Date : 21th February 2019

Reference : Indonesia/Makassar/TPM(MSW)
Project : Headblock Assembly (QC06)

Terminal Petikemas Makassar (TPM)


C/O Pt MSW Teknologi Baru
Makassar, Indonesia.

Attention: Chiang LK

Design, Manufacture and Delivery of Two (02) Unit Headblock For Quay Crane in TPM.

The following for the progress report 18th February 2019 to 21th February 2019 at SF Port EQ
Associate Factory in Klang, Malaysia.

Headblock for QC06


• Headblock returns from Sand Blasting and Painting.
• Sheave and Twist lock installed with greasing.
• Headblock ready for shipment – Pending
The ship booked on 27th experience technical error and will be delayed up till 6th March
Note : If there’s a cancel for shipment headblock will be shipped on 27th Feb.

Page 1 of 3
Headblock with Landside and Seaside
4 rubber mounting
Additional Paint

Page 2 of 3
Additional Cable Drum

Page 3 of 3