Professional Documents
Culture Documents
Prepared by:
Checked by:
GENERAL DATA
DATA WALL FOOTING
Area of ground floor = 116.25 sq.m Height of wall = 4.55 m
Area of lobby = 0 sq.m Height of footing = 0.3 m
Height above the NGL = 4.6 m Width of footing = 0.4 m
Height below the NGL = 1.4 m
FLOOR BEAM 1
TIE BEAM Height = 0.4 m
Height = 0.35 m Width = 0.25 m
Width = 0.25 m Perimeter = 65.625 m
Perimeter = 65.625 m
SEPTIC TANK
SITE CLEARING AND GRUBBING Length = 3.5 m
Unit cost = 40000 php Width = 1.5 m
Height of wall = 1.8 m
LAYOUT AND BATTERBOARD Height of footing = 0.2 m
Unit cost = 55000 php No. of septic tank = 1 pc
BEAM CEILING
2"X3" Vertical support = 6.00 bd.ft 0.4x0.6m spacing (2"x2" = 5.373 bd.ft.
2"X2" Horizontal support = 4.70 bd.ft
VII. STEEL WORKS
V. MASONRY WORKS Factor of Safety = 10 %
Factor of Safety = 20 % Commercial size of pipe = 6 m
No. of CHB per sq.m = 12.5 pcs
W1F1 VIII. TILE WORKS
Size of CHB Factor of Safety = 10 %
Height = 0.2 m Cement mortar = 0.086 bg/sq.m
Width = 0.15 m White cement = 0.50 kg/sq.m
Length = 0.4 m Tile adhesive = 0.110 bg/sq.m
Size of CHB
Height = 0.2 m GROUND FLOOR
Width = 0.1 m 16"X16" Unglazed/pcs = 0.16 sq.m
Length = 0.4 m
BATHROOM
MORTAR 8"X8" Glazed/pcs = 0.04 sq.m
15X20X40 cm CHB, Class B Mixture 8"X8" Unglazed/pcs = 0.04 sq.m
Cement = 1.018 bags
Sand = 0.0844 m³
IX. PAINTING WORKS X. ELECTRICAL WORKS
WALL Commercial cunduit = 150.00 m/box
Concrete Neutralizer = 40 sq.m. PVC conduit = 3.00 m
Primer = 40 sq.m.
Masonry Putty = 40 sq.m.
Finishing = 40 sq.m.
CEILING
Solignum = 40 sq.m.
Primer = 40 sq.m.
Glazing Putty = 40 sq.m.
Finishing = 40 sq.m.
ESTIMATE OF 2-STOREY HARDWARE PROJECT
(First Floor)
(REFER TO PLANNING AND ESTIMATE BOOK BY MAX FAJARDO)
I. EARTHWORKS
A. SITE CLEARING AND GRUBBING
Quantity = 1.000
Unit = lot TOTAL
Unit Cost = 40000 Total cost = 40000.000 php
C. EXCAVATION
COLUMN POST
C1F1
POST FOOTING
Height = 11.100 m Height = 0.300 m
Width = 0.350 m Width = 1.400 m
Length = 0.350 m Length = 1.400 m
Number of footing = 16 pcs Number of footing = 16 pcs
TOTAL VOLUME = 21.756 cu.m. TOTAL VOLUME = 9.408 cu.m.
WALL
W1F1 W2F1
Height = 11.100 m Height = 11.100 m
Width = 0.150 m Width = 0.100 m
Length = 50.850 m Length = 24.425 m
VOLUME = 84.665 cu.m. VOLUME = 27.112 cu.m.
TOTAL VOLUME = 111.777 cu.m.
WALL FOOTING
W1F1 W2F1
Height = 0.300 m Height = 0.300 m
Width = 0.400 m Width = 0.400 m
Length = 50.850 m Length = 24.425 m
VOLUME = 6.102 cu.m. VOLUME = 2.931 cu.m.
TOTAL VOLUME = 9.033 cu.m.
SEPTIC TANK
Height = 2.000 m
Length = 3.500 m
Width = 1.500 m TOTAL VOLUME
Number of septic tan = 1 pc 10.500 cu.m.
CATCH BASIN
Height = 0.700 m
Width = 0.500 m
Length = 0.500 m TOTAL VOLUME
Number of catch bas = 6 pcs 1.05 cu.m.
TOTAL
VOLUME = 163.524 cu.m.
D. BACKFILL
COLUMN
C1F1
POST FOOTING
Excavation = 21.756 cu.m. Excavation = 9.408 cu.m.
Concreting = 21.756 cu.m. Concreting = 9.408 cu.m.
VOLUME = 0.000 cu.m. VOLUME = 0.000 cu.m.
WALL
W1F1 W2F1
Excavation = 84.665 cu.m. Excavation = 27.112 cu.m.
Concreting = 34.705 cu.m. Concreting = 11.113 cu.m.
VOLUME = 49.960 cu.m. VOLUME = 15.998 cu.m.
TOTAL VOLUME = 65.959 cu.m.
WALL FOOTING
W1F1 W2F1
Excavation = 6.102 cu.m. Excavation = 2.931 cu.m.
Concreting = 6.102 cu.m. Concreting = 2.931 cu.m.
VOLUME = 0.000 cu.m. VOLUME = 0.000 cu.m.
TOTAL VOLUME = 0.000 cu.m.
SEPTIC TANK
Excavation = 10.500 cu.m.
Concreting = 3.398 cu.m.
VOLUME = 7.102 cu.m.
CATCH BASIN
Excavation = 1.050 cu.m.
Concreting = 0.470 cu.m.
VOLUME = 0.580 cu.m.
TOTAL
VOLUME = 73.641 cu.m.
E. SOIL POISONING
Area = 116.250 sq.m
Area per bottle = 100.000 sq.m
Unit Cost = 6000 php
TOTAL
Total cost = 6975 php
F. EARTH FILL
SLAB
Compaction = 25.000 %
Space Required = 162.750 cu.m.
Backfill = 73.641 cu.m.
VOLUME = 89.109 cu.m.
TOTAL
VOLUME = 106.931 cu.m.
II. CONCRETE WORKS
A. COLUMN POST
C1F1
Below the GL Above the GL
Height = 11.100 m Height = 4.600 m
Width = 0.350 m Width = 0.350 m
Length = 0.350 m Length = 0.350 m
Number of footing = 16 pcs Number of footing = 16 pcs
TOTAL VOLUME = 21.756 cu.m. TOTAL VOLUME = 9.016 cu.m.
B. COLUMN FOOTING
C1F1
Height = 0.300 m
Width = 1.400 m
Length = 1.400 m
Number of footing = 16 pcs
TOTAL VOLUME = 9.408 cu.m.
C. WALL FOOTING
W1F1 W2F1
Height = 0.300 m Height = 0.300 m
Width = 0.400 m Width = 0.400 m
Length = 50.850 m Length = 24.425 m
VOLUME = 6.102 cu.m. VOLUME = 2.931 cu.m.
TOTAL VOLUME = 9.033 cu.m.
E. SLAB
Height = 0.750 m
Area of ground floor = 116.250 m
Area of carport = 0.000 m
TOTAL VOLUME = 87.188 cu.m.
F. STAIRCASE
OUTSIDE MAIN
Volume per step = 0.150 cu.m. Volume per step = 1.200 cu.m.
Volume of landing = 0.563 cu.m.
TOTAL VOLUME = 1.913 cu.m.
G. SEPTIC TANK
FOOTING CONCRETE COVER
Height = 0.200 m Height = 0.150 m
Width = 0.400 m Width = 1.500 m
Length = 3.660 m Length = 3.500 m
Number of Septic Ta = 1.000 pcs Number of Septic Ta = 1.000 pcs
VOLUME = 0.293 cu.m. VOLUME = 0.788 cu.m.
TOTAL
CEMENT = 1583 bags
SAND = 89 cu.m.
GRAVEL = 177 cu.m.
III. REBAR WORKS
A. COLUMN
MAIN REINFORCEMENT
Commercial length = 6.000 m Number of Steel = 10.000 pcs
Height = 17.100 m Number of footing = 16 pcs
LENGTH = 2736.000 m
No. of RSB = 456.000 pcs of 16mm Ø RSB
LATERAL TIES
Total height = 17.100 m Net Length = 0.270 m
Diameter of ties = 10.000 mm Net Width = 0.270 m
1st Spacing = 0.050 m, 3 pcs Factored = 0.200 m
2nd Spacing = 0.100 m, 3 pcs Size of Lateral ties = 1.280 m
3nd Spacing = 0.150 m, 3 pcs
Spacing = 0.200 m, rest
Length ties @rest = 15.700 m
Pcs of ties in 1 colu = 92.50 pcs
No. of RSB = 315.733 pcs of 10mm Ø RSB
TIE WIRES
No. of kg = 5.236 # 16 G.I. wire
B. COLUMN FOOTING
CUT BARS
Net length = 1.25 m
No. of cut bars = 14 pcs
Total cut bars = 224 pcs
No. of cut bars in 6 = 5 pcs
No. of RSB = 46.667 pcs of 16mm Ø RSB
TIE WIRES
No. of intersection = 49 pcs
No. of tie wires = 784 pcs
Total length of tie wi = 235 m
No. of kg = 4.438 # 16 G.I. wire
C. WALL FOOTING
CONTINUOUS BARS
W1F1 W2F1
Perimeter = 50.85 m Perimeter = 24.425 m
No. of bars = 6 m No. of bars = 6 m
No. of RSB = 50.850 pcs No. of RSB = 24.425 pcs
No. of RSB = 75.275 pcs of 10mm Ø RSB
TRANSVERSE BARS
W1F1 W2F1
Perimeter = 50.85 m Perimeter = 24.425 m
Net length = 0.25 m Perimeter = 0.25 m
Spacing = 0.133 m Spacing = 0.133 m
No. of bars = 383.33 pcs No. of bars = 184.65 pcs
Length = 95.83 m Length = 46.16 m
No. of RSB = 15.972 pcs No. of RSB = 7.694 pcs
No. of RSB = 23.666 pcs of 10mm Ø RSB
TIE WIRES
No. of intersection = 2300 pcs
Length of tie wires = 0.30 m
No. of kg = 13.019 # 16 G.I. wire
D. EXTERIOR WALL
Area = 536.47 sq.m
FOR VERTICAL REINFORCEMENT (SPACING @ 60cm) FOR HORIZONTAL REINFORCEMENT (SPACING @ 60cm)
TIE WIRES
No. of kg = 17.167 # 16 G.I. wire
E. INTERIOR WALL
Area = 257.68 sq.m
FOR VERTICAL REINFORCEMENT (SPACING @ 60cm) FOR HORIZONTAL REINFORCEMENT (SPACING @ 60cm)
TIE WIRES
No. of kg = 8.246 # 16 G.I. wire
F. BEAM
MAIN REINFORCEMENT FB-1
Number of bars = 6 pcs
Perimeter = 65.625 m
No. of RSB = 67 pcs of 16mm Ø RSB
STIRRUPS
Height = 0.400 m Perimeter = 65.625 m
Diameter of ties = 10.000 mm Net Height = 0.320 m
1st Spacing = 0.050 m, 3 pcs Net Width = 0.320 m
2nd Spacing = 0.100 m, 5 pcs Factored = 0.200 m
3nd Spacing = 0.150 m, 5 pcs Size of ties = 0.840 m
Spacing = 0.200 m, rest
Lenght of ties @rest = 64.225 m
Total pcs = 335.13 pcs
No. of RSB = 46.918 pcs of 10mm Ø RSB
TIE WIRES
No. of kg = 11.382 # 16 G.I. wire
G. SLAB
MAIN REINFORCEMENT
Longitudinal bar = 60.00 pcs
Transverse bar = 50.00 pcs
No. of RSB = 225.333 pcs of 12mm Ø RSB
TIE WIRES
No. of kg = 56.604 # 16 G.I. wire
H. STAIRCASE
MAIN REINFORCEMENT
Length = 15 m
No. of RSB = 2.500 pcs of 12mm Ø RSB
STIRRUPS
Length = 32 m
No. of RSB = 5.333 pcs of 10mm Ø RSB
I. SEPTIC TANK
FOR CHB
Total Area = 20.70 sq.m
FOR VERTICAL REINFORCEMENT (SPACING @ 60cm) FOR HORIZONTAL REINFORCEMENT (SPACING @ 60cm)
FOR SLAB
Longitudinal bar = 28.00 pcs No. of septic tank = 1 pcs
Transverse bar = 12.00 pcs
No. of RSB = 19.667 pcs of 12mm Ø RSB
TIE WIRES
No. of kg = 6.340 # 16 G.I. wire
J. CATCH BASIN
FOR CHB
No. of RSB = 3.500 pcs of 10mm Ø RSB
FOR SLAB
Longitudinal bar = 2.00 pcs No. of catch basin = 6 pcs
Transverse bar = 2.00 pcs
No. of RSB = 4.000 pcs of 10mm Ø RSB
TIE WIRES
No. of kg = 0.170 # 16 G.I. wire
TOTAL
10mm RSB = 1162 pcs
12mm RSB = 273 pcs
16mm RSB = 575 pcs
#16 G.I. wire = 136 kg
IV. FORM WORKS
A. COLUMN
PLYWOOD FORM
Lateral perimeter = 1.6 m
Area = 143.36 sq.m
No. of Plywood = 49.78 pcs
WOOD FRAME
No. of wood = 3104.64 bd.ft. No. of nail = 15.52 kg
use 2" x 2" Good lumber use 3" common nail
B. BEAM
PLYWOOD FORM
Lateral perimeter = 1.15 m
Area = 75.46875 sq.m
No. of Plywood = 26.20 pcs
WOOD FRAME
No. of wood = 1400.63 bd.ft. No. of nail = 7.00 kg
use 2" x 2" Good lumber use 3" common nail
WOOD FRAME
FOR VERTICAL SUPPORT FOR HORIZONTAL SUPPORT
No. of wood = 627.20 bd.ft. No. of wood = 2837.63 bd.ft.
use 2" x 3" Good lumber use 2" x 3" Good lumber
WOOD FRAME
FOR VERTICAL SUPPORT FOR HORIZONTAL SUPPORT
No. of wood = 393.75 bd.ft. No. of wood = 308.44 bd.ft.
use 2" x 3" Good lumber use 2" x 2" Good lumber
No. of nail = 2.30 kg No. of nail = 1.54 kg
use 3 1/2" common nail use 3" common nail
TOTAL
ORDINARY PLYWOOD = 84 pcs (1/2"x4'x8')
2" X 2" = 5296 bd.ft.
2" X 3" = 5970 bd.ft.
1" COMMON NAILS = 1 kg
3" COMMON NAILS = 25 kg
3 1/2" COMMON NAILS = 32 kg
V. MASONRY WORKS
A. WALLS
CONCRETE HOLLOW BLOCKS
W1F1 W2F1
Area = 849.20 sq.m Area = 407.90 sq.m
Area of window = 30.65 sq.m Area of window = 0.36 sq.m
Area of doors = 16.38 sq.m Area of doors = 6.72 sq.m
TOTAL AREA = 802.16 sq.m TOTAL AREA = 400.82 sq.m
No. of CHB = 10027 pcs No. of CHB = 5010 pcs
(15x20x40cm) (10x20x40cm)
MORTAR
15X20X40 cm CHB, Class B Mixture 15X20X40 cm CHB, Class B Mixture
Cement = 816.601 bags Cement = 209.227 bags
Sand = 67.703 cu.m. Sand = 17.436 cu.m.
PLASTER
Area = 1604.33 sq.m Area = 801.64 sq.m
B. SEPTIC TANK
CONCRETE HOLLOW BLOCKS
Area = 20.70 sq.m
No. of CHB = 258.750 pcs (15x20x40cm)
MORTAR PLASTER
10X20X40 cm CHB, Class B Mixture 12mm thick, Class C Mixture
Cement = 10.805 bags Cement = 4.471 bags
Sand = 0.900 cu.m. Sand = 0.497 cu.m.
C. CATCH BASIN
CONCRETE HOLLOW BLOCKS
Area = 2.10 sq.m
No. of CHB = 26.250 pcs (10x20x40cm)
MORTAR PLASTER
10X20X40 cm CHB, Class C Mixture 12mm thick, Class C Mixture
Cement = 0.827 bags Cement = 0.454 bags
Sand = 0.091 cu.m Sand = 0.050 cu.m
TOTAL
4" CHB = 6044 pcs
5" CHB = 12343 pcs
CEMENT = 1667 bags
SAND = 139 cu.m.
VI. CARPENTRY WORKS
A. CEILING
CEILING BOARD CEILING JOIST
Area = 118.88 sq.m Area = 118.88 sq.m
No. of plywood = 41 bd.ft. No. of wood = 639 bd.ft.
use 2" x 2" Good lumber
B. DOOR JUMBS
Length = 20.55 m
No. of wood = 20.550 bd.ft. No. of nail = 0.10 kg
use 2" x 2" Good lumber use 3" common nail
TOTAL
PLYWOOD
=
MARINE (1/4"x4'x8') 46 pcs
2" X 2" GOOD LUMB = 726 bd.ft.
3" COMMON NAILS = 4 kg
VII. STEEL WORKS
A. STAIRCASE RAILINGS
Length of main rail = 8.2 m Length of rail = 8.2 m
No. of RSB = 8.200 No. of RSB = 8.200
of 2" Ø GI pipes of 3/4" Ø GI pipes
TOTAL
2" Ø GI pipes = 10 pcs
3/4" Ø GI pipes = 10 pcs
TOTAL
TILES
16"X16" UNGLAZED = 800 pcs
CEMENT MORTAR = 11 pcs
WHITE CEMENT = 64 pcs
TILE ADHESIVE = 15 pcs
IX. PAINTING WORKS
A. WALL
W1F1 W2F1
Area = 1604.325 sq.m. Area = 801.635 sq.m.
Neutralizer = 40.11 L Neutralizer = 20.04 L
Primer = 40.11 L Primer = 20.04 L
Flat Wall Latex Flat Wall Latex
Masonry Putty 40.11 L Masonry Putty 20.04 L
Finishing = 80.22 L Finishing = 40.08 L
Gloss Latex Gloss Latex
B. WOOD
CEILING
Area = 116.25 sq.m.
Solignum = 2.91 L Glazing putty 2.91 L
C. DOOR JUMBS
Area = 0.0530322 sq.m.
TOTAL
NEUTRALIZER = 61 L
PRIMER (FLAT WALL = 64 L
MASONRY PUTTY = 61 L
GLAZING PUTTY = 3 L
FINISHING (GLOSS L = 127 L
SOLIGNUM = 3 L
ROLLER TRAY = 8 pcs
SAND PAPER = 15 pcs
ROLLER BRUSH = 10 pcs
PAINT BRUSH
1 1/2" = 10 pcs
2" = 10 pcs
4" = 8 pcs
X. PLUMBING WORKS
Gate valve = 2 pcs Water meter = 1 pc
TOTAL
GATE VALVE = 2.000 pcs
WATER METER = 1.000 pcs
WATER CLOSET = 2.000 pcs
LAVATORY = 2.000 pcs
SOAP HOLDER = 2.000 pcs
TOILET PAPER HOLDER = 2.000 pcs
FLOOR DRAIN (DURAMETAL) = 2.000 pcs
FAUCET = 1.000 pcs
4" Ø PVC PIPE = 23.000 pcs
3" Ø PVC PIPE = 20.000 pcs
2" Ø PVC PIPE = 2.000 pcs
1" Ø PVC PIPE = 37.000 pcs
1/2" Ø PVC PIPE = 1.000 pcs
4" Ø TEE = 5.000 pcs
3" Ø ELBOW, 90° = 20.000 pcs
4" Ø ELBOW, 90° = 6.000 pcs
1" Ø ELBOW, 90° = 2.000 pcs
1/2" Ø ELBOW, 90° = 4.000 pcs
4" Ø COUPLING = 8.000 pcs
4" Ø WEE = 4.000 pcs
2"-4" Ø REDUCER, 90° = 4.000 pcs
4" Ø FLOOR DRAIN TRAP = 12.000 pcs
2" Ø P-TRAP = 15.000 pcs
4" Ø CLEAN-OUT W/ PLUG = 15.000 pcs
XI. ELECTRICAL WORKS
Breaker 15 Ampere = 6.00 pcs Breaker 50 Ampere = 4.00 pcs
Breaker 20 Ampere = 0.00 pcs Panel board w/ 30 hole = 1.00 pcs
Breaker 30 Ampere = 10.00 pcs
A. LIGHTING
Compact Flourescent Lamp = 0.00 pcs Plastic lamp receptacle
Flourescent lamp = 35.00 pcs CFL = 0.00 pcs
=
2.00mm THHN cunduit 1.00 box Flourescent lamp = 35.00 pcs
PVC conduit = 50 m One-gang wall Switch = 6.00 pcs
uPVC junction box = 8.00 pcs Two-gang wall Switch = 2.00 pcs
uPVC utility box = 8.00 pcs
B. POWER
3.50mm THHN cunduit = 2.00 box ACU C.O. = 1.00 pcs
8.00mm THHN cunduit = 0.33 box uPVC utility box = 13.00 pcs
Duplex C.O. = 12.00 pcs
TOTAL
BREAKER 15 AMPERE = 6 pcs
BREAKER 20 AMPERE = 0 pcs
BREAKER 30 AMPERE = 10 pcs
BREAKER 50 AMPERE = 4 pcs
PANEL BOARD W/ 30 HOLE = 1 pcs
COMPACT FLOURESCENT LAMP = 0 pcs
FLOURESCENT LAMP = 35 pcs
2.00mm THHN CONDUIT = 1 box
3.50mm THHN CONDUIT = 2 box
8.00mm THHN CONDUIT = 1 box
PVC CONDUIT = 50 m
uPVC JUNCTION BOX = 8 pcs
uPVC UTILITY BOX = 21 pcs
PLASTIC LAMP RECEPTACLE
CFL = 0 pcs
FLOURESCENT LAMP = 35 pcs
ONE-GANG SWITCH = 6 pcs
TWO-GANG SWITCH = 2 pcs
DUPLEX CONVENIENCE OUTLET = 12 pcs
AIRCON CONVENIENCE OUTLET = 1 pcs
XII. MISCELLANEOUS
A. DOORS
Single Door with 1/4" Reflective Glass = 1 set
Automatic Double door with 1/4"
= 0 set
Reflective Glass
Automatic Roll-up Door = 2 set
B. WINDOWS
GENERAL DATA
DATA COMFORT ROOMS
Area of second floor = 118.875 sq.m Area of floor = 0 sq.m
Area of balcony = 0 sq.m Area of wall = 0 sq.m
Area of over-hang = 0 sq.m
Area of T & B = 0 sq.m PAINTING WORKS
Height = 3 m Roller tray = 10 pcs
Longitudinal Length = 12.45 m Sand paper = 15 pcs
Transverse Length = 7.5 m Roller brush = 10 pcs
Paint brush
COLUMN 1 1/2" = 6 pcs
Width = 0.35 m 2" = 8 pcs
Length = 0.35 m 4" = 9 pcs
Number of Column = 16 pcs
PLUMBING WORKS
WALL TOILET AND BATH ACCESSORIES
W1 Water closet = 0 pcs
Perimeter = 99.4 m Lavatory = 0 pcs
Area of windows = 0 sq.m Soap holder = 0 pcs
Area of doors = 1.88 sq.m Toilet paper holder = 0 pcs
W2 Floor drain (durametal) = 0 pcs
Perimeter = 45.9 m
Area of windows = 24.915 sq.m BEAM
Area of doors = 6.865 sq.m Height = 0.4 m
Width = 0.25 m
SLAB Perimeter = 73 m
Thickness = 0.125 m
MISCELLANEOUS
POWER DOORS
3.50mm THHN cunduit = 500.00 m Double Sliding Door = 0 sets
8.00mm THHN cunduit = 100.00 m Single Door Fire Exit = 1 sets
Duplex C.O. = 10.00 pcs Single Door = 0 sets
ACU C.O. = 3.00 pcs
uPVC utility box = 13.00 pcs WINDOWS
Seamless Fixed Window with
1/4" thk reflective glass
1.00 m x 2.7 m = 3 sets
0.55 m x 2.7 m = 2 sets
1.25 m x 2.7 m = 1 set
1.35 m x 2.7 m = 2 set
0.60 m x 2.65 m = 2 set
SEWERAGE SANITARY
Length Length
Main line = 54.8 m Main line = 15 m
Other lines = 9.8 m Other line = 6 m
Downspout Faucet = 4 pcs
Length = 3 m 1" Ø Elbow, 90o = 8 pcs
No. of downspout = 6 pcs 1/2" Ø Elbow, 90o = 10 pcs
4" Ø Tee = 5 pcs
3" Ø Elbow, 90o = 20 pcs ELECTRICAL WORKS
4" Ø Elbow, 90o = 6 pcs LIGHTING
4" Ø Coupling = 8 pcs 2.00mm THHN cunduit = 540.00 m
4" Ø Wee = 4 pcs Compact Flourescent Lamp = 3.00 pcs
2"-4" Ø Reducer Elbow, 90o =4 pcs Flourescent lamp = 15.00 pcs
4" Ø Floor Drain Tra = 12 pcs Pinlight = 0.00 pcs
2" Ø P-trap = 15 pcs Chandelier = 0.00 pc
4" Ø Clean-out w/ P = 15 pcs uPVC junction box = 3.00 pcs
uPVC utility box = 3.00 pcs
One-gang wall Switc = 0.00 pcs
Two-gang wall Switch = 0.00 pcs
Three-gang wall Switch = 1.00 pcs
MULTIPLIER
I. CONCRETE WORKS BEAM
Factor of Safety = 20 % No. of bars = 10 pcs
Concrete cover = 0.04 m
Using 40kg Cement, Class A Mixture Spacing
Cement = 9 bags 3 pcs = 0.05 m
Sand = 0.5 cu.m. 5 pcs = 0.1 m
Gravel = 1 cu.m. 5 pcs = 0.15 m
rest = 0.2 m
WALL BEAM
Vertical (3 layers) = 2.13 2"X2" wood frame = 25.06
Horizontal(spaced 60cm) = 2.15 2"X3" wood frame = 37.6
Ties (spaced 60cm) = 0.032
STAGING AND SCAFFOLDING
BEAM COLUMN
2"X3" Vertical suppo = 6.00 bd.ft 2"X3" Vertical suppo = 7.00 bd.ft
2"X2" Horizontal su = 4.70 bd.ft 2"X3" Horizontal sup = 31.67 bd.ft
2"X3" Diagonal supp = 17.50 bd.ft
DOOR JUMBS
Length = 23.8 m
SLAB VI. STEEL WORKS
2"X2" support = 6.10 bd.ft Factor of Safety = 10 %
Commercial size of pipe = 6 m
IV. MASONRY WORKS
Factor of Safety = 20 % VII. TILE WORKS
No. of CHB per sq.m = 12.5 pcs Factor of Safety = 10 %
W1F1 Cement mortar = 0.086 bg/sq.m
Size of CHB White cement = 0.50 kg/sq.m
Height = 0.2 m Tile adhesive = 0.110 bg/sq.m
Width = 0.15 m
Length = 0.4 m FLOOR
Size of CHB 16"X16" Unglazed/p = 0.16 sq.m
Height = 0.2 m
Width = 0.1 m KITCHEN
Length = 0.4 m 8"X8" Glazed/pcs = 0.00 sq.m
MORTAR BATHROOM
15X20X40 cm CHB, Class B Mixture 8"X8" Glazed/pcs = 0.16 sq.m
Cement = 1.018 bags 8"X8" Unglazed/pcs = 0.16 sq.m
Sand = 0.0844 m³
VIII. PAINTING WORKS
10X20X40 cm CHB, Class B Mixture WALL
Cement = 0.522 bags Concrete Neutralizer = 30 sq.m.
Sand = 0.0435 m³ Primer = 30 sq.m.
Masonry Putty = 30 sq.m.
10X20X40 cm CHB, Class C Mixture Finishing = 30 sq.m.
Cement = 0.394 bags
Sand = 0.0435 m³ CEILING
Solignum = 30 sq.m.
PLASTER Primer = 30 sq.m.
12mm thick, Class B Mixture Glazing Putty = 30 sq.m.
Cement = 0.144 bags Finishing = 30 sq.m.
Sand = 0.012 m³
IX. PLUMBING WORKS
12mm thick, Class C Mixture Standard length of pipe = 3 m
Cement = 0.108 bags Teflon Tape (1/2) = 20 pcs
Sand = 0.012 m³
B. BEAM
BEAM 1
Height = 0.400 m Length = 73.350 m
Width = 0.250 m VOLUME = 7.335 cu.m.
TOTAL VOLUME = 7.335 cu.m.
C. SLAB
Height = 0.125 m
Area of ground floor = 118.875 m
Area of carport = 0.000 m
TOTAL VOLUME = 14.859 cu.m.
TOTAL
CEMENT = 304 bags
SAND = 17 cu.m.
GRAVEL = 34 cu.m.
II. REBAR WORKS
A. COLUMN
MAIN REINFORCEMENT
Commercial length = 6.000 m Number of Steel = 8.000 pcs
Height = 3.000 m Number of footing = 16 pcs
LENGTH = 384.000 m
No. of RSB = 64.000 pcs of 16mm Ø RSB
LATERAL TIES
Total height = 3.000 m Net Length = 0.270 m
Diameter of ties = 10.000 mm Net Width = 0.270 m
1st Spacing = 0.050 m, 3 pcs Factored = 0.200 m
2nd Spacing = 0.100 m, 5 pcs Size of Lateral ties = 1.280 m
3nd Spacing = 0.150 m, 5 pcs
Spacing = 0.200 m, rest
Length ties @rest = 1.600 m
Pcs of ties in 1 colu = 22.00 pcs
No. of RSB = 75.093 pcs of 10mm Ø RSB
TIE WIRES
No. of kg = 0.996 # 16 G.I. wire
B. EXTERIOR WALL
Area = 14.91 sq.m
FOR VERTICAL REINFORCEMENT (SPACING @ 60cm) FOR HORIZONTAL REINFORCEMENT (SPACING @ 60cm)
TIE WIRES
No. of kg = 0.477 # 16 G.I. wire
C. INTERIOR WALL
Area = 4.59 sq.m
FOR VERTICAL REINFORCEMENT (SPACING @ 60cm) FOR HORIZONTAL REINFORCEMENT (SPACING @ 60cm)
TIE WIRES
No. of kg = 0.147 # 16 G.I. wire
D. BEAM
MAIN REINFORCEMENT
Number of bars = 10.000 pcs
Perimeter = 73.350 m
No. of RSB = 123 pcs of 16mm Ø RSB
STIRRUPS
Height = 0.400 m Perimeter = 73.350 m
Diameter of ties = 10.000 mm Net Height = 0.320 m
1st Spacing = 0.050 m, 3 pcs Net Width = 0.320 m
2nd Spacing = 0.100 m, 5 pcs Factored = 0.200 m
3nd Spacing = 0.150 m, 5 pcs Size of ties = 0.840 m
Spacing = 0.200 m, rest
Lenght of ties @rest = 71.950 m
Total pcs = 373.75 pcs
No. of RSB = 52.325 pcs of 10mm Ø RSB
TIE WIRES
No. of kg = 21.156 # 16 G.I. wire
E. SLAB
ONE-WAY SLAB
TERRACE T&B
Area = 0.00 sq.m Area = 0.00 sq.m
TWO-WAY SLAB
OFFICE ROOM OTHER ROOM
Area = 118.88 sq.m Area = 0.00 sq.m
TOTAL
10mm RSB = 156 pcs
12mm RSB = 96 pcs
16mm RSB = 206 pcs
#16 G.I. wire = 103 kg
III. FORM WORKS
A. COLUMN
PLYWOOD FORM
Lateral perimeter = 1.6 m
Area = 66.56 sq.m
No. of Plywood = 23.11 pcs
WOOD FRAME
No. of wood = 685.71 bd.ft. No. of nail = 3.43 kg
use 2" x 2" Good lumber use 3" common nail
B. BEAM
PLYWOOD FORM
Lateral perimeter = 1.15 m
Area = 84.3525 sq.m
No. of Plywood = 29.29 pcs
WOOD FRAME
No. of wood = 733.98 bd.ft. No. of nail = 3.67 kg
use 2" x 2" Good lumber use 3" common nail
WOOD FRAME
FOR VERTICAL SUPPORT FOR HORIZONTAL SUPPORT
No. of wood = 291.20 bd.ft. No. of wood = 1317.47 bd.ft.
use 2" x 3" Good lumber use 2" x 3" Good lumber
BEAM
Length = 73.35 m
WOOD FRAME
FOR VERTICAL SUPPORT FOR HORIZONTAL SUPPORT
No. of wood = 440.10 bd.ft. No. of wood = 344.75 bd.ft.
use 2" x 3" Good lumber use 2" x 2" Good lumber
WOOD FRAME
FOR VERTICAL SUPPORT No. of nail = 3.63 kg
No. of wood = 725.14 bd.ft. use 3" common nail
use 2" x 2" Good lumber
TOTAL
ORDINARY PLYWOOD = 58 pcs (1/2"x4'x8')
2" X 2" = 2739 bd.ft.
2" X 3" = 3055 bd.ft.
1" COMMON NAILS = 1 kg
3" COMMON NAILS = 13 kg
3 1/2" COMMON NAILS = 17 kg
IV. MASONRY WORKS
A. WALLS
CONCRETE HOLLOW BLOCKS
W1F1 W2F1
Area = 258.44 sq.m Area = 119.34 sq.m
Area of window = 0.00 sq.m Area of window = 24.92 sq.m
Area of doors = 1.88 sq.m Area of doors = 6.87 sq.m
TOTAL AREA = 256.56 sq.m TOTAL AREA = 87.56 sq.m
No. of CHB = 3207 pcs No. of CHB = 1095 pcs
(15x20x40cm) (10x20x40cm)
MORTAR
15X20X40 cm CHB, Class B Mixture 15X20X40 cm CHB, Class B Mixture
Cement = 261.178 bags Cement = 45.706 bags
Sand = 21.654 cu.m. Sand = 3.809 cu.m.
PLASTER
Area = 513.12 sq.m Area = 175.12 sq.m
TOTAL
4" CHB = 1314 pcs
5" CHB = 3849 pcs
CEMENT = 488 bags
SAND = 41 cu.m.
V. CARPENTRY WORKS
A. CEILING
CEILING BOARD CEILING JOIST
Area = 195.38 sq.m Area = 195.38 sq.m
B. DOOR JUMBS
Length = 23.8 m
TOTAL
PLYWOOD
MARINE (1/4"x4'x8') = 75 pcs
2" X 2" GOOD LUMBER = 1181 bd.ft.
3" COMMON NAILS = 1 kg
VI. TILE WORKS
A. FLOOR
Area = 118.875 sq.m
B. COMFORT ROOM
Area of floor = 0 sq.m
Area of wall = 0 sq.m
Total area = 0 sq.m
TOTAL
TILES
8"X8" GLAZED = 0 pcs
8"X8" UNGLAZED = 0 pcs
16"X16" UNGLAZED = 818 pcs
CEMENT MORTAR = 12 pcs
WHITE CEMENT = 66 pcs
TILE ADHESIVE = 15 pcs
VII. PAINTING WORKS
A. WALL
W1F1 W2F1
Area = 513.12 sq.m. Area = 513.12 sq.m.
B. WOOD
CEILING
Area = 195.38 sq.m.
C. DOOR JUMBS
Area = 0.0614192 sq.m.
TOTAL
NEUTRALIZER = 35 L
PRIMER (FLAT WALL LATEX) = 41 L
MASONRY PUTTY = 35 L
GLAZING PUTTY = 7 L
FINISHING (GLOSS LATEX) = 82 L
SOLIGNUM = 7 L
ROLLER TRAY = 10 pcs
SAND PAPER = 15 pcs
ROLLER BRUSH = 10 pcs
PAINT BRUSH
1 1/2" = 6 pcs
2" = 8 pcs
4" = 9.000 pcs
VIII. PLUMBING WORKS
A. TOILET AND BATH ACCESSORIES
Water closet = 0.00 pcs Toilet paper holder = 0.00 pcs
Lavatory = 0.00 pcs Floor drain (durametal) = 0.00 pcs
Soap holder = 0.00 pcs Shower head = 0.00 pcs
TOTAL
WATER CLOSET = 0 pcs
LAVATORY = 0 pcs
SOAP HOLDER = 0 pcs
TOILET PAPER HOLDER = 0 pcs
FLOOR DRAIN (DURAMETAL) = 0 pcs
FAUCET = 4 pcs
4" Ø PVC PIPE = 19 pcs
3" Ø PVC PIPE = 6 pcs
2" Ø PVC PIPE = 4 pcs
1" Ø PVC PIPE = 5 pcs
1/2" Ø PVC PIPE = 2 pcs
4" Ø TEE = 5 pcs
3" Ø ELBOW, 90° = 20 pcs
4" Ø ELBOW, 90° = 6 pcs
1" Ø ELBOW, 90° = 8 pcs
1/2" Ø ELBOW, 90° = 10 pcs
4" Ø COUPLING = 8 pcs
4" Ø WEE = 4 pcs
2"-4" Ø REDUCER, 90° = 4 pcs
4" Ø FLOOR DRAIN TRAP = 12 pcs
2" Ø P-TRAP = 15 pcs
4" Ø CLEAN-OUT W/ PLUG = 15 pcs
IX. ELECTRICAL WORKS
A. LIGHTING
Compact Flourescent Lamp = 3.00 pcs Plastic lamp receptacle
Flourescent lamp = 15.00 pcs CFL = 3.00 pcs
Pinlight = 0.00 pcs Flourescent lamp = 15.00 pcs
2.00mm THHN cunduit = 3.60 box Pinlight = 0.00 pcs
PVC conduit = 180 m One-gang wall Switch = 0.00 pcs
uPVC junction box = 3.00 pcs Two-gang wall Switch = 0.00 pcs
uPVC utility box = 3.00 pcs Three-gang wall Switch = 1.00 pcs
B. POWER
3.50mm THHN cunduit = 3.33 box ACU C.O. = 3.00 pcs
8.00mm THHN cunduit = 0.67 box uPVC utility box = 13.00 pcs
Duplex C.O. = 10.00 pcs
TOTAL
COMPACT FLOURESCENT LAMP = 3 pcs
FLOURESCENT LAMP = 15 pcs
PINLIGHT = 0 pcs
CHANDELIER = 0 pc
2.00mm THHN CONDUIT = 4 box
3.50mm THHN CONDUIT = 4 box
8.00mm THHN CONDUIT = 1 box
PVC CONDUIT = 180 m
uPVC JUNCTION BOX = 3 pcs
uPVC UTILITY BOX = 16 pcs
PLASTIC LAMP RECEPTACLE
CFL = 3 pcs
FLOURESCENT LAMP = 15 pcs
PINLIGHT = 0 pcs
ONE-GANG SWITCH = 0 pcs
TWO-GANG SWITCH = 0 pcs
DUPLEX CONVENIENCE OUTLET = 10 pcs
AIRCON CONVENIENCE OUTLET = 3 pcs
X. MISCELLANEOUS
A. DOORS
B. WINDOWS
GENERAL DATA
DATA ROOF SLAB
Area of roof slab = 118.875 sq.m Thickness = 0.1 sq.m
Area of balcony = 0 sq.m
Area of over-hang = 0 sq.m SLAB
Area of T & B = 0 sq.m 2"X2" support = 6.10 bd.ft
Height of Parapet Wall = 1 m
Longitudinal Length = 20-4.15 m
Transverse Length = 7.5 m
MULTIPLIER
I. CONCRETE WORKS BEAM
Factor of Safety = 20 % No. of bars = 9 pcs
Concrete cover = 0.04 m
Using 40kg Cement, Class A Mixture Spacing
Cement = 9 bags 3 pcs = 0.05 m
Sand = 0.5 cu.m. 5 pcs = 0.1 m
Gravel = 1 cu.m. 5 pcs = 0.15 m
rest = 0.2 m
TOTAL
CEMENT = 129.000 bags
SAND = 8.000 cu.m.
GRAVEL = 15.000 cu.m.
II. REBAR WORKS
A. SLAB
TWO-WAY SLAB
ROOF
Area = 118.88 sq.m
MAIN REINFORCEMENT
No. of bar = 86.56 pcs
pcs of 12mm Ø RSB
TIE WIRES
No. of kg = 70.37
# 16 G.I. wire
TOTAL
12mm RSB = 96 pcs
#16 G.I. wire = 78 kg
III. FORM WORKS
A. STAGING AND SCAFFOLDING
SLAB
Area = 118.875 sq.m.
WOOD FRAME
FOR VERTICAL SUPPORT No. of nail = 3.63 kg
No. of wood = 725.14 bd.ft. use 3" common nail
use 2" x 2" Good lumber
TOTAL
2" X 2" GOOD LUMBER = 798.000 bd.ft.
3" COMMON NAILS = 4.000 kg
COMPUTATION OF LABOR
(1 working day = 8 hours)
Manual Clearing
Manhour Capability = 0.03 hr/m2
Total Area = 200 m2
Layout & Staking =
Manhour Capability = 0.20 hr/m2
Total Floor Area = 1080.01 m2
No. of Persons = 8
No. of Days = 3.47 day(s) say 4 day(s)
No. of Persons = 6
No. of Days = 1.76 days say 2 day(s)
Manhour Capability =
Pipes = 1.00 hr/pc 6 pcs
Clean Outs = 2.00 hr/pc 6 pcs
No. of Persons = 5
No. of Days = 0.45 days say 1 day(s)
No. of Persons = 5
No. of Days = 4.19 days say 5 day(s)
Equipment Capability
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8 m3/day
Pouring = 5.00 hr/m3
Total Volume = 13.54 m3
No. of Persons = 9
No. of Days = 2.93 days say 3 day(s)
No. of Persons = 10
No. of Days = 4.13 days say 5 day(s)
No. of Persons = 7
No. of Days = 5.4 days say 6 day(s)
Activity K: INSTALLATION OF FORMS, SCAFFOLDING &
STAGING FOR COLUMNS AT 1ST FLOOR
Manhour Capability = 0.85 m2/hr
Total Area of Columns = 123.1 m2
No. of Persons = 8
No. of Days = 4.53 days say 5 day(s)
Equipment
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8 m3/day
Pouring = 5.00 hr/m3
Total Volume = 15.35 m3
No. of Persons = 15
No. of Days = 2.90 days say 3 day(s)
Fabrication of Forms
Manhour Capability = 1.423 MH/m²
Total Area = 0.7 m2
No. of Persons = 2
No. of Days = 0.1 days say 1 day(s)
Installation of Rebars
Manhour Capability = 10 kg/hr
Total No. of KG = 386.40 kg
No. of Persons = 5
No. of Days = 1.93 days say 2 day(s)
Concreting
Equipment
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8 m3/day
Pouring = 5.00 hr/m3
Total Volume = 1.38 m3
No. of Persons = 4
No. of Days = 0.42 days say 1 day(s)
Activity N: FABRICATION OF REBARS FOR BEAM
Equipment Capability
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8 m3/day
Pouring = 5.00 hr/m3
Total Volume = 6.35 m3
No. of Persons = 6
No. of Days = 1.60 days say 2 day(s)
Equipment
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8 m3/day
Pouring = 5.00 hr/m3
Total Volume = 15.75 m3
No. of Persons = 12
No. of Days = 3.14 days say 4 day(s)
No. of Persons = 10
No. of Days = 8.63 days say 9 day(s)
Activity X: INSTALLATION OF FABRICATED DOOR JAMB AT FIRST FLOOR
No. of Persons = 4
No. of Days = 5.43 days say 6 day(s)
Manhour Capability
Lavatory = 8 hr/set 2 sets
Water closet = 8 hr/set 2 sets
Kitchen sink = 14 hr/set - sets
Kitchen faucet = 2 hr/set 2 sets
Gate Valve = 8 hr/set 2 sets
Faucet = 2 hr/set 2 sets
Floor Drain = 2 hr/set 2 sets
No. of Persons = 4
No. of Days = 1.88 days say 2 day(s)
COMPUTATION OF LABOR
(1 working day = 8 hours)
No. of Persons = 8
No. of Days = 0.96 days say 1 day(s)
Activity B': FABRICATION OF REBARS FOR BEAM & SLAB AT 2ND FLOOR
No. of Persons = 10
No. of Days = 1.1 days say 2 day(s)
Activity G': LAYING OF CHB WALL AT 2ND FLOOR
No. of Persons = 8
No. of Days = 3.07 days say 4 day(s)
Equipment
1 Bagger conc. mixer = 8.00 m3/day x 85% = 6.8 m3/day
Pouring = 5.00 hr/m3
Total Volume = 9.36 m3
No. of Persons = 4
No. of Days = 1.60 days say 2 day(s)
No. of Persons = 10
No. of Days = 7.62 days say 8 day(s)
No. of Persons = 6
No. of Days = 7.25 days say 8 day(s)
No. of Persons = 10
No. of Days = 3.69 days say 4 day(s)
Manhour Capability
Doors = 2 sets/day 8 sets
Windows = 1 set/hr 12 sets
No. of Persons = 4
No. of Days = 1.38 days say 2 day(s)
No. of Persons = 6
No. of Days = 9.63 days say 10 day(s)
Activity Z': PAINTING WORKS
No. of Persons = 10
No. of Days = 3.54 days say 4 day(s)
Duration
4
9
2
4
1
1
5
3
5
6
5
3
6
8
3
4
4
2
12
17
4
3
9
1
15
2
DULE OF ACTIVITIES(SECOND FLOOR IN PROGRESS)
Duration
1
6
5
3
1
2
4
1
2
6
4
3
2
7
3
1
7
8
1
6
8
4
2
3
10
4
2
NETWORK DIAGRAM (INITIAL)-Part 1
13 32
13 38
3 2 10 3
3
9 18 29 45
18 29 45
1 4 2 1 6 3 7 5 9 8 11 4 12 4 13
4 15 37 41
0 4 15 37 41
0 4 5 6 5
4 1 5 8 6
8 9 24
9 10 24
ES (Early Start)
LF (Latest Finish)
Duration
2
NETWORK DIAGRAM (INITIAL)-Part 2
76 81
76 87
17 4 20 1
17
47 1 93 99 2
47 88 93 99
14 12 16 19 80 88 23 5 24 27 4 28
59 80 103
59 103
3 15 2 6 3 2
15 9 18 21 25 1 26
50 59 82 96 97
56 65 82 96 97
NETWORK DIAGRAM (INITIAL)-Part 3
4 2
135
118 129 135
1 31 3 32 118 129 36 6 37 8 39 4 40 4 41
115 143 147 153
115 143 149 153
7 1 2
7 38 3
34 3 35 136
125 128 141
125 128
2 42
155
DATA SHEET
Duration in DAYS
REMARK
DAY CRITICAL PATH
* 1 - 4 4
* 5 - 13 9
* 14 - 15 2
16 - 18 3
19 - 24 6
25 - 29 5
30 - 37 8
* 38 - 41 4
42 - 45 4
* 46 - 47 2
* 48 - 59 12
60 - 76 17
77 - 80 4
* 81 - 82 2
83 - 88 6
* 89 - 93 5
* 94 - 96 3
* 97 - 97 1
* 98 - 99 2
* 100 - 103 4
* 104 - 105 2
106 - 111 6
112 - 115 4
116 - 118 3
119 - 125 7
* 126 - 128 3
129 - 129 1
* 130 - 135 6
* 136 - 143 8
* 144 - 153 10
* 154 - 155 2
*
*
*
*
*
*
*
*
*
*
*
*
* 2
GANTT CHART-Part 1 GANTT CHA
DAY
Activity Job Description
0 2 4 6 8 10 12 14 16 18 20
A Site Clearing and & Job Layout
B Excavation (Footing, Column & Septic Tank)
C Construction of job offices & storage shed
D Fabrication of Rebars for CF & WF
E Installation of rebars for C, CF, WF
F Roughing in Plumbing
G Roughing in Electrical Conduit
H Concreting of CF and WF
I Laying of CHB Wall
J Fabrication of forms for colums and beams
K Installation of Forms, scaffolding & staging for columns
L Concreting of Columns
M Construction of Staircase
N Fabrication of rebars for beams and slab
O Removal of forms and staging for columns
P Installation of Forms, scaffolding & staging for Beams
Q Installation of RC beam rebars
R Concreting of RC beams
S Backfilling of footing and GF slab
T Spreading, Tamping & Grading
U Concreting of GF Slab
V Stripping of forms at beams
W Plastering of CHB Walls
X Installation of Fabricated Door Jamb
Y Construction Septic Tank
Z Installation of Sanitary Fixtures
A' Installation of scaffolding and forms for slab
B' Fabrication of rebars for beams and slab
C' Installation of forms, scaffolding & staging for 2nd floor slab
D' Installation of rebars at 2nd floor
E' Concreting of second floor slab
F' Installation of fabricated rebars for column
G' Laying of CHB Wall
H' Installation of forms, scaffolding and staging for column
I' Concreting of Columns
J' Installation of forms, scaffolding and staging for beams
K' Installation of RC beam rebars
L' Concreting RC beams
M' Removal of forms at columns &beams
N' Installation of forms, scaffolding & staging for roof slab
O' Installation of rebars at roof deck
P' Concreting of roof deck
Q' Plastering of CHB walls
R' Plastering of beams, columns and moldings
S' Installation of fabricated Door jamb
T' Installation of ceiling frames
U' Installation of Electrical fixtures
V' Installation of ceiling board
W' Installation of fabricated doors and windows
X' Installation of Stainless railings
Y' Installation of Tiles
Z' Painting works
A'' Clearing of site for final inspection & transfer to the owner
GANTT CHART-Part 2
DAY
20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56
GANTT CHART-Part 3
DAY
56 58 60 62 64 66 68 70 72 74 76 78 80 82 84 86 88 90 92 94 96 98
GANTT CHART-Part 4
DAY
98 100 102 104 106 108 110 112 114 116 118 120 122 124 126 128 130 132 134 136
138 140 142 144 146 148 150 152 154 156 158 160
MANPOWER LEVELING
EVENT
Day 1-2
A = 8 men for 4 days
Total …… 8 x 2 days ……….. 16 man days
Day 3-5
B = 15 men for 9 days
D = 10 men for 4 days
Total …… 25 x 3 days ……….. 75 man days
Day 6
B = 15 men for 9 days
E = 11 men for 1 days
Total …… 26 x 1 days ……….. 26 man days
Day 7-9
F = 5 men for 4 days
B = 15 men for 9 days
E = 11 men for 1 days
Total …… 31 x 3 days ……….. 93 man days
Day 10
F = 5 men for 4 days
C = 6 men for 2 days
G = 5 men for 5 days
Total …… 16 x 1 days ……….. 16 man days
Day 11
C = 6 men for 2 days
G = 5 men for 5 days
Total …… 11 x 2 days ……….. 22 man days
Day 12-14
H = 9 men for 3 days
Total …… 9 x 2 days ……….. 18 man days
Day 15-19
I = 10 men for 5 days
J = 7 men for 6 days
Total …… 17 x 4 days ……….. 68 man days
Day 20-24
K = 8 men for 5 days
Total …… 8 x 5 days ……….. 40 man days
Day 25-27
L = 15 men for 3 days
N = 10 men for 8 days
Total …… 25 x 3 days ……….. 75 man days
Day 28-30
N = 10 men for 8 days
O = 5 men for 3 days
Total …… 15 x 3 days ……….. 45 man days
Day 31-34
M = 16 men for 6 days
P = 9 men for 4 days
Total …… 25 x 4 days ……….. 100 man days
Day 35-36
M = 16 men for 6 days
Q = 10 men for 4 days
Total …… 26 x 2 days ……….. 52 man days
Day 37
Q = 10 men for 4 days
Total …… 10 x 1 days ……….. 10 man days
Day 38-39
R = 6 men for 2 days
Total …… 6 x 2 days ……….. 12 man days
Day 40
S = 10 men for 12 days
V = 4 men for 2 days
Total …… 14 x 1 days ……….. 14 man days
Day 41-42
V = 4 men for 2 days
T = 4 men for 17 days
Total …… 8 x 2 days ……….. 16 man days
Day 43-45
W = 10 men for 9 days
U = 12 men for 4 days
Total …… 22 x 3 days ……….. 66 man days
Day 46-48
W = 10 men for 9 days
Total …… 10 x 3 days ……….. 30 man days
Day 49-63
Y = 14 men for 15 days
Total …… 14 x 15 days ……….. 210 man days
Day 64
X = 2 men for 1 days
Z = 4 men for 2 days
Total …… 6 x 1 days ……….. 6 man days
Day 65
Z = 4 men for 2 days
A' = 8 men for 1 days
Total …… 12 x 1 days ……….. 12 man days
Day 66
Z = 4 men for 2 days
Total …… 4 x 1 days ……….. 4 man days
Day 67-70
B' = 10 men for 6 days
Total …… 10 x 4 days ……….. 40 man days
Dayy 71-75
C' = 10 men for 5 days
Total …… 10 x 5 days ……….. 50 man days
Day 76-77
D' = 12 men for 3 days
Total …… 12 x 2 days ……….. 24 man days
Day 78-83
E' = 28 men for 1 days
Total …… 28 x 6 days ……….. 168 man days
Day 84
F' = 10 men for 2 days
Total …… 10 x 1 days ……….. 10 man days
Day 85-87
G' = 8 men for 4 days
Total …… 8 x 3 days ……….. 24 man days
Day 88
H' = 8 men for 1 days
I' = 4 men for 2 days
Total …… 12 x 1 days ……….. 12 man days
Day 89-90
I' = 4 men for 2 days
Total …… 4 x 2 days ……….. 8 man days
Day 91-93
J' = 8 men for 6 days
Total …… 8 x 3 days ……….. 24 man days
Day 94-96
K' = 10 men for 4 days
Total …… 10 x 3 days ……….. 30 man days
Day 97-98
L' = 5 men for 3 days
Total …… 5 x 2 days ……….. 10 man days
Day 99
M' = 10 men for 2 days
N' = 10 men for 7 days
Total …… 20 x 1 days ……….. 20 man days
Day 100-102
N' = 10 men for 7 days
R' = 10 men for 8 days
Total …… 20 x 3 days ……….. 60 man days
Day 103-104
O' = 10 men for 3 days
R' = 10 men for 8 days
Total …… 20 x 2 days ……….. 40 man days
Day 105-110
P' = 40 men for 1 days
Total …… 40 x 6 days ……….. 240 man days
Day 111
S' = 2 men for 1 days
T' = 5 men for 6 days
Total …… 7 x 1 days ……….. 7 man days
Day 112-114
T' = 5 men for 6 days
Q' = 8 men for 7 days
Total …… 13 x 3 days ……….. 39 man days
Day 115
T' = 5 men for 6 days
W' = 4 men for 2 days
Total …… 9 x 1 days ……….. 9 man days
Day 116
U' = 6 men for 8 days
W' = 4 men for 2 days
Total …… 10 x 1 days ……….. 10 man days
Day 117-118
X' = 6 men for 3 days
U' = 6 men for 8 days
Total …… 12 x 2 days ……….. 24 man days
Day 119-122
V' = 10 men for 4 days
Y' = 6 men for 10 days
Total …… 16 x 3 days ……….. 48 man days
Day 122-124
V' = 10 men for 4 days
Y' = 6 men for 10 days
Total …… 16 x 3 days ……….. 48 man days
Day 125
Z' = 10 men for 4 days
Total …… 10 x 1 days ……….. 10 man days
Day 126-127
A'' = 10 men for 2 days
Total …… 10 x 2 days ……….. 20 man days
13 32
13 C 38 O
3 2 10 3
B 3 L
9 18 29 45
A F 18 I 29 P 45
1 4 2 1 6 3 7 5 9 8 11 4 12 4 13
4 15 H N 37 41 Q
0 4 15 37 41
0 4 5 J 6 5
D G K
4 1 5 8 6
8 E 9 24 M
9 10 24
ES (Early Start)
LF (Latest Finish)
Duration
Critical Path
R
2
NETWORK DIAGRAM (FINAL)-Part 2
76 81
76 U 87
17 4 20 1
T 17 X A' I'
47 1 93 99 2
47 S 88 93 99
14 12 16 19 80 88 23 5 24 27 4 28
59 80 C' G' 103
59 103
V 3 15 2 6 D' 3 2 F'
Y Z B'
15 9 18 21 25 1 26
50 W 59 82 96 E' 97
56 65 82 96 97
NETWORK DIAGRAM (FINAL)-Part 3
7 38 3
34 3 35 Q' 136 X'
125 O' 128 141
125 128
2 42
A'' 155
TIME SCALED DIAGRAM (MANPOWER LEVELING)
DAY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
5 5
F-1
10 10 10 11 5 5 5 5 5
D-4 E-1 G-5
8 8 15 15 15 15 15 15 15 6 6 9 9 9 7 7 7 7 7 8 8 8 8 8 10 10 10
A-4 B-9 C-2 H-3 J-6 K-5 N-8
10
I-5
15 15 15
L-3
8 8 25 25 25 26 20 20 25 16 11 9 9 9 17 7 7 7 7 8 8 8 8 8 25 25 25
8 16 41 66 91 117 137 157 182 198 209 218 227 236 253 260 267 274 281 289 297 305 313 321 346 371 396
0.411 0.822 2.107 3.392 4.676 6.012 7.04 8.068 9.353 10.17 10.74 11.2 11.66 12.13 13 13.36 13.72 14.08 14.44 14.85 15.26 15.67 16.08 16.5 17.78 19.06 20.35
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
PARTIALLY LEVELED MANPOWER
45
40
35
M 30
A 25 25 25
N 25
22
20
P 20
O 17
16
W 15 15 15
14
E
R 10 10 10 10 10 10
10 8 8 8
6
5
DAY
DAY
28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
10 10 10 9 9 9 9 10 10 10 6 6 4 4 4 10 10 10 10 10 10 14 14 14 14 14 14
P-4 Q-4 R-2 V-3 W-9 Y-15
5 5 5
O-3
16 16 16 16 16 16
M-6
10 4 4 12 12 12
S-12 T-17 U-4
15 15 15 25 25 25 25 26 26 10 6 6 14 8 8 22 22 22 10 10 10 14 14 14 14 14 14
411 426 441 466 491 516 541 567 593 603 609 615 629 637 645 667 689 711 721 731 741 755 769 783 797 811 825
21.12 21.89 22.66 23.95 25.23 26.52 27.8 29.14 30.47 30.99 31.29 31.6 32.32 32.73 33.14 34.28 35.41 36.54 37.05 37.56 38.08 38.8 39.52 40.24 40.96 41.68 42.39
28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
DAY
55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
14 14 14 14 14 14 14 14 14 4 4 4 10 10 10 10 10 10 10 10 10 12 12 28 28 28 28
Z-2 B'-6 C'-5 D'-3 E'-1
2 8
X-1 A'-1
14 14 14 14 14 14 14 14 14 6 12 4 10 10 10 10 10 10 10 10 10 12 12 28 28 28 28
839 853 867 881 895 909 923 937 951 957 969 973 983 993 1003 1013 1023 1033 1043 1053 1063 1075 1087 1115 1143 1171 1199
43.11 43.83 44.55 45.27 45.99 46.71 47.43 48.15 48.87 49.18 49.79 50 50.51 51.03 51.54 52.06 52.57 53.08 53.6 54.11 54.62 55.24 55.86 57.3 58.74 60.17 61.61
55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
DAY
82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108
10 10 10 10 10 10
M'-2 R'-8
8
H'-1
28 28 10 8 8 8 4 4 4 8 8 8 10 10 10 5 5 10 10 10 10 10 10 40 40 40 40
F'-2 G'-4 I'-2 J'-6 K'-4 L'-3 N'-7 O'-3 P'-1
28 28 10 8 8 8 12 4 4 8 8 8 10 10 10 5 5 20 20 20 20 20 20 40 40 40 40
1227 1255 1265 1273 1281 1289 1301 1305 1309 1317 1325 1333 1343 1353 1363 1368 1373 1393 1413 1433 1453 1473 1493 1533 1573 1613 1653
63.05 64.49 65.01 65.42 65.83 66.24 66.86 67.06 67.27 67.68 68.09 68.5 69.01 69.53 70.04 70.3 70.55 71.58 72.61 73.64 74.67 75.69 76.72 78.78 80.83 82.89 84.94
82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108
DAY
109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135
6 6 6 0 0 0
2 Y'-10 Y'-
S'-1
40 40 5 5 5 5 5 6 6 6 10 10 10 10 10 10 10 10 10 10 10 0 0 0 0 0 0
T'-6 U'-8 V'-4 Z'-4 A''-2 V'- Z'-
8 8 8 8 4 4
Q'-7 W'-2
10 10 0 0
X'-3 X'-
40 40 15 13 13 13 9 10 16 16 16 16 16 10 10 10 10 10 10 10 10 0 0 0 0 0 0
1693 1733 1748 1761 1774 1787 1796 1806 1822 1838 1854 1870 1886 1896 1906 1916 1926 1936 1946 1956 1966 1966 1966 1966 1966 1966 1966
87 89.05 89.83 90.49 91.16 91.83 92.29 92.81 93.63 94.45 95.27 96.09 96.92 97.43 97.94 98.46 98.97 99.49 100 100.5 101 101 101 101 101 101 101
109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135
136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155
0 0 0
Y'-
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
A''-2 V'- Z'- A''- Z'- A''-
0 0
X'-
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Man power 0 0
Total per day
1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966
101 101 101 101 101 101 101 101 101 101 101 101 101 101 101 101 101 101 101 101 %
136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 Day
TIME SCALED DIAGRAM (MANPOWER LEVELING)
DAY
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
96
91
86
81
76 5 5
71 F-1
66 10 10 10 11 5 5 5 5 5
D-4 E-1 G-5
61
8 8 15 15 15 15 15 15 15 6 6 9 9 9 7 7 7 7 7 8 8 8 8 8 10
56 A-4 B-9 C-2 H-3 J-6 K-5 N-8
51 10
I-5
46
15
41 L-3
36
31
26
21
16
11
6
1
1 82 83 254 255 256 267 208 209 25
10 16
11 11
12 913 914 915 1716 717 718 719 720 821 822 823 824 8 25 2526 27 28
8 16 41 66 91 117 137 157 182 198 209 218 227 236 253 260 267 274 281 289 297 305 313 321 346
0.407 0.814 2.085 3.357 4.629 5.951 6.968 7.986 9.257 10.07 10.63 11.09 11.55 12 12.87 13.22 13.58 13.94 14.29 14.7 15.11 15.51 15.92 16.33 17.6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
DAY
26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
10 10 10 10 10 9 9 9 9 10 10 10 6 6 4 4 4 10 10 10 10 10 10 14 14 14 14
P-4 Q-4 R-2 V-3 W-9 Y-15
15 15 5 5 5
O-3
16 16 16 16 16 16
M-6
10 4 4 12 12 12
S-12 T-17 U-4
25 26 2527 2528 1529 1530 1531 2532 2533 2534 2535 2636 26 37 10 38 6 39 6 40 14 41 8 42 8 43 22 44 22 45 22 46 10 47 10 48 10 49 14 5014 5114 5214 53 54 5
371 396 411 426 441 466 491 516 541 567 593 603 609 615 629 637 645 667 689 711 721 731 741 755 769 783 797
18.87 20.14 20.91 21.67 22.43 23.7 24.97 26.25 27.52 28.84 30.16 30.67 30.98 31.28 31.99 32.4 32.81 33.93 35.05 36.16 36.67 37.18 37.69 38.4 39.11 39.83 40.54
26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
DAY
53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79
14 14 14 14 14 14 14 14 14 14 14 4 4 4 10 10 10 10 10 10 10 10 10 12 12 28 28
Z-2 B'-6 C'-5 D'-3 E'-1
2 8
X-1 A'-1
51 52 5314 5414 5514 5614 5714 5814 5914 6014 6114 6214 6314 646 6512 664 6710 6810 6910 7010 71
10 7210 73
10 10
74 10
75 12
76 12
77 28
78 28
79 80 81
811 825 839 853 867 881 895 909 923 937 951 957 969 973 983 993 1003 1013 1023 1033 1043 1053 1063 1075 1087 1115 1143
41.25 41.96 42.68 43.39 44.1 44.81 45.52 46.24 46.95 47.66 48.37 48.68 49.29 49.49 50 50.51 51.02 51.53 52.03 52.54 53.05 53.56 54.07 54.68 55.29 56.71 58.14
53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79
DAY
80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106
10 10 10 10 10 10
M'-2 R'-8
8
H'-1
28 28 28 28 10 8 8 8 4 4 4 8 8 8 10 10 10 5 5 10 10 10 10 10 10 40 40
F'-2 G'-4 I'-2 J'-6 K'-4 L'-3 N'-7 O'-3 P'-1
78 79 28
80 28
81 28
82 28
83 10
84 8
85 8
86 8
87 12
88 4
89 4
90 8
91 8
92 8
93 10
94 10
95 10
96 5
97 5
98 20
99 20
100 20
101 20 20
102 103 20
104 40
105 40
106 107 108
1171 1199 1227 1255 1265 1273 1281 1289 1301 1305 1309 1317 1325 1333 1343 1353 1363 1368 1373 1393 1413 1433 1453 1473 1493 1533 1573
59.56 60.99 62.41 63.84 64.34 64.75 65.16 65.56 66.17 66.38 66.58 66.99 67.4 67.8 68.31 68.82 69.33 69.58 69.84 70.85 71.87 72.89 73.91 74.92 75.94 77.98 80.01
80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106
DAY
107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133
6 6 6 0 0 0
2 Y'-10 Y'-
S'-1
40 40 40 40 5 5 5 5 5 6 6 6 10 10 10 10 10 10 10 10 10 10 10 0 0 0 0
T'-6 U'-8 V'-4 Z'-4 A''-2 V'-
8 8 8 8 4 4
Q'-7 W'-2
10 10 0 0
X'-3 X'-
105 106 40
107 40
108 40
109 40
110 15
111 13
112 13
113 13
114 9
115 10
116 16
117 16
118 16
119 16
120 16
121 10
122 10
123 10
124 10
125 10
126 10127 10128 10129 0130 0131 0132 0133 134 135
1613 1653 1693 1733 1748 1761 1774 1787 1796 1806 1822 1838 1854 1870 1886 1896 1906 1916 1926 1936 1946 1956 1966 1966 1966 1966 1966
82.04 84.08 86.11 88.15 88.91 89.57 90.23 90.9 91.35 91.86 92.68 93.49 94.3 95.12 95.93 96.44 96.95 97.46 97.97 98.47 98.98 99.49 100 100 100 100 100
107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133
134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155
0 0 0
Y'-
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Z'- A''-2 V'- Z'- A''- Z'- A''-
0 0
X'-
1 132 133 0134 0135 0136 0137 0 138 0 139 0 140 0 141 0 142 0 143 0 144 0 145 0 146 0 147 0 148 0 149 0 150 0 151 0 152 0 1530 1540 155
Man power
1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 1966 Total per day
100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 %
134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 Day
TIME SCALED DIAGRAM (COST)
DAY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
F-1
I-5
4580 4580 19320 19320 19320 6430 22740 22740 22740 4250 6200 5040 5040 5040 17440 17440 17440
4580 9160 28480 47800 67120 73550 96290 119030 141770 146020 152220 157260 162300 167340 184780 202220 219660
0.18113 0.36226 1.126315 1.890374 2.654433 2.908724 3.808036 4.7073479 5.6066598 5.774737 6.019932 6.2192518 6.4185715 6.6178913 7.307601 7.9973108 8.6870205
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
DAY
18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
17440 17440 12050 12050 12050 12050 12050 18960 18960 18960 12060 12060 12060 24800 24800 24800
K-5 N-8 P-4
L-3 O-3
M-6
17440 17440 12050 12050 12050 12050 12050 18960 18960 18960 12060 12060 12060 24800 24800 24800
237100 254540 266590 278640 290690 302740 314790 333750 352710 371670 383730 395790 4E+05 432650 457450 482250
9.3767302 10.06644 10.542988 11.019537 11.496085 11.972633 12.449181 13.199003 13.948825 14.698647 15.175591 15.6525 16.129 17.110259 18.091039 19.071818
18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
DAY
34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
24800 12860 12860 12860 3660 3660 3670 4580 4580 16890 16890 16890 8610 8610 8610 56850
Q-4 R-2 V-3 W-9 Y-15
24800 12860 12860 12860 3660 3660 3670 4580 4580 16890 16890 16890 8610 8610 8610 56850
507050 519910 532770 545630 549290 552950 556620 561200 565780 582670 599560 616450 625060 633670 642280 699130
20.052598 20.56118 21.069762 21.578344 21.723088 21.867832 22.012972 22.1941 22.375227 23.043186 23.711 24.379 24.72 25.060112 25.400617 27.648897
34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
DAY
50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66
56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 1950 3330 1490
Z-2
X-1 A'-1
56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 1950 3330 1490
755980 812830 869680 926530 983380 1040230 1097080 1153930 1210780 1267630 1324480 1381330 1438180 1495030 1496980 1500310 1501800
29.897176 32.145456 34.393736 36.642015 38.890295 41.138575 43.386854 45.635134 47.883414 50.131693 52.379973 54.628253 56.876532 59.124812 59.20193 59.333623 59.392549
50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66
DAY
67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84
11000 11000 11000 11000 13750 13750 13750 13750 13750 20700 20700 41340 41340 41340 41340 41340 41340 2750
B'-6 C'-5 D'-3 E'-1 F'-2
11000 11000 11000 11000 13750 13750 13750 13750 13750 20700 20700 41340 41340 41340 41340 41340 41340 2750
1512800 1523800 1534800 1545800 1559550 1573300 1587050 1600800 1614550 1635250 1655950 1697290 1738630 1779970 1821310 1862650 1903990 1906740
59.827573 60.2626 60.69762 61.13264 61.67642 62.2202 62.76398 63.30776 63.85154 64.67017 65.48881 67.1237 68.7586 70.3935 72.0284 73.66329 75.29819 75.40694
67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84
DAY
85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102
M'-2 R'-8
H'-1
6870 6870 6870 3210 2740 2740 6870 6870 6870 8250 8250 8250 3200 3200 5050 15150 15150 15150
G'-4 I'-2 J'-6 K'-4 L'-3 N'-7
6870 6870 6870 3210 2740 2740 6870 6870 6870 8250 8250 8250 3200 3200 5050 15150 15150 15150
1913610 1920480 1927350 1930560 1933300 1936040 1942910 1949780 1956650 1964900 1973150 1981400 1984600 1987800 1992850 2008000 2023150 2038300
75.67864 75.95033 76.22202 76.34897 76.45733 76.56569 76.83738 77.10907 77.38076 77.70703 78.0333 78.35957 78.48612 78.61267 78.81239 79.41153 80.01068 80.60982
85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102
DAY DAY
103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120
Y'-10
S'-1
10580 10580 57900 57900 57900 57900 57900 57900 2180 10680 10680 10680 2520 2870 6660 6660 12390 12390
O'-3 P'-1 T'-6 U'-8 V'-4
Q'-7 W'-2
X'-3
10580 10580 57900 57900 57900 57900 57900 57900 2180 10680 10680 10680 2520 2870 6660 6660 12390 12390
2048880 2059460 2117360 2175260 2233160 2291060 2348960 2406860 2409040 2419720 2430400 2441080 2443600 2446470 2453130 2459790 2472180 2484570
81.02824 81.44665 83.73645 86.02626 88.31606 90.60587 92.89567 95.18548 95.27169 95.69406 96.11643 96.5388 96.63846 96.75196 97.01534 97.27873 97.76873 98.25872
103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120
DAY
121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138
S'-
12390 12390 2750 2750 2750 5500 5500 5500 5500 5500 2180 10680 10680 10680 2520 2870 0 0
Z'-4 A''-2 T'- U'-
Q'- W'-
X'-
12390 12390 2750 2750 2750 5500 5500 5500 5500 5500 2180 10680 10680 10680 2520 2870 0 0
2496960 2509350 2512100 2514850 2517600 2523100 2528600 2534100 2539600 2545100 2547280 2557960 2568640 2579320 2581840 2584710 2584710 2584710
98.74871 99.23871 99.34747 99.45622 99.56498 99.78249 100 100.2175 100.435 100.6525 100.7387 101.1611 101.5835 102.0059 102.1055 102.219 102.219 102.219
121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138
139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155
Y'-
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
V'- Z'- A''-
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 COST
2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 Total per day
102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 102.219 %
139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 Day
DAY
COST
Total per day
DAY
Costs vs. Time S-Curve
96.00
91.00
86.00
81.00
76.00
71.00
66.00
61.00
56.00
C
o 51.00
s 46.00
t 41.00
( 36.00
% 31.00
) 26.00
21.00
16.00
11.00
6.00
1.00
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 10 1 1 0 5 10 9 11 3 11 7 12 1 1 2 5
DAYS
COST 0.18 0.36 1.13 1.89 2.65 2.91 3.81 4.71 5.61 5.77 6.02 6.22 6.42 6.62 7.31 8.00 8.69 9.38 10.07 10.54 11.02 11.50 11.97 12.45 13.20 13.95 14.70 15.18 15.65 16.13 17.11 18.09 19.07
TIME 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
20.05 20.56 21.07 21.58 21.72 21.87 22.01 22.19 22.38 23.04 23.71 24.38 24.72 25.06 25.40 27.65 29.90 32.15 34.39 36.64 38.89 41.14 43.39 45.64 47.88 50.13 52.38 54.63 56.88 59.12 59.20 59.33 59.39 59.83
34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
60.26 60.70 61.13 61.68 62.22 62.76 63.31 63.85 64.67 65.49 67.12 68.76 70.39 72.03 73.66 75.30 75.41 75.68 75.95 76.22 76.35 76.46 76.57 76.84 77.11 77.38 77.71 78.03 78.36 78.49 78.61 78.81 79.41 80.01
68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101
80.61 81.03 81.45 83.74 86.03 88.32 90.61 92.90 95.19 95.27 95.69 96.12 96.54 96.64 96.75 97.02 97.28 97.77 98.26 98.75 99.24 99.35 99.46 99.56 99.78 ###
102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127
TIME SCALED DIAGRAM (COST)
DAY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
96
91
86
81
76
71 F-1
51 I-5
46
41
36
31
26
21
16
11
6
1
4580 4580 19320 19320 19320 6430 22740 22740 22740 4250 6200 5040 5040 5040 17440 17440
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
4580 9160 28480 47800 67120 73550 96290 119030 141770 146020 152220 157260 162300 167340 184780 202220
0.1772 0.35439 1.101864 1.849337 2.59681 2.84558 3.72537 4.6051588 5.484948 5.6493765 5.8892487 6.0842416 6.2792344 6.4742273 7.1489645 7.8237017
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
DAY
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
17440 17440 17440 12050 12050 12050 12050 12050 18960 18960 18960 12060 12060 12060 24800 24800
K-5 N-8 P-4
L-3 O-3
M-6
17440 17440 17440 12050 12050 12050 12050 12050 18960 18960 18960 12060 12060 12060 24800 24800
6 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 3
219660 237100 254540 266590 278640 290690 302740 314790 333750 352710 371670 383730 395790 4E+05 432650 457450
8.4984389 9.1731761 9.8479133 10.314116 10.78032 11.246523 11.712726 12.178929 12.912474 13.646018 14.379563 14.846153 15.3127 15.779 16.738822 17.69831
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
DAY
33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
24800 24800 12860 12860 12860 3660 3660 3670 4580 4580 16890 16890 16890 8610 8610 8610
Q-4 R-2 V-3 W-9
24800 24800 12860 12860 12860 3660 3660 3670 4580 4580 16890 16890 16890 8610 8610 8610
33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
482250 507050 519910 532770 545630 549290 552950 556620 561200 565780 582670 599560 616450 625060 633670 642280
18.657799 19.617288 20.114829 20.61237 21.109912 21.251514 21.393116 21.535105 21.7123 21.889496 22.542955 23.196 23.85 24.183 24.516097 24.849209
33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
DAY
49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65
56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 1950 3330
Y-15 Z-2
X-1 A'-1
56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 56850 1950 3330
50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69
699130 755980 812830 869680 926530 983380 1040230 1097080 1153930 1210780 1267630 1324480 1381330 1438180 1495030 1496980 1500310
27.048682 29.248155 31.447629 33.647102 35.846575 38.046048 40.245521 42.444994 44.644467 46.84394 49.043413 51.242886 53.442359 55.641832 57.841305 57.916749 58.045583
49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65
DAY
66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82
1490 11000 11000 11000 11000 13750 13750 13750 13750 13750 20700 20700 41340 41340 41340 41340 41340
B'-6 C'-5 D'-3 E'-1
1490 11000 11000 11000 11000 13750 13750 13750 13750 13750 20700 20700 41340 41340 41340 41340 41340
67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86
1501800 1512800 1523800 1534800 1545800 1559550 1573300 1587050 1600800 1614550 1635250 1655950 1697290 1738630 1779970 1821310 1862650
58.10323 58.52881 58.95439 59.37997 59.80555 60.33752 60.8695 61.40147 61.93345 62.46542 63.26629 64.06715 65.66655 67.26596 68.86537 70.46477 72.06418
66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82
Y DAY
83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100
M'-2 R'-8
H'-1
41340 2750 6870 6870 6870 3210 2740 2740 6870 6870 6870 8250 8250 8250 3200 3200 5050 15150
F'-2 G'-4 I'-2 J'-6 K'-4 L'-3 N'-7
41340 2750 6870 6870 6870 3210 2740 2740 6870 6870 6870 8250 8250 8250 3200 3200 5050 15150
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1903990 1906740 1913610 1920480 1927350 1930560 1933300 1936040 1942910 1949780 1956650 1964900 1973150 1981400 1984600 1987800 1992850 2008000
73.66358 73.76998 74.03577 74.30157 74.56736 74.69155 74.79756 74.90357 75.16936 75.43516 75.70095 76.02013 76.33932 76.6585 76.78231 76.90611 77.10149 77.68763
83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100
DAY DAY
101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118
S'-1
15150 15150 10580 10580 57900 57900 57900 57900 57900 57900 2180 10680 10680 10680 2520 2870 6660 6660
O'-3 P'-1 T'-6 U'-8
Q'-7 W'-2
X'-3
15150 15150 10580 10580 57900 57900 57900 57900 57900 57900 2180 10680 10680 10680 2520 2870 6660 6660
101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120
2023150 2038300 2048880 2059460 2117360 2175260 2233160 2291060 2348960 2406860 2409040 2419720 2430400 2441080 2443600 2446470 2453130 2459790
78.27377 78.85991 79.26924 79.67857 81.91867 84.15876 86.39886 88.63896 90.87905 93.11915 93.20349 93.61669 94.02989 94.44309 94.54059 94.65162 94.90929 95.16696
101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118
DAY
119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136
Y'-10
S'-
12390 12390 12390 12390 2750 2750 2750 5500 5500 5500 5500 5500 2180 10680 10680 10680 2520 2870
V'-4 Z'-4 A''-2 T'- U'-
Q'- W'-
12390 12390 12390 12390 2750 2750 2750 5500 5500 5500 5500 5500 2180 10680 10680 10680 2520 2870
118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137
2472180 2484570 2496960 2509350 2512100 2514850 2517600 2523100 2528600 2534100 2539600 2545100 2547280 2557960 2568640 2579320 2581840 2584710
95.64632 96.12568 96.60503 97.08439 97.19079 97.29718 97.40358 97.61637 97.82916 98.04195 98.25474 98.46753 98.55187 98.96507 99.37827 99.79147 99.88896 100
119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136
137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154
Y'-
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
V'- Z'- A''-
X'-
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155
2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710 2584710
100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100
137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154
D
155
0 COST
153 154 155
2584710 Total per day
100 %
155 Day
DAY
TIME SCALED ACTIVITY DIAGRAM
DAY
1 2 3 4 6 7 8 10 13 14 15 16 17 18 19 20 21 23 24 25 27 29 31 33 34 36
F-1
4 5
D-4 E-1 G-5
2 3 6 7 8 9
A-4 B-9 C-2 H-3 J-6 K-5 N-8
I-5
L-3
M-6
DAY
38 40 42 43 44 45 47 48 49 50 52 53 54 55 56 57 58 59 60 62 64 66 67 68 69 70
11 12 13 14 15 18
N-8 P-4 Q-4 R-2 V-3 W-9 Y
10
L-3 O-3
M-6
16 17
S-12 T-17 U-4
DAY
71 72 73 74 75 76 77 78 79 80 81 82 83 85 87 88 89 90 91 92 93 94 95 97 98
19 21 23 24 25
Y-15 Z-2 B'-6 C'-5 D'-3 E'-1
20
X-1 A'-1
DAY
99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 1147 119 120 121 122 123 124 125
33
M'-2 R'-8
H'-1
26 27 28 29 30 31 32 34 35
F'-2 G'-4 I'-2 J'-6 K'-4 L'-3 N'-7
DAY
126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152
Y'-10
S'-1
36 37 39 40 42 41
O'-3 P'-1 T'-6 U'-8 V'-4 Z'-4
38
Q'-7 W'-2
X'-3
153 154 155
Z'-4 A''-2
Man Hour vs. Time S
100
95 Man Hour vs. Time S-Curve
90
85
80
75
70
65
M
60
A
N 55
H 50
O 45
U 40
R 35
(
30
%
) 25
20
15
10
5
0
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 1 0 1 10 5 10 9 1 1 3 1 1 7 1 2 1 12 5
DAYS
0.411
Man Hour vs. Timeday
S-Curve
0.411 1
0.822 2
2.107 3
3.392 4
4.676 5
6.012 6
7.04 7
8.068 8
9.353 9
10.17 10
10.74 11
11.2 12
11.66 13
12.13 14
13 15
13.36 16
13.72 17
14.08 18
14.44 19
14.85 20
15.26 21
15.67 22
16.08 23
16.5 24
17.78 25
19.06 26
20.35 27
21.12 28
21.89 29
22.66 30
23.95 31
25.23 32
26.52 33
27.8 34
29.14 35
30.47 36
31 37
31.29 38
31.6 39
32.32 40
32.73 41
33.14 42
34.28 43
35.41 44
36.54 45
37.05 46
37.56 47
38.08 48
38.8 49
39.52 50
40.24 51
41 52
41.68 53
42.39 54
43.11 55
43.83 56
44.55 57
45.27 58
46 59
46.71 60
47.43 61
48.15 62
48.87 63
49.18 64
49.79 65
50 66
50.51 67
51 68
51.54 69
52.06 70
52.57 71
53.08 72
53.6 73
54.11 74
54.62 75
55.24 76
55.86 77
57.3 78
58.74 79
60.17 80
61.61 81
63.05 82
64.49 83
65 84
65.42 85
65.83 86
66.24 87
66.86 88
67.06 89
67.27 90
67.68 91
68.09 92
68.5 93
69 94
69.53 95
70 96
70.3 97
70.55 98
71.58 99
72.61 100
73.64 101
74.67 102
75.69 103
76.72 104
78.78 105
80.83 106
82.89 107
84.94 108
87 109
89.05 110
89.83 111
90.49 112
91.16 113
91.83 114
92.29 115
92.81 116
93.63 117
94.45 118
95.27 119
96.09 120
96.92 121
97.43 122
97.94 123
98.46 124
99 125
99.49 126
100 127
MANPOWER TABULATION PER ACTIVITY