Professional Documents
Culture Documents
16-1
© 2014 by McGraw-Hill Education. This is proprietary material solely for authorized instructor use. Not authorized for sale or distribution in any
manner. This document may not be copied, scanned, duplicated, forwarded, distributed, or posted on a website, in whole or part.
Chapter 16 - Managing Service Projects
14. Time variance is calculated by subtracting actual time used for work performed from scheduled time
for work performed. (T)
15. When delays occur owing to technical difficulties, performance becomes the source of unexpected
project management problems. (F)
16. Developing a project network is the only major concern for implementing critical path analysis. (F)
17. Merge node bias occurs where the project network contains non-critical paths with small total slack
times. (T)
18. Estimates of project expected completion time and variance usually are not biased when based on the
single critical path. (F)
19. When crashing activities for construction projects, the contractor’s minimum cost duration might not
coincide with the client’s target completion date. (T)
20. A major assumption in project network analysis is that sufficient resources are available to perform
many activities concurrently. (T)
Multiple Choice
1. Which of the following is not true about a critical path in a project network with certain activity times?
a. Activities on the critical path have the least slack.
b. The longest activity in the project must lie on the critical path.*
c. There can be several critical paths in a project network.
d. The first activity in the network is always on the critical path.
2. For a project with uncertain activity times, the probability of project completion exceeding the expected
time calculated for the critical path is:
a. 25 percent.
b. 50 percent.*
c. 75 percent.
d. none of the above.
3. A key assumption underlying project networks is:
a. dummy activities take up no time.
b. the critical path is known with certainty.
c. an activity begins only after all predecessors are completed.*
d. a project network is cyclic.
16-2
© 2014 by McGraw-Hill Education. This is proprietary material solely for authorized instructor use. Not authorized for sale or distribution in any
manner. This document may not be copied, scanned, duplicated, forwarded, distributed, or posted on a website, in whole or part.
Chapter 16 - Managing Service Projects
16-3
© 2014 by McGraw-Hill Education. This is proprietary material solely for authorized instructor use. Not authorized for sale or distribution in any
manner. This document may not be copied, scanned, duplicated, forwarded, distributed, or posted on a website, in whole or part.
Chapter 16 - Managing Service Projects
9. A resource-leveled schedule would have all but one of the following characteristics:
a. the project duration could be longer than normal.
b. slack time is used to begin some activities later than their early start time.
c. the critical path may be changed.*
d. a more balanced use of labor resources would be exhibited.
10. Implementing critical path analysis is faced with all but one of the following problems:
a. availability of project management software.*
b. agreement on the project network.
c. eliciting time estimates for activities.
d. introduction of bias in activity time estimates.
11. Which one of the following attributes is not considered in the selection of a project manager?
a. credibility.
b.originality.*
c. sensitivity.
d.ability to handle stress.
12. The four sequential stages of team development include all but one of the following:
a. forming.
b. storming.
c. coalescing.*
d. performing.
13. Which oneof the following is not considered a source of unexpected project management problems?
a. cost.
b. time.
c. economy.*
d. performance.
16-4
© 2014 by McGraw-Hill Education. This is proprietary material solely for authorized instructor use. Not authorized for sale or distribution in any
manner. This document may not be copied, scanned, duplicated, forwarded, distributed, or posted on a website, in whole or part.
Chapter 16 - Managing Service Projects
14. Projects are terminated for all but one of the following reasons:
a. subtraction.*
b. addition.
c. integration.
d. starvation.
15. A project history report should include all but one of the following items:
a. project performance.
b. organization structure.
c. project success and failures.*
d. project and administrative team.
16. Which one of the following is not considered a source of variance on the earned value chart?
a. time.
b. cost.
c. schedule.
d. none of the above.*
17. Which one of the following makes performance a source of unexpected project management problem?
a. delays owing to technical difficulties.
b. unexpected technical problems.*
c. unforeseen government regulations.
d. increase in the scope of work.
18. Which one of the following is not a critical time estimate for a Beta distribution?
a. optimistic time.
b. pessimistic time.
c. most likely time.
d. expected time.*
16-5
© 2014 by McGraw-Hill Education. This is proprietary material solely for authorized instructor use. Not authorized for sale or distribution in any
manner. This document may not be copied, scanned, duplicated, forwarded, distributed, or posted on a website, in whole or part.
Chapter 16 - Managing Service Projects
19. Which one of the following allows the manager to make probability statements with regard to meeting
project objectives?
a. Gantt chart.
b. CPM.
c. PERT.*
d. earned-value chart.
20. The amount of time an activity can be delayed without delaying the completion of the project is referred
to as:
a. total slack.*
b. late finish.
c. late start.
d. free slack.
16-6
© 2014 by McGraw-Hill Education. This is proprietary material solely for authorized instructor use. Not authorized for sale or distribution in any
manner. This document may not be copied, scanned, duplicated, forwarded, distributed, or posted on a website, in whole or part.