CRONOGRAMA DE EJECUCION DE OBRA VALORIZADO

OBRA : CONSTRUCCION: DE LA INSTITUCION EDUCATIVA NIVEL SECUNDARIO LEONCIO PRADO DE PUCARA

DEPARTAMENTO : PASCO PROVINCIA: PASCO DISTRITO: HUAYLLAY


LUGAR : C.P. PUCARA

PERIODO DE EJECUCION TOTAL


PARTIDA DESCRIPCION MONTO 01 MES 02 MES 03 MES 04 MES
01 SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04 SEM
924.37
01.00.00 OBRAS PROVISIONALES 924.37 924.37 100%
23884.68
02.00.00 TRABAJOS PRELIMINARES 23884.68 23884.68 100%
3179.91 3179.91 4239.88
03.00.00 MOVIMIENTO DE TIERRAS 10599.71 10599.71 100%
4082.73 4082.73 2041.37
04.00.00 OBRAS DE CONCRETO SIMPLE 10206.83 10206.83 100%
26690.46 20017.84 20017.84 20017.84 26690.46 20017.84
05.00.00 OBRAS DE CONCRETO ARMADO 133452.28 133452.28 100%
8257.00 9908.40 9908.40 4954.20
06.00.00 ESTRUCTURA DE MADERA Y COBERT 33027.99 33027.99 100%
231.09
07.00.00 PRUEBA DE CONCRETO 231.09 231.09 100%
3437.74 6875.48 6875.48 6875.48 5156.61 5156.61
08.00.00 MUROS Y TABIQUES DE ALBAÑILERIA 34377.39 34377.39 100%
8224.48 8224.48 8224.48 8224.48
09.00.00 REVOQUES Y ENLUCIDOS 32897.91 32897.91 100%
8329.34 8329.34
10.00.00 CIELORRASOS 16658.67 16658.67 100%
17412.03 17412.03 11608.02 11608.02
11.00.00 PISOS Y PAVIMENTOS 58040.10 58040.10 100%
1109.17 1663.76
12.00.00 CONTRAZOCALOS 2772.93 2772.93 100%
1737.74 2606.61
13.00.00 ZOCALOS 4344.35 4344.35 100%
17979.59
14.00.00 CARPINTERIA DE MADERA 17979.59 17979.59 100%
2260.86 1507.24
15.00.00 CARPINTERIA METALICA 3768.10 3768.10 100%
1968.04
16.00.00 CERRAJERIA 1968.04 1968.04 100%
3135.81 3135.81
17.00.00 VIDRIOS Y CRISTALES 6271.62 6271.62 100%
6281.12 6281.12 8374.83
18.00.00 PINTURA 20937.07 20937.07 100%
676.74
19.00.00 VARIOS 676.74 676.74 100%
1162.77 1550.36 1162.77
20.00.00 APARATOS Y ACCESORIOS SANITARIO 3875.90 3875.90 100%
1735.31 1041.18 694.12
21.00.00 INSTALACIONES SANITARIAS 3470.61 3470.61 100%
1212.38 519.59
22.00.00 SISTEMA DE AGUA FRIA 1731.97 1731.97 100%
736.63 1718.80
23.00.00 SISTEMA DE DESAGUE PLUVIAL 2455.43 2455.43 100%
1946.43 1703.12 1216.52
24.00.00 INSTALACIONES ELECTRICAS 4866.07 4866.07 100%
426.80
25.00.00 CANALIZACIONES Y/O TUBERIAS 426.80 426.80 100%
915.68
26.00.00 CONDUCTORES Y/O CABLES 915.68 915.68 100%
3033.72
27.00.00 ARTEFACTOS ELECTRICOS 3033.72 3033.72 100%
868.08
28.00.00 TABLEROS ELECTRICOS 868.08 868.08 100%
869.13
29.00.00 SISTEMA DE PUESTA A TIERRA 869.13 869.13 100%
970.53
30.00.00 SALIDA PARA INTERNET 970.53 970.53 100%
664.10
31.00.00 ACCESORIOS DE REDES 664.10 664.10 100%
515.20
32.00.00 TRABAJOS PRELIMINARES 515.20 515.20 100%
3193.36 798.34
33.00.00 MOVIMIENTO DE TIERRAS 3991.70 3991.70 100%
1676.96 1676.96 838.48
34.00.00 OBRAS DE CONCRETO SIMPLE 4192.40 4192.40 100%
944.97 708.73 708.73 2362.44
35.00.00 OBRAS DE CONCRETO ARMADO 4724.87 4724.87 100%
1519.22 1519.22 1215.38 1823.06
36.00.00 MUROS Y TABIQUES DE ALBAÑILERIA 6076.88 6076.88 100%
534.39 400.79 400.79
37.00.00 REVOQUES Y ENLUCIDOS 1335.98 1335.98 100%
3345.47 4460.62 3345.47
38.00.00 PISOS Y PAVIMENTOS 11151.56 11151.56 100%
3721.18 3721.18
39.00.00 CARPINTERIA METALICA 7442.35 7442.35 100%
266.48 266.48
40.00.00 PINTURA 532.95 532.95 100%
94.71 94.71
41.00.00 INSTALACIONES SANITARIAS 189.41 189.41 100%
12016.75
42.00.00 MOBILIARIO Y EQUIPAMIENTOS 12016.75 12016.75 100%

COSTO DIRECTO 489,337.54 31,928.61 37,373.38 34,900.52 37,322.03 31,816.16 34,781.31 37,540.14 25,168.87 18,533.67 21,854.05 21,747.50 23,265.13 25,032.52 35,384.67 42,333.51 30,355.47 489,337.54
GASTOS GENERALES 10 % 48,933.75 3192.86 3737.34 3490.05 3732.20 3181.62 3478.13 3754.01 2516.89 1853.37 2185.40 2174.75 2326.51 2503.25 3538.47 4233.35 3035.55 48933.75
UTILIDAD 10 % 48,933.75 3192.86 3737.34 3490.05 3732.20 3181.62 3478.13 3754.01 2516.89 1853.37 2185.40 2174.75 2326.51 2503.25 3538.47 4233.35 3035.55 48933.75
SUB TOTAL 587,205.05 38314.34 44848.05 41880.62 44786.43 38179.39 41737.57 45048.17 30202.64 22240.40 26224.86 26097.00 27918.15 30039.03 42461.61 50800.21 36426.56 587205.05
IMPUESTO 19 % 111,568.96 7279.72 8521.13 7957.32 8509.42 7254.08 7930.14 8559.15 5738.50 4225.68 4982.72 4958.43 5304.45 5707.42 8067.71 9652.04 6921.05 111568.96
PRESUPUESTO DE OBRA 698,774.01 45,594.06 53,369.18 49,837.94 53,295.86 45,433.47 49,667.71 53,607.33 35,941.14 26,466.08 31,207.58 31,055.43 33,222.60 35,746.44 50,529.31 60,452.25 43,347.61 698,774.01