REPORT DATE PROJECT NAME PREPARED BY

December 31, 2018 MATI WATERWORKS SYSTEM ENGR. MARK ROGER HUBERIT II
1. Package 1 - Pipe laying
2. Package 2 - Construction of Intake
3. Package 3 – Site Dev, WTP, and Ops Bldg.

PROJECT SUMMARY

Package 1- Pipe laying project


Location : Mati Davao Oriental
Contract No: PL-MATI-0518-06
Contract amount: 4,849,030.08
Contractor: Nick Cabungcal
Contract duration: 120 Calendar days
Notice to proceed: 05/23/18
Completion date: 20-Sep-18
Percent Accomplishment As of December 31, 2018: 14%

Physical Accomplishment

No. of
Description Concreting Pipe laying Service
Connection

Hydro
Cutting Breaking Restoration Target Energized
Installed tested Installed
(lm) (lm) (lm) Quantity (Lm)
(Lm)

25mm

32mm

50 mm
1276 1276 1276
diameter
100 mm
372.05 336.80 6055.88 2179.5 1782
diameter
150 mm
5.20 17.20 9202.95 1581 1551
diameter

 Project Schedule
Delayed. Request for time extension by contractor under evaluation.
Package 2 - Intake Structure
Location : Mati Davao Oriental
Contract No: WTP-MAT-0818-04
Contract amount: 1,963,677.97
Contractor: Nick Cabungcal
Contract duration: 100 Calendar days
Notice to proceed: 09/25/18
Completion date: 23-Dec-18
Percent Accomplishment As of December 31, 2018: 39.57%

Physical Accomplishment
 Excavation works
A. Riprap Base -100% complete
B. Reservoir / Impounding - 100% complete
C. Intake Chamber - 90% complete
 Masonry works
A. Slope Protection – 100% complete
 On-going works

 Project Schedule
A. Delayed. Request for time extension by contractor under evaluation.

Package 3:
1. Scope - Site Development, WTP, Operations Bulding

2. Detailed Engineering Design

a. WTP – 100% complete


b. Operations Building – 100% complete
c. Site Development including Fencing – 100% complete

3. Capex Budget – for approval


4. Contract Awarding – for negotiation with Nick Cabungcal after approval of SOP by Sir CLP

PROJECT PROGRESS PHOTOS( PRESENT – ACTUAL ACCOMPLISHMENT) DECEMBER 31,2018

Page 2
Revetment Underway riprap works, date Intake/Impounding Underway excavation
TakenRevetment
December Underway
10, 2018- photo
riprap credit
works,Engr
date works, date TakenUnderway
Revetment December 10, 2018-
riprap works,photo
date Taken
Richard Santiago
Taken December 10, 2018- photo credit EngrcreditDecember
Engr Richard
10, Santiago
2018- photo credit Engr Richard
Richard Santiago Santiago

Page 3