You are on page 1of 51

[Maintenance Design of Tennis Court and Mary Stuart Roads] 

DEDICATION 
The story of our lives; an experience of science and technology integrated in the way we breathe, the 
way we communicate and in the way we survive. The findings of this research and study are dedicated 
to all  born in the era  of technology  at  its  climax  and  thus  are  due  to experience  the comfort  of good 
infrastructure.

[Group Project Design]  i 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

ACKNOWLEDGEMENTS 
We are indebted to the Faculty of Technology, Makerere University for integration into the curriculum 
of such opportunities as this is to explore the beauty and importance of civil engineering through a field 
research and design experience. 

We extend our appreciation to our supervisors, Dr. Umaru Bagampadde and Eng. Dr. Albert Rugumayo 
who guided us successfully through the study and without whom we would not have achieved the best 
of the project. 

Our thanks go out to the soil laboratory personnel, in mention, Mr. Fred Mukasa and Mr. Patrick Hamba 


who in their capacity  shared with us their experience  and  expertise  in highway  engineering  and  other 
related  engineering  fields  and  for  their  hospitality  and  friendliness  that  made  the  whole  experience 
more interesting and fun. 

And to God Almighty, for the gift of life and endless opportunities.

[Group Project Design]  ii 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

TABLE OF CONTENTS 
DEDICATION……………………………………………………………………………………………………………………………………………..i 

ACKNOWLEDGEMENTS…………………………………………………………………………………………………………………………...ii 

TABLE OF CONTENTS………………………………………………………………………………………………………………………………iii 

LIST OF FIGURES………………………………………………………………………………………………………………………………………v 

LIST OF TABLES……………………………………………………………………………………………………………………………………….vi 

ABBREVIATIONS…………………………………………………………………………………………………………………………………….vii 

CONTENTS 
CHAPTER ONE: INTRODUCTION ............................................................................................................... 1 
1.1  BACKGROUND.......................................................................................................................... 1 
1.2  PROBLEM STATEMENT ............................................................................................................. 3 
1.3  OBJECTIVES .............................................................................................................................. 4 
1.4  SUMMARY OF ACTIVITIES......................................................................................................... 4 
CHAPTER TWO: LITERATURE REVIEW....................................................................................................... 5 
2.1  INTRODUCTION........................................................................................................................ 5 
2.2  DESIGN OF FLEXIBLE PAVEMENTS ............................................................................................ 6 
2.2.1  STRUCTURAL DESIGN........................................................................................................ 6 
2.2.2  MIX DESIGN.................................................................................................................... 13 
2.3  CONCLUSION ......................................................................................................................... 15 
CHAPTER THREE: METHODOLOGY ......................................................................................................... 16 
3.1  INTRODUCTION...................................................................................................................... 16 
3.2  DATA COLLECTION ................................................................................................................. 16 
3.2.1  TRAFFIC COUNTS ............................................................................................................ 16 
3.2.2  ROAD MARKING ............................................................................................................. 19 
3.2.3  VISUAL SURVEY .............................................................................................................. 19 
3.2.4  PHOTOGRAPHY .............................................................................................................. 19 
3.2.5  FIELD TESTS .................................................................................................................... 19 
3.2.6  LABORATORY TESTS........................................................................................................ 22

[Group Project Design]  iii 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

3.3  OVERLAY DESIGN ................................................................................................................... 25 


CHAPTER FOUR: RESULTS, ANALYSIS AND DISCUSSION.......................................................................... 28 
4.1  INTRODUCTION...................................................................................................................... 28 
4.2  LABORATORY TEST RESULTS................................................................................................... 28 
4.2.1  Soil Classification ............................................................................................................ 29 
4.3  FIELD TEST RESULTS ............................................................................................................... 31 
4.3.1  Field Density Determination ........................................................................................... 31 
4.3.2  Visual Survey Results ...................................................................................................... 31 
4.3.3  DCP Test Results............................................................................................................. 35 
4.4  TRAFFIC COUNT RESULTS ....................................................................................................... 36 
4.5  OVERLAY STRUCTURAL DESIGN .............................................................................................. 38 
4.5.1  Determination of Traffic Load Class, TLC ......................................................................... 38 
4.5.2  Computation of 10th Percentile of Subgrade CBR ........................................................... 39 
4.5.3  Determination of the required structural number........................................................... 39 
4.5.4  Overlay Design ............................................................................................................... 39 
CHAPTER FIVE: CONCLUSION AND RECOMMENDATIONS....................................................................... 42 
5.1  INTRODUCTION...................................................................................................................... 42 
5.2  DEDUCTIONS.......................................................................................................................... 42 
5.3  RECOMMENDATIONS............................................................................................................. 42 
5.3.1  Drainage Improvement................................................................................................... 42 
5.3.2  Side Walks...................................................................................................................... 43 
5.3.3  Road Lighting.................................................................................................................. 43 
6  REFERENCES .................................................................................................................................. 44 
APPENDICES

[Group Project Design]  iv 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Figure 1.1 MAP OF THE PROJECT AREA .................................................................................................... 2 
Figure 2.1 Surface Coarse options     a) Single Surface dressing;  b) Double Surface dressing ............... 9 
Figure 2.2 Monograph ........................................................................................................................... 10 
Figure 2.3 Graphs of stability, bulk density and void ratio against binder content .................................. 15 
Figure 3.1 Positions of traffic counters................................................................................................... 18 
Figure 3.2 Chart of Overlay options ....................................................................................................... 27 
Figure 4.1 Measurement of patched area .............................................................................................. 32 
Figure 4.2 Measurement of potholed area............................................................................................. 32 
Figure 4.3 Maintenance Design Strip Map for Tennis Court Rd – Mary Stuart Rd (1km).......................... 34 
Figure 4.4  Design Overlay Options; (a) AC overlay; (b) Bituminous Mix for Base course; (c) Penetration 
Macadam; (d) Granular Base course. ..................................................................................................... 41

[Group Project Design]  v 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Table 2.1 Classification of Sub grades ...................................................................................................... 8 


Table 2.2 Nominal Values for Layer coefficients..................................................................................... 12 
Table 3.1 Axle loads for the different vehicle types................................................................................ 17 
Table 3.2 Equivalent Axle Load Factors .................................................................................................. 17 
Table 3.3 Traffic Load Classes (TLC)........................................................................................................ 26 
Table 3.4 Determination of required structural number ........................................................................ 26 
Table 4.1 Laboratory Tests..................................................................................................................... 28 
Table 4.2 Soil Classification.................................................................................................................... 30 
Table 4.3 Field Bulk Densities ................................................................................................................ 31 
Table 4.4 Results of Measured Quantities of Distressed area ................................................................. 35 
Table 4.5 DCP Layer Strength Analysis Results ....................................................................................... 36 
Table 4.6 Traffic Count .......................................................................................................................... 36 
Table 4.7 Equivalent Single Axle Loads (ESALs)....................................................................................... 37 
Table 4.8 Average Hourly Volume.......................................................................................................... 37 
Table 4.9 Calculation of Structural Number difference........................................................................... 39

[Group Project Design]  vi 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

LIST OF ABBREVIATIONS 

AC  ‐  Asphalt Concrete 

AASHTO  ‐  American Association of State Highway and Transportation Officials 

BST  ‐  Bituminous Surface Treatment 

CBR  ‐  California Bearing Ratio 

CRB  ‐  Crushed Road Base 

DCP  ‐  Dynamic Cone Penetrometer 

DT  ‐  Design Traffic 

EALF  ‐  Equivalency Axle Load Factor 

ESAL  ‐  Equivalent Standard Axle Load 

LL  ‐  Liquid Limit 

MDD  ‐  Maximum Dry Density 

MOWHC  ‐  Ministry Of Works Housing and Communications 

MPa  ‐  Mega Pascal 

PI  ‐  Plasticity Index 

PL  ‐  Plastic Limit 

PM  ‐  Penetration Macadam 

SN  ‐  Structural Number 

ST  ‐  Surface Treatment 

TLC  ‐  Traffic Load Class 

TRL  ‐  Transport Research Laboratory 

UCS  ‐  Unconfined Compressive Strength

[Group Project Design]  vii 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

1  CHAPTER ONE: INTRODUCTION 

1.1  BACKGROUND 

A  good  highway  or  road  should  ideally  enable  movement  freight  and  passengers  from  one  place  to 
another  in  the  shortest  possible  time  with  minimum  discomfort.  Good  transport  therefore  facilitates 
infrastructural,  economic  and  social  development  of  a  given  area.  The  planning,  design,  construction, 
operation  and  maintenance  of  highways  depend  largely  on  the  efforts  of  the  highway  engineer,  who 
must transform the needs and desires of people for better transportation into reality. 

Many  third  world  countries,  Uganda  inclusive,  have  in  many  cases  had  poorly  constructed  and 
maintained  highway  systems.  A  number  of  problems  are  attributed  to  this  and  these  include  poor 
administration and monitoring of road works, low level of technology and abuse of traffic laws by road 
users.  The  most  prominent  of  the  above  problems  is  poverty  hence  the  need  for  affordable  yet 
adequate designs to cater for the needs of road users. 

Makerere University campus is located about 2km from Kampala city centre. There has been a drastic 
increase  in  population  of  the  campus  over  the  past  couple  of  years.  This  has  caused  increased  traffic 
loading  and  therefore  increased strain on  most  of  the  roads on  the campus.  General  neglect  towards 
maintenance  has  led  to  further  deterioration  of  the  condition,  with  an  increase  in  the  functional 
distresses on the roads. Mary‐Stuart and Tennis court roads are located in the Western part of Makerere 
University and are the roads that were chosen for this project. We decided to zero down to these two 
roads because of their close proximity to the Faculty of Technology which would make field work easier. 
These roads also directly affect vehicles moving to the Faculty. 

Tennis  court  road  is  the  main  access  road  to  a  number  of  campus  facilities  namely;  Complex  Hall  of 
residence, Faculty of Psychology, School of Education, Makerere University Child learning centre and the 
tennis courts while Mary‐ Stuart road is used to access Lumumba and Mary Stuart halls of residence, the 
Faculty  of Technology  and  Departments  of  Food  science  and  Chemistry,  St.  Francis  community  centre 
and St. Augustine student centre.

[Group Project Design]  1 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Figure 1.1 below shows the general location of the roads studied on this project. 

Scale  1: 4300 
Key  Mary Stuart Road 
Tennis Court Road 

Figure 1.1 MAP OF THE PROJECT AREA

[Group Project Design]  2 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

1.2  PROBLEM STATEMENT 
A number of structural and functional distresses have developed on the road pavements. This is because 
the pavements can neither carry out their intended function without  causing discomfort to road users 
nor protect the sub grade. Performance distresses identified along different sections of the road include 
potholes,  corrugations,  and  cracking.  All  the  above  cause  a  number  of  problems  for  the  user  such  as 
increased  fuel  and  oil  consumption,  increased  travel  time,  increased  safety  hazards,  increased vehicle 
maintenance costs and environmental degradation from noise and exhaust. 

Another problem identified on the roads is the poor road drainage system. A number of sections along 
the road have blocked or broken side drains. This causes flooding on the road surface after heavy rains 
which  not  only  ruins  the  pavement  but  makes  movement  of  pedestrians  especially  very  difficult.  A 
fourth year student is currently undertaking a study on the drainage of Mary Stuart Road. 

Many parts of the sidewalk are either broken in or non‐ existent, forcing pedestrians to move along the 
road carriageway. This is very risky for both pedestrians and cyclists as they are vulnerable to vehicular 
traffic.  There is  also a need  to provide ramps  along  the sidewalk  such that  people in wheel  chairs can 
cross the road safely and with ease. 

There is inadequate lighting along the road which impairs safety of road users and people living along 
the road, and hence the need to provide adequate street lighting along the road. 

There are no traffic signs along the road despite the vulnerability of certain sections such as the round 
about  near  the  Faculty  of  Chemistry  and  Makerere  University  Child  learning  centre  at  the  school  of 
education which drivers need to be aware of. Hence a need to provide traffic signs at critical sections of 
the road. 

Part of Mary‐ Stuart road has been turned into a dumping site which is detrimental to aesthetic quality 
of  the  road  and  the  environment.  Consequently,  need  arises  for  clearing  the  road  and  providing  a 
dumping site elsewhere for a safer and more hygienic option. There is also  need to exploit the green 
vegetation  at  some  sections  of  the  road  to  allow  for  infiltration  of  surface  water  from  the  road 
catchment.  This  is  a  much cheaper option  to setup  and  maintain  as compared to drainage  facilities.  It 
also facilitates green engineering which is a boost to the environment in the area.

[Group Project Design]  3 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

All the above reasons necessitated a study aimed at re‐ designing the roads to avert the problems the 
roads in their current state posed to road users. 

1.3  OBJECTIVES 
The main objective  of the project  was  to design a five‐year  maintenance  programme  for  Tennis  Court 
and Mary Stuart Roads. 

The specific objectives of the study were; 

To  establish  the  road  condition  by  conducting  a  condition  survey  of  the  road  using  visual  survey 
and physical measurement of physical distresses 

To establish structural soundness of the pavement through the DCP (Dynamic Cone Penetrometer) 
test 

To design a maintenance programme for both Mary‐ Stuart and Tennis Court roads 

1.4  SUMMARY OF ACTIVITIES 


The following methods were adopted; 

Review  of  literature  on  design  of  highways  from  information  sources  like  road  notes,  design 
manuals, the internet and other publications 
Data  collection  in  form  of  traffic  counts,  maps  of  the  study  area  from  Estates  Department  of 
Makerere University and  visual road surveys 
Road marking and Pavement tests which included DCP and Sand Replacement tests, 
Summary and analysis of data using design standards and computer analysis, 
Structural Maintenance  design of the road pavement and accessories necessary for improvement 
to serve for a five year period.

[Group Project Design]  4 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

2  CHAPTER TWO: LITERATURE REVIEW 

2.1  INTRODUCTION 
The purpose of pavement design is to limit the stresses reaching the subgrade by traffic to a safe level at 
which subgrade deformation is insignificant and the pavement layers do not deteriorate to any serious 
level  within  a  specified  period  of  time.  Therefore,  if  a  road  is  to  be  rehabilitated,  improved  or 
constructed, the design and cost of the required works depend upon a wide range of information. This 
includes the following; 

Detailed condition of the pavement, 

Current overall condition of the road, 

Nature of the road, 

Required standard of the finished road, 

Cost of required activities. 

This chapter contains general literature concerning pavement design. A pavement is a structure that is 
made up of carefully selected and well proportioned materials and is aimed at distributing traffic load 
such that the sub grade is not over stressed. There are two types of pavements namely rigid and flexible 
pavements. A flexible pavement is a structure that maintains intimate contact with and distributes loads 
to  the  sub  grade  and  depends  on  aggregate  interlock,  particle  friction,  and  cohesion  for  stability.  It 
normally  flexes  when  loaded  and  a  substantial  part  of  the  deformation  is  restored  when  the  load  is 
removed and is normally made of three layers; 

Wearing course 
Base course 
Sub base

[Group Project Design]  5 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

2.2  DESIGN OF FLEXIBLE PAVEMENTS 
Design  of  flexible  pavements  entails  four  major  steps;  mix  design,  structural  design,  geometric  and 
drainage  design.  This  project  is  however  concerned  with  structural  and  mix  design  of  pavements.  A 
number of methods of road design are available and these include; 

AASHTO 
Road Note  TRL method 
CBR method 
Ministry of Works and Transport ( MOWT)  method 
However, the AASHTO method which bases on the concept of serviceability of the road pavements to be 
designed is used. 

2.2.1  STRUCTURAL DESIGN 
The main objective is to determine for a given set of materials, the layer thicknesses required for proper 
pavement performance. The principle factors/ input parameters are; 

Traffic loading 
Climate or environment 
Material characteristics 

2.2.1.1  Traffic Loading 
Protection  of  the  sub  grade  from  the  loading  imposed  by  traffic  is  one  of  the  primary  functions  of  a 
pavement  structure.  The  designer  must  provide  a  pavement  that  can  withstand  a  large  number  of 
repeated  applications  of  variable‐  magnitude  loadings.  The  magnitude  of  axle  and  wheel  loads  is  a 
loading factor required in pavement design. Traffic is considered in terms of axles. Some of the common 
types include single axles, tandem axles and tridem axles. It is however convenient to handle all traffic in 
terms of  the legal standard axle load ( an 18,000 pound single axle load with dual tyres) to which all the 
other axle types are converted using an equivalence factor. 

The  Equivalence  Axle  Load  Factor  (EALF)  is  defined  as  the  damage  per  pass  of  a  given  axle  load  to  a 
pavement divided by the damage per pass of the standard axle to the same pavement. 

EALF = Nfs  / Nfi

[Group Project Design]  6 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

If  all  the  axes  are  summed  up  after  converting  them  to  the  standard  axle,  the  sum  gives  the  total 
number of equivalent single axle loads (ESAL). The tire pressure and contact area are other  important 
loading factors. When the tire is in contact with a pavement surface, it exhibits a contact area known as 
the imprint area. The imprint is assumed to be circular with a radius, a. 

Imprint area;  A = πa 2 

Load = area x pressure;  P = A x p 

P = πa 2  p 

a = (P/ pπ) 1/2 

For proper  tyre  inflation,  the pressure between  the road  and  the tyre  surface  should be equal  to  the 
pressure of the tyre. 

2.2.1.2  Climate or Environment 
This  affects  the  behaviour  and  performance  of  the  various  materials  in  the  pavement  and  sub grade. 
Probably the two climatic factors of major influence  are temperature and moisture. The magnitude of 
temperature and its fluctuations affects the properties of certain materials e.g. asphaltic concrete looses 
stability at high temperatures and becomes very hard and stiff at low temperatures. 

Subgrade soils and other paving materials weaken appreciably when saturated, and certain clayey soils 
exhibit  substantial  moisture  –  induced  volume  change  hence  moisture  must  be  taken  into  account. 
Climate  does  not  only  affect  the  choice  of  materials  but  the  drainage  as  well.  Climate in  the  tropics 
covers a wide variety of ranges comprising of; 

Afro – alpine climate, 
Equatorial climate, 
Wet tropical climate, 
Semi arid climate, 
Arid climate and 
Very arid climate.

[Group Project Design]  7 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

2.2.1.3  Material Characteristics 
Various  standard  test  methods  are  used  to  determine  material  properties  but  generally  the  following 
are required. 

a)  Sub grades – CBR, modulus of sub grade reaction and resilient modulus 


b)  Sub base – CBR, resilient modulus 
c)  Base course – CBR, resilient modulus and unconfined compressive stress 
d)  Wearing course – resilient modulus and stability 

SUBGRADES 

These  are  normally  classified  depending  on  their  load  supporting  capacity  under  the  least  favourable 
density and moisture conditions to which they are subjected during the design period. Load supporting 
capacity is determined based on CBR. Normally it is required that sub grades don’t go below 8%. 

Table  2.1  shown  below  is  referenced  from  Highway  Engineering  by  Huang  and  it  shows  the  different 
subgrade classes and their ranges of soaked CBR. 

Table 2.1 Classification of Sub grades 

Sub grade class  Range of soaked CBR 
S0  < 2 
S1  2 – 7 
S2  6 – 14 
S3  12 – 20 
S4  18 – 30 
S5  > 30

SUB BASE 

It is required that if natural gravels are used, the CBR should be at least 30%. In addition, the following 
points should be noted; 

The  maximum  plasticity  index  (PI)  depends  on  the  climate  and  sub  grade.  PIs  up  to  25%  may  be 
tolerated in dry areas where the annual rainfall is less than 500mm. on the contrary; PIs should not 

[Group Project Design]  8 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

exceed 15% in wet areas under permeable bases because of the risk of migration of plastic fines in 
to other layers. 
The  gravel  materials  should  be  carefully  selected  so  as  to  avoid  unsuitable  minerals  e.g.  mica, 
dolomites, etc. 
Natural  gravels,  sands  or  clays  which  don’t  meet  strength  requirements  may  be  improved  by  using 
either cement or lime. 

BASE 

If natural/ crushed gravel is used then these conditions will apply; 

If  the  wearing  course  is  thin  (<  500mm  of  asphalt  concrete),  then  the  4‐  day  soaked  CBR  should 
exceed 80% at 90% MDD. 
Under thick surfacing, lower CBR requirements may be considered. 
If graded/ crushed gravel is used, then the dense graded mix should be obtained with a CBR close to 
100%. 

Cement treated gravels can mobilise a UCS after 7 days of curing of between (2 – 3.5 ) MPa. 

WEARING COURSE 

Surfacing can be done using either surface or asphalt dressings. Surface dressing may be single (12mm 
thick) or double (19+12 mm thick). These are illustrated in Figure 2.1 below 

Stone chippings 
Bitumen 

Option a 

Stone chippings 
Bitumen 
Stone chippings 
Bitumen

Option b 

Figure 2.1 Surface Coarse options  a) Single Surface dressing;  b) Double Surface dressing 

[Group Project Design]  9 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Asphalt concrete consists of a well graded mixture of coarse aggregate, fine aggregate and filler bound 
together  using  straight  run  bitumen  of  preferably  80/  100  penetration  grade.  For  a  high  traffic  and 
temperature, a fairly stiff mix should be used while more flexible mixtures can be tolerated for medium 
and low traffic. In the AASHTO design method, the concept of structural number is employed. Structural 
number (SN) is a measure of the strength of a set of road layers. 

Determination of Structural Number 

Structural Numbers can be calculated using a monograph such as that shown in figure 2.2 below which 
is referenced from Highway Engineering by Huang. 

Resilient  Structural  Modified Structural 


Traffic  Regional Factor (R)
Modulus (E)  Number (SN)  Number (SN) 

Figure 2.2 Monograph 

Parameters of the Monograph 

(i) Traffic 
The total design traffic usually takes into account these factors; 

Directional speed of traffic 
Average daily ESAL (Tb) 
Average annual traffic, T0  = 365*Tb 

[Group Project Design]  10 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Lane split 
Annual rate of traffic growth (r) 
Design life of pavement (n) 

The design traffic is calculated as; 

(1 +  )  − 1 
=  × 

(ii) Resilient Modulus (E) 

This is the dynamic equivalent of elastic modulus of materials in the pavement structure. In reality, most 


materials  that  comprise  flexible  pavements  are  not  elastic  and  exhibit  inelastic  behaviour  such  as 
permanent  deformation  and  time  dependency  (Viscoelastic  behaviour).  If  the  stress  exerted  on  a 
material  is  small  compared  to  its  strength  and  the  exertion  is  repeated  many  times,  the  strain  under 
each  load  application  is  nearly  the  same  and  is  proportional  to  the  stress  hence  it  can  be  considered 
elastic. 

Resilient  Modulus of Sub  grade  soils is  determined using  the Tri  axial  test. However, this is  quite  time 
consuming, therefore, other empirical correlations between resilient modulus and other soil properties 
are  available  and  can  be  used  as  a  guide  to  estimate  the  resilient  modulus  of  a  sub  grade  soil.  One 
relationship involves the use of CBR values of the sub grade soil. 

E (psi) = 1500 CBR 

E (MPa) = 10.3 CBR 

(iii) Regional Factor 
This is dependent on the environmental climate of a particular area and can be referenced from a road 
design manual table. 

Calculation 

Wearing course structural number  SN1  = a1h1 


Base and Wearing coarse structural number  SN2  = a1h1  + a2h2

[Group Project Design]  11 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Sub base, base and Wearing coarse structural number  SN3  = a1h1  + a2h2  + a3h3 


Layer  coefficients  can  be  determined  depending  on  the  materials  used  for  each  layer  and  the  CBR  or 
UCS values as shown in table 2.2 below. 

Table 2.2 Nominal Values for Layer coefficients 

Layer / material  Layer coefficient ( at 25°C) 

A) surfacing 

a) surface dressing  a1  = 0.20 

b) asphalt concrete  a1  = 0.35 

B) Base 

a) bitumen macadam  a2  = 0.20 

b) natural/ crushed gravel  a2 = 0.12 

c) crushed stone 

i) on natural gravel sub base  a2  = 0.14 

ii) on stabilised sub base  a2  = 0.18 

d) cement/ lime treated gravel 

i) 3.5 – 5.0 (UCS)  a2  = 0.18 

ii) 2.0 – 3.5 (UCS)  a2  = 0.14 

C) sub base 

a) natural gravel (CBR > 30)  a3  = 0.11 

b) cement/ lime treated gravel 

i) UCS > 2  a3  = 0.16 

ii) UCS 0.7 ‐ 2  a3  = 0.12

[Group Project Design]  12 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

2.2.2  MIX DESIGN 


This  involves  determination  of  relative  proportions  of  materials  in  a  mixture.  The  basic  principles 
behind mix design include; 

Provision of a suitable air voids content 
Provide adequate stability against deformation 
Account for aggregate absorption 

MIX DESIGN OF PREMIX MATERIALS 

Mix design of pre‐ mix materials has the following purposes; 

Preliminary study of materials 
Determination of a job mix formula 
Quality control in placement of large quantities of mixtures 
Preliminary evaluation of the placed mixture 
The commonly used methods include; 

Marshall method 
Hveem method 
Super pave method 

Marshall Method 

It involves the following procedure; 

a)  Choose a suitable bitumen and a well graded aggregate 
b)  Prepare specimen (in triplicate) for seven different bitumen contents. Most aggregates call for about 
1200 gms to be mixed with bitumen. 
c)  The binder and aggregates are heated to above mixing temperature and mixed when hot for about 2 
minutes 
d)  The  mixture is  poured  into  a  hot  mould  and  compacted  with  75  blows  using  a Marshall  hammer, 
both on top and the bottom of the specimen.

[Group Project Design]  13 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

e)  Keep the specimen in the mould for 24 hours, extrude the specimen from the mould and determine 
the bulk density 
f)  Determine the Maximum Specific Gravity by crushing the specimen and using  Archimedes principle. 
g)  Determine the percentage of air voids using the formula: 

% age Air Voids = 

Where Gmm  = Maximum Specific Gravity 

Gmb  = Bulk Specific Gravity 

Determine  Marshal  Stability  (kN)  and  Marshall  flow  (vertical  displacement  in  0.01  inch)  using  the 
Marshall testing machine. Testing is done at 60°C at loading rate of 50 mm/min. 

The  plots  in  figure  2.3  below  are  made  to  enable  calculation  of  the  design  structural  number  by 
determining  three  different  binder  content  values  based  on  the  relationship  between  stability,  bulk 
density and void air ratio. 

The design binder content is finally calculated using the following formula; 

+  + 

3

[Group Project Design]  14 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Stability

Binder Content 
BC1 

gb 

Binder Content 
BC2 

V air 

4 % 

Binder Content 
BC3 

Figure 2.3 Graphs of stability, bulk density and void ratio against binder content 

2.3  CONCLUSION 
The literature gathered above was found to be sufficient for the design procedure used. It covered the 
entire pavement design. Not only was it comprehensive, it also gave more insight into the methods that 
were  used in the final  stages  of analysis.  However,  the major gap observed in the current  knowledge 
that was assumed important was the absence of data on methods of maintenance design for pavement 
structures. 

[Group Project Design]  15 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

3  CHAPTER THREE: METHODOLOGY 

3.1  INTRODUCTION 
This study methodology includes a review of the details involved in data collection and analysis, making 
conclusions and recommendations based on study findings. 

3.2  DATA COLLECTION 
This included the different forms employed both in the field and laboratory to collect information that 
could be analysed and used to determine the current condition of the road. 

3.2.1  TRAFFIC COUNTS 
Traffic  counts  were  conducted for  two way  traffic  at different  junctions  within  2  hour intervals. These 
were  conducted  from  7‐9  am,  1‐3pm  and  5‐7pm.  The  number  of  vehicles  passing  every  station  at 
different junctions were counted and recorded and the maximum traffic count of each vehicle type in 
either direction was considered. The analysis of the traffic counts are shown in Appendix D. 

The motor traffic was classified depending on the different sizes as shown below; 

Cars and four‐ wheel drives: this category included most passenger cars which approximated to 
1.5 tones in laden weight. 
Coasters: this included passenger cars with more than 4 tires and carriage capacity of about 28 
passengers. 
Motor cycles: (boda‐ bodas, two wheel carriage) 
Pick ups 
Mini buses (matatus): these included taxis and other passenger vans 
Buses 
Trucks: these were mostly being used to transport construction material to various construction 
sites 

The axle loads  of the different  vehicle  types  were  read off  the log  books of each vehicle  type  and  are 
summarised in Table 3.1 below.

[Group Project Design]  16 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Table 3.1 Axle loads for the different vehicle types 

Axle loads 
Front  Rear  Front  Rear 
Vehicle type  kg  kg  lb  lb 
Saloon Car & 4WD  1,000 (s)  1,750 (s)  1,000 (s)  2,000 (s) 
Pick Ups  1,750 (s)  2,250 (s)  2,000 (s)  4,000 (s) 
Mini buses  2,000 (s)  3,000 (s)  4,000 (s)  6,000 (s) 
Coasters  3,000 (s)  5,000 (T)  6,000 (s)  12,000 (T) 
Buses  3,000 (s)  5,500 (T)  6,000 (s)  12,000 (T) 
Trucks  4,000 (s)  8,250 (T)  8,000 (s)  24,000 (T) 

The  equivalent  axle  load  factors  provided  in  table  3.2  were  designed  to  include  the  motorcycle  and 
pedestrian traffic.  The factors were  interpolated  from  the standards provided in Highway  Engineering, 
7 th  edition (Paul H. Wright and Karen Dickson). 

Table 3.2 Equivalent Axle Load Factors 

Axle Load (kg)  E A L F 
1,000 (s)  0.00002 
2,000 (s)  0.00018 
4,000 (s)  0.00209 
6,000 (s)  0.01043 
8,000 (s)  0.03430 
12,000 (T)  0.01440 
24,000 (T)  0.26000 

A drawing showing the positions of traffic counters at the different junctions is shown in figure 
3.1 below.

[Group Project Design]  17 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Lumumba hall 

Mary Stuart Hall  St. Francis 
Faculty of 
community centre 
Agriculture & 
Forestry 

N
Dept. 
psychology 

Tennis courts 
Complex 
Hall 

Figure 3.1 Positions of traffic counters 

KEY:  Station 1  Station 5 


Station 2  Station 6 
Station 3  Station 7 
Station 4 

Stations were positioned immediately after each junction on the road to account for traffic that did not 
proceed  to  successive  stations.  Traffic  was  numerated  in  both  the  Northbound  and  Southbound 
directions at each station. 

[Group Project Design]  18 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

3.2.2  ROAD MARKING 
This  involved  demarcating  the  road  into  100m  sections  using  a  pedometer  to  measure  the  chainages 
and a paint brush and road marking paint to mark the chainage along the curb. The first chainage (0+00) 
was marked at the Complex hall round about along Tennis Court road and the last chainage (1+00) was 
marked at the round about next to the Faculty of Chemistry along Mary‐ Stuart road. 

3.2.3  VISUAL SURVEY 
This  was  carried out  to determine the current  state of both Tennis  court  and  Mary‐  Stuart  roads.  The 
surface condition of the road was assessed based on the potholes, cracks and patched area at different 
chainages.  A  measuring  tape  was  used  to  obtain  the  dimensions  of  the  above  distresses  which  were 
then summed up for  the critical  road sections.  The condition  of the right  and  left  road shoulders was 
also  assessed  depending  on  how  much  of  it  had  been  eroded  over  time.  The  side  drains  were  also 
surveyed,  their  depths  along  different  sections  measured  and  the  presence  of  silt  and  other  material 
causing blockage noted. The above findings were recorded in Appendix C. 

3.2.4  PHOTOGRAPHY 

Photographs  were  taken  at  the  different  test  sites  to  clearly  show  the  current  condition  of  the  road, 
some of which have been included in Appendix A. 

3.2.5  FIELD TESTS 
Two major field tests were carried out namely; 

DCP ( Dynamic Cone Penetration) test 
Sand replacement method for determination of field density 

3.2.5.1  DCP test 

The  DCP  is  used  to  generate  data  which  can  be  analysed  to  produce  accurate  information  on  in  situ 
pavement layer thicknesses and strengths. The DCP apparatus consists of a cone fixed to the bottom of 
a vertical rod. A hammer is attached to the apparatus and a vertical scale alongside the road is used to 
read off measurements.

[Group Project Design]  19 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Procedure 
a)  The  apparatus  was  set  up  on  the  road  pavement  at  the  first  point  at  chainage  0+05  and  the 
hammer  repeatedly  lifted and  dropped onto  a coupling  at  the mid‐height  of the rod  to  deliver a 
standard impact, or ‘blow’, to the cone and drive it into the pavement. 
b)  A  vertical  1  metre  scale  alongside  the rod  was  used to measure the depth of penetration  of the 
cone. 
c)  The penetration and the number of blows were recorded on a Test Data Form, shown in Appendix 
C. 
d)  The above procedure was repeated for 11 other points at different road sections. More than one 
DCP test was carried out on sections which had very weak surface layers. 

Theory 
The DCP instrument with an extension rod of 400 mm can be used to a depth of 1200 mm. Although 
the instrument can be extended beyond this depth, with additional extension rods or an extension road 
longer than 400 mm, it is not recommended that this is done as friction between the rod and the soil 
can give unreliable data. Indeed, if the rod cannot be rotated by hand during a penetration test, it is 
probable that friction is too high, in which case the test should be repeated. 
The penetration  per blow,  the ‘penetration  rate’,  as  the cone  is  driven into the  pavement  is  used to 
calculate the strength of the material through which the cone is passing. A change in penetration rate 
indicates  a  change  in  strength  between  materials,  thus  allowing  layers  to  be  identified  and  the 
thickness  and  strength  of  each  to  be  determined.  These  layers  are  then  grouped  together  into  the 
pavement layers of base, sub‐base and subgrade, guided by test pit or as‐built records if available. 

3.2.5.2  Sand Replacement Test 

The two most important methods of measuring the density of a soil in situ are the ‘sand replacement 
method’ and the ‘core cutter method’ which is suitable for cohesive and non stony soils only. The sand 
replacement  method  is  used  for  non‐  cohesive  fine  soils  and  is  described  below,  with  details  of  the 
results in Appendix B1. The method is applicable to material at the test location containing up to 40% by 
mass  of  particles  larger  than  37.5  mm  size.  The  Sand  Replacement  method  provides  a  practical

[Group Project Design]  20 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

technique of determining  the in‐place  density  of soil and  related materials  in base  courses,  roadways, 


dams, embankments, levees and similar construction. 

Procedure 
Calibration of sand; 

a)  Dry sand was sieved through No. 20 sieve and was set aside for the test. 


b)  The  sand  was  then  poured  to  the  brim  of  a  1litre  capacity  cylinder  which  was  placed  over  a 
calibrating can of 100mm diameter and 150mm depth. The volume of the sand was representative 
of the hole to be dug in the field. 
c)  An outlet in the cylinder was opened and the sand allowed to dispense into the calibrating can. 
d)  The amount of sand  collected in the calibrating can was determined by finding the difference in 
mass between the sand in the cylinder before and after placing it in the can. 
e)  The above procedure was repeated for two other sand samples and the average value computed. 
f)  The amount of sand in cone was determined by placing a cylinder full of sand on a piece of paper 
and opening the outlet thus allowing the sand to flow onto the paper. The mass of sand collected 
on the paper was then determined. 
g)  The calibrating can was then filled to the brim with water and the density of the can determined 
by dividing the mass of water in the can by volume of the can. 

Field test 

a)  The  wearing  course  layer  was  removed  from  an  area  large  enough  to  place  the  field  density 
plate/tray until the base layer was exposed. 
b)  The  plate  had  a  100mm  diameter  hole  at  its  centre,  and  two  small  holes  at  its  diagonal  ends 
through which nails were passed to anchor the plate to the ground. 
c)  A 150mm deep hole was cut out of the layer using a hammer and chisel, through the hole in the 
plate.  In  preparing  the  density  hole,  the  center  opening  of  the  plate  was  used as  a  template  to 
control the diameter of the hole. The plate itself was used as a shelf to prevent the loss of soil. 
d)  The plate facilitated the removal of soil from the density hole. During the removal operation, all the 
extracted soil was placed in a polythene bag together with any that fell on the field density plate /

[Group Project Design]  21 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

tray  such that  none of it  was  lost.  The soil  extracted from  the hole  was  weighed and  the weight 
recorded. 
e)  The cylinder was  placed over  the hole,  on  the tray  and  the hole  filled with sand.  The amount  of 
sand retained in the cylinder after filling the hole was bagged and weighed. 
f)  The above procedure was repeated at three other points 
g)  The thickness of the wearing course at each point was measured using a ruler 
h)  The results of the sand replacement test are recorded in Appendix B1 

3.2.6  LABORATORY TESTS 
The following tests were carried out on samples obtained from different test pits at different chainages 
along the road. 

3.2.6.1  Plasticity test 

3.2.6.1.1  Liquid limit test (Cassagrande’s apparatus) 
Liquid  Limit  (LL  or  wL)  is  the  water  content,  in  percent,  of  a  soil  at  the  arbitrarily  defined  boundary 
between the semi liquid and plastic states. The Liquid Limit Device is a mechanical device consisting of a 
brass cup suspended from a carriage designed to control its drop onto a hard rubber base. The device 
may be operated by either a hand crank or electric motor. A device called a cam is designed to raise the 
cup smoothly and continuously to its maximum height, over a distance of at least 180 o  of cam rotation, 
without developing an upward or downward velocity of the cup when the cam follower leaves the cam. 
A Flat Grooving Tool is a tool made of plastic or non‐corroding metal having specified dimensions used 
to split the soil sample in the brass cup. The results for this test are detailed in Appendix B2. 

Procedure for Liquid Limit 

a)  The liquid limit device was cleaned and the height of drop of the cup adjusted so that the point of 
the cup in contact with the base rose to a height of about 10 mm. 
b)  A  sample  of  the  specimen  was  placed  on  a  glass  plate  and  the  water  content  of  the  specimen 
increased by adding distilled water and mixing on a glass plate with a spatula.

[Group Project Design]  22 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

c)  A portion of the prepared sample was placed in the cup of the liquid limit device at the point where 
the cup rested on the base and spread so that it was 10mm deep at its deepest point. A horizontal 
surface  was  formed over  the soil  and  care  taken to remove  bubbles  from  the soil  specimen.  The 
unused portion of the specimen was kept in a storage container. 
d)  A groove was made in the soil by drawing the grooving tool, beveled edge forward, through the soil 
from the top of the cup to the bottom of the cup. When forming the groove, the tip of the grooving 
tool was held against the surface of the cup and the tool kept perpendicular to the surface of the 
cup. 
e)  The  cup  was  lifted  and  dropped  at  a  rate  of  2  drops  per  second  until  the  two  halves  of  the  soil 
specimen met each other at the bottom of the groove. 
f)  The number  of drops required  to close the groove  was recorded and  a slice  of soil was  removed 
and its water content, w, determined. 
g)  Repeat steps 1 through 5 with a sample of soil at a slightly higher or lower water content. Whether 
water should be added or removed depends on the number of blows required to close the grove in 
the previous sample. 
h)  NB: The liquid limit is the water content at which it  will take 25 blows to close the groove over a 
distance  of  13  mm.  Three  tests  were  run,  increasing  the  water  content  each  time.  As  the  water 
content increased, it took fewer blows to close the groove. 
i)  The relationship between the water content, w, and the corresponding number of drops, N, of the 
cup was plotted on a semi logarithmic graph with water content as the ordinates and arithmetical 
scale,  and  the  number of drops  on  the abscissas  on  a logarithmic  scale.  The best  fit  straight  line 
through the five or more plotted points was drawn. 
j)  The  water  content  corresponding  to  the  intersection  of  the  line  with  the  25  drop  abscissa  was 
taken as the liquid limit, LL, of the soil. 

3.2.6.1.2  Plastic limit test 
Plastic Limit (PL or wP) is the water content, in percent, of a soil at the boundary between the plastic and 
semi‐solid states. 

Procedure for Determination of the Plastic Limit

[Group Project Design]  23 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

About 2g of the same sample used for the preparation for the liquid limit test was selected. 

The test specimen was rolled between the palm and fingers on a ground glass plate to form a 
thread of uniform diameter. 

The rolling was continued until the threads reached a 3mm diameter 

The sample was then rolled into a ball and the procedure repeated until the soil reached a point 
where it crumbled and cracked at that diameter. 

The moisture content of the soil at this point was determined as shown below. The procedure 
was repeated twice such that an average plastic limit for the sample was computed. 

The  average  of  the  water  contents  obtained  from  the  three  plastic  limit  tests  was  computed. 
The plastic limit, PL, was the average of the three water contents. 

3.2.6.1.3  Plasticity Index 
The plasticity index was calculated as follows: 

PI = LL ‐ PL 

Where: 

LL = liquid limit, and PL = plastic limit. 

3.2.6.2  Sieve Analysis 

Separation of the soil into its fractions may be done by a sieve analysis performed directly on soils that 
contain little or no fines. There are two types of sieve analysis namely a wet sieve and dry sieve analysis. 
If the character of the fines is such that the fine material adheres to the coarser particles and cannot be 
removed by dry sieving action, the sample is washed to remove the fine material. 

Procedure 

a)  The  sample  was  pre  washed  so  as  to  remove  fine  material  and  that  retained  on  No.  200  sieve 
during the washing process was then dried in an oven for 24 hours.

[Group Project Design]  24 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

b)  A stack of sieves was arranged in descending order of size from 20mm aperture to 0.75µm. 

c)  The dried soil sample was weighed and allowed to pass freely through the sieves which were then 
manually shaken such that the sample was separated on basis of size. 

d)  The mass of material retained on each sieve was the weighed and recorded in a table. 

e)  The analysis of this is shown in Appendix B5 and the soil characterised accordingly. 

3.2.6.3  Moisture Content test 

The  moisture  content  of  the  soil  was  also  determined  by  placing  a  wet  sample  of  known  mass  into  a 
moisture content tin, which was placed in an oven. The weight of the tin and dry soil was determined 
after leaving the sample in the oven for 24 hours, and finally determining the moisture content of the 
test soil. The moisture content is determined as the percentage of the ratio of the mass of water in the 
soil sample to the dry mass of the soil sample. 

3.3  OVERLAY DESIGN 

The overlay design basically entailed the following steps: 

a)  Determination  of  the  design  traffic  required  for  the  road  currently  in  terms  of  millions  of 
Equivalent  Single  Axle  loads  (ESAL).  Using  Table  3.1  below,  the  Traffic  Load  Class  (TLC)  was 
obtained. 
b)  Knowing the TLC and the 10 th  percentile of the subgrade CBR, Table 3.2 was used to determine 
the  required  structural  number  (SNreq)  for  the  pavement  to  sustain  the  future  traffic  over  the 
design life in years. The design life was chosen as 5 years. 
c)  The difference between the required structural number and the existing structural number gave 
the difference (SNdiff) that accounted for requirement of an overlay or some treatment to improve 
the strength. 
d)  SNdiff  was then used in the chart shown in figure 3.2 below to determine an appropriate option for 
strengthening the existing pavement.

[Group Project Design]  25 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Tables 3.3 and 3.4 and figure 3.2 below were obtained from Over seas Road notes (ORN 18). 

Table 3.3 Traffic Load Classes (TLC) 

Design Traffic Loading  Traffic Load Classes 

(ESAL x 10 6 )  (TLC) 

< 0.2  TLC 02 

0.2 – 0.5  TLC 05 

0.5 – 1  TLC 1 

1 – 3  TLC 3 

3 – 10  TLC 10 

10 – 20  TLC 20 

20 – 50  TLC 50 

Table 3.4 Determination of required structural number 

Required Structural Number, SNreq 
Subgrade  Traffic Load Classes 
CBR  TLC 02  TLC 05  TLC 1  TLC 3  TLC 10  TLC 20  TLC 50 
> 30  1.10  1.25  1.60  1.90  2.35  3.00  3.50 
15 – 29  1.35  1.50  1.80  2.20  2.75  3.80  4.20 
10 – 14  1.60  1.80  2.10  2.50  3.00  4.10  4.50 
7 – 9  1.90  2.00  2.30  2.75  3.30  4.30  4.70 
5 – 6  2.10  2.20  2.50  2.90  3.50  4.50  5.00 
3 – 4  2.40  2.80  3.10  3.40  4.00  5.00  5.50

[Group Project Design]  26 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Figure 3.2 Chart of Overlay options

[Group Project Design]  27 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

4  CHAPTER FOUR: RESULTS, ANALYSIS AND DISCUSSION 

4.1  INTRODUCTION 
This  chapter  contains data obtained from  visual  surveys  and  the results  of the tests  that  were  carried 
out both in the field and in the laboratory, which were carried out to identify and classify the materials 
of the pavement layers, and to establish the distresses on the road. It also contains the analysis of the 
said results and their discussion. The result of the analysis and discussion is the design of a maintenance 
programme for both Tennis Court and Mary Stuart Roads. 

4.2  LABORATORY TEST RESULTS 
The main purpose of the tests was to classify the soils that comprised the different pavement layers. The 
laboratory tests carried out are summarized in Table 4.1 below which shows the different tests, their 
purpose and specific referencing in Appendix B. 

Table 4.1 Laboratory Tests 

Test No.  Test  Purpose  Reference 

1  Sand Replacement  To determine the in‐situ bulk density of the  Appendix B1 


pavement to a depth of 150mm 

2  Cassagrande  To determine the Liquid Limit of the soil  Appendix B2 


samples taken from the pavement layers in 
the field. 

3  Rolling Test  To determine the Plastic Limit of the soil  Appendix B3 


samples taken from the field. 

4  Moisture Content  To determine the moisture content of the 
soil samples taken from the pavement layers 
in the field  Appendix B4 

5  Sieve Analysis  To determine the particle grading according  Appendix B5


to size. 

[Group Project Design]  28 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

4.2.1  Soil Classification 
The AASHTO method of Soil Classification was used to group the soil into standardised soil classes. This 
was done using the particle size grading (Sieve Analysis) and the Atterberg limits. Table 4.2 below shows 
the AASHTO classification based specifically on the liquid limit, plasticity index, moisture content and the 
percentage of fines passing the N0. 200 sieve during sieve analysis.

[Group Project Design]  29 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Table 4.2 Soil Classification 

Sample  Chainage  Bulk density  Liquid Limit  Plasticity  Moisture  %age  AASHTO  General Remarks 


No.  Index  Content  passing 
(g/cm 3 )  (%)  No.200  classification 
(%)  (%)  sieve 

1  0 + 310  2.55  30.82  16.18  12.2  33.7  A‐2‐6  Generally good soil 

Silty or clayey gravel and 
sand 

Large amount of fines in 
the soil 

2  0 + 520  2.35  30.82  21.16  13.5  ‐  ‐  Soil is plastic since the PI 


is greater than 18 

3  0 + 924  2.85  24.54  17.50  10.3  37.7  A‐6  Poor clayey plastic soil 

Large amount of fines in 
the soil 

4  0 + 953  2.21  29.85  22.38  10.1  44.0  A‐6  Poor clayey plastic soil

[Group Project Design]  30 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

4.3  FIELD TEST RESULTS 


The  field  tests  included  determination  of  field  density  using  the  Sand  Replacement  method  and  the 
establishment of the soundness of the subgrade using the Dynamic Cone Penetrometer (DCP) test, the 
results of which test have been included in Appendix C1. 

4.3.1  Field Density Determination 
Field density was determined by the Sand Replacement test. A summary of the test results is shown in 
Table 4.3 below. 

Table 4.3 Field Bulk Densities 

Sample ID  Chainage  Bulk density, ρb  = Mb/Vb 

g/cm 3  or Mg/m 3 

Sample 1 Vb1  0 + 310  2.55 

Sample 2 Vb2  0 + 520  2.35 

Sample 3 Vb3  0 + 924  2.85 

Sample 4 Vb4  0 + 953  2.21 

4.3.2  Visual Survey Results 
The  visual  survey  conducted  aided  the  identification  of  present  road  distresses.  The  major  distresses 
noted were: 

a)  Potholes 
b)  Patching 
c)  Cracking 
d)  Edge failure 
e)  Side drain condition 

Patches 

The lengths (L1 & L2) were measured as shown in Figure 4.1 below using a measuring tape.

[Group Project Design]  31 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

L2 

L1
Figure 4.1 Measurement of patched area 

The total patched area of each section was calculated as Σ (L1 x L2) 

The patched area of each section was then expressed as a percentage of the total area of the section. 
The  average  width  of  the  entire  road  measured  along  different  sections  was  6.8  metres  as  shown  in 
Appendix C2. 

Potholes 

The average diameter of each pothole was calculated as (ф1  + ф2)/ 2, and the total potholed area of each 


section was calculated as ∑ (πф 2 / 4) as shown in Appendix C2. The lengths (ф1, ф2) were measured as 
shown in Figure 4.2 below 

Φ2 

Φ1 

Figure 4.2Measurement of potholed area 

[Group Project Design]  32 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

A survey form – strip map – was prepared for use during maintenance programmes for the roads. The 
map is illustrated below in figure 4.3.

[Group Project Design]  33 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Figure 4.3 Maintenance Design Strip Map for Tennis Court Rd – Mary Stuart Rd (1km)

[Group Project Design]  34 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

A  summary  of  the  analysis  of  the  above  distresses  was  recorded  in  Table  4.4  below  indicative  of  the 
percentage area of each section of the road that was distressed by patching, potholes and cracking. 

Table 4.4 Results of Measured Quantities of Distressed area 

Distress:  Patching  Potholes  Cracking 


Total  Total 
Start  End  % area  Total  % area  % area 
patched  Distress 
Chainage  Chainage  distressed  Distress (m 2 )  distressed  distressed 
area (m 2 )  (m 2 ) 
0 + 000  0 + 100  135.42  20  3.92  1  2.40  0.35 
0 + 100  0 + 200  298.22  44  98.08  14  0.84  0.12 
0 + 200  0 + 300  222.78  33  9.52  1  1.73  0.25 
0 + 300  0 + 400  148.91  22  13.86  2  6.97  1.03 
0 + 400  0 + 500  28.14  4  7.92  1  0.00  0.00 
0 + 500  0 + 600  23.69  3  20.49  3  0.00  0.00 
0 + 600  0 + 700  64.01  9  4.03  1  0.00  0.00 
0 + 700  0 + 800  11.92  2  6.40  1  0.00  0.00 
0 + 800  0 + 900  117.72  17  16.26  2  0.00  0.00 
0 + 900  1 + 000  24.14  4  18.56  3  0.00  0.00 
Average area for a section =  680 m 2 

4.3.3  DCP Test Results 
The DCP test results were analysed using UK DCP 3.1 software. A summary of the penetration data and 
DCP test results has been appended (see Appendix C). The strength analysis of each layer per chainage 
tested was obtained and summarised in table 4.5 below with the inclusion of CBR and computed 
Structural Number (SN) values.

[Group Project Design]  35 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Table 4.5 DCP Layer Strength Analysis Results 

Base  Sub‐base  Subgrade 


Existing 
Test #  Chainage  CBR  CBR 
Thickness  Thickness  CBR %  SN 
%  % 
1  0 + 005  249  149  0  0  61  1.52 
2  0 + 310  163  68  207  38  24  1.81 
3  0 + 520  187  47  116  98  168  1.39 
4  0 + 521  239  105  187  75  235  2.29 
5  0 + 522  161  74  229  71  42  1.98 
6  0 + 730  222  60  58  47  91  1.47 
7  0 + 731  209  119  149  87  54  1.99 
8  0 + 732  164  108  212  102  53  2.01 
9  0 + 924  298  40  47  28  62  1.32 
10  0 + 950  168  59  146  37  49  1.48 
11  0 + 951  178  65  232  29  43  1.85 
12  0 + 953  180  51  204  53  62  1.57 

4.4  TRAFFIC COUNT RESULTS 
The number of axles summarised in table 4.6 below were mirrored as the vehicle traffic on the road. The 
maximum number of vehicles per hour was obtained by comparison of the traffic counts at the different 
junctions to design for the worst case. 

Table 4.6 Traffic Count 

Number of Axles 
North bound  South bound 
Vehicle type  7am‐9am  1pm‐3pm  5pm‐7pm  7am‐9am  1pm‐3pm  5pm‐7pm 
Saloon Car & 
4WD  65  122  145  69  175  238 
Pick Ups  8  17  7  9  18  19 
Mini buses  1  2  7  6  3  8 
Coasters  0  0  0  2  1  1 
Buses  0  0  1  1  1  0 
Trucks  0  4  1  2  6  3 

The axles were then converted into equivalent axle loads using the information in table 3.2 above. The 
computation  of  the  number  of  repetitions  to  give  the  traffic  volume  is  shown  in  tables  4.7  and  4.8 
below.

[Group Project Design]  36 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Table 4.7 Equivalent Single Axle Loads (ESALs) 
Number of Axles  Repetitions 
North bound  South bound  North bound  South bound 
7am‐  1pm‐  5pm‐  7am‐  1pm‐  5pm‐  7am‐  1pm‐  5pm‐  7am‐  1pm‐  5pm‐ 
Axle Load (lb)  E A L F 
9am  3pm  7pm  9am  3pm  7pm  9am  3pm  7pm  9am  3pm  7pm 
1,000 (s)  0.00002  65  122  145  69  175  238  0.0013  0.0024  0.0029  0.0014  0.0035  0.0048 
2,000 (s)  0.00018  73  139  152  78  193  257  0.0131  0.0250  0.0274  0.0140  0.0347  0.0463 
4,000 (s)  0.00209  9  19  14  15  21  27  0.0188  0.0397  0.0293  0.0314  0.0439  0.0564 
6,000 (s)  0.01043  1  2  8  9  5  9  0.0104  0.0209  0.0834  0.0939  0.0522  0.0939 
8,000 (s)  0.03430  0  4  1  2  6  3  0.0000  0.1372  0.0343  0.0686  0.2058  0.1029 
12,000 (T)  0.01440  0  0  1  3  2  1  0.0000  0.0000  0.0144  0.0432  0.0288  0.0144 
24,000 (T)  0.26000  0  4  1  2  6  3  0.0000  1.0400  0.2600  0.5200  1.5600  0.7800 
Total ESALs (repetitions)  0.0437  1.2652  0.4517  0.7724  1.9289  1.0986 

Table 4.8 Average Hourly Volume 

Average Traffic Volume 
2‐hourly  Hourly 
7:00 ‐ 9:00  Lane 1max  0.0437  0.02184 
0.2040 
Lane 2max  0.7724  0.38622 
1:00 ‐ 3:00  Lane 1max  1.2652  0.632615 
0.798528  0.4634 
Lane 2max  1.9289  0.96444 
5:00 ‐ 7:00  Lane 1max  0.4517  0.22583 
0.38757 
Lane 2max  1.0986  0.54931

[Group Project Design]  37 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

Computation of Daily Average Traffic volume 

Assuming a typical working day with 18 driving hours; 

Daily average traffic volume , Tb  =  Average hourly traffic x 18 

=  0.4634 ESALs per hour x 18 hours 

=  8.3412 ESALs. 

Annual ESALs for the year 2007, To, 

T0  =  8.3412 ESALs per day x 365 days per year 

=  3044.538 ESALs. 

Computation of Cumulative Traffic, DT, over a 5‐yr design period 

Assumptions: 

a)  Design period, n = 5 years 
b)  Traffic growth rate, r = 6% 
c)  Traffic growth rate is constant. 

Design traffic, DT = 
(  ) 
=  ×  ESALs 

(  ) 
= 3044.538 ×  ESALs 

DT = 8.528 x 10 6  ESALs 

Thus, the design traffic loading is 8.528 x 10 6  ESALs (repetitions). 

4.5  OVERLAY STRUCTURAL DESIGN 
Reference is made to Table 3.1 in the methodology to obtain the traffic loading class for the road(s). 

4.5.1  Determination of Traffic Load Class, TLC 


The design traffic loading obtained falls in the range (3‐10) x 10 6  ESALs, hence corresponds to the traffic 
load class, TLC 10

[Group Project Design]  38 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

4.5.2  Computation of 10th Percentile of Subgrade CBR 
The  10 th  percentile  of  the  subgrade  CBR  was  determined  using  the  excel  percentile  macro.  It  was 
obtained as 42.1%. 

4.5.3  Determination of the required structural number 
From Table 3.4, the structural number required that corresponds to a TLC of 10 and a CBR value in the 
range >30% is 2.35 

4.5.4  Overlay Design 
The difference between the required structural number and existing structural number is calculated as 
shown in table 4.9 below. 

Table 4.9 Calculation of Structural Number difference 

Existing  Required  SN 


Test #  Chainage 
SN  SN  Difference 
1  0 + 005  1.52  2.35  0.83 
2  0 + 310  1.81  2.35  0.54 
3  0 + 520  1.39  2.35  0.96 
4  0 + 521  2.29  2.35  0.06 
5  0 + 522  1.98  2.35  0.37 
6  0 + 730  1.47  2.35  0.88 
7  0 + 731  1.99  2.35  0.36 
8  0 + 732  2.01  2.35  0.34 
9  0 + 924  1.32  2.35  1.03 
10  0 + 950  1.48  2.35  0.87 
11  0 + 951  1.85  2.35  0.5 
12  0 + 953  1.57  2.35  0.78 

The largest SN difference is 1.03. This value is then compared with overlay options under a bituminous 
mix for base given in figure 3.2 above, to determine an appropriate option for strengthening the existing 
pavement. 
The  greatest  SN  difference  obtained  above  represents  the  most  critical  section  of  the  existing  road 
pavement and hence is the worst case scenario. The closest structural number difference in the chart to
[Group Project Design]  39 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

that calculated is 1.00. The overlay alternatives corresponding to the above difference are indicative of 
the  maintenance  requirement  of  the  road  pavement.  Four  alternatives  are  available.  These  are 
illustrated in Figure 4.4 below.

[Group Project Design]  40 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

ST 

60 mm  80 mm 
AC 

(a)  (b) 

60mm thick asphalt concrete layer placed on the base to sustain it  Surface  Treatment  overlaying  an  80mm  thick  bituminous  dressing 
for the next 5 years at the predicted loading conditions.  over the base course. 

ST  ST

100 mm  150mm 
PM 60  CRB 

(c)  (d) 

Surface Treatment overlaying a 100mm thick macadam (PM 60)  Surface Treatment overlaying a 200mm thick CRR layer over the base 


dressing over the base course.  course 

Figure 4.4  Design Overlay Options; (a) AC overlay; (b) Bituminous Mix for Base course; (c) Penetration Macadam; (d) Granular Base course. 

[Group Project Design]  41 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

5  CHAPTER FIVE: CONCLUSION AND RECOMMENDATIONS 

5.1  INTRODUCTION 
This  chapter  contains  the  interpretation  of  the  analysis  presented  in  Chapter  Four  in  view  of  the 
attainment  of  the  set  objectives  of  the  project.  Wherein  the  said  objectives  were  not  achieved, 
recommendations  have  been  made  in  the  following  paragraphs  to  welcome  future  researchers  and 
designers to collaborate on the project. 

5.2  DEDUCTIONS 
Generally,  the  road  condition  as  evidenced  from  the  condition  survey  conducted  was  poor, 
characterised by a number of physical pavement distresses. The dominant distresses were potholes and 
patches. A few cracks were observed but only one section was severely cracked as indicated on the Strip 
Map in Chapter Four. The map was developed for use in forthcoming maintenance programmes for the 
two roads – Tennis Court Road and Mary Stuart Road. 

The  structural  soundness  of  the  pavement  was  established  through  the  Dynamic  Cone  Penetrometer 
test,  the results  of which were  simulated into the Overlay  Maintenance  Design.  For the design period 
considered – 5 years – it was established that an overlay was required in all sections of the road. Four 
alternatives were presented to this effect. A choice can be made on the alternatives depending on the 
available technology and the economy of the project. 

5.3  RECOMMENDATIONS 

5.3.1  Drainage Improvement 
The  drainage  system  should  be  redesigned  to  incorporate  Green  Engineering  Techniques.  One  key 
aspect  of  Green  Engineering  is  to  preserve  and  promote  riparian  areas  and  drainage  regimes  that 
support them. 

Current practice requires rain falling on impermeable surfaces (such as the Tennis Court and Mary Stuart 


pavements),  drained  into  existing  trenches,  and  disposed  directly  into  waterways  at  velocities  and

[Group Project Design]  42 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

volumes many times greater than predevelopment rates, scouring stream beds and leading to uneven 
base flows. 

Green  infrastructure  reverses  this  by  encouraging  infiltration  of  rainwater  into  the  ground,  where  its 
naturally  filtered  before  reaching  the  stream,  and  also  regulating  the  rate  of  entry  into  the  stream 
system, mimicking predevelopment forest land hydrology. 

One  of  the  largest  generators  of  excess  storm  water  in  any  municipality  is  the  paved  street  system, 
typical curb‐and‐gutter systems, which prevent water from being absorbed into roadside soils. 

Infiltration is encouraged through the use of permeable surfaces and by eliminating curbs thus allowing 
water to infiltrate directly into the infiltration zone, or swale. Only when the swales are saturated does 
water drain into a system of shallow perforated pipes laid into the infiltration zones. This pipe system 
connects all infiltration devices and moves water to retention/treatment ponds or artificial wetlands. 

Paved street widths for  local  and  collector streets in  plan range  from  6m  to 11.3m.  Rights  of way  for 
these  streets  range  from  between  17m  and  22m,  depending  on  specific  infrastructure,  servicing  and 
amenity  requirements  of  each  individual  corridor.  Street  trees  are  planted  within  these  rights  of  way 
such that 60% of the street section will be shaded at maturity. These urban forest trees are an important 
element of the streetscape and a significant factor in the maintenance of watershed health 

5.3.2  Side Walks 
Arising from a great need to accommodate disabled persons on the side walks, it is recommended that 
the curb  be redesigned with ramps  to ease  movement  of wheel  chairs  on  and  off  the pavement  thus 
increasing pedestrian safety. 

5.3.3  Road Lighting 
The current  poor road side lighting  needs to be supplemented with more  street lights  to improve  the 
lighting condition, and thus security.

[Group Project Design]  43 
[Maintenance Design of Tennis Court and Mary Stuart Roads] 

6  REFERENCES 

1.  C A O’Flaherty, Hodder Headline Plc (1988), Highway Engineering, Third Edition, 
2.  E.J Yoder & W.Witezak …………… 
3.  Huang…………. 
4.  John Wiley& sons, Inc Highway engineering, international 7 th  edition, (2004)2.2 
5.  Overseas Road Notes, www.google.co.ug 
6.  P.  M.  Condon  and  K.  Isaac,  ICE  Municipal  Engineer  156,  (2003),  Green  Municipal 
Engineering for Sustainable Communities, 
7.  R. J. Salter & N. B. Hounsell, Highway Traffic Analysis and Design, Third Edition, Macmillan 
Press Ltd. (1996).

[Group Project Design]  44 

You might also like