1 15.1 A Restoration 54 cum 101 5454 total 7.

2% raincuts for 2nd year


2 15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
3 15.3.I Repair of p 0 sqm 6976 0 not required
4 15.3.IV Maintenanc 0 sqm 165 0 not required
5 15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
6 15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
7 15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
8 15.11 Maintenanc 1 km 326 326
9 15.12.I Cutting br 20 no 64 1280
10 15.12.II Cutting of 40 no 4 160
11 15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
12 15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
For 3rd Year
5 15.7.I Maintenance of Hume pipe culverts 1 15.1 A
6 15.9 Maintenance of Road signs 2 15.2.I
7 15.10.II Maintenance of RCC railing 3 15.3.I
8 15.11 Maintenance of 200 m stones and Km stones 4 15.3.IV
9 15.12.I Cutting branches of trees from roadway 5 15.7.I
10 15.12.II Cutting of shrubs from roadway 6 15.9
11 15.12.III Trimming grass and weeds from shoulder 7 15.10.II
12 15.13 White washing of parapet walls of CD works 8 15.11
Total 9 15.12.I
10 15.12.II
For 3rd Year 11 15.12.III
1 15.1 A Restoration of rain cuts 12 15.13
2 15.2.I Maintenance of earthen shoulder ( stripping of excess soil)
3 15.3.I Repair of pot holes by removal of failed material and filling with 75mm BM
4 15.3.IV Maintenance of Bituminous surface (Repair to pot holes and removal of loose material)
5 15.7.I Maintenance of Hume pipe culverts
6 15.9 Maintenance of Road signs
7 15.10.II Maintenance of RCC railing
15.11 Maintenance of 200 m stones and Km stones
15.12.I Cutting branches of trees from roadway
15.12.II Cutting of shrubs from roadway

For 2nd Year


1 15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
2 15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
3 15.3.I Repair of p 0 sqm 6976 0 not required
4 15.3.IV Maintenanc 0 sqm 165 0 not required
5 15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
6 15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
7 15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
8 15.11 Maintenanc 1 km 326 326
9 15.12.I Cutting br 20 no 64 1280
10 15.12.II Cutting of 40 no 4 160
11 15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
12 15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
For 2nd Year
1 15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
2 15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
3 15.3.I Repair of p 0 sqm 6976 0 not required
4 15.3.IV Maintenanc 0 sqm 165 0 not required
5 15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
6 15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
7 15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
8 15.11 Maintenanc 1 km 326 326
9 15.12.I Cutting br 20 no 64 1280
10 15.12.II Cutting of 40 no 4 160
11 15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
12 15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
10 15.12.II Cutting of 40 no 4 160
11 15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
12 15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
2 15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
3 15.3.I Repair of p 0 sqm 6976 0 not required
4 15.3.IV Maintenanc 0 sqm 165 0 not required
5 15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
6 15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
7 15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
8 15.11 Maintenanc 1 km 326 326
9 15.12.I Cutting br 20 no 64 1280
10 15.12.II Cutting of 40 no 4 160
11 15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
12 15.13 White wash 10 sqm 13 130
15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
For 3rd Year
5 15.7.I Maintenance of Hume pipe culverts 1 15.1 A
6 15.9 Maintenance of Road signs 2 15.2.I
7 15.10.II Maintenance of RCC railing 3 15.3.I
8 15.11 Maintenance of 200 m stones and Km stones 4 15.3.IV
9 15.12.I Cutting branches of trees from roadway 5 15.7.I
10 15.12.II Cutting of shrubs from roadway 6 15.9
11 15.12.III Trimming grass and weeds from shoulder 7 15.10.II
12 15.13 White washing of parapet walls of CD works 8 15.11
Total 9 15.12.I
10 15.12.II
For 3rd Year 11 15.12.III
1 15.1 A Restoration of rain cuts 12 15.13
2 15.2.I Maintenance of earthen shoulder ( stripping of excess soil)
3 15.3.I Repair of pot holes by removal of failed material and filling with 75mm BM
4 15.3.IV Maintenance of Bituminous surface (Repair to pot holes and removal of loose material)
5 15.7.I Maintenance of Hume pipe culverts
6 15.9 Maintenance of Road signs
7 15.10.II Maintenance of RCC railing
15.11 Maintenance of 200 m stones and Km stones
15.12.I Cutting branches of trees from roadway
15.12.II Cutting of shrubs from roadway

For 2nd Year


15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
For 2nd Year
15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130

15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
For 3rd Year
5 15.7.I Maintenance of Hume pipe culverts 1 15.1 A
6 15.9 Maintenance of Road signs 2 15.2.I
7 15.10.II Maintenance of RCC railing 3 15.3.I
8 15.11 Maintenance of 200 m stones and Km stones 4 15.3.IV
9 15.12.I Cutting branches of trees from roadway 5 15.7.I
10 15.12.II Cutting of shrubs from roadway 6 15.9
11 15.12.III Trimming grass and weeds from shoulder 7 15.10.II
12 15.13 White washing of parapet walls of CD works 8 15.11
Total 9 15.12.I
10 15.12.II
For 3rd Year 11 15.12.III
1 15.1 A Restoration of rain cuts 12 15.13
2 15.2.I Maintenance of earthen shoulder ( stripping of excess soil)
3 15.3.I Repair of pot holes by removal of failed material and filling with 75mm BM
4 15.3.IV Maintenance of Bituminous surface (Repair to pot holes and removal of loose material)
5 15.7.I Maintenance of Hume pipe culverts
6 15.9 Maintenance of Road signs
7 15.10.II Maintenance of RCC railing
15.11 Maintenance of 200 m stones and Km stones
15.12.I Cutting branches of trees from roadway
15.12.II Cutting of shrubs from roadway

For 2nd Year


15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
For 2nd Year
15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice a year
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trim
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
For 3rd Year
or 2nd year 1 15.1 A Restoration 54 cum 101 5454
2 15.2.I Maintenance 300 sqm 62 18600
3 15.3.I Repair of p 0 sqm 6976 0
4 15.3.IV Maintenanc 0 sqm 165 0
done twice a year 5 15.7.I Maintenanc 4 no 1238 4952
done once in 2 years 6 15.9 Maintenanc 0.5 km 927 463.5
uiring maintenance 7 15.10.II Maintenanc 0.76 m 148 112.48
8 15.11 Maintenanc 1 km 326 326
9 15.12.I Cutting br 20 no 64 1280
10 15.12.II Cutting of 40 no 4 160
the total area requiring grass trimming 11 15.12.III Trimming g 337.5 sqm 1 337.5
12 15.13 White wash 10 sqm 13 130
Total 31815.48

For 2nd Year


Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd year
Maintenance 300 sqm 62 18600 total 12 % for 1st year
Repair of p 0 sqm 6976 0 not required
Maintenanc 0 sqm 165 0 not required
Maintenanc 4 no 1238 4952 maintenance to be done twice a year
Maintenanc 0.5 km 927 463.5 maintenance to be done once in 2 years
Maintenanc 0.76 m 148 112.48 considering 4% requiring maintenance
Maintenanc 1 km 326 326
Cutting br 20 no 64 1280
Cutting of 40 no 4 160
Trimming g 337.5 sqm 1 337.5 considering 15% of the total area requiring grass trimming
White wash 10 sqm 13 130
Total 31815.48

moval of loose material)

or 2nd year

done twice a year


done once in 2 years 1 15.1 A Restoration 54
uiring maintenance 2 15.2.I Maintenance 300
3 15.3.I Repair of p 0
4 15.3.IV Maintenanc 0
5 15.7.I Maintenanc 4
the total area requiring grass trimming 6 15.9 Maintenanc 0.5
7 15.10.II Maintenanc 0.76
8 15.11 Maintenanc 1
9 15.12.I Cutting br 20
10 15.12.II Cutting of 40
or 2nd year 11 15.12.III Trimming g 337.5
12 15.13 White wash 10
Total

done twice a year


done once in 2 years 101 5454 total 7.2% raincuts for 2nd year
uiring maintenance 62 18600 total 12 % for 1st year
6976 0 not required
165 0 not required
1238 4952 maintenance to be done twice a year
the total area requiring grass trimming 927 463.5 maintenance to be done once in 2 years
148 112.48 considering 4% requiring maintenance
326 326
64 1280
4 160
the total area requiring grass trimming 1 337.5 considering 15% of the total area requiring grass trimming
13 130
31815.48

2 15.2.I Maintenance 300 sqm 62 18600


3 15.3.I Repair of p 0 sqm 6976 0
4 15.3.IV Maintenanc 0 sqm 165 0
done twice a year 5 15.7.I Maintenanc 4 no 1238 4952
done once in 2 years 6 15.9 Maintenanc 0.5 km 927 463.5
uiring maintenance 7 15.10.II Maintenanc 0.76 m 148 112.48
8 15.11 Maintenanc 1 km 326 326
9 15.12.I Cutting br 20 no 64 1280
10 15.12.II Cutting of 40 no 4 160
the total area requiring grass trimming 11 15.12.III Trimming g 337.5 sqm 1 337.5
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total are
or 2nd year 15.13 White wash 10 sqm 13 130
15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd yea
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
done twice a year 15.3.IV Maintenanc 0 sqm 165 0 not required
done once in 2 years 15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice
uiring maintenance 15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once i
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maint
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
the total area requiring grass trimming 15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total are
15.13 White wash 10 sqm 13 130
Total 31815.48
For 2nd Year Say Rs. 31815
Restoration 54 For 3rd Year
Maintenance 300 5 15.7.I Maintenance of Hume pipe culverts
Repair of p 0 6 15.9 Maintenance of Road signs
Maintenanc 0 7 15.10.II Maintenance of RCC railing
Maintenanc 4 8 15.11 Maintenance of 200 m stones and Km stones
Maintenanc 0.5 15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total are
Maintenanc 0.76 15.13 White wash 10 sqm 13 130
Maintenanc 1 15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd yea
Cutting br 20 15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
Cutting of 40 15.3.I Repair of p 0 sqm 6976 0 not required
Trimming g 337.5 15.3.IV Maintenanc 0 sqm 165 0 not required
White wash 10 15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice
Total 15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once i
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maint
moval of loose material) 15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total are
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
For 3rd Year
5 15.7.I Maintenance of Hume pipe culverts
or 2nd year 6 15.9 Maintenance of Road signs
7 15.10.II Maintenance of RCC railing
8 15.11 Maintenance of 200 m stones and Km stones
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total are
done twice a year 15.13 White wash 10 sqm 13 130
done once in 2 years 15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd yea
uiring maintenance 15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice
the total area requiring grass trimming 15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once i
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maint
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
or 2nd year 15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total are
15.13 White wash 10 sqm 13 130
Total 31815.48
Say Rs. 31815
done twice a year For 3rd Year
done once in 2 years 5 15.7.I Maintenance of Hume pipe culverts
uiring maintenance 6 15.9 Maintenance of Road signs
7 15.10.II Maintenance of RCC railing
8 15.11 Maintenance of 200 m stones and Km stones
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total are
the total area requiring grass trimming 15.13 White wash 10 sqm 13 130
15.1 A Restoration 54 cum 101 5454 total 7.2% raincuts for 2nd yea
15.2.I Maintenance 300 sqm 62 18600 total 12 % for 1st year
15.3.I Repair of p 0 sqm 6976 0 not required
15.3.IV Maintenanc 0 sqm 165 0 not required
the total area requiring grass trimming 15.7.I Maintenanc 4 no 1238 4952 maintenance to be done twice
15.9 Maintenanc 0.5 km 927 463.5 maintenance to be done once i
15.10.II Maintenanc 0.76 m 148 112.48 considering 4% requiring maint
15.11 Maintenanc 1 km 326 326
15.12.I Cutting br 20 no 64 1280
15.12.II Cutting of 40 no 4 160
15.12.III Trimming g 337.5 sqm 1 337.5 considering 15% of the total are
done twice a year 15.13 White wash 10 sqm 13 130
done once in 2 years Total 31815.48
uiring maintenance Say Rs. 31815
For 3rd Year
5 15.7.I Maintenance of Hume pipe culverts
6 15.9 Maintenance of Road signs
the total area requiring grass trimming 7 15.10.II Maintenance of RCC railing
8 15.11 Maintenance of 200 m stones and Km stones

or 2nd year 1
2
3
4
done twice a year 5
done once in 2 years 6
uiring maintenance 7
8
9
10
the total area requiring grass trimming 11
12

For 2nd Year


Restoration 54 cum 101
Maintenance 300 sqm 62
Repair of p 0 sqm 6976
Maintenanc 0 sqm 165
Maintenanc 4 no 1238
Maintenanc 0.5 km 927
Maintenanc 0.76 m 148
Maintenanc 1 km 326
Cutting br 20 no 64
Cutting of 40 no 4
Trimming g 337.5 sqm 1
White wash 10 sqm 13
Total

moval of loose material)

or 2nd year

done twice a year


done once in 2 years 1
uiring maintenance 2
3
4
5
the total area requiring grass trimming 6
7
8
9
10
or 2nd year 11
12

done twice a year


done once in 2 years 101
uiring maintenance 62
6976
165
1238
the total area requiring grass trimming 927
148
326
64
4
the total area requiring grass trimming 1
13

2
3
4
done twice a year 5
done once in 2 years 6
uiring maintenance 7
8
9
10
the total area requiring grass trimming 11
15.12.III
or 2nd year 15.13
15.1 A
15.2.I
15.3.I
done twice a year 15.3.IV
done once in 2 years 15.7.I
uiring maintenance 15.9
15.10.II
15.11
15.12.I
the total area requiring grass trimming 15.12.II
15.12.III
15.13

For 2nd Year


total 7.2% raincuts for 2nd year
total 12 % for 1st year
not required
not required
maintenance to be done twice a year
maintenance to be done once in 2 years
considering 4% requiring maintenance

considering 15% of the total area requiring grass trimming

g grass trimming
g grass trimming

total 12 % for 1st year


not required
not required
maintenance to be done twice a year
maintenance to be done once in 2 years
considering 4% requiring maintenance

considering 15% of the total area requiring grass trimming


considering 15% of the total area requiring grass trimming

total 7.2% raincuts for 2nd year


total 12 % for 1st year
not required
not required
maintenance to be done twice a year
maintenance to be done once in 2 years
considering 4% requiring maintenance

considering 15% of the total area requiring grass trimming

For 2nd Year


1 15.1 A Restoration 54
2 15.2.I Maintenance 300
3 15.3.I Repair of p 0
4 15.3.IV Maintenanc 0
considering 15% of the total area requiring grass trimming

total 7.2% raincuts for 2nd year


total 12 % for 1st year
not required
not required
maintenance to be done twice a year
maintenance to be done once in 2 years
considering 4% requiring maintenance

considering 15% of the total area requiring grass trimming

For 2nd Year


1 15.1 A Restoration 54
2 15.2.I Maintenance 300
3 15.3.I Repair of p 0
4 15.3.IV Maintenanc 0
considering 15% of the total area requiring grass trimming

total 7.2% raincuts for 2nd year


total 12 % for 1st year
not required
not required
maintenance to be done twice a year
maintenance to be done once in 2 years
considering 4% requiring maintenance

considering 15% of the total area requiring grass trimming

For 2nd Year


1 15.1 A Restoration 54
2 15.2.I Maintenance 300
3 15.3.I Repair of p 0
4 15.3.IV Maintenanc 0
considering 15% of the total area requiring grass trimming

total 7.2% raincuts for 2nd year


total 12 % for 1st year
not required
not required
maintenance to be done twice a year
maintenance to be done once in 2 years
considering 4% requiring maintenance

considering 15% of the total area requiring grass trimming


For 2nd Year
1 15.1 A Restoration 54
2 15.2.I Maintenance 300
3 15.3.I Repair of p 0
4 15.3.IV Maintenanc 0