You are on page 1of 23

MOGUûNOSTI POBOLJŠANJA PLANUMA ŽELEZNIýKE PRUGE

IMPROVEMENT ALTERNATIVES FOR RAILWAY TRACK FORMATION

STRUýNI RAD
)
PROFESSIONAL PAPER
Mirjana TOMIýIý-TORLAKOVIû UDK: 625.113
ID: 204280588

1 UVOD 1 INTRODUCTION

Kolosek treba razmatrati kao jedinstveni sistem. The track has to be regarded as an inherent system.
Svaki pojedini element tog sistema, poþevši od šine i Each individual element of that system, beginning from
praga, preko zastora ili þvrste podloge (beton/asfalt), do rail and sleeper, via the ballast or solid bed
zaštitnog sloja planuma, mora da obezbedi dugotrajnu (concrete/asphalt), down to the formation protection
stabilnost koloseka, zahtevajuüi pritom malo održavanja layer, must provide long-term track stability requiring low
þak i pri velikim gustinama saobraüaja, poveüanim maintenance even at high train density, increasing
brzinama i osovinskim optereüenjima. running speeds and axle loads.
Planum koloseka je površina na kojoj se gradi The track formation is the platform upon which the
kolosek. Njegova glavna funkcija je da bude stabilna track superstructure is constructed. Its main function is
podloga za podzastorne i zastorne slojeve. On je veoma to be a stable foundation for the subballast and ballast
važna komponenta donjeg stroja, koja ima znaþajan layers. It is a very important substructure component,
uticaj na karakteristike i održavanje koloseka. Doprinosi which has a significant influence on track performance
elastiþnosti oslanjanja gornjeg stroja i otuda elastiþnom and maintenance. It contributes to the superstructure
ugibu šine pod optereüanjem toþka. Veliþina krutosti support resiliency and hence to the elastic deflection of
planuma utiþe na propadanje šine, praga i zastora, a the rail under wheel loading. The formation stiffness
takoÿe je uzrok nejednakog sleganja koloseka. magnitude influences rail, sleeper and ballast
Slika 1 [5], [7], [10] pokazuje uobiþajene termine za deterioration and also is a source of track differential
pojedine delove konstrukcije pruge. settlement.

 ravnost i projektovani nagib gornje površine;


Osnovni zahtevi za planum pruge jesu: Figure 1 [5], [7], [10] shows the usual terms of

 izdržljivost na ošteüenja;
individual parts of railway structure.

 Evenness and designed slope of surface;


The main requirements for track formation are:
 nosivost i sposobnost prenosa optereüenja od
 Resistance to wear;
 stabilnost na zamrzavanje;  Bearing and transmit the loading from the
gornjeg stroja;

 filterska stabilnost.
 Stability from freezing;
superstructure;

 Filter stability.

Prof. dr Mirjana Tomiþiü-Torlakoviü, Univerzitet u Beogradu Professor Mirjana Tomicic-Torlakovic, Ph.D.,


- Graÿevinski fakultet, Bulevar kralja Aleksandra 73, University of Belgrade - Faculty of Civil Engineering,
Beograd, Srbija Bulevar kralja Aleksandra 73, Belgrade, Serbia

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 39


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
Slika 1. Definisanje termina konstrukcije pruge
Figure 1. Definition of track structure terminology

Da bi planum ispunio te zahteve i služio kao stabilna To fulfill these requirements and to serve as a stable
osnova, moraju se izbeüi sledeüi oblici njegovog platform, the following formation failure modes must be

 prekomerna plastiþna deformacija;  Excessive plastic deformation;


propadanja planuma moraju biti izbegnuti: avoided:

 konsolidacija i veliki gubitak otpornosti na  Consolidation settlement and massive shear

 ubrzani gubitak otpornosti na smicanje pod  Progressive shear failure from repeated wheel
smicanje; failure;

 znaþajna promena zapremine (bubrenja i  Significant volume change (swelling and


ponavljanim optereüenjem od toþkova; loading;

 omekšavanje usled zamrzavanja i odmrzavanja  Frost and thaw softening;


skupljanja) od promene vlažnosti; shrinking) from moisture change;

 Formation attrition.
 osipanje planuma.
pri dejstvu mraza;

2 TRACK FORMATION BEARING CAPACITY


2 NOSIVOST PLANUMA
The decisive element in the connection between
Odluþujuüa veliþina u meÿusobnoj povezanosti track superstructure and substructure is the bearing
gornjeg i donjeg stroja pruge jeste sposobnost nosivosti capacity of the track formation.
planuma. Insufficient bearing capacity of the formation is

 lošom ili nedostajuüom drenažom;  Poor or lacking drainage;


Nedovoljna nosivost planuma uglavnom je izazvana: mostly caused by:

 spreþenim oticanjem vode s ramena zastorne  Prevented water flow off the ballast shoulders;
 Hollows in contaminated ballast due to insufficient
 udubljenjima u zaprljanom zastoru usled
prizme;
cleaning.
nedovoljnog þišüenja. The following phenomenons of formation deform-

 Permanent and recurrent irregularities of track


Uzroci nestabilnosti koloseka najþešüe su baš ations indicate the defects of the substructure [8], [10]:
deformacije planuma, a one se prepoznaju po sledeüim

 stalna i ponovna pojavljivanja grešaka geometrije  Muddy spots due to subsoil material pumping up
vidnim znacima [8], [10]: geometry;

 blatnjava mesta na površini zastora izazvana  Side squeezing out the wet soil (mostly clay);
koloseka; into ballast during train passing;

prskanjem blata uvis za vreme prolaska vozova  Track settlements due to formation deformation in

 boþno istiskivanje razmekšalog podtla, najþešüe


("pumpanje");
 Raising the track due to substructure freezing;
forms of ballast pockets and troughs full of water;

 Shoulders settlements due to embankment


 sleganje koloseka usled deformisanja planuma tla
kod preoptereüenog glinovitog podtla;

 Shoulders cracks as a result of embankment


shearing and shelling;
u vidu "džepova", "korita" ili "vreüa" u kojima se skuplja
voda; settlements;

40 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
 izdizanje koloseka od zamrzavanja u donjem stroju;  Massive formation shearing during raining.
 sleganje bankina usled klizanja ili školjkanja nasipa;
 pukotine na bankinama kao posledica sleganja
Track formation probable has the greatest influence
on the superstructure support resiliency and its modulus
of deformation varies along the track. Modulus of
 masivno smicanje planuma za vreme velikih kiša.
nasipa;
deformation Ev2 can be derived from the plate static load
Planum verovatno ima najveüi uticaj na krutost bearing test. Taking the nature of train load into
oslanjanja koloseka, a njegov modul deformacije varira consideration, the modulus of dynamic deformation Edin
duž pruge. Modul deformacije planuma Ev2 može se is more competent. By the dynamic plate test an impact
odrediti opitom statiþkog pritiska ploþom. S, obzirom na load for the short term is applied to the formation, which
prirodu optereüenja vozom, merodavniji je dinamiþki induced it to vibrate in damped oscillations. If the
pritisak ploþe, kada se odreÿuje dinamiþki modul settlement and amplitude of the oscillation are high, the
deformacije Edin. Pritom kratkovremensko udarno bearing capacity of the formation is low.

 moisture content and dry density,


optereüenje nanosi se na planum, þime se on pobuÿuje The formation bearing capacity depends on:
na prigušeno oscilovanje. Što su ugibi veüi, pri þemu su i
 plastic behaviour,
 stress/strain relationship.
amplitude prigušenih sopstvenih oscilacija veüe, to
planum ima manju nosivost.

 vlažnosti i suve gustine;


Kapacitet nosivosti planuma zavisi od: Sand and gravel consolidated easily and from that

 plastiþnog ponašanja;
have the high bearing capacity. Coherent soils, like dust
and clay, have the very low bearing capacity and it
 prirode veze napon-deformacija. largely depends on water content. Their bearing capacity
Pesak i šljunak zbijaju se vrlo lako i otuda imaju is higher in dry and hard conditions and falls with the
visoki kapacitet nosivosti. Kohezivna tla, kao što su water content increase, striving to plastic state, even to
prašina i glina, obiþno imaju vrlo nizak kapacitet liquid.
nosivosti, što umnogome zavisi od sadržaja vode. Njihov Table 1 [5] shows the requirements to be met by the
kapacitet nosivosti je veüi u uslovima isušenosti i substructure layers for the modulus of deformation and
oþvršüavanja, a opada s poveüanjem sadržaja vode, consolidation in the case of ballasted or solid track, and
iduüi ka plastiþnom stanju, sve do fluidnog. different line types.
Tabela 1 [5] pokazuje zahteve za pojedine slojeve
donjeg stroja po modulima deformacije i zbijenosti za
sluþaj koloseka u zastoru i na þvrstoj podlozi, a za razne
vrste pruga.

Tabela 1. Zahtevi za donji stroj


Table 1. Substructure requirements
Planum Zemljani planum
Zaštitni sloj
Formation Earth formation
Vrste pruge Protective layer
[MN/m2] [MN/m2]

V > km h @
Line tipe Dubina zamrzavanja
Standard thickness
Ev2 Edin DPr Ev2 Edin
[cm]
I II III
u zastoru
120 50 1,0 70 70 70 80 40
pruge velikih brzina ballast
HST u þvrstoj
(300) podlozi 120 50 1,0 40 40 40 60 35
slab
u zastoru
120 50 1,0 50 60 70 60 40
putniþki saobraüaj ballast
passenger traffic u þvrstoj
Novoizgraÿene

(230) podlozi 120 50 1,0 40 40 40 60 35


New track

slab
putniþki saobraüaj
passenger traffic
(160)
mešoviti saobraüaj
mixed traffic
(160) u zastoru
100 45 1,0 40 50 60 45 35
teretni saobraüaj ballast
freight traffic
(120)
lokalni saobraüaj
commuter traffic
(120)

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 41


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
lokalni saobraüaj
commuter traffic
(80) u zastoru
80 40 1,0 30 40 50 45 30
teretni saobraüaj ballast
freight traffic
(50)
u zastoru
120 50 1,0 70 70 70 80 40
pruge velikih brzina ballast
HST u þvrstoj
(300) podlozi 120 50 1,0 40 40 40 60 35
slab
u zastoru
80 40 1,0 30 40 50 45 30
putniþki saobraüaj ballast
passenger traffic u þvrstoj
(230) podlozi 100 45 1,0 40 40 40 45 30
slab
putniþki saobraüaj
Renewal track

passenger traffic
Obnovljene

(160)
mešoviti saobraüaj
mixed traffic
(160) u zastoru
50 35 1,0 20 25 30 30 25
teretni saobraüaj ballast
freight traffic
(120)
lokalni saobraüaj
commuter traffic
(120)
lokalni saobraüaj
commuter traffic
(80) u zastoru
40 30 0,97 20 20 20 20 25
teretni saobraüaj ballast
freight traffic
(50)

Ev2 – statiþki modul deformacije/modulus of static deformation


Edin – dinamiþki modul deformacije/modulus of dynamic deformation
DPr – zbijenost po Proktoru/Proctor density

3 ZBIJENOST PLANUMA 3 TRACK FORMATION CONSOLIDATION

Pri ispitivanju zbijenosti po Proktoru uzorak Compression test is the famous Proctor test where
materijala iz planuma zbija se u normiranoj þeliþnoj the formation material sample is compressed under
posudi tegom koji pada pod utvrÿenim uslovima, pri predetermined conditions in a calibrated receptacle with
raznim sadržajima vode. Proktorova kriva pokazuje do help of the drop weight, under five different water
kojeg se dozvoljenog sadržaja vode propisana zbijenost content at least. The Proctor curve shows which
može postiüi. Zbijenost po Proktoru odgovara zbijenosti admissible water content the prescribed compression
(radu na zbijanju od oko 60 t/m3), koja može biti value can be reached. The Proctor density corresponds
postignuta na mestu izgradnje pruge sa uobiþajenom to a compression (work done of approx. 60 t/m3) that
opremom za zbijanje. Ona se može definisati putem may be reached on the track's site with the help of the
stepena zbijenosti, koji predstavlja odnos izmerene usual compression devices. It can be defined by means
zapreminske mase u suvom stanju zbijenog tla i of compaction ratio, as the relation between the volume
maksimalne zapreminske mase pri optimalnoj vlažnosti weight in dry condition and in the most favourable water
dobijene Proktorovim opitom: content:
DPr = Jd / maxJ × 100 [%]

42 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
4 ODVODNJAVANJE PLANUMA 4 TRACK FORMATION DRAINAGE

It is well-known that water contained in the formation


Poznato je da voda u planumu negativno utiþe na
has an adverse effect on the correct track geometry.
održavanje pravilne geometrije koloseka, pa treba Therefore, the following measures are applied to reduce

 cleaning the ballast,


the water content in the formation:
 þišüenjem zastora;
nastojati da se njeno prisustvo smanji:

 održavanjem propisanog boþnog nagiba planuma;  maintain the formation cross fall,
 þišüenjem boþnih jarkova i drenaža;  cleaning of side ditches and drainage,
 ako je potrebno, izradom kontrolnih i ventilacionih  if necessary, building up the inspection and
okana. ventilation shafts.
Postoje dva tipa odvodnjavanja: otvoreni i zatvoreni There are two types of drainage facilities: open
sistem odvodnjavanja. drainage facilities and enclosed drainage facilities.
Otvoreni sistem odvodnjavanja obiþno se sastoji od Open drainage system usually consists of the ditches
jarkova i kanala pored pruge u usecima, u koje se and canals in track sides at embankment cuts in which
skuplja površinska voda. Širina jarkova u usecima the surface water should be led away. The ditches width
obiþno je 0,4 m, a dubina ispod planuma 0,4 m. Širina in cats is usually 0.4m and the depth below the formation
kanala iznosi od 0,8 m do 1,6 m i dubina ispod planuma is of 0.4m. The channel width is from 0.8m to 1.6m and
0,2 m. Njihov podužni pad treba da je bar 0,3%, a the depth below the formation is of 0.2m. Their
najviše do 3%. U sluþaju veüeg ili manjeg podužnog longitudinal inclination should be at least 0.3% and at
pada, najbolje je koristiti prefabrikovane betonske kanale most 3%. If the longitudinal inclination is below or above
ili kanale zidane lomljenim kamenom, na peskovito- these values, precast concrete canals in a fine gravel
šljunkovitoj podlozi [8]. Prednost otvorenog sistema bed or a coarse pavement of broken stone on fine gravel
odvodnjavanja u odnosu na zatvoreni jeste to što je have to be provided. The advantage of open drainage
dostupniji i lakše se održava. systems as compared to closed systems is that they are
Zatvoreni sistem odvodnjavanja ugraÿuje se tamo always easily accessible and easy to maintain.
gde nivo podzemnih vode treba da se smanji (<1,5 m Enclosed underground drainage facilities are
ispod gornje ivice šine), tlo oko pruge treba da se installed where the groundwater level has to be lowered
odvodnjava i filtrirana voda ili voda iz slojeva treba da se (<1.5m below TOR), the soil surrounding the track has to
odvede. Kod zatvorenog sistema odvodnjavanja, za be drained and percolating or layer water has to be led
smanjenje nivoa podzemne vode koriste se porozne away. If the groundwater level has to be lowered or the
cevi, propusne sa svih strana. Delimiþno propusne cevi soil has to be drained, the porous pipes, permeable all
(samo s gornje strane) odvode vodu koja se proceÿuje around, are advisable. Partial-permeable, only on their
bilo s površine, bilo iz slojeva konstrukcije. Podužni pad top, pipes are used to lead away percolating and layer
poroznih cevi mora da je bar 0,3%. One se polažu na water. The longitudinal inclination of percolating water
najmanje 60 cm ispod planuma. Kanal za polaganje cevi pipes should be at least 0.3%. They are laid at the depth
mora biti ispunjen šljunkom. Okna za održavanje below the formation of at least 60cm. The pipe ditch has
sistema za odvodnjavanje moraju da budu izraÿena na to be filled with gravel. Inspection pits enable the pipes
50–100 m, i ona se koriste za proveru i þišüenje cevi. to be checked and cleaned and they are provided at
Prednosti zatvorenog sistema odvodnjavanja nad distances of 50-100m. The advantage of enclosed
otvorenim jesu u tome što je potreban manji minimalni drainage systems against open systems is that their
pad i manji prostor, kao i to što ne zahteva reprofilisanje minimum inclination and the required space is less and
i uklanjanje korova. there is no need for reprofiling and weeding.
S dobro projektovanim sistemom za odvodnjavanje If the drainage system is correct designed, it is
moguüe je postiüi efikasno odvodnjavanje i u nekim possible to attain effective track draining and in some
sluþajevima þak odustati od obnove planuma. cases it would not be necessary to renewal the
formation.

5 POBOLJŠANJE PLANUMA 5 FORMATION IMPROVEMENT


U sluþaju kada je planum slabe nosivosti ili male In cases when the track formation is too weak or has
krutosti, što uzrokuje veüe troškove održavanja pruge too low stiffness, that resulting in high cost of track
kao celine, nameüe se potreba za poboljšanjem stanja maintenance, may dictate the need to improve the
planuma. Poboljšanje planuma je skupa mera. U formation conditions. The track formation improvement is
ekonomskim razmatranjima za razdoblje od trideset pet the expensive measure. At economic consideration in
godina, imajuüi u vidu poveüane troškove održavanja thirty five years time period, with taking into account the
ako se poboljšanje ne sprovodi, prednost ove mere maintenance costs, the advantage of the measure is
pokazuje se veü posle deset godina. obvious already after ten years.
Poboljšanje planuma treba da ispuni sledeüe Formation measures should meet the following

 ujednaþeni modul elastiþnosti duž cele dužine


zahteve:
 constant modulus of elasticity along the entire
requirements:

pruge od najmanje 4,5 kN/m2, optimalno 12 kN/m2;


 postepeni pad modula elastiþnosti sa dubinom,
track length of at least 4,5 kN/cm2, optimum 12 kN/cm2,
 gradual decrease of the modulus of elasticity with
inaþe nastaje pumpanje blata; depth, otherwise mud would pumped up,

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 43


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
 stvaranje toplotne izolacione brane;  create the heat insulation barrier,
 spreþavanje stvaranja vodene pare i – ukoliko se  preventing from vapour seal, if happens, draining

 low installation costs,


ipak pojavi – odvoÿenje vode nastale njenom off condensation water,

 mali troškovi ugradnje;  reduction operational hindrance during installation,


kondenzacijom,

 smanjenje poremeüaja saobraüaja pri izgradnji;  life time of more than twenty years.
 trajanost preko dvadeset godina. The formation improvement alternatives are listed in
Moguünosti poboljšanja planuma navedene su u Table 2 [9]. There are six general groups. As for the
tabeli 2 [9]. Postoji šest opštih grupa. Kako je za veüinu majority of these methods the experience is needed,
metoda potrebno iskustvo, þesto i specijalna oprema, often special equipment, it is advisable to consult with
preporuþljivo je konsultovati se sa struþnjacima. specialists.

Tabela 2. Moguünosti poboljšanja planuma


Table 2. Formation improvement alternatives
I Promene osobina planuma na terenu
Altering formation properties in place
A. Injektiranje
Grouting
1. Penetracija
Penetration
2. Zbijanje
Compaction
B. Injektiranje kreþom pod pritiskom
Lime slurry pressure injection
C. Delovanje strujom
Electrical treatment
1. Elektro-osmoza
Electro-osmosis
2. Elektrohemijska stabilizacija
Electrochemical stabilization
II Rekonstrukcija i zamena
Reconstruction and replacement
A. Zbijanje
Compaction
B. Zamena
Replacement
C. Stabilizacija dodacima
Admixture stabilization
1. Cement
Cement
2. Kreþ
Lime
3. Bitumen
Bitumen
III Primena asfalt-betona
Asphalt-concrete applications
A. Na punoj dubini
Full depth (replacing ballast and subballast)
B. U zaštitnom sloju
Underlayment (replacing subballast)
IV Stabilizacija klizišta
Slip stabilization
A. Odvodnjavanje
Drainage
B. Potporne konstrukcije
Retaining structures
C. Promena nagiba
Slope change
V Ugradnja zaštitnog sloja
Insertion of protective layer
VI Primena geosintetiþkih proizvoda
Geosintentic products implementation

44 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
5.1 Promena osobina planuma na terenu 5.1 Altering formation properties in place

5.1.1 Injektiranje 5.1.1 Grouting

Injektiranjem se ubrizgava materijal u tlo kako bi se By grouting a material is injecting into the soil to
ono ojaþalo, izmenilo ili kako bi se smanjila njegova strengthen it, change it or to decrease its permeability.
propustljivost. Penetration grouting strengthens the soil by bonding
Injektiranje penetracijom ojaþava tlo povezujuüi the particles or decreases the permeability by sealing
þestice tla, odnosno zatvaranjem šupljina smanjuje se voids, or both. For the successful grouting the soil or
propustljivost, ili oba. Za uspešno injektiranje rock must be relatively permeable. For reducing the
penetracijom, tlo mora biti relativno propustljivo. sands and gravel permeability in track formation the
Smanjenje propustljivosti peska i šljunka u trupu pruge injection with cement mortar, clay-water slurry, sand and
može se postiüi injektiranjem cementnim malterom, fly ash can be used. The particles of these materials are
glinenim muljem u vodi, peskom i leteüim pepelom. too large to penetrate voids in silts and clays, or in sands
ýestice ovih sredstava prevelike su da bi popunile and gravels with silt and clay components of more than
šupljine u mulju i glini, ili pesku i šljunku s više od 10% 10%. So, penetration grouting is unsuitable for use with
mulja i gline. Zbog toga, ova metoda nije poželjna u tlu fine silts and clays. Chemical grouts (commonly
koje sadrži mulj i glinu. Hemijska sredstva (najþešüe silicates) can penetrate into coarse silts and medium to
silikati) za injektiranje mogu prodreti u grubi mulj i u fine sands. In situ and laboratory permeability tests, as
srednji do fini pesak. Sposobnost sredstva za injektiranje well as a grain size analysis, will judge the ability of grout
da prodre u tlo procenjuje se na osnovu ispitivanja to penetrate into soil. It is suggested [9] that D15 of the
njegove propustljivosti na terenu ili u laboratorijskim soil should be at least 25 times the D85 of the grout
uslovima, kao i analizom veliþine zrna. Prema [9] particles. Strength tests are needed to estimate the
predlaže se da D15 tla treba da bude bar 25 puta D85 formation improvement.
þestica injekcionog sredstva. Takoÿe, potrebna je Compaction grouting compacts and/or displaces
procena poboljšanja þvrstoüe planuma. surrounding soil by the pressure of grout material bulb.
Injektiranjem zbijanjem se zbija i/ili potiskuje okolno Compaction grout is a very stiff mixture of cement, sand,
tlo pritiskom grudvom injekcionog materijala. Injekciono fly ash, clay and water, which is pumped by means of
sredstvo je veoma konzistentna mešavina cementa, pipe to the desired depth at pressure of 700-4000 kPa.
peska, pepela, gline i vode, koja se putem cevi do This treatment is not suitable for strengthening saturated
željene dubine pumpa pod pritiskom 700 –4000 kPa. cohesive soils which are incompressible, because the
Ovaj postupak je neprikladan za ojaþanje natopljenog soil can be displaced by the grout pressure in shallow
vezanog tla koje je nestišljivo, jer se može istisnuti tlo depths.
pod pritiskom sredstva za injektiranje u dubljim
šupljinama.
5.1.2 Lime slurry pressure injection

5.1.2 Injektiranje kreþom pod pritiskom The lime slurry is pumped into the soil through
pushed in pipes at pressure of 340 - 1700 kPa and
Kreþni mulj utiskuje se kroz cevi pod pritiskom od penetrates through fissures, cracks or permeable
340 do 1700 Mpa i prodire u naprsline, pukotine, te seams. Disadvantages are little control over the lime
propusne slojeve. Nedostatak je slaba kontrola distribution and danger of soil fracture and forming the
rasprostiranja sredstva i opasnost od loma tla i new cracks. Therefore the surrounding soil investigation
formiranja novih pukotina. Otuda je potrebno ispitivanje is needed to assess the effectiveness of slurry
okolnog tla za procenu efektivnosti prodiranja sredstva, distribution and laboratory tests to evaluate the soil
a laboratorijska ispitivanja za procenu poboljšanja improvement. Possible adverse effects are high water
osobina. Moguüi neželjeni efekti su visok sadržaj vode, content, high pressure which weakens the soil and water
visok pritisak koji slabi tlo, kao i zagaÿenje vode kreþom. contamination by the lime.
Opiti na železnici pokazuju da ovo poboljšanje traje Railway tests have shown that this improvement
relativno kratko pošto se pod optereüenjem od voza lasts for relatively short time as the clay-lime crumbs
usitnjavaju glineno-kreþne grudve [5]. were crushed under the train loads [5].

5.1.3 Delovanje strujom 5.1.3 Electrical treatment

Efektivan naþin poboljšanja mekanog glinovitog tla An effective way to improve soft clayey soils is to
jeste smanjenje sadržaja vode. Kako takvo tlo nije reduce the water content. As such soils are not free
moguüe slobodno odvodnjavati, mora biti izazvan tok draining, the flow into the drains must be inducted. For
vode ka drenaži. Prilikom izgradnje novih pruga, moguüa new track construction the soil strengthening by long
je konsolidacija dugovremenskim optereüivanjem. Kod term loading is possible. For existing track an alternative,
postojeüih pruga, alternativa í iako skupa í jeste putem although expensive, is through electro-osmosis. A direct
elektroosmoze. Elektriþna struja prolazi kroz tlo izmeÿu electric current is passed through the soil between
elektroda, pri þemu molekuli vode migriraju sa anode u electrodes and the water molecules migrate from the
okoline drenaže (katode), odakle se odvode. Ova anode into the drain surrounding (cathode), from where
metoda je ekonomiþna za zasiüena i normalno they are removed. This method is economical for
konsolidovana blata i gline s niskom koncentracijom saturated and normally consolidated silts and clays and

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 45


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
porne vode kao elektrolita. clays with low pore-water electrolyte concentration.
Tipiþan sistem elektrohemijske stabilizacije sastoji se Typical electrochemical stabilization system consists
od izbušenih gvozdenih ili aluminijskih cevi kao anoda of perforated iron or aluminium pipes as anodes installed
ugraÿenih na 1 do 5m od katoda. Kroz njih se u tlo about 1-5m away from the cathodes. A solution as
ubacuje rastvor kalcijum-hlorida, natrijum-hlorida, calcium, potassium, magnesium or aluminium chloride is
magnezijum-hlorida ili aluminijum-hlorida, koji se kreüe fed into the anodes entering the soil, and moves toward
ka katodama, gde se voda skuplja i uklanja. the cathodes, where water collects and removed.
Ispitivanja na terenu su poželjna za proveru In situ tests are desired to evaluate the effectiveness
efektivnosti metode. Izbor tipa anode i elektrolitskog of the method. Selection of the anode type and
rastvora zahteva hemijsku analizu minerala gline. To je electrolyte solution requires chemical analyses of the
vrlo skupa metoda i koristi se tamo gde druge nisu clay minerals. The method is very expensive and is to be
izvodljive. Glavna prednost, kao i kada je u pitanju used only where other are not feasible. The main
elektroosmoza, jeste to što se elektrode ugraÿuju sa advantage, as for electro-osmosis, is that the work can
suprotnih strana koloseka i što se ne prekida se be done without disrupting the train operation, because
saobraüaj prugom. the pairs of electrodes would be installed on opposite
sides of the track.
5.2 Rekonstrukcija i zamena
5.2 Reconstruction and replacement
5.2.1 Zbijanje
5.2.1 Compaction
Zbijanje je proces zgušnjavanja tla mehaniþkim
presovanjem, na raþun smanjenja zapremine šupljina Compaction is the process of soil densification by
ispunjenih vazduhom, pri þemu vlažnost ostaje nepro- mechanical pressing and in that way reduction in volume
menjena. Sto posto zasiüena tla se ne mogu zbijati, veü of air voids, while the moisture content remains
konsolidovati, što se postiže postepenim potiskivanjem unchanged. The aim of compaction is to improve soil
vode iz pora. Cilj zbijanja je poboljšanje svojstava properties, such as: increasing strength and stiffness;
planuma: poveüanje þvrstoüe i krutosti, a smanjenje decreasing compressibility, plastic strain under repeated
stišljivosti, plastiþne deformacije pod uþestalim optere- load, permeability, and reducing swelling and shrinking.
üenjem, propustljivosti, bubrenja i skupljanja. Meÿutim, However, density is the most commonly used parameter
poveüanje gustine je parametar koji se najþešüe koristi for specifying the desired amount of compaction and for
za specifikaciju željene veliþine zbijanja i odreÿivanje determining the state of compaction and implies an
stanja zbijenosti i podrazumeva poboljšanje ostalih improvement in the other parameters.
pobrojanih parametara. A given compaction effort does not produce the
Data energija zbijanja ne proizvodi istu veliþinu same strength and stiffness for all soils, that is shown for
zbijanja i krutosti za svako tlo, što je na slici 2 pokazano the three soil types in Figure 2. For the same effort the
za tri vrste tla. Za istu energiju, procenat zbijanja poveüava

Slika 2. Uticaj vrste tla na promenu zbijanja i krutosti sa energijom zbijanja


Figure 2. Effect of soil type on variation of compaction and stiffness with compaction effort

46 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
se kako tlo postaje krupnije – slika 2a [9]. Za isti percent compaction increases as the soil becomes more
procenat zbijenosti, rezultujuüa krutost se poveüava, od coarse-grained – Figure 2a). For the same percent
gline, preko prašine, do peska – slika 2b [9]. Razlike su compaction the resulting soil stiffness increases from
još veüe za konstantnu energiju zbijanja. Ovo je važno clay to silt and sand - Figure 2 b). The contrast is greater
uzeti u obzir prilikom odreÿivanja potrebne energije for constant compaction effort. These are important
zbijanja na terenu. considerations in determining the required compaction
Zbijanje se najþešüe radi ploþama i valjcima (statiþni effort for a given application.
i vibracioni). Zbog njihove ograniþene efektivne dubine Compaction is most commonly done using surface
zbijanja, neophodno je zbijanje u slojevima od 15 do 30 rollers, static and vibratory. As the roller have the limited
cm. Postoje i tehnike dubinskog zbijanja udarnim effective depth of compaction, it works in layers of 15-
zbijanjem ili vibracionim zbijanjem vodenim mlazom. 30cm. Deep compaction techniques, by dropping heavy
weight or by inserting of vibration accompanied with
water jets, are available.
5.2.2 Zamena
5.2.2 Replacement
Ako se zasiüena ili skoro zasiüena tla dovoljno isuše,
mogu se ukloniti i zameniti zbijanjem u slojevima. Ovo je If saturated or nearly saturated soils can be dried
izgleda izvodljivije za grubo granulisana ili prašinasta tla, sufficiently, they can be removed and replaced by
nego za glinu koju je teško osušiti. Meÿutim, granulisana compaction in layers. This would more likely be feasible
ili prašinasta tla neüe biti zasiüena ako nisu ispod nivoa for coarse-grained or silty soils than for clayey soils,
podzemne vode, pa je potrebno odvodnjavanje terena which are much difficult to dry. However, coarse-grained
za vreme njihovog uklanjanja i zamene. Ako zbijanje nije or silty soils would probably not be saturated unless they
izvodljivo, zasiüena tla, posebno meke gline, potrebno je were below the ground water table and dewatering of the
ukloniti i zameniti tlom koje ima vlažnost pogodnu za site would be required during the soil excavation and
zbijanje. replacement. If consolidation is unfeasible, the saturated
Organska tla neprihvatljiva su za planum, te se soils, especially soft clays, would need to be removed
moraju ukloniti i zameniti pogodnim tlom. and replaced with soil which has moisture suitable for
compaction.
Organic soils are unacceptable as a track formation
5.2.3 Stabilizacija dodacima and must be replaced by an acceptable soil.

Kao dodatak iskopavanju i zameni sa zbijanjem tla, ili 5.2.3 Admixture stabilization
površinskom zbijanju, osobine tla se mogu poboljšati
mešanjem s materijalima kao što su cement, kreþ, As a supplement to excavation and replacement with
bitumen i leteüi pepeo. compaction, or to surface compaction, soil properties
Mešanje se najbolje izvodi specijalnom opremom za can be improved by mixing in materials such as cement,
mešanje i usitnjavanje. ýesto se koristi konvencionalna lime, bitumen and fly ash.
oprema – drljaþe, buldožeri, grejderi, skreperi. Mixing is best performing by special
Specijalne mašine iskopavaju sloj tla, prevoze ga u mixing/pulverizing equipment. Conventional equipment
mešalice i rasprostiru promenjeno tlo sa zadnje strane is frequently used, like harrows, bulldozers, graders,
bubnja mešalice u neprekidnom procesu. Moguüi su scrapers. Some special machine excavates a soil layer,
zahtevi za poveüanje ili smanjenje postojeüeg sadržaja transports it to mixing drum and deposits the modified
vode pre dodavanja aditiva, kako bi se postigli prihvatljivi soil out the drum rear end in continuous process.
rezultati. Increasing or decreasing the existing moisture content
Cement se može upotrebiti za stabilizaciju skoro svih may be required prior to adding the stabilizing material in
vrsta tla, izuzev organskih, slanih ili sulfatnih materijala. order to achieve acceptable results.
Krupnozrni šljunak zahtevao bi više cementa, a teške Cement may be used to stabilize almost all soil
gline otežavaju mešanje. Najpogodniji je široko except organic, salt or sulphate materials. Coarse gravel
graduiran pesak i šljunak. Uopšte, ova stabilizacija treba requires high cement content and heavy clays show
da se ograniþi na tla s manje od 35% þestica koje mixing difficulties. Broadly-graded sands and gravels are
prolaze kroz sito (0,075 mm) i imaju indeks plastiþnosti best suited. Generally, this stabilization should be limited
manji od 30% [9]. to soils with less than 35% passing the 0,075 mm sieve
Cementnom stabilizacijom postižu se sledeüa and a plasticity index of less than 30% [9].
Cement stabilization achieves the following formation
 poveüana þvrstoüa, ukljuþujuüi i zateznu;
poboljšanja osobina planuma:

 Increases strength including tensile;


performance improvements:
 poveüana krutost;
 poveüana otpornost na uslove vlaženje–sušenje i  Increases stiffness;
 Increases resistance to wet-dry and freeze-thaw
 smanjenje propustljivosti, osim kod glina;
zamrzavanje–otapanje;

 Lowers permeability, except for clay;


condition;
 smanjenje bubrenja u plastiþnim glinama.
Koliþina potrebnog cementa menja se s tipom tla i  Decreases swelling of plastic clays.
zahtevanim osobinama, ali je obiþno izmeÿu 5 i 15% od The amount of required cement will vary with the soil
težine suvog tla. type and required properties, but falls within the range of
5-15% of dry weight of soil.

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 47


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
Cementom stabilizovana tla, postavljena preko tla s Cement stabilized soils over soils with a lower
manjom krutošüu zbog pojave horizontalnog napona stiffness will develop horizontal incremental stress can
zatezanja, mogu puüi i izgubiti neke konstruktivne uloge. crack under the train load and lose some of its structural
Kreþ se može upotrebiti za poboljšanje veüine tla u benefits.
planumu, koja sadrže neke frakcije minerala gline (min Lime may be used to treat most soils that have at
7% od težine) i indeks plastiþnosti veüi od 10%. Dobro je least some clay fraction (min 7% by weight) and
poznato da glinovito tlo, pomešano s kreþom, formira plasticity index which exceeds 10%. It is well-known that
grudvastu strukturu, smanjujuüi bubrenje s vodom i a clayey soil mixed with lime develops a crumbled
poveüavajuüi nosivost. Uobiþajena je koliþina izmeÿu 3 i structure that reduces the plasticity, reduces the
7% kreþa od težine tretiranog tla. swelling with water and increases strength. The required
Glavna prednost upotrebe kreþa jeste to što daje quantity of lime is directly related to clay content. A
trenutno i drastiþno poboljšanje obradljivosti glinovitog range of 3-7% by weight of lime will treat most soils.
tla, tako da þesto obezbeÿuje jedini naþin rada s mekim The main advantage of using lime is that it produces
vlažnim glinovitim tlom, pre nego metoda iskopavanja i immediate and dramatic improvements in the workability
zamene takvog tla. Takoÿe, kreþom tretirano tlo nije of clayey soil, often proving the only way to work with
podložno pucanju kao cementirano. Meÿutim, kreþ nije soft wet clayey soil other than excavating and replacing
pogodan ako se zahteva nagli porast þvrstoüe. it. Also, lime-treated soils are not as susceptible to
Kreþ se ponekad upotrebljava u kombinaciji s drugim cracking as cement-treated. However, lime is unsuitable
dodacima: sa cementom ili bitumenom da bi se if the rapid increase in strength is required.
poboljšala obradljivost tla i unapredilo mešanje i zbijanje, Lime is sometimes used in combination with other
s leteüim pepelom radi obezbeÿenja komponenti additives: with cement or bitumen to improve soil
minerala gline potrebnih za reaktivnost u þisto workability and promote mixing and compaction, with fly
granularnom tlu. ash to provide the clay mineral component required for
Kreþ se mešao u planume pruga s dugim šinskim reactivity in clean granular soils.
tracima, posebno na krajevima mostova (prelazne zona), Lime was mixed into CWR track formations,
radi spreþavanja sleganja, ali na linijama s velikom particularly at the ends of bridges (transition zones), to
gustinom saobraüaja nije pokazao dugotrajni efekat i prevent the recurring settlement, but in heavy traffic lines
postupak je ponavljan više puta [5]. show short-term effect and was repeated several times
Bitumen se koristi za vezivanje tla koje je uglavnom [5].
zrnasto sa ograniþenim þesticama (<0,075 mm), gde se Bitumen is used to stabilize the soils that are mostly
svrstavaju i þist šljunak i pesak. Nije pogodan za vlažna granular with limited plastic fines (less than 0.075mm), in
tla, pošto dodavanje teþnog bitumenskog stabilizatora which belong clear sands and gravels. It is unsuitable for
pogoršava karakteristike takvog tla, koje su potrebne za the wet soils, because adding the liquid bitumen
zbijanje. Mešavine tlo–bitumen prave se s razreÿenim worsens its characteristics needed for compaction. Soil-
asfaltom, emulzijom ili penom, radi unapreÿivanja bitumen mixtures are made with asphalt cutback,
procesa mešanja. Bitumen poveüava þvrstoüu tla i emulsion or foam to promote mixing with soil. Bitumen
smanjuje njegovu propustljivost. Ako se previše increases soil strength and decreases its permeability. If
bitumena doda, smanjuje se þvrstoüa. Da bi se postigla too much bitumen is added, strength will decrease. To
vodootpornost, bitumenska emulzija može da se prska achieve waterproofing, bitumen emulsion can be
po površini zbijenog planuma i utiskuje u njega, tako da sprayed on the surface of the compacted formation and
tanki bitumenski film spreþava prodiranje vode. Ovaj penetrate downward, so the thin bitumen film prevents
proces može da bude efikasan za obradu planuma koji water infiltration. This process may be effective for the
omekšavaju u prisustvu vode, pa nivo podzemne vode railway formations that soften in the presence of water,
mora da bude dovoljno nizak. U tom sluþaju, so the groundwater level must be low enough. In that
razmekšavanje tla ne izaziva voda zarobljena ispod case the softening is unlikely due to water trapped
bitumena. beneath the bitumen.

5.3 Primena asfalt-betona 5.3 Asphalt-concrete application

Asfalt-beton je mešavina bitumena i drobljene stene. Asphalt-concrete is a mixture of bitumen and


Preporuþena mešavina za planum pruge jeste široko crushed stone. The recommended mixture for track
graduiran lomljeni kamen (maksimalne veliþine zrna od formation use is broadly-graded crushed stone
25 do 37 mm) s nešto više bitumena i sitnog agregata (maximum grain size of 25-37mm) with slightly more
nego za kolovoze, i sa 1í3% šupljina. bitumen and aggregate fines than in highway, and with
Dva naþina primene asfalt-betona u planumu pruge 1-3% air voids.
jesu: po celoj dubini zastorne prizme ili samo u donjem Two ways of using asphalt-concrete in the track
delu zastorne prizme. substructure are: either in full-depth ballast bed or in
Uþinci asfalt-betona mogu se proceniti iz uloga ballast bottom. In both cases the crib and shoulder of the
zastora i planuma pruge. ballast remain.
The effectiveness of the asphalt-concrete design can
 veüa vertikalna nosivost, ali manja podužna i
Za zastor: be evaluated from the ballast and formation functions.

 Increased vertical bearing, but decreased lateral


For the ballast:
 elastiþnost oslanjanja koloseka je smanjena,
boþna otpornost;
and longitudinal resistance;
pošto asfalt-beton ima viši modul od zastora, ali

48 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
 Track resiliency is reduced because asphalt-
 efikasno odvodi atmosfersku vodu;
elastiþnost pruža donji stroj;

 podbijanje nije moguüe u primeni asfalt-betona


concrete has a higher modulus than ballast, but most of

 Effectively shed water coming onto the track;


the resiliency gives the formation;

 Tamping is not possible with asphalt-concrete in


celom dubinom, pa je podešavanje vertikalne geometrije

 za istu debljinu zastora, asfalt-beton smanjuje


otežano;
full-depth ballast and track vertical geometry will be

 For a given ballast thickness, asphalt-concrete will


naprezanje donjih slojeva, sve dok ostaje neošteüen, što difficult;
znaþi da pucanje mora biti spreþeno pravilnim

 obezbeÿena je izolacija za zaštitu od mraza;


projektovanjem; reduce stress on bottom layers as long as it remains

 ne podstiþe rast vegetacije;


undamaged that means the cracking must be prevented

 obezbeÿeni su apsorpcija buke i smanjenje  Frost protection will be provided;


by proper design;

 Vegetation growth will not be promoted;


 rekonstrukcija koloseka je mnogo teža i skuplja.  Noise absorption and vibration attenuation will be
vibracija;

 Track renewal will be much more difficult and


affected;
 na smanjenje naprezanja može se uticati
Za planum:
expensive.
 zaštita od mraza može da se smanji ako je
pravilnim projektovanjem;
 On the stress reduction can be influenced by
For the formation:
debljina sloja asfalt-betona manja od debljine zastora,
 Frost protection could be less with the asphalt-
proper design;
 spreþeno je meÿusobno prodiranje þestica zastora
zbog boljeg rasprostiranja optereüenja;
concrete if the layer depth is less than the ballast depth,
 spreþeno je „pumpanje” finih þestica nagore iz
i planuma;
 Interpenetration of ballast and formation grains will
because of the better load spreading;

 spreþeno je habanje planuma zastorom;


drugih slojeva donjeg stroja;
 "Pumping up" of fines from the other substructure
be eliminated;
 obezbeÿeno je odvoÿenje površinske vode.
 Formation attrition by ballast is eliminated;
layers will be prevented;
Bolje je sloj asfalt-betona postaviti na zaštitni
 Water shedding is provided.
drenažni sloj, nego direktno na planum, jer on
predstavlja dobru osnovu za razastiranje i zbijanje asfalt-
A granular drainage layer beneath the asphalt-
betona .
concrete, rather than directly on the formation, might be
Ukratko, da bi projekat sa asfalt-betonom u punoj
desirable, because it also provides a good bed for
visini zastora bio prihvatljiv, mora da ispuni dva uslova:
placing and compacting the asphalt.
1. smanjenje elastiþnosti oslanjanja koloseka i
In summary, two conditions must be met for the
smanjenje popreþne i podužne stabilnosti mora biti u
 Track resiliency reduction and the lateral and
asphalt-concrete in full-depth ballast design to be viable:
prihvatljivim granicama;
2. potreba za podešavanje geometrije i za
longitudinal stability reduction must be within acceptable
rekonstrukciju mora se iskljuþiti.
 The need for geometry adjustment and renewal
limits;
Zahtevana debljina asfalt-betona zavisi od
osovinskog optereüenja, gustine saobraüaja i krutosti
planuma. Tipiþni projekti u SAD koriste od 10 do 20 cm must be eliminated.
debeo sloj asfalt-betona samo u donjem delu zastorne The required thickness of the asphalt-concrete layer
prizme sa 12,5 do 25 cm tucanika do osnove praga. depends on the axle loads, the traffic amount and the
Primena asfalt-betona u SAD, u najviše sluþajeva, jeste formation stiffness. Typical designs in USA have used
prilikom rehabilitacije kratkih deonica koloseka kao što thickness of 10-20cm in ballast bottom with 12.5-25cm of
su ukrštaji, skretnice, prilazi mostu, tunelske podloge i ballast to the sleeper bottom. The majority of asphalt-
ukrštaji s putevima u nivou i ta mesta su þesto concrete application at USA railway lines have been for
problematiþna za održavanje [9]. rehabilitation short track sections such as turnouts,
crossings, bridge approaches, tunnel floors and level
crossings, because these are maintenance problematic
5.4 Stabilizacija klizišta areas [9].

Stabilizacija deonica koloseka s potencijalnim 5.4 Slip stabilization


klizištem je bitna jer klizišta narušavaju planum pruge.
Poremeüaji mogu biti grupisani na sledeüim mestima: The stabilization of track sections with potential slip
kosine useka; kosine nasipa; podloga nasipa; planum failures is essential, because they will affect track
pruge. formation. The failure location may be grouped as: cut
Poremeüaj ili kretanje kosina useka, formiranih za slopes, embankment slopes, embankment foundation
vreme izgradnje pruge, mogu prouzrokovati pomeranje i and track formation.
u planumu pruge i prekid saobraüaja, nanosima zemlje i Failure or movement of cut slopes, formed by track
stena na prugu. Problem stabilnosti obiþno nastaje od building, can cause movement of the track formation and
vode unutar njih, delovanjem pritiska i smanjenjem interrupt traffic by depositing earth and rock on the track.
otpornosti na smicanje. Rešenja ukljuþuju jednu The stability problem usually arises from water within the
moguünost ili više sledeüih moguünosti: skrenuti vodu slope exerting pressure and decreasing the shearing
koja dolazi odozgo, što je moguüe više; postaviti resistance. The solutions include one or more of the

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 49


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
drenaže unutar kosine; ublažiti kosinu; dodati ankere ili following possibilities: divert water coming from above to
potporne konstrukcije. Useci u ekspanzivnim glinama the extent possible, install drains within the slope, flatten
mogu izazvati poteškoüe zbog rastereüenja pri the slope, add anchors or retaining structures. Cuts in
uklanjanju zemlje, u kombinaciji sa izlaganjem ciklusima expansive clays can give difficulties, because of
vlaženja i sušenja. Tada je potrebna zaštita od promene unloading from soil removal combined with exposure to
vlažnosti ili ublaženje kosina. wetting and drying cycles. Protection from moisture
Poremeüaj unutar postojeüeg nasipa obiþno je change or slope flattening may be required.
rezultat prodiranja vode usled jakih padavina i poplava, Failure within existing embankments usually results
koje smanjuju nosivost tla na smicanje i poveüavaju from water infiltration by heavy rainfall or flooding, which
težinu. Zaštita od velikih padavina je odvodnjavanje reduces the soil shear strength and increases its weight.
nasipa. Tamo gde se oþekuje poplava, kosine mogu biti Drainage of the embankment protects from the heavy
ublažene ili se prave berme da obezbede odgovarajuüi rainfall. In areas where flooding is expected, the slopes
faktor sigurnosti od poremeüaja. Alternativno, može biti have to be flattened or have berms to provide an
potrebno ojaþanje dodavanjem potpornih zaštitnih adequate safety factor against failure. Alternatively,
konstrukcija. Erozija postojeüih kosina nasipa takoÿe strengthening through the additional of retaining
smanjuje njihovu sigurnost, pa je poželjna preventivna structures may be necessary. Erosion of existing
zaštita. embankment slopes will also decrease their safety factor
Poremeüaj podloge nasipa þešüi je kod novih pruga, and slope preventive protection must be provided.
jer konsolidacija tla s vremenom pod težinom nasipa Failure of the embankment foundation is more
poveüava njegovu otpornost. Meÿutim, poveüane usually with new track construction, since consolidation
padavine i poplave mogu oslabiti osnovu nasipa i of the soil under the embankment weight will increase
kasnije, pa üe ublaženje kosina i ugradnja bermi takoÿe the foundation strength over time. However, increasing
smanjiti ove potencijalne poremeüajne sile. rainfall or flooding could weaken the foundation strength
Najkritiþnija moguüa situacija postoji kada je nasip na at a later time, so the flattened slopes and berms will
padini. Pomeranje nasipa može da se desi klizanjem reduce this potential force of failure as well.
nizbrdo po površinama kroz nasip ili kroz tlo unutar The most critical situation exists when the
padine, s pretpostavkom da su stepenasti zaseci bili embankment is on the side of a hill. Embankment
korišüeni da zadrže nasip na padini. To pomeranje može movement could occur downhill along embankment
nekada poþeti odmah nakon izgradnje pruge, a surfaces or through the soil within hill, assuming that
verovatnije kao rezultat promena u uslovima površinskog benches are used to key the embankment into the hill.
ili podzemnog odvodnjavanja. Ovaj problem mora da se This movement may begin after track construction, but
reši pre nego što se poremeüaj desi – obezbeÿenjem probably as a result of changes in surface or subsurface
pravilnog odvodnjavanja. drainage conditions. This problem must be corrected
before failure occurs by providing proper drainage.
5.5 Ugradnja zaštitnog sloja
5.5 Insertion of protective layer
Ako planum ne ispunjava postavljene zahteve,
potreban je zaštitni sloj odgovarajuüe debljine od If the track formation does not satisfy the stated
šljunkovito-peskovitog materijala odreÿene granulacije. requirements, the protective layer of appropriate
U suprotnom, takvo stanje planuma vodilo bi veüim thickness made of gravel-sand material definite grading
troškovima održavanja geometrije koloseka, smanjenju is needed. Otherwise, such formation state would lead to
veka trajanja cele pruge, smanjenju brzina vozova i tako high costs of track geometry maintenance, decrease of
dalje. track life cycle, reduction the train speeds and so on.

x nosivi sloj (raspodelom optereüenja na veüu


Zaštitni sloj ugraÿuje se sa sledeüim zadacima: The formation protective layer is inserted to fulfil the

x Supporting layer (by load distribution effect protects


following functions:

x zaštitni sloj od smrzavanja (efektom toplotne


površinu, štiti donji stroj od prevelikog naprezanja);

x Frost protective layer (by its thermal insulating


the subsoil from too high stress);

x filtrirajuüi i razdvajajuüi sloj (spreþavanjem mešanja


izolacije, štiti tlo ispod planuma, osetljivo na mraz);

x Filtering and separating layer (by preventing the


effect protects frost sensitive soils bellow the formation);
zastora s donjim strojem, kao i spreþavanjem migracije
finih þestica u zastor);
x izravnavajuüi sloj (ako je kolosek oslonjen
ballast from mixing in with substructure and fines from

x Equalizing layer (if track is supported unevenly and


rising into the ballast);

x pokrivajuüi
neujednaþeno i neogovarajuüeg boþnog nagiba);

x Covering layer (with low water permeability


sloj (sa smanjenom with unsuitable cross fall);
vodopropustljivošüu štiti tlo osetljivo na vodu od

x sloj za spreþavanje habanja planuma od strane x Attrition prevention layer (against ballast attrition);
površinskih voda); protects soils sensitive to water from surface water);

x Vibration attenuation layer (from vehicle, track and


x sloj za ublažavanje vibracija od vozila, koloseka i
zastora;
subsoil).
zemljanog trupa. Protective layer would have the following

 uglavnom vodonepropustan ili vodopropustan u  Mostly impermeable to water or permeable to


Zaštitni sloj treba da ima sledeüe karakteristike: characteristics:

odreÿenim granicama, tako da najveüi deo vode oteþe such extend that the majority of the water runs off the
po planumu; formation;

50 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
 filterski stabilan prema donjem stroju ili tlu, inaþe  Filter stable against substructure or subsoil,

 elastiþnost (modul elastiþnosti), što ujednaþenije


mu se poveüa debljina za 10cm ili se doda geotekstil; otherwise should be ticker by 10cm or a geotextile

 Elasticity (modulus of elasticity) as uniform as


should be inserted;

 pri debljini preko 30cm, ugraÿuje se i zbija u dva


od zastora ka donjem stroju;

 Thicker than 30cm, have to be laid and


possible from the ballast to the subsoil;

 trajan na abraziju i drobljenje.


sloja;

 Durable against attrition and crumble.


compacted in two layers;
Geometrijski zahtevi za zaštitni sloj, odnosno

 minimalne debljine 20 cm;


planum: The following geometrical requirements have to be

 boþni nagib najmanje 1:25–1:20 ili 4–5% s  Minimum thickness to be inserted is 20cm;
met by the protective layer, i.e. formation:

 Cross inclination of at least 1:25 – 1:20 or 4-5%


 ne sme da odstupa više od ±2 cm od
tolerancijom od 0,5%;

 Must not deviate by more than ±2cm from the


with a tolerance of 0.5%;

 mora biti ravan u podužnom pravcu (”2 cm na


projektovanog položaja;

 Must be plane in longitudinal direction (”2cm on


design position;
osnovici dužine 4 m), ne sme da ima ulegnuüa i
kolotrage, odnosno debljina zastora treba da je the basis of 4m), without any troughs or traffic traces, in

 na nasipima se izvodi do ivice kosine, a u usecima  On embankments must be up to edge of the slope
konstantna; other words must be of uniform thickness;

do sistema za podužno odvodnjavanje. and in cuts up to longitudinal drainage system.


Slika 3 [10] poredi raspodelu naprezanja na planum Figure 3 [10] compares the pressure distribution on
kod koloseka sa zaštitnim slojem i bez njega. formation by the track with and without protective layer.

Slika 3. Raspodela naprezanja na planum sa zaštitnim slojem i bez njega


Figure 3. Pressure distribution on formation with and without protective layer

Slika pokazuje da je pritisak na planum bez zaštitnog The figure shows that the pressure on the formation
sloja mnogo veüi i postavljaju se visoki zahtevi za without protective layer is much higher and this makes
nosivost tla. ýestice tla se penju i prljaju zastor, ugao high demands on the bearing capacity of the soil. Soil
rasprostiranja pritiska se smanjuje i pritisak na donji stroj fines coming up contaminate the ballast, the pressure
se poveüava. Usled zaprljanosti zastora, opada trajnost propagation angle is reduced and the pressure on the
efekta podbijanja, pa ono mora þešüe da se sprovodi. U subsoil increases. As the ballast is contaminated, the
sluþaju sa zaštitnim slojem, voda üe putem njega biti durability of tamping decreases and the cleaning has to
odvoÿena i neüe kvasiti donji stroj. Poveüana debljina be performed more frequently. In the case with
spreþava štete od zamrzavanja. Zaštitni sloj kao filter protective layer the water is led away through it and
spreþava penjanje finih þestica tla. Trajnost podbijanja je cannot soak into the subsoil. The increased thickness
velika, zastor se reÿe þisti.. prevents frost damage. The protective layer as a filter
prevents soil fines from rising. The tamping durability is
high, ballast cleaning becomes less frequently.
5.5.1 Dimenzionisanje zaštitnog sloja kao noseüeg 5.5.1 Protective layer dimensioning as the bearing layer
Da bi zaštitni sloj služio kao konstruktivni materijal, To serve like constructive material, the formation
mora da ima dovoljno veliki modul elastiþnosti i stabilnu protective layer have to be of high enough modulus of
akumulaciju plastiþnih deformacija pod ponavljanim elasticity and the stable plastic deformation accumula-
optereüenjem toþkova. Debljina zaštitnog sloja mora se tion under the repeated wheels load. The thickness is
birati tako da postigne zahtevanu nosivost planuma. Kod chosen in such way as to achieve the required bearing
tla osetljivog na mraz, treba ugraditi sloj za zaštitu od capacity of the formation. By the soil sensitive to frost, a
mraza. frost protective layer has to be inserted.
Tabela 3 daje pregled zahteva za zaštitni sloj Table 3 gives a summary of the requirements for the
planuma i pokazuje kako ih odrediti [5]. formation protective layer and shows how to prove its
suitability [5].

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 51


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
Tabela 3. Zahtevi za zaštitni sloj planuma
Table 3. Track formation requiremants
osobine zahtevi ispitivanje
properties requirements test / assessment
Proktorov opit/Proctor test
opit pritiska ploþom/plate load test
zbijenost/density
nosivost opit sa padanjem tereta/
nosivost/bearing capacity
bearing capacity light hammer
elastiþnost/elasticity
elastiþna deformacija/
elastic deformation

n a  15%
zbijenost/density Proktorov opit/Proctor test
sleganje minimizirana veliþina šupljina/
settlement minimized pore space dupli Proktorov opit/
bez habanja/no wear double Proctor test
mali udeo zrna/small portion of grains
d<0,063mm (<5%)
otpornost na mraz kriva granulometrijskog sastava/
dobro odvodnjavanje/good drainage
resistance to frost grading curve
prekid kapilarnog penjanja/
capillary breaking
filterska pravila/filter rules granulometrijski sastav/
filtersko dejstvo
bez prenosa finih þestica/ grain distribution
filtering effect
no fines transportation filterska pravila/filter rules
elastiþnost što veüi procenat zrna kvarcnog peska/ merenje ugiba praga/
elasticity highest possible portion of quartz sand measurement of the sleeper settlement

Prema [5] preporuþuje se sledeüi kriterijum za modul According to [5] the following criterion for modulus of

 za nove pruge: Ev2 • 120 MN/m2 DPr • 1.03  For the new tracks: Ev2 • 120 MN/m2 DPr • 1.03
deformacije i zbijenost zaštitnog sloja po Proktoru: deformation and Proctor's density is recommended:

 za postojeüe pruge: Ev2 • 80 MN/m2 DPr • 0.97  For the existing tracks: Ev2 • 80 MN/m2 DPr •

stroj, Vdozv može se izraziti empirijskom formulom The admissible pressure Vadm on formation protective
Dozvoljeno naprezanje na zaštitni sloj, odnosno donji 0.97

prema Klompu [5]: layer, i. e. subsoil can be empirically determined

Vdozv = 0,006 Edin/(1+0,7 logN)


according Klompp's formula [5]:

[MN/m2]
gde je: where are:
Edin [MN/m2] – dinamiþki modul elastiþnosti zaštitnog Edin [MN/m2] – modulus of dynamic elasticity of
sloja odnosno donjeg stroja, formation protective layer, i. e. subsoil
N – broj prelazaka optereüenja za vreme kritiþnog N – number of load alternations during the critical
perioda (kod tla osetljivog na vodu i mraz to su periodi period (rain and thaw periods for soils sensitive to water
kiša i otapanja). and frost)
Kod poznatog modula deformacije Ev2, dinamiþki When the modulus of deformation Ev2 is known, the
modul deformacije nevezanog tla može se uzeti kao: modulus of dynamic elasticity of incoherent soils may be
Edin = 1,2 - 2,5 Ev2. assumed as: Edin = 1,2 - 2,5 Ev2.
Tabela 4 [5] pokazuje orjentacione koeficijente Table 4 shows the approximate bed coefficient,
posteljice, dinamiþki modul elastiþnosti i dozvoljena modulus of dynamic elasticity and admissible
naprezanja na pritisak zaštitnog sloja za razliþita tla, compressive strain of different soils depending on the
zavisno od broja ponavljanja optereüenja, kada je zastor number of load repetitions for the ballast thickness of
debljine 30cm i modula deformacije 150MN/m2. 30cm and the modulus of elasticity of 150 MN/m2.
Nosivost se ocenjuje statiþkim modulom deformacije The bearing capacity is assessed by modulus of
Ev2, koji se odreÿuje opitom ploþom i dinamiþkim static deformation Ev2 which is determined in plate load
modulom deformacije Edin, koji se odreÿuje opitom s test, and modulus of dynamic deformation Evd which
padajuüim teretom. Otuda, da bi se debljina zaštitnog determined in drop hammer test. From there, to deter-
sloja odredila, moraju biti poznati sledeüi moduli mine the thickness of the formation protective layer, the
deformacije: modul deformacije planuma tla Ev1, following modules of deformation should be known: the
sopstveni modul deformacije zaštitnog sloja Ev2, te modulus of deformation of the earth formation Ev1, the
modul deformacije planuma pruge Epl. Sopstveni modul modulus of natural deformation of the protective layer
deformacije zaštitnog sloja kod adekvatne raspodele Ev2, and the modulus of deformation of the formation Ef.
zrna i zbijenosti zaštitnog sloja može da se usvoji od 150 The modulus of natural deformation of the protective

52 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
do 200 MN/m2. Modul deformacije planuma tla zavisi od layer by proper grain distribution and density may be
sadržaja vode tla. Nosivost planuma tla je za vreme assumed as 150 - 200 MN/m2. The modulus of defor-
otapanja u proleüe najmanja i tada veliki znaþaj ima mation of the earth formation depends on the water
ugraÿeni sistem odvodnjavanja. Minimalna vrednost content. The bearing capacity is lowest during the thaw
modula deformacije planuma tla može vrlo teško merno in spring, and then the drainage system becomes
da se odredi, te se radi s proraþunskim vrednostima. U enormously important. The minimum modulus of defor-
tabeli 5 date su orijentacione vrednosti zavisne od mation of the earth formation is very hard to determine
materijala tla i hidroloških uslova [5]. by measures and, therefore, calculated values are
applied. In Table 5 the approximate values, depending
on the type of soil and hydrological cases, are given [5].

Tabela 4. Koeficijenti posteljice, dinamiþki modul elastiþnosti i dozvoljena naprezanja na pritisak


zaštitnog sloja za razliþita tla, zavisno od broja ponavljanja optereüenja
Table 4. Bed coefficient, modulus of dynamic elasticity and admissible compressive
strain of different soils depending on the number of load repetitions

Klasifikacija tla/ Vadm[N/cm2]


c [N/cm2] Edin = 1,2 - 2,5 Ev2
Soil classification N=106 N=107
3 10 1,2 1
loše/bad
4 20 2,4 2
srednje/medium 7 50 5,8 5,1
9 80 9,6 8,1
dobro/good
11 100 10,2 10

Tabela 5. Orjentacione vrednosti modula deformacije planuma tla zavisno od materijala tla i hidroloških uslova
Table 5. Approximate modulus of deformation of the earth formation depending on type of soil and hydrological cases

dodatni zahtevi za moduli deformacije/


udeo zrna/additional modulus of deformation
vrsta tla
requirement grain Ev1 [MN/m2]
type of soil
d  0,1mm
share Hidrološki sluþajevi/hydrological cases

1 2 3
muljevit ili glinovit šljunak/
10-20% 60 30 20
silty or clayey gravel
muljevit ili glinovit pesak/
10-20% 50 25 20
silty or clayey sand
jako muljevit ili glinovit šljunak odn. 20-30% 40 20 15
pesak/
highly silty or clayey gravel e.i. sand >30% 30 15 10
lako plastiþni
25 15 10
slightly plastic
mulj ili glina/ srednje plastiþni
25 15 10
silt or clay medium plastic
jako plastiþni
20 15 10
very plastic
Hidrološki sluþajevi/Hydrological cases:
1 – nema dodatnog natapanja, nenaþet planum / no additional soaking, integer formation
2 – povremeno natapane, loše oticanje vode / occasional soaking, bad water drainage
3 – stalno natapanje, bez oticanja vode / permanent soaking, no water drainage

Pri izrazito maloj nosivosti planuma tla, kada je Ev1 < When the bearing capacity of the earth formation is
10 MN/m2, najbolje je sprovesti zamenu tla. Debljina very low, when it is Ev1 < 10 MN/m2, it is advisable to
zaštitnog sloja planuma pruge može se dimenzionisati replace the soil. According the Figure 4 [5], the thickness
zavisno od predviÿene brzine na pruzi i nosivosti of the track formation protective layer can be dimen-
(modula deformacije) planuma tla, prema dijagamu na sioned depending on target line speed and the bearing
slici 4 [5]. capacity (modulus of deformation) of the earth formation.

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 53


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
Slika 4. Dimenzionisanje debljine zaštitnog sloja planuma pruge
Figure 4. Dimensioning the thickness of track formation protective layer

Prema standardima nemaþkih železnica [6], s Furthermore, according to DB standards [6], with
poznatom vrednošüu modula deformacije planuma tla known value of the modulus of deformation of the earth
Ev1 i zahtevanog modula deformacije zaštitnog sloja Ev2, formation Ev1 and required value of modulus of
putem dijagrama na slici 5, može se odrediti minimalna deformation of the protective layer Ev2, with help of the
debljina zaštitnog sloja. diagrams in the Figure 5, the minimum protective layer
thickness can be determined.

Slika 5. Odreÿivanje minimalne debljine zaštitnog sloja iz poznatog Ev1 i zahtevanog Ev2
Figure 5. Determination the minimum protective layer thickness from known Ev1 and required Ev2

ORE komitet D117 [1], na osnovu velikih serija ORE Committee D117 [1], on the basis of the major
merenja i proraþuna, dao je traženu ukupnu debljinu, series of measures and calculations, gives the desired
koja se sastoji od 25 cm zastora i jednog ili više total depth consisting of a 25cm ballast layer and one or
meÿuslojeva ispod njega. Na slici 6 prikazane su krive more intermediate layers below it. In the Figure 6, the
koje se koriste na raznim železnicama (DB, SNCF, curves used by various railways (DB, SNCF, SBB)
SBB), na osnovu CBR indeksa. Slika takoÿe ukazuje i based on the CBR (California Bearing Ratio) index, are
na razne naþine klasifikacije tla, kao što je putem CBR plotted. Figure 6 also indicates the various scales for
indeksa, modula elastiþnosti i prema UIC preporuci classification of soils, such as CBR, modulus of
719R. deformation, and according to UIC leaflet 719R.

54 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
Slika 6. Podaci iz ORE D117
Figure 6. Data from ORE D117

Još jedan naþin odreÿivanja preporuþene debljine One more way of determination the recommended
zaštitnog sloja zajedno sa zastorom, zavisno od thickness of the protective layer together with ballast bed
koeficijenta posteljice zastora c i geometrije pragova, dat related to the coefficient of ballast c and the sleeper
je u tabeli 6 [5]. geometry is given in the Table 6 [5].

Tabela 6. Debljina zaštitnog sloja + zastor zavisno od koeficijenta posteljice zastora c i geometrije pragova
Table 6. Thickness of protective layer+ballast related to the coefficient of ballast c and the sleeper geometry

osovinsko optereüenje
pragovi
axle load 200 250 300
sleepers
[kN]
dužina razmak
lenght spacing c[kN/cm3] 50 100 50 100 50 100

debljina (zastor+zaštitni sloj)


240 55 thickness (ballast+protective layer) 60 30 80 45 100 65
[cm]
debljina (zastor+zaštitni sloj)
260 55 thickness(ballast+protective layer) 45 30 65 35 80 50
[cm]

Linija prosejavanja materijala zaštitnog sloja The usual grain mixture applied for formation
planuma pruge prikazana je na slici 7 [5]. Šrafirano protective layer is represented in Figure 7 [5]. In the
podruþje je dozvoljeno podruþje prosejavanja prema DB shaded surface have to be the scatter of admissible
propisima. Za izradu planuma u sluþaju tla osetljivih na grading curves according to DB regulations. For the
vodu, njegov zaštitni sloj treba da je od vodonepropusne formation construction in the case of water sensitive
mešavine zrna KG1, koja ima najveüi modul deformacije soils, its protective layer would consist of the water
od 250 MN/m2. impermeable grain mixture KG1, which has the highest
modulus of deformation of 250 MN/m2.

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 55


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
Slika 7. Mešavina za zaštitni sloj planuma pruge
Figure 7. Grain mixture for formation protective layer

5.5.2 Uloga odvodnjavanja i filterska stabilnost zaštitnog 5.5.2 Protective layer drainage and filter stability roles
sloja
The protective layer material has to be of such grain
Materijal zaštitnog sloja treba da bude takvog mixture and density to prevent the soil fines migration
sastava zrna i zbijenosti da spreþi migracije i prodiranje and penetration in the ballast, while the water can pass
þestica tla u zastor, dok voda može da prolazi through (separating effect of protective layer). This is
(razdvajajuüa uloga zaštitnog sloja). To üe se ostvariti achieved by the grains irregularity degree of U = d60/d10
kada stepen neujednaþenosti zrna zaštitnog sloja bude • 15 and by fulfilled the filter role of Terzaghi (Figure 8
preko 15 i kad filtersko pravilo po Tercagiju (slika 8 [5]) [5]), with the known relation:
bude ispunjeno poznatim odnosom:
D15 ” 4 × d85
Time je krupnoüa zrna kao filtera ograniþena s gornje This limits the filter grain upwards and by this way
strane i spreþena je kontaktna erozija. Ako ovaj uslov ne the contact erosion is avoided. If this cannot be met,
može da se ispuni, mogu se primeniti geosintetici kao geosynthetic acting as a separating, filtering and
razdvajajuüi, filtrirajuüi i odvodnjavajuüi element. draining element may be used.
Osim uobiþajenog odvodnjavanja, kod železniþkih By railway lines in water-protected zones, except the
linija u zonama vodozaštite, u okviru posebnog projekta, usual drainage system, the water-block mats would be
primenjuju se i prostirke za zaptivanje u zaštitnom sloju inserted in the formation protective layer within the
planuma. separate design.
Pri tome, zaštitni sloj kao filter mora da ima Furthermore, the protective layer as a filter must to
vodopropustljivost veüu od planuma. Brzina protoka ne have permeability to water better than formation. The
sme biti toliko velika da þestice budu isprane, i to je flow rate must not be so high that soil particles are
filterska stabilnost (filterska uloga zaštitnog sloja), što je rinsed out and this is hydraulic filter stability (filtering
zadovoljeno ako je: effect of protective layer), which is fulfilled if:
D15 • 4 × d15
To znaþi da preþnik zrna zastora D15 mora biti veüi This means that the grain size of ballast D15 must be
od þetvorostrukog preþnika zrna zaštitnog sloja d15 i da larger than the fourfold grain size of formation protective
linija prosejavanja seþe liniju AB (pogledati sliku 8). layer d15 and the grading curve intersects the AB line
Ovim odnosom krupnoüa zrna zaštitnog sloja je (see Figure 8). The lower size of protective layer is
ograniþena s donje strane, þime je obezbeÿeno da je tlo limited by this relation and this guaranteed that the soil
ispod zaštiüeno i efikasno odvodnjavano. below is protected and drained effectively.
U sluþaju da ovaj uslov nije ispunjen, može se If this requirement may not be fulfilled, the two-
koristiti dvoslojna zastorna prizma: gornji sloj krupniji - layered protective layer can be used: on top coarse-
da odgovara zastoru a donji sitniji - da odgovara grained to suit the ballast bed and on bottom fine-
planumu (obiþno pesak), ali odnos ta dva sloja mora da grained (usually sand) to suit formation, but the

56 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
zadovolji filtersko pravilo po Tercagiju. Pri tome, poþetna relationship between these two layers must fulfil the
granulacija mora da ostane stabilna kroz vreme. Terzaghi's rule. In addition, the initial grain sizes should
be stable in time.

Slika 8. Filtersko pravilo po Tercagiju za zaštitni sloj planuma pruge


Figure 8. Filter role of Terzaghi for formation protective layer

5.5.3 Dimenzionisanje zaštitnog sloja za zaštitu od 5.5.3 Protective layer dimensioning as the frost
zamrzavanja protection

Problem zamrzavanja-odmrzavanja-omekšavanja tla The freeze-thaw-softening track subsoil problem


ispod pruge dovodi do znaþajnih i neujednaþenih leads to the significant and differential vertical
vertikalnih pomeranja koloseka i ubrzava njegovo displacements of track and accelerates its deterioration.
propadanje. Otuda, ako je tlo osetljivo na zamrzavanje, So, if the soil is frost sensitive, the protective layer must
treba sprovesti dimenzionisanje zaštitnog sloja za be dimensioned to the frost safety. There is a distinction
sigurnost tla od mraza. Pritom treba razlikovati potpunu i between full and partial frost safety. Partial frost safety
delimiþnu sigurnost od mraza. Delimiþna sigurnost znaþi means that a limited frost penetration in the soil is
da je pri jakim zimama dozvoljeno ograniþeno prodiranje admitted in severe winters. Full frost safety is prescribed
mraza u tlo. Potpuna sigurnost od mraza propisana je za for new lines, high-speed lines and ballastless tracks.
novoizgraÿene pruge, pruge za velike brzine i pruge s For all other types of lines the partial frost safety is
kolosekom na þvrstoj podlozi. Za sve ostale pruge admissible.

 frost index as the sum of the products of frost


dozvoljava se delimiþna sigurnost od mraza. The sensitivity to frost depends on:

 indeksa zamrzavanja kao zbira proizvoda dana s


Osetljivost na mraz zavisi od:

 degree of irregularity,
days and the frost temperature within a frost period,

 soil capillarity.
mrazom i temperature zamrzavanja tokom jednog

 stepena neujednaþenosti oblika zrna U=d60/d10,


perioda zamrzavanja;

 kapilarnosti tla ( kapilarnog penjanja vode).


There are three classes of sensitivity to frost (Figure
9 [5]):
Razlikuju se tri klase osetljivosti tla na zamrzavanje F1 – no sensitivity to frost
(dijagram na slici 9 [5]): F2 – low to medium sensitivity to frost (silty and
F1 – neosetljivo na zamrzavanje; clayey gravel and sand, depending on their degree of
F2 – mala do srednja osetljivost tla na zamrzavanje; irregularity and the share of fines with d”0.063mm in
F3 – vrlo osetljivo na zamrzavanje. percents in weight)
F3 – high sensitivity to frost

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 57


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
Malu, srednju do visoku osetljivost na zamrzavanje Low, medium to high sensitivity to frost has silty and
imaju muljevit i glinovit šljunak i pesak, zavisno od clayey gravel and sand, depending on their degree of
indeksa neujednaþenosti U i procenta udela u težini finih irregularity and the share of fines with d”0,063mm in
þestica sa d”0,063mm, prema slici 9. percents in weight according to Figure 9.

Slika 9. Klase osetljivosti tla na zamrzavanje


Figure 9. Classes of sensitivity to frost

Planum osetljiv na mraz takoÿe može da se zaštiti Formation sensitive to frost may also be protected by
ugradnjom termoizolacionog sloja (toplotne brane). Za to the insertion of thermal insulating layers (barriers).
su pogodni noseüi slojevi od lakog betona gustoüe oko Supporting layers of foam concrete with density of about
600 kg/m3 debljine izmeÿu 16 i 20 cm i ploþe od tvrde 600 kg/m3 of thickness between 16-20cm and plastic
penaste plastike gustoüe t30 kg/m3 debljine 5 do 10 cm foam slabs with density of • 30 kg/m3 of thickness
sa slojem peska debljine oko 10 cm odozgo za zaštitu between 5-10cm and protective sand layer on it of at
od proboja zrnima zastora, zavisno od konstrukcije least 10cm against crashing by the ballast, depending on
koloseka i klimatskih uslova. Ta mera se može sprovesti the track structure and climatic conditions, are suitable
u okviru þišüenja zastora specijalnim mašinama za for this. These works may be carried out during
þišüenje ili saniranje planuma. Kada se ove ploþe formation cleaning or improvement measures. When
kombinuju s geotekstilom, smanjuje se buka do 5 dB i these frost protective layers are combined with
prenos vibracija u donji stroj za 20 do 45%. geotextiles the noise level is decreased by least of 5dB
Kada zastor leži preko þvrste (betonske ili stenske) and vibration transfer in substructure by 20-45%.
podloge, mora se predvideti meÿusloj za apsorpciju When the ballast lies on solid (concrete or rock)
udara (npr. elastiþna podzastorna prostirka), kako bi se layers, shock-absorbing layers such as elastic mats
ublažilo njegovo sitnjenje pod toþkovima šinskih vozila. against crushing the ballast grains under the train
PVC folije debljine 2 mm mogu biti korisne kada je wheels, have to be provided.
planum veü raskvašen i jako zbijen, posebno pri PVC foils of thickness of 2mm can be useful, when
dubokim zastornim vreüama. the formation is already soaking and strongly
consolidated, especially with dip ballast troughs.

5.6 Ugradnja geosintetiþkih materijala


5.6 Geosintetic products implementation
Geosintetiþki materijali treba da doprinose smanjenju
naprezanja i deformacija i poboljšanju nosivosti i trajnosti Geosintetics contribute to a reduction of stress and
zaštitnog sloja planuma. Oni se obiþno ugraÿuju izmeÿu deformation, so as to improve and maintain the bearing
tla i zaštitnog sloja ili sloja za zaštitu planuma od mraza, capacity of formation protective layer. They are usually
polažu se na zbijeni i isplanirani planum i pokrivaju inserted between the subsoil and the formation or frost
zaštitnim materijalom. Oni treba da ispunjavaju protective layer, on the compacted and regulated
mehaniþke i hidrauliþke zahteve i treba da spreþe formation and covered by the protective materials. They
pumpanje finih þestica tla nagore. have to fulfil the mechanical and hydraulic requirements

 filterska stabilnost ne postoji izmeÿu tla i zaštitnog


Geosintetiþke materijale treba primenjivati ako: and to prevent soil fines being pumped up.

 filter stability between subsoil and protective layer


Geosintetics should be applied if:

 odvodnjavanje boþnim nagibom planuma tla nije


sloja;

 water drainage by cross fall of the earth formation


do not exists,
dovoljno;

58 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
 postoje mesta sa smanjenom nosivošüu planuma
 there are areas with low bearing capacity in the
is not sufficient,

 treba poboljšati dugovremensko ponašanje donjeg


tla;

 long-term behaviour of substructure on high-


earth formation,
stroja na jako optereüenim prugama.

 geotekstili: razdvajanje, filtracija, prenos, ojaþanje;


Vrste geosintetika i njihove funkcije jesu: density lines has to be improved.

 geomembrane: izolacija, razdvajanje, ojaþanje; x Geotextiles: separation, filtration, transmission,


The types of geosintetics and their functions are:

 georešetke: ojaþanje;
x Geomembranes:
reinforcement;
 geomreže: prenos; isolation, separation,
 geosaüe: ojaþanje;
x Geogrides: reinforcement;
reinforcement;
 vezani (kombinovani) materijali.
x Geonets: transmission;
x Geowebs: reinforcement;
Geosintetiþki materijali se uglavnom proizvode od

x Geocomposites: combinations.
poliestera, polipropilena ili polietilena.
U tabeli 7 skupljeni su zahtevi za geosintetiþke
materijale prema tehniþkim uslovima isporuke na DB [5]. Geosintetics are mainly of polyester, polypropylene
or polyethylene.
Table 7 gives a summary of the requirements to be
met by geosintetics according to the technical terms of
delivery of the DB [5].
Tabela 7. Zahtevi za geosintetike
Table 7. Requirements for geosintetics
najveüa vodopropustljivost
sila
najveüa sila rastegljivost permeability to water
proboja
zahtevi
masa zatezanja maximum [m/s]
plunger
mass maximum elongation
requirements puncture
[g/m2] tensile force under tensile
kv kh force
[kN/m] stress
[kN]
[%]
• 103
filter
100 - 250 • 1,0
filter
razdvojno-filterski sloj
zašt.sloja planuma
• 103 • 103
pruge • 30
• 300 • 16 • 2,0
separating-filtering layer ” 40
of the track formation
protective layer
razdvojno-filterski sloj
• 400 • 16 ” 85
• 103
planuma tla • 2,0
• 200 • 40 ” 25
separating-filtering layer
of earth formation
ojaþanje u zaštitnim
slojevima
• 10 ” 20
reinforcment of
formation protective
layers

Geotekstili se proizvode od mehaniþki, termiþki ili Geotextiles are manufactured from mechanically,
hemijski zbijanih izvlaþenih vlakana. Oni su obiþno thermally or chemically compacted extruded fibers,
pleteni, tkani ili netkani, u obliku prostirki. Mogu da budu which are usually needled, woven or no-woven, in the
pleteni ili nepleteni. Geotekstil ima više moguünosti za form of sheets. Geotextiles have the following
mesto ugradnje: izmeÿu zastora i planuma, izmeÿu alternatives for the installation place: between ballast
zaštitnog sloja i podtla, izmeÿu zastora i zaštitnog sloja, and formation, between protective layer and subsoil,
izmeÿu novog i starog sloja zastora. between ballast and protective layer, between the new
Jedna od glavnih primena geotekstila u koloseku and existing ballast layer.
jeste ispunjenje nekih od funkcija zaštitnog sloja, bilo da One of the primary applications of geotextiles in track
ga zamenjuje, bilo da ga dopunjuje. U tu svrhu, on treba is to fulfil some of the functions of protective layer, either
prvo da izdrži napone pri rukovanju i ugradnji i sile in place of or to assist it. For this purpose it will first
kojima je izložen tokom eksploatacije, ukljuþujuüi withstand the handling and installation and the forces
probode þestica zastora, istezanje da bi se prilagodio encountered in service, including puncturing by ballast
nepravilnostima terena, kao i da se odupre pokretima tla. grains, stretching to conform to the surface irregularities
Geotekstili se obiþno umeüu u kontaktnoj zoni, and to resist soil movements.
izmeÿu zaštitnog sloja i podtla, kao razdvojni, filtrirajuüi i Geotextiles are usually inserted in contact area

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 59


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
odvodnjavajuüi element, ali ojaþanje na zatezanje ima between protective layer and subsoil as separation,
ograniþenja. Što je manja nosivost tla, sve teži geotekstil filtering and draining element, but for tensile
treba da bude. Ispitivanja pokazuju da vlaknasti tkan reinforcement has limitations. The lower the soil bearing
geotekstil zadržava svoje dobre osobine i da na SNCF-u capacity, the heavier used geotextile. Experiments have
uveliko uspešno primenjuju teške geotekstile. Takoÿe, shown that needled filament geotextiles maintain their
pokazalo se da termiþki ojaþani getekstili potpuno good properties and the SNCF have successfully used
zaptivaju, delujuüi kao vodonepropusna membrana. heavier types for a long time. Also, they show that
Vibracije od vozova moraju se uzeti u razmatranje thermally bonded geotextiles got clogged and act as a
kada se projektuje koloseþna noseüa konstrukcija. water-proof membrane.
Kritiþne vibracije nastale u geosintetiþkim materijalima u The vibrations from trains must be taken into
srednjefrekventnom podruþju jesu oko 40 Hz [5]. Jaþina consideration when design the track supporting structure
na zamor geotekstila i veza s tlom (smanjenje reinforced by geotextiles. Critical vibration occurs in it at
koeficijenta trenja) mogu biti izloženi nepovoljnom uticaju about medium frequencies of 40 Hz [5]. The geotextile
vibracija, posebno pri veüim brzinama vozova. fatigue strength and the interface between geotextile and
Ugradnja geotekstila je mehanizovana u okviru soil (reduced friction coefficient) may be adversely influ-
postupaka obnove planuma i vrlo je ekonomiþna, jer enced by vibrations, especially at higher running speeds.
smanjuje troškove održavanja i obnove koloseka, a štete Geotextiles are inserted by machines during
od zamrzavanja tla se izbegavaju. Pri tome bi trebalo da formation renewal and are very economical, as reduce
je geotekstil bar 300 mm ispod dna praga da bi se maintenance and renewal costs and prevent the
izbeglo ošteüenje pri podbijanju, kao i poremeüaji od occurrence of frost damage. In addition, the depth of
þišüenja zastora. Graÿevinska mehanizacija ne sme da geotextiles installation would be at least 300mm below
se vozi preko geotekstila. Treba obezbediti glatku the bottom of the sleepers to avoid damage during
površinu na koju se polaže, bez oštrih objekata i tamping and deteriorating from ballast cleaning.
izloženost ultraljubiþastom zraþenju treba da je što je Construction equipment should not drive over the
moguüe kraüa. Treba izbegavati duple slojeve geotextiles. Smooth surface on which to lay it, without
geotekstila zbog moguünosti da se razviju ravni klizanja sharp objects, should be prepared and the exposure
izmeÿu njih. Naposletku, potrebno je obezbediti time to ultraviolet radiation as short as possible. Double
adekvatan sistem odvodnjavanja. layers of geotextiles should be avoided because of the
Geotekstili su þesto lakši za ugradnju od drugih possibility of slip planes between them. Finally, an
metoda poboljšanja planuma, pa njihova upotreba može adequate drainage system should be established.
rezultirati smanjenjem poþetnih troškova. Istovremeno, Geotextiles are often easier to install from other
geotekstili imaju ograniþenu trajnost poboljšanja koja improvement measures, so their use may result in a
pružaju, pa se moraju periodiþno menjati, što je težak lower initial costs. On the other hand, geotextiles have a
posao koji može prevaziüi dobit od njihove lake limited duration of improvement and have to be replaced
ugradnje. Dalje, geotekstili ne mogu ispuniti sve funkcije periodically, which is a difficult work which may offset the
zaštitnog sloja, pa je potrebno pažljivo razmotriti sve benefits of their ease installation. Further, it cannot fulfil
aspekte da bi se donela odluka o najekonomiþnijem all functions of protective layer, so the careful decision is
rešenju [9]. required for the most economical solution [9].
Geomembrane su nepropusni, savitljivi plastiþni Geomembranes are impermeable, flexible plastic
slojevi debljine od oko 0,15 mm do najviše 3 mm, bez sheets in thickness from 0.15mm to at least 3mm without
otvora, od neoprena, polivinil-hlorida, hlorisanog holes, made from neoprene, polyvinyl chloride,
polietilena ili drugih plastika. Radi ojaþanja na zatezanje, polyethylene or other plastics. For higher strength they
vezuju sa za mrežu od najlona ili poliestera, a površina are bonded to nylon or polyester mesh, and for
im se ohrapavljuje da bi se poveüao otpor smicanja s increased shearing resistance with soil their surface is
tlom. Osnovna funkcija im je spreþavanje prodiranja roughened. The main applications are to prevent
vode odozgo i vlage koja dolazi iz tla odozdo, kao i infiltration of water from the surface, to block water
zadržavanje proticanja podzemne vode. Otuda je proces coming from the soil below and to interrupt the flow of
spajanja ivica í bilo na gradilištu ili tokom proizvodnje í ground water. So, the edges connecting, either at the
kritiþan, pa mnoge membrane propuštaju na šavovima. situ or during fabrication is considered critical as the
Geomembrane postavljaju se na planum, izmeÿu dva many of them leaking at borders. The membrane is
sloja peska debljine najmanje 50 do 100 mm, koji ih štiti placed at formation, between two sand layers of at least
od probijanja; one ne smeju doüi u kontakt sa zastorom. 50-100mm, which protected them from puncturing as
Ozbiljan problem javio bi se ako je suvišna voda they must not come in contact with ballast particles.
zarobljena ispod membrane, što može nastati od Severe problem will occur if excess water is trapped
ponavljanog optereüenja kod zasiüenih tla ili kretanjem beneath the membrane, that result from repeated
podzemne vode nagore. Tada bi ta voda morala da se loading by saturated soils or upward flow of ground
odvede. water. Then, that water must be drained away.
Membrane obezbeÿuju i razdvajanje þestica tla. Membranes also provide the soil separation.
Zbog svoje þvrstoüe na zatezanje imaju i izvesnu ulogu Although they have tensile strength and therefore certain
ojaþanja, ali to nije njihova zahtevana funkcija. reinforcement function, this is not its demanded function.
Alternativni metod za proizvodnju vodonepropusnih An alternative method for producing water imper-
barijera jeste prskanje bitumenom ili polimerom, ili meable barrier is by spraying bitumen or polymer, either
noseüe površine (obiþno nepleteni geotekstil), ili sloja the supporting surface (usually no-woven geotextil) or
peska na planumu. Da bi se spreþila mesta curenja, sand layer on formation. To avoid the leakage points, a
poželjan je zaštitni sloj peska preko bitumena. Površina protective sand layer over bitumen is advisable. The

60 GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62)


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)
mora biti pravilno oblikovana za oticanje vode pre surface must be first properly shaped for shedding water
prskanja, da se ne bi stvarali vodeni džepovi iznad before spraying, to avoid developing water-pockets
premaza. Nepovoljan efekat je zarobljena voda ispod above coating. The adverse effect again is of water
premaza. trapping beneath the coating.
Georešetke nastaju razvlaþenjem sintetiþkog Geogrids originate from strands stretched to align
materijala ili spajanjem niti u nizove molekula polimera s the long-chain polymer molecules for high strength and
velikom jaþinom i krutošüu. One se utiskuju u mešavinu stiffness. The grids interlock with the grain mixture within
þestica unutar zaštitnog sloja i deluju na rasprostiranje the protective layer to create the load-distributing and
optereüenja i smanjenje naprezanja. Na taj naþin, one tension-reducing effects. So, they bridge areas of poor
premošüavaju podruþja pruge male nosivosti i poveüaju bearing capacity and in general increase tensile rein-
njenu zateznu nosivost u svojoj ravni kada su forcement in their plane when the soil strains are exten-
deformacije tla zatežuüe. Dimenzije okaca mreže su sional. The mesh size is between 1.67×d80 and 40mm.
izmeÿu 1,67×d80 i 40 mm. Geonets are flat flow channels consisting of a hollow
Geomreže þine kanali sa strujanjem, koji se sastoje plastic core wrapped with a geotextile. Water from the
od šupljeg plastiþnog jezgra obmotanog geotekstilom. soil will pass through the geotextile and flow along the
Voda iz tla prolazi kroz geotekstil i protiþe duž šupljeg hollow core and perform its function as a transmission
jezgra, tako da geomreža ima funkciju prenosne drain. Geonet must be strong enough to maintain its flow
drenaže. Geomreže moraju da budu dovoljno nosive da channel under pressure from the soil.
izdrže protok kroz kanale pod pritiskom tla. Geowebs are plastic cells with open top and bottom,
Geosaüe þine plastiþne üelije otvorene i ka gore i ka filled with granular soil. Through their tensile strength
dole, ispunjene zrnastim tlom. Svojom þvrstoüom na they form a load bearing reinforced soil layer.
istezanje, formiraju ojaþan sloj tla koji nosi optereüenje. Geocomposites are combinations of different
Vezani materijali su kombinovani razni geosintetiþki geosinthetics, attaining at the same time more effects.
materijali, tako da se istovremeno postiže više efekata. For example, for reinforcement application it is best to
Na primer, za ojaþanje je najbolje polagati georešetku sa lay the geogrids bonded to a geotextile to provide better
geotekstilom, þime se obezbeÿuje održavanje nosivosti i reinforcement capability and separating filter effect under
rastavljajuüe filtersko delovanje pri promenljivim the changeable hydraulic requirements. By using such
hidrološkim zahtevima. Pri upotrebi ovakvog geosinthetic materials with multipurpose effect, the frost
geosintetiþkog materijala s višestrukim dejstvom, može protective layer may be reduced by 10cm.
se smanjiti debljina sloja za zaštitu od mraza za 10 cm.
6 CONCLUSION
6 ZAKLJUýAK
The main track formation function is to provide a
Glavna funkcija planuma pruge jeste da obezbedi stable platform for the track structure. To do this, the
stabilnu podlogu konstrukciji koloseka. Da bi to ispunio, failure modes must be avoided and the track formation
oblici propadanja se moraju izbeüi i planum pruge í kao as the first layer under the track superstructure must be
prvi sloj ispod gornjeg stroja pruge í mora da se improved. The current practice of railway track design
unapredi. Savremena praksa projektovanja pruga i and maintenance planning ignore this fact. Usually, the
planiranja održavanja zanemaruju tu þinjenicu. ýesto se decisions have been made on the empirical bases. The
odluke donose na osnovu iskustva. Prilika da se napravi opportunity for error exists because of the large variety
greška postoji zbog velike razliþitosti uslova na terenu i of field conditions and the changes in track service
promena u saobraüajnim zahtevima kroz vreme. demands over the time.
Iz ovog pregleda moguünosti unapreÿivanja planuma From this review of track formation improvement
pruge, može se zakljuþiti da je odluka o primenjenoj possibilities, it can be decided that the decision about
metodi rezultat jednog procesa. Prvo, mora se odrediti the applied method is the result of a process. First, the
uzrok problema u koloseku pravilnim istraživanjem cause of the track problem is determined by proper
planuma í na terenu i pomoüu laboratorijskih opita i investigations of formation in field and with help of
analiza. Moguüe funkcije i primenljivost postojeüih laboratory tests and analysis. Possible functions and the
moguünosti treba proceniti. To je kljuþni korak i applicability of existing improvement alternatives may be
predstavlja izazov za graÿevinskog inženjera struþnjaka evaluated. This is the key step and presents a challenge
za železnicu, zbog nedostatka uvida u trenutno stanje u to the railway track engineer, because of the lack of
toj oblasti. Posle toga, treba sprovesti uporednu state-of-the-art in that field. Afterwards, comparative
ekonomsku analizu tih moguünosti. Za najbolju metodu, economic analysis of these alternatives should be
pošto obiþno prethodna iskustva na istoj deonici carried out. For the best alternatives, as usually the prior
koloseka ne postoje, preporuþuje se da se sprovedu experiences at the same track section lack, it is
opiti na terenu. Po snimanju karakteristika pruge, u recommended to conduct the field trials. After monitoring
dovoljno dugom periodu, rezultate treba proceniti. the track performance for a sufficient time, the results
Veoma je korisno dokumentovati rezultate izabrane should be accessed. It is very useful to document the
metode poboljšanja planuma pruge za buduüu results of the selected improvement alternatives of track
primenljivu preporuku. formation for the future applicable recommendation.
Potrebu poznavanja stanja planuma pruge i The need for considering conditions of track
moguünosti sprovoÿenja postupaka poboljšanja trebalo formation and its improvement alternatives may be also
bi da prepoznaju i Železnice Srbije, jer üe bez toga trend recognized at Serbian Railways, because in contrary the
porasta troškova održavanja i obnove pruga biti sve increasing trend of track maintenance and renewal costs
oþigledniji. would be more evident.

GRAĈEVINSKI MATERIJALI I KONSTRUKCIJE 56 (2013) 4 (39-62) 61


BUILDING MATERIALS AND STRUCTURES 56 (2013) 4 (39-62)

You might also like