Deltek Acumen Fuse Schedule Diagnostics

Deltek’s Acumen Fuse software package offers a wide range of project analysis
and diagnostic tools to help you raise the quality and effectiveness of your
schedule data.

In this article we will take a look at the Acumen Fuse schedule diagnostics tool and
walk through the process of analyzing a schedule from the Primavera P6 system.
The analysis featured in this article is a general analysis based upon practice
standards of scheduling in the industry. Other analysis such as the DCMA 14 Point
Assessment is also available in Acumen Fuse schedule diagnostics by changing
the selection at the bottom of the window.

Acumen Fuse Projects Tab


The first step in this process is to open the project that you wish to analyze in the
Projects tab of the Acumen Fuse interface. As you can see in the following screen
shot there are a number of systems that you can bring project data in from. These
include Microsoft Project, Primavera P6, Excel spreadsheets, Open Plan,
Cobra, Phoenix Project Manager, a standard UN/CEFACT xml file and Safran.

When you first open Acumen Fuse the Projects list contains an empty Workbook.
The first step is to load a project into the empty workbook. To do this, we click on
the desired external data system: in this case Oracle Primavera P6.
In the ‘Add Primavera P6 File’ dialog, select your .XER or .XML file that contains
your Primavera P6 schedule:

Tip: if you click on the lower part of the product button, Acumen will provide you
with a comprehensive list of all the formats and loading possibilities for the
particular product you are importing.
Having imported your Primavera P6 file, you will see it listed below the Workbook
header. However, this is just the first step. To perform any analysis on this project,
you will need to now import it to Acumen Fuse.
An import is performed using the Import All Projects button located in the Import
section of the Projects ribbon.

With your project name checked in the workbook, click on the Import All Projects
button. Again if you click on the lower half of the button, you will see there are two
import options: Import All Projects (for when you have loaded more than just one
project into the Workbook) or Import Project. In this example we had just one
selected project so we used the second option.
After a brief process execution, the imported project’s details appear in the table
and Gantt Chart area of the Projects tab.

Now would be a good time to go to the Acumen Fuse menu and save your
Workbook.

Having saved your workbook, you can drill down through the various elements of
your project to verify the data. You are now ready to perform a diagnostic on your
schedule.
Acumen Fuse Diagnostics Tab
The next step in this process is to click on the Diagnostics tab to access the
diagnostic tools in Acumen Fuse. Once you open the diagnostics tag you see a
timeline and a ribbon analyzer. You also see a prompt to click Fuse to calculate
metrics and display ribbons. Go to the analyze tool group and click on the fuse
button.

After a few moments the analysis is completed and you will see the project’s score
in the ribbon analyzer along with a detailed table of scores set out across the
project timeline.
In the top right you can see the overall score for the project. In this example the
project scored 79%.

This is considered a high score for the project. We can also see a summary of how
that score was derived in the other cells to the left in the ribbon analyzer. Let’s talk
about some of those scores and what they mean.

Missing Logic – One activity, 2% of the overall activities is missing either a


predecessor or successor.

Logic Density – 2.9 indicates the average number of relationships per activity. In
theory this should be two or more.

Critical – this metric tells us there are 32 critical activities in the project so just over
50% of the project activities are critical.

Hard Constraints – the project contains no hard constraints. Most guidelines


discourage the use of hard constraints.

Negative Float – the number of activities with a negative float value. A gain we
have a zero in this project example which is a high score. Baseline projects, such
as our example, should never contain negative float.
Insufficient Detail – our sample project has two activities that are considered long
duration. That is activities that are 10% of the projects overall duration or greater. If
these are level of effort activities or long lead procurement items, that may be
acceptable. Our project therefore has barely passed this metric.

Number of Lags – a sample project has five activities with lags on them which is
giving a score of 8%. This is well below the 25% guideline.

Number of Leads – leads (or negative lags) in our sample schedule equal zero.
Typical guidelines discourage the use of negative lags and in fact some contracts
outlaw them completely.

Merge Hotspots – areas of the project where there are a high number of
predecessors on an activity. Our project is showing six merge hotspots giving us a
medium to high score on this metric.

In the timeline area is a table showing how the schools breakout across time
phased periods in the project due to the length of this project it showing them in
years. This helps you analyze which areas of the project displaying some of the
issues summarized in the ribbon analyzer.

Finally we can create a report showing the score for our project in a
comprehensive spreadsheet. To do this we go to the publish button at the far right
of the ribbon. When we click on the publish button we see options to publish to
various media including an Executive Briefing in Microsoft Word, In Microsoft Excel
you are offered a ‘To Microsoft Excel’ current ribbon report, a Fuse Analyst analyst
report, a Fuse Summary Metric report, and even a Deltek wInsight Analytics report.
For this example we will select the Fuse Analyst Report. When we run this report,
Deltek writes the information to an Excel spreadsheet as seen in the final
screenshot. This multi-tab report allows you to examine your project in great detail
and look for areas, or identifies specific activities, that need attention.
Click here to download a copy of the spreadsheet.

Summary
Deltek Acumen Fuse schedule diagnostics has been able to present a detailed
analysis of a Primavera P6 schedule XER in a few simple steps. This gives you the
ability to focus on areas of your schedule that may need attention before submitting
that schedule to a government agency or indeed any customer. It will help you
raise your organization’s standards in scheduling best practice and make sure your
customers are always presented with realistic and achievable schedules that will
score highly against any industry standards.

Furthermore, this is just one area of capability offered by Deltek Acumen Fuse.
This application offers many other features and functions including sophisticated
risk management, reporting dashboards, schedule comparisons, forensic analysis
and many other features. We will be covering further acumen examples in some
later articles.