You are on page 1of 27

MATERIALS

L B H Unit Qty Price Total

1 Site clearance Sq.ft


2 Excavation Cu.ft
Sand Filling & Laying
3
of Cement concrete Cu.ft
4 Footing work

4.1 Shuttering/Form work

4.2 PCC work Cu.ft


4.3 RCC work Cu.ft
4.4 Steel work
Cu.ft
DPC & Anti termite
5
treatment
Sq.ft
6 Backfilling Cu.ft
WA
Preparation of
1 waterproof
membrane
2 Priming the Surface
Waterproofing Plinth
3
area
Waterproofing at
4
ceiling slab
Waterproofing at
5
terrace lvl

1 Excavation

2 Sandfilling

3 Creating a formwork

3.1 Shuttering
Steelwork for Plinth
4
Beam
5 Concreting for Plinth
5.1 PCC work
5.22 RCC work
6 Plastering for Plinth
Waterproofing for
5
Plinth
COLUMN
1 Creating a formwork

1.1 Shuttering For column


1.2 Shuttering For Beam

2 Reinforcement

Reinforcement for
2.1 Column
Reinforcement for
2.2 Beam
3 Concreting
Concrete for Column
upto Finished floor
3.1 level
Concrete for Column
3.2 from GF to Fl
Concrete for Column
from GF to First floor
3.2 lvl
Concrete for Column
from 1st floor to 2nd
3.3 floor lvl
3.2 Concrete for Beam
4 Curing

1 Preparation of Mortar
2 External walls

Brickwork upto Floor lvl


2.1
Brickwork from GF To
2.2 1st floor lvl
Brickwork from 1st floor
2.3 lvl - 2nd floor lvl
Brickwork from 2nd
2.4 floor lvl- Terrace lvl
3 Internal walls
Brickwork upto Floor lvl
3.1
Brickwork from GF To
3.2 1st floor lvl
Brickwork from 1st floor
3.3 lvl - 2nd floor lvl
4 Parapet wall
5 Sunshade & Lintel work

Reinforcement for Lintel


5.1
Reinforcement for
5.2 Sunshade
Reinforcement for Sill
5.3 plate

5.4 Concrete for Lintel work


5.5 Concrete for Sunshade
5.6 Concrete for Sill plate
SL
Assemble & erect
1
Formwork
1.1 Shuttering For Slab
2 Reinforcement work
Reinforcement for 1st
2.1
floor slab
Reinforcement for 2nd
2.2
floor slab
Reinforcement for Roof
2.3
slab
3 Concreting
Concreting for 1st floor
3.1
slab
Concreting for 2nd floor
3.2
slab

3.3 Concreting for Roof slab

4 Curing
5 Removing Formwork
P
Preparation of surface
LABOUR

FOUNDATION WORK
Mixer
Bar
Mate Mazdoor Bhisti operato Mixer Vibrator Carpenter Glazier
bender
r

WATERPROOFING WORK

PLINTH BEAM
COLUMN AND BEAM CONSTRUCTION

BRICK WORK
SLAB CONSTRUCTION

PLASTERING WORK
EQUIPMENT

Number
of Per
Per day
Polisher Washer Painter Labour Labour
output
require output
d
SETTING LAYOUT
Levelling
1 instrument
2 Long nails
3 Hammer
4 Right angle
5 Steel tape
6 Cotton thread
7 Cement
8 Screen sand
9 Theodolite
10 Lime powder
Sl.No
1 EARTH WORK EXCAVATION
FOOTING - F1 3 6 7 6 Cu.Ft.

FOOTING - F2 12 6 6 6 Cu.Ft.

EXCAVATION
RFT L B
FOR PLINTH BEAM

PB1 278 1.25 1 Cu.Ft. ###

2 SAND
FOOTING - F1 3 6 7 0.5 Cu.Ft. 63.00

FOOTING - F2 12 6 6 0.5 Cu.Ft.


SAND FOR PLINTH
RFT L B
BEAM
PB1 278 1.25 0.25 Cu.Ft. 86.88

SAND LAYER FOR


27 44 0.5 Cu.Ft. 594
FILLING

3 PCC
FOOTING - F1 3 6 7 0.5 Cu.Ft. 63.00

FOOTING - F2 12 6 6 0.5 Cu.Ft.


SAND FOR PLINTH
RFT L B
BEAM
PB1 278 1.25 0.25 Cu.Ft. 86.88

SAND LAYER FOR


27 44 0.5 Cu.Ft. 594
FLOORING
###
BORING OF
4 L
PILES
3 8 RFT 24

5 RCC
CONCRETE FOR
5.1
FOOTING

FOOTING - F1 3 5 6 1.83 Cu.Ft. ###

FOOTING - F2 12 5 5 1.58 Cu.Ft. ###


638.7
CONCRETE FOR
5.2 COLUMNS UPTO
F.L

COLUMN - C1 3 0.75 1.25 3.58 Cu.Ft. 10.07

COLUMN - C2 12 0.75 1 3.08 Cu.Ft. 27.72


37.8

CONCRETE FOR
5.3 RFT L B
PLINTH BEAM

PB1 278 0.75 1 Cu.Ft. ###


###
CONCRETE FOR
5.4 L B D
PILES

3 0.75 0.75 8 Cu.Ft. 14

CONCRETE FOR
5.5 RFT L B
LINTEL
9"(first floor) 184 0.75 0.5 Cu.Ft. 69

4.5(first floor) 40 0.375 0.375 Cu.Ft. 6


75
CONCRETE FOR
5.6 L B T
SUNSHADE

7 5.5 2 0.25 Cu.Ft. 19.3

2 7.5 2 0.25 Cu.Ft. 7.5

Cu.Ft. 27

CONCRETE FOR
COLUMNS ABOVE
5.7
F.L UPTO G.F
SLAB

COLUMN - C1 3 0.75 1.25 12.58 Cu.Ft. 35.38

COLUMN - C2 12 0.75 1 12.58 Cu.Ft. 113.22


148.6

CONCRETE FOR
5.8 RFT L B
ROOF BEAM

GROUND FLOOR -
142 0.75 0.75 Cu.Ft. 79.88
RB1
GROUND FLOOR -
128 0.75 0.75 Cu.Ft. 72.00
RB2
FIRST FLOOR -
94 0.75 0.75 Cu.Ft. 52.88
RB1
FIRST FLOOR -
73 0.75 0.75 Cu.Ft. 41.06
RB2

Cu.Ft. ###
CONCRETE FOR
5.9 L B AREA
ROOF SLAB

GROUND FLOOR 27 44 0.416 Cu.Ft. ###

FIRST FLOOR 27 16 0.416 Cu.Ft. ###

Cu.Ft. ###

CONCRETE FOR
5.1 L B T
SILL PLATE

7 6 0.75 0.25 Cu.Ft. 7.9

2 8 0.75 0.25 Cu.Ft. 3.0

Cu.Ft. 11
6 STEEL WORK

REINFORCEMENT Wt./sq
6.1 L B
FOR FOOTING .ft

FOOTING - F1 3 5.5 6.5 1.5 KG


FOOTING - F2 12 5.5 5.5 1.5 KG
MT 0.0
10% wastage MT 0.1
MT 0.1

REINFORCEMENT
6.2 FOR COLUMN wt./ft. ht.
UPTO First slab

COLUMN - C1 3 5.5 21.5 KG 354.8


COLUMN - C2 12 5.5 21.5 KG ###
MT 1.77
10% wastage MT 0.2
MT 2.0
REINFORCEMENT
6.3 wt./ft. RFT
FOR PB-1
PB1 3 278 KG
MT 0.00
10% wastage 0.1 0.00
MT 0.00
REINFORCEMENT
6.4 wt./Ft. ht.
FOR PILES
3 2.5 9.5 KG 71.3
MT 0.07
10% wastage 0.1 0.01
MT 0.08
REINFORCEMENT
6.5 wt./ft. RFT
FOR LINTEL
9"
3 224 KG ###
4.5
MT 0.7
10% wastage 0.1 0.1
0.7

REINFORCEMENT wt./s.f
6.6 L B
FOR SUNSHADE t

7 1.5 5.5 2 KG 116


2 1.5 7.5 2 KG 45.00
MT 0.12
10% wastage 0.1 0.01
MT 0.13

REINFORCEMENT Wt /
6.7 RFT
FOR ROOF BEAM ft.

GROUND FLOOR -
142 8 KG ###
RB1
GROUND FLOOR -
128 5.5 KG ###
RB2
FIRST FLOOR -
94 8 KG ###
RB1
FIRST FLOOR -
73 5.5 KG ###
RB2
MT 2.994
10% wastage 0.1 0.299
3.293
REINFORCEMNEN
6.8 T FOR ROOF
SLAB

GROUND FLOOR 27 44 Sq.Ft. ###

FIRST FLOOR 27 16 Sq.Ft. ###

Sq.Ft. ###

REINFORCEMNEN
T FOR ROOF Wt. AREA
SLAB
1.5 ### KG ###
MT 2.4
10% wastage 0.1 0.2
2.7

REINFORCEMENT wt./s.f
6.9 L B
FOR SILL PLATE t.

7 6 KG 42
2 6 KG 12
MT 0.05
10% wastage 0.1 0.01
0.06
7 BRICK WORK

9" thk. BK. WORK


RFT D H
UPTO F.L
232 0.75 3 Cu.Ft. ###

9" thk. BK. WORK


RFT D H
ABOVE F.L IN G.F

128 9.5 Sq.Ft. 1216


DEDUCTION L B
VENTILATOR 1 2 2 Sq.Ft. 4

WINDOW 1 6 4 4 Sq.Ft. 96

WINDOW 2 1 6 4 Sq.Ft. 24.00

DOOR - D1 1 2.5 7 Sq.Ft. 17.50

MAIN DOOR 1 4.5 7 Sq.Ft. 31.50

Sq.Ft. 1043

9" thk. BK. WORK


AREA D
ABOVE F.L IN G.F

1043 0.75 Cu.Ft. 782

4.5" thk. BK.


RFT D H
WORK IN G.F

101.8 9.5 Sq.Ft. 967


DEDUCTION
DOOR - D 3 3 7 Sq.Ft. 63.00

DOOR - D1 1 2.5 7 Sq.Ft. 17.50


Sq.Ft. 886.1

4.5" thk. BK.


WORK ABOVE F.L AREA D
IN G.F

886 0.375 Cu.Ft. 332

9" thk. BK. WORK


RFT D H
IN F.F

86 9.5 Sq.Ft. 817


DEDUCTION
WINDOW 1 1 4 4 Sq.Ft. 16

WINDOW 2 1 6 4 Sq.Ft. 24.00

VENTILATOR 1 2 2 Sq.Ft. 4.00

MAIN DOOR 1 4.5 7 Sq.Ft. 31.50

DOOR - D 1 3 7 Sq.Ft. 21.00

Sq.Ft. 721

9" thk. BK. WORK


Sq.Ft. D H
ABOVE F.L IN F.F

721 0.75 Cu.Ft. 540

9" thk. BK. WORK


IN PARAPET RFT D H
WALL

69.25 0.75 3 Cu.Ft. 156


4.5" thk. BK.
RFT D H
WORK IN F.F

32 9.5 Sq.Ft. 304


DEDUCTION
DOOR - D 1 3 7 21
DOOR - D1 1 2.5 7 Sq.Ft. 17.50

Sq.Ft. 265.5

4.5" thk. BK.


WORK ABOVE F.L AREA D
IN F.F

266 0.375 Sq.Ft. 100


8 WINDOWS L B D
GROUND FLOOR
WINDOW 1 6 4 4 Sq.Ft. 96

WINDOW 2 1 6 4 Sq.Ft. 24.00


FIRST FLOOR
WINDOW 1 1 4 4 Sq.Ft. 16.00

WINDOW 2 1 6 4 Sq.Ft. 24.00

Sq.Ft. ###
9 VENTILATOR L B D
GROUND FLOOR
3 2 2 Sq.Ft. 12.00
& FIRST FLOOR

Sq.Ft. 12.00
10 EARTH FILLING L B D
27 44 1.25 Cu.Ft. 1485

CERAMIC
11 L B AREA
FLOORING IN

FIRST FLOOR 26 66 1716 Sq.Ft. ###

ADD 10%
(SKATING & 0.1 Sq.Ft. 171.6
WASTAGE)

Sq.Ft. 1888
12 WALL CLADDING L B AREA
40 7 Sq.Ft. 280

ADD 10%
(SKATING & 0.1 Sq.Ft. 28
WASTAGE)

Sq.Ft. 308

PLASTERING IN
13 CEILING &
SUNSHADE

GROUND FLOOR 25.5 42.5 Sq.Ft. ###

FIRST FLOOR 25.5 14.38 Sq.Ft. ###

SUNSHADE 1 7 5 2 2 Sq.Ft. ###

SUNSHADE 2 2 7 2 2 Sq.Ft. 56.00

ROOF BEAM
120.4 0.75 Sq.Ft. 90.28
(GROUND FLOOR)

ROOF BEAM
14.38 0.75 Sq.Ft. 10.78
(FIRST FLOOR)
Sq.Ft. ###

WALL
14 RFT ht.
PLASTERING
OUTER WALL
PLASTERING 1 128 10 Sq.Ft. ###
GROUND FLOOR
DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6

DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1

WINDOW -W 6 4 4 0.75 Sq.Ft. 72.0

WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0

VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0

Sq.Ft. 1150.3

PLINTH
RFT ht
PLASTERING

142 3 Sq.Ft. 426

OUTER WALL
PLASTERING RFT ht
FIRST FLOOR

85.75 11 Sq.Ft. 943


DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6

DOOR -D 2 3 7 0.75 Sq.Ft. 31.5


DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1

WINDOW -W 1 4 4 0.75 Sq.Ft. 12.0

WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0

VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0

Sq.Ft. 842.0

RFT ht
PLASTERING
69.75 7 471
PARAPET WALL

Sq.Ft. 471

INNER WALL
PLASTERING

GROUND FLOOR 278.3 9.5 Sq.Ft. ###


DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6

DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1

WINDOW -W 6 4 4 0.75 Sq.Ft. 72.0

WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0

VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0

Sq.Ft. ###
FIRST FLOOR 124 9.5 Sq.Ft. 1178.0
DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6

DOOR -D 2 3 7 0.75 Sq.Ft. 31.5

DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1

WINDOW -W 1 4 4 0.75 Sq.Ft. 12.0

WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0

VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0

Sq.Ft. ###

CEMENT
15
PAINTING
OUTER WALL
PAINTING 1 40 11.583 463.3 Sq.Ft. 463.3
GROUND FLOOR
DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6

DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1

WINDOW -W 6 4 4 0.75 Sq.Ft. 72.0

WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0

VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0

Sq.Ft. 333.6
OUTER WALL
PAINTING FIRST RFT ht
FLOOR

85.75 11 Sq.Ft. 943


DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6

DOOR -D 2 3 7 0.75 Sq.Ft. 31.5

DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1

WINDOW -W 1 4 4 0.75 Sq.Ft. 12.0

WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0

VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0

Sq.Ft. 842.0

RFT ht
PAINTING
69.75 7 471
PARAPET WALL

Sq.Ft. 471

INNER WALL
PAINTING

GROUND FLOOR 278.3 9.5 Sq.Ft. ###


DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6

DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1


WINDOW -W 6 4 4 0.75 Sq.Ft. 72.0

WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0

VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0

Sq.Ft. ###

FIRST FLOOR 124 9.5 Sq.Ft. 1178.0


DEDUCTION
MAIN DOOR 1 4.5 7 0.75 Sq.Ft. 23.6

DOOR -D 2 3 7 0.75 Sq.Ft. 31.5

DOOR - D1 1 2.5 7 0.75 Sq.Ft. 13.1

WINDOW -W 1 4 4 0.75 Sq.Ft. 12.0

WINDOW -W1 1 6 4 0.75 Sq.Ft. 18.0

VENTILATOR 1 2 2 0.75 Sq.Ft. 3.0

Sq.Ft. ###

M.S .GRILLS & MS


16 L B
GATE
GROUND FLOOR
WINDOW 1 6 4 4 3 KG ###
WINDOW 2 1 6 4 3 KG 72.00
FIRST FLOOR
WINDOW 1 1 4 4 3 KG 48.00
WINDOW 2 1 6 4 3 KG 72.00
MS GATE KG ###
M.T 0.68

ENAMEL
17 PAINTING(Doors&
Windows)
GROUND FLOOR
DOOR

MAIN DOOR - MD 1 4.5 7 2 Sq.Ft. 63.00

DOOR - D 3 3 7 2 Sq.Ft. ###

DOOR - D1 2 2.5 7 2 Sq.Ft. 70.00

FIRST FLOOR
DOOR

MAIN DOOR - MD 1 4.5 7 2 Sq.Ft. 63.00

DOOR - D 2 3 7 2 Sq.Ft. 84.00

DOOR - D1 1 2.5 7 2 Sq.Ft. 35.00

GROUND FLOOR
WINDOW

WINDOW - W 6 4 4 2 Sq.Ft. ###

WINDOW -W1 1 6 4 2 Sq.Ft. 48.00

FIRST FLOOR
WINDOW

WINDOW - W 1 4 4 2 Sq.Ft. 32.00

WINDOW -W1 1 6 4 2 Sq.Ft. 48.00

Sq.Ft. ###
18 PLINTH STEPS 6 NOS. 6.0
19 EWC 2 NOS. 2 2
20 WASHBASIN 1 NOS. 1 1
21 SEPTIC TANK 12000 Liters NOS. ###
22 STEPS 24 NOS. 24.0
23 SINTEX TANK 2000 Liters NOS. ###
24 A.T.T 27 47 Sq.Ft. ###

WATER
25 27 47 Sq.Ft. ###
PROOFING

You might also like