Košická energetická spoločnosť a.s. (KES) is well recognized professional company in the
energy sector with excellent know-how in combine production of heat and electricity
KES based on the agreement with VSS a.s. is developing Biomass power plant in areal of VSS
KES obtained license from Ministry Economy to build biomass power plant and approvals from
National electricity network operator (SEPS) and Distribution electricity operation company
(VSD) for connection to network
Based on the technical-economical feasibility study KES prepared basic design for 4 MWe
biomass power plant with heat combine production :
Based on the engineering studies and pricing by international companies the total investment
is estimated to 15,3 mil. EUR
Visualization and
future view from the near road
© 2009 KES a.s.
The combine heat and electricity production was selected for the biomass power plant
Based on the analysis of sensitivity, the price of biomass was found as most critical
The different turbine and boiler manufacturers were included in the pre-tendering procurement phase
including local and international companies
Pre-tendering process documentation was prepared with description of supply and main technical
parameters
Main technology components:
BFB (Bubbling
Fluidized Bed) type
of steam output 22
t/h at 485 oC and
55 bar(a) with
efficiency 89%
nominal power.
The advanced
design of boiler
enabling operate
boiler in the range
between 30% -
100% and bringing Image is intellectual
advantage for the
property of MW Power
available
parameters of fuel.
Extraction
condensing
turbine with
maximum power
4 MWe enabling
to operate with
heating in the
extraction mode
and in the
condensing Images are intellectual
advantage of
condensing
mode is to have
possibility of
operation power
plant during all
year. Image is intellectual
property of SIEMEN
Image is intellectual
property of MW POWER
8 BIOMASS POWER PLANT, KES a.s, Nov-09 CONFIDENTIAL
List of contacted companies
during pre-tendering phase
WEISS – France
MW Power – METSO – WÄRTSILÄ Joint venture
MAWERA – VIESSMAN group
MAXXTEC – Germany
MAN TURBO - Germany
SIEMENS Group
EKOL – Czech republic
KOVOSTA FLUID – Czech republic
BRONSWERK HEAT TRANSFER – Czech republic
SPIG – Italy
FANS – Czech republic
Jeffrey Rader – Sweden
ISTROENERGO – Slovakia
ABB Group
RENEWA – Finland
TGM KANIS – Germany
VAS – Austria
BACOCK WILCOX – Denmark
KALUGA - Russia
9 BIOMASS POWER PLANT, KES a.s, Nov-09 CONFIDENTIAL
Bids and investment structure
In the this investment cost are not include investments needed for
acquisition of land, buildings and infrastructure from VSS a.s. and
preliminary development costs.
10 BIOMASS POWER PLANT, KES a.s, Nov-09 CONFIDENTIAL
Electricity price
electricity sales in units MWh 0 22256 22256 22256 22256 22256 22256 22256 22256
price EUR/MWh 115,9 115,9 115,9 115,9 115,9 115,9 115,9 115,9 115,9
annual growth index index - 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
growth index - 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
total sales of electricity 000 EUR 0,00 2 579,54 2 579,54 2 579,54 2 579,54 2 579,54 2 579,54 2 579,54 2 579,54
Sales total 000 EUR 0,00 4 241,11 4 310,89 4 387,07 4 446,72 4 528,87 4 579,56 4 695,56 4 818,29
Prices are estimated based on legislation and assumptions related to local market
The total volume is estimated based on technology process flows and specific
conditions for heat supplies
Growth indexes were applied due to DCF method used internally.
Costs 2011 2012 2013 2014 2015 2016 2017 2018 2019
biomass consumption t 0 36 363 36 363 36 363 36 363 36 363 36 363 36 363 36 363
biomasss price EUR/t 35,000 35,000 35,000 35,000 35,000 35,000 35,000 35,000 35,000
growth index - 1,000 1,030 1,061 1,093 1,126 1,159 1,194 1,230 1,267
Biomass costs 000 EUR 0,00 1 310,88 1 350,21 1 390,71 1 432,43 1 475,41 1 519,67 1 565,26 1 612,22
el. service kW 0 4000 4000 4000 4000 4000 4000 4000 4000
price of el. service per month EUR/kW 34,400 34,400 34,400 34,400 34,400 34,400 34,400 34,400 34,400
growth index - 1,000 1,030 1,107 1,148 1,182 1,221 1,263 1,316 1,371
Cost of el. service 000 EUR 0 142 152 158 163 168 174 181 189
number of employess 0 6 6 6 6 6 6 6 6
average cost pre month EUR 20000 20000 20000 20000 20000 20000 20000 20000 20000
growth index - 1,000 1,030 1,107 1,148 1,182 1,221 1,263 1,316 1,371
Cost of salaries 000 EUR 0 124 133 138 142 147 152 158 165
maintenance EUR 0 100 000 100 000 100 000 150 000 150 000 150 000 200 000 200 000
cost of fuel handling EUR 0 12 000 12 000 12 000 12 000 12 000 12 000 12 000 12 000
other operational cost EUR 459 000 125 000 125 000 125 000 125 000 125 000 125 000 125 000 125 000
sum EUR 459 000 237 000 237 000 237 000 287 000 287 000 287 000 337 000 337 000
growth index - 1,000 1,030 1,107 1,148 1,182 1,221 1,263 1,316 1,371
Total other costs 000 EUR 459 244 262 272 339 351 362 443 462
Total costs 000 EUR 459 1 820 1 898 1 959 2 076 2 141 2 207 2 348 2 427
Costs structure depends mainly on biomass as fuel for the process, what is calculated based on technical
parameters. Other costs are define by legislation (el. service for back up, insurances, structure of wages) other
costs as maintenance and service are on the minimum level due to guarantees and high quality standards
used for production of technology. Some other costs will specified during specification of detail operation
modes .
14 BIOMASS POWER PLANT, KES a.s, Nov-09 CONFIDENTIAL
Economical summary of project
in 000 EUR 2011 2012 2013 2014 2015 2016 2017 2018 2019
Sales in project total 0,000 4241,105 4310,891 4387,070 4446,719 4528,874 4579,557 4695,558 4818,287
Costs in project total 459,000 1820,319 1897,753 1958,549 2076,002 2140,504 2207,309 2347,564 2427,379
Depreciation assets of project 0,000 706,350 706,350 706,350 706,350 515,100 515,100 515,100 515,100
Profit on project before tax and interest -459,000 1714,436 1706,788 1722,172 1664,367 1873,271 1857,148 1832,893 1875,808
The project shows good parameters of profitability with grant support. Total investment is
projected on 15,3 mil. EUR. Grant represent 39% and bank loan 43%. The amount of own
financial resources was set up based on ratio to bank loan on the level of 30%. For our internal
needs we are working with DCF method and interest rate 7%. Bank loan which we have in
model has the maturity 6 year with grace period of 1 year.
15 BIOMASS POWER PLANT, KES a.s, Nov-09 CONFIDENTIAL
Sensitivity analysis
Month of the year Jan Feb Mar Apr Maj Jun Jul Aug Sep Okt Nov Dec
Days 31 28 31 30 31 30 31 31 30 31 30 31
Heat supply MWt 9 9 9 9 4 3 2 2 3 9 9 9
Electricity supply MWe 4 4 4 4 2 1 1 1 1 4 4 4
Heat supply per month GJ 24106 21773 24106 23328 9641 7662 6108 6601 6783 24106 23328 24106
Total heat supply GJ 201646
Electricity supply per month MWh 2976 2688 2976 2880 1190 946 754 815 837 2976 2880 2976
Consumption MWh 446 269 298 288 119 95 75 81 84 298 288 298
Total electricity supply MWh 22256
Energy in biomass per month GJ 39123 35337 39123 37861 15647 12435 9914 10713 11008 39123 37861 39123
Total energy supplied in biomass GJ 327266
Data in the figures above are estimated based on the preliminary technical
parameters and expected operation mode, which depend on the possibility
to supply the heat. In the winter season is expected to operate the plant on
a full load with delivery within the areal of the VSS and to the network.
Based on heat demand in VSS, we can expect, that ratio of this heat
supplies will be 50:50. Dependence on the supplies of heat during the
summer is minimized by condensation turbine and air condenser, which
will allow to operate turbine at maximum 2 MWe.
Code of call from 26.10.2009 for project is KaHR – 21SP – 0901, call
represents amount of 57 mil. EUR dedicated to energy efficiency and
exploitation of renewable sources.
Specifically for biomass power plants the limit is max. 10 MWe or 30 MWt
thermic energy. In both parameters our projects is well below.
The maximum financial aid for one project is 6 mil. EUR or 50% of all eligible
investment costs.
The maximum of total eligibible cost for project is 25 mil.EUR.
The deadline form submitting of proposal is 22.2.2010.
Other attachment:
Architectonic study
Bids in the pre-tendering process
Commercial register
Audited financial results 2008
Contacts:
Košická energetická spoločnosť a.s.
Teplárenská 3/A
042 92 Košice