MANAGEMENT
BIG NANTES
AMZZOUGH DAVID
CHANDU VARUN GOPAL
GUNDAPANENI JAI SHIVA
QIN HONGZHANG
VYAKARANAM RAMA PHANI SASIKANTH
PROJECT STATEMENT
1. Project justification
The railroad is built to connect Nantes’ three existing railways to transport goods and passengers to maximize the
capacities of the railway systems with a view to reduce the city’s carbon footprint, maintain its green movement
and accelerate dynamic economic growth.
2. Objective
• Connect the existing tramway and busway lines
• Reduce the travelling time of the passengers
• Improve the passengers experience
• Use the tram way to transport goods
• Enhance the economic dynamic of the city
• Reduce the carbon emissions
3. Project Description
3.1 Project Scope / Deliverables
Includes
• Construction of railroads
• Safety Checking
• Constructions of tram stops
• Hiring work force and renting equipment
• Sourcing materials
• Establishing electric lines
• Development and integration of digital services
Excludes (limits of the project)
• Operating trams
• Buying trams
• Maintenance
• Electric grid
Page 1
3. Project Description
3.2 Success Criteria (Performance indicators)
Four categories for success criteria:
• Timelines:
o Cycle time
o Time spent
• Budget:
o Budget variance
o Line items in budget
• Qualtity:
o Customer satisfaction
o Number of errors
• Effectiveness:
o Number of Project Milestones completed on time with sign off
o Number of returns
3.3 Assumptions
• It is possible to build a tram way according to the proposed plan without having any hurdles such as
buildings in between
• Total cost is bared by the government
• Perfect architecture with site verifications done hence no need to use designers for more than once
Page 2
3. Project Description
3.4 Main Risks
Financial Risks :
Reconstruction costs
Over Budgeting
Miscellaneous costs
Organizational Risks :
Lack of
Inflexibility
coordination
Outsourcing Loss of
delays productivity
Incomplete Unexpected
environmental weather
analysis conditions Delay in operations
& Increase in cost
Incomplete New/revised
quantity design
estimates standards
Page 3
4. Milestones
Main phases or deliverables Date, Duration
Site visits and Design the railroad April 1 2019, 4 months
Make supplier evaluation and source required materials June 1 2019, 15 days
Construct Base frame and install the railway June 1 2021, 1 year
5. Resources
Page 4
5. Resources
2 Materials
High quality Steel alloy 100 3 euro/kg
million
kg
Iron bars 50000 kg 2 euro/kg
Glass (1*2) 50 p 50 euro/piece
Cement poles 1000 p 200 euro/pole
Iron sheets(3*3) 24 50 euro/sheet
Cement 100 ton 3000 euro/ton
Sand 100 ton 2000euro/ton
Gravel stones 100 ton 4000 euro/ton
Water 8million 8000euro
Liters
Excavator 3 110 euros/hr
Drilling machine 3 80 euros/hr
Ballast tamping sets 3 100 euros/hr
Gantry cranes 3 110euros/hr
Threader rail machines 3 135 euros/hr
Grinding rail machines 3 100 euros/hr
Maintenance track operation vehicle 3 135 euros/hr
Tool equipment (lifting rack jacks, hydraulic lifting jacks; socket 3 20 euros/hr
wrenches; fishbolt spanners; concrete sleeper tongs; wooden
sleeper tongs, etc.)
Concrete vibrator 3 25 euros/hr
Asphalt cutting machine 3 25 euros/hr
Dozer 3 135 euros/hr
Trucks 3 80 euros/hr
Steel wheel static roller 3 90 euro/hr
Welding generator 3 80 euros/hr
Electric generator 3 80 euros/hr
Road brooming machine 3 40 euros/hr
Page 5
6. Budget (macro)
Main costs based on previous projects.
TOTAL 381,826,670 €
PRE-PRODUCTION
PROJECT INITIATION ANALYZING REQUIREMENTS &TCC
Assign key persons Analyze requirements
Review requirements, objectives& Calculate Total cost
constraints
Review existing tram way Prepare documentation for approval
Design railways Get government verification
Design electric lines Get approval
Design tram stations Assign milestones to key persons
Propose milestones Assign objectives and powers to key
persons
Get it reviewed by government official Hire crew
Page 6
PRODUCTION
CONSTRUCTING RAILWAY CONSTRUCTING TRAM INSTALLING ELECTRIC
STATIONS LINES
Source cement, sand, crushed Source Glass, metal rods, Drill holes for poles
rock, steel bars, water plastic roof, display
Create concrete Drill holes and install poles Install poles
Construct base road parallelly Install glass and wiring Install lights
in 3 sectors
Install base frame Install roof and display Install electric lines
Install rail track Connect lines to lights and
stations
Fill in crushed stones Install network lines
COMPLETION PHASE
DIGITAL INTEGRATION TESTING
Perform internal testing Update data of new tram ways into the
system
Collect data from tests Perform testing on network accuracy
Review for errors
Perform corrections if necessary
Prepare documentation for approval
Get approval from government
Prepare paperwork for final draft
Get necessary signatures
7. Validations
Project budget, WBS, etc. are approved by :
QIN Hongzhang - CEO
GUNDAPANENI Jai Shiva- Project manager
Page 7
PROJECT PLAN: GANTT CHART
COST OVERVIEW:
Page 8
PLAN OF THE NEW RAILWAY:
Page 9