PROJEC Improvement of Water Supply in Improvement of water supply in Pansemal, Rajpur Nag

T NAME
PIPE DETAILS FOR DISTRIB

DIA OF PIPE
SL.NO MATERIAL PN RATING BOQ LENGTH
mm

1 110 HDPE PE-100/ PN-10 41718


2 140 HDPE PE-100/ PN-10 4416
3 160 HDPE PE-100/ PN-10 2905
4 180 HDPE PE-100/ PN-10 637
5 200 HDPE PE-100/ PN-10 989
6 250 HDPE PE-100/ PN-10 1555
TOTAL 52220
water supply in Pansemal, Rajpur Nagar Parishad in Barwani District (M.P) & Kasrawad, Karhi Nagar Parishad in Khargo

PIPE DETAILS FOR DISTRIBUTION SYSTEM OF RAJPUR

AS PER DESIGN
LENGTH DIFFERENCE SOR RATE BOQ AMOUNT IN RS.
m

45270 3552 ₹ 900.00 ₹ 37,546,200.00


2369 -2047 ₹ 1,200.00 ₹ 5,299,200.00
638 -2267 ₹ 1,500.00 ₹ 4,357,500.00
689 52 ₹ 1,800.00 ₹ 1,146,600.00
574 -415 ₹ 2,200.00 ₹ 2,175,800.00
230 -1325 ₹ 3,300.00 ₹ 5,131,500.00
49770 -2450 ₹ 55,656,800.00
wad, Karhi Nagar Parishad in Khargone District (M.P)

AS PER DESIGN
AMOUNT IN RS. DIFFERENCE IN AMOUNT
₹ 40,743,000.00 ₹ 3,196,800.00
₹ 2,842,800.00 ₹ -2,456,400.00
₹ 957,000.00 ₹ -3,400,500.00
₹ 1,240,200.00 ₹ 93,600.00
₹ 1,262,800.00 ₹ -913,000.00
₹ 759,000.00 ₹ -4,372,500.00
₹ 47,804,800.00 ₹ -7,852,000.00
Improvement of Water Supply in Improvement of water supply in Pansemal, Rajpur Nagar Parishad
PROJEC (M.P)
T NAME
PIPE DETAILS FOR DISTRIBUTION SYSTEM

AS PER
DIA OF PIPE BOQ DESIGN
SL.NO MATERIAL PN RATING
mm LENGTH LENGTH
m
1 63 HDPE PE-100/ PN-9 202 0
2 75 HDPE PE-100/ PN-10 7342 24537
3 110 HDPE PE-100/ PN-10 1638 2069
4 160 HDPE PE-100/ PN-10 1104 979
5 200 HDPE PE-100/ PN-10 1076 815
6 250 HDPE PE-100/ PN-10 391 684
7 355 HDPE PE-100/ PN-13 300 554
TOTAL 12053 29638
Pansemal, Rajpur Nagar Parishad in Barwani District (M.P) & Kasrawad, Karhi Nagar Parishad in Khargone District
(M.P)

ILS FOR DISTRIBUTION SYSTEM OF PANSEMAL

BOQ AMOUNT IN
DIFFERENCE SOR RATE
RS. AS PER DESIGN
AMOUNT IN RS.
-202 ₹ 450.00 ₹ 90,900.00 ₹ -
17195 ₹ 600.00 ₹ 4,405,200.00 ₹ 14,722,200.00
431 ₹ 850.00 ₹ 1,392,300.00 ₹ 1,758,650.00
-125 ₹ 1,500.00 ₹ 1,656,000.00 ₹ 1,468,500.00
-261 ₹ 2,200.00 ₹ 2,367,200.00 ₹ 1,793,000.00
293 ₹ 3,300.00 ₹ 1,290,300.00 ₹ 2,257,200.00
254 ₹ 4,000.00 ₹ 1,200,000.00 ₹ 2,216,000.00
₹ 12,401,900.00 ₹ 24,215,550.00
i Nagar Parishad in Khargone District

DIFFERENCE IN AMOUNT
₹ -90,900.00
₹ 10,317,000.00
₹ 366,350.00
₹ -187,500.00
₹ -574,200.00
₹ 966,900.00
₹ 1,016,000.00
₹ 11,813,650.00
PROJEC Improvement of Water Supply in Improvement of water supply in Pansemal, Rajpur Naga
T NAME
PIPE DETAILS FOR DISTRIBUT

DIA OF PIPE
SL.NO MATERIAL PN RATING BOQ LENGTH
mm

1 110 HDPE PE-100/ PN-10 31485


2 140 HDPE PE-100/ PN-10 3598
3 160 HDPE PE-100/ PN-10 2422
4 180 HDPE PE-100/ PN-10 824
5 200 HDPE PE-100/ PN-10 1364
6 250 HDPE PE-100/ PN-10 1746
7 280 HDPE PE-100/ PN-10 377

TOTAL 41816
water supply in Pansemal, Rajpur Nagar Parishad in Barwani District (M.P) & Kasrawad, Karhi Nagar Parishad in Khargo

PIPE DETAILS FOR DISTRIBUTION SYSTEM OF KASRAWAD

AS PER DESIGN
LENGTH DIFFERENCE SOR RATE BOQ AMOUNT IN RS.
m
40497 9012 ₹ 900.00 ₹ 28,336,500.00
8379 4781 ₹ 1,150.00 ₹ 4,137,700.00
1374 -1048 ₹ 1,500.00 ₹ 3,633,000.00
287 -537 ₹ 1,800.00 ₹ 1,483,200.00
448 -916 ₹ 2,200.00 ₹ 3,000,800.00
724 -1022 ₹ 3,300.00 ₹ 5,761,800.00
865 488 ₹ 4,000.00 ₹ 1,508,000.00

52574 10758 ₹ 47,861,000.00


asrawad, Karhi Nagar Parishad in Khargone District (M.P)

AS PER DESIGN AMOUNT


IN RS. DIFFERENCE IN AMOUNT
₹ 36,447,300.00 ₹ 8,110,800.00
₹ 9,635,850.00 ₹ 5,498,150.00
₹ 2,061,000.00 ₹ -1,572,000.00
₹ 516,600.00 ₹ -966,600.00
₹ 985,600.00 ₹ -2,015,200.00
₹ 2,389,200.00 ₹ -3,372,600.00
₹ 3,460,000.00 ₹ 1,952,000.00

₹ 55,495,550.00 ₹ 7,634,550.00
PROJEC Improvement of Water Supply in Improvement of water supply in Pansemal, Rajpur N
T NAME
PIPE DETAILS FOR DISTR

DIA OF PIPE
SL.NO MATERIAL PN RATING BOQ LENGTH
mm

1 110 HDPE PE-100/ PN-10 20423


2 125 HDPE PE-100/ PN-10 0
3 140 HDPE PE-100/ PN-10 2233
4 160 HDPE PE-100/ PN-10 1338
5 180 HDPE PE-100/ PN-10 929
6 200 HDPE PE-100/ PN-10 215
7 250 HDPE PE-100/ PN-10 750
TOTAL 25888
er supply in Pansemal, Rajpur Nagar Parishad in Barwani District (M.P) & Kasrawad, Karhi Nagar Parishad in Khargone D

PIPE DETAILS FOR DISTRIBUTION SYSTEM OF KARAHI

AS PER DESIGN
BOQ AMOUNT IN
LENGTH DIFFERENCE SOR RATE
RS.
m
28525 8102 ₹ 900.00 ₹ 18,380,700.00
0 0 ₹ - ₹ -
1487 -746 ₹ 1,150.00 ₹ 2,567,950.00
81 -1257 ₹ 160.00 ₹ 214,080.00
850 -79 ₹ 1,800.00 ₹ 1,672,200.00
0 -215 ₹ 2,200.00 ₹ 473,000.00
53 -697 ₹ 3,300.00 ₹ 2,475,000.00
30996 5108 ₹ 25,782,930.00
Karhi Nagar Parishad in Khargone District (M.P)

AS PER DESIGN
AMOUNT IN RS. DIFFERENCE IN AMOUNT
₹ 25,672,500.00 ₹ 7,291,800.00
₹ - ₹ -
₹ 1,710,050.00 ₹ -857,900.00
₹ 12,960.00 ₹ -201,120.00
₹ 1,530,000.00 ₹ -142,200.00
₹ - ₹ -473,000.00
₹ 174,900.00 ₹ -2,300,100.00
₹ 29,100,410.00 ₹ 3,317,480.00