You are on page 1of 5

Working

SIZE Blinding Base sl Wall thk Slab thk space


0.600 0.600 1.000 - 0.075 0.250 0.200 0.200 0.750

S.NO Description of Item Quantity Unit Rate Amount

1 Excavation to receive manhole 9.53 M3


2 Back filling by excavated earth 7.09 M3
3 Disposal of excavated earth 2.44 M3
4 50mm thk blinding concrete 1.00 M2
5 C45 base slab 0.25 M3
6 Wall concrete 0.64 M3
7 Roof slab concrete 0.2 M3
8 Benching concrete 0.360 M2

8 Formwork to blinding 4 M
10 Formwork to base slab sides 4 M
11 Formwork to walls 3.20 M2
12 Formwork to roof slab bottom 0.360 M2
13 Form work to roof slab sides 4 M

13 Reinforcement 85.565 KG

14 1000G polythene sheet 1.00 M2


15 Two coats of bituminous paint - Internally 2.400 M2
16 Two coats of bituminous paint - Externally 5.30 M2
17 150mm thk engineering block work 0.64 M2
18 10mm thick epoxy mortar over benching 0.360 M2

19 Manhole cover 1 No
20 Step Iron @ 300 c/c 3 No
Working
SIZE Blinding Base sl Wall thk Slab thk space
0.800 0.700 1.000 - 0.100 0.200 0.200 0.200 0.750

S.NO Description of Item Quantity Unit Rate Amount

1 Excavation to receive manhole 10.53 M3


2 Back filling by excavated earth 6.75 M3
3 Disposal of excavated earth 3.78 M3
4 50mm thk blinding concrete 1.32 M2
5 C45 base slab 0.264 M3
6 Wall concrete 0.76 M3
7 Roof slab concrete 0.264 M3
8 Benching concrete 0.560 M2

8 Formwork to blinding 4.6 M


10 Formwork to base slab sides 4.6 M
11 Formwork to walls 3.80 M2
12 Formwork to roof slab bottom 0.560 M2
13 Form work to roof slab sides 4.6 M

13 Reinforcement 101.108 KG

14 1000G polythene sheet 1.32 M2


15 Two coats of bituminous paint - Internally 3.000 M2
16 Two coats of bituminous paint - Externally 5.98 M2
17 150mm thk engineering block work 0.76 M2
18 10mm thick epoxy mortar over benching 0.560 M2

19 Manhole cover 1 No
20 Step Iron @ 300 c/c 3 No
SOAK PIT
SIZE Strip width Blinding Base slabWall thk Slab thk
0.600 0.600 0.600 0.500 0.050 0.150 0.200 0.150
2.0mx2.0mx2.0m
S.NO Description of Item Quantity Unit Rate Amount

1 Excavation to receive manhole 8.55 M3 2.500 21.375


2 Back filling inside soak pit 0.27 M3 3.000 0.810
3 Gravel filling outside pit 7.20 M3 7.500 54.000
4 Disposal of excavated earth 8.55 M3 1.500 12.825
5 50mm thk blinding concrete 1.60 M2 3.500 5.600
6 C45 base slab 0.24 M3 36.000 8.640
7 Block work infilled 1.92 M2 10.000 19.200
8 Roof slab concrete 0.15 M3 36.000 5.400
-
9 Formwork to blinding 4 M 1.000 4.000
10 Formwork to strip footing sides 6.4 M 1.500 9.600
11 Formwork to roof slab bottom 0.360 M2 6.000 2.160
12 Form work to roof slab sides 4 M 6.000 24.000
-
13 Reinforcement 39 KG 0.450 17.550
-
14 1000G polythene sheet 1.60 M2 0.400 0.640
15 Terram 1000 - Externally 9.60 M2 0.600 5.760
16 150mm thk engineering block work - M2 -
-
17 Manhole cover 1 No 65.000 65.000

256.560
Working
space
1.000
Working
SIZE Blinding Base sl Wall thk Slab thk space
1.800 1.800 1.150 - 0.075 0.200 0.200 0.150 0.750

S.NO Description of Item Quantity Unit Rate Amount

1 Excavation to receive manhole 21.56 M3


2 Back filling by excavated earth 12.99 M3
3 Disposal of excavated earth 8.57 M3
4 50mm thk blinding concrete 4.84 M2
5 C45 base slab 0.968 M3
6 Wall concrete 1.60 M3
7 Roof slab concrete 0.726 M3
8 Benching concrete 3.240 M2

8 Formwork to blinding 8.8 M


10 Formwork to base slab sides 8.8 M
11 Formwork to walls 9.20 M2
12 Formwork to roof slab bottom 3.240 M2
13 Form work to roof slab sides 8.8 M

13 Reinforcement 258.579 KG

14 1000G polythene sheet 4.84 M2


15 Two coats of bituminous paint - Internally 8.280 M2
16 Two coats of bituminous paint - Externally 12.54 M2
17 150mm thk engineering block work 1.20 M2
18 10mm thick epoxy mortar over benching 3.240 M2

19 Manhole cover 1 No
20 Step Iron @ 300 c/c 4 No

You might also like