RCC

ITEM DESCRIPTION UOM QTY RATE AMOUNT REMARKS

Demolishing R.C.C. work manually/ by mechanical


means including stacking of steel bars and disposal of
unserviceable material within 50 metres lead as per
direction of Engineer - in- charge.

Rate Analysis For .5 Cum

Mate/Supervisor Day 0.20 500 100

Blacksmith (2nd Class) Day 0.25 450 113

Labour Skilled For Breaker Day 2.00 450 900

Labour UN-Skilled For Helper Day 1.00 300 300

Breaker Hrs 8.00 240 1920

Scaffolding LS 1.00 200 200

Labour For Stacking Material Day 0.20 350 70

Labour For Stacking Material Day 0.20 350 70

Total 3673

Add CPOH @ 22.5% 826

Cost for .5 Cum 4499

Cost for 1 Cum 8998

Say 8998

Note:- GST Will Be Extra As Applicable

Page 1 of 2
418034040.xlsx
Brick Work

ITEM DESCRIPTION UOM QTY RATE AMOUNT REMARKS

Demolishing brick work manually/ by mechanical


means including stacking of serviceable material and
disposal of unserviceable material within 50 metres
lead as per direction of Engineer-in-charge.

Rate Analysis For 1 Cum

Mate/Supervisor Day 0.20 500 100

Labour Skilled Day 0.30 450 135

Labour Un-Skilled Day 3.00 300 900

Scaffolding LS 1.00 200 200

Labour For Stacking Material Day 0.20 350 70

Labour For Stacking Material Day 0.20 350 70

Total 1475

Add CPOH @ 22.5% 332

Cost for 1 Cum 1807

Say 1807

Note:- GST Will Be Extra As Applicable