Haram Building Architectural Scope

Item. Plotting current progress. Estimated time for completion (1x person).

A. Special Package. 75% 112 day(s).


1. Lighting Fixtures. 95% 12 day(s).
a. chandeliers. 95% 4 day(s).
b. wall luminaires. 95% 4 day(s).
c. led linear luminaires. 95% 4 day(s).
2. Gold‐Plated Screens. 95% 16 day(s).
a. speaker screens. 95% 4 day(s).
b. jet diffuser screens. 95% 4 day(s).
c. ac 70x70 screens. 95% 4 day(s).
d. air return screens. 95% 4 day(s).
3. Rings. 95% 4 day(s).
4. Lighting Corbels. 95% 4 day(s).
5. Brass Octagons. 95% 4 day(s).
6. Aluminum Balustrades. 50% 12 day(s).
7. Aluminum Screens. 50% 12 day(s).
8. Bronze Screens. 50% 12 day(s).
9. Skylights. 80% 4 day(s).
10. Domes. 80% 4 day(s).
11. Minarets. 80% 4 day(s).
12. Decorative False Ceilings. 30% 24 day(s).
B. Marble Package. 50% 168 day(s).
1. Flooring. 50% 24 day(s).
2. Columns. 50% 36 day(s).
a. capitals. 50% 12 day(s).
b. bases. 50% 12 day(s).
c. plenium boxes. 50% 12 day(s).
3. Elevations. 50% 48 day(s).
a. external walls. 50% 12 day(s).
b. internal walls. 50% 12 day(s).
c. shooters. 50% 12 day(s).
d. open courts. 50% 12 day(s).
4. Handrails. 50% 12 day(s).
5. Drinking fountains. 50% 12 day(s).
6. Seats. 50% 12 day(s).
7. Quran racks. 50% 12 day(s).
8. Calligraphy. 50% 12 day(s).
C. Chandelier Waterproofing. 90% 12 day(s).
D. Screed. 50% 8 day(s).
E. Marble Waterproofing. 50% 24 day(s).
F. Blockwork. 70% 24 day(s).
G. Plaster. 70% 16 day(s).
H. Paint. 20% 56 day(s).
I. Wood Cladding. 70% 16 day(s).
J. Vinyl. 70% 16 day(s).
k. G.R.C Skirting. 70% 20 day(s).
L. Ceramic. 50% 36 day(s).