Minutes Of Meeting
会议时间:2017 年 10 月 30 日
会议地点:唐山冀东机电设备有限公司会议室(中国 唐山)
参会人员:
Participants:
蒙水泥建筑材料有限公司(以下简称 MBM)
唐山冀东装备工程股份有限公司(以下简称 JDEE)
to JDEE)
Page1 / 10
翻译 Translation:邹大鹏 Mr.Zou Dapeng、Ms.Zou
纪要 Content:
UBGS 项目在实施过程中遇到了不可预见的问题,给双方造成了很大困难,
以下共识和协议,以资共同遵守:
UBGS project which caused great difficulties for both parties. Now the site
construction is under final stage, for accelerate the progress of UBGS project,
site arrangement, the top management of MBM and JDEE have friendly
communication, the following agreements have been reached and shall abide
by both parties.
1. 关于项目整体工期
目前主生产线已经具备投产条件,将在供电后开始试生产。双方一致认
2 月 20 日为混凝土养护期,安排中国工人冬歇回国;从 2 月 21 日开始复工,
Page2 / 10
At the moment, the production line is ready for put into operation, it will start
commissioning after get the power supply. The both parties agree that the K31
is the main constraints for the completion of the project, consider the special
conditions of K31, after serious discussions by both parties, it agreed that the
31st March,2018 shall be the final date for the whole completion and ready for
load operation of the K31. the details are: 1st Dec.2017, the open caisson of
K31 finished, 8th Feb.2018, the concrete pouring for K31 finished, from 9th
workers back to China for winter break, from 21st Feb. 2018 return to work
1.1 保证冬季施工期间的混凝土正常供应,不影响施工进度;
To insure the normal concrete supply during the winter construction and not
人员);
To insure all of the construction workers (include the workers for multi-year
construction) can get the HG visas in time, not affect the workers come to the
site.
Page3 / 10
1.3 及时进行外部场地协调和铁路协调;
工程予以合理延期。
If the issues mentioned above can not be solved smoothly and caused the
obstacles to the normal construction, the MBM shall consider to give proper
2. 关于费用和付款
在 11 月 3 日前提交抢工增加费用明细,MBM 在 11 月 6 日前确认此费用,
并在一周内办理抢工人员的 HG 签证;
JDEE will spare no effort for put the labors, materials and equipment for catch
up the construction; the MBM shall be borne the related additional costs for the
MBM will pay USD500,000 before 30th November 2017, and pay the rest
finished. The JDEE will submit the detail cost list for the catch up construction
Page4 / 10
on 3rd Nov.2017, the MBM shall confirm and approve it before the 6th
Nov.2017 and manage the HG visas for the workers of catch up construction
within a week.
求的采购到场时间及时采购到位,不影响现场施工。
The MBM agree to supply the back fill soil and borne the cost for purchase the
back fill soil previously. The MBM shall confirm the detail cost list for purchased
back fill soil within 10 days after the date JDEE submit it to the MBM, and with
5 days after confirmation, the payment shall be paid to JDEE. The MBM shall
purchase the back fill soil to the site in future. The JDEE will submit the list for
the needed amount of back fill soil to MBM 5 days in advance and MBM shall
purchase the back fill soil to the site on time based on the requirement of JDEE
和 O&M 两个项目所有应付款。具体款项如下:
The MBM will do all they can do to ensure the construction related payments
can be paid in time and promised to pay all of the payable payments for both
UBGS project and O&M project before the 3rd Nov.2017. the detail as follows:
Page5 / 10
序号 金 额 amount
款项内容 name of payments 备注 remarks
No. (USD)
业主 9 月 18 日已经支付
UBGS 项目 2017 年 8 月份设备发运款
了另外 50%
(50%)
1 551,392.5 The another 50% have
Shipment payment (50%) for
already paid on
Aug.2017 of UBGS project
18th Sept.2017,
2.5%根据设计进度付款
5 2.5%TCP According to the design
progress 388,325
试后支付。
Within 7 days after sign this MOM, the MBM shall pay 50% of Interim Payment
is USD 388,325, the rest 50% shall be paid to JDEE after the JDEE finish the
3. 关于 UBGS 项目预付款保函、履约保函及工程延期责任
Page6 / 10
delay liability of UBGS project
解除,其中履约保函到期后,按照银行规定程序重新签署。
The MBM agree that both advance payment guarantee and performance
that the 31st March 2018 shall be the assessment date for the term “Liquidated
damages for delay in delivery” in the EPC contract. If JDEE failed to make the
K31 ready for load commissioning on 31st March 2018, the liquidated damage
for delay which is USD10,000 (in saying: ten thousand USD) per day for delay
shall be paid by JDEE, the maximum liquidated damage shall not exceed
USD300,000 (in saying: three hundred thousand USD). After settle this term
for the liquidated damage for delay, MBM can not, based on the related terms
of EPC contract, claim any other liquidated damages for delay to JDEE.
Page7 / 10
受冬季气温过低影响,JDEE 将在 2018 年 4 月份以后开始进行道路,屋
顶防水,建筑物泛水等非主生产线土建施工,MBM 不会因这些土建施工
Subject to the excessive low temperature in the winter, the civil works which
not for main production line such as road, roof water proof and building
water-floating shall be start the construction after the April, 2018 by JDEE. The
MBM will not claim for Liquidated damages for delay in delivery based on the
completion date of the civil works mentioned above are exceed the 31st
March 2018.
that the 31st March 2018 shall be the assessment date for the term “Liquidated
damages for delay in delivery” in the EPC contract. If JDEE failed to make the
K31 ready for load commissioning on 31st March 2018, the liquidated damage
for delay which is USD10,000 (in saying: ten thousand USD) per day for delay
shall be paid by JDEE, the maximum liquidated damage shall not exceed
USD300,000 (in saying: three hundred thousand USD). After settle this term
for the liquidated damage for delay, MBM can not, based on the related terms
of EPC contract, claim any other liquidated damages for delay to JDEE.
4. 其他需要尽快解决推进的事项
Page8 / 10
The MBM agree to sign the confirmation letter for JDEE entrust Mongolia sub
which revised by JDEE. It will be signed on 1st Nov, 2017 and send to JDEE.
For the packing plant reform project, the both parties agree that JDEE will
in charge of the installation and construction for this project. After MBM get
the quotation from local FLSimith branch, it will decide if JDEE can in
以上纪要对双方均具有约束力,双方将按照以上纪要内容切实履行各自
责任。
The MOM above has binding on both parties, the parties shall execute their
Page9 / 10
Mr.Kumar Mr.Li Shundong
Mr.Jia Jin
Mr.Shi Qingguo
Page10 / 10