WORLEY STANDARD CALCULATION

Cathodic Protection Requirement Calculations

Project no 402000-01302 Calc no


Activity File
Client HESS
Project UJUNG PANGKAH DEVELOPMENT OFFSHORE PHASE II
Subject CATHODIC PROTECTION DESIGN
Rev AFC

Results Summary (DNV RP B-401)


Mass Requirement 1 Anodes Total Number of Required Anodes #DIV/0! Anodes
Current Requirement #DIV/0! Anodes

Input - Anode Data Input - Current Densities


Alloy Weight Wu 118.4 lb Structure above mudline
Life L 25 Yr Mean Current Density Idm(s) 0.0050 amp/ft2
Length ℓ in Initial Current Density Idi(s) 0.0140 amp/ft2
Height H in Final Current Density Idf(s) 0.0080 amp/ft2
Top Face FT in Structure below mudline
Bottom Face FB in Mean Current Density Idm(bm) 0.0000 amp/ft2
Internal Steel Diameter Di in Initial Current Density Idi(bm) 0.0000 amp/ft2
Utilization Factor UF 0.9 Final Current Density Idf(bm) 0.0000 amp/ft2
Electrochemical Capacity Ur 907 amp-hr/lb Coating Breakdown Factor
Anode - Seawater Potential Va 1.05 Volts Mean Fc(m) 0.1700
Structure - Seawater Potential Above Mudline Vs 0.80 Volts Initial Fc(i) 0.0200
Structure - Seawater Potential Below Mudline Vs1 Volts Final Fc(f) 0.3200
Seawater Resistivity r' 9.843 ohm.in Input - Additional Current Requirement Allowances
Input - Jacket Data (includes 5% of contingency) Conductor Allowance Ic 0 amp/well
Surface area coated area SA(c) 0 ft2 Number of Conductor Wells nc 0
Surface area above mudline SA(s) 375 ft2 Riser Allowance Ir 0 amp/riser
Surface area below mudline SA(bm) 0 ft 2
Number of Attached Risers nr 0
Calculation - Mass Requirement
Consumption Rate of Anode E 9.65 lb/amp-yr Ref: National Association of Corrosion Engineers,
Standard RP0176-83, "Corrosion Control of Steel, Fixed

Above Mudline (coated area included) Offshore Platforms Associated with Petroleum

Mean Current Requirement Im 0.0093863 amps Production", May 1983


Net Mass of Required Anodes W 2.52 lb
Required Number of Anodes Ns 1 Det. Norske Veritas, RP B401, "Cathodic Protection Design",
March 1986
Below Mudline
Mean Current Requirement Im 0.00 amps
Net Mass of Required Anodes W 0.00 lb W .UF
L=
Required Number of Anodes Nbm 0 E.Im

Total Number Anodes Reqd N 1

Calculation - Current Requirement


Perimeter of Cross-Section c 0.00 in
Area of Cross-Section Ac 0.00 in2 ΔV
Driving Voltage Above Mudline DV 0.25 V
I=
Ra
Driving Voltage Below Mudline DV1 1.05 V
i) Initial Current Req.above the mudline (coated area included)
Effective Radius
Circuit Resistance
r
Ra
0.00 in
#DIV/0! ohm
Ra =
r'
2 π⋅ℓ [
4ℓ
ln −1
r ]
Current Output Capacity I #DIV/0! A/Anode

413792093.xls Page 1 of 7 Rev AFC02


WORLEY STANDARD CALCULATION
Cathodic Protection Requirement Calculations

Project no 402000-01302 Calc no


Activity File
Client HESS
Project UJUNG PANGKAH DEVELOPMENT OFFSHORE PHASE II
Subject CATHODIC PROTECTION DESIGN
Rev AFC

Initial Current Requirement Ii 5.26 amps


Number of Initial Anodes Reqd Ni #DIV/0!

413792093.xls Page 2 of 7 Rev AFC02


WORLEY STANDARD CALCULATION
Cathodic Protection Requirement Calculations

Project no 402000-01302 Calc no


Activity File
Client HESS
Project UJUNG PANGKAH DEVELOPMENT OFFSHORE PHASE II
Subject CATHODIC PROTECTION DESIGN
Rev AFC

Calculation - Current Requirement Above the Mudline


ii) Final Current Req. above the mudline (coated area included)
Density of Anode Material r #DIV/0! lb/ft3
Final Weight Wf 11.84 lb
Final Effective radius r #DIV/0! in
Circuit Resistance Ra #DIV/0! ohm
Current Output Capacity I #DIV/0! A/Anode
Final Current Requirement If 3.00 amps
Number of final Anodes Reqd Nf #DIV/0!

Anodes Reqd Above Mudline Ns #DIV/0!

i) Initial Current Requirement below the mudline


Effective Radius r 0.00 in
Circuit Resistance Ra #DIV/0! ohm
Current Output Capacity I #DIV/0! A/Anode
Initial Current Requirement Ii 0.00 amps
Number of Initial Anodes Reqd Ni #DIV/0!

ii) Final Current Requirement below the mudline


Density of Anode Material r #DIV/0! lb/ft3
Final Weight Wf 11.84 lb
Final Effective radius r #DIV/0! in
Circuit Resistance Ra #DIV/0! ohm
Current Output Capacity I #DIV/0! A/Anode
Final Current Requirement If 0.00 amps
Number of final Anodes Reqd Nf #DIV/0!

Anodes Reqd Below Mudline Nbm #DIV/0!

Total Anodes Required N #DIV/0!

Conclusions

413792093.xls Page 3 of 7 Rev AFC02


WORLEY STANDARD CALCULATION
Cathodic Protection Requirement Calculations

Project no 402000-01302 Calc no


Activity File
Client HESS
Project UJUNG PANGKAH DEVELOPMENT OFFSHORE PHASE II
Subject CATHODIC PROTECTION DESIGN
Rev AFC

Results Summary (HESS Specification)

Summary of surface area


Zone 2 (m2) Zone 3 (m2) Zone 4 (m2)

0.00 33.22 0.00

Current Demand Calculation


Surface Area1) Current Densities Current Demand
Zones
m2 ft2 mA/ft2 mA
Zone 2 - EL (+) 3.00m to (-) 1.50m 2)
0.00 0.00 6 0.00
Zone 3 - EL (-) 1.50m to (-) 12.20m 34.88 375.49 6 2252.91
Zone 4 - EL (-) 12.20m to (-) 104.20m 0.00 0.00 2 0.00
TOTAL CURRENT DEMAND 2.25 A
Note:
1. Includes 5% of contingency
2. Submerged coated steel is 10% of total coated area

Anode Requirement

N = [(ix * Ax * 1/1000 + Ic) * T] / [E * W * u]

where N = Number of anodes


ix = current demand in region x (mA/ft2)
Ax = area in region x (ft2)
T = design life (hours) = 25 years = 219000 hours

E = energy capability (amp-hr/lb) = 907 amp-hr/lb

W = net weight of one anode (lb) = 118 lb

u = utilization factor = 0.9

Ic = conductor x allowance x no of conductor (amp)

ix * Ax = 2.25 A

Therefore

N= 5 ea

Anodes required based on HESS Specification are 5 ea

413792093.xls Page 4 of 7 Rev AFC02


PLATFORM
No Item Unit
WHP-B AUP CPP
1 Surface Area
- Zone 2 m2 844.614 552.578
- Zone 3 m2 1541.413 1061.532
- Zone 4 m2 3122.703 1615.637
Rev By Checked Date Comments