Professional Documents
Culture Documents
ABSTRACT
The extensive survey project is the project work prescribed by the Visveswaraya
Technological University for the sixth semester students of Civil engineering, to acquire a
practical knowledge and application of theory and overcome the difficulties that could
arise in field during surveying. And also learn the use of different survey instrument and
to develop the team spirit at work. It also helps to develop the confidence in handling of
project. The department of civil engineering , Bangalore Institute of Technology is
planned to conduct, Extensive Survey Project work at Sri Ghati Subramanya
Doddaballapur taluk ,Bangalore rural district which is 70 Km away from Bangalore and
collecting survey data to design the following
1. To design irrigation tank to store water and supply water to agricultural lands. To design
the tank, suitable site to construct a bund is located by conducting Reconnaissance and
preliminary and final survey. Detail calculation is done for the required earth work.
Considering the rainfall and catchment area, water that can be stored in the tank is
estimated. The water collected is feed to the agricultural land by locating and designing a
suitable canal from the left bank of the bund.
2. A proposal is designed to supply water to PALPAL DINNE village by conducting survey
to locate the source, designing pipe line ,treatment plant, and overhead water tank. Pipe
line layout for village. And also design of sanitary system by conducting required survey
for laying pipeline and treatment plant for disposal of sanitary waste.
3. In highway project, the alignment is located between two given points at a distance of
1.5km. Reconnaissance is done along the alignment. It is located on the ground taking
longitudinal and cross- sectional details. Horizontal and vertical curves are designed by
fixing the gradients. Pavement is designed by taking the soil details. An estimation of
materials and constructions is prepared.
4 A proposal is designed to restore the existing water tank near PALPAL DINNE. Village.
The existing capacity of the tank is estimated and improved capacity of the tank is
calculated by raising the existing bund to a suitable height.
1.4 Methodology
The whole project is presented in four parts. The first part deals with the study of the
project area. It includes rainfall, climate, and topography and crop pattern of the region.
In second part presents the detailed survey work at the site including LS and CS of the
bund capacity contour, canal alignment. In the third part the design of bund or
embankment? The fourth part describes the design of canal land design of sluice gates.
1.5. INVESTIGATION AND STUDIES
1.5.1 : Topography of Catchment Area
Catchment area is the extent of geological area on the upstream side of project site which
drains the surface water flows due to rainfall on that area to the valley across which the
project is envisaged.
The study area consists of the catchments situated in a comparatively small area with the
maximum distance between two points of the study area being about 60 km. Geology are
very variable. The study area, consists of, quartzite, and sedimentary rock with tertiary
and quaternary volcanism. It consists of sandstone, marl, and limestone. All catchment
within the study area belong to the same climatic region (temperate humid), Precipitation
ranges from to 824mm/year.
Elevation ranges from about 49.35m above mean sea level to 846.645MSL.Most of the
catchments are rural with little urbanization. The proportion of forest varies between 14%
and 95catchments, over 70% of the surface area is forested.
Since the catchment area of the project is a part of the total catchment area the extent
which is the catchment area of existing Visveswariah pick up storage located within the
total catchment area of the project site. Catchment area comes under intercepted
catchment area
1. Good catchment
2. Average catchment
3. Bad catchment
The present catchment considered as average catchment since it is with moderate slopes,
little rocky out crops, partly cultivated lands and semi pervious soil.
4. To align the canal and determine the cutting and filling along the length of the canal.
5. To design the. i. Design of surplus weir with apron ii. Design of tank sluice. iii .Design of
canal drop.
In the catchment area and command area these will be a basic data in computing the yield
from the catchment and working out the water requirement of crops. For the present work
the rain fall data is obtained from the Meteorological department of India, and the Gram
panchayath office of S.S. Ghati.
1.8 HYDROLOGY
1.8.1 Assessment of yield:
The yield is mainly dependent on the quantity and distribution of rain fall in the
catchment area of the project. Besides following factors affect the yield.
1. The conditions of the area as regard geological formation, permeability of soil surface
slopes, wind, temperature and humidity.
2. The nature and quantity of vegetation in the area.
3. Humidity of the surface and subsurface in the area at the time of rain fall and existence of
surface water.
A long term gauge data of a stream or river at the project site enables a reasonable
assessment of yield at the site at the desired dependability. However in case of small
streams which are not gauged the yield will have to be computed based on individual rain
fall data of influencing rain gauge stations within or outside the catchment area of the
project.
Duty:
Duty represents the irrigating capacity of a unit of water. It is the relation between the
area of a crop irrigated and the quantity of irrigation water required during the entire
period of growth of that crop.
Delta:
Delta is the total depth of water required by a crop during the entire period from the day
of sowing to harvesting.
Crop period:
Crop period is the time, in days, that a crop takes from the instant of its sowing to its
harvesting.
Base period:
Base period for a crop refers to the whole period of cultivation from the time of first
watering for sowing the crop, to the last watering before harvesting.
Bibliography
1. ENGINEERING HYDROLOGY by SUBRAMANYA.K; Tata McGraw Hill New Delhi-
2008(Ed).
IRRIGATION ENGINEERING AND HYDRAULIC STRUCTURES By S.K GARG,
Khanna Publishers, New Delhi
2. ENGINEERING HYDROLOGY by SUBRAMANYA.K; Tata McGraw Hill New Delhi-
2008(Ed).
3. IRRIGATION ENGINEERING AND HYDRAULIC STRUCTURES By S.K GARG,
Khanna Publishers, New Delhi.
BASE
DELTA(Δ) AREA (A) VOLUME DUTY DISCHARGE
CROP PERIOD
In m hect m3 hect/cums cums
(days)
JOWAR 140 0.3 42 126000 4032 0.0104
TOTAL 126000 0.0104
1.2 Computation of water requirement
To calculate the yield at the site:-
Is found to be 18.9sq.km...The average annual rainfall recorded is found to be 82.71cm.
The average rainfall of a bad year may be taken as 2/3 to ¾ of mean of annual rainfall.
Taking it to be ¾ the bad year‘s rainfall 3/4x82.71=62.03cm. Assuming the run off co-
efficient for the concerned catchment area to be 20% average rainfall.
Therefore Annual yield= (20/100) x62.03 =12.406
Annual yield from catchment = [18.9x10002] X [12.406/100]
= 2.34X106 m3.
Assuming 10% of evaporation loss and 10% of seepage in reservoir= 80/100 x 2.34 x 10 6
Use full Water from catchment area = 1872000.0m³
Volume of that can be stored in tank = 2.34 x 106m³
1.6 Filling of tank : Depending of the extent of rain fall in the area the capacity
of small tanks is fixed as noted below
Gross Capacity of Tank =Live capacity + only one requirement of dead storage
evaporation losses irrespective of number of fillings.
As per minor irrigation department of Karnataka for minor tanks Strangers condition is
preferred
Cumulatve volume m³
300000
250000
200000
150000
100000
50000
0
800 805 810 815 820
Contour RL in m
Table 1.7: Top width and side slopes of the bund as per stranger’s recommendation
Height Top
Maximum D/s U/s
of dam width
freeboard in Side side
in (A) in
meters slope slope
meters meters
Up to
1.2 to 1.5 1.85 1.5:1 2:1
4.5
4.5 to
1.5 to 1.8 1.85 1.75:1 1.5:1
7.5
15 to
2.1 3.0 2:1 1.5:1
22.5
Downstream Side slope of the bund = 2:1
Upstream Side Slope of the Bund = 1.5:1
Table 1.8: Top width of the bund according to stranger’s recommendation are:
Height of dam above
foundation level [m] Top width of bund [m]
up to 4.5 1.8
4.5 - 7.5 1.85
7.5 - 15 2.5
15 - 22.5 3
Table 1.9: Top width of bund are selected as per this recommendations.
Height of dam above
foundation level [m] Top width of bund [m]
15m T = 0.2 x [Z+3]
30< T = [0.55 x √Z] + [0.2*Z]
T = 0.2 x [Z+3]
T = 0.2 x [15.42+3]
V= Velocity of flow
Q= Discharge
Q= AV
For a non-silting and non-scouring canal, velocity of 0.5m/sec. For bed slope of 1:2000 is
taken.
Q= 0.02353+ [[20/100]*0.02353]
= 0.028236m3/sec.
= 0.028/0.5
= 0.056 m2
Assuming the side slope of canal as 1.5:1 as most economical for a most economical
Trapezoidal section:
(B ((2nd)/2) = nd2+d2
b+3d =3.6d
b=0.6d...................1
For the most economical trapezoidal section the hydraulics mean depth:
m=d/2
m= Area/wetted perimeter
A = 2.1d2
0.056 = 2.1d2
d2 = 0.026
= 0.2 + 0.45
= 0.65 m
Note: Canal drop is essential at which design of low head structures up to 5-10mtrs drop
in elevation for dissipating scouring action in canal bed.
Table 1.12: Size Stone Masonry Calculation from Ground level to Hard rock level
Sl Reduced
no Chain age level Depth Mean B C (B/2) Area Length Qty
1 0 817 0 0 0 0 0 0 0
2 50 810.87 808.87 1 2.2883 1.144166667 1.71625 50 85.8125
3 100 809.57 807.57 2 3.1933 1.596666667 4.79 50 239.5
4 150 801.77 799.77 2 4.71 2.355 7.065 50 353.25
5 200 805.09 803.09 2 5.4567 2.728333333 8.185 50 409.25
6 250 808.33 806.33 2 4.3633 2.181666667 6.545 50 327.25
7 300 814.83 812.83 2 2.8233 1.411666667 4.235 50 211.75
8 308.86 817 815 2 1.7117 0.855833333 2.5675 10 25.675
Total Volume 1652.49
Mean
Sl.no Distance Depth depth Bed SD Area Length Quantity
1 0 0 0 0 0 0 0 0
2 30 0.6 1.95 1.755 0.54 2.295 30 68.85
3 60 0.58 1.95 1.755 0.5046 2.2596 30 67.788
4 90 0.57 1.95 1.755 0.48735 2.24235 30 67.2705
5 120 0.55 1.95 1.755 0.45375 2.20875 30 66.2625
6 150 0.53 1.95 1.755 0.42135 2.17635 30 65.2905
7 180 0.52 1.95 1.755 0.4056 2.1606 30 64.818
Total Volume 400.2795
1.7. DETAILED AND ABSTRACT ESTIMATION OF
EARTHWORK
Details of Site
Melinajuganahalli, Kelagina
Juganahalli.
Location of the Project : SS Ghati
Distance from the Bangalore : 60 km
Distance from Development : 2 km from Ghati
Nature of the Project : New Tank Project
Type of the Bund : Earthen Bund
Details of the Reservoir
Total Catchment Area of the
Tank : 18.9 sq. Km
Area to be Irrigated : 150 hectares
Proposed crop pattern : Crops and Vegetables
Length of bund : 308.06m
Top Width of the Bund : 4.00 m
Maximum height of bund : 15m
Top level of bund (TBL) : 817
Maximum water level
(MWL) : 815
Full tank level (FTL) : 811
Lowest bed level (LBL) : 801.300 m
Upstream Slope : 1.5 :1
Downstream Slope : 2:1
60 cm thick Stone Revetment
Upstream Revetment : with gravel backing
Sluice Level : 801
Details of Waste Weir
Type : Broad Crested Weir
Full tank level (FTL) : 814
Length of Weir : 47.2 m
Top Width of Weir : 1.6 m
Bottom Width of Weir : 3.3 m
Details of Plug Sluice
Height of the Plug : 1.2 m
Bottom Diameter of the Plug : 0.2 m
Details of the Canal
Channel off taking RL : 805.090 m
Longitudinal Gradient of the
bed : 1 in 2000
Bottom Width of the
Channel : 0.5 m
Depth of the water : 0.2 m
Side slopes : 1.5 : 1
Free Board : 0.4 m
WATER SUPPLY
AND
SANITARY PROJECT
CHAPTER-2 WATER SUPPLY AND SANITARY PROJECT
2.1 INTRODUCTION
Water is an essential component in order to sustain life on earth. It is essential for human
beings, animals and plants for survival. Humans use water for various purposes like
domestic use, industrial use, agricultural use etc. Water is known to be universal solvent
which makes it really easy to get polluted with various chemicals and particles. This
makes the water unfit for consumption. Naturally, water is available in abundance stored
in ponds, lakes, rivers, oceans etc. but majority of it is unfit for use and requires
treatment. Rain proves to be one the most prominent sources of fresh water available to
mankind in the form of rain drops or snow. But rainfall is distributed unevenly
geographically and isn‘t sufficient to fulfil all the needs of growing population throughout
the year. This generates a need to create systems which have the ability to provide potable
water to each and every household during the course of the year to meet their water
demands.
The role of engineers, hence, is to solve this problem in the most efficient and effective
manner by the collection of suitable data that will be required for appropriate design of
tanks, pipes and to create the schematic plans and estimates of the entire project. Proper
planning will ensure minimum operational problems and being cost effective at the same
time.
From the public health point of view, it is necessary that the water required for their need
must be invariably free from all type of impurities whether suspended or dissolved in
water and no risk should occur to the health of the public as a result of any water
contamination.
A public water supply or water works system has to be both from the point of view of
providing an adequate and reliable supply of water catering to all the public need
ensuring that the supply so made are not only potable but also fully protected against
every infection which might otherwise pollute water and cause outbreak of disease.
The planned water supply scheme should not only help in supplying
wholesome water to the people for drinking cooking, bathing etc.., so as to keep disease
away and there by promoting better health but it should also help in supplying water for
fountains, garden etc. Thus helping in maintaining better sanitation and beautification of
surrounding thereby reducing environmental pollution .The schemes should therefore
help in promoting wealth and welfare of the entire humanity as a whole.
2.3 Location:
Water supply project is to be proposed at PalPal Dinne village (13°23'18.28"N
77°32'24.40"E). SS Ghati Grama panchayat, Doddaballapura taluk, Bangalore Rural
District.
2.4 Source:
Identification of surface water body (Ghatti lake) is to be treated and supplied to meet
the demand of the Palpal Dinne village. The site conditions are suitable for the
construction of the treatment plant opposite the source. The water needs to be conveyed
from the treatment plant to the overhead tank of Palpaldinne village is at a distance of
1km from PalPal Dinne village and 2.5km from SS Ghatti.
Fig:2.1 source (SS Ghati kere)
The time lag between preparation design, tendering, Construction and Completion/
Project components may be designed to meet the requirements of the following design
period. TABLE:2.5.2
1. Physical characteristics:
1. Turbidity
2. Colour
3. Taste
4. Temperature.
2. Chemical characteristics:
1. Total solids and suspended solids
2. pH value
3. Hardness
4. Chlorides
5. Nitrogen
6. Manganese
7. Other metals and dissolved gases
Radiological α-emitters
β-emitters
2.8 Water quantity management:
Water quantity management is important when there is an increase in population or a
population explosion. Increase in migration of people to a certain development area due
to job opportunities, quality education, religious/cultural activities, natural disasters in the
neighbouring areas, due to commercial or industrial interest or due to economic policies
which causes increase in demand for water and rapid depletion of the supplies. This
increase in demand forces us to alternate sources of water there by leading to ground
water exploitation altering the quality of the ground water and polluting the surface water
also.
In order to ensure the availability of sufficient quantity of good quality of drinking water,
it becomes almost imperative in a modern society, to plan and build suitable water supply
schemes, which may provide potable water to the various sections of the community in
accordance with their demands and requirements. The provision for such a scheme shall
ensure a constant and a reliable water supply to that section of the people for which it has
been designed. Such a scheme shall not only help in promoting hygiene and public health,
also supplying water for fountains, gardens, etc. for beautification of the surroundings,
but also shall ensure safety against fire by supplying sufficient quantity of water to
extinguish it. The existence of such a water supply scheme shall further help in attracting
industries and thereby helping in industrialization and modernization of the society,
consequently reducing unemployment and ensuring better living standards.
2. Reconnaissance: An appropriate site for treatment plant is chosen with the help of
topographic map and a rough survey is conducted to collect the maximum possible
information.
Surveys conducted for designing water treatment units for a particular area are:
Equipment‘s used:
1.Prismatic compass with stand
2. Levelling instruments and staff.
3.Tape, chain, arrows, ranging rod etc.
Procedure:
3.The selection of site for water treatment plant should be such that it should serve its
purpose in the most efficient and economical manner.
4.Block levels are done to know the elevation and depression of area so as to locate
various units by which gravity flow can be permitted through them.
Equipment used:
1. Domestic demand
2. Industrial demand
3. Commercial demand
4. Fire demand
5. Demand for compensatory losses
2.11 Break up for various water demand:
Industrial demand 40
Commercial demand 25
Fire demand 15
Compensatory loss 55
1. Arithmetic increase method :This method is based upon the assumption that
the population increases at a constant rate; i.e. the rate of change of population with time
is a constant.
2. Geometric increase method: In this method, as per the decade percentage
increase or percentage growth rate (r) is assumed to be constant, and the increase is
compounded over the existing population every decade. Hence, this method is also
known as uniform increase method.
3. Incremental increase method: In this method, per decade growth is not
assumed to be constant as in previous methods, but is progressively increasing or
decreasing, positive or negative.
4. Decreasing rate of growth method: In this method, the average decrease in
the percentage increase is worked out, and then it is subtracted from the latest percentage
increase for each successive decade.
Simple graphical method: In this method, a graph is plotted from the available data,
between the time and population. The curve is smoothly extended up to the desired
1year.
Table 2.12.1 Details of population in ‘PalpalDinne’ village
1985 2000
5.
1. Arithmetic increase method:
Pn= (P+nx) (1)
P(2035) =3800(1+23.94/100)2
P(2035) = 5838
Pn = P+nI+r*n(n+1)/2 (3)
P(2035) =3800+(2*600)+50*2(2+1)/2
P(2035) = 5150
Therefore, increase in population by the year 2035 through Incremental increase method
is 5150.
Considering the population of SS Ghatti as 2000, so the new increase in population by the
year 2035=2000+5150=7150.
SOURCE Primary
Screening Aeration
Sedimentation
Coagulant
Coagulation
Flocculation
Secondary
Sedimentation
Filtration
2) Sometimes, an approach channel is constructed and water is led to the intake tower.
3) If the water level in the river is low, a weir may be constructed across it to raise the
water level and divert it to the intake tower.
Reservoir Intake Structures:
1) When the flow in the river is not guaranteed throughout the year, a dam is constructed
across it to store water in the reservoir so formed.
2) These are similar to river intake, except that these are located near the upstream face of
the dam where maximum depth of water is available.
4) The intake pipes are located at different levels with common vertical pipe. Each intake
pipe is provided with bell mouth entry with perforations of fine screen on its surface.
5) The location of inlet pipes at different levels ensures supply of water from a level
lower than the surface level of water
2) These are constructed as cribs or bell mouths. The cribs are made of heavy timber
frame work which is partly or wholly filled with rip-rap to protect the intake conduit
against damage by waves etc.
1) In some cases, source of water supply to a small town may be an irrigation canal
passing nearer or through the town. Then it will be constructed.
3) A fine screen is provided over the bell mouth entry of the outlet pipe.
4) The intake chamber may be constructed inside the canal bank if it does not offer any
appreciable resistance to normal flow in the canal.
5) It‘s preferred to provide lining to the canal near the intake chamber.
2.16 Water treatment process:Water treatment is any process that makes water
more acceptable for a specific end-use. The end use may be drinking, industrial water
supply, irrigation, river flow maintenance, water recreation or many other uses including
being safely returned to the environment. Water treatment removes contaminants or
reduces their concentration so that the water becomes fit for its desired end use.
2.17 Functions and benefits Water treatment process:
Sl Unit Function Benefits
no operation
2.18 Aeration
Aeration is the process of bringing water and air into close contact in order to remove
dissolved gases, such as carbon dioxide, and to oxidize dissolved metals such as iron and
Manganese. It can also be used to remove volatile organic chemicals (VOC) in
the water. Aeration is the first major process at the treatment plant.
Types of Aerators
2.19 Sedimentation
Waters exiting the flocculation basin may enter the sedimentation basin, also called a
clarifier or settling basin. It is a large tank with low water velocities, allowing floc to
settle to the bottom. The sedimentation basin is best located close to the flocculation basin
so the transit between the two processes does not permit settlement or floc break up.
Sedimentation basins may be rectangular, where water flows from end to end, or circular
where flow is from the Centre outward. Sedimentation basin outflow is typically over a
weir so only a thin top layer of water that furthest from the sludge exits.
After screening out debris and testing the raw water, water treatment really begins
at the flash mix chamber. Here, chemicals are added to the water, primarily to aid in
coagulation and flocculation. In the flash mixer, the water is agitated violently for a short
period of time before being released into the flocculation basin.
The duration of mixing in the flash mix chamber is carefully controlled and is
usually between thirty seconds and one minute. If the water is mixed for less than thirty
seconds, then the chemicals will not be properly mixed into the water. But if the water is
mixed for more than sixty seconds, then the blades will shear the newly forming floc back
into smaller particles. When determining the length of time that water must spend in the
flash mix chamber, flow rates must be calculated. The volume of the flash mix chamber
and the amount of flow determine the contact time.
2.21 Coagulation
Small and colloidal particles are not removed efficiently by sedimentation because they
settle too slowly; they may also pass through filters. They would be easier to remove if
they coalesce together (coagulated) to form larger particles, but they don't because they
have a negative charge and repel each other (like two north poles of a magnet).
Wier
Inlet channel
outlet channel
Settling Tank
Floc Chamber
The most common type of filter is a rapid sand filter. Water moves vertically through sand
which often has a layer of activated carbon or anthracite coal above the sand. The top
layer removes organic compounds, which contribute to taste and odor. The space between
sand particles is larger than the smallest suspended particles, so simple filtration is not
enough. Most particles pass through surface layers but are trapped in pore spaces or
adhere to sand particles. Effective filtration extends into the depth of the filter. This
property of the filter is key to its operation: if the top layer of sand were to block all the
particles, the filter would quickly clog
2.24 Disinfection
Disinfection is accomplished both by filtering out harmful micro-organisms and also by
adding disinfectant chemicals. Water is disinfected to kill any pathogens which pass
through the filters and to provide a residual dose of disinfectant to kill or inactivate
potentially harmful micro-organisms in the storage and distribution systems. Possible
pathogens include viruses, bacteria, including Salmonella, Cholera, Campylobacter and
aprotozoa, including Giardia lamblia and other cryptosporidium.
2.25 Chlorination
Chlorination commonly used to indicate broadly that the water has been treated with
a sterilizing agent.
Disinfecting Action of Chlorine When chlorine is added to water, it forms hypochlorous
acid or hypochloride ions, which have an immediate and disastrous effect on most forms
of microscope organisms. The reactions that take place are
The hypochlorous acid is unstable and may break into hydrogen ions and hypochlorite
ions
The above reaction is reversible and depends upon the pH valve of water. The
dissociation of hypochlorous acid into ions is more effective at high pH valves and vice
versa. Thus, at pH valves greater than 10, only OCl ions are found; while in pH valves of
less than 7 (more than 5), HOCl will generally exist without dissociating into OCl ions;
and in the pH range of below 5, chlorine does not react and remains as elemental
chlorine.
Out of these forms of free available chlorine, the hypochlorous acid is the most
destructive, being about 80 times more effective than the hypochlorite ions. For this
reason, the pH valve of water during chlorination is generally maintained slightly less
than 7, so as to keep the dissociation of HOCl to minimum, and thereby keeping more
HOCl in solution compared to OCl ions.
Fig 2.8 Chlorine demand curve
2.26 DESIGN OF SANITARY
2.27 Flow diagram of Sewage Treatment Plant
EQUILISATIO N TANKS AERATION TANKS
BAR SCREENS
DISPOSAL OF SLUDGE
SECONDARY SEDIMENTAION TANK
Three distinct stages have been found to occur in the biological action involved in
the natural process of sludge digestion tank. These stages are:
Sludge drying beds are open beds of land, 45 to 60 cm deep, and consisting of
about 30 to 45 cm thick graded layers of gravel or crushed stone varying in size from 15
cm at bottom to 1.25 cm at top, and overlain by 10 to 15 cm thick coarse sand layer.
Open jointed under-drain pipes @ 5 to 7 cm c/c spacing are laid below the gravel layer in
valleys, at a longitudinal slope of about 1 in 100. The beds are around 15 X 30 m and are
surrounded by brick walls rising about 1 meter above the sand surface.
1 .Disposal in water
This is an economical but not common method because it is contingent on the availability
of bodies of water adequate to permit it. At some seacoast cities, sludge either raw or
digested is pumped to barges and carried to sea to be dumped in deep water far enough
off shore to provide huge dilution factors and prevent any ill effects along shore.
2 .Disposal in land
Under land disposal the following methods may be included :
1. Burial.
2. Fill.
3. Application as fertilizer or soil conditioner.
1. Burial disposal
This method is used principally for raw sludge, where, unless covered by earth, serious
odour nuisances are created. The sludge is run into trenches two to three feet wide and
about two feet deep. The raw sludge in the trenches should be covered by at least 12
inches of earth. Where large areas of land are available, burial of raw sludge is probably
the most economical method of sludge disposal as it eliminates the costs of all sludge
treatment processes. It is, however, rarely used and even then as a temporary makeshift
because of the land area required. The sludge in the trenches may remain moist and
malodorous for years so that an area once used cannot be reused for the same purpose or
for any other purpose for a long period of time.
2. Fill disposal
Use of sludge for fill is confined almost entirely to digested sludge which can be exposed
to the atmosphere without creating serious or widespread odour nuisances. The sludge
should be well digested without any appreciable amount of raw or undigested mixed with
it.
Either wet or partially dewatered sludge, such as obtained from drying beds or
vacuum filters can be used to fill low areas. Where wet sludge is used the area becomes a
sludge lagoon, which has been discussed. When used as a method of disposal, the lagoon
area is used only until filled, and then abandoned. When used as a method of treatment,
the sludge after some drying, is removed for final disposal and the lagoon reused.
Lagoons used for disposal are usually fairly deep. Sludge is added in successive layers
until the lagoon is completely filled. Final disposal of digested sludge by lagoons is
economical as it eliminates all dewatering treatments.
It is applicable, however, only where low waste areas are available on the plant site or
within reasonable piping distance. They are frequently used to supplement inadequate
drying bed facilities.
Dewatered digested sludge from drying beds and vacuum filters can be disposed of by
filling low areas at the plant site or hauled to similar areas elsewhere without creating
nuisances.
3. Application as fertilizer or soil conditioner.
Sewage sludge contains many elements essential to plant life, such as nitrogen,
phosphorous, potassium, and in addition, at least traces of minor nutrients which are
considered more or less indispensable for plant growth, such as boron, calcium, copper,
iron, magnesium, manganese, sulphur , and zinc. In fact, sometimes these trace elements
are found in concentrations, perhaps from industrial wastes, which may be detrimental.
The sludge humus, besides furnishing plant food, benefits the soil by increasing the water
holding capacity and improving the tilth, thus making possible the working of heavy soils
into satisfactory seed beds. It also reduces soil erosion.
Design of Water supply network
The population of PALPAL DINNE village by 2035 is estimated to be 7150 by
INCREMENTAL INCREASE METHOD.
Q = 0.0335m3/sec
= 0.98√0.0335
d = 0.179m
Taking, d=0.2m
A= 0.0314m2
Q=A*V
V=.0335/0.0314
V=1.07m/s
=2*0.0314
=0.0628m2
=0.28m ≈ 0.3m
Q=0.0335*3600*4= 482.4 m3
Hs=887.65-879.75= 7.9m
Hd=891.99-887.65= 4.34m
Hf= (4flv2/2gd)
= ((4*0.01*57.8*1.072)/(2*9.81*0.2))
=0.6746m
Hm=HS+Hd+Hf
=7.9+4.34+.6746= 12.9146m
Therefore Hm=12.9146+1.2915=14.2061m
= (1000*0.0335*14.2061/75*0.85*.85)
=10BHP
2.4 Ground level storage tank
Storage capacity=Q*60*60*3
=0.0335*60*60*3
=361.8m3
Area=L*B
Area=B2
Total depth=D=2.5+0.6=3.1m
B=√144.72=12.03m L=12.03m.
=0.045*.0335*60*60
=5.7510m2
=√(4*34.66)/ Π
= 2.63 m
Discharge Q,
Q=0.0335m3/s=120.6m3/hr=2894400.00 lpd
=361.8m3
=2.5+0.6+0.45=3.55m
=361.8/3.55
=101.9155m2
1.5B2= 101.9155
B=√A/1.5=√101.9155/1.5 = 8.24m
Therefore L= 1.5*8.24=12.36m
B=8.25m
Surface loading=volume/area
=2894400.00/101.9155
=28340 lpd/m2
=2894400.00/8.24
=351262 lpd/m
=0.98√0.0335
d=0.179m
d=0.2m
Q=A*v
v=Q/A
v= .0335/0.0314
v=1.07m/s
Therefore velocity of the inlet pipe will be least of the above two velocities ,i.e
v=1.07m
=301.5m2
B=7m, L=1.5*7=10.7m
Depth of gravel=5 cm
Effective size of sand=0.9 mm
Depth of tank=2m
1930500.00 l/day
=0.98 √Q
d =0.98√.0335
=0.2m
Q=A* V
A = Π*(0.2)2 / 4
A =0.0314m2
V= 1.07 m/s
Hs=0m
Hd= difference of levels between the pump station and overhead tank
Hd=(901.615+10)-(874.6)=37.015m
L= 1053m
Hf=(4flv2/2gd)
=((4*0.02*1053*1.072)/(2*9.81*0.2))
=24.58m
Hm=HS +Hd+Hf
=0+37.015+24.58=61.595m
Assume 10% losses
Therefore Hm=61.595+6.1595=67.75m=68m
=(1000*0.0355*68/75*0.8)
=40.233BHP =40BHP
Discharge =0.0355m3/sec
Assume ht to diameter= 3m
=10.65m3
=10.65/3
=3.55m2
Diameter of tank=√(4A/Π)
=2.13m≈2.15m
Discharge =0.0355m3/s
=191.7 m3
Area of sump=volume/depth
=191.7/5
=38.34 m2
Diameter of sump=√(4A/Π)
=6.98m ≈ 7m
SANITARY
2.12 Design of bar screens
Qav = 0.0284 m3/s
Qpeak = 1.5*0.0284
= 0.0426 m3/s
Q= A*V
0.0426= (Π*d2/4 )*(1/0.012)*(d/4)2/3 (√1/1000)
0.0426=0.8213*d8/3
0.0426=d2*d2/3*( Π*1/4*1/0.012*(1/4)2/3 *(1/1000)1/2 )
d8/3 = 0.0426/0.8213
d=0.33
d= 0.3m or 300mm diameter pipe
Vact= 1/n *R2/3*√s
Where,
n= 0.012
s= 1/1000
Vact= (1/0.012)*(0.3/4)2/3*(1/1000)1/2
Vact= 0.46 m/sec
3.1 : Introduction:
Preparation of highway project involves a chain of activities, such as, field surveys and
investigations, selection of alignment, carrying out various designs, preparations of
drawings and estimates, etc. The extent and quality of investigations have a strong
influence on selection of most cost-effective design, estimation of quantities cost and
execution of the job itself.
Administrative, developmental, strategic and other needs would determine the obligatory
points to be connected by a road. Control points will be governed by saddles, passes, river
crossing and other natural features like escarpments and unstable areas.
Optimum alignment will be one, which yields the least overall transportation cost, taking
into account the cost of construction and maintenance of the road as well as the recurring
cost of vehicle operation, and at the same time having least adverse impact on the
environmental and ecological balance.
The proposed highway projected is at latitude and longitude of 13 24‘ 15.4‖N 77 32‘
05.9‖E which connects the lagumenahalli mile stone, proposed town and Hanuman
temple at SS ghati.
3.2 : Objectives:
1. To propose new alignment to connect the town which has been planned i.e. from
lagumenahalli road to Hanuman Temple.
2. To reduce the number of curves by aligning as straight as possible.
3. To workout the area of land to be acquired, the quantities of materials required, like
earthwork and various pavement materials for the proposed road.
4. To provide a two lane road of 7.5m length with raised kerbs.
Fig no. 3.1: Aerial view of Highway Project
3.3 : Map Study:
Toposheet of No. D43R11 is used for the reconnaissance survey. This map help us to
suggest the likely routes of the road. The main features like hills, valley, etc... Are
shown on the map. The probable alignment can be located on the map are as follows:
1. Traffic reconnaissance survey: the data regarding the local industries, religion festival,
nature and volume of exports, existing transport, the amount of traffic served by the new
alignment can be determined.
2. Engineering Reconnaissance survey: This provide the information of availability of
water, material, nature of soil, position of hills and lakes, streams, etc.
The details to be collected from the reconnaissance survey are given below:
1. Marshy land, bridges, permanent structure and other obstructions not available on the
map.
2. Approximate values of gradient, length of gradients and radius of curves of alternate
alignments
3. Number and type of cross drainage structures, maximum flood level and natural ground
level along probable routes.
4. Sources of construction of materials, water and location of stone quarries near by the
probable routes.
5. If the route is passing through mountains, the details like type of rock, dip of strata,
seepage condition, etc.
3.5 : Preliminary survey: - The art of finding the details of alternative alignment
found suitable during the reconnaissance survey is known as preliminary survey.it is the
rough type of survey, which is conducted to have a fair idea of the surrounding areas. It is
carried by the survey instrument to calculate the rough earth work.
After the preliminary survey, the necessary plans are prepared to the survey work and
rough estimate is made. The most economical and the best of these alignment is selected.
The survey instruments used for the project are as fallows.
3.5.1: Establishing TBM: Dumpy level is used to fix the temporary Bench Mark
[T.B.M] which is to be laid on the Lagumenahalli mile stone [0 Mile stone] carrying the
fly levelling from known Bench Mark i.e. B.M at Makkalidurga railway Station. Now the
longitudinal and Cross sectional levelling, Block levelling is carried for the proposed
highway alignment from 0 mile stone t hanuman temple.
3.5.2 : Fixing Initial alignment using Plane table: on other side plain table is used to
draw the proposed alignment with existing features like tress, rocks, temples, curves etc.
The instruments like U-frame, plumb bob, Alidade, truff compass are used.
3.5.3 : Setting out of necessary curves: Two transition curves and one valley curve was
proposed based on the preliminary survey and the same were set on the field using the
transit theodolite and the gradients in case of valley curve was checked using Ceylon ghat
Tracer.
3.6 : Detailed and final location Survey: The detailed examination of the field
along the alignment finally recommended during the preliminary survey and Following
parameters were arrived.
1. The center line of the proposed road was fixed on the ground
2. The field data necessary was collected for the acquision of right of way.
3. The quantity of earthwork along the proposed alignment was computed.
3.7 : Geometric Design:
The physical features of road are known as road geometrics. Properly designed road
geometrics provide optimum efficiency in traffic operation, with maximum safety. Road
geometrics include the dimension of highway, features such as Design speed, Horizontal
Curve IRC NO 73 – 2007.
3.7.1: Design speed: The design speed is the most important factor controlling design
elements of highway. The design speed is taken into account the overall requirement of
the highway.in India different speed standard have been assigned depending upon the
importance. The design speed in the rural terrain is standardized by the IRC for different
class of road.
Table 3.1: IRC value for Design speed in Rural Roads (Kmph)
M.D.R 80 65 65 50 40 30 30 20
O.D.R 65 50 50 40 30 25 25 20
V.R 50 40 40 35 25 20 25 20
3.7.2: Horizontal curve: a horizontal curve is a curve in plan to provide change in direction
to the center line of a road. When a vehicle traverse a horizontal curve the centrifugal force
acts horizontally outwards through the center of gravity of the vehicle.
Table 3.2: IRC value for Min Horizontal curve in Rural Roads (M)
Roadway width m at
3.8.2: Width of formation: width of formation or roadway width is the sum of the
widths of pavements or carriage way including separators and shoulders. The values
suggested by IRC are s given below:
Road classification
Width of Formation for various classed of Roads
NH/SH 12 6.25-8.88
MDR 9 1.75
ODR 7.5-9.0 1.75
VR 7.5 1
3.8.3: Carriage way width or pavement width: the portion of the roadway constructed
for movement of vehicular traffic is called carriage way. The width of carriage way shall
be decided by the number of traffic lanes. The carriage way intended for one line of
traffic movement is called traffic lane. The width of carriageway for various classes of
roads standardized by IRC are given below
Table 3.5: IRC value for width of carriage way (M)
3.8.5: Sight distance: the longest a driver can see in front of him, may be termed as sight
distance. In the design of roads following three type of sight distances should be given
due consideration:
3.8.5.1: Stopping sight Distance: The distance required for an emergency stop is
stopping sight distance.
Fig 3.3: SSD at Horizontal Curve
3.8.5.2: Safe Overtaking distance: the distance required when vehicle can overtake and
pass each other is known as safe overtaking distance.
Safe sight distance for entering into intersection: the driver entering on uncontrolled
intersection should have sufficient visibility to enable him to take control of his vehicle
and avoid collision with other vehicle is termed s safe sight distance.
Design values in
Speed meters
(Kmph) Stopping sight Intermediate sight
distance distance
20 20 40
25 25 50
30 30 60
35 40 80
40 45 90
50 60 120
3.8.6 : Super elevation: the inward transverse inclination provided to the cross section of
the carriage way at horizontal curved portion of a road is called super elevation, cant or
banking.it help a fast moving vehicle to negotiate a curved path without overturning and
skidding.
3.8.7: Widening of road at Horizontal Curves: The position of extra pavement width at
sharp horizontal curves is known as widening of road on curves.
1
6
U 2 4 0 Ab
1
pt 1 1 1 ov
-
o - - - e
1
2 4 6 3 30
0
Radius of curve in 0 1 0 0 0
0
meters 0
1 1 0 0
1.
Extra widths in . . . . nil
5
meters Two Lane 5 2 9 6
0 0 n
0. n
. . i nil
9 il
single lane 6 6 l
3.8.8: Transition curve: a curve which is provided to effect an easy change of direction
of a pavement is called transition curve. The radius of the transition curve changes
gradually from infinite to finite value.
3.8.9: Gradients: the rate of rise or fall of road level along its length is termed as
gradient.
The gradient of a pavement is governed by the following factors:
1.Topography of the country.
2.Drainage.
3.Nature of traffic.
4.Obligatory points.
Ruling radius R =
Super elevation e =
=
= 0.12 > 0.07
Therefore, the value of super elevation is greater than the maximum ‗e‘ of 0.07. So super
elevation to be provided is 0.07
e=
0.07 =
V = 60.18 Kmph.
e+f=
0.07 + f =
We= Wm +Wps
Wps =
√
= = 0.56
√
Wm= = = 0.16
Maximum length of vehicle L = 6m
Extra widening at curve we = 0.56+0.16
= 0.72m
3.1.4 : Design of camber
Camber is provided based o rainfall range
Camber to be provided as 1 In 50
Width of carriage way = 5.5m
V = = 22.22 m/sec.
=VXt+
= 22.22 X 2...5 +
SD = 0.278 X 80 X 2.5 +
T=√ =√ = 10.41
OSD = (0.28 x64 x 2.0) + (0.28 x64 x 10.41 + 2.0) + (0.28 x80 x10.41)
OSD = 457.57m say 458m
( )
M = 229 – [229 – 2.055] X COS 15.65
M = 10.46 m.
= = 0.52
= 92.73 m
2. By rate of introduction of Super elevation
(The pavement is rotated about the inner edge)
Rate of introduction of Super elevation, N= 1 in 60
Width of road at Curves= W + We = 7.5 + 0.95= 8.45 m
Ls= e (W + We) N= 0.07 x 8.45 x 60= 35.49 m
Shift, S= =
= 1.55 m
Spiral
∆ angle
ᵒ
= = = 11.55
s
Central angle for Circular Curve, ∆c= ∆ - 2∆s=79 – 2 x 11.55= 55.89ᵒ
= 2(0.05*22.223/0.6)1/2 = 60.47m≈61m99
N=
N = 68402715.38
N = 68.40 msa
Corresponding to this design traffic, pavement thickness can be calculated from IRC charts:
Corresponding to CBR 6%, pavement thickness required is 675mm for 50msa and 700mm for
100msa. Interpolating these values, the pavement thickness for 68.40msa.
t = 675 +
T2=
i= = 0.021 m-sec
Ad= 590x727=428930
2
= =428.9 mm
= (0.3x0.021x429)
Q = 2.70 m/sec
Q1=1.35
V= 0.8 m/sec
B = 0.75 M
V= ()
Q=
Q = 5.4m2
5.4= (dx0.5)+2((1/2)*d2)
5.4=0.5d+1.5d2
=6.03m
R= 0.89m
OLD TANK
PROJECT
CHAPTER-4 OLD TANK PROJECT
4.1 Introduction
Water is a prime natural resource, a basic human need and a precious national asset.
Water as a resource is indivisible; rainfall, river waters, surface ponds and lakes and
ground water are part of a single unit, which needs a holistic and efficient management to
ensure their long-term quality and availability.
Agriculture is the main occupation of rural population in India. Irrigation has played a
pivotal role in India‘s agricultural production and growth. Both at national and regional
levels, agricultural growth and overall development closely follow the growth pattern in
irrigation.
Minor Irrigation (MI) in India is defined as one with a command area of less than 2,000
hectares. There are mainly five types of MI structures that – dug wells, shallow tube
wells, deep tube wells, surface lift systems, and surface flow systems. Except the surface
flow systems, all others are groundwater structures. Through the ages, these surface flow
system or water bodies, either natural or man-made such as lakes, tanks, ponds and
similar structures have sustained the Indian agriculture. A water body is a structure where
water from ice-melt, streams, springs, rain or drainage of water from residential areas is
accumulated or water is stored by diversion from a stream, nala or river.
. Due to progressive silting in the reservoir, its storage capacity gets reduced. The demand
for irrigation water cannot be met due to reduced storage.
Further, in future there may be demand for water cultivation of large area. In view of
these two factors it becomes necessary to restore the storage capacity of the reservoir to a
value equal to its original value.
The storage capacity is increased in two ways
1. Raising F.T.L of the reservoir after making suitable modifications in the profile of the
existing bund.
2. De-silting the reservoir: This would require the employment of sophisticated equipment
such as hydraulic dredges. Before taking up the project, it is necessary to study whether .
4.2 Objectives:
4.3 Study Area: The tank which is supposed to be restored is Pal Paldinne kere
situated at a distance of approximately 2.5km along S.S.Ghati, Doddaballapura road. Due
to inadequate maintenance the downstream side slope of bund is eroded and due to silting
the quantity of water stored is less. Hence we have taken the restoration of this old tank
4.4 Investigations and Surveys:
The surveys are carried out to collect field data to obtain all information needed for
the restoration of the existing tank. The total survey is carried out using conventional
survey instrument.
4.5 Reconaissence :
The existing site condition are explored by visiting the OTP site and adequate data
of area is collected .
4.6 Preliminary Survey :
The temparory Bench Mark is established at the Ashwath Katte near OTP site.
4.7 Detailed Survey
Alignment of existing bund using plane table survey was carried out and the plan was
prepared showing all the salient features along the centre line of the bund.as shown in the
fig.no 1.
1. Longitudinal section along the existing centreline of the bund were carried out using
dumpy level and The cross sections are taken at regular intervals (3m, 6m, 9m etc.) along
the alignment
2. Details of existing waste weir and sluice points including block levelling at waste weir.
3. Water spread contour to explore the quantity.
FIG NO 1
V1 = d {(A1+A2)/2}
= 30{(10.97+16.62)/2} = 413.85m3.
V2 = d {(A2+A3)/2}
= 30{(16.62+21.67)/2}
= 574.35m3
V3 = d {(A3+A4)/2}
= 30{(21.67+23.084)/2}
= 559.425m3.
V4 = d {(A4+A5)/2}
= 30{(23.084+35.52)/2}
= 146.51m3.
V5 = d {(A5+A6)/2}
= 30{(35.52+36.92)/2}
= 1086.65m
V6 = d {(A6+A7)/2}
= 30{(36.93+27.92)/2}
= 972.645m3.
From 150-180m chainage:
V7 = d {(A7+A8)/2}
= 45{(27.92+31.0)/2}
= 883.8m3.
V8 = d {(A8+A9)/2}
= 30{(31+12.08)/2} = 646.2m3.
V9= d {(A9+A10)/2}
= 30{(12.08+15.96)/2}
= 420.6m3.
TOTAL VOLUME
V = V1+V2+V3+V4+V5+V6+V7+V8+V9+V10.
V=413.85+574.35+559.42+146.51+1086.65+972.64+883.8+646.2+420.6
=5704.02m3.
883.735 1822.2145
883.985 1972.1201
(FTL+1)884.235 2100.179
Township refers to an urban or rural settlement which consists of group of people living
within close vicinity. The group of people shares the privilege of the common utilities
available within the community, making such allowances more accessible, economically.
The design of such township is a process encompassing a number of civil egg aspects.
The main objective is to gain the practical knowledge about
Feasibility studies
Governmental approvals – environmental impact assessment
Scientific planning and design of various infrastructures of the layout like Residential
units, Commercial units, Water supply lines, Sewerage lines, Roads networks, Rain water
harvesting units etc.
In order to promote public health, safety and general social welfare of the communities it
is necessary to apply reasonable limitations of the use of land and buildings. This is to
ensure that the most appropriate economical and healthy development of the proposed
city or townships or layout or any other purposes takes place in accordance with the land
use plan i.e. Comprehensive development plan (CDP). For these purposes classification
of land in to various uses or developments that are permissible in to following zones.
a. Residential
b. Commercial
c. Industrial
d. Public and Semi public
e. Utilities and Services
f. parks and open spaces, playground (including public recreational area)
g. Transportation and communication
h. Agricultural land and water sheet
For the above said purposes land shall be non-agricultural land i.e. the agricultural land
converted in to non-agricultural land as per the land acquisition act. After completion of
the above procedure the land can be used for the above said zones.
Residential zones: After the land acquisition required extent the layout for residential
purpose shall be subjected to the following conditions.
i. 52% of the total area shall be earmarked for residential sites
ii. 48% of the area earmarked for civic amenities, such as Roads, Playground,
Hospitals, Parks and Play grounds and Public schools, Post office, police station,
fire station, Overhead tank, Library, religious groups etc.
5.2 Design requirements
Residential Sites – Space for individual plots and mass housing (to cover approximately
50% of the proposed township area excluding the area for primary school and primary
health care centre).
Civic Amenities – Space for offices, shops etc. (To cover approximately 5% of the
proposed township area excluding the area for primary school building and primary
health care centre).
Park Area: (To cover approximately about 15% of the township area excluding the area
for primary school building and primary health care centre).
Main Roads and internal roads – For accessibility to township area.
Water Supply distribution system with overhead tank (OHT)
Underground drainage (UGD) System for sewage and its connection to STP.
Sewage Treatment Plant (STP) With eventual disposal to natural drain.
5.3 Objectives:
1. To study the necessary approvals and to design the residential layout according to
the government bylaws.
2. To plan and prepare lay out plan of amenities, Road network, and layout of residential
area
3. To design Water supply system and Sewerage system for proposed residential layout
5.4 Location of the township site
A small piece of land nearly 28 acres was identified near SS Ghatti, adjacent to
Doddaballapur and Ghatti road which is about 70km from Bangalore. The general
boundary of the township site is as shown in fig 5.1
5.5 Methodology:
1. The land for the proposed layout was surveyed using total station and this data was
imported into the computer
2. Planning of the layout amenities. The whole area was divided into plots of various sizes
along with provision of other amenities of the layout such as main roads, arterial roads,
parks and public facilities using CADD and the planning of the layout is carried as per the
guidelines of local authorities. The guiding criteria are there must be adequate space for
Residential area
Commercial area
Recreational area
Must be according to by- laws
Planning must takes care of environmental considerations
All necessary engineering aspect (including slope, aspect etc)
Planning should be such that Resources are optimally used.
The public space must be located away from the residential
area Easy access for all people to all amenities provided
3. Referring to the codal provisions the various necessities like water supply, sewerage
system of the residential layout was designed according to civil engineering practices
Designing of these features required inputs such as the slope of the land ,distance,
position of the various amenities of the layout, These inputs were used in the form of
different layers containing the location of the sites, another layer containing the details of
the position of Sewerage treatment plant, water tank etc were overlapped on each other
and by using various civil engineering methodologies the position of the water lines and
their diameter were fixed and then mapped along with their attribute values. The water
supply and sewer lines for layout is shown in figure:-
5.6 Drawings
The detailed survey was conducted using total station and all the data was transferred to
the computer. Planning of the layout amenities are carried out and the following drawings
are prepared.
5.6.1 Layout plan superimposing on existing contour map
Layout plan superimposing on existing contour map of the plot proposed to be developed.
The contour map of the township site is as shown in fig 2
Fig5.2: The contour map of the proposed layout site
The drawing contained road network of layout and the civic amenities to be provided
for the layout is as shown in fig 3
Fig 5.3: Road network and the civic amenities of layout
5.6.3 Drawing showing water supply and sanitary network of the layout
All the above proposed township details are shown in fig 5.6
5.8 Bibliography
√
Where, Cd = Coefficient of discharge assumed as 0.6
L = Length of waste Weir in m
h = Head over weir = MWL-FTL = 815.000-814.000= 1 m
Substituting the values, the Length of Waste Weir is found to be 39 m
Since arrangements are to be made on the top of the Waste Weir to store the water in
times of necessity, grooved dam stones of size 0.2mX0.2m will be fixed at the centre of
the weir at 1m centre to centre interval with its top at Maximum Water Level.
Number of Dam Stones to be provided = 39
Width of one Dam Stone = 0.20 m
Width of Dam Stones = 41 x 0.2 = 8.2 m
Therefore total length of the Waste Weir = 39+8.2 = 47.20 m
1.2.3: Design of Weir Wall
Crest Level of Weir Wall = FTL = 814.000 m
Top level of the Dam stone = MWL = 815.000 m
Bottom Level of foundation concrete = 810.699-0.50 = 813.500 m
Height of Masonry weir above foundation H= 814.000-810.699= 3.787 m.
√ √
= 00.55[3.3+1]
= 1.55m ≈ 1.6 m.
B =3.85 m.
APPENDIX-II
Solution:
Discharge required =
=
Q = 0.0231 m
Q = 0.0278 m
NOTE: Sluice Bed Level or Floor Level is located at canal bed level = 809.50m
h = 0.6X.85
Velocity (V) = √
V=0.6 √
V = 2.06m/sec
Q=AXV
A = Q/V
A = 0.0278/2.06
A = 0.0135 m²
d=√
Top Level of Cistern = Canal TBL =Sill bed Level + Canal depth + 0.3 Rise
Bed width 8m 8m
Design the drop wall, the notches, solid apron. Draw to scale
x
1. /2 front and x/2 sectional elevation
x
2. /2 plan at bottom and x/2 at top
3. Cross section along the flow through one of the notches.
Solution : Notches : Assume 3 notches an consider one notch for analysis . The conditions of full
supply and x/2 supply will be as follows.
3
a) Full supply discharge / notch= 8.0/3 m /s
b) Full supply depth (d) = 1.5m (on upstream side)
3
c) Half supply discharge/notch= 4/3 m /s
d) Half supply depth (dc) = 2/3 x full supply depth
=2/3 x 1.5= 1m
Discharge through 1 trapezoidal notch is given by Q
Type formula
L+ 0.6n= 0.7443
L+ 0.4n= 0.6837,
Where n= 0.303 and l= 0.56, say 0.6m
Also top width of notch
1.5.1 Pier
The top of the notch wall will be kept at upstream FSL = 21.50m The notch wall rests on the drop
wall
Thickness of notch wall= dc/2= 80cm.
The sides of the notch wall are kept vertical.
(Note: The length of the notch wall i.e the distance from abutment to abutment measured at the
top of the notch wall should be about 7/8 canal bed width)
The top of the drop wall will be kept at the upstream bed level i.e at 20.00
The top width of the drop wall may be kept at 15-30cm more than that of the notch wall . Hence
assume top thickness of 1m
Note: The bottom width and R.L of bottom of the drop wall can be obtained only after designing
the water cushion.
1.5.2 : Water cushion:
= 20-2.4 = 17.60
( note The apron is extended to form the foundation for the drop wall , we see that the top of the
apron will also be at 17.60)
B=H+dc/ V(S
= 2.6m where G= 2.25
Provide symmetrical batter on upstream side and downstream sides for the drop wall
1.5.3 :Solid apron
The top of the solid apron will be at 17.60. Thickness of apron t= V2 (VHl+dc) = lm
The minimum and maximum length of the apron from the toe A are
L min= 1.5+ 2vT//rfc= 4.96m
L max= 2dc+ 2^/Hldc = 6.50m
Assume L= 5.5m (or 5m or 6m)
Length of downstream revetment= 4(d+H)= 14mThe length of bed pitching will be kept
revetment = 7m
Provide a 1:5 reverse slope to connect apron and downstream bed.
Note : 1. For the drop wall, the abutment, wing wall, downstream return only, we extend the solid
apron in order to form the foundation. Thus the bottom of the above walls will be at 17.60, It in
the top of the apron.
17.60 well below good foundation level, however the apron is not extended below the upstream
wing wall. For this wall we provide a separate strip foundation based on good foundation level as
usual.
Note : 2. The top of the bank is the highest level of the earth in the canal. The top of any wall in
contact with the earth of the canal at respect to TBL. Thus on the upstream side the top of the wall
must be at
the upstream TBL of 22.50, similarly on the downstream side the top of the return which is in
contact with the canal should be at the downstream TBL of 20.50
The abutment is in contact with the upstream TBL.
Note: 3. Since the top of the upstream wing wall is kept level at the upstream TBL, we donot
provide return on the upstream side. Also the downstream wing wall will slope down from
22.50(u/s TBL to d/s TBL) the top of the downstream return wall will be kept at the downstream
TBL
Note 4: The end of downstream wing wall will lie both at the end of the apron and the canal bed
time. But on the upstream side there is no apron, hence it is the upstream wing wall will be
splayed at 45. Also the upstream wing wall will be extended 50cm into the upstream top of the
bank.
Similarly the downstream return will be extended by 50cm into the downstream top of the bank.
This will automatically fix the length of upstream wing wall and downstream return.
1.5.6 :Abutment
The downstream return will be extended by 50cm into the downstream top of the bank. The splay
of the downstream will be automatically fixed in the drawing
Note2. The Berm is the horizontal platform at Ground level but within the canl Cross section.
Assume berm width 0.5m-3m.
Note 3. Side slopes of the canal may be assumed as cutting—1:1 or 11/2 : 1 ( H:V)
Filling 11/2 :1 or 2:1
Note4. The top of the bank is the highest level of the earth in the canal . This level should be
above the FSL by a distance known as free board. The top width of the bank may be assumed
from 1m - 6m.
Note 5. Standard cross section of the canal. The canal may be partly in cutting and partly in filling
or it may be fully in cutting as .
In this case the ground level it gives sufficient free board. Hence cutting, filling is not required.
However we provide small banks known as spoil banks as shown. In this case the TBL will be at
Ground level. Large banks in filling are required if the Ground level is such that it cannot give
sufficient fee board as shown below.
Note 6. In our case the cross section of the upstream and downstream canals will be as follows.
1.5.9 :Up/stream
CBL = 20 m
FSL = 21.50 m
GL = 20.50 m
We should see whether ground level can provide sufficient free board or not. In this case ground
level cannot provided sufficient free board and hence we must provide fillings above ground
level. If we assume free board of 1mabove FSL the upstream TBL will be at 22.50, as given. Thus
the section will be partly in cutting and partly in filling.
The ground level in this case is sufficient to provide which is 1m in this case. Hence the canal is
in full cutting, and ground level itself becomes the TBL on the downstream side. However
provide small protection.
The length at the top of notch wall should be about 7/8canal bed with which becomes 7m in this
case. The length of the notch wall between notches should not be less than d c/2. Further the length
of the end notch walls should not be less than the intermediate walls. Also in this case the length
of the notch at the top is 1.1m . Hence the length of various portions of notch wall can be
assumed.
1.
2.
3.
4.
5.
6.
HIGHWAY PROCJECT
APPENDIX-IV
3.4.1: DESIGN OF PAVEMENT:-
Computation of design traffic:
N = [2734]
N=
N = 68402715.38
N = 68.40 msa
Corresponding to this design traffic, pavement thickness can be calculated from IRC
charts:
Corresponding to CBR 6%, pavement thickness required is 675mm for 50msa and
700mm for 100msa. Interpolating these values, the pavement thickness for 68.40msa.
t = 675 +
t = 684.2 mm say 685 mm.
The pavement composition maybe
Sub base = 260 mm
Base = 250 mm
DBM = 131 mm
BC = 44 mm