


0
25 .1
715.1 772.5

221.6 MW
UKR
405.6 69.6 69.5
94

97.3
199
21.6 104 MSAJI 408.2 35.4 35.6
403.5 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 402.6 OWIEN 2 MGOD 4 407.8 226.3
21.0 27.8
450.0 MW
10.7 10.6

41.0

58.4
53.4
58.4
53.4
166
MGYOR 2 MTLOK 2
43.1 42.7 7.7 29.3
234.3 230.5 224.4
7.5 23.2
ONEUSI2 UMUKACH
233.5 15.0 14.9 229.0 166 167 90.
MSAJO 4
14.5 28.6
410.0
57.2 52.9
412.0 3.1 7

HUN
-1249.4 MW

22. 4

22. 4
3

2
163

58.

58.
36.

90. 7
59.
LPODLO2229.9 LMARIB1 403.9 281 282
MBEKO 4 NADAB

9
MHEVI 4 409.5 63.8 74.5 ROSIORI 410.3
LDIVAC1 406.3 404.4
215.0 MW

42.7

42.7
106

106
IRDPV111

SLO
159 159
62.7 41.5 66
401.4 403.0 92 .6 MPECS 4 409.8 MSAFA 4 404.1
.0
LKRSKO1 403.2 LCIRKO2 228.9 247 249 ARAD
LDIVAC2 .1
32 10

2. 5

2. 5
13.0 59.7

.
53.8

53.8

45.2
25.4
176

176

3
IPDRV121 1 402.9

77

77
28.0 28.0 32
45.4 49.0 29 .6
231.3 230.8 .0

ROM
ISACCEA 414.3

4
66.7
68.2

77 6.8

98.7
77.

198
5 5
10 .5 10 .5
930.0 MW

32.0
46 .4

135
62 62

.8
ERNESTIN

44 6.
MELINA 407.3 ZERJAVIN 406.7 JSOMB31
396.6 JSUBO31 398.8

1
.9 6
ZERJAVIN 230.4 332 334
JSMIT21
32.7

17 3

17 3
71.3 103

29

29
19.3

407.8

6
.

12.4
105
TUMBRI 404.2 DAKOVO 225.8

68 278
PEHLIN 233.7 MRACLIN 227.2MEDURIC 226.6

58.0
23.4

39.6
103

.1
403.2

51.4
20.8

51.2
12.5
JHDJE11 P.D.FIE
250 250
42.3 41.6 TANTAREN 415.6
404.2 404.3

CRO

42.5

42.5
130

130
276

58. 7
18.

68.
105
-1682.8 MW 39.2

51.5

3
19.5
51 .5

4
36
10 9
28
.7 GRADACAC 228.5 UGLJEVIK 405.1

.
4
SCG
PRIJED2 226.0 TE TUZL 233.7

VISEGRA JVARDI22
101.4 MW

40.8
53.0 53.2 230.5

199
232.4

12 1

12 1
59.2 61.0

6.

6.
BIH

9
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 415.8 DOBRUD4 421.3
290 291 236.2 MW 232.2 147 148 236.1 CRG 248.4 MW JNIS2 1 374 377 SOFIA_W4
408.4
0.6 46.9
408.6
16.6 14.3
-147.0 MW 395.7
138 108
411.9
HE ZAKUC 125 128 MO-4 RP TREB JHPERU21
14.3 16.2 34.1 33.9 229.6
233.3 234.8 233.1
18.8 26.7

BUL
18.6 18.7
RP TREB JPODG211 JLESK21
76.9 120 JPODG121228.5
404.1 386.9
787.0 MW

24.7
20.6
JPRIZ22
223.0 JTKOSA2
226.9JTKOSB1406.9

7.0
5.8
397.2

.8 3
45 0.

6.8 7

6.8 7

26.0
28.6
1

18.

18.
JVRAN31
0.000

15.3
7.0

37 0.0
.2
24.6
48.5

1
AVDEJA1 395.4
AVDEJA2
227.4AFIERZ2228.4 C_MOGILA

29.4

29.4
26.0
21.7
6.9

6.9
27.7
128
6
17 7
SK 1 223.3 SK 4
407.3 408.3 . 413.8
48

-268.0 MW STIP 1 5
17 .0

MKD
BITOLA 2 416.4
412.4
38

BLAGOEV414.5 MI_3_4_1 420.4


27.3

DUBROVO 412.4
167

31.9
49.4
1
7. 2.7

38. 1
AKASHA1 386.0

9
68.7
33.2

11 1.
24
63. 1
2

48.

1
.0 9
7
ALB
-441.0 MW .8

63. 6
31 .9

25.

12 5.9
11.0
68.8
45

9
.6
9 4HAMITAX

7
AHS_FLWR417.6 LAGAD K 414.1 23 6.0 11.0 10.9 415.6
FILIPPOI 7
23.7 23.7 68.8 80.1
398.2 4BABAESK

68.8
28.2
22.6
K-KEXRU
417.9 71.6
KARDIA K 415.6 415.7
411 417 416.8 QES/H K 413.2
135 112
AZEMLA1
0.0 MW
-0.1 MW TUR
GRE
KARACQOU
250 419.1
50.0

GIS REGIONAL MODEL - AVERAGE HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2010 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 4.1.2 - Power flows along interconnection lines in the region for 2010 - base case - average hydrology scenario

4.4
Table 4.1.2 - Power flows along regional interconnection lines for 2010 - base case-average hydrology scenario

Power Flow
Interconnection line % of thermal
rating
MW Mvar
OHL 400 kV Zemlak (ALB) Kardia (GRE) -410.7 -135.0 32
OHL 220 kV Fierze (ALB) Prizren (SER) -10.0 37.2 15
OHL 220 kV V.Dejes (ALB) Podgorica (MON) 7.0 -15.3 6
OHL 400 kV V.Dejes (ALB) Podgorica (MON) -24.6 -48.5 4
OHL 400 kV Ugljevik (B&H) Ernestinovo (CRO) 105.4 -68.4 10
OHL 400 kV Mostar (B&H) Konjsko (CRO) 291.3 -46.9 22
OHL 400 kV Ugljevik (B&H) S. Mitrovica (SER) -276.4 39.2 21
OHL 400 kV Trebinje (B&H) Podgorica (MON) -18.6 76.9 9
OHL 220 kV Trebinje (B&H) Plat (CRO) -104.8 40.0 36
OHL 220 kV Prijedor (B&H) Mraclin (CRO) 51.7 -28.5 18
OHL 220 kV Prijedor (B&H) Medjuric (CRO) 51.5 -19.5 17
OHL 220 kV Gradacac (B&H) Djakovo (CRO) 58.3 18.7 21
OHL 220 kV Tuzla (B&H) Djakovo (CRO) 103.9 36.9 36
OHL 220 kV Mostar (B&H) Zakucac (CRO) 127.6 -16.2 33
OHL 220 kV Visegrad (B&H) Vardiste (SER) -53.0 59.2 26
OHL 220 kV Sarajevo 20 (B&H) Piva (MON) -147.1 -16.6 38
OHL 220 kV Trebinje (B&H) Perucica (MON) 34.1 18.8 14
OHL 400 kV Blagoevgrad (BUL) Thessaloniki (GRE) 31.9 -49.4 8
OHL 400 kV M.East 3 (BUL) Filippi (GRE) 240.9 -38.9 35
OHL 400 kV M.East 3 (BUL) Babaeski (TUR) 11.0 -11.9 5
OHL 400 kV M.East 3 (BUL) Hamitabat (TUR) 12.7 -7.2 5
OHL 400 kV C.Mogila (BUL) Stip (MCD) 175.7 -48.7 25
OHL 400 kV Dobrudja (BUL) Isaccea (ROM) 199.5 -40.8 15
OHL 2x400 kV ckt.1 Kozloduy (BUL) Tantarena (ROM) -129.5 -6.1 10
OHL 2x400 kV ckt.2 Kozloduy (BUL) Tantarena (ROM) -129.5 -6.1 10
OHL 400 kV Sofia West (BUL) Nis (SER) 377.1 108.2 55
OHL 2x400 kV ckt.1 Zerjavinec (CRO) Heviz (HUN) -105.4 -62.5 9
OHL 2x400 kV ckt.2 Zerjavinec (CRO) Heviz (HUN) -105.4 -62.5 9
OHL 2x400 kV ckt.1 Ernestinovo (CRO) Pecs (HUN) -77.4 -46.8 7
OHL 2x400 kV ckt.2 Ernestinovo (CRO) Pecs (HUN) -77.4 -46.8 7
OHL 2x400 kV ckt.1 Tumbri (CRO) Krsko (SLO) -176.0 29.3 16
OHL 2x400 kV ckt.2 Tumbri (CRO) Krsko (SLO) -176.0 29.3 16
OHL 400 kV Melina (CRO) Divaca (SLO) 66.8 53.5 10
OHL 400 kV Ernestinovo (CRO) S.Mitrovica (SER) -332.1 71.3 25
OHL 220 kV Zerjavinec (CRO) Cirkovce (SLO) -44.9 16.6 16
OHL 220 kV Pehlin (CRO) Divaca (SLO) 32.7 19.3 13
OHL 400 kV Dubrovo (MCD) Thessaloniki (GRE) -68.7 -33.2 6
OHL 400 kV Bitola (MCD) Florina (GRE) -63.7 -48.1 6
OHL 400 kV Skopje (MCD) Kosovo B (UNMIK) 26.0 -21.7 3
OHL 2x220 kV ckt.1 Skopje (MCD) Kosovo A (UNMIK) 6.9 -29.4 9
OHL 2x220 kV ckt.2 Skopje (MCD) Kosovo A (UNMIK) 6.9 -29.4 9
OHL 400 kV Arad (ROM) Sandorfalva (HUN) 248.6 -59.7 21
OHL 400 kV - Nadab (ROM) Bekescaba (HUN) 281.9 -74.5 24
OHL 400 kV Rosiori (ROM) Mukacevo (UKR) 90.9 -59.7 9
OHL 400 kV Portile De Fier (ROM) Djerdap (SER) 249.7 41.6 19
OHL 400 kV Subotica (SER) Sandorfalva (HUN) -32.0 -135.1 10
OHL 400 kV Ribarevine (MON) Kosovo B (UNMIK) -296.0 -15.0 22
OHL 220 kV Pljevlja (MON) Bajina Basta (SER) -46.0 10.7 17
OHL 220 kV Pljevlja (MON) Pozega (SER) 34.9 35.3 19

4.5
Figure 4.1.3 shows that the tie lines in the region are mostly loaded less than 25% of their thermal
limits for the analyzed hydrological base case scenario in year 2010. Among total number of forty
nine 400 kV and 220 kV interconnection lines in the region only seven are loaded between 25% and
50% of their thermal ratings. Only one line (OHL 400 kV Sofia – Nis between Bulgaria and Serbia)
is loaded more than 50% of its thermal rating, which is set at lower value (692.8 MVA) on the
Bulgarian side compared to the line rating on the Serbian side (1330.2 MVA).

45
40
35
30
Frequency

25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.1.3 - Histogram of interconnection lines loadings for 2010-base case-average hydrology scenario ("Frequency"
denotes number of lines and "Bin" denotes loading range in % of thermal limit)

Table 4.1.3 lists all network elements loaded over 80% of their thermal limits. As it can be seen
from this output list, most of the elements loaded over 80% are transformers in some substations
and internal 110 kV and 220 kV lines. Thus, certain internal network reinforcements are necessary
to sustain given load-demand level and production pattern.

Two 220/110 kV transformers in the Fierze substation in Albania are slightly overloaded in this
scenario, while the third transformer in the same substation is loaded near permitted values. It is
expected that the transformers in that substation will be replaced with larger transformer units.

There are two 110 kV internal lines in Romania which are loaded over 80% of their thermal limits,
but none of them is overloaded. These lines are related to the Bojuren and Domnesti nodes.

Two 220 kV lines and thirteen 110 kV lines in the Serbian power system are highly loaded when all
branches are available in the analyzed scenario. Highly loaded 220 kV lines are connected to the
Obrenovac substation, while 110 kV lines are located mostly in the area of Belgrade. Four 110 kV
lines are overloaded, ranging between 108% Ithermal and 118% Ithermal.

Power systems of Bulgaria, Bosnia and Herzegovina, Croatia, Macedonia and Montenegro do not
have or have very few highly loaded branches in 110 kV networks.

Figure 4.1.4 shows histogram of 400 kV and 220 kV regional internal lines and 400/x kV and 220/x
kV transformers loadings. 47% of observed branches are loaded below 25% of their thermal ratings,
34% are loaded between 25% and 50%, 16% are loaded between 50% and 75% and only 2% of
observed branches are loaded between 75% and 100% of their thermal ratings. Two branches
(transformers 220/110 kV Fierze in Albania, 102% - 106% Sn) are overloaded if all branches are in
operation for the analyzed scenario.

4.6
Table 4.1.3 - Network elements loaded over 80% of thermal limits for 2010-base case-average hydrology scenario

LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Transformers
TR 220/110 kV AFIER 2-AFIER 5 ckt.1 116.8 120.0 93.7
ALB TR 220/110 kV AFIER 2-AFIER 5 ckt.2 95.7 90.0 106.4
TR 220/110 kV AFIER 2-AFIER 5 ckt.3 91.4 90.0 101.5
BIH TR 400/110 kV UGLJEV 1 254.8 300 84.9
TR 400/220 kV MINTIA-MINTIA B 385.7 400.0 96.4
ROM
TR 220/110 kV FUNDENI-FUNDE2B 173.1 200.0 86.6

400
350
300
Frequency

250
200
150
100
50
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.1.4 - Histogram of 400 kV and 220 kV regional lines loadings for 2010-base case-average hydrology scenario
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

4.1.2 Voltage Profile in the Region

Voltage profile in the region within this scenario which is defined by given generation and demand
pattern is seen as satisfactory despite several appearances of certain bus voltage deviations. The
deviations are shown in Table 4.1.4, which includes only 400 kV and 220 kV network buses.

Table 4.1.4 - Bus voltage deviations for 2010-base case-average hydrology scenario, complete network
Voltages
Country Node
pu kV
ALBANIA - - -
BOSNIA AND HERZEGOVINA - - -
400 kV VARNA4 1.054 421.4
400 kV BURGAS 1.051 420.5
400 kV MARITSA EAST2 1.055 422.1
400 kV TECMIG5 1.051 420.5
400 kV TECMIG7 1.051 420.5
400 kV DOBRUD4 1.053 421.3
BULGARIA 400 kV MARITSA EAST 3_4_1 1.051 420.5
400 kV TECMIG6 1.051 420.5
220 kV SESTRIMO 1.104 242.8
220 kV BPC_220 1.102 242.5
220 kV MIZIA2 1.101 242.1
220 kV AEC_220 1.103 242.6
220 kV TECVARNA 1.104 242.9
CROATIA - - -
MACEDONIA - - -
MONTENEGRO - - -
ROMANIA - - -
SERBIA AND UNMIK - - -

4.7
Bus voltage magnitudes below permitted limits are not found in the analyzed scenario. Bus voltage
magnitudes that are found above permitted limits (110% Vnominal in 110 kV and 220 kV networks
and 105% Vnominal in 400 kV network) are detected only in Bulgaria. There are eight 400 kV buses
and five 220 kV buses with voltages slightly above permitted limits. Figure 4.1.5 shows histogram
of voltages in monitored 400 kV and 220 kV substations.

120
100
Frequency

80
60
40
20
0
x<0.9

0.9<x<0.95

0.975<x<1

1<x<1.025

1.05<x<1.1

x>1.1
0.95<x<0.975

1.025<x<1.05
Bin

Figure 4.1.5 - Histogram of voltages in monitored substations for 2010-base case-average hydrology scenario
("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

It should be emphasized that these results represent only a situation when additional devices
(transformer automatic tap changers, switched shunts, etc.) are not used for voltage regulation.
Impacts of such devices, which exist in many points of the SEE regional transmission network,
need more comprehensive and thorough analysis.

4.1.3 Security (n-1) analysis

Results of security (n-1) analysis for the 2010-base case-average hydrology scenario are presented
in Table 4.1.5 and Table 4.1.6.

Insecure states for given generation and demand pattern are detected mostly in the power systems of
Romania and Serbia, although there is one contingency in Albania which leads to insecure state.

The most critical branch in the analyzed load/generation scenario is the transformer 400/220 kV in
the Mintia B substation in Romania. It is due to a high level of generation in DEVA 1 power plant
(850 MW), which is connected to 220 kV busbars in that substation. Noted transformer becomes
overloaded if one among eleven 400 kV and 220 kV lines or 400/220 kV transformers in the
Romanian or Serbian power system goes out of operation. Secure operating conditions can be
achieved if the generation level in DEVA 1 (Mintia) power plant is significantly lowered. Other
way to achieve more secure operation with the same level of production in DEVA 1 power plant is
to change network topology (connect generators in DEVA 1 to the second busbars or to connect
two busbar systems in Mintia substation). Loss of 400/220 kV transformer in the Mintia B
substation can jeopardize system security due to possible overloading of two 220 kV lines in
Romania. Loss of one 400 kV line in Romania (Mintia-Arad) is critical because the 400 kV line
Mintia-Sibiu can be overloaded. Single outages of 400/110 kV transformers in the stations Brasov

4.8
and Dirste in Romania are also found critical, since the second transformer 400/110 kV in the
Brasov substation is permanently out of operation in the model.

Loss of OHL 220 kV in the Belgrade area can cause overloading of the parallel line. Loss of one
400/110 kV transformer in the Nis substation is critical due to possible overloading of the other
parallel one.

Loss of 220 kV line between the Rashbul and Tirana substations can cause overloading of 220 kV
line between the Elbasan and Fier substations in Albania.

The heaviest line overloading (147% Ithermal) in the analyzed scenario is related to a 220 kV line in
Romania around the Mintia substation. The heaviest transformer overloading (137% Sn) is related to
the transformer 400/110 kV in the Dirste substation (Romania) when the transformer 400/110 kV in
the Brasov substation is outaged (the parallel one is permanently out of operation in the model).

Figure 4.1.6 shows geographical positions of critical elements in the analyzed scenario. A green
color reveals 220 kV elements (line 220 kV or transformer 220/x kV), while a red one reveals 400
kV elements (line 400 kV or transformer 400/x kV).

According to the obtained and presented results, it may be concluded that a re-dispatching of
generation in the Romanian power system, especially of the DEVA 1 power plant (to decrease its
generation level from the initially assumed 850 MW in this scenario), as well as certain
reinforcements in the internal networks of Romania, Albania and Serbia are necessary shall this
generation/load pattern be made more secure. Re-dispatching of Romanian power plants may be
avoided if network topology is changed, especially in Mintia substation. None of the identified
congestions is located at the border lines.

Table 4.1.5 - Lines overloadings for 2010–base case-average hydrology scenario, single outages
Loadings
Outage Overloaded line(s) Country
MVA %
OHL 220 kV AKASHA2-ARRAZH2 OHL 220 kV AELBS12-AFIER 2 253.1 113.2 ALBANIA
OHL 400 kV MINTIA-ARAD OHL 400 kV MINTIA-SIBIU 408.2 106.5
TR 400/220 kV MINTIA B OHL 220 kV PESTIS-MINTIA A 431.1 147.3 ROMANIA
TR 400/220 kV MINTIA B OHL 220 kV PESTIS-MINTIA B 351.4 119.3
OHL 220 kV JBGD172-JBGD8 22 ckt.1 OHL 220 kV JBGD172-JBGD8 22 ckt.2 434.8 122.2 SERBIA

Table 4.1.6 - Transformers overloadings for 2010–base case-average hydrology scenario, single outages
Loadings
Outage Overloaded branch(es) Country
MVA %
OHL 400 kV TANTAREN-SIBIU TR 400/220 kV MINTIA B 412.1 103.0
OHL 220 kV HAJD OT-MINTIA B TR 400/220 kV MINTIA B 404.4 101.1
OHL 220 kV PESTIS-MINTIA A TR 400/220 kV MINTIA B 511.2 127.8
OHL 220 kV MINTIA A-TIMIS TR 400/220 kV MINTIA B 412.3 103.1
OHL 220 kV MINTIA B-AL.JL TR 400/220 kV MINTIA B 474.8 118.7
OHL 220 kV CLUJ FL-AL.JL TR 400/220 kV MINTIA B 496.0 124.0 ROMANIA
TR 400/220 kV MINTIA A TR 400/220 kV MINTIA B 530.8 132.7
TR 400/220 kV MINTIA B TR 400/220 kV MINTIA A 459.5 114.9
TR 400/220 kV ARAD TR 400/220 kV MINTIA B 401.2 100.3
TR 400/220 kV BUC.S ckt.1 TR 400/220 kV BUC.S ckt.2 410.2 102.5
400/110 kV BRASOV 400/110 kV DIRSTE 341.3 136.5
400/110 kV DIRSTE 400/110 kV BRASOV 337.5 135.0
400/110 kV NIS ckt.1 400/110 kV NIS ckt.2 312.3 104.1 SERBIA

4.9
SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE
400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.1.6 - Geographical positions of the critical elements for 2010-base case-average hydrology scenario

4.10
4.2 Scenario 2010 – dry hydrology
This part of the Study presents the results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as GTmax run for year 2010 - dry hydrology.

4.2.1 Lines loadings


Figure 4.2.1 shows power exchanges between areas for 2010-dry hydrology scenario. Power flows
along interconnection lines in the region together with balances of the systems are shown in Figure
4.2.2. Area totals are shown in Table 4.2.1. Figure 4.2.3 shows histogram of tie lines loadings. It is
concluded that most of the tie lines are loaded less than 25% of their thermal limits.
SVK UKR
0
450 42

30
AUT
28
9

HUN
16
8
68

SLO
47

ROM
31

ITA
14
7

CRO 195
52
2

4
17

BIH 89 SRB
164
36

273
27
0

MNG BUL
33
34
16
7

27

74
MKD
122

TUR
ALB 27
95
25
0

GRE

Figure 4.2.1 - Area exchanges in analyzed electric power systems for 2010-dry hydrology scenario

Table 4.2.1 - Area totals in analyzed electric power systems for 2010-dry hydrology scenario
AREA GENERATION LOAD LOSSES INTERCHANGE
ALBANIA 953.3 1290.5 46.8 -384
BULGARIA 6709.6 5970 133.6 606
BIH 2842.4 1989 60.3 793
CROATIA 2294.6 3147 41.6 -894
MACEDONIA 1021.1 1206 18.1 -203
ROMANIA 6742 6703.8 238 -199.9
SERBIA 7311.7 6944 201.6 166
MONTENEGRO 467.8 671 16.9 -220
TOTALS 28342.5 27921.3 756.9 -335.9

4.11
GABICK1400.0 LEVIC 1400.0

CENTREL

251
113

200
140
450.0 MW
346 350
MAISA 7 UZUKRA01
804 297

UCTE OWIEN 1 MGYOR 4 714.8 772.5


0
25 .4
223.5 MW
UKR
405.4 106 105
90

94.6
199
24.2 101 MSAJI 408.1 35.5 35.6
403.3 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.5 OWIEN 2 MGOD 4 407.6 226.3
20.9 27.7
450.0 MW
10.8 10.6

49.2

39.5
41.8
39.5
41.8
156
MGYOR 2 MTLOK 2
52.7 52.2 7.6 29.2
234.2 230.5 224.4
5.8 20.7
ONEUSI2 UMUKACH
233.5 23.0 22.9 228.9 39.0 39.1 37.
MSAJO 4
12.7 26.6
410.0
71.8 47.0
412.0 70. 1
5

-1250.0 MW
HUN

10. 5

10. 5
7

5
154

39.

39.
45.

36. 1
13
LPODLO2228.9 LMARIB1 402.4 64.7 64.8
MBEKO 4 NADAB

8
MHEVI 4 408.3 52.7 71.6 ROSIORI 402.1
LDIVAC1 404.6 402.2
215.0 MW

35.4
21.9
35.4
21.9
IRDPV111

SLO
180 180
3.3 24.1 97
400.9 400.9 30 .7 MPECS 4 408.2 MSAFA 4 402.4
.7
LKRSKO1 401.0 LCIRKO2 227.1 38.0 38.0 ARAD
LDIVAC2 .5
30 41

37 .7

37 .7
16.6 43.0

26.9

26.9
156

156

6.5
4.2

.8

.8
IPDRV121 1 401.5

71

71
11.4 11.4 10
73.6 77.1 2. .7
230.3 229.3 6

ROM
ISACCEA 405.4

8
97.8
7.2

71 5.8
.3 .3

71.

212
121
35 .2 35 .2
-369.2 MW

30.7
85 .8

165
85 85

.8
ERNESTIN

6. .7
MELINA 402.1 ZERJAVIN 403.4 JSOMB31
393.4 JSUBO31 396.0

5
5
ZERJAVIN 226.9 207 208
JSMIT21
10.7

15 0

15 0
40.3 85.1

2.

2.
7.6

404.5

29.5
153
TUMBRI 401.0 DAKOVO 222.5

24 4.0
PEHLIN 229.2 MRACLIN 222.3MEDURIC 219.6

59.9
27.1

47.0
110

.0
400.9

5
34.7
26.6

4.9
6.8
JHDJE11 P.D.FIE
69.5 69.5
72.5 71.5 TANTAREN 413.7
405.9 406.0

CRO

76.1
35.8
76.1
35.8
53.9

60. 7
22.

81.
153
-1086.4 MW 16.2

2
34 .3

4.9

4
46
11 0
1.1
34
.9 GRADACAC 225.5 UGLJEVIK 400.9

.
2
SCG
PRIJED2 220.1 TE TUZL 231.7

VISEGRA JVARDI22
37.2 37.3 229.6 756.2 MW

214
231.4

9.8
76 .0

76 .0
14

14
51.9 54.0

BIH

.1

.1
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 414.7 DOBRUD4 417.1
317 319 758.8 MW 230.5 138 139 236.0 CRG 864.0 MW JNIS2 1 228 230 SOFIA_W4
402.2
16.4 24.0
404.6
29.5 26.3
-107.7 MW 396.5
145 92.4
411.0
HE ZAKUC 127 130 MO-4 RP TREB JHPERU21
18.2 19.2 103 102 221.1
231.4 232.4 228.9
43.5 45.0

BUL
148 147
RP TREB JPODG211 JLESK21
147 181 JPODG121219.0
396.9 0.000
766.0 MW

205
165
JPRIZ22
214.1 JTKOSA2
227.0JTKOSB1412.4

73.7
47.1
384.0

.1 8
25 2.

18. 0

18. 0

347
20.0
8

17.

17.
JVRAN31

7
0.000

72.8
50.8

28 1.9
.5
8
204
180
AVDEJA1 AVDEJA2
373.2 210.7AFIERZ2208.0 C_MOGILA

18.6
27.5
18.6
27.5

48.8
345
204
180
.0
SK 1 222.9 SK 4
407.5 407.7 48 .0
34 412.8

-444.0 MW STIP 1 .9
47 .8

MKD
BITOLA 2 414.2
410.5
59

BLAGOEV413.3 MI_3_4_1 419.3


DUBROVO 410.7
202
204

35.3
45.4
1
13 1.3

45. 9
AKASHA1 358.9

5
48.0
5.0

8. 6.
17
18. 1
.8

72.

1
5 9
1
ALB
-720.0 MW .4

18. 7
35 . 4

49.

11 9.1
63.7
49

8.5

8
.3
8 4HAMITAX

1
AHS_FLWR416.1 LAGAD K 413.3 17 7.2 8.5 8.5 415.4
FILIPPOI 7
19.8 19.8 63.7 75.0
381.4 4BABAESK

14.0
21.7
K-KEXRU
417.8 70.7

5.0
KARDIA K 415.5 415.5
357 364 414.9 QES/H K 412.2
271 257
AZEMLA1
0.0 MW
0.2 MW TUR
GRE
KARACQOU
250 418.1
50.0

GIS REGIONAL MODEL - DRY HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2010 TOPOLOGY 2010 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 4.2.2 - Power flows along interconnection lines in the region with balances of the systems for 2015-dry hydrology scenario – 2010 topology

4.12
Histogram
50
45
40
35

Frequency
30
25
20
15
10
5
0
25 50 75 100 More
Bin

Figure 4.2.3 - Histogram of interconnection lines loadings for 2010-dry hydrology scenario ("Frequency" denotes
number of lines and "Bin" denotes loading range in % of thermal limit)

Following Table 4.2.2 shows all network elements loaded over 80% of their thermal limits. As it
can be seen only transformers 220/110 kV in substation Fier in Albania are highly loaded. Also,
transformer 220/110 kV in substation Fundeni in Romania is loaded over 80 % of its thermal limit.
Figure 4.2.4 shows histogram of branch loadings in the system. As for the conclusion regarding
thermal loadings in this scenario it can be said that almost all of the network elements are loaded
less then 75% of their thermal limits, but there are some elements highly loaded. The elements
loaded over 80% are transformers 220/110 kV in substation Fier and transformer 220/110 kV in
substation Fundeni in Romania, so some internal network reinforcements are necessary to sustain
this load-demand level and production pattern. It is expected that transformers in Fierza substation
will be replaced with more powerful transformer units.

Table 4.2.2 - Network elements loaded over 80% of their thermal limits for 2010-dry hydrology scenario
BRANCH LOADINGS ABOVE 80.0 % OF RATING:
LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Transformers
TR 220/110 kV AFIER 1 106.8 120 89
ALB TR 220/110 kV AFIER 2 87.5 90 97.2
TR 220/110 kV AFIER 3 83.5 90 92.8
ROM TR 220/110 kV FUNDE2 1 168.1 200 84.1

Histogram
400
350
300
Frequency

250
200
150
100
50
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.2.4 - Histogram of branch loadings for 2010-dry hydrology scenario ("Frequency" denotes number of branches
and "Bin" denotes loading range in % of thermal limit)

4.13
4.2.2 Voltage Profile in the Region

Figure 4.2.5 shows histogram of voltages in monitored substations. Voltages in almost all
monitored substations are found within permitted limits.

Histogram

140

120

100
Frequency

80

60

40

20

0
x<0.9

0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

Bin x>1.1

Figure 4.2.5 - Histogram of voltages in monitored substations for 2010-dry hydrology scenario ("Frequency" denotes
number of busses and "Bin" denotes voltage range in p.u.)

In the rest of the monitored network the voltage profile is satisfying and that most of the substations
have magnitudes in range 0.975-1.05 p.u.

4.2.3 Security (n-1) analysis

Results of security (n-1) analysis for 2010-dry hydrology scenario are presented in Table 4.2.3.
Figure 4.2.6 shows the geographical position of the critical elements in monitored systems.

It can be concluded that all identified insecure states are located in internal networks that belong to
monitored power systems of Romania and Serbia. In the most critical cases in Romanian system,
the critical elements are transformers 400/110 kV in substations Dirste and Brasov. The most
critical elements in Serbian system are lines 220 kV Beograd 8 – Beograd 17 and Obrenovac –
Beograd 3.

Some of the overloadings identified can be relieved by certain dispatch actions (splitting busbars,
changing lower voltage network topology in order to redistribute load-demand or change of
generation units engagement), like in the case of most severe overloading in Romanian network
happens on transformer 400/110 kV Dirste when transformer 400/110 kV in Brasov is outaged, but
this is a consequence of the fact that second transformer unit 400/110 kV in Brasov is out of

4.14
operation. Switching on of this transformer clears this critical outage. The similar situation is with
outage of the 400 kV line Obrenovac-Beograd 3 in Serbia. Splitting off the 220 kV busbars in
substation Beograd 3 relieves this overloading, but voltage profile in Serbian network remains
critical, so additional dispatching actions are necessary too.

All in all, certain reinforcement of internal network is necessary (more about this in chapter 6) in
order to make this regime more secure. None of the identified congestions is located at border lines.

Table 4.2.3 - Network overloadings for 2010-dry hydrology scenario, single outages
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
CS OHL 220kV JBGD172 -JBGD8 22 1 CS HL 220kV JBGD172-JBGD8 22 2 365.8MVA 440.8MVA 123.1%
CS OHL 400kV JBGD8 1 -JOBREN11 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 340.1MVA 115.4%
RO TR 400/110 BRASOV 1 RO TR 400/110kV/kV DIRSTE 1 250MVA 333.3MVA 133.3%
RO TR 400/110 DIRSTE 1 RO TR 400/110kV/kV BRASOV 1 250MVA 329.9MVA 132.0%
CS TR 400/110 JNIS2 1 CS TR 400/110kV/kV JNIS2 1 2 300MVA 338.2MVA 112.7%
RO TR 400/220 BUC.S 1 RO TR 400/220kV/kV BUC.S 2 400MVA 403.8MVA 101.0%
RO TR 400/220kV/kV MINTIA 1 400MVA 419.5MVA 104.9%
RO TR 400/220 MINTIA 1
RO HL 220kV PESTIS-MINTIA A 1 277.4MVA 313.9MVA 105.5%
RO TR 400/220 MINTIA 1 RO TR 400/220kV/kV MINTIA 1 400MVA 433MVA 108.3%

SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE 400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.2.6 – Geographical position of critical elements for 2010-dry hydrology scenario

4.15
4.3 Scenario 2010 – wet hydrology
This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as Scenario 2010 – wet hydrology.

4.3.1 Line loadings


Area totals and power exchanges for the 2010-base case-wet hydrology scenario are shown in
Figure 4.3.1 and Table 4.3.1. Power flows along regional interconnection lines and system balances
are shown in Figure 4.3.2. Power flows along interconnection lines are also given in Table 4.3.2,
while Figure 4.3.3 shows histogram of tie lines loadings.

SVK
4 50 UKR

7
54

97
AUT
1
51

HUN
37
2
71

SLO
35
6

ITA ROM
30
28
6

CRO 356
50
5

5
17

357 SRB
BIH
12

41 4
12

1
25
9

MNT BUL
21

118
4

1
6

15
MKD
247

TUR
ALB
99

0 16
41
4

GRE
2 50

Figure 4.3.1 - Area exchanges in analyzed electric power systems for 2010-base case-wet hydrology scenario

Table 4.3.1 - Area totals in analyzed electric power systems for 2010-base case-wet hydrology scenario
Country Generation Load Bus Shunt Line Shunt Losses Net Interchange
(MW) (MW) (Mvar) (Mvar) (MW) (MW)
Albania 898.6 1287.3 0 0 50.3 -439.0
Bulgaria 6940.4 5966.2 0 14.3 120.9 839.0
Bosnia and Herzegovina 2037.1 1961.1 0 0 57.0 19.0
Croatia 1735.4 3136.7 0 0 50.7 -1452.0
Macedonia 1081.8 1194.0 0 0 19.8 -132.0
Romania 7342.4 6423.7 0 79.9 206.6 632.2
Serbia and UNMIK 7406.2 6875.1 0 13.6 220.4 297.1
Montenegro 586.3 669.2 0.6 1.6 15.9 -101.0
TOTAL - SE EUROPE 28028.1 27513.3 0.6 109.4 741.5 -336.7

4.16
GABICK1400.0 LEVIC 1400.0

CENTREL

251
117

200
144
450.0 MW
346 350
MAISA 7 UZUKRA01
802 300

UCTE OWIEN 1 MGYOR 4 715.3 772.5


0
25 .8
221.7 MW
UKR
405.6 87.2 87.1
94

98.7
199
22.9 103 MSAJI 408.2 35.5 35.6
403.5 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 402.6 OWIEN 2 MGOD 4 407.9 226.3
21.0 27.8
450.0 MW
10.8 10.6

41.0

53.3
52.8
53.3
52.8
164
MGYOR 2 MTLOK 2
46.4 46.0 7.7 29.3
234.3 230.5 224.4
6.9 22.3
ONEUSI2 UMUKACH
233.5 17.8 17.6 229.0 173 174 97.
MSAJO 4
13.9 27.9
410.0
56.4 53.0
412.0 6.6 1

HUN
-1249.7 MW

21. 2

21. 2
5

6
162

53.

53.
36.

97. 0
56.
LPODLO2229.9 LMARIB1 403.9 217 217
MBEKO 4 NADAB

3
MHEVI 4 409.5 49.0 63.5 ROSIORI 410.7
LDIVAC1 407.0 405.5
215.0 MW

93.6
40.7
93.6
40.7
IRDPV111

SLO
168 169
63.5 42.5 10
401.5 403.1 90 0 MPECS 4 409.4 MSAFA 4 404.5
.4
LKRSKO1 403.2 LCIRKO2 228.8 155 155 ARAD
LDIVAC2 .1
35 26

5. 3

5. 3
6.9 48.5

.
53.2

53.2

44.1
24.2
179

179

7
IPDRV121 1 403.9

59

59
30.4 30.4 40
45.4 49.0 28 .3
231.4 230.8 .2

ROM
ISACCEA 415.7

3
67.1
100

59 5.0
.3 .3

97.1
59.

172
93 .4 93 .4
631.9 MW

35.2
55 .3

151
65 65

.0
ERNESTIN

43 5.
MELINA 407.4 ZERJAVIN 406.6 JSOMB31
396.5 JSUBO31 398.7

1
.8 4
ZERJAVIN 230.2 355 357
JSMIT21
40.4

17 8

17 8
75.5 104

28

28
18.7

407.0

9
.

22.2
126
TUMBRI 404.2 DAKOVO 224.3

58 277
PEHLIN 233.8 MRACLIN 226.9MEDURIC 226.3

49.4
20.5

91.5
36.0

.9
402.4

59.4
24.6

57.2
14.8
JHDJE11 P.D.FIE
175 175
38.0 37.1 TANTAREN 415.7
404.9 405.0

CRO

80.3
40.5
80.3
40.5
276

49. 5
15.

76.
127
-1452.0 MW 30.1

57.6

92 .0
6
21.3
59 .8

7
32
31

.6
GRADACAC 226.6 UGLJEVIK 403.7
.9

SCG
PRIJED2 225.5 TE TUZL 231.3

VISEGRA JVARDI22
196.1 MW

47.0
80.1 80.4 230.0

173
231.7

80 .6

80 .6
59.3 60.4

9
BIH

.2

.2
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 416.1 DOBRUD4 421.8
222 223 19.0 MW 231.3 169 171 235.8 CRG 297.1 MW JNIS2 1 411 415 SOFIA_W4
410.6
7.0 61.5
409.2
16.2 18.1
-101.0 MW 396.4
128 105
412.3
HE ZAKUC 55.5 56.0 MO-4 RP TREB JHPERU21
13.7 25.6 35.3 35.2 229.9
236.9 235.2 233.3
18.0 25.9

BUL
19.9 20.0
RP TREB JPODG211 JLESK21
78.3 122 JPODG121228.8
404.6 387.6
839.0 MW

23.8
22.4
JPRIZ22
223.3 JTKOSA2
227.3JTKOSB1407.4

2.9
6.1
397.6

43 4.2
.8

28. 6

28. 6

60.7
28.3
19.

19.
JVRAN31

3
0.000

15.6
2.9

35 .0
.1
23.7
50.4

4
AVDEJA1 AVDEJA2
395.7 227.5AFIERZ2228.6 C_MOGILA

28.5
29.7
28.5
29.7
60.8
21.7
24.5
129
1
15 6
SK 1 224.2 SK 4
408.1 409.0 . 414.2
48

-132.0 MW STIP 1 0
15 .6

MKD
BITOLA 2 416.6
412.9
40

BLAGOEV414.8 MI_3_4_1 420.6


24.1

DUBROVO 412.8
168

17.8
47.0
8
6. .4

38. 0
AKASHA1 386.2

5
59.4
31.2

7. 1.
23
39. 9
1

45.

1
5 0
5
ALB
-439.0 MW .7

39. 2
17 .7

23.

69.8

8. .1
48

7.5

97
9 4HAMITAX

3
AHS_FLWR417.8 LAGAD K 414.2 22 8.1 7.5 7.5 415.6
FILIPPOI 7
15.9 15.9 69.8 81.2
398.3 4BABAESK

59.4
30.5
21.8
K-KEXRU
417.9 70.9
KARDIA K 415.7 415.7
412 418 416.9 QES/H K 413.3
134 111
AZEMLA1
0.0 MW
-0.1 MW TUR
GRE
KARACQOU
250 419.1
0.0

GIS REGIONAL MODEL - WET HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2010 TOPOLOGY 2010 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 4.3.2 - Power flows along interconnection lines in the region for 2010 - base case - wet hydrology scenario
4.17
Table 4.3.2 - Power flows along regional interconnection lines for 2010 wet hydrology scenario

Power Flow
Interconnection line % of thermal
rating
MW Mvar
OHL 400 kV Zemlak (ALB) Kardia (GRE) -411.6 -134.3 32
OHL 220 kV Fierze (ALB) Prizren (SER) -4.0 35.1 14
OHL 220 kV V.Dejes (ALB) Podgorica (MON) 2.9 -15.6 5
OHL 400 kV V.Dejes (ALB) Podgorica (MON) -23.7 -50.4 4
OHL 400 kV Ugljevik (B&H) Ernestinovo (CRO) 126.8 -76.7 11
OHL 400 kV Mostar (B&H) Konjsko (CRO) 223.2 -61.5 17
OHL 400 kV Ugljevik (B&H) S. Mitrovica (SER) -275.6 30.1 21
OHL 400 kV Trebinje (B&H) Podgorica (MON) -19.9 78.3 9
OHL 220 kV Trebinje (B&H) Plat (CRO) -104.8 39.9 36
OHL 220 kV Prijedor (B&H) Mraclin (CRO) 59.9 -31.8 21
OHL 220 kV Prijedor (B&H) Medjuric (CRO) 57.6 -21.3 19
OHL 220 kV Gradacac (B&H) Djakovo (CRO) 49.6 15.5 18
OHL 220 kV Tuzla (B&H) Djakovo (CRO) 92.6 32.0 32
OHL 220 kV Mostar (B&H) Zakucac (CRO) 56.0 -25.6 18
OHL 220 kV Visegrad (B&H) Vardiste (SER) -80.1 59.3 32
OHL 220 kV Sarajevo 20 (B&H) Piva (MON) -169.2 -16.2 44
OHL 220 kV Trebinje (B&H) Perucica (MON) 35.3 18.0 14
OHL 400 kV Blagoevgrad (BUL) Thessaloniki (GRE) 17.8 -47.0 7
OHL 400 kV M.East 3 (BUL) Filippi (GRE) 230.0 -38.5 34
OHL 400 kV M.East 3 (BUL) Babaeski (TUR) 7.5 -11.0 5
OHL 400 kV M.East 3 (BUL) Hamitabat (TUR) 8.4 -6.1 5
OHL 400 kV C.Mogila (BUL) Stip (MCD) 151.0 -48.6 22
OHL 400 kV Dobrudja (BUL) Isaccea (ROM) 172.5 -47.0 13
OHL 2x400 kV ckt.1 Kozloduy (BUL) Tantarena (ROM) -80.2 -9.6 6
OHL 2x400 kV ckt.2 Kozloduy (BUL) Tantarena (ROM) -80.2 -9.6 6
OHL 400 kV Sofia West (BUL) Nis (SER) 414.9 105.0 60
OHL 2x400 kV ckt.1 Zerjavinec (CRO) Heviz (HUN) -93.3 -65.4 9
OHL 2x400 kV ckt.2 Zerjavinec (CRO) Heviz (HUN) -93.3 -65.4 9
OHL 2x400 kV ckt.1 Ernestinovo (CRO) Pecs (HUN) -59.3 -55.0 6
OHL 2x400 kV ckt.2 Ernestinovo (CRO) Pecs (HUN) -59.3 -55.0 6
OHL 2x400 kV ckt.1 Tumbri (CRO) Krsko (SLO) -178.6 28.8 16
OHL 2x400 kV ckt.2 Tumbri (CRO) Krsko (SLO) -178.6 28.8 16
OHL 400 kV Melina (CRO) Divaca (SLO) 100.0 52.7 11
OHL 400 kV Ernestinovo (CRO) S.Mitrovica (SER) -354.6 75.5 28
OHL 220 kV Zerjavinec (CRO) Cirkovce (SLO) -43.8 15.4 15
OHL 220 kV Pehlin (CRO) Divaca (SLO) 40.4 18.7 15
OHL 400 kV Dubrovo (MCD) Thessaloniki (GRE) -59.4 -31.2 6
OHL 400 kV Bitola (MCD) Florina (GRE) -39.5 -45.9 4
OHL 400 kV Skopje (MCD) Kosovo B (UNMIK) 60.8 -21.7 5
OHL 2x220 kV ckt.1 Skopje (MCD) Kosovo A (UNMIK) 28.5 -29.7 13
OHL 2x220 kV ckt.2 Skopje (MCD) Kosovo A (UNMIK) 28.5 -29.7 13
OHL 400 kV Arad (ROM) Sandorfalva (HUN) 155.0 -48.5 28
OHL 400 kV - Nadab (ROM) Bekescaba (HUN) 217.3 -63.5 18
OHL 400 kV Rosiori (ROM) Mukacevo (UKR) 97.3 -56.0 9
OHL 400 kV Portile De Fier (ROM) Djerdap (SER) 174.5 37.1 13
OHL 400 kV Subotica (SER) Sandorfalva (HUN) 35.2 -151.3 12
OHL 400 kV Ribarevine (MON) Kosovo B (UNMIK) -300.0 -16.4 22
OHL 220 kV Pljevlja (MON) Bajina Basta (SER) -30.1 8.5 12
OHL 220 kV Pljevlja (MON) Pozega (SER) 46.0 34.5 21

4.18
Figure 4.3.3 shows that the tie lines in the region are mostly loaded less than 25% of their thermal
limits for the analyzed hydrological base case scenario in year 2010. Among total number of forty
nine 400 kV and 220 kV interconnection lines in the region only eight are loaded between 25% and
50% of their thermal ratings. Only one line (OHL 400 kV Sofia – Nis between Bulgaria and Serbia)
is loaded more than 50% of its thermal rating, which is set at lower value (692.8 MVA) on the
Bulgarian side compared to the line rating on the Serbian side (1330.2 MVA).

45
40
35
30
Frequency

25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.3.3 - Histogram of interconnection lines loadings for 2010-base case-wet hydrology scenario ("Frequency"
denotes number of lines and "Bin" denotes loading range in % of thermal limit)

Table 4.3.3 lists all network elements loaded over 80% of their thermal limits. As it can be seen
from this output list, most of the elements loaded over 80% are transformers in some substations
and internal 110 kV and 220 kV lines. Thus, certain internal network reinforcements are necessary
to sustain given load-demand level and production pattern.

Two 220/110 kV transformers in the Fierze substation in Albania are slightly overloaded in this
scenario, while the third transformer in the same substation is loaded near permitted values.

There are three 220 kV and two 110 kV internal lines in Romania which are loaded over 80% of
their thermal limits, but none of them is overloaded. These lines are related to the Lotru, Sibiu,
Parosen, Bojuren and Domnesti nodes. Transformer 220/110 kV in the Fundeni substation is highly
loaded in this scenario.

Two 220 kV lines and twelve 110 kV lines in the Serbian power system are highly loaded when all
branches are available in the analyzed scenario. Highly loaded 220 kV lines are connected to the
Obrenovac substation, while 110 kV lines are located mostly in the area of Belgrade. Four 110 kV
lines are overloaded, ranging between 108% Ithermal and 117% Ithermal.

Power systems of Bulgaria, Bosnia and Herzegovina and Croatia have several highly loaded
branches in 110 kV networks. High loading of 110 kV line Komolac-Plat is caused by radial
connection of one unit in the HPP Dubrovnik to the grid. High loading of 110 kV lines between the
Resnik, Zitnjak and TETO substations in the Zagreb area are caused by disconnection of generating
units in the TETO power plant in analyzed scenario. These combined heat and electricity generating
units are normally put into the operation during winter high load period, because their main purpose
is to produce heat for consumers in the Croatian capitol Zagreb.

4.19
Figure 4.3.4 shows histogram of 400 kV and 220 kV regional internal lines and 400/x kV and 220/x
kV transformers loadings. 46% of observed branches are loaded below 25% of their thermal ratings,
35% are loaded between 25% and 50%, 16% are loaded between 50% and 75% and only 2% of
observed branches are loaded between 75% and 100% of their thermal ratings. Two branches
(transformers 220/110 kV Fierze in Albania, 101% - 106% Sn) are overloaded if all branches are in
operation for the analyzed scenario.

Table 4.3.3 - Network elements loaded over 80% of thermal limits for 2010-base case-wet hydrology scenario

LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
OHL 220 kV LOTRU-SIBIU ckt.1 276.0 277.4 99.5
ROM OHL 220 kV LOTRU-SIBIU ckt.2 276.0 277.4 99.5
OHL 220 kV TG.JIU-PAROSEN 181.6 208.1 87.3
Transformers
TR 220/110 kV AFIER 2-AFIER 5 ckt.1 116.5 120.0 97.1
ALB TR 220/110 kV AFIER 2-AFIER 5 ckt.2 95.5 90.0 106.1
TR 220/110 kV AFIER 2-AFIER 5 ckt.3 91.1 90.0 101.3
ROM TR 220/110 kV FUNDENI-FUNDE2B 168.7 200.0 84.4

400
350
300
Frequency

250
200
150
100
50
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.3.4 - Histogram of 400 kV and 220 kV regional lines loadings for 2010-base case-wet hydrology scenario
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

4.3.2 Voltage Profile in the Region

Voltage profile in the region within this scenario which is defined by given generation and demand
pattern is seen as satisfactory despite several appearances of certain bus voltage deviations which
are shown in Table 4.3.4. Presented table includes only 400 kV and 220 kV network buses.

Bus voltage magnitudes below permitted limits are not found in the analyzed scenario. Bus voltage
magnitudes that are found above permitted limits (110% Vnominal in 110 kV and 220 kV networks
and 105% Vnominal in 400 kV network) are detected only in Bulgaria. There are nine 400 kV buses
and four 220 kV buses with voltages slightly above permitted limits. Figure 4.2.5 shows histogram
of voltages in monitored 400 kV and 220 kV substations.

4.20
Table 4.3.4 - Bus voltage deviations for 2010-base case-wet hydrology scenario, complete network
Voltages
Country Node
pu kV
ALBANIA - - -
BOSNIA AND HERZEGOVINA - - -
400 kV VARNA4 1.057 421.9
400 kV BURGAS 1.052 420.8
400 kV MARITSA EAST2 1.056 422.2
400 kV TECMIG5 1.052 420.6
400 kV TECMIG7 1.051 420.6
400 kV DOBRUD4 1.055 421.8
BULGARIA 400 kV MARITSA EAST 3_4_1 1.051 420.6
400 kV MARITSA EAST 1.051 420.6
400 kV TECMIG6 1.052 420.6
220 kV BPC_220 1.103 242.6
220 kV MIZIA2 1.101 242.3
220 kV AEC_220 1.103 242.7
220 kV TECVARNA 1.104 243.0
CROATIA - - -
MACEDONIA - - -
MONTENEGRO - - -
ROMANIA - - -
SERBIA AND UNMIK - - -

120
100
Frequency

80
60
40
20
0
x<0.9

0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

x>1.1

Bin

Figure 4.3.5 - Histogram of voltages in monitored substations for 2010-base case-wet hydrology scenario ("Frequency"
denotes number of busses and "Bin" denotes voltage range in p.u.)

4.3.3 Security (n-1) analysis

Results of security (n-1) analysis for the 2010-base case-wet hydrology scenario are presented in
Table 4.3.5 and Table 4.3.6.

Insecure states for given generation and demand pattern are detected in the power systems of
Romania and Serbia, although there is one contingency in Albania which leads to insecure state.

The most critical branches in the analyzed load/generation scenario are those ones connected to the
Sibiu substation 400/220 kV in Romania. Double circuit line 220 kV Lotru-Sibiu is loaded near
4.21
upper limit (99% Ithermal) when all branches are available. It becomes overloaded if one circuit goes
out of operation. Line 400 kV Mintia-Sibiu is overloaded when 400 kV line Sibiu-Iernut goes out of
operation. Transformer 400/220 kV in Sibiu is overloaded if the parallel one is unavailable.
Reasons for these overloadings are found in a rather high level of hydro generation in the LOTRU
CIUNGET power station in this scenario (478 MW). More secure operation could be achieved by
decreasing a generation level in this hydro power plant.

Double circuit 220 kV lines around the Resita substation (Portile de Fier-Resita and Timisoara-
Resita) are overloaded if one circuit goes out of operation, due to high generation in the PORTILE
1 hydro power plant (796 MW). Secure operation could be achieved by decreasing a generation
level in this power plant.

OHL 220 kV Targa Jiu-Paroseni is overloaded if one of the 400 kV lines Mintia-Sibiu, Tantareni-
Sibiu in Romania or Djerdap-Kostolac B in Serbia goes out of operation. Higher engagement of the
TPP Paroseni resolves these overloads.

Single outages of 400/110 kV transformers in the stations Brasov and Dirste in Romania are also
recognized as critical, since the second transformer 400/110 kV in the Brasov substation is
permanently out of operation in the model.

Loss of OHL 220 kV in the Belgrade area can cause overloading of the parallel line. Loss of one
400/110 kV transformer in the Nis substation is critical due to possible overloading of the other
parallel one.

Loss of 220 kV line between the Rrashbul and Tirana substations can cause overloading of 220 kV
line between the Elbassan and Fier substations in Albania.

The heaviest line overloading (124% Ithermal) in the analyzed scenario is related to a 400 kV line in
Romania around the Sibiu substation (Mintia-Sibiu). The heaviest transformer overloading (137%
Sn) is related to the transformer 400/110 kV in the Dirste substation (Romania) when the
transformer 400/110 kV in the Brasov substation is outaged (the parallel one is permanently out of
operation in the model).

Figure 4.3.6 shows geographical positions of critical elements in the analyzed scenario. A green
color reveals 220 kV elements (line 220 kV or transformer 220/x kV), while a red one reveals 400
kV elements (line 400 kV or transformer 400/x kV).

According to the obtained and presented results, it may be concluded that a re-dispatching of
generation in the Romanian power system, especially of the HPP LOTRU CIUNGET and HPP
PORTILE 1 (to decrease their generation level in this scenario from the initially assumed 478 MW
and 796 MW respectively) and TPP PAROSENI (to increase its generation level in this scenario
from the initially assumed 120 MW), as well as certain reinforcements in the internal networks of
Romania, Albania and Serbia are necessary shall this generation/load pattern be made more secure.
None of the identified congestions is located at the border lines.

4.22
Table 4.3.5 - Lines overloadings for 2010–base case-wet hydrology scenario, single outages
Loadings
Outage Overloaded line(s) Country
MVA %
OHL 220 kV AKASHA2-ARRAZH2 OHL 220 kV AELBS12-AFIER 2 251.4 111.9 ALBANIA
OHL 400 kV MINTIA-SIBIU OHL 220 kV TG.JIU-PAROSEN 242.7 111.7
OHL 400 kV TANTAREN-SIBIU OHL 220 kV TG.JIU-PAROSEN 227.1 104.5 ROMANIA
OHL 400 kV SIBIU-IERNUT OHL 400 kV MINTIA-SIBIU 477.3 124.3
OHL 220 kV P.D.F.A-RESITA ckt.1 OHL 220 kV P.D.F.A-RESITA ckt.2 315.5 108.4
OHL 220 kV RESITA-TIMIS ckt.1 OHL 220 kV RESITA-TIMIS ckt.2 315.9 112.8
OHL 220 kV JBGD172-JBGD8 22 ckt.1 OHL 220 kV JBGD172-JBGD8 22 ckt.2 434.4 122.2 SERBIA

Table 4.3.6 - Transformers overloadings for 2010–base case-wet hydrology scenario, single outages
Loadings
Outage Overloaded branch(es) Country
MVA %
TR 400/220 kV SIBIU ckt.1 TR 400/220 kV SIBIU ckt.2 527.3 131.8
400/110 kV BRASOV 400/110 kV DIRSTE 332.7 133.1 ROMANIA
400/110 kV DIRSTE 400/110 kV BRASOV 329.7 131.9
400/110 kV NIS ckt.1 400/110 kV NIS ckt.2 313.1 104.4 SERBIA

SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE
400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.3.6 - Geographical positions of the critical elements for 2010-base case-wet hydrology scenario

4.23
4.4 Scenario 2015 – average hydrology – 2010 topology
This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as GTmax run for year 2015 - average hydrology and expected network topology for 2010.

4.4.1 Lines loadings


Figure 4.4.1 shows power exchanges between areas for 2015-average hydrology scenario. Power
flows along interconnection lines in the region together with balances of the systems are shown in
Figure 4.4.2. Area totals are shown in Table 4.4.1. Figure 4.4.3 shows histogram of tie lines
loadings. It is concluded that most of the tie lines are loaded less than 25% of their thermal limits.

SVK UKR
1
450
47

21
AUT
12
4

HUN
13
3
10
1

129

SLO ROM
56

ITA
31
6

CRO 311
72
1

0
13

BIH 372 SRB


236
39

1 253
38
0

MNG BUL
53
293
30

10

54
MKD
167

TUR
ALB 10
6
41
3

GRE

Figure 4.4.1 - Area exchanges in analyzed electric power systems for 2015-average hydrology scenario – 2010 topology

Table 4.4.1 - Area totals in analyzed electric power systems for 2015-average hydrology scenario – 2010 topology
AREA GENERATION LOAD LOSSES INTERCHANGE
ALB 1116.1 1531 81.2 -496
BUL 7332.7 6483 150.7 699
BIH 2316.6 2279 78.7 -41.1
CRO 2316.3 3657 63.4 -1404.1
MKD 1087 1407 20 -340
ROM 7712.8 7317.4 347.4 47.9
SRB 8687.6 7263 268.7 1156
CRG 735 671 25 39
TOTALS 31304.1 30608.4 1035.1 -339.3

4.24
GABICK1400.0 LEVIC 1400.0

CENTREL

251
109

200
136
450.0 MW
346 350
MAISA 7 UZUKRA01
807 292

UCTE OWIEN 1 MGYOR 4


0
25 .2
714.0 772.5

224.4 MW
UKR
405.3 63.0 62.9
86

90.0
199
20.5 105 MSAJI 408.1 35.5 35.7
403.2 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.2 OWIEN 2 MGOD 4 407.3 226.3
20.7 27.5
450.0 MW
10.8 10.7

50.6

56.0
41.4
56.0
41.4
161
MGYOR 2 MTLOK 2
44.6 44.2 7.5 29.1
234.2 230.5 224.4
7.5 23.0
ONEUSI2 UMUKACH
233.4 16.3 16.1 228.8 96.3 96.6 20.
MSAJO 4
14.4 28.4
410.0
65.9 50.3
412.0 106 2

HUN
-1249.9 MW

10. 0

10. 0
0

4
159

56.

56.
46.

20. 5
16
LPODLO2228.6 LMARIB1 402.1 96.2 96.4
MBEKO 4 NADAB

7
MHEVI 4 407.4 86.5 104 ROSIORI 399.3
LDIVAC1 401.1 397.3
215.0 MW

76.2
20.6
76.2
20.6
IRDPV111

SLO
163 163
7.0 28.1 55
400.9 400.8 33 .2 MPECS 4 407.4 MSAFA 4 399.2
.0
LDIVAC2 LKRSKO1 400.4 LCIRKO2 226.8 9 36.5 36.6 ARAD
12 3

47 .2

47 .2
17.6 75.4

20.5

20.5
160

160

9.5
1.1

.2

.2
IPDRV121 15 395.3

48

48
8.8 8.8 4.
74.5 77.9 3. 2
230.3 229.3 7

ROM
ISACCEA 404.5

3
55.3
9.0

48 5.2
.9 .9

48.

192
127
75 .2 75 .2
47.9 MW

95 .3

129
174
84 84

.2
ERNESTIN

9. .7
MELINA 401.8 ZERJAVIN 401.8 JSOMB31
390.0 JSUBO31 392.6

8
5
ZERJAVIN 226.0 310 312
JSMIT21

16 2

16 2
70.4 103
4.2

4.

4.
6.5

402.9

79.1
33.8
TUMBRI 400.2 DAKOVO 221.4

38 282
PEHLIN 229.2 MRACLIN 221.2MEDURIC 218.5

46.9
27.3

93.1
47.2

.3
398.2

35.5
26.4

4.9
7.0
JHDJE11 P.D.FIE
130 130
13.8 12.8 TANTAREN 411.8
401.0 401.0

CRO

21.3
60.4
21.3
60.4
281

47. 5

79. 6
22.

88.
-1404.1 MW 11.1

94 .3
1

3
35 .0

4.9

44
0.9
34

.3
.8 GRADACAC 224.3 UGLJEVIK 398.2

SCG
PRIJED2 219.0 TE TUZL 230.2

VISEGRA JVARDI22
90.0 90.3 228.5 1195.0 MW

194
230.0

6.4
21 .4

21 .4
10

10
53.5 54.4

BIH

.3

.3
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 413.9 DOBRUD4 416.8
388 391 -41.1 MW 228.3 226 229 235.7 CRG 1156.0 MW JNIS2 1 252 253 SOFIA_W4
399.4
5.9 32.9
400.9
25.1 41.0
39.0 MW 396.1
139 89.7
410.4
HE ZAKUC 158 162 MO-4 RP TREB JHPERU21
16.1 9.5 7.9 7.9 226.8
228.0 231.2 229.9
22.4 30.5

BUL
158 159
RP TREB JPODG211 JLESK21
92.8 129 JPODG121225.8
396.8 0.000
699.0 MW

49.8
99.0
JPRIZ22
222.3 JTKOSA2
229.5JTKOSB1415.1

19.7
11.1
389.7

.6 3
25 3.

11. 6

11. 6

270
34.7
5

23.

23.
JVRAN31

6
0.000

19.7
20.1

18 2.9
.2
49.6

5
124
AVDEJA1 AVDEJA2
383.4 224.3AFIERZ2223.9 C_MOGILA

11.4
34.3
11.4
34.3

72.6
269
49.6
124
.6
SK 1 224.6 SK 4
409.2 409.2 53 .6
43 412.4

-340.0 MW STIP 1 .5
53 .1

MKD
BITOLA 2 415.0
411.2
50

BLAGOEV413.0 MI_3_4_1 419.2


49.2

DUBROVO 411.6
160

24.7
51.2
5
15 .9

46. 2
AKASHA1 373.9

8
13.9
44.0

4. 7.
19
7.8 0
.0

69.

1
2 9
ALB
-496.0 MW .8
24 .8

46.
7.8

62.7

6. .0
43

4.2

88
1 4HAMITAX

0
19 4.3

5
AHS_FLWR416.7 LAGAD K 413.6 FILIPPOI 7 4.2 4.2 415.3
10.1 10.1 62.7 74.0
390.3 4BABAESK

13.9
18.2
22.8
K-KEXRU
417.8 71.9
KARDIA K 415.6 415.5
410 417 415.8 QES/H K 412.7
194 178
AZEMLA1
0.0 MW
0.0 MW TUR
GRE
KARACQOU
250 418.6
50.0

GIS REGIONAL MODEL - AVERAGE HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 TOPOLOGY 2010 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 4.4.2 - Power flows along interconnection lines in the region with balances of the systems for 2015-average hydrology scenario – 2010 topology
4.25
Histogram
45
40
35
30

Frequency
25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.4.3 - Histogram of interconnection lines loadings for 2015-average hydrology scenario – 2010 topology
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

Following Table 4.4.2 lists all network elements loaded over 80% of their thermal limits. As it can
be seen some lines 220 kV voltage level in Albania, Romania and Serbia are loaded over 80%.
Also, most of the elements loaded over 80% are transformers in some substations, again, in
Albania, Bosnia & Herzegovina, Romania and Serbia. Figure 4.4.4 shows histogram of branch
loadings in the system. As for the conclusion regarding thermal loadings in this scenario it can be
said that most of the network elements are loaded between 25-75% of their thermal limits, but there
are some elements highly loaded. Most of the elements loaded over 80% are transformers in some
substations, so some internal network reinforcements are necessary to sustain this load-demand
level and production pattern. There are some elements that are overloaded (220 kV lines Targu Jiu –
Paroseni and Urechesti-Targu Jiu in Romania, and 220/110 kV transformers in Fier substation in
Albania. This leads to conclusion that transmission network is not able to sustain this load-demand
level and this production pattern and certain network reinforcement are necessary. It should be
pointed out that higher engagement of TPP Paroseni resolves this overloads of the 220 kV lines
Targu Jiu – Paroseni and Urechesti-Targu Jiu and decreases the load of the 400/220 transformer in
Urechesti substation. Also, it is expected that transformers in Fier substation will be replaced with
more powerful transformer units.

4.26
Table 4.4.2 - Network elements loaded over 80% of their thermal limits for 2015-average hydrology scenario – 2010
topology
BRANCH LOADINGS ABOVE 80.0 % OF RATING:
LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB HL 220kV AKASHA2-ARRAZH2 1 250.1 270 92.6
HL 220kV P.D.F.A-CETATE1 1 205.2 208.1 98.6
HL 220kV P.D.F.A-RESITA 1 236.2 277.4 85.2
HL 220kV P.D.F.A-RESITA 2 236.2 277.4 85.2
ROM
HL 220kV P.D.F.II-CETATE1 1 267.7 277.4 96.5
HL 220kV TG.JIU-PAROSEN 1 278.2 208.1 133.7
HL 220kV URECHESI-TG.JIU 1 278.2 277.4 100.3
SRB HL 220kV JBGD3 21-JOBREN2 1 261 301 86.7
Transformers
TR 220/110 kV AELBS1 1 78 90 86.6
TR 220/110 kV AELBS1 2 78 90 86.6
TR 220/110 kV AELBS1 3 83.8 90 93.1
TR 220/110 kV AFIER 1 138.2 120 115.2
TR 220/110 kV AFIER 2 113.3 90 125.9
ALB
TR 220/110 kV AFIER 3 108.1 90 120.2
TR 220/110 kV AFIERZ 1 51.9 60 86.5
TR 220/110 kV AFIERZ 2 51.9 60 86.5
TR 220/110 kV AKASHA 1 84.1 100 84.1
TR 220/110 kV AKASHA 2 84.1 100 84.1
BIH TR 400/110 kV UGLJEV 1 254.8 300 84.9
TR 220/110 kV FUNDE2 1 193.3 200 96.7
TR 220/110 kV FUNDEN 1 162.9 200 81.4
ROM
TR 400/220 kV IERNUT 1 320.4 400 80.1
TR 400/220 kV URECHE 1 395.4 400 98.9
TR 220/110 kV JBGD3 1 166.7 200 83.4
TR 220/110 kV JBGD3 2 125.6 150 83.7
TR 220/110 kV JTKOSA 2 130.7 150 87.1
SRB TR 220/110 kV JTKOSA 3 133 150 88.7
TR 220/110 kV JZREN2 2 123.6 150 82.4
TR 400/220 kV JTKOSB 2 325.8 400 81.4
TR 400/220 kV JTKOSB 3 325.8 400 81.4

Histogram
350

300

250
Frequency

200

150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.4.4 - Histogram of branch loadings for 2015-average hydrology scenario – 2010 network topology
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

4.4.2 Voltage Profile in the Region

Figure 4.4.5 shows histogram of voltages in monitored substations. Voltages in almost all
monitored substations are found within permitted limits. Only in substation Elbasan and Kashar,
where voltages are around 373 kV, but this can be resolved with changing of the setting of the tap
changing transformers in these substations.

4.27
Histogram

100
90
80
70

Frequency
60
50
40
30
20
10
0
x<0.9

0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

x>1.1
Bin

Figure 4.4.5 - Histogram of voltages in monitored substations for 2015-average hydrology scenario – 2010 network
topology ("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

In the rest of the monitored network the voltage profile is satisfying and that most of the substations
have magnitudes in range 0.975-1.05 p.u.

4.4.3 Security (n-1) analysis


Results of security (n-1) analysis for 2015-dry hydrology scenario and expected topology for 2010
are presented in Table 4.4.3. Figure 4.4.6 shows the geographical position of the critical elements in
monitored systems.

It can be concluded that all identified insecure situations are located in internal networks that belong
to monitored power systems of Albania, Croatia, Romania and Serbia. In most critical case in
Romanian system, the critical elements are 220 kV lines Targu Jiu – Paroseni and Urechesti-Targu
Jiu and 400/220 kV transformer in Urechesti substation, but these elements are overloaded by full
topology too, which is the main reason why they appear as critical by most outages analyzed. As it
has been stated before, this can be resolved by higher engagement of the TPP Paroseni.

Some of the overloadings identified can be relieved by changing internal network topology
(splitting busbars, changing lower voltage network topology in order to redistribute load-demand or
change of generation units engagement), like in the case of most severe overloading in Romanian
network happens on transformer 400/110 kV Dirste when transformer 400/110 kV in Brasov is
outaged, but this is a consequence of the fact that second transformer unit 400/110 kV in Brasov is
out of operation. Switching on of this transformer clears this critical outage. The similar situation is
with outage of the 400 kV line Obrenovac-Beograd 8 in Serbia. Splitting of the busbars in 220 kV
Beograd 3 in substation relieves this overloading, but voltage profile in Serbian network remains
critical, so additional dispatching actions are necessary too.
Losing the 400 kV line Kosovo B-Pec or one transformer unit in substation Kosovo B causes
overloading of the transformer units in this substation. This is consequence of the low level of

4.28
production in 220 kV network in Kosovo region, due to decommissioning of the generation units in
TPP Kosovo A.

All in all, certain reinforcement of internal network is necessary in order to make this regime more
secure (more about this in chapter 6). None of the identified congestions is located at border lines.

Table 4.4.3 - Network overloadings for 2015-average hydrology scenario, single outages – 2010 network topology
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
BASE CASE RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 282.6MVA 133.7%
RO OHL 220kV P.D.F.A -CALAFAT 1 RO HL 220kV P.D.F.A-CETATE1 1 208.1MVA 259.4MVA 126.5%
RO TR 400/220kV/kV URECHESI 1 400MVA 417.6MVA 104.4%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 299MVA 106.6%
RO OHL 220kV P.D.F.A -RESITA 1
RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 337.8MVA 128.0%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 299MVA 142.1%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 292.7MVA 104.1%
RO OHL 220kV RESITA -TIMIS 1 RO HL 220kV RESITA-TIMIS 2 277.4MVA 348.7MVA 129.1%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 292.7MVA 138.8%
RO TR 400/220kV/kV URECHESI 1 400MVA 416.1MVA 104.0%
RO OHL 220kV PESTIS -MINTIA A 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 293.8MVA 105.4%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 287.2MVA 140.6%
RO TR 400/220kV/kV URECHESI 1 400MVA 412.9MVA 103.2%
RO OHL 220kV CLUJ FL -MARISEL 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 293.3MVA 104.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 293.3MVA 139.6%
RO TR 400/220kV/kV URECHESI 1 400MVA 424.3MVA 106.1%
RO OHL 220kV AL.JL -GILCEAG 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 306MVA 109.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 299.7MVA 146.3%
RO OHL 400kV TANTAREN-SLATINA 1 RO TR 400/220kV/kV URECHESI 1 400MVA 442.8MVA 110.7%
RO TR 400/220kV/kV URECHESI 1 400MVA 420.4MVA 105.1%
RO OHL 400kV TANTAREN-BRADU 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.5MVA 106.2%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 296.5MVA 141.6%
RO TR 400/220kV/kV URECHESI 1 400MVA 443.9MVA 111.0%
RO OHL 400kV TANTAREN-SIBIU 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 327.5MVA 117.9%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 327.5MVA 157.2%
RO TR 400/220kV/kV URECHESI 1 400MVA 444MVA 111.0%
RO OHL 400kV URECHESI-DOMNESTI 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 299MVA 106.8%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 299MVA 142.3%
RO TR 400/220kV/kV URECHESI 1 400MVA 443.2MVA 110.8%
RO OHL 400kV MINTIA -SIBIU 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 330.1MVA 118.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 322.6MVA 158.2%
RO OHL 400kV P.D.FIE -SLATINA 1 RO TR 400/220kV/kV URECHESI 1 400MVA 428.1MVA 107.0%
RO TR 400/220kV/kV URECHESI 1 400MVA 413.5MVA 103.4%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 295MVA 105.0%
RO OHL 400kV DOMNESTI-BRAZI 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 295MVA 140.0%
RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 331.2MVA 102.7%
RO OHL 400kV SUCEAVA -GADALIN 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 282MVA 136.7%
RO TR 400/220kV/kV URECHESI 1 400MVA 413.5MVA 103.4%
RO OHL 400kV SMIRDAN -GUTINAS 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 298.1MVA 106.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 298.1MVA 142.2%
RO OHL 400kV GADALIN -ROSIORI 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 280.1MVA 135.6%
CS OHL 220kV JBGD172 -JBGD8 22 1 CS HL 220kV JBGD172-JBGD8 22 2 365.8MVA 462.8MVA 133.3%
CS OHL 400kV JBGD8 1 -JOBREN11 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 429.3MVA 155.8%
RO TR 400/220kV/kV URECHESI 1 400MVA 436.7MVA 109.2%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 316.6MVA 113.9%
CS OHL 400kV JHDJE11 -JTDRMN1 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 316.6MVA 151.8%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 319.6MVA 109.6%
RO TR 400/220kV/kV URECHESI 1 400MVA 422.5MVA 105.6%
CS OHL 400kV JNSAD31 -JSUBO31 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 303.6MVA 108.6%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 303.6MVA 144.7%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 294.1MVA 104.9%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 294.1MVA 139.8%
CS OHL 400kV JTKOSB1 -JPEC 1 A CS TR 400/220kV/kV JTKOSB1 1 400MVA 419.7MVA 104.9%
CS TR 400/220kV/kV JTKOSB1 2 400MVA 438.6MVA 109.6%
CS TR 400/220kV/kV JTKOSB1 3 400MVA 438.6MVA 109.6%
RO TR 400/110 BRASOV 1 RO TR 400/110kV/kV DIRSTE 1 250MVA 385.8MVA 154.3%
RO TR 400/110 CLUJ E 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 282.5MVA 137.1%
RO TR 400/110 DIRSTE 1 RO TR 400/110kV/kV BRASOV 1 250MVA 380MVA 152.0%
CS TR 400/110 JNIS2 1 CS TR 400/110kV/kV JNIS2 1 2 300MVA 332.5MVA 110.8%
RO TR 400/220 BUC.S 1 RO TR 400/220kV/kV BUC.S 2 400MVA 483MVA 120.8%
RO HL 400kV GADALIN-CLUJ E 1 238.3MVA 238.1MVA 102.9%
RO TR 400/220 IERNUT 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 282.5MVA 137.4%
RO HL 220kV STEJARU-GHEORGH 1 208.1MVA 211.8MVA 121.7%
CS TR 400/220kV/kV JTKOSB1 2 400MVA 457.2MVA 114.3%
CS TR 400/220 JTKOSB 1
CS TR 400/220kV/kV JTKOSB1 3 400MVA 457.2MVA 114.3%
RO TR 400/220 SLATINA 1 RO TR 400/220kV/kV URECHESI 1 400MVA 424.9MVA 106.2%

4.29
SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE 400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.4.6 – Geographical position of critical elements for 2015-average hydrology scenario

4.30
4.5 Scenario 2015 – average hydrology – topology 2015
This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as GTmax run for year 2015 - average hydrology and expected network topology for 2015.

4.5.1 Lines loadings


Figure 4.5.1 shows power exchanges between areas for 2015-average hydrology scenario. Power
flows along interconnection lines in the region together with balances of the systems are shown in
Figure 4.5.2. Area totals are shown in Table 4.5.1. Figure 4.5.3 shows histogram of tie lines
loadings. It is concluded that most of the tie lines are loaded less than 25% of their thermal limits.
SVK UKR
1
450 46

11
AUT
13
5

HUN
10
6
89

126

SLO ROM
28

ITA
30
4

CRO 301
77
1

3
12

BIH 336 SRB


193
47

1 247
16
6

MNG BUL
2
38
220
27
6

98
MKD
169

TUR
ALB
298

8
7
27
11
2

GRE

Figure 4.5.1 - Area exchanges in analyzed electric power systems for 2015-average hydrology scenario

Table 4.5.1 - Area totals in analyzed electric power systems for 2015-average hydrology scenario
AREA GENERATION LOAD LOSSES INTERCHANGE
ALB 1118.1 1541 73.1 -496
BUL 7332.9 6483 150.9 699
BIH 2317.2 2279 79.2 -41
CRO 2317 3657 64 -1404
MKD 1088.4 1407 21.4 -340
ROM 7708.6 7317.4 343.1 48.1
SRB 8689.4 7279 254.4 1156
CRG 735.2 676 20.3 39
TOTALS 31306.8 30639.4 1006.4 -338.9

As it can be seen, new elements that are expected to be build till 2015 cause totally different
distribution of power flows in the southern part of the region (Albania, FYR of Macedonia, Serbia,
and Montenegro).

4.31
GABICK1400.0 LEVIC 1400.0

CENTREL

251
109

200
137
450.0 MW
346 350
MAISA 7 UZUKRA01
806 293

UCTE OWIEN 1 MGYOR 4 714.1 772.5


0
25 .0
224.0 MW
UKR
405.3 71.3 71.2
87

90.7
199
21.1 104 MSAJI 408.1 35.5 35.7
403.2 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.3 OWIEN 2 MGOD 4 407.3 226.3
20.7 27.5
450.0 MW
10.8 10.7

50.3

52.9
41.6
52.9
41.6
160
MGYOR 2 MTLOK 2
46.2 45.7 7.5 29.2
234.2 230.5 224.4
7.1 22.6
ONEUSI2 UMUKACH
233.4 17.6 17.5 228.8 87.2 87.4 11.
MSAJO 4
14.1 28.1
410.0
66.9 49.9
412.0 98. 1
7

HUN
-1249.9 MW

10. 9

10. 9
9

5
158

52.

52.
45.

11. 8
15
LPODLO2228.7 LMARIB1 402.2 82.0 82.2
MBEKO 4 NADAB

5
MHEVI 4 407.5 81.1 98.9 ROSIORI 400.0
LDIVAC1 401.6 397.9
215.0 MW

68.9
20.8
68.9
20.8
IRDPV111

SLO
166 166
4.0 25.0 63
400.9 400.9 35 .8 MPECS 4 407.6 MSAFA 4 399.7
.4
LDIVAC2 LKRSKO1 400.5 LCIRKO2 226.8 6 23.7 23.8 ARAD
12 0

44 .6

44 .6
12.9 71.1

21.9

21.9
160

160

9.1
1.4

.6

.6
IPDRV121 15 396.1

54

54
9.7 9.8 6.
73.6 77.0 4. 5
230.3 229.3 2

ROM
ISACCEA 404.9

7
63.9
11.4

54 2.7
.7 .7

54.

184
128
68 .6 68 .6
48.0 MW

92 .7

127
172
84 84

.7
ERNESTIN

9. .4
MELINA 402.1 ZERJAVIN 402.1 JSOMB31
390.6 JSUBO31 393.2

8
1
ZERJAVIN 226.2 299 301
JSMIT21

16 8

16 8
63.9 98.1
6.5

2.

2.
6.0

403.3

89.7
29.3
TUMBRI 400.3 DAKOVO 221.7

38 255
PEHLIN 229.3 MRACLIN 221.4MEDURIC 218.7

49.4
27.1

96.2
46.9

.9
399.0

40.5
26.3

7.6
7.1
JHDJE11 P.D.FIE
123 123
10.9 11.9 TANTAREN 412.3
402.1 402.0

CRO

61.9

61.9
4.1

4.1
254

49. 3

89. 1
22.

84.
-1404.0 MW 9.1

97 .3
6

9
40 .7

7.6

44
0.8
33

.5
GRADACAC 224.6 UGLJEVIK 399.1
.8

SCG
PRIJED2 219.3 TE TUZL 230.5

VISEGRA JVARDI22
81.0 81.3 229.6 1195.0 MW

185
230.9

7.2
11
4. 7
11
4. 7
48.8 50.1

BIH

.
1
.
1
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 414.4 DOBRUD4 417.1
406 409 -41.0 MW 229.5 222 225 237.3 CRG 1156.0 MW JNIS2 1 246 248 SOFIA_W4
401.0
3.5 21.2
403.6
29.1 43.7
39.0 MW 402.0
97.1 43.0
411.5

94.3 94.4
51.1 71.9
HE ZAKUC 162 166 MO-4 RP TREB JHPERU21
15.4 7.9 22.0 22.1 230.3
228.8 232.3 232.4
17.3 25.6

BUL
225 226
RP TREB JPODG211 JLESK21
35.2 71.4 JPODG121229.9
403.9 403.8
699.0 MW

14.0 13.9
30.1 68.4
223
6.4
JPRIZ22
226.6 JTKOSA2
232.4JTKOSB1419.0

52.7
18.2
401.5

.0 2
21 6.

20. 4

20. 4

294
69.2
1

29.

29.
JVRAN31

9
406.8
398 8

53.0
26.1

56.1
114
397

11 6.3
97.

.4
16.1
110

1
223
AVDEJA1 AVDEJA2
402.6 228.4AFIERZ2229.2 C_MOGILA

10 14
.8
20.7
39.9
20.7
39.9

1
293
105
75.0
91.9
75.0
91.8
.4
SK 1 226.3 SK 4
410.5 409.9 98 .3
43 413.3

-340.0 MW STIP 1 .1
98 .8

MKD
BITOLA 2 414.5
411.7
48

BLAGOEV413.9 MI_3_4_1 419.4


74.7

74.7

DUBROVO 412.0
133

133

25.9
50.2
278 4
8 14 .8

47. 5
AKASHA1 395.2 42.

1
56.5
42.4

3. 7.
19
242 0
.1

82.

1
3 1
ALB
-496.0 MW .0
26 .1

63.
242

63.4

4 . .0
45

3.3

89
4 4HAMITAX

8
19 3.7

8
AHS_FLWR417.3 LAGAD K 414.3 3.3 3.3 415.4
79 7
.7

FILIPPOI 7
27

8.1 8.0 63.4 74.8


408.7 4BABAESK

56.6
19.3
23.1
K-KEXRU
417.9 72.1
KARDIA K 415.7 415.6
112 113 417.8 QES/H K 413.5
106 36.8
AZEMLA1
0.0 MW
-0.1 MW TUR
GRE
KARACQOU
250 419.6
50.0

GIS REGIONAL MODEL - AVERAGE HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 TOPOLOGY 2015 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 4.5.2 - Power flows along interconnection lines in the region with balances of the systems for 2015-average hydrology scenario
4.32
Histogram
45
40
35
30

Frequency
25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.5.3 - Histogram of interconnection lines loadings for 2015-average hydrology scenario ("Frequency" denotes
number of lines and "Bin" denotes loading range in % of thermal limit)

Following PSS/E output (Table 4.5.2) lists all network elements loaded over 80% of their thermal
limits. Figure 4.5.4 shows histogram of branch loadings in the system.

Table 4.5.2 - Network elements loaded over 80% of their thermal limits for 2015-average hydrology scenario
BRANCH LOADINGS ABOVE 80.0 % OF RATING:
LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB HL 220kV AKASHA2-ARRAZH2 1 237.7 270 88
HL 220kV P.D.F.A-CETATE1 1 205 208.1 98.5
HL 220kV P.D.F.A-RESITA 1 232.2 277.4 83.7
HL 220kV P.D.F.A-RESITA 2 232.2 277.4 83.7
ROM
HL 220kV P.D.F.II-CETATE1 1 267.5 277.4 96.4
HL 220kV TG.JIU-PAROSEN 1 272.6 208.1 131
HL 220kV URECHESI-TG.JIU 1 272.6 277.4 98.3
SRB HL 220kV JBGD3 21-JOBREN2 1 261.8 301 87
Transformers
TR 220/110 kV AELBS1 1 74.3 90 82.5
TR 220/110 kV AELBS1 2 74.3 90 82.5
TR 220/110 kV AELBS1 3 79.8 90 88.7
TR 220/110 kV AFIER 1 134.9 120 112.5
TR 220/110 kV AFIER 2 110.6 90 122.9
ALB
TR 220/110 kV AFIER 3 105.6 90 117.3
TR 220/110 kV AFIERZ 1 50.3 60 83.8
TR 220/110 kV AFIERZ 2 50.3 60 83.8
TR 220/110 kV AKASHA 1 82.1 100 82.1
TR 220/110 kV AKASHA 2 82.1 100 82.1
TR 220/110 kV FUNDE2 1 193 200 96.5
ROM TR 220/110 kV FUNDEN 1 162.6 200 81.3
TR 400/220 kV URECHE 1 390.9 400 97.7
TR 220/110 kV JBGD3 1 166.6 200 83.3
SRB TR 220/110 kV JBGD3 2 125.8 150 83.9
TR 220/110 kV JZREN2 2 123.5 150 82.3
BIH TR 400/110 kV UGLJEV 1 252.5 300 84.2

4.33
Histogram
350

300

250

Frequency
200

150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.5.4 - Histogram of branch loadings for 2015-average hydrology scenario ("Frequency" denotes number of lines
and "Bin" denotes loading range in % of thermal limit)

As it can be seen from these outputs, most of the network elements are loaded between 25-75% of
their thermal limits and most of the elements loaded over 80% are transformers in some substations,
so some internal network reinforcements are necessary to sustain this load-demand level and
production pattern. Also, planned network reinforcements compared to network topology 2010,
reduce load of some elements in southern part of Serbia.

4.5.2 Voltage Profile in the Region

Figure 4.5.5 shows histogram of voltages in monitored substations. Voltages in all monitored
substations are found within permitted limits. It is concluded that voltage profile is satisfying and
that most of the substations have magnitudes in range 1-1.05 p.u.

Histogram
120

100

80
Frequency

60

40

20

0
x<0.9

0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

x>1.1

Bin

Figure 4.5.5 - Histogram of voltages in monitored substations for 2015-average hydrology scenario ("Frequency"
denotes number of busses and "Bin" denotes voltage range in p.u.)

4.34
4.5.3 Security (n-1) analysis

Results of security (n-1) analysis for 2015-average hydrology scenario are presented in Table 4.5.3
and Figure 4.5.6.

Like for expected topology 2010 (previous chapter), it can be concluded that all identified insecure
situations are located in internal networks that belong to monitored power systems of Albania,
Croatia, Romania and Serbia. Also, the planned network reinforcements till 2015 resolve some of
the noticed critical contingencies, especially in southern part of Serbia. The rest of the conclusions
are the same as for the analyzed topology 2010, and that is that certain level of network
reinforcement is necessary to make this regime more secure.

SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE 400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.5.6 – Geographical position of critical elements for 2015-average hydrology scenario

4.35
Table 4.5.3 - Network overloadings for 2015-average hydrology scenario, single outages
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
BASE CASE RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 277.6MVA 131.0%
AL OHL 220kV AELBS12 -AFIER 2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 364.3MVA 142.6%
BA OHL 400kV VISEGRA -HE VG 1 BA HL 220kV RP KAKAN-KAKANJ5 1 316MVA 338.8MVA 103.8%
RO OHL 220kV P.D.F.A -CALAFAT 1 RO HL 220kV P.D.F.A-CETATE1 1 208.1MVA 259.1MVA 125.9%
RO TR 400/220kV/kV URECHESI 1 400MVA 413.4MVA 103.3%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 293.7MVA 104.4%
RO OHL 220kV P.D.F.A -RESITA 1
RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 333.5MVA 125.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 293.7MVA 139.2%
RO OHL 220kV RESITA -TIMIS 1 RO HL 220kV RESITA-TIMIS 2 277.4MVA 343.7MVA 126.7%
RO OHL 220kV CRAIOV B-ISALNI A 1 RO TR 400/220kV/kV URECHESI 1 400MVA 412.5MVA 103.1%
RO TR 400/220kV/kV URECHESI 1 400MVA 412.7MVA 103.2%
RO OHL 220kV PESTIS -MINTIA A 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 289.3MVA 103.5%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 283MVA 138.1%
RO OHL 220kV CLUJ FL -AL.JL 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 264.9MVA 124.7%
RO TR 400/220kV/kV URECHESI 1 400MVA 420.3MVA 105.1%
RO OHL 220kV AL.JL -GILCEAG 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 301MVA 107.6%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 294.9MVA 143.5%
RO OHL 400kV TANTAREN-SLATINA 1 RO TR 400/220kV/kV URECHESI 1 400MVA 437.9MVA 109.5%
RO TR 400/220kV/kV URECHESI 1 400MVA 416.1MVA 104.0%
RO OHL 400kV TANTAREN-BRADU 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 291.3MVA 104.0%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 291.3MVA 138.6%
RO TR 400/220kV/kV URECHESI 1 400MVA 438.7MVA 109.7%
RO OHL 400kV TANTAREN-SIBIU 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 321.3MVA 115.3%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 321.3MVA 153.7%
RO TR 400/220kV/kV URECHESI 1 400MVA 439.9MVA 110.0%
RO OHL 400kV URECHESI-DOMNESTI 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 294MVA 104.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 294MVA 139.5%
RO TR 400/220kV/kV URECHESI 1 400MVA 437.6MVA 109.4%
RO OHL 400kV MINTIA -SIBIU 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 323.1MVA 115.8%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 316MVA 154.4%
RO OHL 400kV P.D.FIE -SLATINA 1 RO TR 400/220kV/kV URECHESI 1 400MVA 424.6MVA 106.2%
RO OHL 400kV SUCEAVA -GADALIN 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 276.9MVA 133.8%
RO TR 400/220kV/kV URECHESI 1 400MVA 409.4MVA 102.4%
RO OHL 400kV SMIRDAN -GUTINAS 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 292.8MVA 104.5%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 292.8MVA 139.3%
RO OHL 400kV SIBIU -IERNUT 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 277.6MVA 134.5%
RO OHL 400kV GADALIN -CLUJ E 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 277.8MVA 134.5%
CS OHL 220kV JBGD172 -JBGD8 22 1 CS HL 220kV JBGD172-JBGD8 22 2 365.8MVA 463.6MVA 133.1%
CS OHL 400kV JBGD8 1 -JOBREN11 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 432.1MVA 156.1%
RO TR 400/220kV/kV URECHESI 1 400MVA 414.3MVA 103.6%
CS OHL 400kV JBOR 21 -JHDJE11 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 291.3MVA 103.8%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 291.3MVA 138.4%
RO TR 400/220kV/kV URECHESI 1 400MVA 430.1MVA 107.5%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 309.2MVA 110.8%
CS OHL 400kV JHDJE11 -JTDRMN1 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 309.2MVA 147.7%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 319.4MVA 109.2%
RO TR 400/220kV/kV URECHESI 1 400MVA 418.4MVA 104.6%
CS OHL 400kV JNSAD31 -JSUBO31 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 298.5MVA 106.4%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 298.5MVA 141.9%
RO TR 400/110 BRASOV 1 RO TR 400/110kV/kV DIRSTE 1 250MVA 385.1MVA 154.1%
RO TR 400/110 CLUJ E 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 277.8MVA 134.4%
RO TR 400/110 DIRSTE 1 RO TR 400/110kV/kV BRASOV 1 250MVA 379.5MVA 151.8%
RO TR 400/220 BUC.S 1 RO TR 400/220kV/kV BUC.S 2 400MVA 482.6MVA 120.6%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 277.8MVA 134.6%
RO TR 400/220 IERNUT 1
RO HL 220kV STEJARU-GHEORGH 1 208.1MVA 210.4MVA 120.3%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 314.5MVA 108.5%
CS TR 400/220 JBGD8 1
CS HL 220kV JBGD3 22-JBGD8 22 2 365.8MVA 372MVA 107.5%
RO TR 400/220 SLATINA 1 RO TR 400/220kV/kV URECHESI 1 400MVA 421MVA 105.2%

4.5.4 Summary of Impacts - 2015 topology versus 2010 topology

Compared to the expected topology 2010, analyzed in previous chapter, it can be seen that the
network losses are smaller as a consequence of building of new elements for 2015 network
topology, especially in the cases of Albania, Serbia and Montenegro. Overall reduction of loses is
around 30 MW.

Also, planned network reinforcements compared to network topology 2010, reduce load of some
elements in southern part of Serbia.

4.36
Compared to the 2010 topology, voltage profile is somewhat better, especially in southern and
central part of Serbia, as well as in Albania.

Realization of the planed investments till 2015 has impact on secure operation of the network.
Some of the insecure states identified with 2010 topology are relieved and do not exist with
expected 2015 network topology. Also, level of overloadings due to outages is decreased.

All in all overall network performance is better, especially in the region where new planed
investments are to be realized (Albania, southern Serbia and Montenegro).

4.37
4.6 Scenario 2015 – dry hydrology – 2010 topology
This part of the Study presents the results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as GTmax run for year 2015 - dry hydrology and expected network topology for 2010.

4.6.1 Lines loadings

Figure 4.6.1 shows power exchanges between areas for 2015-dry hydrology scenario. Power flows
along interconnection lines in the region together with balances of the systems are shown in Figure
4.6.2. Area totals are shown in Table 4.6.1. Figure 4.6.3 shows histogram of tie lines loadings. It is
concluded that most of the tie lines are loaded less than 25% of their thermal limits.

SVK UKR
3
450

41

37
AUT
18
1

HUN
10
3
43

SLO
31

ROM
73

ITA
25
8

CRO 207
69
4

70

BIH 91 SRB
366
15

0 229
23
6

MNG BUL
82
383
27
8

20

48
MKD
143

TUR
ALB 20
13
36
0

GRE

Figure 4.6.1 - Area exchanges in analyzed electric power systems for 2015-dry hydrology scenario – topology 2010

Table 4.6.1 - Area totals in analyzed electric power systems for 2015-dry hydrology scenario – topology 2010
AREA GENERATION LOAD LOSSES INTERCHANGE
ALBANIA 894.7 1521.9 92.7 -720
BULGARIA 7363.9 6450 147.9 766
BIH 3140.9 2304 78.2 758.8
CROATIA 2636.7 3665 58.2 -1086.4
MACEDONIA 985.1 1410 19.1 -444
ROMANIA 7724.6 7798.4 295.5 -369.2
SERBIA 8397.9 7296 237.9 864
MONTENEGRO 586.3 672 22.1 -107.7
TOTALS 31730.1 31117.3 951.6 -338.5

4.38
GABICK1400.0 LEVIC 1400.0

CENTREL

251
113

200
140
450.0 MW
346 350
MAISA 7 UZUKRA01
804 297

UCTE OWIEN 1 MGYOR 4


0
714.8 772.5

223.5 MW 2 5 .4

UKR
106 105
405.4 90

94.6
199
24.2 101 MSAJI 4408.1 35.5 35.6
403.3 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.5 OWIEN 2 MGOD 4 407.6 226.3
20.9 27.7
450.0 MW

49.2

39.5
41.8

39.5
41.8
10.8 10.6

156
MGYOR 2 MTLOK 2
7.6 29.2
234.2 52.7 52.2 230.5 224.4
5.8 20.7
ONEUSI2 UMUKACH
233.5 23.0 22.9 228.9 39.0 39.1 37.
MSAJO 4
12.7 26.6 71.8 47.0 70. 1
410.0 412.0 5

HUN
-1250.0 MW

10. 5

5
7

5
154

39.

39.
45.

10.

36.
131
LPODLO2228.9 LMARIB1 402.4 64.7 64.8
MBEKO 4 NADAB

8
MHEVI 4 408.3 52.7 71.6 ROSIORI 402.1
LDIVAC1 404.6 402.2
215.0 MW

35.4
21.9

35.4
21.9
IRDPV111

SLO
180 180
3.3 24.1 97
400.9 400.9 30 . 7 MPECS 4 408.2 MSAFA 4 402.4
.7
LKRSKO1 401.0 LCIRKO2 227.1 38.0 38.0 ARAD
LDIVAC2 .5
30 41

37 .7

37 .7
16.6 43.0

26.9

26.9
156

156

6.5
4.2

.8

.8
1 401.5

71

71
IPDRV121
11.4 11.4
10
73.6 77.1 2. .7
230.3 229.3 6

ROM
ISACCEA 405.4

8 8
97.8
7.2

71 5.8

212
121
.3 .3

71.
35 .2 35 .2
-369.2 MW

30.7
85 .8
85 85

165
.8
ERNESTIN

6. .7
MELINA 402.1 ZERJAVIN 403.4 JSOMB31
393.4 JSUBO31 396.0

5
5
ZERJAVIN 226.9 207 208
JSMIT21

15 0

15 0
40.3 85.1
10.7

2.

2.
7.6

404.5

29.5
153
TUMBRI 401.0 DAKOVO 222.5

24 4.0
59.9
27.1

47.0
PEHLIN 229.2 MRACLIN 222.3 MEDURIC 219.6

110

.0
400.9

5
34.7
26.6

4.9
6.8
JHDJE11 P.D.FIE
69.5 69.5
72.5 71.5
405.9 406.0 TANTAREN 413.7

CRO

76.1
35.8

76.1
35.8
53.9

60.
-1086.4 MW

22.

81.
153
16.2

2
34 .3

4
4 .9

11 0
46
1.1
34

GRADACAC 225.5 UGLJEVIK 400.9


.9

2
.
SCG
PRIJED2 220.1 TE TUZL 231.7

VISEGRA JVARDI22
37.2 37.3 756.2 MW

21 4
231.4 229.6

9.8
76 .0

76 .0
51.9 54.0

14

14
BIH

.1

.1
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 414.7 DOBRUD4 417.1
317 319 758.8 MW 230.5 138 139 236.0 CRG 864.0 MW JNIS2 1 228 230 SOFIA_W4
402.2
16.4 24.0
404.6
29.5 26.3
-107.7 MW 396.5
145 92.4
411.0
HE ZAKUC 127 130 MO-4 RP TREB JHPERU21
18.2 19.2
231.4 232.4 228.9 103 102 221.1
43.5 45.0

BUL
148 147
RP TREB JPODG211 JLESK21
147 181
396.9 JPODG121219.0 0.000
766.0 MW

205
165

73.7
47.1
384.0 JPRIZ22214.1 JTKOSA2 227.0
JTKOSB1
412.4

.1 8
25 2.

18. 0

18. 0

347
8

20.0
17.

17.
7

7
JVRAN31
0.000

72. 8
50.8

.5 9
28 1.
8
204
180
AVDEJA1 373.2AVDEJA2
210.7 AFIERZ2208.0 C_MOGILA

18.6
27.5

18.6
27.5

48.8
204
180

345
.0
48 .0
SK 1 222.9 407.5SK 4 407.7 34 412.8

-444.0 MW STIP 1 .9
47 .8

MKD
BITOLA 2 414.2
410.5
59

BLAGOEV413.3 MI_3_4_1 419.3

35.3
45.4
DUBROVO 410.7
202
204

11

179
13 .3

5
48.0
AKASHA1 358.9

5.0

8. 6.
18. 1

45.
.8

72.

1
5 9
1
ALB
-720.0 MW .4

18. 7
35 .4

49.

11 9.
63.7
49

8
.3 1
8.5
8 4HAMITAX

1
AHS_FLWR416.1 LAGAD K 413.3 17 7.2 8.5 8.5 415.4
FILIPPOI 7
63.7 75.0
19.8 19.8
381.4 4BABAESK
21.7 70.7

14.0
K-KEXRU
417.8

5.0
KARDIA K 415.5 415.5
357 364 414.9 QES/H K 412.2
271 257
AZEMLA1
0.0 MW
0.2 MW TUR
GRE
KARACQOU
250 418.1
50.0

GIS REGIONAL MODEL - DRY HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 TOPOLOGY 2010 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 4.6.2 - Power flows along interconnection lines in the region with balances of the systems for 2015-dry hydrology scenario – 2010 topology
4.39
Histogram
40
35
30

Frequency
25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.6.3 - Histogram of interconnection lines loadings for 2015-dry hydrology scenario – topology 2010
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

Following Table 4.6.2 lists all network elements loaded over 80% of their thermal limits. As it can
be seen some lines 220 kV voltage level in Albania, Romania and Serbia are loaded over 80%.
Also, the most of the elements loaded over 80% are transformers in some substations, again, in
Albania, Bosnia & Herzegovina, Romania and Serbia. Figure 4.6.4 shows histogram of branch
loadings in the system.
As for the conclusion regarding thermal loadings in this scenario it can be said that the most of the
network elements are loaded less then 75% of their thermal limits, but there are some elements
highly loaded. Most of the elements loaded over 80% are transformers in some substations, so some
internal network reinforcements are necessary to sustain this load-demand level and production
pattern. There are some elements that are overloaded (220 kV line Kashar – Rashbul and
transformers 220/110 kV in substation Fierza and one transformer 220/110 kV in substation
Elbasan 1in Albania). This leads to conclusion that transmission network is not able to sustain this
load-demand level and this production pattern needs reinforcement as necessary. It should be
pointed out that it is expected that transformers in substation Fierza will be replaced with more
powerful transformer units.

4.40
Table 4.6.2 - Network elements loaded over 80% of their thermal limits for 2015-dry hydrology scenario – 2010
topology
BRANCH LOADINGS ABOVE 80.0 % OF RATING:
LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB HL 220kV AKASHA2-ARRAZH2 1 275.3 270 102
ROM HL 220kV BUC.S-B-FUNDENI 1 261.2 320 81.6
SRB HL 220kV JBGD3 21-JOBREN2 1 293.6 301 97.5
Transformers
TR 220/110 kV AELBS1 1 84.7 90 94.1
TR 220/110 kV AELBS1 2 84.7 90 94.1
TR 220/110 kV AELBS1 3 91 90 101.1
TR 220/110 kV AFIER 1 146.8 120 122.3
TR 220/110 kV AFIER 2 120.3 90 133.7
TR 220/110 kV AFIER 3 114.8 90 127.6
ALB TR 220/110 kV AFIERZ 1 59 60 98.3
TR 220/110 kV AFIERZ 2 59 60 98.3
TR 220/110 kV AKASHA 1 90.8 100 90.8
TR 220/110 kV AKASHA 2 90.8 100 90.8
TR 220/110 kV ARRAZH 1 84.7 100 84.7
TR 220/110 kV ARRAZH 2 84.7 100 84.7
TR 220/110 kV ATIRAN 3 98.2 120 81.9
BIH TR 400/110 kV UGLJEV 1 242.4 300 80.8
TR 220/110 kV FUNDE2 1 199.9 200 99.9
ROM TR 220/110 kV FUNDEN 1 168.5 200 84.2
TR 400/220 kV IERNUT 1 325.2 400 81.3
TR 220/110 kV JBGD3 1 171.1 200 85.6
TR 220/110 kV JBGD3 2 129.8 150 86.5
TR 220/110 kV JPRIS4 1 121.6 150 81.1
TR 220/110 kV JPRIS4 2 121.6 150 81.1
SRB TR 220/110 kV JTKOSA 2 133.3 150 88.9
TR 220/110 kV JTKOSA 3 135.7 150 90.5
TR 400/220 kV JTKOSB 1 323.1 400 80.8
TR 400/220 kV JTKOSB 2 337.6 400 84.4
TR 400/220 kV JTKOSB 3 337.6 400 84.4

Histogram
350

300

250
Frequency

200

150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.6.4 - Histogram of branch loadings for 2015-dry hydrology scenario – 2010 network topology ("Frequency"
denotes number of lines and "Bin" denotes loading range in % of thermal limit)

4.6.2 Voltage Profile in the Region

Figure 4.6.5 shows histogram of voltages in monitored substations. Voltages in almost all
monitored substations are found within permitted limits. Only in substations Elbasan and Kashar
voltages are below limits (around 359 kV), but this can be resolved with changing of the setting of
the tap changing transformers in these substations. Also, as a consequence of high imports, voltages
in network of Albania are very near low limits.

4.41
Histogram

120

100

80

Frequency
60

40

20

0
x<0.9

0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

x>1.1
Bin

Figure 4.6.5 - Histogram of voltages in monitored substations for 2015-dry hydrology scenario – 2010 network
topology ("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

In the rest of the monitored network the voltage profile is satisfying and that most of the substations
have magnitudes in range 0.975-1.05 p.u.

4.6.3 Security (n-1) analysis

Results of security (n-1) analysis for 2015-dry hydrology scenario and expected topology for 2010
are presented in Table 4.6.3. Figure 4.6.6 shows the geographical position of the critical elements in
monitored systems.

It can be concluded that all identified insecure situations are located in internal networks that belong
to monitored power systems of Albania, Romania and Serbia. The most critical element in Albanian
system is 220 kV line Elbasan-Fierza. In most critical case in Romanian system, the critical
elements are transformers 400/110 kV in substations Dirste and Brasov. The most critical element
in Serbian system are line 220 kV Obrenovac – Beograd 3.

Some of the overloadings identified can be relieved by dispatch actions (splitting busbars, changing
lower voltage network topology in order to redistribute load-demand or change of generation units
engagement), like in the case of most severe overloading in Romanian network happens on
transformer 400/110 kV Dirste when transformer 400/110 kV in Brasov is outaged, but this is a
consequence of the fact that second transformer unit 400/110 kV in Brasov is out of operation.
Switching on of this transformer clears this critical outage. The similar situation is in case of outage
of the 400 kV line Obrenovac – Beograd 8 in Serbia. Splitting off the 220 kV busbars in substation
Beograd 3 relieves this overloading, but voltage profile in Serbian network remains critical, so
additional dispatching actions are necessary too.

All in all, certain reinforcement of internal network is necessary in order to make this regime more
secure. None of the identified congestions is located at border lines.
4.42
Table 4.6.3 - Network overloadings for 2015-dry hydrology scenario, single outages – 2010 network topology
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
BASE CASE AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 242.3MVA 102.0%
AL OHL 220kV AFIERZ2 -ABURRE2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 261.1MVA 126.2%
AL OHL 220kV ATIRAN2 -AKASHA2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 254.3MVA 106.6%
AL OHL 220kV AELBS12 -AFIER 2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 361.1MVA 180.3%
AL OHL 220kV AFIER 2 -ARRAZH2 1 AL HL 220kV AELBS12-AFIER 2 1 270MVA 194.4MVA 104.8%
RO OHL 220kV FUNDENI -BUC.S-B 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 342.8MVA 106.8%
CS OHL 220kV JBBAST2 -JBGD3 21 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 327.8MVA 111.5%
CS OHL 220kV JBGD172 -JBGD8 22 1 CS HL 220kV JBGD172-JBGD8 22 2 365.8MVA 466.5MVA 133.2%
CS OHL 220kV JBGD3 22-JBGD8 21 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 312.8MVA 106.4%
CS OHL 220kV JGLOGO2 -JPRIZ22 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 231.3MVA 128.2%
CS OHL 220kV JHIP 2 -JPANC22 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 304.5MVA 103.4%
CS OHL 220kV JNSAD32 -JOBREN2 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 311.5MVA 105.2%
CS OHL 220kV JNSAD32 -JZREN22 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 312.6MVA 106.1%
CS OHL 220kV JOBREN2 -JSABA32 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 314.3MVA 106.6%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 511.9MVA 184.1%
CS OHL 400kV JBGD8 1 -JOBREN11 1
CS HL 220kV JBGD3 22-JBGD8 22 2 365.8MVA 354.7MVA 106.4%
CS OHL 400kV JBGD8 1 -JBGD201 A CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 306.4MVA 103.9%
CS OHL 400kV JHDJE11 -JTDRMN1 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 324.4MVA 110.4%
CS OHL 400kV JKRAG21 -JTKOLB1 A CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 306.5MVA 103.9%
CS OHL 400kV JPANC21 -JTDRMN1 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 314.9MVA 107.7%
CS TR 400/220kV/kV JTKOSB1 1 400MVA 413.9MVA 103.5%
CS OHL 400kV JTKOSB1 -JPEC 1 A CS TR 400/220kV/kV JTKOSB1 2 400MVA 432.5MVA 108.1%
CS TR 400/220kV/kV JTKOSB1 3 400MVA 432.5MVA 108.1%
RO TR 400/110 BRASOV 1 RO TR 400/110kV/kV DIRSTE 1 250MVA 401MVA 160.4%
RO TR 400/110 DIRSTE 1 RO TR 400/110kV/kV BRASOV 1 250MVA 394.4MVA 157.7%
CS TR 400/110 JNIS2 1 CS TR 400/110kV/kV JNIS2 1 2 300MVA 363.8MVA 121.3%
AL TR 400/220kV/kV AELBS22 2 300MVA 307.5MVA 102.5%
AL TR 400/220 AELBS2 1
AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 259.2MVA 132.1%
RO TR 400/220 BRAZI 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 346.4MVA 109.9%
RO TR 400/220 BUC.S 1 RO TR 400/220kV/kV BUC.S 2 400MVA 506.1MVA 126.5%
RO TR 400/220 IERNUT 1 RO HL 220kV STEJARU-GHEORGH 1 208.1MVA 191.8MVA 108.6%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 342.9MVA 117.8%
CS TR 400/220 JBGD8 1
CS HL 220kV JBGD3 22-JBGD8 22 2 365.8MVA 385.9MVA 110.9%
CS TR 400/220 JBGD8 2 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 320.8MVA 109.4%
CS TR 400/220 JNIS2 1 CS TR 400/110kV/kV JNIS2 1 1 300MVA 303.3MVA 101.1%
CS TR 400/220 JPANC2 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 300.3MVA 101.8%
CS TR 400/220kV/kV JTKOSB1 2 400MVA 471.5MVA 117.9%
CS TR 400/220 JTKOSB 1
CS TR 400/220kV/kV JTKOSB1 3 400MVA 471.5MVA 117.9%
RO TR 400/220 MINTIA 1 RO HL 220kV PESTIS-MINTIA A 1 277.4MVA 324.3MVA 111.1%
RO TR 400/220 ROSIORI 1 RO TR 400/220kV/kV IERNUT 1 400MVA 425.1MVA 106.3%

SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE 400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.6.6 – Geographical position of critical elements for 2015-dry hydrology scenario – topology 2010

4.43
4.7 Scenario 2015 – dry hydrology – topology 2015
This part of the Study presents the results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as GTmax run for year 2015 - dry hydrology and expected network topology for 2015.

4.7.1 Lines loadings

Figure 4.7.1 shows power exchanges between areas for 2015-dry hydrology scenario. Power flows
along interconnection lines in the region together with balances of the systems are shown in Figure
4.7.2. Area totals are shown in Table 4.7.1. Figure 4.7.3 shows histogram of tie lines loadings. It is
concluded that most of the tie lines are loaded less than 25% of their thermal limits.

SVK UKR
6
450

40

44
AUT
19
0

HUN
81
33

SLO
29

ROM
94

ITA
24
8

CRO 199
73
3

78

BIH 63 SRB
328
89

221
52
MNG BUL
9
35
304
33

18

90
MKD
145

TUR
ALB
291

18
1
24
86

GRE

Figure 4.7.1 - Area exchanges in analyzed electric power systems for 2015-dry hydrology scenario

As it can be seen, new elements that are expected to be build till 2015 cause totally different
distribution of power flows in the southern part of the region (Albania, FYR of Macedonia, Serbia
and Montenegro).

Compared to the expected topology 2010, analyzed in previous chapter, it can be seen that the
network losses are decreased as a consequence of building of new elements for 2015 network
topology, especially in the cases of Albania, Serbia and Montenegro. Overall reduction of loses is
around 40 MW.

4.44
GABICK1400.0 LEVIC 1400.0

CENTREL

251
113

200
141
450.0 MW
346 350
MAISA 7 UZUKRA01
804 297

UCTE OWIEN 1 MGYOR 4


0
714.8 772.5

222.8 MW 25 .8

UKR
112 112
405.4 90

95.0
199
24.7 100 MSAJI 4408.1 35.5 35.6
403.3 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.6 OWIEN 2 MGOD 4 407.7 226.3
20.9 27.7
450.0 MW

48.9

37.0
41.9

37.0
41.9
10.8 10.6

155
MGYOR 2 MTLOK 2
7.6 29.2
234.2 54.0 53.4 230.5 224.4
5.6 20.3
ONEUSI2 UMUKACH
233.5 24.1 23.9 229.0 31.8 31.9 44.
MSAJO 4
12.5 26.3 72.5 46.5 66. 3
410.0 412.0 7

HUN
-1250.0 MW

10. 0

0
6

7
153

37.

37.
45.

10.

44.
128
LPODLO2228.9 LMARIB1 402.5 53.2 53.3
MBEKO 4 NADAB

0
MHEVI 4 408.4 49.4 68.5 ROSIORI 402.4
LDIVAC1 404.9 402.6
215.0 MW

29.6
22.0

29.6
22.0
IRDPV111

SLO
182 183
0.7 21.4 10
401.0 401.0 32 5 MPECS 4 408.4 MSAFA 4 402.7
.9
LKRSKO1 401.1 LCIRKO2 227.2 27.6 27.6 ARAD
LDIVAC2 .2
29 38

35 .7

35 .7
19.3 40.6

28.1

28.1
156

156

6.2
4.6

.1

.1
1 402.0

76

76
IPDRV121
12.2 12.2
12
72.8 76.3 3. . 6
230.3 229.4 1

ROM
ISACCEA 405.7

8 8
105
9.5

76 3.2

205
122
.5 .5

76.
29 .3 29 .3
-368.9 MW

29.4
83 .8
85 85

162
.2
ERNESTIN

6. .3
MELINA 402.3 ZERJAVIN 403.6 JSOMB31
393.8 JSUBO31 396.4

5
2
ZERJAVIN 227.0 198 199
JSMIT21

15 2

15 2
35.1 80.8
12.6

3.

3.
7.1

404.9

24.8
161
TUMBRI 401.1 DAKOVO 222.8

25 2.8
61.8
27.1

46.9
PEHLIN 229.3 MRACLIN 222.5 MEDURIC 219.9

112

.0
401.7

3
38.7
25.7

7.1
7.3
JHDJE11 P.D.FIE
77.6 77.6
55.8 54.8
407.7 407.8 TANTAREN 414.3

CRO

61.0
38.2

61.0
38.2
32.7

62.
-1085.9 MW

22.

76.
162
15.6

2
39 .4

5
7.1

11 2
46
0. 7
33
.0 GRADACAC 225.8 UGLJEVIK 401.8

4
.
SCG
PRIJED2 220.5 TE TUZL 232.1

VISEGRA JVARDI22
30.5 30.5 756.0 MW

206
232.6 231.1

9. 9
61 .0

61 .0
44.9 47.2

12

12
BIH

.0

.0
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 415.4 DOBRUD4 417.4
330 333 759.0 MW 232.1 135 136 238.3 CRG 864.0 MW JNIS2 1 220 221 SOFIA_W4
404.1
32.3 7.2
408.1
35.7 31.7
-108.0 MW 403.5
96.1 38.3
412.5

79.8 79.8
39.8 61.1
HE ZAKUC 131 133 MO-4 RP TREB JHPERU21
14.5 15.1
232.3 234.1 233.6 86.4 85.7 229.7
14.2 19.1

BUL
104 104
RP TREB JPODG211 JLESK21
42.5 86.1
407.8 JPODG121229.3 405.0
766.0 MW

26.6 26.5
20.2 58.8
9.2
0.1

24.3
12.1
402.7 JPRIZ22224.5 JTKOSA2 232.1
JTKOSB1
419.1

8. .6
3
15

28. 1

28. 1

374
67.8
27.

27.
3

3
JVRAN31
407.4
343

48.3
2 4.2

124
21.2
342

1 5
109

1. 5.
127

29.1

1
9.2
AVDEJA1 402.0AVDEJA2
226.7 AFIERZ2224.6 C_MOGILA

3. 24
28.0
37.4

28.0
37.4

93.9

2
1
143
101

143
100

372
.2
90 .1
SK 1 226.2 410.6SK 4 410.0 38 414.0

-444.0 MW STIP 1 .0
90 .7

MKD
BITOLA 2 414.4
411.9
54

BLAGOEV414.5 MI_3_4_1 419.5

36.1
45.0
DUBROVO 412.0
143
139

143
139

242 10
3

182
51. 12 .2

2
60.5
42.2
AKASHA1 393.7

7. 5.
230 4

46.
.6

84.

1
6 8
ALB
-720.0 MW .1
3 6 .3

65.

10 0.
231

64.8
50

9
.2 5
7.6
1 4HAMITAX
18 6.3

8
AHS_FLWR417.3 LAGAD K 414.4 7 7.6 7.6 415.4
90 1
.9

FILIPPOI
24

64.8 76.1
17.8 17.7
408.2 4BABAESK
22.1 71.1

60.5
19.4
415.8 K-KEXRU
417.9 415.6
KARDIA K
86.1 86.6 417.8 QES/H K 413.6
114 43.8
AZEMLA1
0.0 MW
-0.1 MW TUR
GRE
KARACQOU
250 419.6
50.0

GIS REGIONAL MODEL - DRY HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 TOPOLOGY 2015 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR

Figure 4.7.2 - Power flows along interconnection lines in the region with balances of the systems for 2015-dry hydrology scenario
4.45
Table 4.7.1 - Area totals in analyzed electric power systems for 2015-dry hydrology scenario
AREA GENERATION LOAD LOSSES INTERCHANGE
ALBANIA 893.6 1542 71.6 -720
BULGARIA 7363.9 6450 147.8 766
BIH 3141.2 2305 77.1 759
CROATIA 2637.7 3665 58.7 -1085.9
MACEDONIA 985.2 1409 20.2 -444
ROMANIA 7722.9 7798.4 293.5 -368.9
SERBIA 8396.3 7308 224.3 864
MONTENEGRO 586.3 678 16.4 -108
TOTALS 31727.1 31155.4 909.6 -337.8

Histogram
45
40
35
30
Frequency

25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.7.3 - Histogram of interconnection lines loadings for 2015-dry hydrology scenario ("Frequency" denotes
number of lines and "Bin" denotes loading range in % of thermal limit)

Following Table 4.7.2 lists all network elements loaded over 80% of their thermal limits. Figure
4.7.4 shows histogram of branch loadings in the system.

Table 4.7.2 - Network elements loaded over 80% of their thermal limits for 2015-dry hydrology scenario
BRANCH LOADINGS ABOVE 80.0 % OF RATING:
LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB HL 220kV AKASHA2-ARRAZH2 1 242.7 270 89.9
ROM HL 220kV BUC.S-B-FUNDENI 1 260.6 320 81.4
SRB HL 220kV JBGD3 21-JOBREN2 1 294.6 301 97.9
Transformers
TR 220/110 kV AELBS1 1 75.4 90 83.8
TR 220/110 kV AELBS1 2 75.4 90 83.8
TR 220/110 kV AELBS1 3 81 90 90
TR 220/110 kV AFIER 1 136.9 120 114.1
TR 220/110 kV AFIER 2 112.2 90 124.7
ALB
TR 220/110 kV AFIER 3 107.1 90 119
TR 220/110 kV AFIERZ 1 52.1 60 86.9
TR 220/110 kV AFIERZ 2 52.1 60 86.9
TR 220/110 kV AKASHA 1 83.5 100 83.5
TR 220/110 kV AKASHA 2 83.5 100 83.5
BIH TR 400/110 kV UGLJEV 1 240.7 300 80.2
TR 220/110 kV FUNDE2 1 199.6 200 99.8
ROM TR 220/110 kV FUNDEN 1 168.2 200 84.1
TR 400/220 kV IERNUT 1 324.2 400 81.1
TR 220/110 kV JBGD3 1 170.9 200 85.5
SRB
TR 220/110 kV JBGD3 2 130 150 86.6

4.46
Histogram
350

300

250

Frequency
200

150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.7.4 - Histogram of branch loadings for 2015-dry hydrology scenario ("Frequency" denotes number of lines and
"Bin" denotes loading range in % of thermal limit)

As it can be seen from these outputs, most of the network elements are loaded less then 75% of
their thermal limits and most of the elements loaded over 80% are transformers in some substations,
so some internal network reinforcements are necessary to sustain this load-demand level and
production pattern. There are some elements that are overloaded (transformers 220/110 kV in
substation Fierza in Albania). This leads to conclusion that transmission network is not able to
sustain this load-demand level and this production pattern needs reinforcement as necessary. It
should be pointed out that it is expected that transformers in substation Fierza will be replaced with
more powerful transformer units. Also, planned network reinforcements compared to network
topology 2010, reduce loading of some elements in southern part of Serbia.

4.7.2 Voltage Profile in the Region

Figure 4.7.5 shows histogram of voltages in monitored substations. Voltages in all monitored
substations are found within permitted limits. It is concluded that voltage profile is satisfying and
that most of the substations have magnitudes in range 1-1.05 p.u. Compared to the 2010 topology,
voltage profile is somewhat better, especially in southern and central part of Serbia, as well as in
Albania.

4.47
Histogram
100
90
80
70

Frequency
60
50
40
30
20
10
0 x<0.9

0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

x>1.1
Bin

Figure 4.7.5 - Histogram of voltages in monitored substations for 2015-dry hydrology scenario ("Frequency" denotes
number of busses and "Bin" denotes voltage range in p.u.)

4.7.3 Security (n-1) analysis

Results of security (n-1) analysis for 2015-dry hydrology scenario are presented in Table 4.7.3.
Figure 4.7.6 shows the geographical position of the critical elements in monitored systems.

Like for expected topology 2010 (previous chapter), it can be concluded that all identified insecure
situations are located in internal networks that belong to monitored power systems of Albania,
Romania and Serbia. Also, the planned network reinforcements till 2015 resolve some of the
noticed critical contingencies, especially in southern part of Serbia. The rest of the conclusions are
the same as in case of the analyzed topology 2010, and that is that certain level of network
reinforcement is necessary to make this regime more secure.

4.48
SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE 400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.7.6 – Geographical position of critical elements for 2015-dry hydrology scenario

4.49
Table 4.7.3 - Network overloadings for 2015-dry hydrology scenario, single outages
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
AL OHL 220kV AELBS12 -AFIER 2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 376.7MVA 151.9%
RO OHL 220kV FUNDENI -BUC.S-B 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 342.5MVA 106.6%
RO OHL 220kV STEJARU -GHEORGH 1 RO TR 400/220kV/kV IERNUT 1 400MVA 406.2MVA 101.5%
RO OHL 400kV DOMNESTI-BRAZI 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 330.3MVA 102.0%
CS OHL 220kV JBBAST2 -JBGD3 21 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 331MVA 112.3%
CS OHL 220kV JBGD172 -JBGD8 22 1 CS HL 220kV JBGD172-JBGD8 22 2 365.8MVA 467.1MVA 133.0%
CS OHL 220kV JBGD3 22-JBGD8 21 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 314MVA 106.6%
CS OHL 220kV JHIP 2 -JPANC22 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 305.8MVA 103.6%
CS OHL 220kV JNSAD32 -JOBREN2 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 313.5MVA 105.6%
CS OHL 220kV JNSAD32 -JZREN22 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 314.5MVA 106.5%
CS OHL 220kV JOBREN2 -JVALJ32 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 301.6MVA 101.5%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 514.9MVA 184.3%
CS OHL 400kV JBGD8 1 -JOBREN11 1
CS HL 220kV JBGD3 22-JBGD8 22 2 365.8MVA 359.3MVA 107.2%
CS OHL 400kV JBGD8 1 -JBGD201 A CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 308.3MVA 104.2%
CS OHL 400kV JHDJE11 -JTDRMN1 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 324.2MVA 110.1%
CS OHL 400kV JKRAG21 -JTKOLB1 A CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 307.8MVA 104.0%
CS OHL 400kV JPANC21 -JTDRMN1 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 316MVA 107.8%
AL TR 400/110 AZEMLA 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 263.6MVA 108.6%
RO TR 400/110 BRASOV 1 RO TR 400/110kV/kV DIRSTE 1 250MVA 401.1MVA 160.4%
RO TR 400/110 DIRSTE 1 RO TR 400/110kV/kV BRASOV 1 250MVA 394.7MVA 157.9%
RO TR 400/220 BRAZI 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 346.3MVA 109.8%
RO TR 400/220 BUC.S 1 RO TR 400/220kV/kV BUC.S 2 400MVA 506MVA 126.5%
RO TR 400/220 IERNUT 1 RO HL 220kV STEJARU-GHEORGH 1 208.1MVA 190.9MVA 107.9%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 344.1MVA 117.9%
CS TR 400/220 JBGD8 1
CS HL 220kV JBGD3 22-JBGD8 22 2 365.8MVA 388.2MVA 111.3%
CS TR 400/220 JBGD8 2 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 322MVA 109.5%
CS TR 400/220 JPANC2 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 301.9MVA 102.0%
RO TR 400/220 MINTIA 1 RO HL 220kV PESTIS-MINTIA A 1 277.4MVA 325.2MVA 111.3%
RO TR 400/220 ROSIORI 1 RO TR 400/220kV/kV IERNUT 1 400MVA 425.1MVA 106.3%

4.7.4 Summary of Impacts - 2015 topology versus 2010 topology

Compared to the expected topology 2010, analyzed in previous chapter, it can be seen that the
network losses are reduced as a consequence of building of new elements for 2015 network
topology, especially in the cases of Albania, Serbia and Montenegro. Overall reduction of losses is
around 40 MW.

Also, planned network reinforcements compared to network topology 2010, reduce load of some
elements in southern part of Serbia.

Compared to the 2010 topology, voltage profile is somewhat better, especially in southern and
central part of Serbia, as well as in Albania.

Realization of the planed investments till 2015 has impact on secure operation of the network.
Some of the insecure states identified with 2010 topology are relieved and do not exist with
expected 2015 network topology. Also, levels of overloadings due to outages are decreased.

All in all overall network performance is better, especially in the region where new planed
investments are to be realized (Albania, southern Serbia and Montenegro).

4.50
4.8 Scenario 2015 – wet hydrology – 2010 topology
This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as Scenario 2015 wet hydrology and expected network topology for 2010.

4.8.1 Line loadings

Area totals and power exchanges for the 2015-base case-wet hydrology-topology 2010 scenario are
shown in Figure 4.8.1 and Table 4.8.1. Power flows along regional interconnection lines and system
balances are shown in Figure 4.8.2. Power flows along interconnection lines are also given in Table
4.8.2, while Figure 4.8.3 shows histogram of tie lines loadings.

SVK
UKR
4 50

1
46

11
AUT
1
69

HUN
99
54

SLO
86

ITA ROM
15
26
9

CRO 256
38
1

3
13

BIH 320 SRB


366

28 0
26

5
26
1

MNT BUL
89

31

368

9
10
MKD
201

ALB TUR
109

0 1
37
0

GRE
2 50

Figure 4.8.1 - Area exchanges in analyzed electric power systems for 2015-base case-wet hydrology-2010 topology
scenario

4.51
Table 4.8.1 - Area totals in analyzed electric power systems for 2015-base case-wet hydrology-topology 2010 scenario
Country Generation Load Bus Shunt Line Shunt Losses Net Interchange
(MW) (MW) (Mvar) (Mvar) (MW) (MW)
Albania 1124.5 1528.9 0 0 85.8 -490.1
Bulgaria 7553.2 6446.1 0 14.7 137.4 955.0
Bosnia and Herzegovina 2154.2 2278.6 0 0 74.8 -199.3
Croatia 2799.9 3660.4 0 0 60.9 -921.3
Macedonia 869.5 1407.6 0 0 18.9 -557.0
Romania 7953.9 7704.0 0 74.3 298.9 -123.3
Serbia and UNMIK 8413.1 7209.2 0 12.7 278.4 912.7
Montenegro 778.7 669.8 0.5 1.7 21.6 85.0
TOTAL - SE EUROPE 31646.9 30904.6 0.5 103.4 976.6 -338.3

Figure 4.8.3 shows that the tie lines in the region are mostly loaded less than 25% of their thermal
limits for the analyzed hydrological base case scenario in year 2015, examined on network topology
in 2010. Among total number of forty nine 400 kV and 220 kV interconnection lines in the region
only eight are loaded between 25% and 50% of their thermal ratings. Only one line (OHL 400 kV
Sarajevo 20 – Piva between Bosnia and Herzegovina and Montenegro) is loaded more than 50% of
its thermal rating.

Table 4.8.3 lists all network elements, observing only lines 400 kV and 220 kV and transformers
400/x kV and 220/x kV, that are loaded over 80% of their thermal limits. Most of the elements
loaded over 80% are transformers in some substations and internal 110 kV and 220 kV lines. Thus,
certain internal network reinforcements are necessary to sustain given load-demand level and
generation pattern.

All three 220/110 kV transformers in the Fierze substation in Albania are overloaded in this
scenario. There are eight 220/110 kV transformers in Albania which are highly loaded. Line 220 kV
from Tirana to Rashbull is loaded near its limit. There are fourteen 110 kV lines in Albania loaded
over 80% of their thermal rating and five of them are overloaded (the largest overloading is noticed
for the 110 kV line Fierze-F.arrez).

Power systems of Bulgaria and Bosnia and Herzegovina have several highly loaded branches in the
110 kV networks. Highly loaded high voltage branches are 220 kV line M.East-St.Zagora in
Bulgaria and transformer 400/110 kV in TPP Ugljevik in Bosnia and Herzegovina. Line 110 kV
Orasje-Zupanja between Croatia and Bosnia and Herzegovina is overloaded too (135 % Ithermal).

There are ten 220 kV and four 110 kV internal lines in Romania which are loaded over 80% of their
thermal limits, whereas four of them are overloaded. These lines are related to the Lotru, Sibiu,
Tg.Jiu and Parosen nodes. Transformer 400/220 kV in the Urechesti substation is slightly
overloaded in this scenario.

Three 220 kV lines and nineteen 110 kV lines in the Serbian power system are highly loaded or
overloaded when all branches are available in the analyzed scenario. Highly loaded 220 kV lines are
connected to the Obrenovac substation, while 110 kV lines are located mostly in the areas of
Belgrade, Bor, Kragujevac, Sombor and Novi Sad. One 220 kV line and nine 110 kV lines are
overloaded, ranging between 104% Ithermal and 129% Ithermal.

4.52
GABICK1400.0 LEVIC 1400.0

CENTREL

251
112

200
136
450.0 MW
346 350
MAISA 7 UZUKRA01
807 292

UCTE OWIEN 1 MGYOR 4 713.9 772.5


0
25 .7
223.3 MW
UKR
405.4 97.8 97.7
89

89.9
199
23.2 102 MSAJI 408.1 35.5 35.7
403.3 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.7 OWIEN 2 MGOD 4 407.3 226.3
20.6 27.4
450.0 MW
10.8 10.7

48.0

44.7
43.7
44.7
43.7
158
MGYOR 2 MTLOK 2
50.7 50.2 7.5 29.1
234.2 230.5 224.4
6.3 21.4
ONEUSI2 UMUKACH
233.5 21.3 21.2 228.9 87.0 87.2 10.
MSAJO 4
13.2 27.1
410.0
67.0 49.9
412.0 100 9

-1250.0 MW
HUN

12. 7

12. 7
1

5
156

44.

44.
44.

11. 9
15
LPODLO2229.0 LMARIB1 402.6 75.2 75.4
MBEKO 4 NADAB

4
MHEVI 4 408.4 86.0 104 ROSIORI 399.8
LDIVAC1 400.5 396.6
215.0 MW

52.9
26.2
52.9
26.2
IRDPV111

SLO
177 178
7.7 13.2 10
401.0 401.3 40 3 MPECS 4 406.7 MSAFA 4 398.4
.7
LKRSKO1 401.3 LCIRKO2 227.4 23.2 23.2 ARAD
LDIVAC2 .8
85 58

59 .3

59 .3
17.9 75.7

30.5

30.5

13.4
165

165

7.0

.5

.5
IPDRV121 1 394.4

45

45
15.1 15.1 20
69.8 73.3 5. .4
230.5 229.5 9

ROM
ISACCEA 402.9

5
17.3
103
.8 .8

45.

211
127
45 07
52 .6 52 .6
-123.4 MW

86.1
10 .5

180
80 80

1
ERNESTIN

7
13 2.8
MELINA 403.0 ZERJAVIN 403.8 JSOMB31
388.7 JSUBO31 391.4

.4
ZERJAVIN 227.3 255 257
JSMIT21
20.4

16 8

16 8
67.3 105

5.

5.
4.2

401.3

63.5
43.1
TUMBRI 401.4 DAKOVO 218.6

27 234
PEHLIN 229.9 MRACLIN 222.9MEDURIC 219.6

47.5
21.2

93.9
39.7

.8
396.2

33.6
37.5

10.4
1.3
JHDJE11 P.D.FIE
133 133
47.0 46.1 TANTAREN 409.3
397.4 397.6

CRO

77.2
76.6
77.2
76.6
233

47. 5

63. 5
16.

97.
-921.3 MW 3.0

10.4

95 .9
7

7
34 .9

36
6.6
44

.1
GRADACAC 221.0 UGLJEVIK 395.7
.0

SCG
PRIJED2 219.5 TE TUZL 226.4

VISEGRA JVARDI22
86.5 86.9 225.8 997.8 MW

212
227.6

2.2
77 .0

77 .0
28

28
64.2 64.9

BIH

.4

.4
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 412.6 DOBRUD4 415.8
237 238 -199.3 MW 226.4 218 221 232.9 CRG 912.7 MW JNIS2 1 278 281 SOFIA_W4
403.8
21.7 71.8
401.4
19.6 34.2
85.0 MW 388.0
191 152
408.6
HE ZAKUC 54.5 55.1 MO-4 RP TREB JHPERU21
18.8 30.1 18.9 18.7 224.0
234.0 231.5 228.9
32.5 40.0

BUL
75.8 76.1
RP TREB JPODG211 JLESK21
116 154 JPODG121221.7
394.6 375.6
955.0 MW

84.0
87.7
JPRIZ22
215.1 JTKOSA2
221.8JTKOSB1400.0

43.6
5.1
385.2

.2 5
28 1.

17.

17.

333
57.1
3

8.9

8.9
JVRAN31

9
0.000

51.1
4.9

20 1.4
.3
83.7

3
111
AVDEJA1 AVDEJA2
379.3 215.4AFIERZ2217.7 C_MOGILA

17.8
19.2
17.8
19.2

30.0
332
92.2
163
9
10 4
SK 1 219.0 SK 4
401.1 402.6 . 410.7
32

-557.0 MW STIP 1 8
10 .7

MKD
BITOLA 2 412.5
407.9
57

BLAGOEV411.6 MI_3_4_1 419.1


91.5

DUBROVO 408.0
195

57.1
3.7
0
16 .7

46. 5
AKASHA1 366.9

2
30.8
66.0

0. 9.
20
49.
.3

104

1
0 0
8
ALB
-490.1 MW 7

49. 0
3. .5

82.

61.5

0. .7
37

0.0

86
4 4HAMITAX

8
AHS_FLWR415.4 LAGAD K 412.7 20 3.1 0.0 0.1 415.3
FILIPPOI 7
0.8 0.7 61.5 72.9
386.0 4BABAESK

30.9
23.3
K-KEXRU
417.8 72.3

5.0
KARDIA K 415.3 415.5
367 373 415.0 QES/H K 411.6
232 212
AZEMLA1
0.0 MW
0.0 MW TUR
GRE
KARACQOU
250 418.1
50.0

GIS REGIONAL MODEL - WET HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 TOPOLOGY 2010 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 4.8.2 - Power flows along interconnection lines in the region for 2015 - base case - wet hydrology scenario – topology 2010
4.53
Table 4.8.2 - Power flows along regional interconnection lines for 2015 - base case-wet hydrology scenario-topology
2010

Power Flow
Interconnection line % of thermal
rating
MW Mvar
OHL 400 kV Zemlak (ALB) Kardia (GRE) -367.1 -231.6 33
OHL 220 kV Fierze (ALB) Prizren (SER) -31.4 20.3 14
OHL 220 kV V.Dejes (ALB) Podgorica (MON) -4.9 -51.1 19
OHL 400 kV V.Dejes (ALB) Podgorica (MON) -83.7 -111.5 11
OHL 400 kV Ugljevik (B&H) Ernestinovo (CRO) 63.7 -97.5 9
OHL 400 kV Mostar (B&H) Konjsko (CRO) 237.9 -71.8 19
OHL 400 kV Ugljevik (B&H) S. Mitrovica (SER) -232.7 -3.0 18
OHL 400 kV Trebinje (B&H) Podgorica (MON) -75.8 115.9 13
OHL 220 kV Trebinje (B&H) Plat (CRO) -104.8 40.5 37
OHL 220 kV Prijedor (B&H) Mraclin (CRO) 34.0 -44.9 18
OHL 220 kV Prijedor (B&H) Medjuric (CRO) 10.4 -6.6 4
OHL 220 kV Gradacac (B&H) Djakovo (CRO) 47.7 16.5 18
OHL 220 kV Tuzla (B&H) Djakovo (CRO) 95.1 36.9 35
OHL 220 kV Mostar (B&H) Zakucac (CRO) 55.1 -30.1 18
OHL 220 kV Visegrad (B&H) Vardiste (SER) -86.5 64.2 35
OHL 220 kV Sarajevo 20 (B&H) Piva (MON) -217.9 -19.6 58
OHL 220 kV Trebinje (B&H) Perucica (MON) 18.9 32.5 14
OHL 400 kV Blagoevgrad (BUL) Thessaloniki (GRE) -3.7 -57.1 8
OHL 400 kV M.East 3 (BUL) Filippi (GRE) 205.4 -46.2 30
OHL 400 kV M.East 3 (BUL) Babaeski (TUR) 0.0 -19.0 5
OHL 400 kV M.East 3 (BUL) Hamitabat (TUR) -0.7 -16.3 5
OHL 400 kV C.Mogila (BUL) Stip (MCD) 108.7 -32.4 16
OHL 400 kV Dobrudja (BUL) Isaccea (ROM) 212.0 -2.2 15
OHL 2x400 kV ckt.1 Kozloduy (BUL) Tantarena (ROM) 77.4 28.0 8
OHL 2x400 kV ckt.2 Kozloduy (BUL) Tantarena (ROM) 77.4 28.0 8
OHL 400 kV Sofia West (BUL) Nis (SER) 280.6 151.6 45
OHL 2x400 kV ckt.1 Zerjavinec (CRO) Heviz (HUN) -52.8 -80.6 7
OHL 2x400 kV ckt.2 Zerjavinec (CRO) Heviz (HUN) -52.8 -80.6 7
OHL 2x400 kV ckt.1 Ernestinovo (CRO) Pecs (HUN) 45.5 -106.9 9
OHL 2x400 kV ckt.2 Ernestinovo (CRO) Pecs (HUN) 45.5 -106.9 9
OHL 2x400 kV ckt.1 Tumbri (CRO) Krsko (SLO) -165.2 5.8 14
OHL 2x400 kV ckt.2 Tumbri (CRO) Krsko (SLO) -165.2 5.8 14
OHL 400 kV Melina (CRO) Divaca (SLO) 103.3 3.0 10
OHL 400 kV Ernestinovo (CRO) S.Mitrovica (SER) -255.3 67.3 21
OHL 220 kV Zerjavinec (CRO) Cirkovce (SLO) -13.4 -2.8 5
OHL 220 kV Pehlin (CRO) Divaca (SLO) 20.4 -4.2 6
OHL 400 kV Dubrovo (MCD) Thessaloniki (GRE) -30.8 -66.0 5
OHL 400 kV Bitola (MCD) Florina (GRE) -49.8 -103.8 8
OHL 400 kV Skopje (MCD) Kosovo B (UNMIK) -331.6 30.0 25
OHL 2x220 kV ckt.1 Skopje (MCD) Kosovo A (UNMIK) -17.8 -19.2 8
OHL 2x220 kV ckt.2 Skopje (MCD) Kosovo A (UNMIK) -17.8 -19.2 8
OHL 400 kV Arad (ROM) Sandorfalva (HUN) 23.2 -75.7 7
OHL 400 kV - Nadab (ROM) Bekescaba (HUN) 75.4 -103.7 11
OHL 400 kV Rosiori (ROM) Mukacevo (UKR) 11.4 -159.3 14
OHL 400 kV Portile De Fier (ROM) Djerdap (SER) 133.0 46.1 11
OHL 400 kV Subotica (SER) Sandorfalva (HUN) 86.1 -180.5 16
OHL 400 kV Ribarevine (MON) Kosovo B (UNMIK) -452.0 4.3 35
OHL 220 kV Pljevlja (MON) Bajina Basta (SER) 40.2 5.4 14
OHL 220 kV Pljevlja (MON) Pozega (SER) 105.0 42.5 38

4.54
Figure 4.8.4 shows histogram of 400 kV and 220 kV regional internal lines and 400/x kV and 220/x
kV transformers loadings. 37% of observed branches are loaded below 25% of their thermal ratings,
36% are loaded between 25% and 50%, 19% are loaded between 50% and 75%, 7% of observed
branches are loaded between 75% and 100% of their thermal ratings and 1% of them are overloaded
(ten branches in total) if all branches are in operation for the analyzed scenario.

Table 4.8.3 - Network elements loaded over 80% of thermal limits for 2015-base case-wet hydrology-2010 topology
scenario (branches 400 kV and 220 kV)

LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB OHL 220 kV AKASHA2-ARRAZH2 259.3 270.0 96.0
BUL OHL 220 kV MI_2_220-ST ZAGORA 191.0 228.6 83.5
OHL 220 kV MINTIA-SIBIU 324.2 381.1 85.1
OHL 220 kV P.D.F.II-CETATE1 269.0 277.4 97.0
OHL 220 kV LOTRU-SIBIU ckt.1 303.6 277.4 109.4
OHL 220 kV LOTRU-SIBIU ckt.2 303.6 277.4 109.4
OHL 220 kV URECHESI-TG.JIU 280.4 277.4 101.1
ROM
OHL 220 kV P.D.F.A-CETATE1 206.0 208.1 99.0
OHL 220 kV P.D.F.A-RESITA ckt.1 239.1 277.4 86.2
OHL 220 kV P.D.F.A-RESITA ckt.2 239.1 277.4 86.2
OHL 220 kV TG.JIU-PAROSEN 280.4 208.1 134.7
OHL 220 kV BUC.S-B-FUNDENI 285.4 320.0 89.2
SRB OHL 220 kV JBGD3 21-JOBREN2 313.3 301.0 104.1
Transformers
TR 220/110 kV AFIERZ2-AFIERZ5 ckt.1 54.6 60.0 91.1
TR 220/110 kV AFIERZ2-AFIERZ5 ckt.2 54.6 60.0 91.1
TR 220/110 kV AELBS12-AELBS15 ckt.1 81.4 90.0 90.5
TR 220/110 kV AELBS12-AELBS15 ckt.2 81.4 90.0 90.5
TR 220/110 kV AELBS12-AELBS15 ckt.3 87.5 90.0 97.2
ALB TR 220/110 kV AKASHA2-AKASH25 ckt.1 87.2 100.0 87.2
TR 220/110 kV ARRAZH2-ARRAZB5 ckt.1 80.3 100.0 80.3
TR 220/110 kV ARRAZH2-ARRAZB5 ckt.1 80.3 100.0 80.3
TR 220/110 kV AFIER 2-AFIER 5 ckt.1 141.1 120.0 117.5
TR 220/110 kV AFIER 2-AFIER 5 ckt.2 115.6 90.0 128.5
TR 220/110 kV AFIER 2-AFIER 5 ckt.3 110.4 90.0 122.6
B&H TR 400/110 kV UGLJEVIK 270.0 300.0 90.0
TR 400/220 kV URECHESI 414.4 400.0 103.6
TR 400/220 kV BUC.S-BUC.S-B ckt.2 340.0 400.0 85.0
ROM TR 400/220 kV BUC.S-BUC.S-B ckt.3 340.0 400.0 85.0
TR 220/110 kV FUNDENI 175.9 200.0 88.0
TR 220/110 kV FUNDENI-FUNDE2B 208.6 200.0 104.3
TR 400/220 kV JBGD8-JBGD8 22 338.0 400.0 84.5
TR 400/220 kV JTKOSB1-JTKOSB2 ckt.1 324.6 400.0 81.1
TR 400/220 kV JTKOSB1-JTKOSB2 ckt.2 324.6 400.0 81.1
TR 400/110 kV JJAGO41-JJAGO45 247.4 300.0 82.5
SRB TR 220/110 kV JBGD3 21-JBGD 351 197.2 200.0 98.6
TR 220/110 kV JBGD3 22-JBGD 352 134.5 150.0 89.7
TR 220/110 kV JTKOSA2-JTKOSA5 ckt.2 131.9 150.0 87.9
TR 220/110 kV JTKOSA2-JTKOSA5 ckt.3 134.2 150.0 89.5
TR 220/110 kV JZREN22-JZREN25 121.9 150.0 81.3

4.55
45
40
35
30

Frequency
25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.8.3 - Histogram of interconnection lines loadings for 2015-base case-wet hydrology-2010 topology scenario
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

300

250

200
Frequency

150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.8.4 - Histogram of 400 kV and 220 kV regional lines loadings for 2015-base case-wet hydrology-2010
topology scenario ("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

4.8.2 Voltage Profile in the Region

Voltage profile in the region within this scenario which is defined by given generation and demand
pattern is seen as satisfactory despite several appearances of certain bus voltage deviations. The
deviations are shown in Table 4.8.4, which includes only 400 kV and 220 kV network buses.

Bus voltage magnitudes which are found below permitted limits (90% Vnominal in 220 kV network
and 95% Vnominal in 400 kV network) are detected in Albania (three 400 kV and two 220 kV nodes)
and Serbia (three 400 kV nodes). Bus voltage magnitudes that are found above permitted limits
(110% Vnominal in 110 kV and 220 kV networks and 105% Vnominal in 400 kV network) are detected
only in Bulgaria in one node. Figure 4.8.5 shows histogram of bus voltage magnitudes in monitored
400 kV and 220 kV substations.

4.56
Table 4.8.4 - Bus voltage deviations for 2015-base case-wet hydrology-2010 topology scenario, complete network

Voltages
Country Node
pu kV
400 kV AELBS21 0.917 366.7
400 kV AVDEJA1 0.948 379.3
ALBANIA 400 kV AKASHA1 0.917 366.9
220 kV AFIER 2 0.856 188.3
220 kV ABABIC2 0.868 191.0
BOSNIA AND HERZEGOVINA - - -
BULGARIA 400 kV MARITSA EAST2 1.051 420.3
CROATIA - - -
MACEDONIA - - -
MONTENEGRO - - -
ROMANIA - - -
400 kV JBGD201 0.947 378.9
SERBIA AND UNMIK 400 kV JPANC21 0.944 377.5
400 kV JLESK21 0.939 375.6

90
80
70
Frequency

60
50
40
30
20
10
0
x<0.9

x>1.1
0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

Bin

Figure 4.8.5 - Histogram of voltages in monitored substations for 2015-base case-wet hydrology-2010 topology
scenario ("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

It should be emphasized that these results represent only a situation when additional devices
(transformer automatic tap changers, switched shunts, etc.) are not used for voltage regulation.
Impacts of such devices, which exist in many points of the SEE regional transmission network,
need more comprehensive and thorough analysis.

4.8.3 Security (n-1) analysis

Results of security (n-1) analysis for the 2015-base case-wet hydrology-2010 topology scenario are
presented in Table 4.8.5 and Table 4.8.6. Critical contingencies which are included there are related
only to the branches which are not overloaded in the base case when all branches are available.

4.57
Insecure states for given generation and demand pattern are detected in the power systems of
Romania, Serbia, Albania, although there is one contingency in Bulgaria which leads to insecure
state.

The most often overloaded lines in the Romanian power system are 400 kV OHL Mintia-Sibiu, 220
kV OHL Bucuresti Sud-Fundeni and lines 220 kV connected to the Portile de Fier substation. These
lines are overloaded in several contingency cases. Lines 220 kV Lotru-Sibiu, Urechesti-Targa Jiu,
Paroseni-Targa Jiu and transformer in 400/220 kV substation Urechesti are already overloaded in
the base case when all branches are available. Possible actions to reduce the loading of the critical
branches look for a re-dispatching of the generators in Romania within this scenario, especially the
HPP LOTRU CIUNGET (dispatched at 510 MW in the base case), HPP PORTILE 1 (921 MW),
TPP ROVINARI (540 MW) and TPP PAROSENI.

Line 400 kV Mintia-Sibiu has rating of 381 MVA on the model which seems as too low value, so
contingencies in which this line is overloaded are not included in the contingency tables. It is
overloaded if one among following lines goes out of operation: 400 kV Sibiu-Iernut (loading of
Mitia-Sibiu line is 142.3 % Ithermal), 400 kV Iernut-Gadalin (107.7 % Ithermal), 400 kV Rosiori-
Gadalin (100.3 % Ithermal), 220 kV Urechesi-Tg.Jiu (117.7 % Ithermal), 220 kV Tg.Jiu-Parosen (117.6
% Ithermal) and 220 kV Baru M-Hajd Ot (100.0 % Ithermal).

Line 220 kV Buc.S-B-Fundeni is the double circuit line but one circuit is permanently out of
operation on the model which is the reason why this line is included in the contingency tables.

Installed capacity in the substations 400/220 Bucuresti Sud, Brasov, Dirste, Sibiu and Brazi in
Romania are too low to support this generation/demand scenario.

Critical lines in the Serbian power system for this scenario are detected mostly in 220 kV network
of the Beograd area. Installed transformer capacities are inadequate in the Kragujevac, Nis, Kosovo
B and Pancevo substations.

Single outages of 400/110 kV transformers in the stations Brasov and Dirste in Romania are also
found critical, since the second transformer 400/110 kV in the Brasov substation is permanently out
of operation in the model.

The heaviest line overloading (197% Ithermal) in the analyzed scenario is related to 220 kV line in
Serbia (Beograd 3-Obrenovac) when the line 400 kV Beograd 1-Obrenovac goes out of operation.
The heaviest transformer overloading (168% Sn) is related to the transformer 400/110 kV in the
Dirste substation (Romania) when the transformer 400/110 kV in the Brasov substation is outaged
(the parallel one is permanently out of operation in the model).

Figure 4.8.6 shows geographical positions of the critical elements in the analyzed scenario. A green
color reveals 220 kV elements (line 220 kV or transformer 220/x kV), while a red one reveals 400
kV elements (line 400 kV or transformer 400/x kV).

According to the obtained and presented results, it may be concluded that the network topology as
predicted to exist in 2010 is not suitable for the analyzed generation pattern. Larger investments in
the internal networks, especially in the power systems of Romania, Serbia and Albania, will be
necessary in order to support such generation pattern.

4.58
Table 4.8.5 - Lines overloadings for 2015–base case-wet hydrology-2010 topology scenario, single outages

Loadings
Outage Overloaded line(s) Country
MVA %
TR 400/220 kV URECHESI 418.5 104.6
OHL 220 kV LOTRU-SIBIU ckts. 1 & 2 311.4 109.4
Base case OHL 220 kV URECHESI-TG.JIU 282.1 101.1 ROMANIA
OHL 220 kV TG.JIU-PAROSEN 282.1 134.7
OHL 220 kV JBGD3 21-JOBREN2 299.7 104.1 SERBIA
OHL 220 kV AFIERZ2-ABURRE2 OHL 220 kV AKASHA2-ARRAZH2 256.7 112.9 ALBANIA
TR 400/220 kV AELBS21-AELBS22 OHL 220 kV AKASHA2-ARRAZH2 253.7 109.1
B&H/MONT
OHL 400 kV RP TREB-JPODG221 OHL 220 kV AKASHA2-ARRAZH2 242.9 105.4 /ALB
OHL 220 kV G_ORIAH-MI_2_220 OHL 220 kV MI_2_220_ST.ZAGORA 255.4 105.1 BULGARIA
OHL 400 kV TANTAREN-BRADU OHL 220 kV BUC.S-B-FUNDENI 329.5 108.3
OHL 400 kV DOMNESTI-BUC.S OHL 220 kV BUC.S-B-FUNDENI 321.8 102.7
OHL 400 kV DOMNESTI-BRAZI OHL 220 kV BUC.S-B-FUNDENI 355.5 114.6
OHL 220 kV P.D.F.A-CALAFAT OHL 220 kV P.D.F.A-CETATE1 259.9 128.7 ROMANIA
OHL 220 kV P.D.F.A-RESITA ckt.1 OHL 220 kV P.D.F.A-RESITA ckt.2 338.8 129.6
OHL 220 kV RESITA-TIMIS ckt.1 OHL 220 kV RESITA-TIMIS ckt.2 342.8 128.2
OHL 220 kV FUNDENI- BUC.S-B OHL 220 kV BUC.S-B-FUNDENI 368.3 118.1
TR 400/220 kV BRAZI OHL 220 kV BUC.S-B-FUNDENI 369.7 122.0
OHL 400 kV JHDJE11-JTDRMN1 OHL 220 kV P.D.F.A-RESITA ckt.1&2 266.6 102.0 SER/ROM
OHL 400 kV JTKOSB1-JPEC 1 OHL 220 kV AKASHA2-ARRAZH2 243.2 107.0 SER/ALB
OHL 220 kV JBGD172-JBGD8 22 ckt.1 OHL 220 kV JBGD172-JBGD8 22 ckt.2 475.9 140.2 SERBIA
TR 400/220 kV JBGD8 OHL 220 kV JBGD3 22-JBGD8 22 364.7 108.4

Table 4.8.6 - Transformers overloadings for 2015–base case-wet hydrology-2010 topology scenario, single outages

Loadings
Outage Overloaded branch(es) Country
MVA %
TR 400/220 kV BUC.S-BUC.S-B ckt.1 TR 400/220 kV BUC.S-BUC.S-B ckt.2 536.5 134.1
400/110 kV BRASOV TR 400/110 kV DIRSTE 420.0 168.0
400/110 kV DIRSTE TR 400/110 kV BRASOV 410.8 164.3
ROMANIA
TR 400/220 kV SIBIU ckt.1 TR 400/220 kV SIBIU ckt.2 573.0 143.3
TR 400/220 kV BUC.S ckt.1 413.3 103.3
TR 400/220 kV BRAZI
TR 400/220 kV BUC.S ckt.2 413.3 103.3
TR 400/110 kV JKRAG ckt.1 TR 400/110 kV JKRAG ckt.2 316.5 105.5
TR 400/110 kV NIS ckt.1 TR 400/110 kV NIS ckt.2 340.4 113.5
OHL 220 kV JBGD3 22-JBGD8 22 TR 400/220 kV JBGD8 1-JBGD8 22 412.1 103.0 SERBIA
TR 400/110 kV JPANC ckt.1 TR 400/110 kV JPANC ckt.2 334.0 111.3
TR 400/110 kV JTKOSB ckt.1 TR 400/110 kV JTKOSB ckt.2 439.3 109.8

4.59
SVK

AUT
HUN

SLO ROM

CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

GRE
critical elements
400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.8.6 - Geographical positions of the critical elements for 2015-base case-wet hydrology-topology 2010 scenario

4.60
4.9 Scenario 2015 – wet hydrology – topology 2015
This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as Scenario 2015 wet hydrology and expected network topology for 2015.

4.9.1 Line loadings

Area totals and power exchanges for the 2015-base case-wet hydrology-topology 2015 scenario are
shown in Figure 4.9.1 and Table 4.9.1. Power flows along regional interconnection lines and system
balances are shown in Figure 4.9.2. Power flows along interconnection lines are also given in Table
4.9.2, while Figure 4.9.3 shows histogram of tie lines loadings.
SVK
UKR
4 50

3
45

3
AUT
1
79

HUN
74
43

SLO
84

ITA ROM
9
25
8

CRO 246
42
6

7
12

289 SRB
BIH
327

275
33

72
6

MNT BUL
1

1
79

292
33

9
14
MKD
202

TUR
ALB
355

9 1
23
98

GRE
2 50

Figure 4.9.1 - Area exchanges in analyzed electric power systems for 2015-base case-wet hydrology-2015 topology
scenario

Table 4.9.1 - Area totals in analyzed electric power systems for 2015-base case-wet hydrology-topology 2015 scenario
Country Generation Load Bus Shunt Line Shunt Losses Net Interchange
(MW) (MW) (Mvar) (Mvar) (MW) (MW)
Albania 1111.0 1528.9 0 0 72.1 -490.0
Bulgaria 7553.3 6446.1 0 14.7 137.5 955.0
Bosnia and Herzegovina 2155.1 2278.6 0 0 75.6 -199.0
Croatia 2800.9 3660.4 0 0 61.6 -921.1
Macedonia 870.8 1407.6 0 0 20.2 -557.0
Romania 7950.3 7704.0 0 74.5 294.8 -123.0
Serbia and UNMIK 8398.5 7209.2 0 13.2 263.2 913.0
Montenegro 774.1 669.8 0.5 1.8 16.9 85.0
TOTAL - SE EUROPE 31613.9 30904.6 0.5 104.2 941.8 -337.2

4.61
New elements that are expected to be built till 2015 cause significantly different distribution of
power flows in the southern part of the region (Albania, FYR of Macedonia, Serbia, Montenegro).

Compared to the expected topology 2010, analyzed in the previous chapter, it can be seen that the
network losses are smaller as a consequence of building the new elements in the 2015 network
topology, especially in the cases of Albania, Serbia and Montenegro. Overall reduction of losses is
about 35 MW.

Figure 4.9.3 shows that the tie lines in the region are mostly loaded less than 25% of their thermal
limits for the analyzed hydrological base case scenario in year 2015, examined on the planned
network topology for that year. Among total number of fifty two 400 kV and 220 kV
interconnection lines in the region only eight are loaded between 25% and 50% of their thermal
ratings. Only one line (OHL 400 kV Sarajevo 20 – Piva between Bosnia and Herzegovina and
Montenegro) is loaded more than 50% of its thermal rating.

Table 4.9.4 lists all network elements, observing only lines 400 kV and 220 kV and transformers
400/x kV and 220/x kV, that are loaded over 80% of their thermal limits. Most of the elements
loaded over 80% are transformers in some substations and internal 110 kV and 220 kV lines. Thus,
certain internal network reinforcements are necessary to sustain given load-demand level and
generation pattern.

Being compared to the same generation pattern, but with the 2010 network topology, the loading
relief of some branches and transformers in the southern Serbia and Albania may be noticed.

Figure 4.9.4 shows histogram of 400 kV and 220 kV regional internal lines and 400/x kV and 220/x
kV transformers loadings. 38% of observed branches are loaded below 25% of their thermal ratings,
36% are loaded between 25% and 50%, 20% are loaded between 50% and 75%, 5% of observed
branches are loaded between 75% and 100% of their thermal ratings and 1% of them are overloaded
(nine branches in total) if all branches are in operation for the analyzed scenario.

Being compared to the same generation pattern on the 2010 network topology, it is noticed that
there are no significant changes in the total number of branches and the ranges of internal lines
loading. Only one internal branch is loaded below permitted limit in the case of building new
interconnection lines as predicted to exist in 2015.

4.62
GABICK1400.0 LEVIC 1400.0

CENTREL

251
113

200
136
450.0 MW
346 350
MAISA 7 UZUKRA01
807 293

UCTE OWIEN 1 MGYOR 4


0
25 .3
714.0 772.5

222.3 MW
UKR
405.4 105 105
90

90.4
199
23.7 101 MSAJI 408.1 35.5 35.7
403.3 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.7 OWIEN 2 MGOD 4 407.3 226.3
20.7 27.5
450.0 MW
10.8 10.7

47.7

41.9
43.7
41.9
43.7
157
MGYOR 2 MTLOK 2
52.0 51.5 7.5 29.1
234.2 230.5 224.4
6.1 21.0
ONEUSI2 UMUKACH
233.5 22.4 22.3 228.9 78.8 79.0 2.7
MSAJO 4
12.9 26.8 67.8 49.4 94.
410.0 412.0 4

HUN
-1249.9 MW

12. 8

12. 8
1

5
155

41.

41.
44.

3.1
154
LPODLO2229.1 LMARIB1 402.7 62.6 62.7
MBEKO 4 NADAB
MHEVI 4 408.5 82.0 100 ROSIORI 400.3
LDIVAC1 400.9 397.1
215.0 MW

46.5
26.3
46.5
26.3
IRDPV111

SLO
181 181
9.3 11.5 11
401.0 401.4 41 1 MPECS 4 406.9 MSAFA 4 398.8
.7
LKRSKO1 401.3 LCIRKO2 227.4 11.7 11.8 ARAD
LDIVAC2 .1
84 54

55 .0

55 .0
14.8 72.8

31.5

31.5

12.9
165

165

7.3

.6

.6
IPDRV121 1 395.0

51

51
15.9 16.0 22
69.4 72.9 6. .4
230.5 229.6 0

ROM
ISACCEA 403.2

2
18.4
111
.3 .3

51.

203
128
51 03
46 .8 46 .8
-123.1 MW

84.4
10 .2

177
80 80

1
ERNESTIN

3
12 2.6
MELINA 403.1 ZERJAVIN 404.0 JSOMB31
389.3 JSUBO31 392.0

.9
ZERJAVIN 227.4 246 247
JSMIT21
22.4

16 8

16 8
62.2 102

6.

6.
4.0

401.9

73.3
39.5
TUMBRI 401.5 DAKOVO 218.9

28 209
PEHLIN 230.0 MRACLIN 223.0MEDURIC 219.8

49.8
21.1

96.8
39.5

.3
397.0

38.3
37.2

12.9
1.4
JHDJE11 P.D.FIE
127 127
24.2 23.2 TANTAREN 409.7
398.4 398.5

CRO

61.8
78.0
61.8
78.0
208

50. 5

73. 0
16.

94.
-921.1 MW 4.4

12.9

98 .1
0

5
38 .5

37
6.5
44

.1
.7 GRADACAC 221.4 UGLJEVIK 396.6

SCG
PRIJED2 219.8 TE TUZL 226.9

VISEGRA JVARDI22
80.0 80.3 226.9 998.0 MW

204
228.6

2.9
61 .0

61 .0
29

29
59.3 60.3

BIH

.9

.9
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 413.0 DOBRUD4 416.0
252 253 -199.0 MW 227.8 216 219 235.1 CRG 913.0 MW JNIS2 1 274 276 SOFIA_W4
405.0
9.9 59.1
403.9
26.6 40.1
85.0 MW 393.0
156 111
409.5

20.0 39.2
132 132
HE ZAKUC 58.4 58.9 MO-4 RP TREB JHPERU21
16.0 27.2 5.4 5.4 228.7
234.4 232.5 231.5
18.5 26.9

BUL
133 133
RP TREB JPODG211 JLESK21
70.9 111 JPODG121227.6
401.0 393.6
955.0 MW

14.8

21.8 21.7
43.6 79.9
150
JPRIZ22
220.6 JTKOSA2
223.4JTKOSB1400.0

28.6
16.2
395.3

.5 7
51 0.

26. 2

26. 2

354
44.5
3

13.

13.
JVRAN31

8
397.4
362 8

28.8
24.9

64.6
113
361

43 1.1
11.

.9
39.6
26.5

3
151
AVDEJA1 AVDEJA2
394.9 225.8AFIERZ2227.9 C_MOGILA

21 14
.5
26.7
23.2
26.7
23.2

20.1

1
352
91.7
67.5
91.7
67.4
9
14 3
SK 1 219.6 SK 4
400.1 401.3 . 411.3
26

-557.0 MW STIP 1 9
14 .9

MKD
BITOLA 2 411.3
407.6
60

BLAGOEV412.1 MI_3_4_1 419.2


91.5

91.5

DUBROVO 407.4
108

108

56.8
5.1
240 0
4 15 .2

46. 8
AKASHA1 388.8 45.

3
95.3
71.9

0. 8.
20
259
.6

131

1
8 5
ALB
-490.0 MW 2
5. .0

260

62.1
114

0. .4
38

0.7

87
7 4HAMITAX

2
AHS_FLWR415.6 LAGAD K 413.2 20 2.7 0.7 0.7 415.3
84 9
.4

FILIPPOI 7
23

1.0 1.0 62.1 73.4


405.5 4BABAESK

95.5
12.8
23.5
K-KEXRU
417.8 72.5
KARDIA K 415.4 415.5
98.1 98.8 416.9 QES/H K 412.2
128 60.5
AZEMLA1
0.0 MW
-0.1 MW TUR
GRE
KARACQOU
250 419.1
50.0

GIS REGIONAL MODEL - WET HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 TOPOLOGY 2015 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 4.9.2 - Power flows along interconnection lines in the region for 2015 - base case - wet hydrology scenario – topology 2015
4.63
Table 4.9.2 - Power flows along regional interconnection lines for 2015 - base case-wet hydrology scenario-topology
2015

Power Flow
Interconnection line % of thermal
rating
MW Mvar
OHL 400 kV Zemlak (ALB) Kardia (GRE) -98.1 -128.3 12
OHL 220 kV Fierze (ALB) Prizren (SER) 31.1 43.9 20
OHL 220 kV V.Dejes (ALB) Podgorica (MON) 28.8 -24.9 13
OHL 400 kV V.Dejes (ALB) Podgorica (MON) 150.5 -39.6 12
OHL 400 kV Ugljevik (B&H) Ernestinovo (CRO) 73.5 -94.0 9
OHL 400 kV Mostar (B&H) Konjsko (CRO) 253.5 -59.1 19
OHL 400 kV Ugljevik (B&H) S. Mitrovica (SER) -208.1 -4.4 16
OHL 400 kV Trebinje (B&H) Podgorica (MON) -133.1 70.9 13
OHL 220 kV Trebinje (B&H) Plat (CRO) -104.8 40.2 36
OHL 220 kV Prijedor (B&H) Mraclin (CRO) 38.7 -44.5 19
OHL 220 kV Prijedor (B&H) Medjuric (CRO) 12.9 -6.5 5
OHL 220 kV Gradacac (B&H) Djakovo (CRO) 50.0 16.5 18
OHL 220 kV Tuzla (B&H) Djakovo (CRO) 98.1 37.1 35
OHL 220 kV Mostar (B&H) Zakucac (CRO) 58.9 -27.2 19
OHL 220 kV Visegrad (B&H) Vardiste (SER) -80.0 59.3 32
OHL 220 kV Sarajevo 20 (B&H) Piva (MON) -215.8 -26.6 57
OHL 220 kV Trebinje (B&H) Perucica (MON) 5.4 18.5 9
OHL 400 kV Blagoevgrad (BUL) Thessaloniki (GRE) -5.1 -56.8 8
OHL 400 kV M.East 3 (BUL) Filippi (GRE) 208.0 -46.3 30
OHL 400 kV M.East 3 (BUL) Babaeski (TUR) 1.0 -18.5 5
OHL 400 kV M.East 3 (BUL) Hamitabat (TUR) 0.0 -15.6 5
OHL 400 kV C.Mogila (BUL) Stip (MCD) 149.4 -26.3 21
OHL 400 kV Dobrudja (BUL) Isaccea (ROM) 204.0 -2.9 15
OHL 2x400 kV ckt.1 Kozloduy (BUL) Tantarena (ROM) 61.9 29.0 7
OHL 2x400 kV ckt.2 Kozloduy (BUL) Tantarena (ROM) 61.9 29.0 7
OHL 400 kV Sofia West (BUL) Nis (SER) 276.1 111.2 42
OHL 2x400 kV ckt.1 Zerjavinec (CRO) Heviz (HUN) -46.3 -80.8 7
OHL 2x400 kV ckt.2 Zerjavinec (CRO) Heviz (HUN) -46.3 -80.8 7
OHL 2x400 kV ckt.1 Ernestinovo (CRO) Pecs (HUN) 51.2 -103.2 9
OHL 2x400 kV ckt.2 Ernestinovo (CRO) Pecs (HUN) 51.2 -103.2 9
OHL 2x400 kV ckt.1 Tumbri (CRO) Krsko (SLO) -165.2 6.8 14
OHL 2x400 kV ckt.2 Tumbri (CRO) Krsko (SLO) -165.2 6.8 14
OHL 400 kV Melina (CRO) Divaca (SLO) 111.0 4.3 10
OHL 400 kV Ernestinovo (CRO) S.Mitrovica (SER) -245.7 62.2 20
OHL 220 kV Zerjavinec (CRO) Cirkovce (SLO) -12.9 -2.6 4
OHL 220 kV Pehlin (CRO) Divaca (SLO) 22.4 -4.0 7
OHL 400 kV Dubrovo (MCD) Thessaloniki (GRE) -95.3 -71.9 8
OHL 400 kV Bitola (MCD) Florina (GRE) -259.0 -130.7 24
OHL 400 kV Skopje (MCD) Kosovo B (UNMIK) -351.8 20.1 27
OHL 2x220 kV ckt.1 Skopje (MCD) Kosovo A (UNMIK) -26.7 -23.2 11
OHL 2x220 kV ckt.2 Skopje (MCD) Kosovo A (UNMIK) -26.7 -23.2 11
OHL 400 kV Arad (ROM) Sandorfalva (HUN) 11.8 -72.8 6
OHL 400 kV - Nadab (ROM) Bekescaba (HUN) 62.7 -100.0 10
OHL 400 kV Rosiori (ROM) Mukacevo (UKR) 3.1 -154.0 13
OHL 400 kV Portile De Fier (ROM) Djerdap (SER) 126.8 23.2 10
OHL 400 kV Subotica (SER) Sandorfalva (HUN) 84.4 -176.8 16
OHL 400 kV Ribarevine (MON) Kosovo B (UNMIK) -281.4 26.7 22
OHL 220 kV Pljevlja (MON) Bajina Basta (SER) 49.2 11.1 17
OHL 220 kV Pljevlja (MON) Pozega (SER) 113.7 45.4 38
OHL 400 kV* Skopje 4 (MCD) Vranje (SER) 113.6 21.5 10
OHL 400 kV* Zemlak (ALB) Bitola (MCD) 239.8 45.4 19
OHL 400 kV* V.Dejes (ALB) Kosovo B (UNMIK) -360.9 -26.5 27
* new lines planned till 2015

4.64
Table 4.9.3 - Network elements loaded over 80% of thermal limits for 2015-base case-wet hydrology-2015 topology
scenario (branches 400 kV and 220 kV)

LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB OHL 220 kV AKASHA2-ARRAZH2 237.0 270.0 87.8
BUL OHL 220 kV MI_2_220-ST ZAGORA 190.4 228.6 83.3
OHL 220 kV MINTIA-SIBIU 313.4 381.1 82.2
OHL 220 kV P.D.F.II-CETATE1 268.4 277.4 96.8
OHL 220 kV LOTRU-SIBIU ckt.1 303.4 277.4 109.4
OHL 220 kV LOTRU-SIBIU ckt.2 303.4 277.4 109.4
OHL 220 kV URECHESI-TG.JIU 275.4 277.4 99.3
ROM
OHL 220 kV P.D.F.A-CETATE1 205.6 208.1 98.8
OHL 220 kV P.D.F.A-RESITA ckt.1 235.6 277.4 84.9
OHL 220 kV P.D.F.A-RESITA ckt.2 235.6 277.4 84.9
OHL 220 kV TG.JIU-PAROSEN 275.4 208.1 132.3
OHL 220 kV BUC.S-B-FUNDENI 284.6 320.0 88.9
SRB OHL 220 kV JBGD3 21-JOBREN2 312.6 301.0 103.8
Transformers
TR 220/110 kV AFIERZ2-AFIERZ5 ckt.1 50.2 60.0 83.7
TR 220/110 kV AFIERZ2-AFIERZ5 ckt.2 50.2 60.0 83.7
TR 220/110 kV AELBS12-AELBS15 ckt.1 74.8 90.0 83.2
TR 220/110 kV AELBS12-AELBS15 ckt.2 74.8 90.0 83.2
TR 220/110 kV AELBS12-AELBS15 ckt.3 80.4 90.0 89.3
ALB
TR 220/110 kV AKASHA2-AKASH25 ckt.1 82.3 100.0 82.3
TR 220/110 kV AKASHA2-AKASH25 ckt.2 82.3 100.0 82.3
TR 220/110 kV AFIER 2-AFIER 5 ckt.1 134.5 120.0 112.1
TR 220/110 kV AFIER 2-AFIER 5 ckt.2 110.3 90.0 122.5
TR 220/110 kV AFIER 2-AFIER 5 ckt.3 105.2 90.0 116.9
B&H TR 400/110 kV UGLJEVIK 267.6 300.0 89.2
TR 400/220 kV URECHESI 410.3 400.0 102.6
TR 400/220 kV BUC.S-BUC.S-B ckt.1 339.3 400.0 84.8
ROM TR 400/220 kV BUC.S-BUC.S-B ckt.2 339.3 400.0 84.8
TR 220/110 kV FUNDENI 175.7 200.0 87.8
TR 220/110 kV FUNDENI-FUNDE2B 208.3 200.0 104.1
TR 400/220 kV JBGD8-JBGD8 22 334.9 400.0 83.7
TR 220/110 kV JBGD3 21-JBGD 351 196.6 200.0 98.3
SRB
TR 220/110 kV JBGD3 22-JBGD 352 134.4 150.0 89.6
TR 220/110 kV JZREN22-JZREN25 121.5 150.0 81.0

50
45
40
35
Frequency

30
25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.9.3 - Histogram of interconnection lines loadings for 2015-base case-wet hydrology-2015 topology scenario
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

4.65
300

250

200
Frequency
150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 4.9.4 - Histogram of 400 kV and 220 kV regional lines loadings for 2015-base case-wet hydrology-2015
topology scenario ("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

4.9.2 Voltage Profile in the Region

Voltage profile in the region within this scenario which is defined by given generation and demand
pattern is seen as satisfactory despite several appearances of certain bus voltage deviations. The
deviations are shown in Figure 4.9.5, which includes only 400 kV and 220 kV network buses.

Table 4.9.4 - Bus voltage deviations for 2015-base case-wet hydrology-2015 topology scenario, complete network
Voltages
Country Node
pu kV
ALBANIA - - -
BOSNIA AND HERZEGOVINA - - -
BULGARIA 400 kV MARITSA EAST2 1.051 420.4
CROATIA - - -
MACEDONIA - - -
MONTENEGRO - - -
ROMANIA - - -
SERBIA AND UNMIK 400 kV JPANC21 0.947 378.8

Bus voltage magnitudes which are found below permitted limits (90% Vnominal in 220 kV network
and 95% Vnominal in 400 kV network) are detected only in Serbia (one 400 kV node). Bus voltage
magnitudes that are found above permitted limits (110% Vnominal in 110 kV and 220 kV networks
and 105% Vnominal in 400 kV network) are detected only in Bulgaria in one node. Figure 4.3.11
shows a histogram of voltages in monitored 400 kV and 220 kV substations.

Being compared to the same generation pattern on the 2010 network topology, it is noticed that
there are significant voltage profile improvements, especially in the power systems of Albania and
Serbia.

4.66
90
80
70

Frequency
60
50
40
30
20
10
0
x<0.9

x>1.1
0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1
Bin

Figure 4.9.5 - Histogram of voltages in monitored substations for 2015-base case-wet hydrology-2015 topology
scenario ("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

4.9.3 Security (n-1) analysis

Results of security (n-1) analysis for the 2015-base case-wet hydrology-2015 topology scenario are
presented in Table 4.9.5 and Table 4.9.6. Critical contingencies which are included there are related
only to the branches which are not overloaded in the base case when all branches are available.

Insecure states for given generation and demand pattern are detected in the power systems of
Romania, Serbia, Albania, although there is one contingency in Bulgaria and Bosnia and
Herzegovina each which leads to insecure state.

Being compared to the same generation and demand scenario on the 2010 network topology, it is
concluded that there are several new contingency cases in the power system of Albania and one new
contingency case in the power systems of Romania and Bosnia and Herzegovina (marked with red
color in Table 4.9.5 and Table 4.9.6). At the same time, several contingency cases do not appear
any more (marked in blue color in Table 4.9.5 and Table 4.9.6). These contingency cases are related
to the power systems of Albania, Serbia and Romania, although it is noticed that the influence of
the new investments is less significant in the power system of Romania than it is in Albania and
southern Serbia.

There are no contingency cases in the 2015 network topology which are related to the
interconnection lines. The same conclusion is valid for the 2010 network topology and analyzed
generation/demand scenario.

Figure 4.9.6 shows geographical positions of the critical elements in the analyzed scenario. A green
color reveals 220 kV elements (line 220 kV or transformer 220/x kV), while a red one reveals 400
kV elements (line 400 kV or transformer 400/x kV).

According to the obtained and presented results, it may be concluded that the network topology as
predicted to exist in 2015 is not suitable for the analyzed generation pattern. Larger investments in
the internal networks, especially in power systems of Romania, Serbia and Albania, are necessary
shall such generation pattern be supported.

4.67
Table 4.9.5 - Lines overloadings for 2015–base case-wet hydrology-2015 topology scenario, single outages
Loadings
Outage Overloaded line(s) Country
MVA %
TR 400/220 kV URECHESI 414.9 103.7
OHL 220 kV LOTRU-SIBIU ckt. 1 & 2 311.3 109.4
Base case OHL 220 kV URECHESI-TG.JIU ROMANIA
OHL 220 kV TG.JIU-PAROSEN 277.5 132.3
OHL 220 kV JBGD3 21-JOBREN2 299.9 103.8 SERBIA
OHL 400 kV AELBS21-AZEMLA1 OHL 220 kV AKASHA2-ARRAZH2 242.5 100.5
OHL 220 kV AELBS12-AFIER 2 OHL 220 kV AKASHA2-ARRAZH2 359.7 143.7
TR 400/110 kV AZEMLA1-AZEMLK5 OHL 220 kV AKASHA2-ARRAZH2 254.1 102.6 ALBANIA
OHL 220 kV AFIERZ2-ABURRE2 OHL 220 kV AKASHA2-ARRAZH2
TR 400/220 kV AELBS21-AELBS22 OHL 220 kV AKASHA2-ARRAZH2
B&H/MONT
OHL 400 kV RP TREB-JPODG221 OHL 220 kV AKASHA2-ARRAZH2 /ALB
OHL 220 kV G_ORIAH-MI_2_220 OHL 220 kV MI_2_220_ST.ZAGORA 254.6 104.7 BULGARIA
OHL 400 kV TANTAREN-BRADU OHL 220 kV BUC.S-B-FUNDENI 328.6 107.7
OHL 400 kV DOMNESTI-BUC.S OHL 220 kV BUC.S-B-FUNDENI 321.0 102.3
OHL 400 kV DOMNESTI-BRAZI OHL 220 kV BUC.S-B-FUNDENI 354.5 114.1
OHL 220 kV P.D.F.A-CALAFAT OHL 220 kV P.D.F.A-CETATE1 259.6 128.2 ROMANIA
OHL 220 kV P.D.F.A-RESITA ckt.1 OHL 220 kV P.D.F.A-RESITA ckt.2 335.1 127.6
OHL 220 kV RESITA-TIMIS ckt.1 OHL 220 kV RESITA-TIMIS ckt.2 338.3 126.1
OHL 220 kV FUNDENI- BUC.S-B OHL 220 kV BUC.S-B-FUNDENI 367.8 117.8
TR 400/220 kV BRAZI OHL 220 kV BUC.S-B-FUNDENI 369.5 121.8
OHL 400 kV JHDJE11-JTDRMN1 OHL 220 kV P.D.F.A-RESITA ckt.1&2 SER/ROM
OHL 400 kV JTKOSB1-JPEC 1 OHL 220 kV AKASHA2-ARRAZH2 SER/ALB
OHL 220 kV JBGD172-JBGD8 22 ckt.1 OHL 220 kV JBGD172-JBGD8 22 ckt.2 475.6 139.6 SERBIA
TR 400/220 kV JBGD8 OHL 220 kV JBGD3 22-JBGD8 22 366.1 108.4

Table 4.9.6 - Transformers overloadings for 2015–base case-wet hydrology-2015 topology scenario, single outages
Loadings
Outage Overloaded branch(es) Country
MVA %
OHL 400 kV BLUKA 6-TS TUZL TR 400/110 kV UGLJEVIK 311.0 103.7 B&H
OHL 220 kV BUC.S-B-FUNDENI TR 400/220 kV BRAZI 414.2 103.6
TR 400/220 kV BUC.S-BUC.S-B ckt.1 TR 400/220 kV BUC.S-BUC.S-B ckt.2 535.9 134.0
TR 400/110 kV BRASOV TR 400/110 kV DIRSTE 419.2 167.7
ROMANIA
TR 400/110 kV DIRSTE TR 400/110 kV BRASOV 410.2 164.1
TR 400/220 kV SIBIU ckt.1 TR 400/220 kV SIBIU ckt.2 571.7 142.9
TR 400/220 kV BUC.S ckt.1 413.1 103.3
TR 400/220 kV BRAZI
TR 400/220 kV BUC.S ckt.2 413.1 103.3
TR 400/110 kV JKRAG ckt.1 TR 400/110 kV JKRAG ckt.2 314.4 104.8
TR 400/110 kV NIS ckt.1 TR 400/110 kV NIS ckt.2
OHL 220 kV JBGD3 22-JBGD8 22 TR 400/220 kV JBGD8 1-JBGD8 22 411.2 102.8 SERBIA
TR 400/110 kV JPANC ckt.1 TR 400/110 kV JPANC ckt.2 332.5 110.8
TR 400/110 kV JTKOSB ckt.1 TR 400/110 kV JTKOSB ckt.2

4.68
SVK

AUT
HUN

SLO ROM

CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

GRE
critical elements
400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 4.9.6 - Geographical positions of the critical elements for 2015-base case-wet hydrology-topology 2015 scenario

4.9.4 Summary of Impacts - 2015 topology versus 2010 topology

Compared to the expected topology 2010, analyzed in previous chapter, it can be seen that the
network losses are smaller as a consequence of building the new elements for 2015 network
topology, especially in the cases of Albania, Serbia and Montenegro. Overall reduction of losses is
around 35 MW.

Comparing to the same generation pattern on the 2010 network topology, it is noticed that there are
no significant changes in the total number of branches and the ranges of internal lines loading.

Being compared to the same generation pattern on the 2010 network topology, it is noticed that
there are significant voltage profile improvements, especially in the power systems of Albania and
Serbia.

Being compared to the same generation and demand scenario on the 2010 network topology, it is
concluded that there are several new contingency cases in the power system of Albania and one new
contingency case in the power systems of Romania and Bosnia and Herzegovina. At the same time,
several contingency cases do not appear any more. These contingency cases are related to the power
systems of Albania, Serbia and Romania, although it is noticed that the influence of the new
investments is less significant in the power system of Romania than it is in Albania and southern
Serbia.

Planned new investments in 2015 make overall network performance better, especially in the region
where new planed investments are to be realized (Albania, southern Serbia and Montenegro), but do

4.69
not solve all contingences which are happening for analyzed generation and demand scenario.
Further internal network reinforcements, especially in the power systems of Romania, Albania and
Serbia, will be necessary in order to allow such generation dispatch with significant level of
network operation security.

4.70
5 LOAD FLOW AND CONTINGENCY ANALYSIS –
SENSITIVITY CASES

5.1
Introduction

In this chapter load-flow and security (n-1) analysis for sensitivity cases defined in Chapter 2 is
described. The analyzed network models are:

Special
Year Topology
conditions
2010 2010
Import/Export 2010
2015
2015
2010 2010
High load 2010
2015
2015

The load-flow analysis includes line loading and voltage profile analysis, analysis of losses and also
analysis of power flows through interconnection lines.

The system reliability and adequacy is checked using “n-1” contingency criterion. List of
contingencies includes:
• all interconnection lines;
• all 400 and 220 kV lines in analyzed region, except lines which outage cause “island”
operation (in case of parallel and double circuit lines, outage of one line is considered);
• all transformers 400/x kV in analyzed region (in case of parallel transformers, outage of one
transformer is considered).

Current thermal limits are used as rated limits of lines and transformers, as described in Chapter 2.
Voltage limits are defined in Chapter 2, also.
Every branch with current above its thermal limit is treated as overloaded. States with overloaded
branches and/or voltages below or above defined voltage limits are treated as "insecure".

5.1 Scenario 2010 – average hydrology – import/export - 2010 topology

This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as Scenario 2010 – sensitivity case – average hydrology – import 1500 MW.

Concerning the import/export case, the simulated regime means the following:

▪ Import 750 MW from UCTE


▪ Import 500 MW from Turkey
▪ Export 500 MW to Greece
▪ Import 750 MW from Ukraine

5.1.1 Line loadings


Area totals and power exchanges for the 2010-sensitivity case-average hydrology-import 1500 MW
scenario are shown in Figure 5.1.1 and Table 5.1.1. Power flows along regional interconnection
lines and system balances are shown in Figure 5.1.2. Power flows along interconnection lines are
also given in Table 5.1.2, while Figure 5.1.3 shows histogram of tie lines loadings.

5.2
SVK
UKR

4 50

6
74

4 54
AUT

4
13
HUN
16
1
55
9

164
SLO

6
ITA ROM
35
77
4

CRO 140
21
4

0
16
135 SRB
BIH

29
4 08
30

37
1

MNT BUL
1
91

36

67

2
70
3
22
MKD

381
TUR
ALB
77

0 230
28
5

GRE
2 50

Figure 5.1.1 - Area exchanges in analyzed electric power systems for 2010-sensitivity case-average hydrology-import
1500 MW scenario

Table 5.1.1 - Area totals in analyzed electric power systems for 2010-sensitivity case-average hydrology-import 1500
MW scenario
Country Generation Load Bus Shunt Line Shunt Losses Net Interchange
(MW) (MW) (Mvar) (Mvar) (MW) (MW)
Albania 898.2 1288.5 0 0 49.7 -440.0
Bulgaria 6827.0 5967.5 0 14.2 131.2 714.0
Bosnia and Herzegovina 2398.3 1965.0 0 0 54.3 379.0
Croatia 1705.2 3143.3 0 0 44.9 -1483.0
Macedonia 965.5 1178.3 0 0 20.1 -233.0
Romania 6877.4 6733.1 0 80.0 169.1 -104.8
Serbia and UNMIK 6591.7 6901.7 0 13.4 198.6 -521.9
Montenegro 542.1 670.2 0.5 1.5 16.9 -147.0
TOTAL - SE EUROPE 26805.4 27847.6 0.5 109.1 684.8 -1836.7

By comparing the average hydrology situation in 2010 and balanced SE Europe power system to
the average hydrology situation and 1500 MW of power import, significant increase of power flows
is noticed along Slovenian-Croatian, Ukrainian-Romanian and Bosnian-Montenegrin interfaces.
However, interconnection lines are not jeopardised since they are loaded far below their thermal
ratings. Power flows through Bosnian-Croatian, Serbian-Bosnian, Serbian-Croatian, Serbian-
Montenegrin and Grecian-Albanian interfaces are decreased at the same time.

5.3
Power losses, compared to the situation of balanced SE Europe power system, are increased in the
power systems of Bulgaria (7.9 %) and Montenegro (9 %). In other power systems these losses are
decreased, with the most significant drop in Romania (-16 %) and Serbia and UNMIK (-10.1 %).
Regional power losses are decreased (-7.1 %) when the situation includes additional power import.

Figure 5.1.3 shows that the tie lines in the region are mostly loaded less than 25% of their thermal
limits for the analyzed import/export scenario in year 2010. Among total number of forty nine 400
kV and 220 kV interconnection lines in the region only seven are loaded between 25% and 50% of
their thermal ratings. Only one line (OHL 400 kV Sofia – Nis between Bulgaria and Serbia) is
loaded more than 50% of its thermal rating, which is set at lower value (692.8 MVA) on the
Bulgarian side compared to the line rating on the Serbian side (1330.2 MVA).

Table 5.1.3 lists all network elements loaded over 80% of their thermal limits. As it can be seen
from this output list, most of the elements loaded over 80% are transformers in some substations
and internal 110 kV and 220 kV lines. Thus, certain internal network reinforcements are necessary
to sustain given load-demand level and generation pattern including import of 1500 MW from
analyzed directions.

Figure 5.1.4 shows histogram of 400 kV and 220 kV regional internal lines and 400/x kV and 220/x
kV transformers loadings. Some 46% of observed branches are loaded below 25% of their thermal
ratings, 36% are loaded between 25% and 50%, 16% are loaded between 50% and 75% and only
1% of observed branches are loaded between 75% and 100% of their thermal ratings. Two branches
(transformers 220/110 kV Fierze in Albania, 102% - 106% Sn) are overloaded when all branches are
in operation for the analyzed scenario.

By comparing the average hydrology situation in 2010 and balanced SE Europe power system to
the average hydrology situation and 1500 MW of power import it is noticed that power system of
Bosnia and Herzegovina is slightly relieved, while some highly loaded branches appear in the
power system of Bulgaria. Distribution of internal branches loading stays almost the same.

5.4
GABICK1400.0 LEVIC 1400.0

CENTREL

251
113

200
148
450.0 MW
346 350
MAISA 7 UZUKRA01
800 304

UCTE OWIEN 1 MGYOR 4 716.0 772.5


0
25 .2
971.8 MW
UKR
405.0 288 287
91

199
102
38.6 75.9 MSAJI 408.2 35.8 35.9
403.4 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 402.6 OWIEN 2 MGOD 4 408.2 226.3
21.3 28.1
1200.0 MW
11.1 10.9

40.6

56.2

56.2
217

106

106
MGYOR 2 MTLOK 2
80.6 79.4 7.7 29.3
233.5 230.5 224.4
0.8 12.2
ONEUSI2 UMUKACH
232.8 46.0 45.6 228.6 370 374 457
MSAJO 4
7.2 19.9 22.4 50.7 39.
410.0 412.0 8

HUN
-1250.0 MW

7
213

106

106
24.

25.

25.

22.
452
LPODLO2229.7 LMARIB1 403.9 87.4 87.5
MBEKO 4 NADAB

0
MHEVI 4 410.2 20.0 39.4 ROSIORI 410.4
LDIVAC1 408.6 407.8
215.0 MW

51.3
38.6
51.3
38.6
IRDPV111

SLO
102 102
93.9 72.0 87
401.2 403.0 11 .2 MPECS 4 410.3 MSAFA 4 406.1
1
LDIVAC2 LKRSKO1 403.3 LCIRKO2 228.8 4 73.0 73.1 ARAD
16 5 33.3 26.9

16 27

16 27
62.8

62.8

96.1
34.1
271

271

.7

.7
IPDRV121 10 407.0

1
30.1 30.1 10
35.4 39.1 36 .5
231.4 230.8 .3

ROM
ISACCEA 414.5

87.0
87.9

12 1.1
.1 .1

93.9
127

197
51 .8 51 .8
-104.9 MW

163
128
69 69

.1
31 7
ERNESTIN

95 9.
MELINA 407.5 ZERJAVIN 407.3 JSOMB31
398.4 JSUBO31 400.6

2
.0 5
ZERJAVIN 230.5 139 140
JSMIT21
10.5

27 5

27 5
38.6 89.2

42

42
26.3

409.0

1
.

40.2
2.1
TUMBRI 404.4 DAKOVO 226.3

57 121
PEHLIN 233.9 MRACLIN 227.4MEDURIC 227.0

58.6
22.6

38.6
103

.1
404.9

14.1

40.3
8.2

8.7
JHDJE11 P.D.FIE
159 160
54.1 53.1 TANTAREN 416.2
407.5 407.7

CRO

25.5

25.5
114

114
121

58. 9

40. 6
17.

60.
-1483.0 MW 17.9

40.5

3
16.3
14 .2

35
10 8
17
.2 GRADACAC 228.8 UGLJEVIK 406.6

.
5
SCG
PRIJED2 226.5 TE TUZL 233.9

VISEGRA JVARDI22
-668.9 MW

45.6
14.0 14.1 230.9

199
233.0

23
11 8
23
11
59.1 61.3

BIH

.
3
.8
3
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 415.6 DOBRUD4 420.7
81.3 81.4 379.0 MW 232.7 73.6 73.9 235.2 CRG -521.9 MW JNIS2 1 405 410 SOFIA_W4
410.6
14.2 50.3
409.6
17.7 6.1
-147.0 MW 392.5
149 128
410.7
HE ZAKUC 60.7 61.2 MO-4 RP TREB JHPERU21
2.5 14.0 104 103 228.3
234.6 235.1 232.3
13.4 16.4

BUL
218 217
RP TREB JPODG211 JLESK21
78.7 113 JPODG121227.1
402.9 382.6
714.0 MW

145
2.6
JPRIZ22
219.0 JTKOSA2
221.4JTKOSB1395.7

46.2
7.0
394.7

.1 7
53 5.

7.6 2

7.6 2

51.1
90.5
3

10.

10.
JVRAN31
0.000

46.0

45 6.1
1.3

.9
27.5

3
145
AVDEJA1 393.2
AVDEJA2
226.4AFIERZ2226.7 C_MOGILA

20.7

20.7
51.2
43.6
7.6

7.6
131
108
4
22 2
SK 1 219.1 SK 4
401.3 403.3 . 412.4
38

-233.0 MW STIP 1 2
22 .3

MKD
BITOLA 2 414.1
409.6
42

BLAGOEV412.9 MI_3_4_1 419.2


DUBROVO 409.4
130
145

67.7
48.6
1
9. 49

40. 5
AKASHA1 384.3

0
66.3
42.2

12 .2
31
10. 6
3

65.

4
0
1
ALB
-440.0 MW .5

10. 2
67 .8

43.

80.3

15 06
44

120
2

1
4HAMITAX

0
AHS_FLWR415.8 LAGAD K 412.1 31 1.3 120 120 414.2
FILIPPOI 6
230 231 80.3 90.9
397.4 4BABAESK

66.4
18.5
54.4
K-KEXRU
417.2 96.8
KARDIA K 414.6 414.4
284 287 414.7 QES/H K 411.0
148 102
AZEMLA1
500.0 MW
-500.1 MW TUR
GRE
KARACQOU
250 416.3
50.0

GIS REGIONAL MODEL - AVERAGE HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2010 SENSITIVITY CASE - IMPORT 1500 MW BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 5.1.2 - Power flows along interconnection lines in the region for 2010-sensitivity case-average hydrology-import 1500 MW scenario

5.5
Table 5.1.2 - Power flows along regional interconnection lines for 2010-sensitivity case-average hydrology-import 1500
MW scenario

Power Flow
% of thermal
Interconnection line
rating
MW Mvar
OHL 400 kV Zemlak (ALB) Kardia (GRE) -283.7 -148.0 24
OHL 220 kV Fierze (ALB) Prizren (SER) 36.1 45.9 21
OHL 220 kV V.Dejes (ALB) Podgorica (MON) -46.0 -1.3 16
OHL 400 kV V.Dejes (ALB) Podgorica (MON) -144.6 -27.5 11
OHL 400 kV Ugljevik (B&H) Ernestinovo (CRO) 40.3 -60.6 6
OHL 400 kV Mostar (B&H) Konjsko (CRO) 81.4 -50.3 7
OHL 400 kV Ugljevik (B&H) S. Mitrovica (SER) -120.9 17.9 10
OHL 400 kV Trebinje (B&H) Podgorica (MON) 218.2 78.7 19
OHL 220 kV Trebinje (B&H) Plat (CRO) -104.8 40.1 36
OHL 220 kV Prijedor (B&H) Mraclin (CRO) 38397 -17.2 7
OHL 220 kV Prijedor (B&H) Medjuric (CRO) 40.5 -16.3 13
OHL 220 kV Gradacac (B&H) Djakovo (CRO) 58.9 17.9 21
OHL 220 kV Tuzla (B&H) Djakovo (CRO) 104.6 35.8 36
OHL 220 kV Mostar (B&H) Zakucac (CRO) 61.2 -14.0 19
OHL 220 kV Visegrad (B&H) Vardiste (SER) -14.0 59.1 20
OHL 220 kV Sarajevo 20 (B&H) Piva (MON) -73.6 -17.7 19
OHL 220 kV Trebinje (B&H) Perucica (MON) 103.7 13.4 33
OHL 400 kV Blagoevgrad (BUL) Thessaloniki (GRE) 67.7 -48.6 12
OHL 400 kV M.East 3 (BUL) Filippi (GRE) 314.9 -40.0 44
OHL 400 kV M.East 3 (BUL) Babaeski (TUR) -119.9 4.2 11
OHL 400 kV M.East 3 (BUL) Hamitabat (TUR) -149.5 9.3 10
OHL 400 kV C.Mogila (BUL) Stip (MCD) 223.5 -38.2 32
OHL 400 kV Dobrudja (BUL) Isaccea (ROM) 198.6 -45.6 15
OHL 2x400 kV ckt.1 Kozloduy (BUL) Tantarena (ROM) -113.5 -23.8 9
OHL 2x400 kV ckt.2 Kozloduy (BUL) Tantarena (ROM) -113.5 -23.8 9
OHL 400 kV Sofia West (BUL) Nis (SER) 409.7 128.1 60
OHL 2x400 kV ckt.1 Zerjavinec (CRO) Heviz (HUN) -51.1 -69.8 6
OHL 2x400 kV ckt.2 Zerjavinec (CRO) Heviz (HUN) -51.1 -69.8 6
OHL 2x400 kV ckt.1 Ernestinovo (CRO) Pecs (HUN) -126.8 -31.1 10
OHL 2x400 kV ckt.2 Ernestinovo (CRO) Pecs (HUN) -126.8 -31.1 10
OHL 2x400 kV ckt.1 Tumbri (CRO) Krsko (SLO) -270.6 42.5 24
OHL 2x400 kV ckt.2 Tumbri (CRO) Krsko (SLO) -270.6 42.5 24
OHL 400 kV Melina (CRO) Divaca (SLO) -87.0 73.5 12
OHL 400 kV Ernestinovo (CRO) S.Mitrovica (SER) -139.2 38.6 12
OHL 220 kV Zerjavinec (CRO) Cirkovce (SLO) -95.0 29.5 32
OHL 220 kV Pehlin (CRO) Divaca (SLO) -10.5 26.3 11
OHL 400 kV Dubrovo (MCD) Thessaloniki (GRE) -66.3 -42.2 6
OHL 400 kV Bitola (MCD) Florina (GRE) -10.1 -65.6 5
OHL 400 kV Skopje (MCD) Kosovo B (UNMIK) 51.2 43.6 8
OHL 2x220 kV ckt.1 Skopje (MCD) Kosovo A (UNMIK) 7.6 -20.7 7
OHL 2x220 kV ckt.2 Skopje (MCD) Kosovo A (UNMIK) 7.6 -20.7 7
OHL 400 kV Arad (ROM) Sandorfalva (HUN) 73.1 -26.9 14
OHL 400 kV - Nadab (ROM) Bekescaba (HUN) 87.5 -39.4 8
OHL 400 kV Rosiori (ROM) Mukacevo (UKR) -452.1 22.0 38
OHL 400 kV Portile De Fier (ROM) Djerdap (SER) 159.5 53.1 12
OHL 400 kV Subotica (SER) Sandorfalva (HUN) -163.4 -127.7 17
OHL 400 kV Ribarevine (MON) Kosovo B (UNMIK) -38.0 12.2 5
OHL 220 kV Pljevlja (MON) Bajina Basta (SER) -73.1 5.8 24
OHL 220 kV Pljevlja (MON) Pozega (SER) 30.9 31.4 17

5.6
45
40
35
30

Frequency
25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.1.3 - Histogram of interconnection lines loadings for 2010-sensitivity case-average hydrology-import
1500 MW scenario ("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

Table 5.1.3 - Network elements loaded over 80% of thermal limits for 2010-sensitivity case-average hydrology-import
1500 MW scenario

LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB OHL 110 kV AFIERZ5-AFARRZ5 61.7 68.0 90.7
BUL OHL 220 kV M.EAST-ST.ZAGORA 188.8 228.6 82.6
Transformers
TR 220/110 kV AFIER 2-AFIER 5 ckt.1 117.1 120.0 97.6
ALB TR 220/110 kV AFIER 2-AFIER 5 ckt.2 96.0 90.0 106.6
TR 220/110 kV AFIER 2-AFIER 5 ckt.3 91.6 90.0 101.8
ROM TR 220/110 kV FUNDENI-FUNDE2B 173.9 200.0 86.9

400
350
300
Frequency

250
200
150
100
50
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.1.4 - Histogram of 400 kV and 220 kV regional lines loadings for 2010-sensitivity case-average hydrology-
import 1500 MW scenario ("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal
limit)

5.7
5.1.2 Voltage Profile in the Region

Voltage profile in the region within this scenario which is defined by given generation pattern and
power import is seen as satisfactory despite several appearances of certain bus voltage deviations.
The deviations are shown in Table 5.1.4, which includes only 400 kV and 220 kV network buses.

Table 5.1.4 - Bus voltage deviations for 2010-sensitivity case-average hydrology-import 1500 MW scenario, complete
network
Country Node Voltages
pu kV
ALBANIA - - -
BOSNIA AND HERZEGOVINA - - -
400 kV VARNA4 1.052 420.8
400 kV MARITSA EAST2 1.053 421.0
400 kV DOBRUD4 1.052 420.7
220 kV SESTRIMO 1.104 242.8
220 kV BPC_220 1.101 242.2
220 kV AEC_220 1.102 242.4
BULGARIA 220 kV TECVARNA 1.103 242.7
CROATIA - - -
MACEDONIA - - -
MONTENEGRO - - -
ROMANIA - - -
SERBIA AND UNMIK - - -

Bus voltage magnitudes which are found below permitted limits (90% Vnominal in 220 kV network
and 95% Vnominal in 400 kV network) are not detected in the analyzed scenario. Bus voltage
magnitudes that are found above permitted limits (110% Vnominal in 110 kV and 220 kV networks
and 105% Vnominal in 400 kV network) are detected only in Bulgaria, where tree 400 kV buses and
four 220 kV buses have the magnitudes slightly above permitted limits. Figure 5.1.5 shows
histogram of voltages in monitored 400 kV and 220 kV substations.

120
100
Frequency

80
60
40
20
0
x<0.9

x>1.1
0.9<x<0.95

1.05<x<1.1
0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

Bin

Figure 5.1.5 - Histogram of voltages in monitored substations for 2010-sensitivity case-average hydrology-import
1500 MW scenario ("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

5.8
It should be emphasized that these results represent only a situation when additional devices
(transformer automatic tap changers, switchable shunts, etc.) are not used for voltage regulation.
Impacts of such devices, which exist in many points of the SEE regional transmission network,
need more comprehensive and thorough analysis.

5.1.3 Security (n-1) analysis

Results of security (n-1) analysis for the 2010-sensitivity case-average hydrology-import 1500 MW
scenario are presented in Tables 5.1.5 - 5.1.6.

Insecure system situations for given generation pattern and power import are detected in the power
systems of Albania, Bulgaria, Romania and Serbia.

Loss of 220 kV line between the Rrashbul and Tirana substations can cause overloading of 220 kV
line between the Elbassan and Fier substations in Albania. The opposite case is also found critical.

Loss of 400 kV line in Bulgaria, M.East 2-Bourgas can cause overloading of 400 kV line Plovdiv-
M. East 3. Loss of 220 kV line M. East 2-G.Oryahovitsa can cause overloading of 220 kV line M.
East 2-St. Zagora.

Single outages of 400/110 kV transformers in the stations Brasov and Dirste in Romania are also
found critical, since in the model the second transformer 400/110 kV in the Brasov substation is
permanently switched out of operation.

Loss of OHL 220 kV in the Belgrade area can cause overloading of the parallel line. Loss of 220
kV line between pumped storage power plant Bajina Basta and SS Pozega is also found critical.
Loss of one 400/110 kV transformer in the Nis substation is critical due to possible overloading of
the other parallel one but this problem could be solved by dispatcher intervention.

Figure 5.1.6 shows geographical positions of critical elements in the analyzed scenario. A green
colour reveals 220 kV elements (line 220 kV or transformer 220/x kV), while a red one reveals 400
kV elements (line 400 kV or transformer 400/x kV).

According to the obtained and presented results, it may be concluded that certain reinforcements in
the internal networks of Romania, Bulgaria, Albania and Serbia are necessary shall this generation
pattern and 1500 MW of power import be made more secure. None of the identified congestions is
located at the border lines.

By comparing the average hydrology situation in 2010 and balanced SE Europe power system to
the average hydrology situation and 1500 MW of power import, it may be noticed that some critical
contingencies in the Romanian power system disappear, especially those connected with Mintia
substation, while some new contingencies appear in the power system of Bulgaria (lines around
Maritsa East substation). This is due to different dispatching conditions of DEVA 1 power plant in
Romania (disconnected in import/export scenario, dispatched with 850 MW in the base case) and
power import through Turkish-Bulgarian interface that goes through Maritsa East 3 substation.

5.9
Table 5.1.5 - Lines overloadings for 2010-sensitivity case-average hydrology-import 1500 MW scenario, single outages
Outage Overloaded line(s) Loadings Country
MVA %
OHL 220 kV AKASHA2-ARRAZH2 OHL 220 kV AELBS12-AFIER 2 254.8 116.3 ALBANIA
OHL 220 kV AELBS12-AFIER 2 OHL 220 kV AKASHA2-ARRAZH2 263.3 100.6
OHL 400 kV BURGAS-MI_2_400 OHL 400 kV PLOVDIV4-MI_400 762.3 107.4 BULGARIA
OHL 220 kV G_ORIAH-MI_2_220 OHL 220 kV MI_2_220-ST.ZAGORA 255.0 104.2
OHL 220 kV JBGD172-JBGD8 22 ckt.1 OHL 220 kV JBGD172-JBGD8 22 ckt.2 438.3 122.9 SERBIA
OHL 220 kV JBBAST2-JPOZEG2 OHL 220 kV JPOZEG2-JVARDI22 294.0 100.0

Table 5.1.6 - Transformers overloadings for 2010-sensitivity case-average hydrology-import 1500 MW scenario, single
outages
Outage Overloaded branch(es) Loadings Country
MVA %
TR 400/220 kV BUC.S ckt.1 TR 400/220 kV BUC.S ckt.2 407.4 101.9
400/110 kV BRASOV 400/110 kV DIRSTE 343.9 137.5 ROMANIA
400/110 kV DIRSTE 400/110 kV BRASOV 340.6 136.2
400/110 kV NIS ckt.1 400/110 kV NIS ckt.2 304.8 101.6 SERBIA

SVK

AUT
HUN

SLO ROM

CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE
400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 5.1.6 - Geographical positions of the critical elements for 2010-sensitivity case-average hydrology-import 1500
MW scenario

5.10
5.2 Scenario 2010 – average hydrology – high load

This part of the Study presents the results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as GTmax run for year 2010 - average hydrology – high load and with new generation facilities
implemented. High load conditions denotes high load growth rate scenario. This scenario (higher
growth rate) is analyzed in order to evaluate network performance for "heavy" load conditions.

5.2.1 Lines loadings

Figure 5.2.1 shows power exchanges between areas for 2010-average hydrology high load scenario.
Power flows along interconnection lines in the region together with balances of the systems are
shown in Figure 5.2.2. Area totals are shown in Table 5.2.1 and comparison of the average hydro
regimes with normal load projection and high load projection is shown in
Table 5.2.2. As it can be seen, increase of load level for around 3.61% on regional level, causes
network losses to rise for up to 177 MW or 24%. This is consequence of higher network load and
somewhat lower voltage levels.
Figure 5.2.3 shows histogram of tie lines loadings. It can be concluded that the most of the tie lines
are loaded less than 25% of their thermal limits.

SVK UKR
450

7
45
7

AUT
17
3

HUN
12
8
49

SLO
72

ROM
31

ITA
26
4

CRO 239
56
2

5
11

BIH 267 SRB


306
15

6 306
31
4

MNG BUL
5
10
145
1

10

85
MKD
170

TUR
ALB 10
30
38
0

GRE

Figure 5.2.1 - Area exchanges in analyzed electric power systems for 2010-average hydrology high load scenario –
2010 topology

5.11
GABICK1400.0 LEVIC 1400.0

CENTREL

251
116

200
140
450.0 MW
346 350
MAISA 7 UZUKRA01
804 297

UCTE OWIEN 1 MGYOR 4


0
25 .6
714.7 772.5

222.2 MW
UKR
405.5 101 101
93

94.5
199
23.6 102 MSAJI 408.1 35.5 35.7
403.5 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 402.4 OWIEN 2 MGOD 4 407.6 226.3
20.8 27.6
450.0 MW
10.8 10.7

43.2

44.3
49.7
44.3
49.7
158
MGYOR 2 MTLOK 2
51.0 50.5 7.6 29.2
234.2 230.5 224.4
6.1 21.1
ONEUSI2 UMUKACH
233.5 21.5 21.4 229.0 82.7 82.9 6.7
MSAJO 4
13.0 26.9 67.4 49.6 55.
410.0 412.0 8

HUN
-1249.9 MW

18. 3

18. 3
6

4
156

44.

44.
39.

6.9
118
LPODLO2229.7 LMARIB1 403.6 89.1 89.2
MBEKO 4 NADAB
MHEVI 4 409.4 62.8 81.1 ROSIORI 403.9
LDIVAC1 403.9 401.1
215.0 MW

61.5
35.2
61.5
35.2
IRDPV111

SLO
170 170
48.3 27.3 84
401.3 402.6 77 .8 MPECS 4 409.1 MSAFA 4 401.7
.5
LKRSKO1 402.7 LCIRKO2 228.4 39.0 39.0 ARAD
LDIVAC2 .2
72 38

21 .2

21 .2
0.1 59.1

46.7

46.7

17.9
17.9
170

170

.8

.8
IPDRV121 1 399.4

46

46
26.8 26.8 30
50.7 54.3 23 .9
231.2 230.5 .7

ROM
ISACCEA 409.3

3
84.9
53.8

46 0.9
.4 .4

88.4
46.

309
61 .3 61 .3
-56.8 MW

72.5
70 .3

162
72 72

.9
ERNESTIN

17 8.1
MELINA 406.1 ZERJAVIN 405.9 JSOMB31
393.1 JSUBO31 395.6

.9
ZERJAVIN 229.6 239 240
JSMIT21
31.0

17 1

17 1
55.6 97.6

22

22
13.9

406.2

0
.

65.0
5.9
TUMBRI 403.5 DAKOVO 225.2

65 213
PEHLIN 232.9 MRACLIN 226.5MEDURIC 226.4

43.3
27.4

84.3
45.0

.6
401.8

52.1
18.8

4.0
2.5
JHDJE11 P.D.FIE
115 115
26.2 25.2 TANTAREN 413.7
403.1 403.2

CRO

46.4

46.4
2.2

2.2
213

43. 2

65. 0
22.

63.
-1095.9 MW 32.1

85 .5
5

2
10.9
52 .5

4.0

40
26

.3
.4 GRADACAC 228.0 UGLJEVIK 403.8

SCG
PRIJED2 225.5 TE TUZL 233.2

VISEGRA JVARDI22
561.3 MW

25.7
53.7 54.0 229.3

312
231.4

2. 2

2. 2
65.2 66.7

4.

4.
BIH

2
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 414.9 DOBRUD4 418.2
307 309 141.1 MW 231.1 159 160 234.9 CRG 724.2 MW JNIS2 1 304 307 SOFIA_W4
406.5
3.0 46.2
406.8
12.8 12.8
-163.0 MW 394.3
154 113
411.1
HE ZAKUC 132 134 MO-4 RP TREB JHPERU21
14.8 15.2 27.8 27.7 228.5
232.2 234.0 231.9
19.3 27.4

BUL
46.0 46.2
RP TREB JPODG211 JLESK21
97.5 139 JPODG121227.5
401.1 0.000
858.0 MW

25.8
62.6
JPRIZ22
224.6 JTKOSA2
227.1JTKOSB1406.8

27.1
3.7
392.9

44 106
.9

11. 4

11. 4

122
41.3
17.

17.
JVRAN31

6
0.000

27.2
5.4

43 05
.0
25.8
89.1

1
AVDEJA1 AVDEJA2
388.8 228.1AFIERZ2227.9 C_MOGILA

11.5
28.0
11.5
28.0
122
6.3
25.8
89.1
.5
SK 1 223.1 SK 4
407.3 408.2 85 .2
47 413.1

-261.0 MW STIP 1 .3
85 .7

MKD
BITOLA 2 416.3
412.1
45

BLAGOEV413.8 MI_3_4_1 419.7


25.5

DUBROVO 412.2
128

22.5
49.1
5
11 .7

44. 3
AKASHA1 381.7

4
31.1
38.7

4. 5.
19
0.7 1
.6

54.

1
0 1
ALB
-484.0 MW .5
22 .2

31.
0.7

65.5

5. .5
46

4.0

91
2 4HAMITAX

8
19 6.8

4
AHS_FLWR417.5 LAGAD K 414.1 FILIPPOI 7 4.0 4.0 415.4
9.7 9.7 65.5 76.8
396.2 4BABAESK

31.1
23.4
22.0
K-KEXRU
417.9 71.1
KARDIA K 415.7 415.6
378 383 416.6 QES/H K 413.1
158 130
AZEMLA1
0.0 MW
-0.1 MW TUR
GRE
KARACQOU
250 419.0
50.0

GIS REGIONAL MODEL - AVERAGE HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2010 HIGH LOAD - NEW GENERATION - TOPOLOGY 2010 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 5.2.2 - Power flows along interconnection lines in the region with balances of the systems for 2010-average hydrology high load scenario – 2010 topology

5.12
Table 5.2.1 - Area totals in analyzed electric power systems for 2010- average hydrology high load scenario –
2010 topology
AREA GENERATION LOAD LOSSES INTERCHANGE
ALBANIA 931.7 1358 57.7 -484
BULGARIA 7282.5 6278 146.5 858
BIH 2202.8 2004 57.8 141.1
CROATIA 2254.6 3295 55.4 -1095.9
MACEDONIA 991.1 1234 18.1 -261
ROMANIA 7113.3 6859.4 310.6 -56.7
SERBIA 8103.8 7131 248.6 724.2
MONTENEGRO 542.3 686 19.2 -163
TOTALS 29422.1 28845.4 913.9 -337.3

Table 5.2.2 – Comparison of Area totals in analyzed electric power systems for 2010- average hydrology versus average
hydrology high load scenario – 2010 topology
LOAD LOSSES
AREA normal normal
high load high load
load load
ALBANIA 1287.3 1358 5.49% 50.4 57.7 14.48%
BULGARIA 5977.3 6278 5.03% 121.6 146.5 20.48%
BIH 1971.3 2004 1.66% 58.6 57.8 -1.37%
CROATIA 3136.7 3295 5.05% 49 55.4 13.06%
MACEDONIA 1198.2 1234 2.99% 20.1 18.1 -9.95%
ROMANIA 6728.3 6859.4 1.95% 201.2 310.6 54.37%
SERBIA 6873.1 7131 3.75% 220.8 248.6 12.59%
MONTENEGRO 669.2 686 2.51% 15.5 19.2 23.87%
TOTALS 27841.4 28845.4 3.61% 737.1 913.9 23.99%

Histogram
45
40
35
30
Frequency

25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.2.3 - Histogram of interconnection lines loadings for 2010- average hydrology high load scenario –
2010 topology ("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

Table 5.2.3 shows all network elements loaded over 80% of their thermal limits. As it can be seen
some lines 220 kV voltage level in Albania, Romania and Serbia are loaded over 80%. Also, most
of the elements loaded over 80% are transformers in some substations, again, in Albania, Romania
and Serbia. Figure 5.2.4 shows histogram of branch loadings in the system.

5.13
As for the conclusion regarding thermal loadings in this scenario it can be said that most of the
network elements are loaded up to 75% of their thermal limits, but there are some elements highly
loaded, even overloaded. It can be concluded that overall load of the system is higher than by
normal load projection. Higher load-demand level causes that increase of load of the elements
which supply large consumption areas are is higher than increase of load-demand level. This goes
especially for transformer units over which large consumption areas are connected to high voltage
network. Also, most of the elements loaded over 80% are transformers in some substations, and
loading of these elements is higher than in case of normal load projection. There are some elements
that are overloaded (220 kV lines Targu Jiu – Paroseni and Urechesti-Targu Jiu in Romania, and
220/110 kV transformers in Fier substation in Albania), and this load is higher than in case of
normal load projection. Like in previous scenarios analyzed, higher engagement of TPP Paroseni
resolves this overloads of the 220 kV lines Targu Jiu – Paroseni and Urechesti-Targu Jiu and
decreases the load of the 400/220 transformer in Urechesti substation. Also, it is expected that
transformers in Fierza substation will be replaced with more powerful transformer units.

Table 5.2.3 - Network elements loaded over 80% of their thermal limits for 2010-average hydrology high load scenario
– 2010 topology
BRANCH LOADINGS ABOVE 80.0 % OF RATING:
LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
HL 220kVP.D.F.A-RESITA 1 226.8 277.4 81.7
HL 220kVP.D.F.A-RESITA 2 226.8 277.4 81.7
ROM
HL 220kVTG.JIU-PAROSEN 1 277.8 208.1 133.5
HL 220kVURECHESI-TG.JIU 1 277.8 277.4 100.1
Transformers
TR 220/110 kV AFIER 1 122.2 120 101.8
ALB TR 220/110 kV AFIER 2 100.1 90 111.3
TR 220/110 kV AFIER 3 95.6 90 106.2
TR 400/220 kV URECHE 1 344.4 400 86.1
ROM
TR 220/110 kV FUNDE2 1 178.6 200 89.3
TR 220/110 kV JTKOSA 2 131.5 150 87.7
TR 220/110 kV JTKOSA 3 133.9 150 89.3
SRB
TR 220/110 kV JZREN2 2 120.2 150 80.1
TR 400/220 kV JBGD8 1 326.3 400 81.6

Histogram
350

300

250
Frequency

200

150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.2.4 - Histogram of branch loadings for 2010- average hydrology high load scenario – 2010 topology
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

5.14
5.2.2 Voltage Profile in the Region

Figure 5.2.5 shows histogram of voltages in monitored substations. Voltages in almost all
monitored substations are found within permitted limits. Voltage profile in network of Albania is
somewhat near low limits, but this can be resolved by changing of the setting of the tap changing
transformers in some substations. Also, voltage levels are somewhat lower comparing to normal
load projection scenario. Higher load of network elements, which is consequence of the higher
demand level, causes voltage drops along network elements to be higher.

Histogram

120

100

80
Frequency

60

40

20

0
x<0.9

0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

x>1.1

Bin

Figure 5.2.5 - Histogram of voltages in monitored substations for 2010- average hydrology high load scenario –
2010 topology ("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

5.2.3 Security (n-1) analysis

Results of security (n-1) analysis for 2010-average hydrology high load scenario and expected
topology for 2010 are presented in Table 5.2.4. Figure 5.2.6 shows the geographical position of the
critical elements in monitored systems.

It can be concluded that all identified insecure situations are located in internal networks that belong
to monitored power systems of Albania, Romania and Serbia. In most critical case in Romanian
system, the critical elements are 220 kV lines Targu Jiu – Paroseni and Urechesti-Targu Jiu and
400/220 kV transformer in Urechesti substation, but these elements are overloaded in case of full
topology also, which is the main reason why they appear as critical by most outages analyzed. As it
has been stated before, this can be resolved by higher engagement of the TPP Paroseni. Compared
to the normal load projection (chapter 4.1) it can be concluded that the critical elements are almost
the same. The only difference is overload of the 400/110 kV transformer unit in SS Pancevo. This is
cosequence of higher load of these transformers in full network topology compared to the normal
demand scenario.

5.15
Like by normal demand scenario (chapter 4.1), some of the overloadings identified can be relieved
by certain dispatch actions (splitting busbars, changing lower voltage network topology in order to
redistribute load-demand or change of generation units engagement).

All in all, certain reinforcement of internal network is necessary in order to make this regime more
secure. Especially, taking into consideration that higher demand causes higher load of transformer
units in whole monitored region.
Table 5.2.4 - Network overloadings for 2010- average hydrology high load scenario , single outages – 2010 topology
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
BASE CASE RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 285.6MVA 133.5%
AL OHL 220kV AELBS12 -AFIER 2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 289.9MVA 112.2%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 301.5MVA 106.1%
RO OHL 220kV P.D.F.A -RESITA 1 RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 331.5MVA 122.8%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 301.5MVA 141.4%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 295.7MVA 103.9%
RO OHL 220kV RESITA -TIMIS 1 RO HL 220kV RESITA-TIMIS 2 277.4MVA 348.7MVA 127.0%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 295.7MVA 138.5%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.3MVA 104.8%
RO OHL 220kV PESTIS -MINTIA A 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 290.4MVA 139.7%
RO OHL 220kV CLUJ FL -AL.JL 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 271MVA 126.4%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 308.8MVA 109.1%
RO OHL 220kV AL.JL -GILCEAG 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 308.8MVA 145.4%
RO OHL 400kV TANTAREN-URECHESI 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 292.5MVA 102.6%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 300.1MVA 105.9%
RO OHL 400kV TANTAREN-BRADU 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 300.1MVA 141.1%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 331.1MVA 117.3%
RO OHL 400kV TANTAREN-SIBIU 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 331.1MVA 156.4%
RO OHL 400kV URECHESI-P.D.FIE 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 268.7MVA 124.5%
RO TR 400/220kV/kV URECHESI 1 400MVA 400.6MVA 100.1%
RO OHL 400kV URECHESI-DOMNESTI 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 305.6MVA 107.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 305.6MVA 143.6%
RO OHL 400kV MINTIA -ARAD 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 263.1MVA 123.1%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 326.2MVA 115.5%
RO OHL 400kV MINTIA -SIBIU 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 326.2MVA 153.9%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.2MVA 104.0%
RO OHL 400kV DOMNESTI-BRAZI 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 296.2MVA 138.7%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.9MVA 104.5%
RO OHL 400kV SMIRDAN -GUTINAS 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 296.9MVA 139.3%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.3MVA 104.3%
RO OHL 400kV BRASOV -BRADU 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 296.3MVA 139.0%
CS OHL 220kV JBGD172 -JBGD8 22 1 CS HL 220kV JBGD172-JBGD8 22 2 365.8MVA 453.5MVA 129.0%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 300.9MVA 106.1%
CS OHL 400kV JBOR 21 -JHDJE11 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 300.9MVA 141.4%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 315.8MVA 111.9%
CS OHL 400kV JHDJE11 -JTDRMN1 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 315.8MVA 149.1%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 304.1MVA 107.2%
CS OHL 400kV JNSAD31 -JSUBO31 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 304.1MVA 142.8%
RO TR 400/110 BRASOV 1 RO TR 400/110kV/kV DIRSTE 1 250MVA 353.9MVA 141.6%
RO TR 400/110 DIRSTE 1 RO TR 400/110kV/kV BRASOV 1 250MVA 350MVA 140.0%
CS TR 400/110 JNIS2 1 CS TR 400/110kV/kV JNIS2 1 2 300MVA 323.1MVA 107.7%
CS TR 400/110 JPANC2 1 CS TR 400/110kV/kV JPANC21 2 300MVA 318.8MVA 106.3%

5.16
SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE 400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 5.2.6 – geographical position of critical elements for 2010- average hydrology high load scenario –
2010 topology

5.17
5.3 Scenario 2015 – average hydrology – import/export – 2010 topology

This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as Scenario 2015 – sensitivity case – average hydrology – import 1500 MW – topology 2010.

Concerning the import/export case, the simulated regime means the following:

▪ Import 750 MW from UCTE


▪ Import 500 MW from Turkey
▪ Export 500 MW to Greece
▪ Import 750 MW from Ukraine

Calculations on the model characterized by the 2010 network topology, appropriate GTMax
generation dispatch, predicted load level in 2015 and power import/export as explained above,
could not lead to a convergent load flow solution due to reactive power problems. Lack of reactive
power in the analyzed situation is visible especially in the power system of Albania.

If the power plants reactive limits are ignored in the model, a convergent solution is found and the
following can be concluded:

▪ There is a permanent lack of reactive power for analyzed generation dispatch, load level
and power import/export in the power system of Albania. Generators in power plants
Balsh, Fierza and Vau Dejes exceed their Var limits in order to keep nominal voltages.
This proves the necessity to install compensation devices or new power plants in the
Albanian power system, or to construct new interconnection lines to make network
connections stronger.

▪ Generators in Bulgarian power system, which are dispatched in the analyzed scenario
and whose reactive power limits are exceeded, are operated mostly in the under-
excitation area below their minimum Var limits. This means that there is a sufficient
reactive power reserve, but problems with high voltages may be expected especially in
lower bus loading conditions (nights, summer).

▪ Reactive power problems in the analyzed situation are not detected in the power systems
of Bosnia and Herzegovina, Croatia and Macedonia.

▪ In the power system of Romania, the generator Var limits are occasionally exceeded in
both directions (some generators work in the over-excitation area and some in the under-
excitation one) in order to achieve scheduled (mostly nominal) voltages in the analyzed
situation. The Var limits are not significantly exceeded when observing all dispatched
generators in Romania.

▪ Certain lack of reactive power is visibly present in the power system of Serbia and
UNMIK. Ten power plants are operated slightly above their maximum Var limits.

▪ Smaller lack of reactive power also exists in the power system of Montenegro that is
affected by the poor voltage profile in Albania.

5.18
To provide deeper insight into the voltage problems which are obviously present in the analyzed
export/import scenario in 2015, but on the network topology predicted to exist in 2010, it is
necessary to conduct more comprehensive and thorough analysis. It is assumed that the utilisation
of existing devices such as transformer automatic tap changers and switchable shunts, or the
generation re-dispatch may mitigate these voltage problems without a need to construct new lines.

If new interconnection lines predicted to exist in 2015 are included in the model, Vranje (Serbia) –
Skopje 4 (Macedonia), Zemlak (Albania) – Bitola 2 (Macedonia), and V. Dejes (Albania) – Kosovo
B (UNMIK), a convergent solution is found. Power flow solution is explained in the following
Chapter.

A convergent solution for the 2010 network topology is found when only 400 kV line V.Dejes
(Albania) – Kosovo B (UNMIK) is included in the model, but without satisfactory network voltage
profile. Two 400 kV nodes in Albania (Elbassan and Tirana) and five 400 kV nodes in Romania
(Domnesti, Dirste, Brazi, Brasov, Bradu) have small voltage values (between 374 kV and 379 kV).
Two 220 kV nodes in Albania (Fier and Babic) have also small voltage values (193 kV and 196 kV
respectively). Sixty two 110 kV nodes, mostly in Albania, have low voltages, ranging between 80
kV and 99 kV.

Convergent solution on network topology in 2010 is found also if only 400 kV line Zemlak
(Albania) – Bitola (Macedonia) is included on the model, but voltage profile in the network is
unsatisfactory again. Two 400 kV nodes in Albania (Elbassan and Tirana) and five 400 kV nodes in
Romania (Domnesti, Dirste, Brazi, Brasov, Bradu) have small voltage values (between 373 kV and
379 kV). Two 220 kV nodes in Albania (Fier and Babic) have small voltage values also (192 kV
and 195 kV respectively). Seventy five 110 kV nodes, mostly in Albania, have low voltages,
ranging between 78 kV and 99 kV.

To conclude, the analyzed scenario which is characterized by large power import in 2015, but on
the 2010 network topology, can not be supported from a transmission network viewpoint due to
voltage problems. Their existence is the most obvious in the power system of Albania due to scarce
reactive power sources. To mitigate such problems it is necessary to construct at least one new 400
kV interconnection line between Albania and UNMIK or Macedonia.

5.19
5.4 Scenario 2015 – average hydrology – import/export – 2015 topology

This part of the Study presents results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as Scenario 2015 – sensitivity case – average hydrology – import 1500 MW – topology 2015.

5.4.1 Lines loadings

Area totals and power exchanges for the 2015-sensitivity case-average hydrology-import 1500
MW-topology 2015 scenario are shown in Figure 5.4.1. Power flows along interconnection lines in
the region together with balances of the systems are shown in Figure 5.4.2. Area totals are shown in
Table 5.4.1. Table 5.4.2 shows power flows along regional interconnection lines for 2015-
sensitivity case-average hydrology-import 1500 MW-topology 2015 scenario

SVK
UKR
4 50

0
68

5 20
AUT
3
61

HUN
62
61
4

SLO
1
8

ITA ROM
17
82
9

CRO 175
36
3

BIH 245 SRB


390

3 36
88

20

MNT BUL
28

162
26

2
88

7
21
MKD
352

ALB TUR
217

7 212
28
65

GRE
2 50

Figure 5.4.1 - Area exchanges in analyzed electric power systems for 2010-sensitivity case-average hydrology-import
1500 MW-topology 2015 scenario

5.20
Table 5.4.1 - Area totals in analyzed electric power systems for 2015-sensitivity case-average hydrology-import 1500
MW-topology 2015 scenario
Country Generation Load Bus Shunt Line Shunt Losses Net Interchange
(MW) (MW) (Mvar) (Mvar) (MW) (MW)
Albania 1027.5 1544.0 0 0 71.5 -588.0
Bulgaria 7582.2 6418.9 0 14.6 142.7 1006.0
Bosnia and Herzegovina 2394.9 2293.8 0 0 70.1 31.0
Croatia 2173.9 3660.1 0 0 58.8 -1545.0
Macedonia 1076.3 1393.7 0 0 22.5 -340.0
Romania 7187.7 7831.2 0 74.6 253.9 -972.0
Serbia and UNMIK 8029.8 7270.7 0 14.1 215.1 530.0
Montenegro 731.9 675.0 0.6 1.8 15.6 39.0
TOTAL - SE EUROPE 30204.2 31087.4 0.6 105.0 850.3 -1839.0

By comparing the average hydrology situation in 2015 and balanced SE Europe power system to
the average hydrology situation and 1500 MW of power import, a significant increase of the power
flows is noticed along the Slovenian-Croatian and Ukrainian-Romanian interfaces. However, the
interconnection lines are not jeopardized since their loading levels fall far below their thermal
ratings. In the same time, power flows through other interfaces between countries in the SE Europe
are mostly decreased.

Power losses, in comparison to the situation of balanced SE Europe power system, are increased
only in the power system of Macedonia (5%). In other power systems power losses are decreased,
the most significantly in the power systems of Romania (-26%) and Montenegro (-23%). Power
losses are decreased (-16%) in the region when analyzing the additional power import.

Figure 5.4.3 shows that all tie lines in the region are loaded less than 50% of their thermal limits for
the analyzed import/export scenario in year 2015. Among total number of fifty two 400 kV and 220
kV interconnection lines in the region only ten are loaded between 25% and 50% of their thermal
ratings. Other tie lines are loaded less than 25% of their thermal ratings.

Table 5.4.3 lists all network elements loaded over 80% of their thermal limits. As it can be seen
from this output list, most of the elements loaded over 80% are transformers in some substations
and internal 110 kV and 220 kV lines. 110 kV lines which are loaded over 80% Ithermal are not
shown in the table. Certain internal network reinforcements are necessary to sustain given load-
demand level and production pattern including import of 1500 MW from analyzed directions.

Figure 5.4.4 shows histogram of 400 kV and 220 kV regional internal lines and 400/x kV and 220/x
kV transformers loadings. Some 40% of observed branches are loaded below 25% of their thermal
ratings, 36% are loaded between 25% and 50%, 20% are loaded between 50% and 75% and 5% of
observed branches are loaded between 75% and 100% of their thermal ratings. Four branches
(transformers 220/110 kV Fierze in Albania, 102% - 106% Sn and 220/110 kV transformer in
Fundeni substation in Romania) are overloaded when all branches are in operation.

By comparing the average hydrology situation in 2015 and balanced SE Europe power system to
the average hydrology situation and 1500 MW of power import, it is noticed that power system of
Romania becomes slightly relieved while some highly loaded branches are present in the power
systems of Albania, Serbia and Bulgaria. Distribution of internal branches loading is slightly
changed because a number of branches loaded between 25% and 75% of their thermal ratings is
increased compared to the situation characterized by balanced SE Europe power system.

5.21
GABICK1400.0 LEVIC 1400.0

CENTREL

251
102

200
140
450.0 MW
346 350
MAISA 7 UZUKRA01
805 296

UCTE OWIEN 1 MGYOR 4 714.7 772.5


0
25 .7
974.2 MW
UKR
404.4 244 243
79

94.3
199
38.8 78.8 MSAJI 408.2 35.8 35.9
402.9 MKISV 2 UMUKACH2
OOBERS2236.5 OKAINA1 399.7 OWIEN 2 MGOD 4 407.6 226.3
21.0 27.7
1200.0 MW
11.0 10.9

38.7

55.0

55.0
218

121

121
MGYOR 2 MTLOK 2
74.5 73.5 7.6 29.2
233.3 230.5 224.4
1.5 13.7
ONEUSI2 UMUKACH
232.6 41.0 40.7 228.4 318 321 510
MSAJO 4
8.1 21.1 32.6 52.6 66.
410.0 412.0 5

-1250.0 MW
HUN

3
214

121

121
21.

25.

25.

68.
504
LPODLO2227.8 LMARIB1 400.9 6.0 6.1
MBEKO 4 NADAB

9
MHEVI 4 407.2 58.5 77.6 ROSIORI 400.5
LDIVAC1 403.5 400.5
215.0 MW

77.9
17.8
77.9
17.8
IRDPV111

SLO
108 108
25.4 3.4 10
400.6 400.8 60 7 MPECS 4 407.7 MSAFA 4 401.6
.1
LKRSKO1 399.9 LCIRKO2 226.3 18.6 18.6 ARAD
LDIVAC2 .0
33 22

35 .5

35 .5
4.7 54.7

31.6

31.6

75.5
13.0
265

265

.4

.4
IPDRV121 1 399.3

25

25
49.9 49.9 37
63.7 67.1 14 .5
230.3 229.3 .2

ROM
ISACCEA 401.3

5
36.9
107

25 4.1
.7 .7

88.3
25.

391
77 .8 77 .8
-972.0 MW

32.8
84 .5

147
86 86

.1
ERNESTIN

74 6.5
MELINA 402.4 ZERJAVIN 401.3 JSOMB31
393.2 JSUBO31 395.8

.8
ZERJAVIN 225.7 148 149
JSMIT21
37.4

26 5

26 5
25.3 74.3

11

11
4.6

403.5

5
.

13.8
6.5
TUMBRI 399.8 DAKOVO 221.8

31 204
PEHLIN 229.8 MRACLIN 220.8MEDURIC 218.6

51.8
27.5

99.5
47.5

.1
400.5

16.0
11.8

11.1
5.9
JHDJE11 P.D.FIE
2.1 2.1
31.2 32.3 TANTAREN 410.2
402.1 402.0

CRO

28.5
76.6
28.5
76.6
204

52. 8

13. 5
22.

63.
-1545.0 MW 2.8

8
16 .2

5.9

45
10 3
3.2
20
.0 GRADACAC 224.7 UGLJEVIK 400.3

.
1
SCG
PRIJED2 219.6 TE TUZL 230.8

VISEGRA JVARDI22
28.8 28.9 231.2 569.0 MW

396
232.5

3.9
28 .1

28 .1
27

27
38.7 41.1

BIH

.5

.5
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 413.2 DOBRUD4 413.8
227 228 31.0 MW 230.8 156 158 237.3 CRG 530.0 MW JNIS2 1 302 305 SOFIA_W4
404.4
21.9 30.6
405.9
34.2 34.1
39.0 MW 398.3
107 62.6
410.0

14.1 32.7
181 181
HE ZAKUC 112 113 MO-4 RP TREB JHPERU21
6.7 10.9 42.0 41.8 229.9
231.0 233.2 232.6
11.2 19.0

BUL
0.6 0.7
RP TREB JPODG211 JLESK21
43.1 87.8 JPODG121229.2
404.3 398.6
1006.0 MW

33.3

32.7 32.8
37.2 74.4
4.6
JPRIZ22
222.9 JTKOSA2
227.3JTKOSB1408.0

9.8
5.6
399.6

.8 9
37 6.

11. 3

11. 3

218
5.8
1

22.

22.
JVRAN31

3
401.8
290 0

15.2

61.8
59.9
289

9.7

29 7.1
47.

.0
33.3
23.9
68.7

1
AVDEJA1 AVDEJA2
399.4 227.7AFIERZ2227.9

.2 9
C_MOGILA

14 1.
11.1
32.8
11.1
32.8

47.0

6
217
78.7

78.7
111

111
7
19 0
SK 1 222.5 SK 4
404.5 404.8 . 411.6
36

-340.0 MW STIP 1 6
19 .0

MKD
BITOLA 2 412.0
408.7
47

BLAGOEV412.2 MI_3_4_1 418.0


DUBROVO 408.8
111
119
111
119

50.5
53.9
280 1
7 1. 58

48. 1
AKASHA1 392.6 39.

8
61.0
50.9

12 .6
29
184
9

102

1
7
ALB
-588.0 MW .4
50 .9

82.
184

73.9

15 .7
39

128

97
9 4HAMITAX

9
28 6.7

5
AHS_FLWR415.3 LAGAD K 412.2 128 128 414.0
75 9
.7

FILIPPOI 5
27

214 214 73.9 84.4


406.4 4BABAESK

61.1
55.6
K-KEXRU
417.2 98.8

9.8
KARDIA K 414.6 414.3
58.6 59.0 415.4 QES/H K 411.2
111 40.8
AZEMLA1
500.0 MW
-500.2 MW TUR
GRE
KARACQOU
250 416.7
50.0

GIS REGIONAL MODEL - AVERAGE HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 SENSITIVITY CASE - IMPORT 1500 MW - TOPOLOGY 2015 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 5.4.2 - Power flows along interconnection lines in the region for 2015-sensitivity case-average hydrology-import 1500 MW-topology 2015 scenario

5.22
Table 5.4.2 - Power flows along regional interconnection lines for 2015-sensitivity case-average hydrology-import 1500
MW-topology 2015 scenario
Power Flow % of thermal
Interconnection line
MW Mvar rating
OHL 400 kV Zemlak (ALB) Kardia (GRE) -58.6 -110.9 9
OHL 220 kV Fierze (ALB) Prizren (SER) 17.1 29.0 14
OHL 220 kV V.Dejes (ALB) Podgorica (MON) -9.7 -15.2 6
OHL 400 kV V.Dejes (ALB) Podgorica (MON) 33.3 -23.9 3
OHL 400 kV Ugljevik (B&H) Ernestinovo (CRO) -13.8 -63.5 5
OHL 400 kV Mostar (B&H) Konjsko (CRO) 228.5 -30.6 17
OHL 400 kV Ugljevik (B&H) S. Mitrovica (SER) -203.8 -2.8 16
OHL 400 kV Trebinje (B&H) Podgorica (MON) -0.6 43.1 7
OHL 220 kV Trebinje (B&H) Plat (CRO) -104.8 40.0 36
OHL 220 kV Prijedor (B&H) Mraclin (CRO) 16.0 -20.2 8
OHL 220 kV Prijedor (B&H) Medjuric (CRO) 5.9 3.2 4
OHL 220 kV Gradacac (B&H) Djakovo (CRO) 52.0 22.8 20
OHL 220 kV Tuzla (B&H) Djakovo (CRO) 100.8 45.3 37
OHL 220 kV Mostar (B&H) Zakucac (CRO) 113.4 -10.9 36
OHL 220 kV Visegrad (B&H) Vardiste (SER) -28.8 38.7 16
OHL 220 kV Sarajevo 20 (B&H) Piva (MON) -156.5 -34.2 41
OHL 220 kV Trebinje (B&H) Perucica (MON) 42.0 11.2 15
OHL 400 kV Blagoevgrad (BUL) Thessaloniki (GRE) 50.5 -53.9 10
OHL 400 kV M.East 3 (BUL) Filippi (GRE) 290.6 -48.8 41
OHL 400 kV M.East 3 (BUL) Babaeski (TUR) -127.3 -1.6 12
OHL 400 kV M.East 3 (BUL) Hamitabat (TUR) -158.4 1.9 10
OHL 400 kV C.Mogila (BUL) Stip (MCD) 197.4 -36.0 28
OHL 400 kV Dobrudja (BUL) Isaccea (ROM) 396.1 3.9 29
OHL 2x400 kV ckt.1 Kozloduy (BUL) Tantarena (ROM) 28.5 27.1 6
OHL 2x400 kV ckt.2 Kozloduy (BUL) Tantarena (ROM) 28.5 27.1 6
OHL 400 kV Sofia West (BUL) Nis (SER) 304.5 62.6 44
OHL 2x400 kV ckt.1 Zerjavinec (CRO) Heviz (HUN) -77.7 -86.8 9
OHL 2x400 kV ckt.2 Zerjavinec (CRO) Heviz (HUN) -77.7 -86.8 9
OHL 2x400 kV ckt.1 Ernestinovo (CRO) Pecs (HUN) -25.5 -84.1 7
OHL 2x400 kV ckt.2 Ernestinovo (CRO) Pecs (HUN) -25.5 -84.1 7
OHL 2x400 kV ckt.1 Tumbri (CRO) Krsko (SLO) -264.6 11.5 23
OHL 2x400 kV ckt.2 Tumbri (CRO) Krsko (SLO) -264.6 11.5 23
OHL 400 kV Melina (CRO) Divaca (SLO) -106.6 22.8 11
OHL 400 kV Ernestinovo (CRO) S.Mitrovica (SER) -148.4 25.3 12
OHL 220 kV Zerjavinec (CRO) Cirkovce (SLO) -74.8 6.5 25
OHL 220 kV Pehlin (CRO) Divaca (SLO) -37.4 4.6 12
OHL 400 kV Dubrovo (MCD) Thessaloniki (GRE) -61.0 -50.9 5
OHL 400 kV Bitola (MCD) Florina (GRE) -183.9 -101.9 17
OHL 400 kV Skopje (MCD) Kosovo B (UNMIK) -216.8 -47.0 16
OHL 2x220 kV ckt.1 Skopje (MCD) Kosovo A (UNMIK) -11.1 -32.8 11
OHL 2x220 kV ckt.2 Skopje (MCD) Kosovo A (UNMIK) -11.1 -32.8 11
OHL 400 kV Arad (ROM) Sandorfalva (HUN) -18.6 -54.7 5
OHL 400 kV - Nadab (ROM) Bekescaba (HUN) 6.1 -77.6 6
OHL 400 kV Rosiori (ROM) Mukacevo (UKR) -503.9 -68.9 43
OHL 400 kV Portile De Fier (ROM) Djerdap (SER) -2.1 -32.3 2
OHL 400 kV Subotica (SER) Sandorfalva (HUN) -32.8 -147.1 11
OHL 400 kV Ribarevine (MON) Kosovo B (UNMIK) -148.4 -17.0 11
OHL 220 kV Pljevlja (MON) Bajina Basta (SER) -11.3 9.6 9
OHL 220 kV Pljevlja (MON) Pozega (SER) 75.9 40.3 29
OHL 400 kV* Skopje 4 (MCD) Vranje (SER) 61.9 14.2 6
OHL 400 kV* Zemlak (ALB) Bitola (MCD) -279.2 -75.7 21
OHL 400 kV* V.Dejes (ALB) Kosovo B (UNMIK) -289.3 -68.7 22
* new lines planned till 2015

5.23
45
40
35
30
Frequency
25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.4.3 - Histogram of interconnection lines loadings for 2015-sensitivity case-average hydrology-import 1500
MW-topology 2015 scenario ("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal
limit)

Table 5.4.3 - Network elements loaded over 80% of thermal limits for 2015-sensitivity case-average hydrology-import
1500 MW-topology 2015 scenario

LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB OHL 220 kV AKASHA2-ARRAZH2 235.7 270.0 87.3
OHL 220 kV MI_2_220-ST ZAGORA 191.0 228.6 83.5
BUL
OHL 400 kV PLOVDIV4-MI_400 605.2 692.8 87.4
OHL 220 kV BRADU-TIRGOVI 246.9 302.6 81.6
ROM OHL 220 kV P.D.F.A-CETATE1 204.3 208.1 98.2
OHL 220 kV BUC.S-B-FUNDENI 266.0 320.0 83.1
SRB OHL 220 kV JBGD3 21-JOBREN2 277.4 301.0 92.2
Transformers
TR 220/110 kV AFIERZ2-AFIERZ5 ckt.1 50.9 60.0 84.8
TR 220/110 kV AFIERZ2-AFIERZ5 ckt.2 50.9 60.0 84.8
TR 220/110 kV ABURRE2-ABURRL5 ckt. 1 49.1 40.0 81.8
TR 220/110 kV ABURRE2-ABURRL5 ckt. 2 49.1 40.0 81.8
TR 220/110 kV ABURRE2-ABURRL5 ckt. 3 49.1 40.0 81.8
TR 220/110 kV AELBS12-AELBS15 ckt.1 74.0 90.0 82.2
ALB TR 220/110 kV AELBS12-AELBS15 ckt.2 74.0 90.0 82.2
TR 220/110 kV AELBS12-AELBS15 ckt.3 79.5 90.0 88.3
TR 220/110 kV AKASHA2-AKASH25 ckt.1 82.9 100.0 82.9
TR 220/110 kV AKASHA2-AKASH25 ckt.2 82.9 100.0 82.9
TR 220/110 kV AFIER 2-AFIER 5 ckt.1 130.7 120.0 108.9
TR 220/110 kV AFIER 2-AFIER 5 ckt.2 107.1 90.0 119.0
TR 220/110 kV AFIER 2-AFIER 5 ckt.3 102.2 90.0 113.6
B&H TR 400/110 kV UGLJEVIK 256.3 300.0 85.4
TR 400/110 kV BRASOV 202.5 250.0 81.0
ROM TR 220/110 kV FUNDENI 181.0 200.0 90.5
TR 220/110 kV FUNDENI-FUNDE2B 214.4 200.0 107.2
TR 220/110 kV JBGD3 21-JBGD 351 169.4 200.0 84.7
SRB TR 220/110 kV JBGD3 22-JBGD 352 126.8 150.0 84.5
TR 220/110 kV JZREN22-JZREN25 121.5 150.0 81.0

5.24
350

300

250

Frequency
200

150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.4.4 - Histogram of 400 kV and 220 kV regional branches loadings for 2015-sensitivity case-average
hydrology-import 1500 MW-topology 2015 scenario ("Frequency" denotes number of lines and "Bin" denotes loading
range in % of thermal limit)

5.4.2 Voltage Profile in the Region

Voltage profile in the region within this scenario which is defined by given generation pattern and
power import is seen as satisfactory because there are no voltages outside permitted limits. Figure
5.4.5 shows histogram of voltages in monitored 400 kV and 220 kV substations.

100
90
80
70
Frequency

60
50
40
30
20
10
0
x<0.9

x>1.1
0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

Bin

Figure 5.4.5 - Histogram of voltages in monitored substations for 2015-sensitivity case-average hydrology-import
1500 MW-topology 2015 scenario ("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

5.25
5.4.3 Security (n-1) analysis

Results of security (n-1) analysis for the 2015-sensitivity case-average hydrology-import 1500
MW-topology 2015 scenario are presented in Tables 5.3.4 - 5.3.5.

Insecure system situations for given generation pattern and power import are detected in the power
systems of Albania, Bulgaria, Bosnia and Herzegovina, Croatia, Romania and Serbia. Some
possible actions for transmission system relief during certain contingency cases are previously
described while the transformer overloadings in Zerjavinec (Croatia), Nis and Pancevo (Serbia)
substations may be removed by system operator actions.

Figure 5.4.6 shows geographical positions of critical elements in the analyzed scenario. A green
colour reveals 220 kV elements (line 220 kV or transformer 220/x kV), while a red one reveals 400
kV elements (line 400 kV or transformer 400/x kV).

According to the obtained and presented results, it may be concluded that certain reinforcements in
the internal networks of Romania, Bulgaria, Albania and Serbia are necessary shall this generation
pattern and 1500 MW of power import be made more secure. None of the identified congestions is
located at the border lines.

Table 5.4.4 - Lines overloadings for 2015-sensitivity case-average hydrology-import 1500 MW scenario-topology 2015,
single outages
Loadings
Outage Overloaded line(s) Country
MVA %
OHL 220 kV AELBS12-AFIER 2 OHL 220 kV AKASHA2-ARRAZH2 351.1 136.4 ALBANIA
OHL 400 kV BURGAS-MI_2_400 OHL 400 kV PLOVDIV4-MI_400 742.9 104.9
OHL 220 kV G_ORIAH-MI_2_220 OHL 220 kV MI_2_220-ST.ZAGORA 255.1 105.0 BULGARIA
OHL 400 kV VISEGRA-HE VG OHL 220 kV RP KAKAN-KAKANJ5 335.1 102.3 B&H
OHL 400 kV TANTAREN-BRADU OHL 220 kV BUC.S-B-FUNDENI 312.8 103.4
OHL 400 kV DOMNESTI-BRAZI OHL 220 kV BUC.S-B-FUNDENI 319.8 103.1
OHL 220 kV P.D.F.A-CALAFAT OHL 220 kV P.D.F.A-CETATE1 257.9 125.0
OHL 220 kV P.D.F.A-RESITA ckt.1 OHL 220 kV P.D.F.A-RESITA ckt.2 273.3 100.9
OHL 220 kV FUNDENI-BUC.S-B OHL 220 kV BUC.S-B-FUNDENI 342.7 110.2
TR 400/220 kV ROSIORI OHL 400 kV GADALIN-CLUJ E 242.2 105.7 ROMANIA
OHL 220 kV BRADU-TIRGOVI 285.9 105.9
TR 400/220 kV BRAZI
OHL 220 kV BUC.S-B-FUNDENI 355.6 118.4
TR 400/220 kV JBGD8 ckt.2 OHL 220 kV JBGD3 21-JOBREN2 307.4 104.7
OHL 220 kV JBGD3 21-JOBREN2 329.2 112.9
TR 400/220 kV JBGD8 ckt.1
OHL 220 kV JBGD3 22-JBGD8 22 373.7 107.3
OHL 400 kV JBGD8 1-JOBREN11 OHL 220 kV JBGD3 21-JOBREN2 468.7 167.2
OHL 400 kV JHDJE11-JTDRMN1 OHL 220 kV JBGD3 21-JOBREN2 321.3 109.1
OHL 400 kV JPANC21-JTDRMN1 OHL 220 kV JBGD3 21-JOBREN2 302.0 103.1
OHL 220 kV JBBAST2-JBGD3 21 OHL 220 kV JBGD3 21-JOBREN2 304.8 103.6 SERBIA
OHL 220 kV JBGD3 22-JBGD8 21 OHL 220 kV JBGD3 21-JOBREN2 300.2 102.0
OHL 220 kV JBGD172-JBGD8 22 ckt.1 OHL 220 kV JBGD172-JBGD8 22 ckt.2 464.7 132.6

5.26
Table 5.4.5 - Transformer overloadings for 2015-sensitivity case-average hydrology-import 1500 MW scenario-
topology 2015, single outages
Loadings
Outage Overloaded branch(es) Country
MVA %
OHL 400 kV BLUKA 6-TS TUZL TR 400/110 kV UGLJEVIK 302.7 100.9 B&H
TR 400/110 kV ZERJAVIN ckt.1 TR 400/110 kV ZERJAVIN ckt.2 300.8 100.3 CROATIA
OHL 400 kV BRASOV-DIRSTE TR 400/110 kV BRASOV 253.8 101.5
OHL 220 kV BUC.S-B-FUNDENI TR 400/220 kV BRAZI 418.6 104.6
TR 400/220 kV BUC.S ckt.1 TR 400/220 kV BUC.S ckt.2 505.1 126.3
TR 400/110 kV BRASOV TR 400/110 kV DIRSTE 434.5 173.8 ROMANIA
TR 400/110 kV DIRSTE TR 400/110 kV BRASOV 423.8 169.5
TR 400/110 kV NIS ckt.1 TR 400/110 kV NIS ckt.2 304.8 101.6
SERBIA
TR 400/110 kV PANCEVO ckt.1 TR 400/110 kV PANCEVO ckt.2 305.8 101.9

SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE
400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 5.4.6 – Geographical positions of the critical elements for 2015-sensitivity case-average hydrology-import
1500 MW-topology 2015 scenario

5.4.4 Summary of Impacts - 2015 topology versus 2010 topology

Compared to the expected topology 2010, analyzed in previous chapter, it can be seen that planned
investments make analyzed generation, demand and power import scenario feasible. This scenario
could not be solved on 2010 topology because lack of reactive power support especially in the
power system of Albania. Construction of at least one new interconnection line from Albania
(V.Dejes or Zemlak) to UNMIK (Kosovo B) or Macedonia (Bitola) makes this scenario feasible but
voltage profile in Albania, Montenegro and Serbia is poor. If all planned new lines are in operation
voltage profile is satisfactory but some internal reinforcements will be necessary to make this
generation pattern and power import more secure.

5.27
5.5 Scenario 2015 – average hydrology – high load – 2010 topology
This part of the Study presents the results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as GTmax run for year 2015 - average hydrology high load and expected network topology for
2010 with new generation facilities implemented.

5.5.1 Lines loadings

Figure 5.5.1 shows power exchanges between areas for 2015-average hydrology high load scenario
and 2010 topology. Power flows along interconnection lines in the region together with balances of
the systems are shown in Figure 5.5.2. Area totals are shown in Table 5.5.1 and comparison of the
average hydro regimes with normal load projection and high load projection is shown in Table
5.5.2. Difference of load-demand level for these two regimes for 2015 is around 8.11% on regional
level. As a consequence of this high load level, network losses are increased by 262 MW or 25%.
Further differences are explained in detail in following chapter.

SVK UKR
450

8
39

52
AUT
16
1

HUN
62
60

180

SLO
3

ITA ROM
12
27
5

CRO 318
97
8

43

BIH 249 SRB


883
61

5 109
31
5

MNG BUL
7
20
849
28
7

59

63
MKD
30

TUR
ALB
169

59
38
9

GRE

Figure 5.5.1 - Area exchanges in analyzed electric power systems for 2015-average hydrology high load scenario –
topology 2010

Figure 5.5.3 shows histogram of tie lines loadings. It is concluded that most of the tie lines are
loaded less than 50% of their thermal limits, but there are some that are loaded up to 75% of their
thermal limit like the 220 kV line from Pizren (Serbia-UNMIK)-Fierza (Albania).

5.28
GABICK1400.0 LEVIC 1400.0

CENTREL

251
106

200
124
450.0 MW
346 350
MAISA 7 UZUKRA01
813 282

UCTE OWIEN 1 MGYOR 4 712.0 772.5


0
25 .7
221.2 MW
UKR
405.2 89.3 89.2
83

77.9
199
21.5 104 MSAJI 408.1 35.5 35.7
403.1 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.0 OWIEN 2 MGOD 4 406.4 226.2
20.1 26.9
450.0 MW
10.8 10.7

52.3

44.9
37.8
44.9
37.8
156
MGYOR 2 MTLOK 2
50.6 50.1 7.3 28.9
234.1 230.4 224.4
6.6 21.6
ONEUSI2 UMUKACH
233.4 21.3 21.2 228.8 24.1 24.2 53.
MSAJO 4
13.5 27.3
410.0
73.1 46.0
412.0 276 3

HUN
-1249.8 MW

6.7 9

6.7 9
6
153

44.

44.
48.

50. 5
31
LPODLO2228.5 LMARIB1 401.7 4.2 3.9
MBEKO 4 NADAB

9
MHEVI 4 407.1 155 170 ROSIORI 382.8
LDIVAC1 392.1 384.5
215.0 MW

46.1
15.9
46.1
15.9
IRDPV111

SLO
175 175
29.1 49.8 82
400.7 400.1 7. .7 MPECS 4 406.7 MSAFA 4 391.4
8
LDIVAC2 LKRSKO1 399.7 LCIRKO2 226.6 0 58.4 58.1 ARAD
18 9 77.6 130

62 08

62 08
12.1

12.1
161

161

7.8
0.6

.6

.6
IPDRV121 15 381.3

1
9.3 9.4 9.
83.4 86.8 4. 9
230.0 228.8 9

ROM
ISACCEA 387.7

82.8
15.8
.0 .0

108

421
123
10 08
46 .8 46 .8
-1039.9 MW

180
177
89 89

1
10 8
ERNESTIN

8
7. .4
MELINA 399.9 ZERJAVIN 401.3 JSOMB31
381.7 JSUBO31 384.7

10
8
ZERJAVIN 226.1 317 319
JSMIT21

16 4

16 4
88.6 119

12

12
15.0
9.9

401.6

1
.

52.8
156
TUMBRI 399.2 DAKOVO 220.6

41 188
PEHLIN 228.0 MRACLIN 222.0MEDURIC 221.3

52.6
27.7

47.7
100

.6
395.6

49.4
32.1

22.5
5.2
JHDJE11 P.D.FIE
43.1 43.1
50.8 51.8 TANTAREN 402.8
395.8 395.6

CRO

228
113
228
113
187

52. 2
23.

157
-1447.8 MW 7.8

103
22.5

8
13.0
49 .1

45
10 8
39

GRADACAC 223.6 UGLJEVIK 396.1


.8

.
2
SCG
PRIJED2 219.6 TE TUZL 229.7

VISEGRA JVARDI22
2639.2 MW

61.9
61.4 61.7 226.4

427
228.4

73
22 3
73
22 3
63.3 64.7

BIH

.
9
.
9
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 409.5 DOBRUD4 408.8
489 494 113.2 MW 225.4 264 234.3 CRG 2052.2 MW JNIS2 1 109 109 SOFIA_W4
393.0
2.9 5.6
396.9
45.3
587.0 MW 390.4
168 109
406.0
HE ZAKUC 185 191 MO-4 RP TREB JHPERU21
11.0 4.1 30.7 30.9 225.3
224.1 230.0 229.2
34.4 41.6

BUL
313 315
RP TREB JPODG211 JLESK21
103 125 JPODG121223.8
393.6 0.000
899.0 MW

210
131
JPRIZ22
224.7 JTKOSA2
230.2JTKOSB1419.8

77.5
26.3
387.2

15 210
.8

69. 8

69. 8

717
113
26.

26.
JVRAN31

3
0.000

76.7
31.4

1. 05
8
2
209
148
AVDEJA1 AVDEJA2
378.4 218.1AFIERZ2218.4 C_MOGILA

68.6
34.0
68.6
34.0

71.3
709
209
148
.1
SK 1 223.2 SK 4
408.2 407.8 63 .5
44 408.5

-617.0 MW STIP 1 .2
63 .4

MKD
BITOLA 2 413.9
408.8
47

BLAGOEV409.6 MI_3_4_1 417.4


DUBROVO 409.7
208
174

92.3
64.1
3
26 2 . 9

57. 2
AKASHA1 366.3

1
76.8
60.3

26 6.
12
92. 7
.3

88.

2
.2 5
1
ALB
-883.0 MW .6

92. 1
92 .4

67.

32 6.1
26.2
53.5
27

7
.9
2 4HAMITAX

0
AHS_FLWR415.9 LAGAD K 412.9 12 0.3 26.2 26.2 414.9
FILIPPOI 7
59.1 59.0 53.5 64.8
385.6 4BABAESK

76.7
23.6
K-KEXRU
417.7 72.2

0.0
KARDIA K 415.4 415.2
386 393 415.1 QES/H K 411.9
232 217
AZEMLA1
0.0 MW
-0.1 MW TUR
GRE
KARACQOU
250 418.2
50.0

GIS REGIONAL MODEL - AVERAGE HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 HIGH LOAD - NEW GENERATION - TOPOLOGY 2010 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 5.5.2 - Power flows along interconnection lines in the region with balances of the systems for 2015-average hydrology high load scenario – 2010 topology
5.29
Table 5.5.1 - Area totals in analyzed electric power systems for 2015-average hydrology high load scenario –
2010 topology
AREA GENERATION LOAD LOSSES INTERCHANGE
ALBANIA 896.1 1680 99 -883
BULGARIA 8157.8 7083 175.8 899
BIH 2479.4 2274 92.2 113.2
CROATIA 2591 3959 79.8 -1447.8
MACEDONIA 895 1489 23 -617
ROMANIA 7684.5 8269.8 454.5 -1039.8
SERBIA 10024.2 7635 337 2052.2
MONTENEGRO 1324.6 702 35.6 587
TOTALS 34052.6 33091.8 1296.9 -336.2

Table 5.5.2 - Comparison of Area totals in analyzed electric power systems for 2015- average hydrology versus average
hydrology high load scenario – 2010 topology
LOAD LOSSES
AREA normal normal
high load high load
load load
ALBANIA 1531 1680 9.73% 81.2 99 21.92%
BULGARIA 6483 7083 9.25% 150.7 175.8 16.66%
BIH 2279 2274 -0.22% 78.7 92.2 17.15%
CROATIA 3657 3959 8.26% 63.4 79.8 25.87%
MACEDONIA 1407 1489 5.83% 20 23 15%
ROMANIA 7317.4 8269.8 13.02% 347.4 454.5 30.83%
SERBIA 7263 7635 5.12% 268.7 337 25.42%
MONTENEGRO 671 702 4.62% 25 35.6 42.4%
TOTALS 30608.4 33091.8 8.11% 1035.1 1296.9 25.29%

Histogram
35

30

25
Frequency

20

15

10

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.5.3 - Histogram of interconnection lines loadings for 2015- average hydrology high load scenario – topology
2010 ("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

Following Table 5.5.3 lists all network elements loaded over 80% of their thermal limits. As it can
be seen large number of lines 220 kV voltage level in Albania, Romania and Serbia are loaded over
80%. It can be concluded that overall load level of the transmission network increased, especially in
parts of the network that supply major consumption areas (Tirana in Albania, Bucharest and
Timisoara in Romania, Belgrade in Serbia and Pristina in Serbia-UNMIK). Most of the elements
loaded over 80% are 220 kV lines in Romania, but also transformers in some substations that
supply the major consumption areas.

5.30
There are some elements that are overloaded (220 kV lines Targu Jiu – Paroseni and Urechesti –
Targu Jiu in Romania and 220/110 kV transformers in Fierza and Elbasan 1 substation in Albania,
and 400/220 kV and 220/110 kV transformers in Kosovo B and Kosovo A substations in Serbia-
UNMIK. This leads to conclusion that transmission network is not able to sustain this load-demand
level and this production pattern.

Table 5.5.3 - Network elements loaded over 80% of their thermal limits for 2015-average hydrology high load scenario
– 2010 topology
BRANCH LOADINGS ABOVE 80.0 % OF RATING:
LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB HL 220kV AKASHA2-ARRAZH2 1 287.7 270 106.6
HL 220kV BRADU-TIRGOVI 1 285.4 302.6 94.3
HL 220kV BUC.S-B-FUNDENI 1 309.4 320 96.7
HL 220kV FILESTI-BARBOSI 1 248.3 277.4 89.5
HL 220kV L.SARAT-FILESTI 1 241 277.4 86.9
HL 220kV P.D.F.A-CETATE1 1 207.2 208.1 99.6
HL 220kV P.D.F.A-RESITA 1 266.9 277.4 96.2
HL 220kV P.D.F.A-RESITA 2 266.9 277.4 96.2
ROM
HL 220kV P.D.F.II-CETATE1 1 271.1 277.4 97.7
HL 220kV PAROSEN-BARU M 1 227.6 277.4 82
HL 220kV RESITA-TIMIS 1 229.6 277.4 82.8
HL 220kV RESITA-TIMIS 2 229.6 277.4 82.8
HL 220kV TG.JIU-PAROSEN 1 320.7 208.1 154.1
HL 220kV URECHESI-TG.JIU 1 320.4 277.4 115.5
HL 400kV GADALIN-CLUJ E 1 208.4 238.3 87.5
SRB HL 220kV JBGD3 21-JOBREN2 1 291 301 96.7
Transformers
TR 220/110 kV ABURRE 1 49.5 60 82.5
TR 220/110 kV ABURRE 2 49.5 60 82.5
TR 220/110 kV ABURRE 3 49.5 60 82.5
TR 220/110 kV AELBS1 1 87.7 90 97.5
TR 220/110 kV AELBS1 2 87.7 90 97.5
TR 220/110 kV AELBS1 3 94.2 90 104.7
TR 220/110 kV AFIER 1 149 120 124.1
TR 220/110 kV AFIER 2 122.1 90 135.7
ALB TR 220/110 kV AFIER 3 116.5 90 129.5
TR 220/110 kV AFIERZ 1 58 60 96.7
TR 220/110 kV AFIERZ 2 58 60 96.7
TR 220/110 kV AKASHA 1 93.4 100 93.4
TR 220/110 kV AKASHA 2 93.4 100 93.4
TR 220/110 kV ARRAZH 1 87.7 100 87.7
TR 220/110 kV ARRAZH 2 87.7 100 87.7
TR 220/110 kV ATIRAN 2 97.5 120 81.3
TR 220/110 kV ATIRAN 3 102.2 120 85.2
BIH TR 400/110 kV UGLJEV 1 258.8 300 86.3
CRO TR 220/110 kV TESISA 1 178.8 200 89.4
TR 220/110 kV BARBOS 1 167.1 200 83.6
TR 220/110 kV FUNDE2 1 240.8 200 120.4
TR 220/110 kV FUNDEN 1 203.9 200 101.9
TR 220/110 kV TIMIS 1 171.7 200 85.9
TR 400/110 kV BRASOV 1 231.5 250 92.6
ROM TR 400/110 kV CLUJ E 1 208.4 250 83.4
TR 400/110 kV DIRSTE 1 221 250 88.4
TR 400/220 kV BUC.S 1 378.4 400 94.6
TR 400/220 kV BUC.S 2 378.4 400 94.6
TR 400/220 kV IERNUT 1 408.1 400 102
TR 400/220 kV URECHE 1 486.6 400 121.6
SRB TR 220/110 kV JBGD3 1 174.9 200 87.5
TR 220/110 kV JBGD3 2 137.1 150 91.4
TR 220/110 kV JPRIS4 1 137 150 91.3
TR 220/110 kV JPRIS4 2 137 150 91.3
TR 220/110 kV JTKOSA 2 151.3 150 100.9
TR 220/110 kV JTKOSA 3 154 150 102.7
TR 220/110 kV JZREN2 2 133.8 150 89.2
TR 400/110 kV JJAGO4 A 245.8 300 81.9
TR 400/220 kV JBGD8 1 332.2 400 83
TR 400/220 kV JTKOSB 1 411.6 400 102.9

5.31
Histogram
300

250

200

Frequency
150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.5.4 - Histogram of branch loadings for 2015-average hydrology high load scenario – 2010 topology
("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

5.5.2 Voltage Profile in the Region

Figure 5.5.5 shows histogram of voltages in monitored substations. Overall voltage profile is not
adequate. In most of the network, especially in major consumption areas of Albania and Romania,
voltages in some monitored substations are below limits. Using of voltage control devices (tap
changing transformers, shunt devices) in Albania and Romania is not analyzed, but especially
Albania, these devices have very limited abilities for improving voltage profile. All in all it can be
concluded that conditions in some parts of the transmission network in this regime are dangerously
close to voltage collapse.

Histogram

80
70

60
Frequency

50
40
30

20
10
0
x<0.9

x>1.1
0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

Bin

Figure 5.5.5 - Histogram of voltages in monitored substations for 2015-dry hydrology scenario – 2010 topology
("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

5.32
5.5.3 Security (n-1) analysis

Results of security (n-1) analysis for 2015-average hydrology high load scenario and expected
topology for 2010 are presented in Table 5.5.4. Figure 5.5.6 shows the geographical position of the
critical elements in monitored systems. As it can be seen, by lot of investigated contingencies,
insecure states are identified. Almost all elements that are loaded over 80% in base case (Table
5.5.3), represent critical elements in n-1 analyses. Furthermore, for lot of contingency cases (losing
of major interconnection and internal lines) results could not be presented because of mathematical
instability of the model. This indicates that all these cases are not feasible in reality, and that these
contingencies can lead to voltage collapse and partial black outs in some parts of the monitored
network.
Table 5.5.4 - Network overloadings for 2015-dry hydrology scenario , single outages – 2010 topology
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 263MVA 106.6%
RO TR 400/220kV/kV URECHESI 1 400MVA 483.6MVA 120.9%
RO HL 220kV LOTRU-SIBIU 1 277.4MVA 275.6MVA 102.1%
RO HL 220kV LOTRU-SIBIU 2 277.4MVA 275.6MVA 102.1%
BASE CASE RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 307.7MVA 115.5%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 298.9MVA 154.1%
CS TR 400/220kV/kV JTKOSB1 1 400MVA 432MVA 108.0%
CS TR 400/220kV/kV JTKOSB1 2 400MVA 451.4MVA 112.9%
CS TR 400/220kV/kV JTKOSB1 3 400MVA 451.4MVA 112.9%
AL OHL 220kV AVDEJA2 -ATIRAN2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 275.2MVA 123.9%
AL OHL 220kV ATIRAN2 -AKASHA2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 274.6MVA 111.1%
IN OHL 400kV KONJSKO -MO-4 1 HR HL 220kV XRA_ZA21-HE ZAKUC 1 297MVA 343.9MVA 115.1%
IN OHL 400kV ISACCEA -DOBRUD4 1 RO TR 400/220kV/kV URECHESI 1 400MVA 506.7MVA 126.7%
RO OHL 220kV STUPARE -BRADU 1 RO HL 220kV AREF-RIURENI 1 277.4MVA 252.6MVA 106.6%
RO OHL 220kV URECHESI-SARDANE 1 RO TR 400/220kV/kV URECHESI 1 400MVA 455.2MVA 113.8%
RO HL 400kV MINTIA-SIBIU 1 381.1MVA 387.2MVA 116.9%
RO HL 220kV P.D.F.A-RESITA 1 277.4MVA 269.1MVA 108.8%
RO OHL 220kV URECHESI-TG.JIU 1
RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 269.1MVA 108.8%
RO HL 220kV PESTIS-MINTIA A 1 277.4MVA 256.1MVA 105.5%
RO OHL 220kV P.D.F.A -CALAFAT 1 RO HL 220kV P.D.F.A-CETATE1 1 208.1MVA 259.6MVA 129.9%
RO TR 400/220kV/kV URECHESI 1 400MVA 504MVA 126.0%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 325.7MVA 123.6%
RO OHL 220kV P.D.F.A -RESITA 1
RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 355.4MVA 145.4%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 315.2MVA 165.0%
RO TR 400/220kV/kV URECHESI 1 400MVA 494.2MVA 123.6%
RO OHL 220kV RESITA -TIMIS 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 317.8MVA 119.9%
RO HL 220kV RESITA-TIMIS 2 277.4MVA 351.8MVA 136.8%
RO OHL 220kV CRAIOV A-TR. MAG 1 RO TR 400/220kV/kV URECHESI 1 400MVA 464.8MVA 116.2%
RO OHL 220kV CRAIOV B-ISALNI A 1 RO TR 400/220kV/kV URECHESI 1 400MVA 499.6MVA 124.9%
RO HL 400kV MINTIA-SIBIU 1 381.1MVA 386.7MVA 117.0%
RO HL 220kV P.D.F.A-RESITA 1 277.4MVA 269.1MVA 109.0%
RO OHL 220kV TG.JIU -PAROSEN 1
RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 269.1MVA 109.0%
RO HL 220kV PESTIS-MINTIA A 1 277.4MVA 257.2MVA 106.3%
RO TR 400/220kV/kV URECHESI 1 400MVA 507.3MVA 126.8%
RO OHL 220kV PESTIS -MINTIA A 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 326MVA 124.6%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 313.5MVA 166.4%
RO HL 400kV GADALIN-CLUJ E 1 238.3MVA 216.3MVA 101.8%
RO OHL 220kV MINTIA B-AL.JL 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.3MVA 111.1%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 288.2MVA 148.3%
RO HL 220kV BRADU-TIRGOVI 1 302.6MVA 273.6MVA 108.2%
RO OHL 220kV FUNDENI -BUC.S-B 1
RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 389.3MVA 134.8%
RO TR 400/220kV/kV URECHESI 1 400MVA 495.9MVA 124.0%
RO OHL 220kV STEJARU -GHEORGH 1
RO TR 400/220kV/kV IERNUT 1 400MVA 487.2MVA 121.8%
RO OHL 220kV GHEORGH -FINTINE 1 RO TR 400/220kV/kV IERNUT 1 400MVA 412.5MVA 103.1%
RO OHL 220kV CLUJ FL -MARISEL 1 RO TR 400/220kV/kV URECHESI 1 400MVA 497MVA 124.3%
RO TR 400/220kV/kV URECHESI 1 400MVA 471.7MVA 117.9%
RO OHL 220kV CLUJ FL -AL.JL 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 294.1MVA 110.1%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 286.3MVA 146.9%
RO TR 400/220kV/kV URECHESI 1 400MVA 514.1MVA 128.5%
RO OHL 220kV AL.JL -GILCEAG 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 333MVA 127.8%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 320.8MVA 170.6%
RO OHL 220kV BRAZI A-TELEAJEN 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 307.4MVA 105.4%
RO OHL 220kV TELEAJEN-STILPU 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 307.8MVA 105.6%
RO OHL 400kV TANTAREN-URECHESI 1 RO TR 400/220kV/kV URECHESI 1 400MVA 467.2MVA 116.8%
RO TR 400/220kV/kV URECHESI 1 400MVA 559.7MVA 139.9%
RO HL 220kV BRADU-TIRGOVI 1 302.6MVA 272.9MVA 104.1%
RO OHL 400kV TANTAREN-SLATINA 1
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 292.5MVA 112.9%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 284.5MVA 150.6%

5.33
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
RO TR 400/220kV/kV URECHESI 1 400MVA 451.1MVA 112.8%
RO OHL 400kV URECHESI-P.D.FIE 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 290.7MVA 108.8%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 282.7MVA 145.2%
RO TR 400/220kV/kV URECHESI 1 400MVA 551.6MVA 137.9%
RO HL 220kV BRADU-TIRGOVI 1 302.6MVA 274.9MVA 106.9%
RO OHL 400kV URECHESI-DOMNESTI 1
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 329.2MVA 125.9%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 318.2MVA 168.0%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 295.6MVA 113.4%
RO OHL 400kV MINTIA -ARAD 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 283.8MVA 151.7%
RO TR 400/220kV/kV URECHESI 1 400MVA 527.9MVA 132.0%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 355.6MVA 135.8%
RO OHL 400kV MINTIA -SIBIU 1 RO HL 220kV P.D.F.A-RESITA 1 277.4MVA 262.9MVA 103.9%
RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 262.9MVA 103.9%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 343.2MVA 181.2%
RO OHL 400kV P.D.FIE -SLATINA 1 RO TR 400/220kV/kV URECHESI 1 400MVA 518.9MVA 129.7%
RO OHL 400kV DOMNESTI-BUC.S 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 327.2MVA 110.4%
RO TR 400/220kV/kV URECHESI 1 400MVA 505.8MVA 126.4%
RO TR 400/220kV/kV BUC.S 1 400MVA 436MVA 109.0%
RO TR 400/220kV/kV BUC.S 2 400MVA 436MVA 109.0%
RO OHL 400kV DOMNESTI-BRAZI 1
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 323.6MVA 123.6%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 312.2MVA 165.0%
RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 374.2MVA 131.0%
RO OHL 400kV GR.IAL -L.SARAT 1 RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 304.5MVA 103.3%
RO OHL 400kV GR.IAL -CERNAV 1 RO HL 400kV GR.IAL-CERNAV 2 791.2MVA 775.9MVA 102.0%
RO OHL 400kV GR.IAL -CERNAV 2 RO HL 400kV GR.IAL-CERNAV 1 791.2MVA 773.4MVA 101.6%
RO OHL 400kV BACAU -ROMAN 1 RO TR 400/220kV/kV URECHESI 1 400MVA 493.8MVA 123.5%
RO TR 400/220kV/kV URECHESI 1 400MVA 498.6MVA 124.7%
RO HL 220kV BRADU-TIRGOVI 1 302.6MVA 304.9MVA 114.7%
RO OHL 400kV BRASOV -BRADU 1
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 319.2MVA 121.2%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 309MVA 161.7%
RO HL 400kV MINTIA-SIBIU 1 381.1MVA 345.1MVA 102.9%
RO OHL 400kV IERNUT -GADALIN 1
RO TR 400/220kV/kV IERNUT 1 400MVA 413.3MVA 103.3%
CS OHL 220kV JBBAST2 -JBGD3 21 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 314.9MVA 110.0%
CS OHL 220kV JBGD172 -JBGD8 22 1 CS HL 220kV JBGD172-JBGD8 22 2 365.8MVA 488.5MVA 144.0%
CS OHL 220kV JBGD3 22-JBGD8 21 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 308.5MVA 107.6%
CS OHL 220kV JBGD3 22-JBGD8 22 2 CS TR 400/220kV/kV JBGD8 1 1 400MVA 425.8MVA 106.5%
CS OHL 220kV JHIP 2 -JPANC22 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 296.7MVA 103.4%
CS TR 400/220kV/kV JTKOSB1 1 400MVA 443.8MVA 111.0%
CS OHL 220kV JLESK22 -JNIS 22 1 CS TR 400/220kV/kV JTKOSB1 2 400MVA 463.8MVA 115.9%
CS TR 400/220kV/kV JTKOSB1 3 400MVA 463.8MVA 115.9%
CS OHL 220kV JNSAD32 -JOBREN2 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 303.6MVA 105.2%
CS OHL 220kV JNSAD32 -JZREN22 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 303.6MVA 106.0%
CS OHL 220kV JOBREN2 -JVALJ32 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 291MVA 100.8%
CS OHL 220kV JTKOSA2 -JTKOSB2 1 CS HL 220kV JTKOSA2-JTKOSB2 2 365.8MVA 453.9MVA 119.0%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 490.7MVA 187.1%
CS OHL 400kV JBGD8 1 -JOBREN11 1
CS HL 220kV JBGD3 22-JBGD8 22 2 365.8MVA 337MVA 108.2%
CS OHL 400kV JBGD8 1 -JBGD201 A CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 298.4MVA 104.1%
CS OHL 400kV JBOR 21 -JHDJE11 1 RO TR 400/220kV/kV URECHESI 1 400MVA 494.5MVA 123.6%
RO TR 400/220kV/kV URECHESI 1 400MVA 496.6MVA 124.1%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 319.6MVA 121.0%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 309.6MVA 161.5%
CS OHL 400kV JNIS2 1 -JJAGO41 A
CS TR 400/220kV/kV JTKOSB1 1 400MVA 444.6MVA 111.1%
CS TR 400/220kV/kV JTKOSB1 2 400MVA 464.6MVA 116.1%
CS TR 400/220kV/kV JTKOSB1 3 400MVA 464.6MVA 116.1%
RO TR 400/220kV/kV URECHESI 1 400MVA 511.8MVA 128.0%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 331.7MVA 126.7%
CS OHL 400kV JNSAD31 -JSUBO31 1 RO HL 220kV P.D.F.A-RESITA 1 277.4MVA 266.3MVA 106.1%
RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 266.3MVA 106.1%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 320.3MVA 169.1%
RO TR 400/220kV/kV URECHESI 1 400MVA 501MVA 125.3%
CS OHL 400kV JOBREN12-JTKOLB1 A RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 323.4MVA 122.9%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 313MVA 164.0%
CS OHL 400kV JPANC21 -JTDRMN1 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 313MVA 110.1%
RO TR 400/220kV/kV URECHESI 1 400MVA 497MVA 124.2%
CS OHL 400kV JRPMLA1 -JSMIT21 1
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 318.6MVA 120.6%
BG TR 400/110 CAREVEC 1 BG TR 400/110kV/kV CAREVEC 2 275MVA 281.3MVA 102.3%
CS TR 400/110 JBGD20 A CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 289.5MVA 100.6%
CS TR 400/110 JKRAG2 1 CS TR 400/110kV/kV JKRAG21 2 300MVA 314.1MVA 104.7%
CS TR 400/110 JNIS2 1 CS TR 400/110kV/kV JNIS2 1 2 300MVA 353.3MVA 117.8%
CS TR 400/110 JPANC2 1 CS TR 400/110kV/kV JPANC21 2 300MVA 327.4MVA 109.1%
CS TR 400/220kV/kV JTKOSB1 1 400MVA 472.2MVA 118.1%
CS TR 400/110 JPEC A CS TR 400/220kV/kV JTKOSB1 2 400MVA 493.4MVA 123.4%
CS TR 400/220kV/kV JTKOSB1 3 400MVA 493.4MVA 123.4%
BG TR 400/110 PLOVDIV 1 BG TR 400/110kV/kV PLOVDIV4 2 275MVA 284.4MVA 103.4%
CS TR 400/220kV/kV JTKOSB1 1 400MVA 448.2MVA 112.0%
MK TR 400/110 SK 1 1 CS TR 400/220kV/kV JTKOSB1 2 400MVA 468.3MVA 117.1%
CS TR 400/220kV/kV JTKOSB1 3 400MVA 468.3MVA 117.1%
RO TR 400/110 SMIRDAN 1 RO HL 220kV L.SARAT-FILESTI 1 277.4MVA 302.2MVA 113.5%
RO TR 400/220 BRAZI 1 RO TR 400/220kV/kV BUC.S 1 400MVA 447MVA 111.8%
RO TR 400/220kV/kV BUC.S 2 400MVA 447MVA 111.8%
RO HL 220kV BRADU-TIRGOVI 1 302.6MVA 302.8MVA 123.3%
RO HL 220kV FUNDENI-BUC.S-B 1 320MVA 290.1MVA 104.0%

5.34
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
RO HL 220kV BUC.S-B-FUNDENI 1 320MVA 387.2MVA 138.6%
RO TR 400/220 BUC.S 1 RO TR 400/220kV/kV BUC.S 2 400MVA 577.8MVA 144.4%
CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 340.4MVA 120.3%
CS TR 400/220 JBGD8 1
CS HL 220kV JBGD3 22-JBGD8 22 2 365.8MVA 398.3MVA 118.3%
CS TR 400/220 JBGD8 2 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 315.3MVA 110.4%
CS TR 400/220kV/kV JTKOSB1 1 400MVA 447.5MVA 111.9%
CS TR 400/220 JNIS2 1 CS TR 400/220kV/kV JTKOSB1 2 400MVA 467.6MVA 116.9%
CS TR 400/220kV/kV JTKOSB1 3 400MVA 467.6MVA 116.9%
CS TR 400/220kV/kV JTKOSB1 2 400MVA 610MVA 152.5%
CS TR 400/220 JTKOSB 1
CS TR 400/220kV/kV JTKOSB1 3 400MVA 610MVA 152.5%
RO TR 400/220kV/kV URECHESI 1 400MVA 501.5MVA 125.4%
RO TR 400/220 MINTIA 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 323MVA 122.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 311.7MVA 163.7%
RO TR 400/220 SIBIU 1 RO TR 400/220kV/kV SIBIU 2 400MVA 490.9MVA 122.7%
RO TR 400/220kV/kV URECHESI 1 400MVA 518.8MVA 129.7%
RO TR 400/220 SLATINA 1
RO TR 400/220kV/kV SLATINA 2 400MVA 460.5MVA 115.1%

SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE 400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 5.5.6 – geographical position of critical elements for 2015-average hydrology high load scenario –
topology 2010

Some of these problems identified are connected to the problem of new generation units
implemented in the model. For some, there is great insecurity how these units will be connected to
the transmission network, especially in the case of new generation capacities in Kosovo B region
(Serbia-UNIMK). In this regime new 3000 MW generation capacity is analyzed. Problem of
feasible connection of such a large generation capacity is not in the scope of this study and separate
study, that will analyze this problem alone is necessary to give right answer to this question.

All in all, it can be concluded that this regime is not feasible without major reinforcement of
transmission network.

5.35
5.6 Scenario 2015 – average hydrology – high load – topology 2015
This part of the Study presents the results of static load flow and voltage profile analyses that are
conducted for complete network topology and (n-1) contingencies in the scenario which is denoted
as GTmax run for year 2015 - average hydrology high load scenario and expected network topology
for 2015 and new planned generation capacities implemented.

5.6.1 Lines loadings

Figure 5.6.1 shows power exchanges between areas for 2015-average hydrology high load scenario.
Power flows along interconnection lines in the region together with balances of the systems are
shown in Figure 5.6.2. Area totals are shown in Table 5.6.1 and comparison of the average hydro
regimes with normal load projection and high load projection is shown in Table 5.6.2. Difference of
load-demand level for these two regimes is around 8.11% on regional level. As a consequence of
this high load level, network losses are increased by 251 MW or 25%. Figure 5.6.3 shows
histogram of tie lines loadings. It is concluded that most of the tie lines are loaded less than 50% of
their thermal limits.

SVK UKR
450

9
38
61

AUT
17
3

HUN
89
49

175

SLO
1

ITA ROM
15
26
4

CRO 305
10
30

55

BIH 208 SRB


835
71

95
32
0

MNG BUL
1
68
691
91

56
7
MKD
32

TUR
ALB
170

56
7
23
57

GRE

Figure 5.6.1 - Area exchanges in analyzed electric power systems for 2015-average hydrology high load scenario –
2015 topology

As it can be seen, new elements that are expected to be build till 2015 cause totally different
distribution of power flows in the southern part of the region (Albania, FYR of Macedonia, Serbia
and Montenegro). Compared to the expected topology 2010, analyzed in previous chapter, it can be
seen that the network losses are decreased as a consequence of building of new elements for 2015
network topology, especially in the cases of Albania, Serbia and Montenegro. Overall reduction of
loses is around 39 MW.

5.36
GABICK1400.0 LEVIC 1400.0

CENTREL

251
107

200
125
450.0 MW
346 350
MAISA 7 UZUKRA01
813 282

UCTE OWIEN 1 MGYOR 4 712.1 772.5


0
25 .2
222.4 MW
UKR
405.2 98.4 98.3
84

78.7
199
22.2 103 MSAJI 408.1 35.5 35.7
403.1 MKISV 2 UMUKACH2
OOBERS2238.7 OKAINA1 401.0 OWIEN 2 MGOD 4 406.4 226.2
20.2 27.0
450.0 MW
10.8 10.7

52.2

41.7
37.7
41.7
37.7
155
MGYOR 2 MTLOK 2
52.4 51.9 7.3 28.9
234.1 230.4 224.4
6.3 21.2
ONEUSI2 UMUKACH
233.4 22.7 22.6 228.8 14.9 15.0 62.
MSAJO 4
13.1 27.0
410.0
73.9 45.3
412.0 264 4

HUN
-1249.9 MW

6.5 7

6.5 7
7
152

41.

41.
48.

60. 4
30
LPODLO2228.5 LMARIB1 401.8 18.3 18.0
MBEKO 4 NADAB

2
MHEVI 4 407.2 148 163 ROSIORI 383.9
LDIVAC1 392.7 385.4
215.0 MW

38.4
15.5
38.4
15.5
IRDPV111

SLO
178 178
28.4 49.1 91
400.7 400.1 7. .5 MPECS 4 406.9 MSAFA 4 392.0
6
LDIVAC2 LKRSKO1 399.8 LCIRKO2 226.6 5 71.0 70.7 ARAD
17 7 70.9 123

61 14

61 14
12.7

12.7
161

161

8.1
0.6

.1

.1
IPDRV121 15 382.4

1
10.1 10.2 12
83.3 86.6 5. .1
230.0 228.9 2

ROM
ISACCEA 388.6

91.6
15.9
.2 .2

114

411
123
11 07
38 .5 38 .5
-1040.2 MW

176
176
90 90

1
10 4
ERNESTIN

7
8. .4
MELINA 400.0 ZERJAVIN 401.4 JSOMB31
382.4 JSUBO31 385.4

10
1
ZERJAVIN 226.1 304 306
JSMIT21
12.1

16 8

16 8
81.8 114

11

11
15.2

401.9

1
.

50.7
167
TUMBRI 399.2 DAKOVO 220.7

38 157
PEHLIN 228.0 MRACLIN 222.1MEDURIC 221.3

55.3
27.4

47.2
104

.7
396.2

54.7
32.8

19.6
5.4
JHDJE11 P.D.FIE
55.4 55.4
74.2 75.2 TANTAREN 403.6
397.0 396.9

CRO

209
112
209
112
157

55. 9
22.

168
-1448.1 MW 3.0

100
19.5

6
13.2
55 .4

45
10 7
39
.2 GRADACAC 223.7 UGLJEVIK 396.7

.
5
SCG
PRIJED2 219.7 TE TUZL 229.8

VISEGRA JVARDI22
2638.9 MW

57.5
50.7 50.8 227.4

417
229.3

70
21 6
70
21 6
58.1 59.8

BIH

.
0
.
0
KONJSKO MO-4 SA 20 JHPIVA21 SRB AEC_400 410.0 DOBRUD4 409.2
507 513 112.9 MW 226.0 258 235.7 CRG 2051.9 MW JNIS2 1 95.1 95.5 SOFIA_W4
393.7
1.9 3.1
398.4
52.3
587.0 MW 396.5
125 60.8
407.1

67.6 67.6
14.1 34.9
HE ZAKUC 190 195 MO-4 RP TREB JHPERU21
11.2 5.2 50.6 51.0 228.1
224.5 230.5 230.9
29.4 36.2

BUL
386 388
RP TREB JPODG211 JLESK21
61.2 77.7 JPODG121227.2
398.3 397.2
899.0 MW

13.4

95.1 94.9
46.2 81.9
108
JPRIZ22
228.7 JTKOSA2
231.8JTKOSB1420.0

17.8
28.4
395.7

15 112
.3

78. 6

78. 6

725
134
32.

32.
JVRAN31

9
401.5
570

17.6
36.9

68.0
183
566
142

17 11
.5
39.7
131

1
109
AVDEJA1 AVDEJA2
395.0 222.7AFIERZ2223.7 C_MOGILA

27 84
.7
77.9
38.8
77.9
38.8

89.1

1
717
185
107
185
107
2
7. 6
SK 1 223.8 SK 4
406.9 406.1 . 409.3
39

-617.0 MW STIP 1 2
7. .5

MKD
BITOLA 2 412.1
408.3
53

BLAGOEV410.3 MI_3_4_1 417.5


DUBROVO 408.9
184
141
184
141

93.2
62.3
237 3
0 25 1.4

57. 6
AKASHA1 386.0 76.

1
67.4
9.8

25 5.
12
160
.4

127

2
.0 8
ALB
-883.0 MW .5
93 .4

160

31 7.0
25.0
54.2
107
29

7
.4
6 4HAMITAX
AHS_FLWR416.0 LAGAD K 413.4 12 0.1 25.0 25.0 414.9
11 6

FILIPPOI 7
23
4

56.4 56.4 54.2 65.5


404.2 4BABAESK
23.7
K-KEXRU
417.8 72.3

9.9
5.9
KARDIA K 415.5 415.3
56.2 56.8 416.9 QES/H K 412.4
146 77.2
AZEMLA1
0.0 MW
0.0 MW TUR
GRE
KARACQOU
250 419.1
50.0

GIS REGIONAL MODEL - AVERAGE HYDRO BUS -VOLTAGE(KV)


SHAW POWER
2015 HIGH LOAD - NEW GENERATION - TOPOLOGY 2015 BRANCH -MW/MVAR
TECHNOLOGIES
INC. R KV: 110 , 220 , 400 EQUIPMENT -MW/MVAR
Figure 5.6.2 - Power flows along interconnection lines in the region with balances of the systems for 2015-dry hydrology scenario
5.37
Table 5.6.1 - Area totals in analyzed electric power systems for 2015-average hydrology high load scenario –
2015 topology
AREA GENERATION LOAD LOSSES INTERCHANGE
ALBANIA 897.7 1684 96.7 -883
BULGARIA 8157.4 7083 175.4 899
BIH 2479.7 2272 94.7 112.9
CROATIA 2592.1 3959 81.1 -1448.1
MACEDONIA 895.7 1489 23.7 -617
ROMANIA 7676.4 8269.8 446.7 -1040.1
SERBIA 10023.9 7660 311.9 2051.9
MONTENEGRO 1322.6 708 27.6 587
TOTALS 34045.5 33124.8 1257.8 -337.4

Table 5.6.2 - Comparison of Area totals in analyzed electric power systems for 2015- average hydrology versus average
hydrology high load scenario –2015 topology
LOAD LOSSES
AREA normal normal
high load high load
load load
ALBANIA 1541 1684 9.28% 73.1 96.7 32.28%
BULGARIA 6483 7083 9.25% 150.9 175.4 16.24%
BIH 2279 2272 -0.31% 79.2 94.7 19.57%
CROATIA 3657 3959 8.26% 64 81.1 26.72%
MACEDONIA 1407 1489 5.83% 21.4 23.7 10.75%
ROMANIA 7317.4 8269.8 13.02% 343.1 446.7 30.2%
SERBIA 7279 7660 5.23% 254.4 311.9 22.6%
MONTENEGRO 676 708 4.73% 20.3 27.6 35.96%
TOTALS 30639.4 33124.8 8.11% 1006.4 1257.8 24.98%

Histogram
40
35
30
Frequency

25
20
15
10
5
0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.6.3 - Histogram of interconnection lines loadings for 2015-average hydrology high load scenario –
2015 topology ("Frequency" denotes number of lines and "Bin" denotes loading range in % of thermal limit)

Following Table 5.6.3 shows all network elements loaded over 80% of their thermal limits.
Histogram of branch loadings in the system is shown in Figure 5.6.4. As it can be seen large
number of lines 220 kV voltage level in Albania, Romania and Serbia are loaded over 80% for the
reasons described in previous chapter in detail. It can be concluded that new expected network
topology for 2015 compared to 2010 topology has small influence in overall load level of the
transmission network. Almost the same elements are found critical as for topology 2010, especially
in parts of the network that supply major consumption areas (Tirana in Albania, Bucharest and
Timisoara in Romania, Belgrade in Serbia and Pristina in Serbia-UNMIK).

5.38
Table 5.6.3 - Network elements loaded over 80% of their thermal limits for 2015-average hydrology high load scenario
– 2015 topology
BRANCH LOADINGS ABOVE 80.0 % OF RATING:
LOADING RATING
AREA ELEMENT PERCENT
MVA MVA
Lines
ALB HL 220kV AKASHA2-ARRAZH2 1 290.4 270 107.6
HL 220kV BRADU-TIRGOVI 1 283.9 302.6 93.8
HL 220kV BUC.S-B-FUNDENI 1 307.5 320 96.1
HL 220kV FILESTI-BARBOSI 1 245.8 277.4 88.6
HL 220kV L.SARAT-FILESTI 1 239 277.4 86.2
HL 220kV LOTRU-SIBIU 1 281.2 277.4 101.4
HL 220kV LOTRU-SIBIU 2 281.2 277.4 101.4
HL 220kV P.D.F.A-CETATE1 1 206.3 208.1 99.1
ROM
HL 220kV P.D.F.A-RESITA 1 262.1 277.4 94.5
HL 220kV P.D.F.A-RESITA 2 262.1 277.4 94.5
HL 220kV P.D.F.II-CETATE1 1 269.9 277.4 97.3
HL 220kV RESITA-TIMIS 1 225 277.4 81.1
HL 220kV RESITA-TIMIS 2 225 277.4 81.1
HL 220kV TG.JIU-PAROSEN 1 313.8 208.1 150.8
HL 220kV URECHESI-TG.JIU 1 313.5 277.4 113
SRB HL 220kV JBGD3 21-JOBREN2 1 292 301 97
Transformers
TR 220/110 kV ABURRE 1 52.2 60 87
TR 220/110 kV ABURRE 2 52.2 60 87
TR 220/110 kV ABURRE 3 52.2 60 87
TR 220/110 kV AELBS1 1 87.8 90 97.6
TR 220/110 kV AELBS1 2 87.8 90 97.6
TR 220/110 kV AELBS1 3 94.4 90 104.8
TR 220/110 kV AFIER 1 151.7 120 126.4
TR 220/110 kV AFIER 2 124.4 90 138.2
ALB TR 220/110 kV AFIER 3 118.7 90 131.9
TR 220/110 kV AFIERZ 1 59.9 60 99.8
TR 220/110 kV AFIERZ 2 59.9 60 99.8
TR 220/110 kV AKASHA 1 94.7 100 94.7
TR 220/110 kV AKASHA 2 94.7 100 94.7
TR 220/110 kV ARRAZH 1 87.5 100 87.5
TR 220/110 kV ARRAZH 2 87.5 100 87.5
TR 220/110 kV ATIRAN 2 96.4 120 80.3
TR 220/110 kV ATIRAN 3 100.6 120 83.9
TR 220/110 kV MO-4 3 124.4 150 83
BIH
TR 400/110 kV UGLJEV 1 256.1 300 85.4
CRO TR 220/110 kV TESISA 1 179.4 200 89.7
TR 220/110 kV BARBOS 1 166.6 200 83.3
TR 220/110 kV FUNDE2 1 239.8 200 119.9
TR 220/110 kV FUNDEN 1 203 200 101.5
TR 220/110 kV TIMIS 1 170.4 200 85.2
TR 400/110 kV BRASOV 1 230.2 250 92.1
ROM TR 400/110 kV CLUJ E 1 206.4 250 82.6
TR 400/110 kV DIRSTE 1 219.6 250 87.8
TR 400/220 kV BUC.S 1 376.5 400 94.1
TR 400/220 kV BUC.S 2 376.5 400 94.1
TR 400/220 kV IERNUT 1 404.8 400 101.2
TR 400/220 kV URECHE 1 479.7 400 119.9
TR 220/110 kV JBGD3 1 174.8 200 87.4
TR 220/110 kV JBGD3 2 137.5 150 91.7
TR 220/110 kV JTKOSA 2 133.5 150 89
TR 220/110 kV JTKOSA 3 135.9 150 90.6
SRB TR 220/110 kV JZREN2 2 133.8 150 89.2
TR 400/220 kV JBGD8 1 330.3 400 82.6
TR 400/220 kV JTKOSB 1 351.9 400 88
TR 400/220 kV JTKOSB 2 367.7 400 91.9
TR 400/220 kV JTKOSB 3 367.7 400 91.9
MNG TR 220/110 kV JTPLJE 1 102.4 125 82

Histogram
300

250

200
Frequency

150

100

50

0
x<25 25<x<50 50<x<75 75<x<100 x>100
Bin

Figure 5.6.4 - Histogram of branch loadings for 2015-average hydrology scenario – 2015 topology ("Frequency"
denotes number of lines and "Bin" denotes loading range in % of thermal limit)

5.39
This leads to conclusion that planned network reinforcements compared to network topology 2010,
reduce loading of some elements in southern part of Serbia, and that in order for transmission
network to sustain this load-demand level and this production pattern, additional network
reinforcements are necessary, especially in increasing transformer capacity in substations that
supply major consumption areas in Albania, Romania and Serbia.

5.6.2 Voltage Profile in the Region

Figure 5.6.5 shows histogram of voltages in monitored substations. Like for the investigated
topology 2010, overall voltage profile is not adequate, but comparing to 2010 topology voltage
profile is much better in monitored parts of Albanian and Serbian network. In some parts of the
network, especially in major consumption areas of Romania, voltages in some monitored
substations are below allowed limits. Using of voltage control devices (tap changing transformers,
shunt devices) can improve voltage profile in this region, but it can be concluded that conditions in
some parts of the transmission network of Romania are dangerously close to voltage collapse. Since
this is local problem, detailed analyses is necessary to analyze this situation.

Histogram

80

70

60
Frequency

50

40

30

20

10

0
x<0.9

0.9<x<0.95

0.95<x<0.975

0.975<x<1

1<x<1.025

1.025<x<1.05

1.05<x<1.1

x>1.1

Bin

Figure 5.6.5 - Histogram of voltages in monitored substations for 2015-average hydrology high load scenario –
2015 topology ("Frequency" denotes number of busses and "Bin" denotes voltage range in p.u.)

5.6.3 Security (n-1) analysis

Results of security (n-1) analysis for 2015-average hydrology high load scenario and expected
network topology for 2015 are presented in Table 5.6.4. Figure 5.6.6 shows the geographical
position of the critical elements in monitored systems.

5.40
Like for expected topology 2010 (previous chapter), it can be concluded that all identified insecure
situations are located in internal networks that belong to monitored power systems of Albania,
Romania and Serbia. Also, the planned network reinforcements till 2015 resolve some of the
noticed critical contingencies, especially in southern part of Serbia. Compared to the similar
scenario with normal load projection, it can be concluded that higher load-demand projected and
new production capacities modeled, increase the overload level of some critical elements. The rest
of the conclusions are the same as in case of the analyzed normal load projection and expected
topology 2015, and that is that certain level of network reinforcement is necessary to make this
regime more secure.

SVK

AUT
HUN

SLO ROM
CRO

BIH SRB

MNG BUL

MKD
TUR
ALB

critical elements
GRE 400 kV line or 400/x kV transformer
220 kV line or 220/x kV transformer

Figure 5.6.6 – geographical position of critical elements for 2015-average hydrology high load scenario –
2015 topology

5.41
Table 5.6.4 - Network overloadings for 2015-average hydrology high load scenario , single outages – 2015 topology
overloadings limit Flow rate
/ / / /
Area contingency Area out of limits voltages # Unom Voltage volt.dev.
1 2 3 4 5 6 7 8
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 285.6MVA 100.1%
BASE CASE
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 285.6MVA 133.5%
AL OHL 220kV AELBS12 -AFIER 2 1 AL HL 220kV AKASHA2-ARRAZH2 1 270MVA 289.9MVA 112.2%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 301.5MVA 106.1%
RO OHL 220kV P.D.F.A -RESITA 1 RO HL 220kV P.D.F.A-RESITA 2 277.4MVA 331.5MVA 122.8%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 301.5MVA 141.4%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 295.7MVA 103.9%
RO OHL 220kV RESITA -TIMIS 1 RO HL 220kV RESITA-TIMIS 2 277.4MVA 348.7MVA 127.0%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 295.7MVA 138.5%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.3MVA 104.8%
RO OHL 220kV PESTIS -MINTIA A 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 290.4MVA 139.7%
RO OHL 220kV CLUJ FL -AL.JL 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 271MVA 126.4%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 308.8MVA 109.1%
RO OHL 220kV AL.JL -GILCEAG 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 308.8MVA 145.4%
RO OHL 400kV TANTAREN-URECHESI 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 292.5MVA 102.6%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 300.1MVA 105.9%
RO OHL 400kV TANTAREN-BRADU 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 300.1MVA 141.1%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 331.1MVA 117.3%
RO OHL 400kV TANTAREN-SIBIU 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 331.1MVA 156.4%
RO OHL 400kV URECHESI-P.D.FIE 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 268.7MVA 124.5%
RO TR 400/220kV/kV URECHESI 1 400MVA 400.6MVA 100.1%
RO OHL 400kV URECHESI-DOMNESTI 1 RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 305.6MVA 107.7%
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 305.6MVA 143.6%
RO OHL 400kV MINTIA -ARAD 1 RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 263.1MVA 123.1%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 326.2MVA 115.5%
RO OHL 400kV MINTIA -SIBIU 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 326.2MVA 153.9%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.2MVA 104.0%
RO OHL 400kV DOMNESTI-BRAZI 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 296.2MVA 138.7%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.9MVA 104.5%
RO OHL 400kV SMIRDAN -GUTINAS 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 296.9MVA 139.3%
RO HL 220kV URECHESI-TG.JIU 1 277.4MVA 296.3MVA 104.3%
RO OHL 400kV BRASOV -BRADU 1
RO HL 220kV TG.JIU-PAROSEN 1 208.1MVA 296.3MVA 139.0%
CS OHL 220kV JBGD172 -JBGD8 22 1 CS HL 220kV JBGD172-JBGD8 22 2 365.8MVA 453.5MVA 129.0%
CS OHL 400kV JBGD8 1 -JOBREN11 1 CS HL 220kV JBGD3 21-JOBREN2 1 301MVA 293.8MVA 102.6%
RO TR 400/110 BRASOV 1 RO TR 400/110kV/kV DIRSTE 1 250MVA 353.9MVA 141.6%
RO TR 400/110 DIRSTE 1 RO TR 400/110kV/kV BRASOV 1 250MVA 350MVA 140.0%
CS TR 400/110 JNIS2 1 CS TR 400/110kV/kV JNIS2 1 2 300MVA 323.1MVA 107.7%
CS TR 400/110 JPANC2 1 CS TR 400/110kV/kV JPANC21 2 300MVA 318.8MVA 106.3%
RO TR 400/220 BUC.S 1 RO TR 400/220kV/kV BUC.S 2 400MVA 405.6MVA 101.4%
RO TR 400/220 IERNUT 1 RO HL 220kV STEJARU-GHEORGH 1 208.1MVA 196.5MVA 106.0%

5.6.4 Summary of Impacts - 2015 topology versus 2010 topology

Compared to the expected topology 2010, analyzed in previous chapter, it can be seen that the
network losses are smaller as a consequence of building of new elements for 2015 network
topology, especially in the cases of Albania, Serbia and Montenegro. Overall reduction of loses is
around 39 MW.

Also, planned network reinforcements compared to network topology 2010, reduce load of some
elements in southern part of Serbia. Compared to the 2010 topology, voltage profile is somewhat
better, especially in southern and central part of Serbia, as well as in Albania. This is direct
consequence of the building of the new 400 kV line Nis-Leskovac-Vranje-Skopje and substation
400/110 kV Vranje. However, voltage profile is still not satisfying.

Realization of the planed investments till 2015 has impact on secure operation of the network.
Some of the insecure states identified with 2010 topology are relieved and do not exist with
expected 2015 network topology.

Main conclusion can be that even with 2015 topology, this load-generation regime is not feasible
enough and additional network reinforcements are necessary, especially in the major consumption
area.

5.42
6 ANALYSES SUMMARY AND RECOMMENDATIONS

6.1
In this chapter, comparison of the all analyzed scenarios is presented. Main issues are impact of
different generation patterns and planed network investments on system losses and system security.
The authors tried to give main indicators how to resolve some insecure states identified, based on
prerequisites and assumptions presented in Chapter 2 and only results of the analyses of scenarios.
Deeper impacts of the proposed remedies are not analyzed whether they are or not in compliance
with long term investments plans of the countries in the region.

6.1 Reference cases

Reference cases consist of nine cases. Three different hydrology scenarios are analyzed (average,
dry and wet) for years 2010 and 2015. Also, for each of these generation-load patterns in year 2015
two cases are analyzed (first for 2010 topology, i.e. without any new line or transformer planned for
commissioning between 2010 and 2015 and second for expected topology in year 2015).

6.1.1 Analyses comparison

Main focus of this subchapter is to analyze influence of different generation patterns and planed
network investments on overall network performance and system losses.

Table 6.1.1 shows overview of losses on regional level. It can be seen that new elements planned
for commissioning between 2010 and 2015 influence reduction of losses in analyzed region, no
matter of hydrology. This reduction of losses is between 30 and 40 MW.

Table 6.1.1: Peak Hour - Regional Losses (MW)


Year 2010 Year 2015
Topology
Dry Average Wet Dry Average Wet
2010 756.9 737.1 741.5 951.6 1,035.1 976.6
2015 - - - 909.6 1,006.4 941.8

These changes are consequence of better voltage profile in analyzed region, especially in areas
directly influenced by the new elements. For example, new interconnection line Nis-Leskovac-
Vranje-Skopje greatly improves voltage profile in southern part of Serbia and new interconnection
lines Podgorica – V.Dejes – Kashar – Elbasan and Kosovo B – V.Dejes – Kashar – Elbasan greatly
improve voltage profile in Albania. Higher voltages and reduction of load of some elements that are
highly influenced by the new elements, reduce power losses mainly in Albania, Southern Serbia,
and in the region as whole.

Table 6.1.2 shows overview of area summaries for analyzed reference cases. Comparing cases with
different hydrology (for the same year and topology) it can be concluded following:
ƒ Since analyzed region is balanced, deficit of power produced by hydro power plants is
compensated by greater power produced by thermal power plants. Different hydrology
causes different generation and interchange patterns.
ƒ Because of different generation and interchange patterns, power flows are different and this
cause different level of losses, but it is not possible to establish clear connection between
these factors.
ƒ Level of intersystem interchanges is much higher than in present or history. It has to be
stated that networks of single systems are developed mainly to cover their demand with their
own production capacities, so this kind of power plant engagement and level of interchanges
cause power flows and network status that are different from ones recorded. This goes
especially Albanian and Serbian system.

6.2
Table 6.1.2: Overview of area summaries for analyzed reference cases (in MW)
Total
Year Hydrology Topology Data type Albania B&H Bulgaria Croatia Macedonia Montenegro Romania Serbia
(SE Europe)
Generation 896.7 2266.1 6900.4 1502.9 950.3 539.8 7939.9 7355.9 28351.9
Load 1287.3 1971.3 5977.3 3136.7 1198.2 669.2 6728.3 6873.1 27841.4
Average 2010
Losses 50.4 58.6 121.6 49.0 20.1 15.5 201.2 220.8 737.1
Interchange -441.0 236.2 787.0 -1682.8 -268.0 -147.0 930.4 248.4 -336.7
Generation 953.3 2842.4 6709.6 2294.6 1021.1 467.8 6742.0 7311.7 28342.5
Load 1290.5 1989.0 5970.0 3147.0 1206.0 671.0 6703.8 6944.0 27921.3
2010 Dry 2010
Losses 46.8 60.3 133.6 41.6 18.1 16.9 238.0 201.6 756.9
Interchange -384.0 793.0 606.0 -894 -203.0 -220.0 -199.9 166.0 -335.9
Gen 898.6 2037.1 6940.4 1735.4 1081.8 586.3 7342.4 7406.2 28028.1
Load 1287.3 1961.1 5966.2 3136.7 1194.0 669.2 6423.7 6875.1 27513.3
Wet 2010
Losses 50.3 57.0 120.9 50.7 19.8 15.9 206.6 220.4 741.5
Interchange -439.0 19.0 839.0 -1452.0 -132.0 -101.0 632.1 297.1 -336.7
Generation 1116.1 2316.6 7332.7 2316.3 1087.0 735.0 7712.8 8687.6 31304.1
Load 1531.0 2279.0 6483.0 3657.0 1407.0 671.0 7317.4 7263.0 30608.4
2010
Losses 81.2 78.7 150.7 63.4 20.0 25.0 347.4 268.7 1035.1
Interchange -496.0 -41.1 699.0 -1404.1 -340.0 39.0 47.9 1156.0 -339.3
Average
Generation 1118.1 2317.2 7332.9 2317.0 1088.4 735.2 7708.6 8689.4 31306.8
Load 1541.0 2279.0 6483.0 3657.0 1407.0 676.0 7317.4 7279.0 30639.4
2015
Losses 73.1 79.2 150.9 64.0 21.4 20.3 343.1 254.4 1006.4
Interchange -496.0 -41.0 699.0 -1404.0 -340.0 39.0 48.1 1156.0 -338.9
Generation 894.7 3140.9 7363.9 2636.7 985.1 586.3 7724.6 8397.9 31730.1
Load 1521.9 2304.0 6450.0 3665.0 1410.0 672.0 7798.4 7296.0 31117.3
2010
Losses 92.7 78.2 147.9 58.2 19.1 22.1 295.5 237.9 951.6
Interchange -720.0 758.8 766.0 -1086.4 -444.0 -107.7 -369.2 864.0 -338.5
2015 Dry
Generation 893.6 3141.2 7363.9 2637.7 985.2 586.3 7722.9 8396.3 31727.1
Load 1542.0 2305.0 6450.0 3665.0 1409.0 678.0 7798.4 7308.0 31155.4
2015
Losses 71.6 77.1 147.8 58.7 20.2 16.4 293.5 224.3 909.6
Interchange -720.0 759.0 766.0 -1085.9 -444.0 -108.0 -368.9 864.0 -337.8
Generation 1124.5 2154.2 7553.2 2799.9 869.5 778.7 7953.9 8413.1 31646.9
Load 1528.9 2278.6 6446.1 3660.4 1407.6 669.8 7704.0 7209.2 30904.6
2010
Losses 85.8 74.8 137.4 60.9 18.9 21.6 298.9 278.4 976.6
Interchange -490.1 -199.3 955.0 -921.3 557.0 85.0 -123.3 912.7 -338.3
Wet
Generation 1111.0 2155.1 7553.3 2800.9 870.8 774.1 7950.3 8398.5 31613.9
Load 1528.9 2278.6 6446.1 3660.4 1407.6 669.8 7704.0 7209.2 30904.6
2015
Losses 72.1 75.6 137.5 61.6 20.2 16.9 294.8 263.2 941.8
Interchange -490.0 -199.0 955.0 -921.1 -557.0 85.0 -123.0 913.0 -337.2

6.3
Table 6.1.3: Overview of high loaded elements in analyzed reference cases
LOAD LEVEL 2010 2015
HYDROLOGY average dry wet average dry wet
TOPOLOGY 2010 2015 2010 2015 2010 2015
RATING LOAD LOAD LOAD LOAD LOAD LOAD LOAD LOAD LOAD
AREA ELEMENT % % % % % % % % %
MVA MVA MVA MVA MVA MVA MVA MVA MVA MVA
Lines
ALB OHL 220 kV AKASHA2-ARRAZH2 270 250 92.6 238 88 275 102 243 89.9 259 96 237 87.8
BUL OHL 220 kV MI_2_220-ST ZAGORA 228.6 191 83.5 190 83.3
OHL 220 kV MINTIA-SIBIU 381.1 268 96.5 268 96.4 324 85.1 313 82.2
OHL 220 kV P.D.F.II-CETATE1 277.4 205 98.6 205 98.5 269 97 268 96.8
OHL 220 kV P.D.F.A-CETATE1 208.1 236 85.2 232 83.7 206 99 206 98.8
OHL 220 kV P.D.F.A-RESITA ckt.1 277.4 236 85.2 232 83.7 239 86.2 236 84.9
OHL 220 kV P.D.F.A-RESITA ckt.2 277.4 239 86.2 236 84.9
ROM
OHL 220 kV LOTRU-SIBIU ckt.1 277.4 276 99.5 304 109 303 109
OHL 220 kV LOTRU-SIBIU ckt.2 277.4 276 99.5 304 109 303 109
OHL 220 kV URECHESI-TG.JIU 277.4 278 100 273 98.3 280 101 275 99.3
OHL 220 kV TG.JIU-PAROSEN 208.1 182 87.3 278 134 273 131 280 135 275 132
OHL 220 kV BUC.S-B-FUNDENI 320 261 81.6 261 81.4 285 89.2 285 88.9
SRB OHL 220 kV JBGD3 21-JOBREN2 301 261 86.7 262 87 294 97.5 295 97.9 313 104 313 104
Transformers
TR 220/110 kV AFIERZ2-AFIERZ5 ckt.1 60 51.9 86.5 50.3 83.8 59 98.3 52.1 86.9 54.6 91.1 50.2 83.7
TR 220/110 kV AFIERZ2-AFIERZ5 ckt.2 60 51.9 86.5 50.3 83.8 59 98.3 52.1 86.9 54.6 91.1 50.2 83.7
TR 220/110 kV AELBS12-AELBS15 ckt.1 90 78 86.6 74.3 82.5 84.7 94.1 75.4 83.8 81.4 90.5 74.8 83.2
TR 220/110 kV AELBS12-AELBS15 ckt.2 90 78 86.6 74.3 82.5 84.7 94.1 75.4 83.8 81.4 90.5 74.8 83.2
TR 220/110 kV AELBS12-AELBS15 ckt.3 90 83.8 93.1 79.8 88.7 91 101 81 90 87.5 97.2 80.4 89.3
TR 220/110 kV AKASHA2-AKASH25 ckt.1 100 84.1 84.1 82.1 82.1 90.8 90.8 83.5 83.5 87.2 87.2 82.3 82.3
ALB TR 220/110 kV AKASHA2-AKASH25 ckt.2 100 84.1 84.1 82.1 82.1 90.8 90.8 83.5 83.5 82.3 82.3
TR 220/110 kV AFIER 2-AFIER 5 ckt.1 120 117 93.7 107 89 117 97.1 138 115 135 113 147 122 137 114 141 118 135 112
TR 220/110 kV AFIER 2-AFIER 5 ckt.2 90 95.7 106 87.5 97.2 95.5 106 113 126 111 123 120 134 112 125 116 129 110 123
TR 220/110 kV AFIER 2-AFIER 5 ckt.3 90 91.4 102 83.5 92.8 91.1 101 108 120 106 117 115 128 107 119 110 123 105 117
TR 220/110 kV ARRAZH 1 100 84.7 84.7 80.3 80.3
TR 220/110 kV ARRAZH 2 100 84.7 84.7 80.3 80.3
TR 220/110 kV ATIRAN 3 120 98.2 81.9
B&H TR 400/110 kV UGLJEVIK 300 255 84.9 255 84.9 253 84.2 242 80.8 241 80.2 270 90 268 89.2
TR 400/220 kV URECHESI 400 395 98.9 391 97.7 414 104 410 103
TR 400/220 kV BUC.S-BUC.S-B ckt.1 400 340 85 339 84.8
TR 400/220 kV BUC.S-BUC.S-B ckt.2 400 340 85 339 84.8
ROM TR 220/110 kV FUNDE2 1 200 173 86.6 168 84.1 169 84.4 193 96.7 193 96.5 200 99.9 200 99.8 209 104 208 104
TR 220/110 kV FUNDEN 1 200 163 81.4 163 81.3 169 84.2 168 84.1 176 88 176 87.8
TR 400/220 kV MINTIA-MINTIA B 400 386 96.4
TR 400/220 kV IERNUT 1 400 320 80.1 325 81.3 324 81.1
TR 400/220 kV JBGD8 1 400 338 84.5 335 83.7
TR 220/110 kV JBGD3 1 200 167 83.4 167 83.3 171 85.6 171 85.5 197 98.6 197 98.3
TR 220/110 kV JBGD3 2 150 126 83.7 126 83.9 130 86.5 130 86.6 135 89.7 134 89.6
TR 220/110 kV JZREN2 2 150 124 82.4 124 82.3 122 81.3 122 81
TR 220/110 kV JTKOSA 2 150 131 87.1 133 88.9 132 87.9
TR 220/110 kV JTKOSA 3 150 133 88.7 136 90.5 134 89.5
SRB
TR 400/220 kV JTKOSB 1 400 323 80.8
TR 400/220 kV JTKOSB 2 400 326 81.4 338 84.4 325 81.1
TR 400/220 kV JTKOSB 3 400 326 81.4 338 84.4 325 81.1
TR 220/110 kV JPRIS4 1 150 122 81.1
TR 220/110 kV JPRIS4 2 150 122 81.1
TR 400/110 kV JJAGO4 300 247 82.5

6.4
Table 6.1.3 shows summary for elements loaded over 80% of their thermal limits. In network
planning practice, this is used as one of the main indicators which parts of the transmission network
represent weak spots and what network reinforcements are necessary in sense of generation and
supply, without taking into consideration the security aspects. Analysis of these results leads to
conclusion that transmission network is capable of transferring power from generation facilities to
major consumption areas, and network reinforcement is not necessary (without taking n-1 criterion
into consideration). But, in some substations, there is not enough transformer capacity to supply
demand from transmission network, since the load of these elements do not depend on generation
pattern and level of system interchange, but only on load level in these substations. This is problem
of local supply, and this should be studied as program of local not regional system development.
Increase of transformer installed capacity is needed in substations 220/110 kV Fier, Elbasan, Fierza
and Kashar in Albania, 400/110 kV Ugljevik in Bosnia and Herzegovina.

Also, it should be noted that level of reactive power consumption in load flow model of Albania is
very high comparing to the other systems and not realistic. This is one of the reasons why voltage
profile in Albanian network is very close to voltage collapse in some investigated scenarios.
Because of the problem with unrealistic reactive power demand new reactive power demand
forecast is needed.

Influence of voltage control equipment was not tested on regional level, and therefore it is not
possible to give answer weather there is possibility to better voltage profile in certain regimes. Also,
no light load regimes were analyzed, so there is no possibility to analyze effect of new reactive
power control devices.

6.1.2 Overview on possible solutions for system relief

In this subchapter, security aspects of network performance in analyzed scenarios are presented. As
it has been concluded in Chapter 4, in all investigated scenarios, some elements are highly loaded
even in case of full topology. Most of the elements loaded over 80% are transformers in some
substations and also there are some overloaded elements (Table 6.1.3).

Based on full topology and n-1 contingency analyses, some internal network reinforcements are
necessary to sustain analyzed load-demand level and production pattern. In other words, optimum
GTMax dispatch, according to analyzed generation and load scenarios, is not possible to achieve
with desired level of network security. Internal network reinforcements are necessary in order to
achieve such optimal dispatch.

Most of the identified critical network elements in Romania can be relieved by dispatching actions
(change of network topology or production units engagement). Re-dispatching actions, mostly in
the power system of Romania (power plants DEVA 1, LOTRU CIUNGET, PORTILE 1,
PAROSENI and ROVINARI) will be necessary to keep desired network security level according to
the (n-1) criterion. Also, installing a new transformer unit 400/110 kV in Brasov is planned and
helps resolving some critical states in Romanian network. Upgrading the Timisoara substation to
400 kV level and supplying this area from 400 kV network instead from 220 kV would resolve
some problems in Romanian network.

Reinforcement of local network in vicinity of Belgrade is necessary, but as it has been stated before,
this is local development. Problem of supplying Belgrade area must be part of more complex and
thorough analyses.

6.5
Central part of the 400 kV network in Serbia is heavy loaded due to large energy transits from
Romania, Bulgaria and south of Serbia (Kosovo and Metohija) to Croatia and Hungary.
Strengthening of the 400 kV corridor from Romania through Serbia to Croatia (East-West), by
building 400 kV lines Romania (e.g. new proposed substation Timisoara)-(Vrsac)-Drmno and
Belgrade-Obrenovac can relieve this problem.

For all of this, more thorough analyses are needed and only adequate feasibility studies can give the
proper answer to the question about the level and type of network reinforcements.

Final conclusions concerning year 2010 are:


- expected network topology in year 2010 is sufficient for all investigated generation and
load pattern for year 2010, except in South Serbia and Belgrade area;
- building of the 400 kV corridor Nis-Leskovac-Vranje-Skoplje before 2010 resolves all
insecure states identified in network of southern Serbia for investigated regimes in
2010;
- network reinforcement in Belgrade area is necessary;
- level of reactive power consumption in load flow model of Albania is very high
comparing to the other systems and not realistic and this causes some overloads due to
low voltage profile in Albanian network;
- high loads and overloads of elements in Romania can be relieved by operational
methods.

Expected network topology for 2015 generally improves network performance, especially in the
cases of Albanian and Serbian network. But, additional network reinforcements are necessary,
especially in increasing transformer capacities in mentioned substations, over which large
consumption areas are supplied. In case of Romania, it is hard to say what reinforcements are
necessary, since most of the identified insecure states can be relieved with production redispatch
and network topology changes.

New proposed lines (Visegrad – Pljevlja, Tumbri – Banja Luka and Pecs – Sombor) do not resolve
any of the identified insecure states, since these lines are electrically far from these critical network
elements, and therefore do not have significant influence. But, they do increase transfer capabilities
of interconnected network.

Final conclusions concerning year 2015 are:


- new lines commissioned to come into operation between 2010 and 2015 greatly reduce
losses in analyzed region, regardless of hydrology;
- expected network topology in year 2015 is sufficient for all investigated generation and
load pattern for year 2010, except in Belgrade area;
- building of the 400 kV corridor Nis-Leskovac-Vranje-Skoplje resolves all insecure
states identified in network of southern Serbia for investigated regimes in 2015;
- network reinforcement in east-west corridor in Serbia is necessary (this includes
Belgrade area also);
- level of reactive power consumption in load flow model of Albania is very high
comparing to the other systems and not realistic and this causes some overloads due to
low voltage profile in Albanian network;
- high loads and overloads of elements in Romania can be relieved by operational
methods;
- proposed interconnection lines candidates do not resolve any of the identified
problems.

6.6
6.2 Sensitivity cases

Sensitivity cases consist of six scenarios. In all of these cases average hydrology is used. Two
different scenarios are analyzed (first 1500 MW of import plus 500 MW of transit and second high
load growth) for years 2010 and 2015. Also, for each of these scenarios in year 2015 two cases are
analyzed (first for 2010 topology, i.e. without any new line or transformer planned for
commissioning between 2010 and 2015 and second for expected topology in year 2015).

6.2.1 Analyses comparison

Main focus of this subchapter is to analyze influence of high load growth rate and import/export
regime on system losses and overall network performance.

Table 6.2.1 shows overview of losses on regional level. It can be seen that new elements planned
for commissioning between 2010 and 2015 influence reduction of losses in analyzed region, no
matter of hydrology. This reduction of losses is between 30 and 40 MW.

Table 6.2.1: Peak Hour - Regional Losses (MW) under Average Hydrologic Conditions
Year 2010 Year 2015
Case
2010* 2010 *
2015*
Reference Case 737.1 1,035.1 1,006.4
Imports/Exports 684.8 NA 850.3
High Load Forecast 913.9 1,296.9 1,257.8
*
topogy

These changes are consequence of better voltage profile in analyzed region, especially in areas
directly influenced by the new elements. For example, new interconnection line Nis-Leskovac-
Vranje-Skopje greatly improves voltage profile in southern part of Serbia and new interconnection
lines Podgorica – V.Dejes – Kashar – Elbasan and Kosovo B – V.Dejes – Kashar – Elbasan greatly
improve voltage profile in Albania. Higher voltages and reduction of load of some elements that are
highly influenced by the new elements, reduce power losses mainly in Albania, Southern Serbia,
and in the region as whole.

Table 6.2.2 shows overview of area summaries for analyzed reference cases and Table 6.2.3 shows
overview of high loaded elements in analyzed sensitivity cases.

Import/export sensitivity scenarios

Concerning the import/export case, the simulated regime means the following:
▪ Import 750 MW from UCTE
▪ Import 500 MW from Turkey
▪ Export 500 MW to Greece
▪ Import 750 MW from Ukraine

Large imports from analyzed directions cause significant increase of power flows along Slovenian-
Croatian, Ukrainian-Romanian and Bosnian-Montenegrin interfaces in 2010, but interconnection
lines are not jeopardised since they are loaded far below their thermal ratings.

6.7
Power losses on network topology in 2010, compared to the situation of balanced SE Europe power
system, are increased in the power systems of Bulgaria (7.9 %) and Montenegro (9 %). In other
power systems these losses are decreased, with the most significant drop in Romania (-16 %) and
Serbia and UNMIK (-10.1 %). Regional power losses are decreased (-7.1 %) when the situation
includes additional power import. It can be concluded that for this exchange scenario, power flows
and voltage profile are such that transmission network is better utilized, and as a consequence losses
are smaller.

By comparing the average hydrology situation in 2010 and balanced SE Europe power system to
the average hydrology situation and 1500 MW of power import, it may be noticed that some critical
contingencies in the Romanian power system disappear, especially those connected with Mintia
substation, while some new contingencies appear in the power system of Bulgaria (lines around
Maritsa East substation). This is due to different dispatching conditions of DEVA 1 power plant in
Romania (disconnected in import/export scenario, dispatched with 850 MW in the base case) and
power import through Turkish-Bulgarian interface that goes through Maritsa East 3 substation.

The analyzed scenario which is characterized by large power import in 2015, but on the 2010
network topology, can not be supported from a transmission network viewpoint due to voltage
problems. Their existence is the most obvious in the power system of Albania due to scarce reactive
power sources. To mitigate such problems it is necessary to construct at least one new 400 kV
interconnection line between Albania and UNMIK or Macedonia.

Large imports from analyzed directions in 2015 cause significant increase of the power flows along
the Slovenian-Croatian and Ukrainian-Romanian interfaces. However, the interconnection lines are
not jeopardized since their loading levels fall far below their thermal ratings.

Power losses, in comparison to the situation of balanced SE Europe power system, are increased
only in the power system of Macedonia (5%). In other power systems power losses are decreased,
the most significantly in the power systems of Romania (-26%) and Montenegro (-23%). Power
losses are decreased (-16%) in the region when analyzing the additional power import.

Certain reinforcements in the internal networks of Romania, Bulgaria, Albania and Serbia till 2015
are necessary shall analyzed generation pattern and 1500 MW of power import be made more
secure. None of the identified congestions is located at the border lines.

High load growth rate

Pessimistic (high) load growth rate is more close to load forecast made by electric power utilities in
analyzed region.

In case of high load growth rate power flows through lines and transformers are greater. This cause
greater level of losses, increased number of elements loaded over 80 % and overloaded elements
also and greatly decreased level of system security (Table 6.2.3).

In case of year 2015 and 2010 topology it is not feasible to realize this generation-load pattern due
to network constraints in Albania, but in Serbia and Romania also.

As it has been concluded in Chapter 5, in all investigated scenarios, some elements are highly
loaded even in case of full topology. Most of the elements loaded over 80% are transformers in
some substations and also there are some overloaded elements (Table 6.2.3).

6.8
Table 6.2.2: Overview of area summaries for analyzed sensitivity cases (in MW)
Total
Year Case Topology Data type Albania B&H Bulgaria Croatia Macedonia Montenegro Romania Serbia
(SE Europe)
Generation 896.7 2266.1 6900.4 1502.9 950.3 539.8 7939.9 7355.9 28351.9
Reference case Load 1287.3 1971.3 5977.3 3136.7 1198.2 669.2 6728.3 6873.1 27841.4
2010
Average hydrology Losses 50.4 58.6 121.6 49.0 20.1 15.5 201.2 220.8 737.1
Interchange -441.0 236.2 787.0 -1682.8 -268.0 -147.0 930.4 248.4 -336.7
Generation 898.2 2398.3 6827.0 1705.2 965.5 542.1 6877.4 6591.7 26805.4
Import/export Load 1288.5 1965.0 5967.5 3143.3 1178.3 670.2 6733.1 6901.7 27847.6
2010 2010
Average hydrology Losses 49.7 54.3 131.2 44.9 20.1 16.9 169.1 198.6 684.8
Interchange -440.0 379.0 714.0 -1483.0 -233.0 -147.0 -104.8 -521.9 -1836.7
Generation 931.7 2202.8 7282.5 2254.6 991.1 542.3 7113.3 8103.8 29422.1
High load Load 1358.0 2004 6278.0 3295.0 1234.0 686.0 6859.4 7131.0 28845.4
2010
Average hydrology Losses 57.7 57.8 146.5 55.4 18.1 19.2 310.6 248.6 913.9
Interchange -484.0 141.1 858.0 -1095.9 -261.0 -163 -56.7 724.2 -337.3
Generation 1116.1 2316.6 7332.7 2316.3 1087.0 735.0 7712.8 8687.6 31304.1
Load 1531.0 2279.0 6483.0 3657.0 1407.0 671.0 7317.4 7263.0 30608.4
2010
Losses 81.2 78.7 150.7 63.4 20.0 25.0 347.4 268.7 1035.1
Reference case Interchange -496.0 -41.1 699.0 -1404.1 -340.0 39.0 47.9 1156.0 -339.3
Average hydrology Generation 1118.1 2317.2 7332.9 2317.0 1088.4 735.2 7708.6 8689.4 31306.8
Load 1541.0 2279.0 6483.0 3657.0 1407.0 676.0 7317.4 7279.0 30639.4
2015
Losses 73.1 79.2 150.9 64.0 21.4 20.3 343.1 254.4 1006.4
Interchange -496.0 -41.0 699.0 -1404.0 -340.0 39.0 48.1 1156.0 -338.9
Generation * * * * * * * * *
Load * * * * * * * * *
2010
Losses * * * * * * * * *
Import/export Interchange * * * * * * * * *
2015
Average hydrology Generation 1027.5 2394.9 7582.2 2173.9 1076.3 731.9 7187.7 8029.8 30204.2
Load 1544.0 2293.8 6418.9 3660.1 1393.7 675.0 7831.2 7270.7 31087.4
2015
Losses 71.5 70.1 142.7 58.8 22.5 15.6 253.9 215.1 850.3
Interchange -588.0 31.0 1006.0 -1545.0 -340.0 39.0 -972.0 530.0 -1839.0
Generation 896.1 2479.4 8157.8 2591.0 895.0 1324.6 7684.5 10024.2 34052.6
Load 1680.0 2274.0 7083.0 3959.0 1489.0 702.0 8269.8 7635.0 33091.8
2010
Losses 99.0 92.2 175.8 79.8 23.0 35.6 454.5 337.0 1296.9
High load Interchange -883.0 113.2 899.0 -1447.8 -617.0 587.0 -1039.8 2052.2 -336.2
Average hydrology Generation 897.7 2479.7 8157.4 2592.1 895.7 1322.6 7676.4 10023.9 34045.5
Load 1684.0 2272.0 7083.0 3959.0 1489.0 708.0 8269.8 7660.0 33124.8
2015
Losses 96.7 94.7 175.4 81.1 23.7 27.6 446.7 311.9 1257.8
Interchange -883.0 112.9 899.0 -1448.1 -617.0 587.0 -1040.1 2051.9 -337.4
* convergent load flow solution was not found
6.9
Table 6.2.3: Overview of high loaded elements in analyzed sensitivity cases
year 2010 2015
regime average imp/exp high load average imp/exp high load
topology 2010 2015 2010* 2015 2010 2015
RATING LOAD LOAD LOAD LOAD LOAD LOAD LOAD LOAD LOAD
AREA ELEMENT % % % % % % % % %
MVA MVA MVA MVA MVA MVA MVA MVA MVA MVA
Lines
ALB HL 220kV AKASHA2-ARRAZH2 1 270 250 92.6 238 88 236 87.3 288 107 290 108
BUL HL 220 kV M.EAST-ST.ZAGORA 228.6 189 82.6 191 83.5
HL 220kV BRADU-TIRGOVI 1 302.6 247 81.6 285 94.3 284 93.8
HL 220kV BUC.S-B-FUNDENI 1 320 266 83.1 309 96.7 308 96.1
HL 220kV FILESTI-BARBOSI 1 277.4 248 89.5 246 88.6
HL 220kV L.SARAT-FILESTI 1 277.4 241 86.9 239 86.2
HL 220kV LOTRU-SIBIU 1 277.4 281 101
HL 220kV LOTRU-SIBIU 2 277.4 281 101
HL 220kV P.D.F.A-CETATE1 1 208.1 205 98.6 205 98.5 204 98.2 207 99.6 206 99.1
HL 220kV P.D.F.A-RESITA 1 277.4 227 81.7 236 85.2 232 83.7 267 96.2 262 94.5
ROM
HL 220kV P.D.F.A-RESITA 2 277.4 227 81.7 267 96.2 262 94.5
HL 220kV P.D.F.II-CETATE1 1 277.4 236 85.2 232 83.7 271 97.7 270 97.3
HL 220kV PAROSEN-BARU M 1 277.4 228 82
HL 220kV RESITA-TIMIS 1 277.4 230 82.8 225 81.1
HL 220kV RESITA-TIMIS 2 277.4 230 82.8 225 81.1
HL 220kV TG.JIU-PAROSEN 1 208.1 278 134 278 134 273 131 321 154 314 151
HL 220kV URECHESI-TG.JIU 1 277.4 278 100 278 100 273 98.3 320 116 314 113
HL 220 kV MINTIA-SIBIU 381.1 268 96.5 268 96.4
SRB HL 220kV JBGD3 21-JOBREN2 1 301 261 86.7 262 87 277 92.2 291 96.7 292 97
Transformers
TR 220/110 kV ABURRE 1 60 49.1 81.8 49.5 82.5 52.2 87
TR 220/110 kV ABURRE 2 60 49.1 81.8 49.5 82.5 52.2 87
TR 220/110 kV ABURRE 3 60 49.1 81.8 49.5 82.5 52.2 87
TR 220/110 kV AELBS1 1 90 78 86.6 74.3 82.5 74 82.2 87.7 97.5 87.8 97.6
TR 220/110 kV AELBS1 2 90 78 86.6 74.3 82.5 74 82.2 87.7 97.5 87.8 97.6
TR 220/110 kV AELBS1 3 90 117 97.6 122 102 83.8 93.1 79.8 88.7 79.5 88.3 94.2 105 94.4 105
TR 220/110 kV AFIER 1 120 117 93.7 96 107 100 111 138 115 135 113 131 109 149 124 152 126
TR 220/110 kV AFIER 2 90 95.7 106 91.6 102 95.6 106 113 126 111 123 107 119 122 136 124 138
ALB TR 220/110 kV AFIER 3 90 91.4 102 108 120 106 117 102 114 117 130 119 132
TR 220/110 kV AFIERZ 1 60 51.9 86.5 50.3 83.8 50.9 84.8 58 96.7 59.9 99.8
TR 220/110 kV AFIERZ 2 60 51.9 86.5 50.3 83.8 50.9 84.8 58 96.7 59.9 99.8
TR 220/110 kV AKASHA 1 100 84.1 84.1 82.1 82.1 82.9 82.9 93.4 93.4 94.7 94.7
TR 220/110 kV AKASHA 2 100 84.1 84.1 82.1 82.1 82.9 82.9 93.4 93.4 94.7 94.7
TR 220/110 kV ARRAZH 1 100 87.7 87.7 87.5 87.5
TR 220/110 kV ARRAZH 2 100 87.7 87.7 87.5 87.5
TR 220/110 kV ATIRAN 2 120 97.5 81.3 96.4 80.3
TR 220/110 kV ATIRAN 3 120 102 85.2 101 83.9
TR 220/110 kV MO-4 3 150 124 83
BIH
TR 400/110 kV UGLJEV 1 300 255 84.9 255 84.9 253 84.2 256 85.4 259 86.3 256 85.4
CRO TR 220/110 kV TESISA 1 200 179 89.4 179 89.7
TR 220/110 kV BARBOS 1 200 174 86.9 167 83.6 167 83.3
TR 220/110 kV FUNDE2 1 200 173 86.6 179 89.3 193 96.7 193 96.5 214 107 241 120 240 120
TR 220/110 kV FUNDEN 1 200 163 81.4 163 81.3 181 90.5 204 102 203 102
TR 220/110 kV TIMIS 1 200 172 85.9 170 85.2
TR 400/110 kV BRASOV 1 250 203 81 232 92.6 230 92.1
TR 400/110 kV CLUJ E 1 250 208 83.4 206 82.6
ROM
TR 400/110 kV DIRSTE 1 250 221 88.4 220 87.8
TR 400/220 kV BUC.S 1 400 378 94.6 377 94.1
TR 400/220 kV BUC.S 2 400 378 94.6 377 94.1
TR 400/220 kV IERNUT 1 400 320 80.1 408 102 405 101
TR 400/220 kV URECHE 1 400 344 86.1 395 98.9 391 97.7 487 122 480 120
TR 400/220 kV MINTIA 400 386 96.4
TR 220/110 kV JBGD3 1 200 167 83.4 167 83.3 169 84.7 175 87.5 175 87.4
TR 220/110 kV JBGD3 2 150 126 83.7 126 83.9 127 84.5 137 91.4 138 91.7
TR 220/110 kV JPRIS4 1 150 137 91.3
TR 220/110 kV JPRIS4 2 150 137 91.3
TR 220/110 kV JTKOSA 2 150 132 87.7 131 87.1 151 101 134 89
TR 220/110 kV JTKOSA 3 150 134 89.3 133 88.7 154 103 136 90.6
SRB
TR 220/110 kV JZREN2 2 150 120 80.1 124 82.4 124 82.3 122 81 134 89.2 134 89.2
TR 400/110 kV JJAGO4 A 300 246 81.9
TR 400/220 kV JBGD8 1 400 326 81.6 332 83 330 82.6
TR 400/220 kV JTKOSB 1 400 412 103 352 88
TR 400/220 kV JTKOSB 2 400 326 81.4 430 108 368 91.9
TR 400/220 kV JTKOSB 3 400 326 81.4 430 108 368 91.9
MNG TR 220/110 kV JTPLJE 1 125 102 82

*convergent load flow solution was not found

6.10
As it has been said above, in some substations there is not enough transformer capacity to supply
demand from transmission network, since the load of these elements do not depend on generation
pattern and level of system interchange, but only on load level in these substations, particularly in
this case.

This is problem of local supply. It should be pointed out that load patterns (in all reference and
sensitivity cases) have the greatest influence to identified problems.

6.2.2 Overview on possible solutions for system relief

Security aspects of network performance in analyzed scenarios are presented in this subchapter.

It has to be said, that new generation facilities in UNMIK area, are too large to be investigated as
they were. Over 3000 MW of new production were connected to only one substation, Kosovo B. It
is almost certain, that installing such large capacities demands different and more detailed solution,
as well as large changes in internal network of UNMIK area, in order to supply this energy to
consumers. Also, large changes in internal network of Serbia are necessary too, since installing of
these 3000 MW causes great changes in energy flows in region, and therefore different supply
routes in internal network. That is why, more detailed analysis is necessary in order to draw
conclusions that will give right indices about eventual congestions and necessary network
reinforcements. One of possible solutions is building of 400 kV ring (Kosovo B – Pristina 4 –
Kosovo C) that will connect new production facilities with existing substations Kosovo B and new
substation 400 kV Pristina 4. The other is to connect the all new plants to existing 400 kV
substation Kosovo B radial through new 400 kV lines (as it was analyzed in this study). This
solution is better from network point of view, but from generation point of view is less reliable and
secure.

More thorough analyses is needed and only adequate feasibility studies can give the proper answer
to the question about the level and type of network reinforcements, especially in the case of the new
generation facilities proposed.

Concerning internal network reinforcements, same conclusions can be made as in previous


chapter.

Additional conclusions concerning year 2010 are:


- level of power losses for import/export scenario are significantly lower as consequence
of better utilization of the transmission network. It should be pointed out that this
scenario is more close to recorded system behavior, since Greece is one of the major
regional importers
- level of load of high loaded and overloaded elements is greater, especially in case of
high load scenario;
- building of the 400 kV corridor Nis-Leskovac-Vranje-Skoplje before 2010 resolves has
much greater significance.

Additional conclusions concerning year 2015 are:


- expected network topology in year 2015 is not sufficient in case of high load scenario;
- operational methods in network of Romania can relieve some of identified problems,
but in case of high load scenario network reinforcement should be analyzed also;
- new production units in UNMIK area require detailed analysis related to connection of
these units to power system network.

6.11
6.3 List of priorities

Based on main conclusions above lists of priorities are given in Table 6.3.1 and Table 6.3.2. It
should be pointed out that these elements are not ranked according to some criteria, but presented
according commissioning date and approved development plans from each responsible power
company in the region. Realization of all of these projects is necessary for secure and reliable
operation of regional transmission network (as described in previous subchapters).

Table 6.3.1: List of priorities until year 2010

Interconnected Year of
Interconnection line
countries commissioning

Ugljevik - S. Mitrovica BA - SER 2005/06


Kashar - Podgorica AL - MN 2006/07
C. Mogila - Stip BG - MK 2006/07
Florina - Bitola GR - MK 2006/07
Maritsa Istok - Filipi BG - GR 2007/08
Ernestinovo - Pecs (double) HR - HU 2007/08
(Filipi) - Kehros - Babaeski GR - TR 2007/08
Bekescaba - Nadab (Oradea) HU - RO 2008

Table 6.3.2: List of priorities between 2010 and 2015

Interconnected Year of
Interconnection line
countries commissioning

Zemlak - Bitola AL - MK 2010/15


Kashar (V. Dejes) - Kosovo B AL – CS 2010/15
(Nis) – (Leskovac) – Vranje - Skopje CS – MK 2010/15

It also should be pointed out that local networks also need to be reinforced to satisfy security and
reliability criteria, but this is not problem of transmission network then local supply problem. In
case of new production units, especially in UNMIK area, detailed analysis related to connection of
these units to power system network is required.

In Table 6.3.3 and Table 6.3.4 are presented some recommendations that would make operation of
regional transmission network more reliable and secure.

Table 6.3.3 – Recommendation for new transformers in new substations


Length
Country Line Voltage
(km)
Romania Arad-Timisoara 400 kV 55
Obrenovac-Belgrade ?-Pancevo 400 kV 80
Serbia
Drmno-Vrsac 400 kV 50
TPP Kosovo NEW-Pristina 400 kV 20
UNMIK
TPP Kosovo NEW-Kosovo B 400 kV 20
Interconnection Timisoara (ROM)-Vrsac (SCG) 400 kV 80

6.12
Table 6.3.4 – Recommendation for new transformers in new substations
Voltage New
Name of
Country levels transformers
substation
kV/kV MVA
Romania Timisoara 400/110 2x300
Vrsac 400/110 2x300
Serbia
Beograd ? 400/110 2x300
UNMIK Pristina 400/110 2x300

It should be pointed out that these recommendations are not according to the long term development
plans of power utilities in the region, but just ideas of authors that can resolve some of the identified
problems in regional network. They should be taken into consideration in future studies and
analyses. Without detailed analyses it is not possible to rank these recommendations.

6.13
7. LITERATURE
[1] Study, Development of the interconnection of the electric power systems of
SECI member countries for better integration with European systems: Project
of regional transmission network planning, Construction of the regional model,
2002, EKC,
[2] Study, Development of the interconnection of the electric power systems of
SECI member countries for better integration with European systems: Project
of regional transmission network planning, effects of the construction of new
proposed interconnection lines in SECI countries, 2002, EKC, EIHP, NEK,
ZEKC
[3] Project group on development of interconnection of electric power systems of
Black sea region, Regional Transmission Planning Project Regional model
construction for 2010. year, EKC
[4] Study, Audit of overcurrent protection relay settings on north-south
transmission corridor, HTSO-Hellenic Transmission System Operator, EKC,
2004
[5] Report of UCTE Executive Team "North-South Re-Synchronization", Load-
flow analyses, Technical committee UCTE, EKC, MVM, ZEKC, 2004
[6] Report of UCTE Executive Team "North-South Re-Synchronization", Load-
flow analyses, Technical committee UCTE, EKC, MVM, ZEKC, 2004
[7] SECI project group on development of interconnection of electric power
systems of SECI countries for better integration to the European system,
Regional Transmission Planning Project, Regional model construction for
2005. year(updating and expanding existing Regional Transmission Network
Model for the year 2005 ) and 2010. year, USAID, SECI
[8] Study, Technical and economical aspects of connection electric power systems
between Serbia and Macedonia with new transmission line 400 kV Niš-
(Leskovac-Vranje)-Skopje, Feasibility study, EPS-Serbia, EKC, 2003
[9] Study for new 400 kV interconnection lines between FYROM-Serbia and
Albania-Montenegro, Transient Security Assessment, Total Transmission
Capacities (TTC’s), European Commission, TREN Energy Directorate
General, EKC, HTSO,EPS,ESM,KESH,EPCG, 2003
[10] The study of long-term development of 400 kV, 220 kV and 110 kV
transmission networks in the area of the Republic of Serbia for the period until
2020, 1997, EINT
[11] Analysis of technical possibilities for the reconnection of the south-eastern
with the western part of UCPTE Interconnection, Institute Nikola Tesla,
Beograd, 1996
[12] Stability of the Synchronously Interconnected Operation of the Electricity
Networks of UCTE/CENTREL, Bulgaria and Romania, Final Report 2000
[13] Research Project, Evaluation Of Transfer Capabilities In Balkan
Interconnected Network, Technical Report, Joint Greek-Yugoslav Research,
General Secretariat for Research and Technology, Greece, EKC, HTSO-
GREECE, NTUA-GREECE, 2004
[14] Study for new 400 kV interconnection lines between FYROM-Serbia and
Albania-Montenegro Energy Directorate General, HSSO, EKC 2003
[15] Report of UCTE Executive Team "North-South Re-Synchronization": Load-
flow analyses, Technical committee UCTE, MVM, ZEKC 2003
[16] Bosnia and Herzegovina and Republic of Macedonia Study on Gas and
Electricity Interconnection in the Trans European Networks, 1997
[17] Feasibility Study, 400 kV Transmission line Elbasan-Podgorica, FICHTNER,
July 2001
[18] Study, Upgrading of Transmission Lines 220 kV, ALSTOM 2001
[19] Feasibility Study, Rehabilitation of transmission network, DECON,BEA, EINT
2002
[20] Reconnection of the UCPTE Network and Parallel operation of the Bulgarian
and Romanian networks with UCPTE - SUDEL ad hoc Group 1996
[21] Technical feasibility study of interconnection of the electric power systems of
Bulgaria (NEK) and Romania (RENEL) with the interconnected power system
of Greece (PPC), power systems under EKC coordination and Albania
(KESH), for parallel and synchronous operation in compliance with UCPTE
regulations and standards - PPC - RENEL - NEK - EKC - Nikola Tesla
Institute 1995
[22] Technical feasibility study of upgrading at 400 kV of the existing 150 kV line
Bitola - Amyndaio, PPC, NEK, EKC, 1998
[23] Technical feasibility study of a new interconnection tie-line at 400 kV between
Greece and Bulgaria, PPC, NEK, EKC, 1998
[24] Technical feasibility study of Interconnection of the Balkan Countries
(Albania, Bulgaria and Romania) to UCPTE - PHARE A 1994 and PHARE B
1996
[25] Project of the construction of 400 kV OHL Niš-Skopje, Elektroistok 2001
[26] 400 kV Interconnection Macedonia – Bulgaria, 400 kV Overhead Transmission
Line and 400/110 kV Stip Substation, Environmental Impact Assessment
(EIA)
[27] 400 kV Interconnection Macedonia – Bulgaria, 400 kV Overhead Transmission
Line and 400/110 kV Stip Substation, Techno-Economical Aspects
[28] Elaboration “Perspectives of one part of 220 kV network, Phase I, EINT
Beograd, 2003.
[29] Annual report of EKC for 1999, 2000, 2001, 2002 and 2003
[30] Annual report of the Electric Power Utility of Serbia, 2000, 2001, 2002, 2003
[31] Annual report of the Electric Power Utility of FYR of Macedonia, 2001, 2002,
2003,
[32] Annual report of the Transelectrica, 2001, 2002, 2003,
[33] Annual report of the NEK-Bulgaria, 2001, 2002, 2003,

You might also like