PROJECT: HHR- LINK 1B 17 April 2014

SUBJECT: REPLY TO QUERY ABOUT REINFORCEMENT OF CIS BEAM AT PIER 19B


SKETCH No. 001 Rev 00
Bars (15A)&(15B)
do not interfere
with Anchors as
clearly indicated.
Bars 4&5
distribution is
modified. Bar 3
diameter modified
accordingly